CN114928060A
CN114928060A CN202210532650.5A CN202210532650A CN114928060A CN 114928060 A CN114928060 A CN 114928060A CN 202210532650 A CN202210532650 A CN 202210532650A CN 114928060 A CN114928060 A CN 114928060A
Authority
CN
China
Prior art keywords
load control
control information
main network
management system
network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210532650.5A
Other languages
Chinese (zh)
Inventor
余文辉
吴争荣
孙奇珍
章坚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Southern Power Grid Co Ltd
Original Assignee
China Southern Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Southern Power Grid Co Ltd filed Critical China Southern Power Grid Co Ltd
Priority to CN202210532650.5A priority Critical patent/CN114928060A/en
Publication of CN114928060A publication Critical patent/CN114928060A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • H02J3/144Demand-response operation of the power transmission or distribution network
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/04Circuit arrangements for ac mains or ac distribution networks for connecting networks of the same frequency but supplied from different sources
    • H02J3/06Controlling transfer of power between connected networks; Controlling sharing of load between connected networks
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/10Power transmission or distribution systems management focussing at grid-level, e.g. load flow analysis, node profile computation, meshed network optimisation, active network management or spinning reserve management
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2310/00The network for supplying or distributing electric power characterised by its spatial reach or by the load
    • H02J2310/50The network for supplying or distributing electric power characterised by its spatial reach or by the load for selectively controlling the operation of the loads
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a load control method and a device based on a power network, wherein the method comprises the following steps: the method comprises the steps that a main network management system detects whether a main network triggers a target event or not, main network load control information corresponding to the target event is generated when the main network triggers the target event is detected, the main network load control information is issued to a distribution network management system, the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, the main network load control information and the distribution network load control information are sent to a power mechanism in communication connection with the distribution network management system, the main network management system generates target load control information aiming at the target event according to the main network load control information, the distribution network load control information and load control mode information, and the power mechanism adopts the target load control information to carry out load control on the power network. Therefore, the cooperation efficiency can be improved and the potential safety hazard can be reduced by implementing the method.

Description

Load control method and device based on power network
Technical Field
The invention relates to the technical field of power grid management, in particular to a load control method and device based on a power network.
Background
At present, a power grid generally comprises a main grid rack and a distribution grid rack, wherein the main grid rack is a main rack for power supply enterprises to transmit power from a power plant to a distribution grid, and the distribution grid rack is a main rack for distributing the power transmitted by the main grid to power consumers. When a planned power failure occurs to the main network rack, the power resources distributed to the distribution network rack can be influenced, so that the normal power utilization of power utilization users in a power supply jurisdiction of the distribution network rack is influenced, and even economic loss can be caused.
At present, in order to reduce the influence of planned power failure of a main network rack on normal power utilization of power utilization users in the area of a distribution network rack, cooperative work between the main network rack and the distribution network rack is needed, the cooperative work between the main network rack and the distribution network rack is generally completed by offline communication between workers of the main network rack and the workers of the distribution network rack, so that the problem of low cooperative efficiency exists, when the cooperative work content is changed, the workers of the main network rack and the distribution network rack are also needed to communicate in time, if the communication is not in time, the workers still operate according to the unchanged work content, and potential safety hazards exist.
Disclosure of Invention
The technical problem to be solved by the invention is to provide a load control method and device based on a power network, which can improve the cooperation efficiency among a main network management system, a distribution network management system and a power mechanism, and reduce the situation that cooperation is completed by offline communication of workers, thereby reducing the problem of untimely communication, improving the reliability of cooperation, and reducing the potential safety hazard of the power network.
In order to solve the technical problem, a first aspect of the present invention discloses a load control method based on a power network, the method is applied to a power grid management platform, the power grid management platform includes a main network management system, a distribution network management system and a power mechanism, the power network includes a main network and a distribution network, the main network management system is used for managing the main network, the distribution network management system is used for managing the distribution network, and the main network management system is in communication connection with the distribution network management system, and the method includes:
the main network management system detects whether the main network triggers a target event or not, generates main network load control information corresponding to the target event when the main network triggers the target event, and sends the main network load control information to the distribution network management system;
the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system, and the power mechanism is used for generating load control mode information according to the main network load control information and the distribution network load control information and feeding the load control mode information back to the main network management system;
the main network management system receives the load control mode information fed back by the power mechanism, acquires the distribution network load control information in the distribution network management system, and generates target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information;
and the power mechanism adopts the target load control information to carry out load control on the power network.
As an optional implementation manner, in the first aspect of the present invention, when it is detected that the target event is triggered by the main network, the main network management system generates main network load control information corresponding to the target event, including:
when the fact that the target event is triggered by the main network is detected, the main network management system determines main network power equipment information corresponding to the target event from the main network;
the main network management system determines a main network load control value corresponding to the target event according to the main network power equipment information;
the main network management system determines a load control type corresponding to the target event, and generates main network load control information corresponding to the target event according to the main network power equipment information, the main network load control value and the load control type.
As an optional implementation manner, in the first aspect of the present invention, the determining, by the distribution network management system according to the main network load control information issued by the main network management system, distribution network load control information corresponding to the main network load control information by the distribution network management system includes:
the distribution network management system determines a network architecture between the main network and the distribution network, and determines an influence area influenced by the target event and determines user information in the influence area according to the network architecture between the main network and the distribution network and the main network load control information issued by the main network management system;
the distribution network management system determines a distribution network load control value aiming at the distribution network according to the main network load control value and the user information in the affected area;
and the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the user information and the distribution network load control value in the affected area.
As an optional implementation manner, in the first aspect of the present invention, after the distribution network management system issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system, and before the main network management system receives the load control manner information fed back by the power mechanism, the method further includes:
the power mechanism generates load control mode information aiming at the target event according to the main network load control information and the distribution network load control information;
and the power mechanism generates load control mode information for the target event according to the main network load control information and the distribution network load control information, and the method comprises the following steps:
the power mechanism determines a power transfer and supply area which needs to execute power transfer and supply operation in the influence area and a power failure area which needs to execute power failure operation in the influence area according to the main network power equipment information in the main network load control information and the influence area in the distribution network load control information;
and the power mechanism generates load control mode information aiming at the target event according to the power supply transfer area and the power failure area.
As an optional implementation manner, in the first aspect of the present invention, the load control of the power network by the power mechanism using the target load control information includes:
the power mechanism executes the power outage operation for the power outage area and the power transfer operation for the power transfer area according to the load control mode information in the target load control information.
As an optional implementation manner, in the first aspect of the present invention, after the master network management system generates the master network load control information corresponding to the target event, the method further includes:
the main network management system acquires progress information aiming at the main network load control information in real time and detects whether a change event related to the main network load control information is triggered or not, wherein the change event is triggered based on the progress information;
when the change event is detected to be triggered, the main network management system acquires change information aiming at the main network load control information, updates the main network load control information by adopting the change information, and executes a step of issuing the main network load control information to the distribution network management system according to the updated main network load control information.
As an optional implementation manner, in the first aspect of the present invention, the generating, by the master network management system, the target load control information for the target event according to the master network load control information, the distribution network load control information, and the load control manner information includes:
the main network management system respectively carries out parameter check on the main network load control information, the distribution network load control information and the load control mode information according to a preset check rule;
and when the parameters in the main network load control information, the distribution network load control information and the load control mode information are checked to be correct, the main network management system generates target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information.
The invention discloses a load control device based on a power network, which is applied to a power grid management platform, wherein the power grid management platform comprises a main network management system, a distribution network management system and a power mechanism, the power network comprises a main network and a distribution network, the main network management system is used for managing the main network, the distribution network management system is used for managing the distribution network, the main network management system is in communication connection with the distribution network management system, the main network management system comprises a main network load control information generation module and a target load control information generation module, the distribution network management system comprises a distribution network load control information generation module, and the power mechanism comprises a load control module;
the main network load control information generation module is used for detecting whether a target event is triggered by the main network, generating main network load control information corresponding to the target event when the target event is triggered by the main network, and sending the main network load control information to the distribution network management system;
the distribution network load control information generation module is used for determining distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, issuing the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system, and the power mechanism is used for generating load control mode information according to the main network load control information and the distribution network load control information and feeding the load control mode information back to the main network management system;
the target load control information generation module is used for receiving the load control mode information fed back by the power mechanism, acquiring the distribution network load control information in the distribution network management system, and generating target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information;
and the load control module is used for carrying out load control on the power network by adopting the target load control information.
As an optional implementation manner, in the second aspect of the present invention, when it is detected that the target event is triggered by the master network, a specific manner of generating the master network load control information corresponding to the target event in the master network load control information generation module is as follows:
when the fact that the target event is triggered by the main network is detected, main network power equipment information corresponding to the target event is determined from the main network; determining a main network load control value corresponding to the target event according to the main network power equipment information; and determining a load control type corresponding to the target event, and generating main network load control information corresponding to the target event according to the main network power equipment information, the main network load control value and the load control type.
As an optional implementation manner, in the second aspect of the present invention, a specific manner of determining, by the distribution network load control information generation module, the distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system is as follows:
determining a network architecture between the main network and the distribution network, and determining an influence area influenced by the target event and determining user information in the influence area according to the network architecture between the main network and the distribution network and the main network load control information issued by the main network management system; determining a distribution network load control value aiming at the distribution network according to the main network load control value and the user information in the influence area; and determining distribution network load control information corresponding to the main network load control information according to the user information and the distribution network load control value in the affected area.
As an alternative embodiment, in the second aspect of the present invention, the electric power mechanism further includes:
a load control mode information generating module, configured to generate load control mode information for the target event according to the main network load control information and the distribution network load control information after the distribution network management system issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system and before the main network management system receives the load control mode information fed back by the power mechanism;
and the specific way of generating the load control mode information for the target event in the load control mode information generating module according to the main network load control information and the distribution network load control information is as follows:
determining a power transfer and supply area which needs to execute power transfer and supply operation in the influence area and a power failure area which needs to execute power failure operation in the influence area according to the main network power equipment information in the main network load control information and the influence area in the distribution network load control information; and generating load control mode information aiming at the target event according to the power supply switching area and the power failure area.
As an optional implementation manner, in the second aspect of the present invention, a specific manner of performing load control on the power network by using the target load control information in the load control module is as follows:
and according to the load control mode information in the target load control information, executing the power outage operation aiming at the power outage area, and executing the power transfer operation aiming at the power transfer area.
As an optional implementation manner, in the second aspect of the present invention, the main network management system further includes:
a master network load control information updating module, configured to obtain, in real time, progress information for the master network load control information after generating master network load control information corresponding to the target event, and detect whether to trigger a change event associated with the master network load control information, where the change event is triggered based on the progress information; and when the change event is detected to be triggered, obtaining change information aiming at the main network load control information, adopting the change information to update the main network load control information, and executing the step of sending the main network load control information to the distribution network management system according to the updated main network load control information.
As an optional implementation manner, in the second aspect of the present invention, a specific manner of generating, by the target load control information generation module, the target load control information for the target event according to the master network load control information, the distribution network load control information, and the load control manner information is as follows:
according to preset checking rules, parameter checking is respectively carried out on the main network load control information, the distribution network load control information and the load control mode information; and when the parameters in the main network load control information, the distribution network load control information and the load control mode information are checked to be correct, generating target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information.
The third aspect of the present invention discloses another load control device based on a power network, the device comprising:
a memory storing executable program code;
a processor coupled with the memory;
the processor calls the executable program codes stored in the memory to execute the load control method based on the power network disclosed by the first aspect of the invention.
In a fourth aspect, the present invention discloses a computer storage medium storing computer instructions for executing the method for controlling a load based on a power network disclosed in the first aspect of the present invention when the computer instructions are called.
Compared with the prior art, the embodiment of the invention has the following beneficial effects:
in the embodiment of the invention, a main network management system is used for detecting whether a main network triggers a target event or not, generating main network load control information corresponding to the target event when the main network triggers the target event, and issuing the main network load control information to a distribution network management system, the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, and issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system, the power mechanism is used for generating load control mode information according to the main network load control information and the distribution network load control information and feeding the load control mode information back to the main network management system, the main network management system receives the load control mode information fed back by the power mechanism and acquires the distribution network load control information in the distribution network management system, and generating target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information, and carrying out load control on the power network by the power mechanism by adopting the target load control information. Therefore, when a target event is triggered, the target load control information aiming at the target event can be generated through the main network management system, the distribution network management system and the power mechanism, the cooperation efficiency among the main network management system, the distribution network management system and the power mechanism is improved, and the situation that cooperation is completed by offline communication of workers is reduced, so that the problem of untimely communication is reduced, the cooperation reliability is improved, and the potential safety hazard of a power network is reduced.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the description of the embodiments will be briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without creative efforts.
Fig. 1 is a schematic flow chart of a load control method based on a power network according to an embodiment of the present invention;
FIG. 2 is a schematic flow chart of another method for controlling a load based on a power network according to an embodiment of the present disclosure;
fig. 3 is a schematic structural diagram of a load control device based on an electric power network according to an embodiment of the present invention;
FIG. 4 is a schematic structural diagram of another load control device based on an electric power network according to an embodiment of the disclosure;
fig. 5 is a schematic structural diagram of another device for controlling a load based on a power network according to an embodiment of the present invention.
Detailed Description
In order to make the technical solutions of the present invention better understood, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be obtained by a person skilled in the art without inventive step based on the embodiments of the present invention, are within the scope of protection of the present invention.
The terms "first," "second," and the like in the description and claims of the present invention and in the above-described drawings are used for distinguishing between different objects and not necessarily for describing a particular sequential or chronological order. Furthermore, the terms "include" and "have," as well as any variations thereof, are intended to cover non-exclusive inclusions. For example, a process, method, apparatus, article, or article that comprises a list of steps or elements is not limited to only those steps or elements listed, but may alternatively include other steps or elements not listed, or inherent to such process, method, article, or article.
Reference herein to "an embodiment" means that a particular feature, structure, or characteristic described in connection with the embodiment can be included in at least one embodiment of the invention. The appearances of the phrase in various places in the specification are not necessarily all referring to the same embodiment, nor are separate or alternative embodiments mutually exclusive of other embodiments. It is explicitly and implicitly understood by one skilled in the art that the embodiments described herein can be combined with other embodiments.
The invention discloses a load control method and device based on a power network, which can improve the cooperation efficiency among a main network management system, a distribution network management system and a power mechanism and reduce the condition that the cooperation is completed by off-line communication of workers, thereby reducing the problem of untimely communication, improving the reliability of cooperation and reducing the potential safety hazard of the power network. The following are detailed descriptions.
Example one
Referring to fig. 1, fig. 1 is a schematic flow chart illustrating a load control method based on a power network according to an embodiment of the present invention. Wherein, the load control method based on the power network described in fig. 1 can be applied to a power grid management platform, the power network can include a main network and a distribution network, the power network is a power network, the main network is a main network rack, the distribution network is a distribution network rack, the power network can be a transmission network for transmitting the electric energy generated by the power generation equipment to the electricity consumers, the main network can be a transmission network for transmitting electricity in the power network, the distribution network can be a transmission network for distributing the electric energy to the electricity consumers in the power network, the power grid management platform can be used for managing the power network, the power grid management platform can include a main network management system, a distribution network management system and a power organization, the main network management system can be used for managing the main network, such as a main network OMS (scheduling operation management system), the distribution network management system can be used for managing the distribution network, for example, the distribution network OMS, the main network management system may be in communication connection with the distribution network management system, and the embodiment of the present invention is not limited.
As shown in fig. 1, the power network-based load control method may include the operations of:
step 101, a main network management system detects whether a main network triggers a target event, generates main network load control information corresponding to the target event when the main network triggers the target event is detected, and sends the main network load control information to a distribution network management system.
Wherein the target event may be an event that the power supply capacity of the main network is weakened to influence the power supply amount distributed to the distribution network, the reason for weakening the power supply capacity of the main network may include a power failure of the main network, for example, an event that a planned power failure occurs in the main network to influence the power supply amount in a corresponding jurisdiction of the distribution network, the main network load control information may be control information for the power supply amount of the main network obtained based on the target event, the main network load control information may include main network power device information and a main network load control value, the main network power device information may be information of devices in the main network related to load control, the main network power device information may include main network substation information, to-be-overhauled device information, and main network control device information for controlling a load of the main network, the main network load control value may be control information in the main network related to load control, the main network load control value may include a load predicted value, a load demand value, a load control value, load control time information, and load control reason information, the load predicted value may be a load value after predicting that the power supply amount of the main network is affected by the target event, the load demand value may be a load value satisfying normal power consumption of the power consumer affected by the target event, the load control value may be a load value required to be controlled by the main network obtained based on the load predicted value and the load demand value, and the load control time information may include a start time of load control, and an end time of load control.
The main network management system can detect the running state of the power network in real time, particularly detect whether an event of power supply capacity weakening occurs in the main network, and further can judge whether the event of power supply capacity weakening occurring in the main network influences the power supply amount of the distribution network, if so, the main network can be judged to trigger a target event, and if not, the main network can be judged not to trigger the target event.
Generally, when an event that the power supply capability is weakened occurs in the main network, the power supply amount of the distribution network is affected, and it can be determined that the main network triggers the target event when the event that the power supply capability is weakened occurs in the main network is detected.
When the target event triggered by the main network is detected, the main network management system can generate main network load control information corresponding to the target event and send the main network load control information to the distribution network management system.
In practical application, when the main network management system detects that the main network triggers a target event, the main network management system can generate a load control application form for the target event, and add main network power equipment information and load control information corresponding to the target event into the load control application form by analyzing the range and the degree of influence of the target event, that is, add the main network load control information into the load control application form, and then can issue the load control application form to the distribution network management system.
Specifically, the load control application form may include, in addition to the main network load control information, creation time of the load control application form, task identification of the load control application form, and person information related to the load control application form.
In an optional embodiment, when the target event is an event corresponding to a planned power outage, for example, an event that some devices need to be overhauled and a power outage needs to be planned in the main network, the generated load control request form may further include planned power outage information for to-be-overhauled device information that needs to be overhauled in the main network.
The planned power failure information may include time information of planned power failure.
In an optional embodiment, after generating the master network load control information corresponding to the target event, step 101 may further include the following steps:
the main network management system acquires progress information aiming at the main network load control information in real time and detects whether a change event associated with the main network load control information is triggered or not; when a trigger change event is detected, the main network management system acquires change information aiming at the main network load control information, updates the main network load control information by adopting the change information, and executes a step of issuing the main network load control information to the distribution network management system according to the updated main network load control information.
The progress information may be progress information associated with the main network load control information, the progress information may include a change event that may be an event that changes the main network load control information, the change event may be triggered based on the progress information, and the change information may be information that needs to be changed in the main network load control information.
After the master network load control information corresponding to the target event is generated, the progress information associated with the master network load control information can be acquired in real time, and whether to trigger a change event associated with the master network load control information is detected based on the progress information of the master network load control information.
In practical application, after generating the main network load control information corresponding to the target event, the main network management system may search the load control application form for the main network load control information in the power grid management platform through the task identifier of the load control application form, and acquire the progress information of the load control application form in real time.
In a specific implementation, after the master network load control information corresponding to the target event is generated and before the master network load control information is issued to the distribution network management system, the schedule information of the load control application form in the power network management platform may include the master network load control information, after the distribution network load control information corresponding to the master network load control information is determined and before the master network load control information and the distribution network load control information are issued to the power mechanism in communication connection with the distribution network management system, the schedule information of the load control application form in the power network management platform may include the master network load control information and the distribution network load control information, and after the master network management system receives the load control mode information fed back by the power mechanism, the schedule information of the load control application form in the power network management platform may include the master network load control information, the distribution network load control information, the schedule information of the load control application form in the power network management platform, and the schedule information of the load control application form in the power network management platform may include the master network load control information and the distribution network load control information, Load control mode information.
After the progress information of the load control application form is obtained, the power grid management platform can detect whether a change event associated with the main network load control information is triggered or not according to a preset trigger rule and by combining the real-time obtained progress information of the load control application form.
Specifically, the trigger rule may be a trigger rule based on the main network load control information, the distribution network load control information, or the load control mode information.
For example, when a part of parameters in the main network load control information or the distribution network load control information or the load control manner information satisfies the trigger rule, a change event associated with the main network load control information may be detected to be triggered, and when a part of parameters in the main network load control information or the distribution network load control information or the load control manner information does not satisfy the trigger rule, a change event associated with the main network load control information may be detected to be not triggered.
Furthermore, whether a change operation performed by an operator on the main network load control information is received or not may be detected, and when the change operation performed by the operator on the basis of the schedule information of the load control application form acquired in real time is detected, it may be determined that a change event associated with the main network load control information is triggered, and when the change operation performed by the operator on the basis of the schedule information of the load control application form acquired in real time is not detected, it may be determined that the change event associated with the main network load control information is not triggered.
The change operation may be performed by the staff based on the schedule information of the load control application form acquired in real time, or may be performed by the staff needing to change the main network load control information based on the work demand.
When a trigger change event is detected, the main network management system can acquire change information aiming at the main network load control information, and then can update the main network load control information by adopting the change information, so that the step of issuing the main network load control information to the distribution network management system is executed according to the updated main network load control information.
In practical application, when a currently triggered change event is triggered based on a trigger rule, the power grid management platform may further determine a parameter to be changed in the main grid load control information according to the change rule, and generate change information of the parameter to be changed, and then the main grid management system may obtain the change information, generated by the power grid management platform according to the change rule, for the main grid load control information, and update the parameter in the main grid load control information by using the change information, so as to perform a step of issuing the main grid load control information to the distribution network management system according to the updated main grid load control information.
When the currently triggered change event is triggered by change operation based on workers, the power grid management platform can respond to the change operation of the workers, determine parameters needing to be changed in the main grid load control information, determine change information of the parameters needing to be changed in the main grid load control information in the change operation of the workers, and then the main grid management system can acquire the change information of the parameters needing to be changed in the main grid load control information determined by the power grid management platform from the change operation of the workers, update the parameters in the main grid load control information by adopting the change information, and execute a step of sending the main grid load control information to the distribution network management system according to the updated main grid load control information.
In the specific implementation, because when the cooperative work content is changed, the problem that the communication between the main network and the distribution network staff is not timely occurs, so that the staff still operates according to the unchanged work content, and potential safety hazards exist, the power grid management platform can detect whether a change event is triggered or not, and further can change the cooperative work content between the main network management system and the distribution network management system, namely when the parameters in the main network load control information are changed, the trigger change event is detected, and update is performed on the parameters in the main network load control information by responding to the change operation of the staff, or update is performed on the parameters in the main network load control information by a change rule, so that the updated main network load control information can be sent to the distribution network management system, and the cooperative change of the main network management system and the distribution network management system is completed, therefore, the problem that the main network is not communicated with the working personnel of the distribution network in time is avoided, and the potential safety hazard that the operation is still carried out according to the unchanged working content is reduced.
In an optional embodiment, a specific manner of updating the parameter in the main network load control information by using the change information may be to update the parameter of the main network load control information in the load control application form.
102, the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, and issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system.
The distribution network load control information can be control information aiming at the power supply quantity of the distribution network obtained based on a target event, the distribution network load control information can comprise distribution network power equipment information, user information and a distribution network load control value, the distribution network power equipment information can be information of equipment related to load control in the distribution network, the distribution network power equipment information can comprise distribution network substation information, distribution network power supply office information and distribution network control equipment information used for controlling the load of the distribution network, the distribution network load control value can be control information related to load control in the distribution network, the distribution network load control value can comprise load control quantity information and load transfer quantity information, the load control quantity information can be obtained based on a load predicted value, a load demand value and a load control value in main network load control information, and the load control quantity information can be the load quantity required to be controlled by the distribution network, the load transfer amount information may be load amount required to be transferred by the distribution network, the user information may be information of power users required to be controlled in the distribution network, the user information may include user control amount information, the user control amount information may be the number of the power users required to be controlled by the distribution network, the power mechanism may be a dispatch mechanism used for performing maintenance management on a main network and the distribution network in the power network, the power mechanism may be configured to generate load control mode information according to the main network load control information and the distribution network load control information and feed the load control mode information back to the main network management system, the load control mode information may be control information for the power mechanism obtained based on a target event, and the load control mode information may include user information and distribution network load control values in the distribution network load control information.
After the main network management system issues the main network load control information to the distribution network management system, the distribution network management system can determine distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, and issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system.
In practical application, after the distribution network management system determines the distribution network load control information corresponding to the main network load control information, the distribution network load control information can be added to a load control application form in the power grid management platform, and then the main network management system can obtain the distribution network load control information corresponding to the main network load control information in the load control application form in real time through the power grid management platform.
And 103, the main network management system receives the load control mode information fed back by the power mechanism, acquires distribution network load control information in the distribution network management system, and generates target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information.
The target load control information may be linkage control information related to the main network management system, the distribution network management system and the power mechanism, and the target load control information may be used to control the power supply amount of the main network and the distribution network through the main network management system, the distribution network management system and the power mechanism.
After the power mechanism feeds back the load control mode information to the main network management system, the main network management system can receive the load control mode information fed back by the power mechanism and acquire distribution network load control information in the distribution network management system, and then can generate target load control information for a target event according to the main network load control information, the distribution network load control information and the load control mode information.
In practical application, the power mechanism may add the load control mode information to the load control request form in the power grid management platform, so that the main grid management system obtains the load control mode information in the load control request form through the power grid management platform, and completes feedback of the load control mode information, and then the main grid management system may obtain the load control task corresponding to the target event by obtaining the main grid load control information, the distribution network load control information, and the load control mode information in the load control request form in the power grid management platform, and integrating the obtained main grid load control information, the distribution network load control information, and the load control mode information, and may issue the load control task after obtaining the load control task.
Specifically, the load control tasks may include a load control subtask for the main network management system, a load control subtask for the distribution network management system, and a load control subtask for the electric power mechanism, and the load control tasks may be used to trigger operations for controlling the power supply amount in the main network management system, the distribution network management system, and the electric power mechanism.
In an optional embodiment, the specific implementation manner of generating the target load control information for the target event according to the main network load control information, the distribution network load control information, and the load control manner information in step 103 may be:
the main network management system respectively checks parameters of main network load control information, distribution network load control information and load control mode information according to preset checking rules; and when the parameters in the main network load control information, the distribution network load control information and the load control mode information are checked to be correct, the main network management system generates target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information.
The checking rule is used for checking parameters in the main network load control information, the distribution network load control information and the load control mode information, and the checking rule is generated based on user requirements.
After the main network management system can receive the load control mode information fed back by the power mechanism and acquire the distribution network load control information in the distribution network management system, the main network management system can perform parameter checking on the main network load control information, the distribution network load control information and the load control mode information according to a checking rule.
In practical application, the main network management system may check whether parameters in the main network load control information, the distribution network load control information, and the load control manner information are abnormal according to a check rule, for example, the main network management system may determine a value range of each parameter in the main network load control information, the distribution network load control information, and the load control manner information according to the check rule, and compare the value of each parameter in the actually acquired main network load control information, distribution network load control information, and load control manner information with the value range of each parameter in the main network load control information, the distribution network load control information, and the load control manner information, so as to determine whether parameters in the main network load control information, the distribution network load control information, and the load control manner information are abnormal.
When it is determined that a parameter in the main network load control information, the distribution network load control information, and the load control manner information is abnormal, the main network management system may determine that the parameter in the main network load control information, the distribution network load control information, and the load control manner information is checked incorrectly, the main network management system may generate a parameter abnormality message, notify a worker of the parameter abnormality message to the main network management system, and further receive a reset operation performed by the worker of the main network management system based on the parameter abnormality message, where the reset operation may be used by the main network management system to re-perform the steps from step 101 to step 103 until each parameter in the main network load control information, the distribution network load control information, and the load control manner information obtained after the re-execution is not abnormal.
When it is determined that each parameter in the main network load control information, the distribution network load control information and the load control mode information is not abnormal, the main network management system can determine that the parameters in the main network load control information, the distribution network load control information and the load control mode information are checked to be correct, and the main network management system generates target load control information aiming at a target event according to the main network load control information, the distribution network load control information and the load control mode information.
In practical application, when it is determined that each parameter in the main network load control information, the distribution network load control information and the load control mode information is not abnormal, the main network management system can integrate the acquired main network load control information, the distribution network load control information and the load control mode information to obtain a load control task, and the load control task is issued in the power grid management platform.
And 104, the power mechanism performs load control on the power network by adopting the target load control information.
After obtaining the target load control information, the power mechanism may perform load control on the power network using the target load control information.
In practical application, the power mechanism can be in communication connection with the power grid management platform, so that a load control task corresponding to a target event issued by the main network management system in the power grid management platform can be found, target load control information in the load control task is obtained, and load control is performed on the power network by adopting the target load control information.
In an alternative embodiment, after the power mechanism can perform load control on the power network by using the target load control information, the main network management system can detect the power supply amount in the main network in real time, and the distribution network management system can detect the power supply amount in the distribution network in real time, and add the power supply amount in the main network and the power supply amount in the distribution network to the load control task, respectively, so that the main network management system can obtain the power supply amount in the main network and the power supply amount in the distribution network in real time, can compare the power supply amount in the main network with the main network load control value in the main network load control information, and can compare the power supply amount in the distribution network with the distribution network load control value in the distribution network load control information, and can make the power supply amount in the main network not satisfy the main network load control value in the distribution network load control information, and/or when the power supply amount in the distribution network does not satisfy the distribution network load control value in the distribution network load control information, the main network management system may generate a load control abnormal message, may notify a worker of the main network management system of the load control abnormal message, and may further receive a second resetting operation performed by the worker of the main network management system based on the load control abnormal message, where the second resetting operation may be used by the main network management system to re-perform the steps from step 101 to step 103, until the power supply amount in the main network satisfies the main network load control value in the main network load control information and the power supply amount in the distribution network satisfies the distribution network load control value in the distribution network load control information by performing load control on the power network using the re-performed target load control information.
And when the power supply amount in the main network meets the main network load control value in the main network load control information and the power supply amount in the distribution network meets the distribution network load control value in the distribution network load control information, completing the load control task.
In practical applications, the load control abnormal message may indicate that the control effect of performing load control on the power network by using the target load control information does not satisfy the normal power consumption of the power consumption user, that is, the control effect of performing load control on the power network by using the target load control information does not satisfy the expected effect, and that the control effect of performing load control on the power network by using the target load control information satisfies the main network load control value in the main network load control information when the power supply amount in the main network satisfies the distribution network load control value in the distribution network load control information, and may indicate that the control effect of performing load control on the power network by using the target load control information satisfies the expected effect.
In the embodiment of the invention, a main network management system is used for detecting whether a main network triggers a target event or not, generating main network load control information corresponding to the target event when the main network triggers the target event is detected, and issuing the main network load control information to a distribution network management system, the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, and issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system, the power mechanism is used for generating load control mode information according to the main network load control information and the distribution network load control information and feeding the load control mode information back to the main network management system, the main network management system receives the load control mode information fed back by the power mechanism and acquires the load control information in the distribution network management system, and generating target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information, and carrying out load control on the power network by the power mechanism by adopting the target load control information. Therefore, when the target event is triggered, the target load control information aiming at the target event can be generated through the main network management system, the distribution network management system and the power mechanism, the cooperation efficiency among the main network management system, the distribution network management system and the power mechanism is improved, and the condition that the cooperation is completed by offline communication of workers is reduced, so that the problem of untimely communication is reduced, the reliability of cooperation is improved, and the potential safety hazard of the power network is reduced.
Example two
Referring to fig. 2, fig. 2 is a schematic flowchart illustrating another load control method based on an electrical power network according to an embodiment of the present invention. The load control method based on the power network described in fig. 2 may be applied to a power grid management platform, where the power network may include a main network and a distribution network, the power network may be a power transmission network that transmits electric energy generated by power generation equipment to power consumers, the main network may be a power transmission network used for transmitting power in the power network, the distribution network may be a power transmission network used for distributing electric energy to the power consumers in the power network, the power grid management platform may include a main network management system, a distribution network management system and a power mechanism, the main network management system may be used for managing the main network, the distribution network management system may be used for managing the distribution network, and the main network management system may be in communication connection with the distribution network management system.
As shown in fig. 2, the power network-based load control method may include the operations of:
step 201, the main network management system detects whether the main network triggers a target event.
Step 202, when detecting that the main network triggers the target event, the main network management system determines main network power equipment information corresponding to the target event from the main network.
When the target event triggered by the main network is detected, the main network management system may determine, from the main network, main network substation information and main network control device information corresponding to the target event.
For example, the main network may include an area a network and an area B network, and the main network management system may determine, from all area networks, that an area where the target event is located is the area a network, and may further determine a main network substation in the area a network, determine a main network control device for controlling load in the area a network in the main network, and acquire main network substation information of the main network substation in the area a network and main network control device information of the main network control device for controlling load in the area a network in the main network.
In an optional embodiment, when the target event is a planned power outage, the master network management system may determine, from all the area networks, the to-be-overhauled device that triggers the target event, and may further determine the to-be-overhauled device information of the to-be-overhauled device that triggers the target event.
In step 203, the primary grid management system determines a primary grid load control value corresponding to the target event according to the primary grid power device information.
After determining the primary network power device information corresponding to the target event, the primary network load control value corresponding to the target event may be determined from the primary network power device information.
In practical application, the load predicted value, the load demand value, the load control value and the load control time information corresponding to the target event can be determined according to the main network substation information and the main network control device information in the main network power device information, and the load control reason information corresponding to the target event can be determined according to the to-be-overhauled device information in the main network power device information.
In step 204, the main network management system determines the load control type corresponding to the target event, and generates main network load control information corresponding to the target event according to the main network power device information, the main network load control value and the load control type.
The load control type can correspond to a control requirement in actual load control, the load control type can comprise a first control type for controlling according to load and a second control type for controlling according to the number of people, and the control requirement can be preset or can be set by a worker according to an actual situation.
After determining the master network load control value corresponding to the target event, the master network management system may obtain a control demand for the target event, may further determine a load control type corresponding to the target event according to the control demand for the target event, and may generate master network load control information corresponding to the target event according to the master network power device information, the master network load control value, and the load control type.
In practical application, the main network management system may generate a load control application form for the target event, further add the main network power device information, the main network load control value, and the load control type to the load control application form, and issue the load control application form with the main network power device information, the main network load control value, and the load control type added thereto to the power grid management platform, that is, the main network load control information corresponding to the target event.
Step 205, the main network load control information is sent to the distribution network management system.
And step 206, the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, and issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system.
In an optional embodiment, in step 206, the specific implementation manner of determining, by the distribution network management system according to the main network load control information issued by the main network management system, the distribution network load control information corresponding to the main network load control information may be:
the distribution network management system determines a network architecture between a main network and a distribution network, and determines an influence area influenced by a target event and user information in the influence area according to the network architecture between the main network and the distribution network and main network load control information issued by the main network management system; the distribution network management system determines a distribution network load control value aiming at a distribution network according to the main network load control value and the user information in the affected area; and the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the user information and the distribution network load control value in the affected area.
The network architecture may be a connection hierarchical relationship between a main network and a distribution network in a power transmission direction, the influence area may be an area in the distribution network where the power supply amount is influenced by a target event, and the user information may be information of a power consumption user in the influence area in the distribution network.
After the main network management system issues the main network load control information to the distribution network management system, the distribution network management system can determine a network architecture between the main network and the distribution network, determine an affected area affected by a target event in the distribution network according to the network architecture between the main network and the distribution network and information of equipment to be overhauled in the main network load control information issued by the main network management system, and determine user information in the affected area.
After the user information in the affected area is determined, the distribution network management system may determine a distribution network load control value for the distribution network according to a main network load control value in the main network load control information issued by the main network management system and the user information in the affected area, and determine distribution network load control information corresponding to the main network load control information according to the user information in the affected area and the distribution network load control value.
In practical application, the distribution network management system can acquire a load control request form for the target event from the power grid management platform, and further can add user information and distribution network load control values in the affected area to the load control request form, namely distribution network load control information corresponding to the main network load control information.
And step 207, the main network management system receives the load control mode information fed back by the power mechanism, acquires the distribution network load control information in the distribution network management system, and generates target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information.
In an alternative embodiment, after step 206 and before step 207, the method may further comprise the steps of:
and the power mechanism generates load control mode information aiming at the target event according to the main network load control information and the distribution network load control information.
After the main network load control information and the distribution network load control information are issued to the power mechanism in communication connection with the distribution network management system, the power mechanism can receive the main network load control information and the distribution network load control information issued by the distribution network management system, can further generate load control mode information according to the main network load control information and the distribution network load control information, and feeds the load control mode information back to the main network management system.
In practical application, the power mechanism may also be in communication connection with the power grid management platform, so as to obtain, in real time, distribution network load control information corresponding to the master network load control information in the load control request form through the power grid management platform, to generate load control mode information according to the obtained master network load control information and the distribution network load control information, and after the load control mode information is generated, the load control mode information may be added to the load control request form in the power grid management platform.
In an optional embodiment, a specific implementation manner of the power mechanism generating the load control manner information for the target event according to the main network load control information and the distribution network load control information may be:
the power mechanism determines a power transfer area needing to perform power transfer operation in the influence area and determines a power failure area needing to perform power failure operation in the influence area according to the main network power equipment information in the main network load control information and the influence area in the distribution network load control information; the power mechanism generates load control mode information for a target event based on the power transfer area and the power outage area.
Wherein, the load control mode information may include user information and distribution network load control value in the distribution network load control information, and may further include a power failure control message for a power failure area, and a power transfer control message for a power transfer area, and/or, maintenance control information, the power failure control message may be control information of a power failure operation for performing load control based on the power mechanism, the power transfer control message may be control information of a power transfer operation for performing load control based on the power mechanism, the power transfer control message may include power transfer time information, power transfer related power failure information, power transfer user influence information, and power transfer operation information, the power transfer time information may be a start time for performing the power transfer operation, the power transfer related power failure information may be a power failure event related to performing the power transfer operation, and the power transfer user influence information may be information of a power user influenced by the power transfer operation, the power supply switching operation information can be flow information for executing power supply switching operation, the maintenance control information can be control information of maintenance operation corresponding to a target event, the maintenance control information can comprise maintenance time information, maintenance associated power failure information, maintenance user influence information and maintenance operation information, the maintenance time information can be start and stop time for executing the maintenance operation, the maintenance associated power failure information can be power failure events associated with executing the maintenance operation, the maintenance user influence information can be information of power users influenced by the maintenance operation, and the maintenance operation information can be flow information for executing the maintenance operation.
After the main network load control information and the distribution network load control information are issued to a power mechanism in communication connection with the distribution network management system, the power mechanism can determine a power transfer area in which power transfer operation needs to be executed in the influence area and a power failure area in which power failure operation needs to be executed in the influence area according to main network power equipment information in the main network load control information and the influence area in the distribution network load control information, and then can generate load control mode information aiming at a target event according to the power transfer area and the power failure area.
And step 208, the power mechanism carries out load control on the power network by adopting the target load control information.
In an alternative embodiment, step 208 may include the following substeps:
the power mechanism performs a power outage operation for the power outage area and a power transfer operation for the power transfer area in accordance with the load control manner information in the target load control information.
After generating the load control manner information for the target event, the power mechanism may determine the power transfer control information for the power transfer area and/or the maintenance control information and determine the power outage control message for the power outage area according to the load control manner information in the target load control information, and may perform the power outage operation for the power outage area according to the power transfer control information for the power transfer area and/or the maintenance control information and perform the power transfer operation for the power transfer area according to the power transfer control information for the power outage area.
In the embodiment of the invention, whether a main network triggers a target event is detected through a main network management system, when the main network triggers the target event, the main network management system determines main network power equipment information corresponding to the target event from the main network, the main network management system determines a main network load control value corresponding to the target event according to the main network power equipment information, determines a load control type corresponding to the target event, generates main network load control information corresponding to the target event according to the main network power equipment information, the main network load control value and the load control type, and issues the main network load control information to a distribution network management system, the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, and issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system The power mechanism is used for generating load control mode information according to the main network load control information and the distribution network load control information and feeding the load control mode information back to the main network management system, the main network management system receives the load control mode information fed back by the power mechanism and obtains the distribution network load control information in the distribution network management system, target load control information aiming at a target event is generated according to the main network load control information, the distribution network load control information and the load control mode information, and the power mechanism adopts the target load control information to carry out load control on the power network. Therefore, when a target event is triggered, the target load control information aiming at the target event can be generated through the main network management system, the distribution network management system and the power mechanism, the cooperation efficiency among the main network management system, the distribution network management system and the power mechanism is improved, and the situation that cooperation is completed by offline communication of workers is reduced, so that the problem of untimely communication is reduced, the cooperation reliability is improved, and the potential safety hazard of a power network is reduced.
EXAMPLE III
Referring to fig. 3, fig. 3 is a schematic structural diagram of a load control device based on an electric power network according to an embodiment of the present invention. As shown in fig. 3, the apparatus is applied to a power grid management platform, the power grid management platform includes a main network management system, a distribution network management system, and a power mechanism, the power network includes a main network and a distribution network, the main network management system is configured to manage the main network, the distribution network management system is configured to manage the distribution network, the main network management system is in communication connection with the distribution network management system, the main network management system includes a main network load control information generation module 301 and a target load control information generation module 303, the distribution network management system includes a distribution network load control information generation module 302, and the power mechanism includes a load control module 304.
The main network load control information generation module 301 is configured to detect whether a main network triggers a target event, generate main network load control information corresponding to the target event when the main network triggers the target event, and send the main network load control information to the distribution network management system;
the distribution network load control information generation module 302 is configured to determine distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, and issue the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system, where the power mechanism is configured to generate load control mode information according to the main network load control information and the distribution network load control information, and feed the load control mode information back to the main network management system;
the target load control information generation module 303 is configured to receive load control mode information fed back by the power mechanism, acquire distribution network load control information in the distribution network management system, and generate target load control information for a target event according to the main network load control information, the distribution network load control information, and the load control mode information;
the load control module 304 is configured to perform load control on the power network using the target load control information.
In an optional embodiment, when the master network load control information generating module 301 detects that the master network triggers the target event, a specific manner of generating the master network load control information corresponding to the target event is as follows:
when a target event triggered by a main network is detected, determining main network power equipment information corresponding to the target event from the main network; determining a main network load control value corresponding to the target event according to the main network power equipment information; the load control type corresponding to the target event is determined, and the main network load control information corresponding to the target event is generated according to the main network power equipment information, the main network load control value and the load control type.
In an optional embodiment, the specific manner of determining the distribution network load control information corresponding to the master network load control information according to the master network load control information issued by the master network management system in the distribution network load control information generation module 302 is as follows:
determining a network architecture between a main network and a distribution network, determining an influence area influenced by a target event and determining user information in the influence area according to the network architecture between the main network and the distribution network and main network load control information issued by a main network management system; determining a distribution network load control value aiming at the distribution network according to the main network load control value and the user information in the affected area; and determining distribution network load control information corresponding to the main network load control information according to the user information and the distribution network load control value in the affected area.
Fig. 4 is a schematic structural diagram of another load control device based on an electric power network according to an embodiment of the present invention. As shown in fig. 4, the electric power mechanism further includes:
a load control mode information generating module 305, configured to generate load control mode information for a target event according to the main network load control information and the distribution network load control information after the distribution network management system issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system and before the main network management system receives the load control mode information fed back by the power mechanism;
the specific way of generating the load control manner information for the target event according to the main network load control information and the distribution network load control information in the load control manner information generating module 305 is as follows:
determining a power transfer area in the influence area, which needs to execute power transfer operation, and a power failure area in the influence area, which needs to execute power failure operation, according to the main network power equipment information in the main network load control information and the influence area in the distribution network load control information; and generating load control mode information aiming at the target event according to the power transfer area and the power failure area.
As an optional implementation manner, the specific manner in which the load control module 304 performs load control on the power network by using the target load control information is as follows:
and according to the load control mode information in the target load control information, performing power failure operation aiming at the power failure area, and performing power transferring operation aiming at the power transferring area.
As an alternative implementation, as shown in fig. 4, the main network management system further includes:
a main network load control information updating module 306, configured to obtain, in real time, progress information for the main network load control information after generating main network load control information corresponding to the target event, and detect whether to trigger a change event associated with the main network load control information, where the change event is triggered based on the progress information; and when a trigger change event is detected, obtaining change information aiming at the main network load control information, updating the main network load control information by adopting the change information, and executing a step of issuing the main network load control information to the distribution network management system according to the updated main network load control information.
As an optional implementation manner, the specific manner of generating the target load control information for the target event according to the main network load control information, the distribution network load control information, and the load control manner information in the target load control information generating module 303 is as follows:
according to preset checking rules, parameter checking is respectively carried out on the main network load control information, the distribution network load control information and the load control mode information; and when the parameters in the main network load control information, the distribution network load control information and the load control mode information are checked to be correct, generating target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information.
In the embodiment of the invention, a main network management system is used for detecting whether a main network triggers a target event or not, generating main network load control information corresponding to the target event when the main network triggers the target event, and issuing the main network load control information to a distribution network management system, the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, and issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system, the power mechanism is used for generating load control mode information according to the main network load control information and the distribution network load control information and feeding the load control mode information back to the main network management system, the main network management system receives the load control mode information fed back by the power mechanism and acquires the distribution network load control information in the distribution network management system, and generating target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information, and carrying out load control on the power network by the power mechanism by adopting the target load control information. Therefore, when the target event is triggered, the target load control information aiming at the target event can be generated through the main network management system, the distribution network management system and the power mechanism, the cooperation efficiency among the main network management system, the distribution network management system and the power mechanism is improved, and the condition that the cooperation is completed by offline communication of workers is reduced, so that the problem of untimely communication is reduced, the reliability of cooperation is improved, and the potential safety hazard of the power network is reduced.
Example four
Referring to fig. 5, fig. 5 is a schematic structural diagram of another load control device based on a power network according to an embodiment of the present disclosure. As shown in fig. 5, the power network-based load control apparatus may include:
a memory 501 in which executable program code is stored;
a processor 502 coupled to the memory 501;
the processor 502 calls the executable program code stored in the memory 501 to execute the steps of the power network-based load control method described in the first embodiment of the present invention or the second embodiment of the present invention.
EXAMPLE five
The embodiment of the invention discloses a computer storage medium, which stores computer instructions, and when the computer instructions are called, the computer instructions are used for executing the steps of the load control method based on the power network described in the first embodiment or the second embodiment of the invention.
EXAMPLE six
The embodiment of the invention discloses a computer program product, which comprises a non-transitory computer readable storage medium storing a computer program, wherein the computer program is operable to make a computer execute the steps of the load control method based on the power network described in the first embodiment or the second embodiment of the invention.
The above-described embodiments of the apparatus are only illustrative, and the modules described as separate parts may or may not be physically separate, and the parts displayed as modules may or may not be physical modules, may be located in one place, or may be distributed on a plurality of network modules. Some or all of the modules may be selected according to actual needs to achieve the purpose of the solution of this embodiment. One of ordinary skill in the art can understand and implement it without inventive effort.
Through the above detailed description of the embodiments, those skilled in the art will clearly understand that the embodiments may be implemented by software plus a necessary general hardware platform, and may also be implemented by hardware. Based on such understanding, the above technical solutions may be embodied in the form of a software product, which may be stored in a computer-readable storage medium, where the storage medium includes a Read-Only Memory (ROM), a Random Access Memory (RAM), a Programmable Read-Only Memory (PROM), an Erasable Programmable Read-Only Memory (EPROM), a One-time Programmable Read-Only Memory (OTPROM), an Electrically Erasable Programmable Read-Only Memory (EEPROM), a Compact Disc-Read-Only Memory (CD-ROM), or other disk memories, CD-ROMs, or other magnetic disks, A tape memory, or any other medium readable by a computer that can be used to carry or store data.
Finally, it should be noted that: the load control method and apparatus based on the power network disclosed in the embodiments of the present invention are only the preferred embodiments of the present invention, and are only used for illustrating the technical solutions of the present invention, not for limiting the same; although the present invention has been described in detail with reference to the foregoing embodiments, it will be understood by those of ordinary skill in the art; the technical solutions described in the foregoing embodiments may still be modified, or some technical features may be equivalently replaced; and such modifications or substitutions do not depart from the spirit and scope of the corresponding technical solutions of the embodiments of the present invention.

Claims (10)

1. A load control method based on a power network is applied to a power grid management platform, the power grid management platform comprises a main network management system, a distribution network management system and a power mechanism, the power network comprises a main network and a distribution network, the main network management system is used for managing the main network, the distribution network management system is used for managing the distribution network, and the main network management system is in communication connection with the distribution network management system, and the method comprises the following steps:
the main network management system detects whether the main network triggers a target event or not, generates main network load control information corresponding to the target event when the main network triggers the target event, and sends the main network load control information to the distribution network management system;
the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, issues the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system, and the power mechanism is used for generating load control mode information according to the main network load control information and the distribution network load control information and feeding the load control mode information back to the main network management system;
the main network management system receives the load control mode information fed back by the power mechanism, acquires the distribution network load control information in the distribution network management system, and generates target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information;
and the power mechanism adopts the target load control information to carry out load control on the power network.
2. The power-network-based load control method of claim 1, wherein the generating, by the master network management system, master network load control information corresponding to the target event when the master network triggering the target event is detected comprises:
when the fact that the target event is triggered by the main network is detected, the main network management system determines main network power equipment information corresponding to the target event from the main network;
the main network management system determines a main network load control value corresponding to the target event according to the main network power equipment information;
the main network management system determines a load control type corresponding to the target event, and generates main network load control information corresponding to the target event according to the main network power equipment information, the main network load control value and the load control type.
3. The power network-based load control method of claim 2, wherein the determining, by the distribution network management system, the distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system comprises:
the distribution network management system determines a network architecture between the main network and the distribution network, and determines an influence area influenced by the target event and determines user information in the influence area according to the network architecture between the main network and the distribution network and the main network load control information issued by the main network management system;
the distribution network management system determines a distribution network load control value aiming at the distribution network according to the main network load control value and the user information in the influence area;
and the distribution network management system determines distribution network load control information corresponding to the main network load control information according to the user information in the affected area and the distribution network load control value.
4. The power network-based load control method according to claim 3, wherein after the distribution network management system issues the main network load control information and the distribution network load control information to a power mechanism communicatively connected to the distribution network management system, and before the main network management system receives the load control mode information fed back by the power mechanism, the method further comprises:
the power mechanism generates load control mode information aiming at the target event according to the main network load control information and the distribution network load control information;
and the power mechanism generates load control mode information for the target event according to the main network load control information and the distribution network load control information, and the method comprises the following steps:
the power mechanism determines a power transfer and supply area which needs to execute power transfer and supply operation in the influence area and a power failure area which needs to execute power failure operation in the influence area according to the main network power equipment information in the main network load control information and the influence area in the distribution network load control information;
the power mechanism generates load control mode information for the target event based on the power supply transfer area and the power outage area.
5. The power-network-based load control method according to claim 4, wherein the power mechanism performs load control on the power network using the target load control information, including:
the power mechanism executes the power outage operation for the power outage area and the power transfer operation for the power transfer area according to the load control mode information in the target load control information.
6. The power-network-based load control method according to any one of claims 1 to 5, wherein after the master network management system generates master network load control information corresponding to the target event, the method further comprises:
the main network management system acquires progress information aiming at the main network load control information in real time and detects whether a change event related to the main network load control information is triggered or not, wherein the change event is triggered based on the progress information;
when the change event is detected to be triggered, the main network management system acquires change information aiming at the main network load control information, updates the main network load control information by adopting the change information, and executes a step of sending the main network load control information to the distribution network management system according to the updated main network load control information.
7. The power network-based load control method according to any one of claims 1 to 5, wherein the generating, by the master network management system, the target load control information for the target event according to the master network load control information, the distribution network load control information, and the load control manner information includes:
the main network management system respectively performs parameter checking on the main network load control information, the distribution network load control information and the load control mode information according to a preset checking rule;
and when the parameters in the main network load control information, the distribution network load control information and the load control mode information are checked to be correct, the main network management system generates target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information.
8. A load control device based on a power network is characterized in that the device is applied to a power grid management platform, the power grid management platform comprises a main network management system, a distribution network management system and a power mechanism, the power network comprises a main network and a distribution network, the main network management system is used for managing the main network, the distribution network management system is used for managing the distribution network, the main network management system is in communication connection with the distribution network management system, the main network management system comprises a main network load control information generation module and a target load control information generation module, the distribution network management system comprises a distribution network load control information generation module, and the power mechanism comprises a load control module;
the main network load control information generation module is used for detecting whether a target event is triggered by the main network, generating main network load control information corresponding to the target event when the target event is triggered by the main network, and sending the main network load control information to the distribution network management system;
the distribution network load control information generation module is used for determining distribution network load control information corresponding to the main network load control information according to the main network load control information issued by the main network management system, issuing the main network load control information and the distribution network load control information to a power mechanism in communication connection with the distribution network management system, and the power mechanism is used for generating load control mode information according to the main network load control information and the distribution network load control information and feeding the load control mode information back to the main network management system;
the target load control information generation module is used for receiving the load control mode information fed back by the power mechanism, acquiring the distribution network load control information in the distribution network management system, and generating target load control information aiming at the target event according to the main network load control information, the distribution network load control information and the load control mode information;
and the load control module is used for carrying out load control on the power network by adopting the target load control information.
9. A load control device based on an electric power network, the device comprising:
a memory storing executable program code;
a processor coupled with the memory;
the processor invokes the executable program code stored in the memory to perform the method of power network based load control as claimed in any one of claims 1-7.
10. A computer storage medium storing computer instructions for performing the method of any one of claims 1-7 when invoked.
CN202210532650.5A 2022-05-13 2022-05-13 Load control method and device based on power network Pending CN114928060A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210532650.5A CN114928060A (en) 2022-05-13 2022-05-13 Load control method and device based on power network

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210532650.5A CN114928060A (en) 2022-05-13 2022-05-13 Load control method and device based on power network

Publications (1)

Publication Number Publication Date
CN114928060A true CN114928060A (en) 2022-08-19

Family

ID=82808758

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210532650.5A Pending CN114928060A (en) 2022-05-13 2022-05-13 Load control method and device based on power network

Country Status (1)

Country Link
CN (1) CN114928060A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110264276A1 (en) * 2009-10-30 2011-10-27 Rudin Management Co. Inc. Interconnected electrical network and building management system and method of operation
CN107093902A (en) * 2017-06-27 2017-08-25 南方电网科学研究院有限责任公司 Power load regulation and control method and system
CN107134787A (en) * 2017-06-23 2017-09-05 国网江苏省电力公司电力科学研究院 Urgent accurate cutting load control system and cutting load method based on distributed feeder automation
CN110854848A (en) * 2019-11-20 2020-02-28 广东电网有限责任公司 Control aid decision-making method for distribution network scheduling load
WO2022021550A1 (en) * 2020-07-31 2022-02-03 广东卓维网络有限公司 Rapid power recovery management platform

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20110264276A1 (en) * 2009-10-30 2011-10-27 Rudin Management Co. Inc. Interconnected electrical network and building management system and method of operation
CN107134787A (en) * 2017-06-23 2017-09-05 国网江苏省电力公司电力科学研究院 Urgent accurate cutting load control system and cutting load method based on distributed feeder automation
CN107093902A (en) * 2017-06-27 2017-08-25 南方电网科学研究院有限责任公司 Power load regulation and control method and system
CN110854848A (en) * 2019-11-20 2020-02-28 广东电网有限责任公司 Control aid decision-making method for distribution network scheduling load
WO2022021550A1 (en) * 2020-07-31 2022-02-03 广东卓维网络有限公司 Rapid power recovery management platform

Similar Documents

Publication Publication Date Title
KR101439614B1 (en) Agent based energy management system and method
US9020800B2 (en) Method and apparatus for controlling energy services based on market data
EP2455897B1 (en) Methods and systems involving power system grid management
US10809753B2 (en) Real-time simulator and controller of power system using distributed data streaming server
CN103477607B (en) Energy automation installation and the method for running energy automation installation
CN102931726A (en) Power supply system is protected to main and distribution network integration
CN108462175A (en) A kind of electric heating equipment demand response interactive approach, system and device
CN102570607B (en) Redundant data processing system of intelligent substation
CN106532660B (en) A kind of main station system, remote system and the control method of relay fixed value modification
JP2015530863A (en) Energy storage system and module communication
CN109782724B (en) Control method for preventing misoperation-locking and terminal equipment
CN102158387A (en) Protection fault information processing system based on dynamic load balance and mutual hot backup
CN106357414A (en) The information exchange method and system used for base station power generation management
Li et al. Collaborative cyber-physical restoration for enhancing the resilience of power distribution systems
CN102594910B (en) Method adopting data service bus to realize single-instance transformer station programmed processing
CN106655520B (en) Ensure the method that relay protection remote operation securely and reliably executes
CN104253859A (en) Centralized scheduling resource distributing load balancing device and method
CN114928060A (en) Load control method and device based on power network
CN108460517A (en) A kind of power distribution network management-control method and device
CN111813430A (en) Robot cluster intelligent updating and deploying method and system
CN103491115A (en) Resource dispatching method, resource dispatching device and resource dispatching system
CN106655176B (en) Power distribution network online loop closing decision method and system
CN112152878B (en) Monitoring and management method, system, terminal and storage medium for digital channel of transformer substation
CN105122165A (en) Plant control system and plant control method
KR101862931B1 (en) Management system for analyzing program of distribution system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination