CN114912178A CN202210544235.1A CN202210544235A CN114912178A CN 114912178 A CN114912178 A CN 114912178A CN 202210544235 A CN202210544235 A CN 202210544235A CN 114912178 A CN114912178 A CN 114912178A
Authority
CN
China
Prior art keywords
pipeline
result
evaluation
layout
conditioning equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210544235.1A
Other languages
Chinese (zh)
Other versions
CN114912178B (en
Inventor
白艳
钟广文
刘和森
李文凭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Chuangbo Electromechanical Equipment Installation Co ltd
Original Assignee
Guangzhou Chuangbo Electromechanical Equipment Installation Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Chuangbo Electromechanical Equipment Installation Co ltd filed Critical Guangzhou Chuangbo Electromechanical Equipment Installation Co ltd
Priority to CN202210544235.1A priority Critical patent/CN114912178B/en
Publication of CN114912178A publication Critical patent/CN114912178A/en
Application granted granted Critical
Publication of CN114912178B publication Critical patent/CN114912178B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/04Constraint-based CAD

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Theoretical Computer Science (AREA)
  • Mathematical Optimization (AREA)
  • Computational Mathematics (AREA)
  • Architecture (AREA)
  • Mathematical Analysis (AREA)
  • Structural Engineering (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Air Conditioning Control Device (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a heating ventilation air-conditioning equipment installation method and system based on BIM, which are applied to the technical field of air-conditioning equipment installation, and the method comprises the following steps: and building a BIM model of the building according to the basic information of the building. And acquiring the installation constraint conditions of the heating, ventilating and air conditioning equipment of the building according to the basic information. And fitting the installation positions of the equipment according to the constraint conditions to obtain a plurality of installation position fits. And obtaining the laid pipeline information according to the construction result, and generating a pipeline association constraint condition according to the laid pipeline information. And laying the plurality of fitting result pipelines according to the pipeline association constraint conditions to obtain a plurality of laying results. And evaluating the layout result by using pipelines to obtain the evaluation sequence of the pipeline evaluation result, and installing the heating ventilation air conditioning equipment according to the optimal scheme in the evaluation sequence. The technical problem that the pipeline layout scheme has defects when the heating ventilation air conditioning equipment is installed due to human reasons because a standardized heating ventilation air conditioning equipment installation method is lacked in the prior art is solved.

Description

Heating ventilation air conditioning equipment installation method and system based on BIM
Technical Field
The invention relates to the technical field of air conditioning equipment installation, in particular to a heating ventilation air conditioning equipment installation method and system based on BIM.
Background
BIM is a building information model, the core of which is to establish a virtual building engineering three-dimensional model, provide a complete building engineering information base consistent with the actual situation by utilizing a digitization model, and greatly improve the information integration degree of the building engineering by virtue of the model, thereby providing an information exchange platform for the building engineering project.
However, in the prior art, the installation of the heating, ventilating and air conditioning equipment often depends on manual work to observe the field situation to determine the installation scheme, a large amount of manpower and material resources are consumed to determine the final installation scheme of the heating, ventilating and air conditioning equipment, and the determined installation scheme may have many defects in the pipeline layout scheme due to manual reasons.
Therefore, in the prior art, a standardized heating, ventilating and air conditioning equipment installation method is lacked, so that the technical problem that a pipeline layout scheme has defects when heating, ventilating and air conditioning equipment is installed due to human factors is caused.
Disclosure of Invention
The application provides a heating ventilation air conditioning equipment installation method and system based on BIM, which are used for solving the technical problem that the pipeline layout scheme has defects when heating ventilation air conditioning equipment is installed due to human reasons because a standardized heating ventilation air conditioning equipment installation method is lacked in the prior art.
In view of the above problems, the present application provides a method and system for installing a heating, ventilating and air conditioning device based on BIM.
In a first aspect of the present application, there is provided a BIM-based hvac apparatus installation method, including: obtaining basic information of a building, and building a BIM (building information modeling) model of the building according to the basic information to obtain a building result; carrying out heating ventilation air conditioning equipment constraint on the building according to the basic information to obtain constraint conditions; performing position fitting on the heating ventilation air conditioning equipment in the construction result according to the constraint condition to obtain a fitting result, wherein the fitting result comprises a plurality of position fitting results; acquiring laid pipeline information according to the construction result, and generating a pipeline association constraint condition of the heating ventilation air conditioning equipment according to the laid pipeline information; performing pipeline layout of the fitting result according to the pipeline association constraint condition, and generating pipeline evaluation results of a plurality of position fitting results based on the layout result; and carrying out evaluation sequencing according to the pipeline evaluation result to obtain a pipeline evaluation result, and installing the heating, ventilating and air conditioning equipment based on a pipeline layout result corresponding to the pipeline evaluation result.
In a second aspect of the present application, there is provided a BIM-based hvac apparatus mounting system, the system including: the model construction module is used for obtaining basic information of a building, and constructing a BIM (building information modeling) model of the building according to the basic information to obtain a construction result; the constraint condition acquisition module is used for carrying out constraint on heating ventilation air conditioning equipment of the building according to the basic information to obtain constraint conditions; the position fitting module is used for performing position fitting on the heating ventilation air conditioning equipment in the constructed result according to the constraint condition to obtain a fitting result, wherein the fitting result comprises a plurality of position fitting results; the pipeline association constraint condition acquisition module is used for acquiring the laid pipeline information according to the construction result and generating the pipeline association constraint condition of the heating, ventilating and air conditioning equipment according to the laid pipeline information; the pipeline evaluation module is used for laying the fitting result pipelines according to the pipeline association constraint conditions and generating pipeline evaluation results of a plurality of position fitting results based on laying results; and the pipeline evaluation sequencing module is used for carrying out evaluation sequencing according to the pipeline evaluation result to obtain a pipeline evaluation result and carrying out installation of the heating, ventilating and air conditioning equipment based on a pipeline layout result corresponding to the pipeline evaluation result.
One or more technical solutions provided in the present application have at least the following technical effects or advantages:
according to the building BIM model building method, building BIM model building is carried out through basic information of a building, and a building result is obtained. And carrying out the restraint of the heating ventilation air conditioning equipment of the building according to the basic information to obtain a restraint condition. And performing position fitting on the heating ventilation air conditioning equipment in the constructed result according to the constraint condition to obtain a fitting result, wherein the fitting result comprises a plurality of position fitting results. And acquiring the laid pipeline information according to the construction result, and generating a pipeline association constraint condition of the heating, ventilating and air conditioning equipment according to the laid pipeline information. And performing pipeline layout of the fitting result according to the pipeline association constraint conditions, and generating pipeline evaluation results of a plurality of position fitting results based on the layout result. And carrying out evaluation sequencing according to the pipeline evaluation result to obtain a pipeline evaluation result, and installing the heating, ventilating and air conditioning equipment based on the pipeline layout result corresponding to the pipeline evaluation result. The technical problem that the pipeline layout scheme has defects when the heating ventilation air conditioning equipment is installed due to human reasons because a standardized heating ventilation air conditioning equipment installation method is lacked in the prior art is solved. The technical effect of obtaining the optimal scheme for installing the heating, ventilating and air conditioning equipment is achieved.
The foregoing description is only an overview of the technical solutions of the present application, and the present application can be implemented according to the content of the description in order to make the technical means of the present application more clearly understood, and the following detailed description of the present application is given in order to make the above and other objects, features, and advantages of the present application more clearly understandable.
Drawings
Fig. 1 is a schematic flow chart of a method for installing a heating, ventilating and air conditioning equipment based on BIM provided by the present application;
fig. 2 is a schematic flow chart illustrating obtaining of pipeline association constraint conditions in a BIM-based hvac apparatus installation method provided in the present application;
fig. 3 is a schematic flow chart illustrating a pipeline evaluation result obtained according to an accessory quantity evaluation result and a convenience evaluation result in the BIM-based heating, ventilating and air conditioning equipment installation method provided by the present application;
fig. 4 is a schematic structural diagram of a BIM-based hvac equipment installation system according to the present application.
Description of reference numerals: the system comprises a model building module 11, a constraint condition obtaining module 12, a position fitting module 13, a pipeline association constraint condition obtaining module 14, a pipeline evaluation module 15 and a pipeline evaluation sequencing module 16.
Detailed Description
The application provides a heating ventilation air conditioning equipment installation method and system based on BIM, which are used for solving the technical problem that the reference value of a city knowledge archive is low due to the fact that the city knowledge archive is artificially influenced due to the fact that a standardized city knowledge archive construction method is lacked in the prior art.
The technical solution in the present application will be described clearly and completely with reference to the accompanying drawings. The embodiments described are only a part of the disclosure that can be realized by the present application, and not the entire disclosure of the present application.
Example one
As shown in fig. 1, the present application provides a BIM-based hvac apparatus installation method, which includes:
s100: obtaining basic information of a building, and building a BIM (building information modeling) model of the building according to the basic information to obtain a building result;
specifically, the BIM model is a building information model, simulates real information of a building through digital information, and includes not only information described by geometric shapes, but also a large amount of non-geometric information, such as construction cost, purchase information, and information of internal pipeline lines. And acquiring basic information of the building, wherein the basic information of the building comprises information of geometric shape description of the building, construction cost, purchase information, internal pipeline line and the like. And building a BIM model of the building through the information, wherein the building is the building to be provided with the heating, ventilating and air conditioning equipment, and a final building result, namely the building result, is obtained.
S200: carrying out heating ventilation air conditioning equipment constraint on the building according to the basic information to obtain constraint conditions;
specifically, constraints on the heating, ventilating and air conditioning equipment of the building, such as budgets of the heating, ventilating and air conditioning equipment, preset installation positions, reserved power and other information specified in the basic information, are obtained according to the basic information. The actual constraint conditions are obtained based on the contents described in the basic information, for example, constraint information such as a cost constraint condition of the hvac equipment, a power constraint condition of the hvac equipment, a size of the hvac equipment, an installation location constraint condition of the hvac equipment, a radiation range of the hvac equipment, and an internal pipe line of the hvac equipment is obtained, and the constraint conditions are collectively configured by the constraint information. The heating ventilation air-conditioning equipment, the installation mode and the wiring mode which accord with the constraint conditions need to be selected before the heating ventilation air-conditioning equipment is installed, the situation that all projects are incompatible is avoided, for example, the heating ventilation air-conditioning equipment pipeline conflicts with other equipment lines, or the situation that all radiation spaces are uneven in cold and hot is caused by unreasonable installation positions is avoided, the problems can be found in time before the heating ventilation air-conditioning equipment is installed according to the constraint conditions, and then guidance is provided for the installation of the heating ventilation air-conditioning equipment.
S300: performing position fitting on the heating ventilation air conditioning equipment in the construction result according to the constraint condition to obtain a fitting result, wherein the fitting result comprises a plurality of position fitting results;
specifically, the heating ventilation air conditioning equipment position fitting of the construction result is carried out according to the obtained constraint condition, namely the specific installation position of the heating ventilation air conditioning equipment is fitted in the construction result through the constraint condition, and the fitting of the installation position, namely the fitting result, is obtained. The method can be determined according to the constraint condition when the heating, ventilating and air conditioning equipment installation position fitting is carried out. Since multiple solutions can be included when the constraint condition is satisfied, multiple different fitting results can be fitted by performing the device position fitting. And acquiring a fitting result, wherein the fitting result comprises fitting results of a plurality of installation positions, namely the fitting result actually comprises a plurality of different installation schemes.
S400: acquiring laid pipeline information according to the construction result, and generating a pipeline association constraint condition of the heating ventilation air conditioning equipment according to the laid pipeline information;
specifically, the information of the pipelines already laid in the building is obtained according to the construction result, and since the information of the pipelines already laid affects the arrangement of the pipelines of the heating, ventilation and air conditioning in the embodiment, the arrangement of the installed pipelines needs to be analyzed before the heating, ventilation and air conditioning is installed. Whether the information of the arranged pipelines influences or restricts the heating and ventilation air conditioner to be installed is obtained, for example, the routing of the internal pipelines of the heating and ventilation air conditioner conflicts with the arranged pipelines, or certain potential safety hazards and other abnormal situations can be caused when the routing of the internal pipelines of the heating and ventilation air conditioner and the routing of the internal pipelines of the heating and ventilation air conditioner are installed together. In order to avoid the above abnormal situation, it is necessary to avoid conflicts between the internal pipelines of the hvac and the laid pipelines as much as possible when the internal pipelines of the hvac are routed, and obtain the pipeline association constraint conditions of the hvac equipment. For example, the pipelines of the heating, ventilating and air conditioning equipment and the laid pipelines cannot be installed in the same accommodating space at the same time. And further limiting the pipeline layout for obtaining a plurality of fitting results through the obtained fitting results according to the constraint conditions.
S500: performing pipeline layout of the fitting result according to the pipeline association constraint conditions, and generating pipeline evaluation results of a plurality of position fitting results based on the layout result;
s600: and evaluating and sequencing according to the pipeline evaluation result to obtain a pipeline evaluation and sequencing result, and installing the heating, ventilating and air conditioning equipment based on a pipeline layout result corresponding to the pipeline evaluation result.
Specifically, the pipelines are laid according to the pipeline association constraint conditions of the heating ventilation air conditioning equipment, and the selection of the pipeline arrangement path under the constraint conditions can be realized through the pipeline association constraint conditions during the pipeline laying so as to realize the pipeline laying and obtain a plurality of pipeline laying schemes with fitting results. And evaluating the pipeline layout result of the position fitting result to obtain pipeline evaluation results of a plurality of layout schemes. The pipeline evaluation result comprises a plurality of evaluation parameters, the pipeline evaluation result is evaluated through the plurality of evaluation parameters, a final pipeline evaluation result is obtained, and the pipeline evaluation result is used for reflecting the reasonable degree of the pipeline layout of the fitting result. And then, evaluating and sequencing the obtained multiple pipeline evaluation results, namely sequencing the reasonable degree of the pipeline layout, and obtaining the layout scheme with the best evaluation and most reasonable pipeline layout, namely the pipeline layout result. And installing the heating ventilation air conditioning equipment according to the obtained pipeline arrangement result, obtaining constraint conditions through BIM to install and fit the installation modes of the heating ventilation air conditioning equipment, fitting the pipeline arrangement results of a plurality of installation schemes, and screening out the pipeline arrangement scheme of the optimal installation scheme. The acquisition of the optimal scheme for installing the heating, ventilating and air conditioning equipment is realized.
As shown in fig. 2, step S400 of the method provided in the embodiment of the present application includes:
s410: obtaining a pipeline layout data set through big data;
s420: constructing distance parameters of different pipeline types according to the pipeline layout data set to obtain distance parameter constraint conditions;
s430: performing pipeline layout level sequence evaluation according to the pipeline layout data set, and obtaining a pipeline level sequence constraint condition according to an evaluation result;
s440: and obtaining the pipeline association constraint condition according to the distance parameter constraint condition and the pipeline level sequence constraint condition.
Specifically, a pipeline layout data set is obtained through big data, wherein the big data are historical data of pipeline layout, and the historical data of the pipeline layout are obtained to form the pipeline layout data set. The pipeline layout data set includes pipeline layout modes of various types of requirements. The method comprises the steps of obtaining distance parameters of different types of pipelines according to a pipeline layout data set, obtaining safety distances among the pipelines in the pipeline layout data set, for example, obtaining the safety distances between a water channel pipeline and a circuit pipeline in the pipeline layout data set as distance constraint conditions of different pipeline types, namely distance parameter constraint conditions, when the water channel pipeline and the circuit pipeline need to be placed in a certain space. And then, carrying out pipeline layout level sequence evaluation according to the pipeline layout data set, wherein different pipeline layouts need to be arranged according to a certain level, for example, when a water pipeline and a circuit pipeline are crossed, the layout level distribution exists, the level distribution under different installation conditions is different, for example, when the water pipeline and the circuit pipeline simultaneously go underground, the circuit pipeline is convenient to overhaul, the water pipeline is difficult to overhaul, and the water pipeline needs to be replaced under the water pipeline level when water leakage occurs, so that the circuit pipeline is often installed under the water pipeline level. The method comprises the steps of carrying out layout level sequence evaluation on installation modes of different pipelines in a pipeline layout data set, evaluating the advantages and disadvantages of the installation modes, and obtaining a constraint condition of a pipeline level installation sequence, namely a pipeline level sequence constraint condition according to a final evaluation result. And finally, acquiring a pipeline association constraint condition according to the distance parameter constraint condition and the pipeline level sequence constraint condition, wherein the pipeline association constraint condition is used for constraining the installation of the heating, ventilating and air conditioning equipment pipeline. The pipeline association constraint conditions obtained by the method reduce unreasonable pipeline arrangement schemes of heating, ventilating and air conditioning equipment, and further improve the compatibility among various projects.
The method provided by the embodiment of the application comprises the following steps of S440:
s441: judging whether pipeline position conflict exists in the process of laying the fitting result pipelines according to the pipeline association constraint conditions;
s442: when the pipeline position conflict exists, obtaining conflict node information;
s443: obtaining the number evaluation parameters of the collision nodes of the fitting result according to the information of the collision nodes;
s444: performing adjustment amplitude evaluation on each collision node according to the collision node information to obtain adjustment amplitude evaluation parameters of the fitting result;
s445: and obtaining the pipeline evaluation result according to the number evaluation parameter of the conflict nodes and the adjustment amplitude evaluation parameter.
Specifically, fitting result pipeline layout is carried out according to the pipeline association constraint conditions to generate a layout result, the layout result comprises the specific pipeline layout mode, the pipeline layout result of the fitting result is evaluated, and whether conflicts among pipelines in aspects such as positions and layout rules exist in the pipeline layout process in the pipeline layout result is evaluated. Since the pipeline lines are already arranged on the building equipment before the heating, ventilating and air conditioning equipment is installed, in order to avoid position conflicts between the fitting result pipeline arrangement result and the installed pipeline lines, after the fitting result pipeline arrangement result is obtained, whether conflicts in the aspects of pipeline positions, arrangement rules and the like exist in the pipeline arrangement result needs to be judged. And when conflicts in the aspects of pipeline positions, layout rules and the like exist, acquiring corresponding conflict nodes, wherein the conflict nodes are nodes with conflict in positions or rules between the installed pipeline lines and the layout results of the fitting result pipelines. And obtaining the number evaluation parameters of the collision nodes of the fitting result according to the obtained information of the collision nodes, wherein the number evaluation parameters of the collision nodes are evaluated according to the number of the collision nodes, and the number evaluation parameters of the collision nodes are higher when the number of the collision nodes is larger. And then, evaluating the adjustment amplitude of each collision node according to the information of the collision nodes, wherein the adjustment amplitudes of the collision nodes are different in the mode and the difficulty degree which are required to be avoided by the collision nodes at different positions, so that the adjustment amplitude evaluation of the collision nodes can be obtained in a manual evaluation mode, and the specific scores of the evaluations, namely the adjustment amplitude evaluation parameters of the fitting results, are obtained. And finally, obtaining a pipeline evaluation result according to the number evaluation parameter and the adjustment amplitude evaluation parameter of the conflict nodes. The pipeline evaluation result is used for reflecting the reasonable degree of the pipeline layout of the fitting result, and the pipeline evaluation result is obtained, so that the reasonable degree of the pipeline layout of the fitting result is accurately evaluated.
The method provided by the embodiment of the present application further includes step S440:
s441-1: judging whether the conflict node information has an abnormal rule to adjust the conflict node;
s441-2: when the abnormal rule adjustment conflict node exists, performing abnormal conflict node identification to obtain an identification result;
s441-3: performing abnormal coefficient evaluation on the identification result to obtain an abnormal coefficient evaluation result;
s441-4: and obtaining the pipeline evaluation result according to the abnormal coefficient evaluation result and the identification result.
Specifically, whether the conflict node information has an abnormal rule to adjust the conflict node is judged, and the pipeline is usually laid according to a certain laying rule when being laid, for example, a small pipeline avoids a large pipeline, a small pipeline has low manufacturing cost and is easy to avoid a large pipeline, and the like. When the conflict node is adjusted according to the abnormal rule, the reason for the conflict node is that construction is not carried out according to the conventional laying rule. And then, identifying the abnormal conflict node, namely identifying the reason of the abnormal conflict node, and acquiring a final identification result, wherein the final identification result can be acquired in a manual evaluation mode when the abnormal conflict node is identified. And acquiring an abnormal coefficient evaluation according to the identification result, wherein the abnormal coefficient evaluation is used for indicating the difficulty degree of processing the identification result, and the conflict node is difficult to process due to regularity, so that the abnormal rule adjustment conflict node needs to be independently evaluated. And finally, obtaining a pipeline evaluation result according to the abnormal coefficient evaluation result and the identification result. The pipeline evaluation result is used for reflecting the reasonable degree of the pipeline layout of the fitting result, and the pipeline evaluation result is obtained, so that the reasonable degree of the pipeline layout of the fitting result is accurately evaluated.
The method provided by the embodiment of the present application further includes step S440:
s441-5: evaluating the space utilization rate according to the layout result to obtain a space utilization rate evaluation result;
s441-6: evaluating the length of the pipeline according to the layout result to obtain an evaluation result of the length of the pipeline;
s441-7: and obtaining the pipeline evaluation result according to the space utilization rate evaluation result and the pipeline length evaluation result.
Specifically, space utilization rate evaluation is carried out according to the layout result, when the space utilization rate of the pipeline layout is evaluated, the space utilization rate evaluation result of the pipeline layout is obtained by obtaining the number of bent wiring in the layout result, and when the number of bent wiring is more, the space utilization rate of the wiring mode is lower, wherein the space utilization rate evaluation result is a specific score which corresponds to the number of bent wiring in the pipeline. And evaluating the length of the pipeline according to the layout result, and determining the length of the pipeline according to the shortest distance between the two points and the ratio of the actual use length in the layout result when evaluating the length of the pipeline to obtain the evaluation result of the length of the pipeline. Illustratively, a pipeline is connected with an end A and an end B, wherein the shortest distance from the end A to the end B is 1 meter, and the pipeline is not arranged according to the shortest distance in the actual arrangement result, at this time, the actual distance of the pipeline in the arrangement result is obtained, and the pipeline length evaluation result is determined according to the ratio of the actual distance to the shortest distance. And obtaining the pipeline evaluation result according to the space utilization rate evaluation result and the pipeline length evaluation result. The pipeline evaluation result is used for reflecting the reasonable degree of the pipeline layout of the fitting result, and the pipeline evaluation result is obtained, so that the reasonable degree of the pipeline layout of the fitting result is accurately evaluated.
The method provided by the embodiment of the present application further includes step S440:
s441-8: constructing an evaluation parameter standard value set, wherein each evaluation parameter in the evaluation parameter standard value set has a preset assigned value;
s441-9: performing standard value deviation comparison in the evaluation parameter standard value set according to the number evaluation parameter of the conflict nodes, the adjustment amplitude evaluation parameter, the abnormal coefficient evaluation result, the space utilization rate evaluation result and the pipeline length evaluation result to obtain a deviation comparison result;
s441-10: and obtaining the pipeline evaluation result according to the deviation comparison result and the preset distribution value.
Specifically, obtaining standard values of the evaluation parameters, wherein the evaluation parameters include the number of collision nodes evaluation parameters, the adjustment amplitude evaluation parameters, the abnormal coefficient evaluation result, the space utilization rate evaluation result and the pipeline length evaluation result, obtaining the standard values of the evaluation parameters, the standard values being predetermined distribution values of the evaluation parameters, being set according to actual conditions, and constructing an evaluation parameter standard value set according to the standard values of the evaluation parameters. And performing deviation comparison one by one according to the number evaluation parameters of the conflict nodes, the adjustment amplitude evaluation parameters, the abnormal coefficient evaluation results, the space utilization evaluation results, the pipeline length evaluation results and the evaluation parameter standard values in the evaluation parameter standard value set obtained in the steps in the embodiment to obtain deviation comparison results, wherein the deviation comparison results comprise deviation values of the evaluation parameters. And obtaining the pipeline evaluation result according to the deviation comparison result and a preset distribution value, namely the evaluation parameter standard value, wherein the pipeline evaluation result comprises the deviation value of each evaluation parameter, the evaluation parameter standard value and the actual value of the evaluation parameter, so that the reasonable degree of pipeline layout of the fitting result can be more intuitively and accurately evaluated, unreasonable evaluation parameters can be intuitively obtained, and the pipeline layout result can be improved or optimized in time.
As shown in fig. 3, the method step S500 provided in the embodiment of the present application includes:
s510: obtaining the evaluation result of the number of the pipeline accessories according to the layout result;
s520: evaluating the pipeline installation convenience of the layout result to obtain a convenience evaluation result;
s530: and obtaining the pipeline evaluation result according to the accessory quantity evaluation result and the convenience evaluation result.
Specifically, obtain the annex quantity of laying the pipe fitting according to the pipeline and lay the result, the pipeline annex is other parts except accomplishing warm logical air conditioning equipment function itself, for example, some warm logical air conditioning equipment has contained refrigeration plant, ventilation equipment, electrical control equipment, the box, some pipelines and parts such as a plurality of wire constitute, above-mentioned equipment is the equipment of accomplishing warm logical air conditioning equipment function itself, and the equipment that is used for fixed above-mentioned pipeline and circuit to play certain fixed function is accessory equipment, accessory equipment is not the equipment of accomplishing warm logical air conditioning equipment function itself. The number of accessories of the pipeline is obtained, the evaluation result of the number of accessories of the pipeline is obtained according to the number of accessories of the pipeline, the evaluation result of the number of accessories of the pipeline is lower when the number of accessories of the pipeline is larger, the evaluation result of the number of accessories of the pipeline is lower according to the added value of the number of accessories of the pipeline, for example, the evaluation result of the number of accessories of the pipeline is reduced by one evaluation level when the number of accessories of the pipeline is increased by 10. And evaluating the pipeline installation convenience degree of the layout result to obtain a convenience degree evaluation result, wherein the evaluation is carried out according to the installation environment of the layout result when the pipeline installation convenience degree evaluation is carried out, the evaluation process can be manually analyzed to obtain the final convenience degree evaluation result. And obtaining the pipeline evaluation result according to the accessory quantity evaluation result and the convenience evaluation result. The pipeline evaluation result is further enriched by acquiring the accessory quantity evaluation result and the convenience evaluation result, so that the acquired pipeline evaluation result is more accurate and comprehensive.
To sum up, the method provided by the embodiment of the present application constructs the building BIM model through the basic information of the building. And acquiring the installation constraint conditions of the heating, ventilating and air conditioning equipment of the building according to the basic information. And fitting the installation positions of the equipment according to the constraint conditions to obtain a plurality of installation position fits. And obtaining the laid pipeline information according to the construction result, and generating a pipeline association constraint condition according to the laid pipeline information. And laying the plurality of fitting result pipelines according to the pipeline association constraint conditions to obtain a plurality of laying results. And evaluating the layout result by using pipelines to obtain the evaluation sequence of the pipeline evaluation result, and installing the heating ventilation air conditioning equipment according to the optimal scheme in the evaluation sequence. The technical problem that the pipeline layout scheme has defects when the heating ventilation air conditioning equipment is installed due to human reasons because a standardized heating ventilation air conditioning equipment installation method is lacked in the prior art is solved. The technical effect of obtaining the optimal scheme for installing the heating, ventilating and air conditioning equipment is achieved.
Example two
Based on the same inventive concept as the method for installing the heating, ventilating and air conditioning equipment based on the BIM in the foregoing embodiment, as shown in fig. 4, the present application provides a system for installing the heating, ventilating and air conditioning equipment based on the BIM, the system including:
the model construction module 11 is used for obtaining basic information of a building, and constructing a BIM (building information modeling) model of the building according to the basic information to obtain a construction result;
a constraint condition obtaining module 12, configured to perform constraint on the heating, ventilation and air conditioning equipment of the building according to the basic information to obtain a constraint condition;
a position fitting module 13, configured to perform position fitting on the heating, ventilating and air conditioning equipment in the constructed result according to the constraint condition to obtain a fitting result, where the fitting result includes multiple position fitting results;
a pipeline association constraint condition obtaining module 14, configured to obtain the laid pipeline information according to the building result, and generate a pipeline association constraint condition of the hvac device according to the laid pipeline information;
the pipeline evaluation module 15 is used for performing pipeline layout of the fitting result according to the pipeline association constraint conditions and generating pipeline evaluation results of a plurality of position fitting results based on the layout result;
and the pipeline evaluation sequencing module 16 is used for carrying out evaluation sequencing according to the pipeline evaluation result to obtain a pipeline evaluation result, and carrying out installation of the heating, ventilating and air conditioning equipment based on a pipeline layout result corresponding to the pipeline evaluation result.
Further, the pipeline association constraint obtaining module is further configured to:
obtaining a pipeline layout data set through big data;
constructing distance parameters of different pipeline types according to the pipeline layout data set to obtain distance parameter constraint conditions;
performing pipeline layout level sequence evaluation according to the pipeline layout data set, and obtaining a pipeline level sequence constraint condition according to an evaluation result;
obtaining the pipeline association constraint according to the distance parameter constraint and the pipeline hierarchy order constraint.
Further, the pipeline evaluation module is further configured to:
performing entity extraction on the archive information to obtain knowledge graph entity information;
judging whether pipeline position conflict exists in the process of laying the fitting result pipelines according to the pipeline association constraint conditions;
when the pipeline position conflict exists, obtaining conflict node information;
obtaining the number evaluation parameters of the collision nodes of the fitting result according to the information of the collision nodes;
performing adjustment amplitude evaluation on each collision node according to the collision node information to obtain adjustment amplitude evaluation parameters of the fitting result;
and obtaining the pipeline evaluation result according to the number evaluation parameter of the conflict nodes and the adjustment amplitude evaluation parameter.
Further, the pipeline evaluation module is further configured to:
acquiring a node memory intensity attribute and a node influence intensity attribute;
traversing the node cluster to extract information according to the node memory strength attribute and the node influence strength attribute to obtain a node memory strength attribute value set and a node influence strength attribute value set;
and sequentially inputting the node memory intensity attribute value set and the node influence intensity attribute value set into an importance degree evaluation channel to obtain an importance degree set, wherein the importance degrees are in one-to-one correspondence with the nodes.
Further, the pipeline evaluation module is further configured to:
evaluating the space utilization rate according to the layout result to obtain a space utilization rate evaluation result;
evaluating the length of the pipeline according to the layout result to obtain an evaluation result of the length of the pipeline;
and obtaining the pipeline evaluation result according to the space utilization rate evaluation result and the pipeline length evaluation result.
Further, the pipeline evaluation module is further configured to:
constructing an evaluation parameter standard value set, wherein each evaluation parameter in the evaluation parameter standard value set has a preset assigned value;
performing standard value deviation comparison in the evaluation parameter standard value set according to the number evaluation parameters of the conflict nodes, the adjustment amplitude evaluation parameters, the abnormal coefficient evaluation results, the space utilization rate evaluation results and the pipeline length evaluation results to obtain deviation comparison results;
and obtaining the pipeline evaluation result according to the deviation comparison result and the preset distribution value.
Further, the pipeline evaluation module is further configured to:
obtaining the evaluation result of the number of the pipeline accessories according to the layout result;
evaluating the pipeline installation convenience of the layout result to obtain a convenience evaluation result;
and obtaining the pipeline evaluation result according to the accessory quantity evaluation result and the convenience evaluation result.
The second embodiment is used for executing the method as in the first embodiment, and both the execution principle and the execution basis can be obtained through the content recorded in the first embodiment, which is not described herein again. Although the present application has been described in connection with particular features and embodiments thereof, the present application is not limited to the example embodiments described herein. Based on the embodiments of the present application, those skilled in the art can make various changes and modifications to the present application without departing from the scope of the present application, and the content thus obtained also falls within the scope of protection of the present application.

Claims (8)

1. A BIM-based heating, ventilating and air conditioning equipment installation method is characterized by comprising the following steps:
obtaining basic information of a building, and constructing a BIM (building information modeling) model of the building according to the basic information to obtain a construction result;
carrying out heating ventilation air conditioning equipment constraint on the building according to the basic information to obtain constraint conditions;
performing position fitting on the heating ventilation air conditioning equipment in the construction result according to the constraint condition to obtain a fitting result, wherein the fitting result comprises a plurality of position fitting results;
acquiring laid pipeline information according to the construction result, and generating a pipeline association constraint condition of the heating ventilation air conditioning equipment according to the laid pipeline information;
performing pipeline layout of the fitting result according to the pipeline association constraint condition, and generating pipeline evaluation results of a plurality of position fitting results based on the layout result;
and carrying out evaluation sequencing according to the pipeline evaluation result to obtain a pipeline evaluation result, and installing the heating, ventilating and air conditioning equipment based on a pipeline layout result corresponding to the pipeline evaluation result.
2. The method of claim 1, wherein generating the piping association constraints for the hvac unit from the deployed piping information further comprises:
obtaining a pipeline layout data set through big data;
constructing distance parameters of different pipeline types according to the pipeline layout data set to obtain distance parameter constraint conditions;
performing pipeline layout level sequence evaluation according to the pipeline layout data set, and obtaining a pipeline level sequence constraint condition according to an evaluation result;
and obtaining the pipeline association constraint condition according to the distance parameter constraint condition and the pipeline level sequence constraint condition.
3. The method of claim 2, wherein said performing said pipeline layout according to said pipeline association constraints, generating pipeline evaluation results for a plurality of position fitting results based on layout results, further comprises:
judging whether pipeline position conflict exists in the process of laying the fitting result pipelines according to the pipeline association constraint conditions;
when the pipeline position conflict exists, obtaining conflict node information;
obtaining the number evaluation parameters of the conflict nodes of the fitting result according to the conflict node information;
performing adjustment amplitude evaluation on each collision node according to the collision node information to obtain adjustment amplitude evaluation parameters of the fitting result;
and obtaining the pipeline evaluation result according to the number evaluation parameter of the conflict nodes and the adjustment amplitude evaluation parameter.
4. The method of claim 3, wherein the method further comprises:
judging whether the conflict node information has an abnormal rule to adjust the conflict node;
when the abnormal rule adjustment conflict node exists, the abnormal conflict node carries out identification to obtain an identification result;
performing abnormal coefficient evaluation on the identification result to obtain an abnormal coefficient evaluation result;
and obtaining the pipeline evaluation result according to the abnormal coefficient evaluation result and the identification result.
5. The method of claim 4, wherein the method further comprises:
evaluating the space utilization rate according to the layout result to obtain a space utilization rate evaluation result;
evaluating the length of the pipeline according to the layout result to obtain an evaluation result of the length of the pipeline;
and obtaining the pipeline evaluation result according to the space utilization rate evaluation result and the pipeline length evaluation result.
6. The method of claim 5, wherein the method further comprises:
constructing an evaluation parameter standard value set, wherein each evaluation parameter in the evaluation parameter standard value set has a preset assigned value;
performing standard value deviation comparison in the evaluation parameter standard value set according to the number evaluation parameter of the conflict nodes, the adjustment amplitude evaluation parameter, the abnormal coefficient evaluation result, the space utilization rate evaluation result and the pipeline length evaluation result to obtain a deviation comparison result;
and obtaining the pipeline evaluation result according to the deviation comparison result and the preset distribution value.
7. The method of claim 1, wherein the method further comprises:
obtaining the evaluation result of the number of the pipeline accessories according to the layout result;
evaluating the pipeline installation convenience of the layout result to obtain a convenience evaluation result;
and obtaining the pipeline evaluation result according to the accessory quantity evaluation result and the convenience evaluation result.
8. A BIM-based hvac unit mounting system, the system comprising:
the model construction module is used for obtaining basic information of a building, and constructing a BIM (building information modeling) model of the building according to the basic information to obtain a construction result;
the constraint condition acquisition module is used for carrying out constraint on heating ventilation air conditioning equipment of the building according to the basic information to obtain constraint conditions;
the position fitting module is used for performing position fitting on the heating ventilation air conditioning equipment in the constructed result according to the constraint condition to obtain a fitting result, wherein the fitting result comprises a plurality of position fitting results;
the pipeline association constraint condition acquisition module is used for acquiring the laid pipeline information according to the construction result and generating the pipeline association constraint condition of the heating, ventilating and air conditioning equipment according to the laid pipeline information;
the pipeline evaluation module is used for laying the fitting result pipelines according to the pipeline association constraint conditions and generating pipeline evaluation results of a plurality of position fitting results based on laying results;
and the pipeline evaluation sequencing module is used for carrying out evaluation sequencing according to the pipeline evaluation result to obtain a pipeline evaluation result and carrying out installation of the heating, ventilating and air conditioning equipment based on a pipeline layout result corresponding to the pipeline evaluation result.
CN202210544235.1A 2022-05-19 2022-05-19 Heating ventilation air conditioning equipment installation method and system based on BIM Active CN114912178B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210544235.1A CN114912178B (en) 2022-05-19 2022-05-19 Heating ventilation air conditioning equipment installation method and system based on BIM

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210544235.1A CN114912178B (en) 2022-05-19 2022-05-19 Heating ventilation air conditioning equipment installation method and system based on BIM

Publications (2)

Publication Number Publication Date
CN114912178A true CN114912178A (en) 2022-08-16
CN114912178B CN114912178B (en) 2022-12-23

Family

ID=82769184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210544235.1A Active CN114912178B (en) 2022-05-19 2022-05-19 Heating ventilation air conditioning equipment installation method and system based on BIM

Country Status (1)

Country Link
CN (1) CN114912178B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115358034A (en) * 2022-08-31 2022-11-18 扬州工业职业技术学院 Intelligent arrangement method and system based on BIM (building information modeling) comprehensive optimization design
CN117053868A (en) * 2023-08-15 2023-11-14 苏州苏明装饰股份有限公司 Detection and evaluation method and system for assembled partition wall system

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20160012357A1 (en) * 2014-07-09 2016-01-14 International Business Machines Corporation Automated Space Layout Based on Business Constraints
JP2016095581A (en) * 2014-11-12 2016-05-26 株式会社日立製作所 Equipment arrangement device and equipment arrangement method
CN107545080A (en) * 2016-06-23 2018-01-05 中国铁道科学研究院铁道建筑研究所 A kind of virtual pre-assembly method of steel bridge based on BIM models
CN108898662A (en) * 2018-05-30 2018-11-27 中国人民解放军陆军勤务学院 Pipeline facility BIM model automatization method for reconstructing based on point cloud data
CN110502803A (en) * 2019-07-29 2019-11-26 兰州容大信息科技有限公司 Wiring method and device based on BIM technology
US20210056242A1 (en) * 2019-08-21 2021-02-25 Bricsys Nv Computer-implemented generation of an analytical model of a structure
CN112464424A (en) * 2020-12-21 2021-03-09 同济大学建筑设计研究院(集团)有限公司 Air duct system prefabricating method based on BIM
CN112560212A (en) * 2020-12-22 2021-03-26 中设数字技术股份有限公司 Spraying system based on BIM model, spraying head and pipeline generation type design method
CN113806894A (en) * 2021-08-06 2021-12-17 国网河北省电力有限公司雄安新区供电公司 Power grid BIM planning method based on smart city data
CN114297748A (en) * 2021-12-13 2022-04-08 盈嘉互联(北京)科技有限公司 Method for predicting hidden line of existing building based on Scan-to-BIM

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20160012357A1 (en) * 2014-07-09 2016-01-14 International Business Machines Corporation Automated Space Layout Based on Business Constraints
JP2016095581A (en) * 2014-11-12 2016-05-26 株式会社日立製作所 Equipment arrangement device and equipment arrangement method
CN107545080A (en) * 2016-06-23 2018-01-05 中国铁道科学研究院铁道建筑研究所 A kind of virtual pre-assembly method of steel bridge based on BIM models
CN108898662A (en) * 2018-05-30 2018-11-27 中国人民解放军陆军勤务学院 Pipeline facility BIM model automatization method for reconstructing based on point cloud data
CN110502803A (en) * 2019-07-29 2019-11-26 兰州容大信息科技有限公司 Wiring method and device based on BIM technology
US20210056242A1 (en) * 2019-08-21 2021-02-25 Bricsys Nv Computer-implemented generation of an analytical model of a structure
CN112464424A (en) * 2020-12-21 2021-03-09 同济大学建筑设计研究院(集团)有限公司 Air duct system prefabricating method based on BIM
CN112560212A (en) * 2020-12-22 2021-03-26 中设数字技术股份有限公司 Spraying system based on BIM model, spraying head and pipeline generation type design method
CN113806894A (en) * 2021-08-06 2021-12-17 国网河北省电力有限公司雄安新区供电公司 Power grid BIM planning method based on smart city data
CN114297748A (en) * 2021-12-13 2022-04-08 盈嘉互联(北京)科技有限公司 Method for predicting hidden line of existing building based on Scan-to-BIM

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
ANDREAS SPORR等: "Automated HVAC Control Creation Based on Building Information Modeling (BIM): Ventilation System", 《 IEEE ACCESS 》 *
张宁波等: "机电安装工程暖通空调新技术及发展趋势概述", 《安装》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115358034A (en) * 2022-08-31 2022-11-18 扬州工业职业技术学院 Intelligent arrangement method and system based on BIM (building information modeling) comprehensive optimization design
CN117053868A (en) * 2023-08-15 2023-11-14 苏州苏明装饰股份有限公司 Detection and evaluation method and system for assembled partition wall system
CN117053868B (en) * 2023-08-15 2024-03-26 苏州苏明装饰股份有限公司 Detection and evaluation method and system for assembled partition wall system

Also Published As

Publication number Publication date
CN114912178B (en) 2022-12-23

Similar Documents

Publication Publication Date Title
CN114912178B (en) Heating ventilation air conditioning equipment installation method and system based on BIM
US7065476B2 (en) Adaptable multi-representation building systems part
JP5557622B2 (en) Construction simulation method and apparatus
TWI546687B (en) System and method for automated building services design
US8499275B2 (en) Planar manufacturing drawing production support device, planar manufacturing drawing production support method, planar manufacturing drawing production support program and branch angle design support device
US10331845B2 (en) Fuse multiple drawings into an equipment (BIM) model
O'Neill et al. Modeling and Calibration of Energy Models for a DoD Building.
US7689386B1 (en) Automated duct work designer and layout engine
WO2023286756A1 (en) Method for arranging environment adjustment device, device, and system
CN111859515B (en) Pump house modeling method based on BIM technology
US20210232724A1 (en) Method and Apparatus for Specifying Locations for Objects, and Determining Routes for Connecting Mediums Between the Objects, in a Three-Dimensional Model of a Building
JP2023168401A (en) Cable management apparatus and cable management method
JP5324363B2 (en) Airflow state calculation method, program and apparatus
Chen et al. Robust IFC files to improve information exchange: An application for thermal energy simulation
US20120109588A1 (en) Manufacture of heat trace cable, design, installation, and management, and method thereof
JP2024516117A (en) CAD APPARATUS WITH UTILITY ELEMENT ROUTING AND ASSOCIATED METHODS - Patent application
JP6544989B2 (en) Plant construction process change impact assessment device
WO2020209380A1 (en) Machine learning device
Liang et al. Realization of rule-based automated design for HVAC duct layout
KR20140067798A (en) An installation guide system for an air conditioner and a using method the same
JP2020174343A (en) Machine learning device
KR102622096B1 (en) Quantity calculation and management system by applying family parts for cooling, heating and air conditioning systems of facilities
CN112528380A (en) Method and system for optimizing ventilation environment of electric room
CN114323261B (en) Method for forecasting and evaluating vibration noise of ventilation system of offshore equipment
EP4293561A1 (en) A method for installation of an acoustical system in a room

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant