CN114899755A - Pipeline fixer - Google Patents
Pipeline fixer Download PDFInfo
- Publication number
- CN114899755A CN114899755A CN202210660479.6A CN202210660479A CN114899755A CN 114899755 A CN114899755 A CN 114899755A CN 202210660479 A CN202210660479 A CN 202210660479A CN 114899755 A CN114899755 A CN 114899755A
- Authority
- CN
- China
- Prior art keywords
- layer
- sleeves
- pipeline
- frame structure
- sleeve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
- H02G1/08—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G3/00—Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
- H02G3/36—Installations of cables or lines in walls, floors or ceilings
- H02G3/38—Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G3/00—Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
- H02G3/36—Installations of cables or lines in walls, floors or ceilings
- H02G3/38—Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts
- H02G3/386—Installations of cables or lines in walls, floors or ceilings the cables or lines being installed in preestablished conduits or ducts in walls
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention belongs to the technical field of pipeline fixing in building construction, and particularly relates to a pipeline construction fixing device for a weak current household box. The method is characterized in that: the fixer is fixed into a double-layer frame structure by steel bars, a plurality of sleeves are welded on the frame structure of each layer, and plugging caps are arranged in the sleeves on the upper layer; the distance intervals between every two sleeves are consistent, and the sleeves of the upper layer and the lower layer correspond to each other one by one. The length of each sleeve pipe on the lower layer is 3-8 cm, and the length of each sleeve pipe on the upper layer is 5-12 cm. The steel reinforcement frame made of excess steel reinforcement, the sleeve made of JDG pipe with diameter of 25 or 32mm and the blocking cap made of PVC pipe define the position of the upper end of the pipeline entering the weak current branch box. The invention aims to solve the problem of complicated steps in the process of pipeline construction and installation, so that the pipeline can be fixed and positioned in one step.
Description
Technical Field
The invention belongs to the technical field of pipeline fixing in building construction, and particularly relates to a pipeline construction fixing device for a weak current household box.
Background
In the early stage of building electrical engineering, in the stage of embedding the electrical pipelines, the disordered arrangement state of the pipelines often appears; especially, when the electrical pipelines are bent and are perpendicular to the floor slab, the arrangement is very disordered at the beginning, the pipelines have certain strength, and a part of the pipelines are rebounded after bending, so that the distance and the extension direction of the pipelines are uneven, the pipelines are easy to deviate in the subsequent concrete pouring, great difficulty is caused for the connection of the subsequently installed weak current household boxes, and the pipelines are difficult to manufacture and survive once; even a mode of secondary pipe connection and box feeding is adopted, so that material and labor waste is caused, and the risk of pipe blockage is easily caused by adding a pipe joint in the shear wall.
In addition, some pipeline fixing devices need to drill holes on each casing pipe, and the positions of the pipeline fixing devices are fixed through screws, namely the cylindrical cambered surface of the PVC pipe and the conical shape of the screw, so that the operation is very inconvenient, and great inconvenience is brought to construction.
Furthermore, in the past, before concrete pouring, each pipeline is sleeved with a buckle cover, so that the blockage caused by scattering in the concrete pouring process is avoided, and time and labor are wasted.
Disclosure of Invention
The invention provides a pipeline fixer, which aims to solve the problem of complicated steps in the pipeline construction and installation process, so that the pipeline fixing and positioning can be completed in one step.
A line retainer, comprising: the fixer is fixed into a double-layer frame structure by steel bars, a plurality of sleeves are welded on the frame structure of each layer, and plugging caps are arranged in the sleeves on the upper layer; the distance intervals between every two sleeves are consistent, and the sleeves of the upper layer and the lower layer correspond to each other one by one.
Preferably, each layer of the fixer is provided with two rows of sleeves, and auxiliary steel bars are welded between the two rows of sleeves.
Preferably, the length of each sleeve on the lower layer is 3-8 cm, and the length of each sleeve on the upper layer is 5-12 cm.
Preferably, the double-layer frame structure is formed by welding and fixing steel bars, and the height of the double-layer frame structure is the distance between the floor surface and the weak current household box.
Preferably, the location of the pipeline into the light current household box is defined by a double-layer frame structure made of excess steel bars and a sleeve made of JDG pipe with the diameter of 25 or 32 mm.
Preferably, the blocking cap made of PVC pipe defines the location of the upper end of the pipeline entering the weak current household box.
Preferably, each layer of the frame structure is provided with steel strands for winding the anchor and enabling the anchor to be reused.
Preferably, a limiting groove for fixing the pipeline is arranged in the plugging cap.
The advantages and effects are as follows:
the invention can well solve the complex problem of the installation and the fixation of the line pipe, can be used for installation and fixation, can limit and fix the position, and can be completed by one-step operation. The installation operation is extremely simple, and the previous complex processes are reduced. In addition, the invention adopts the existing device made of leftover bits and pieces, has extremely low cost and can be popularized in a large range. The frame adopts the short ends of the on-site reinforcement excess materials, thereby being low-carbon, environment-friendly, cost-reducing and efficiency-improving. The pipe hoop adopts the direct preparation of JDG pipe, and a pair needs 10~20 to vary, according to different models, its unit price is about 0.65~0.8 yuan, calculate according to every 20, and single pair material cost is about 16 yuan, and every family is in the construction line production section to quantity assurance, and the processing manual work is 50 for a welder can make finished product for a worker day, and welder day unit price considers 350~400 every worker day at present, and 7~8 pieces of single labour cost, and the expense adds up: the cost of a single finished product is 24 pieces of money, 6 pairs of finished products are considered for two households according to three units and one ladder, and about 6X 24=144 yuan is needed for one building. In addition, the device can be recycled.
Drawings
FIG. 1 is a schematic diagram of the main structure of the present invention;
FIG. 2 is a side view of FIG. 1;
FIG. 3 is a schematic diagram of a prior art configuration;
FIG. 4 is a bottom view of the containment cap of the present invention;
fig. 5 is a position relation diagram of the weak current household box 8.
The reference numerals are represented as:
a holder 1; a frame structure 2; a sleeve 3; a plugging cap 4; a steel strand 5; a screw 6; a limiting groove 7; a weak current household box 8; a pipeline 9 and an auxiliary reinforcing steel bar 10.
Detailed Description
The most critical place for the positioner 1 of the present invention is to position the pipeline accurately. Before concrete is poured on the building floor, the pipelines are bent to be vertical to the floor after the pipelines on the floor are arranged, and the pipelines 9 need to be strictly arranged at intervals. The steel bar is used as a framework and is designed into an upper-layer frame structure 2 and a lower-layer frame structure 2, a plurality of sleeves 3 are welded on the frame structure 2 of each layer, and plugging caps 4 are arranged in the sleeves 3 of the upper layer; the distance between each casing 3 is consistent, and each casing 3 of the upper and lower layers corresponds to each other, so that the position of each pipeline is approximately consistent, as shown in fig. 1 and 2.
After the pipeline 9 is bent to a position vertical to the floor surface, the sleeve 3 on the positioner 1 passes through the pipeline, and the steel strands 5 at two ends are bound on the nearby floor steel bars for fixing. The weak current household boxes 8 can be arranged in a plurality of rows, generally arranged in two rows, the invention is arranged in two rows, pipelines in each row are not equal, and the invention is arranged in 4 rows. The former worker is simple in operation, only one welding point is electrically welded on the upper row of sleeves 3 and the lower row of sleeves 3, the welding point is arranged at the position where the reinforcing steel bars 2 are contacted with the sleeves 3, and the falling-off condition is always found in the practical process. From the mechanical point of view, each sleeve 3 is only welded at the edge and is not firm, so the auxiliary steel bars 10 are also welded between the two rows of sleeves 3, and thus, the two welding points balance the stress of the sleeves 3 and keep the strength.
Each sleeve 3 on the lower layer is 3-8 cm in length and mainly plays a role in limiting, and the line pipe 9 penetrates through the sleeves 3 and is approximately consistent in range within a certain distance. Each sleeve 3 on the upper layer is 5-12 cm in length and slightly longer than the sleeve 3 on the lower layer, because the sleeve 3 on the upper layer is internally provided with a plugging cap 4 with a certain length, generally 4-8 cm, and the plugging cap 4 is internally provided with a limiting groove 7, as shown in figure 4.
The previous fixator 1 is of a single-layer structure, holes need to be drilled in the sleeve 3 of the fixator 1, as shown in the attached drawing 3, after the sleeve is sleeved with the pipeline 9, accurate positioning is needed, because the pouring force easily deflects the pipeline when concrete is poured, and after the concrete is solidified, the subsequent installation of the weak current household box 8 is very laborious, and secondary treatment often occurs, so that the bolt 6 is tightened to the pipeline 9 to enable the pipeline to be located at the center position in the sleeve 3.
In the invention, the plugging cap 4 is arranged in the upper-layer sleeve 3, the limiting groove 7 is arranged in the plugging cap 4, and the pipeline 9 is inserted into the limiting groove 7 in the plugging cap 4, so that drilling on the sleeve 3 is saved, and the step of fixing the pipeline 9 by the screw 6 is also saved. Since the pipe line 9 is a cylindrical arc surface and the screw 6 is a cone, the fixation is difficult, so the invention is very easy in the process operation. Meanwhile, each pipeline needs to be plugged after the former pipeline 9 is fixed, so that residues are prevented from entering the pipeline 9 to plug the pipeline in the concrete pouring process.
The height of the double-layer frame structure 2 formed by welding and fixing the steel bars is the distance between the floor surface and the weak current household box. The double-layer frame structure 2 is made of excess materials and leftover materials of reinforcing steel bars, the double-layer frame structure 2 and the auxiliary reinforcing steel bars 10 are made of excess material stubs, and the total length of the fixer 1 is less than 40-60 cm, the height is 20-30 cm, and therefore the excess materials and the leftover materials are completely used. The JDG pipe with the diameter of 25 or 32mm is made of a corner waste material, the length of the JDG pipe is 3-12 cm, and the plugging cap 4 is made of a PVC material and is also made of a corner excess material plug of a wire pipe, so that the manufacturing cost is greatly reduced.
The holder 1 can be reused 7. After the pipelines 9 are bent and vertical to a floor slab, each pipeline 9 penetrates through the sleeve 3, the fixator 1 is tightly bound through the steel strand 5, each pipeline 9 is limited and fixed through the limiting groove 7 in the plugging cap 4 in the upper-layer sleeve 3, at the moment, concrete pouring is started, and after concrete is solidified and formed, the position of the weak current household box 8 is designed, as shown in the attached drawing 5. Before the weak current household separation box 8 is installed, the steel strand 5 can be untied from the nearby steel bars, the whole fixer 1 with the double-layer frame structure is detached, and the next recycling can be realized.
In conclusion, by adopting the technical scheme of the invention, although a small amount of cost is increased in the pre-burying stage, the primary survival rate of the line pipe is improved when the weak current branch box 8 is pre-buried and installed, if the lengths of the reserved line pipes are consistent, the primary survival can be realized, and the step of secondary pipe connection is omitted (which is easier to realize through practical practice). The joints of the embedded pipelines are reduced by avoiding secondary connection, so that the risk of pipe blockage can be avoided, and part of labor cost is saved. By adopting the measures, the survival effect is obviously improved, common quality problems such as deviation of the line pipes, different lengths of reserved line pipes, untight plugging of the line pipes and the like which are easy to occur at the positions of the household boxes are avoided, and the rework cost for maintaining the wall body grooving at the later stage is indirectly saved.
Claims (8)
1. A line retainer, comprising: the fixer (1) is fixed into a double-layer frame structure (2) by steel bars, a plurality of sleeves (3) are welded on the frame structure (2) on each layer, and plugging caps (4) are arranged in the sleeves (3) on the upper layer; the distance intervals between the sleeves (3) are consistent, and the sleeves (3) of the upper layer and the lower layer correspond to each other one by one.
2. The line retainer of claim 1, wherein: each layer of the fixer (1) is provided with two rows of sleeves (3), and an auxiliary reinforcing steel bar (10) is welded between the two rows of sleeves (3).
3. The line retainer of claim 1, wherein: the length of each sleeve (3) on the lower layer is 3-8 cm, and the length of each sleeve (3) on the upper layer is 5-12 cm.
4. The line retainer of claim 1, wherein: the double-layer frame structure (2) is fixed by welding steel bars, and the height of the double-layer frame structure is the distance between the floor surface and the weak current household box.
5. The line retainer of claim 1, wherein: the position of the pipeline entering the weak current branch box is limited by a double-layer frame structure (2) made of excess steel bars and a sleeve (3) made of JDG pipe with the diameter of 25 or 32 mm.
6. The line holder of claim 1, wherein: a plugging cap (4) made of PVC pipe defines the position of the upper end of the pipeline entering the weak current branch box.
7. The line retainer of claim 1, wherein: each layer of the frame structure (2) is provided with a steel strand (5) for winding the fixator (1) and enabling the fixator (1) to be reused.
8. The line retainer of claim 1, wherein: a limiting groove (7) for fixing the pipeline is arranged in the plugging cap (4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210660479.6A CN114899755A (en) | 2022-06-13 | 2022-06-13 | Pipeline fixer |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210660479.6A CN114899755A (en) | 2022-06-13 | 2022-06-13 | Pipeline fixer |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114899755A true CN114899755A (en) | 2022-08-12 |
Family
ID=82728011
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210660479.6A Pending CN114899755A (en) | 2022-06-13 | 2022-06-13 | Pipeline fixer |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114899755A (en) |
-
2022
- 2022-06-13 CN CN202210660479.6A patent/CN114899755A/en active Pending
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202391019U (en) | End part thickened grouting connector of steel bar | |
CN103806651A (en) | Bridge embedded part and method for installing bridge through bridge embedded part | |
CN107642179A (en) | Assembled frame-shear structure steel plate keyway attachment structure and assembling method | |
CN202117341U (en) | Template for embedding foundation bolts of steel structures of buildings | |
KR100770006B1 (en) | Vertical connection steel-bar reinforcing structure of precast concreate column | |
CN101356318B (en) | Precast concrete segment having connecting structure using steel duct, and connecting structure thereof | |
CN106337561A (en) | Reinforcing structure for shearing wall template and reinforcing construction method thereof | |
CN106958324B (en) | Large-diameter steel bar mesh and method for butting large-diameter steel bar mesh by using connecting rods | |
CN104775617A (en) | Method for reinforcing cast-in-place concrete formwork | |
US5761870A (en) | Connecting structure of concrete blocks and connecting method therefor | |
CN114899755A (en) | Pipeline fixer | |
KR101269639B1 (en) | The core-type sleeve of precast concrete for member of framework | |
CN217692321U (en) | Pipeline fixer | |
CN204252400U (en) | A kind of reinforcing bar connector for earthquake-proof frame top story knee joint | |
CN205791363U (en) | A kind of electrical engineering positioning installation apparatus | |
CN202596173U (en) | Embedded part for cable bridge | |
CN113090025B (en) | Aluminum mold matching overhanging outer frame construction method of full concrete outer wall structure | |
CN109695347B (en) | Building construction method based on round steel holding bender | |
CN113006345A (en) | Steel plate wall and construction method thereof | |
CN211285571U (en) | Asymmetric screw sleeve connecting device for main reinforcement of bridge drilling cast-in-place pile reinforcement cage | |
CN211499326U (en) | Synchronous construction structures of concrete infilled wall and cast-in-place structure | |
CN210369306U (en) | Steel pipe takes assembled concrete frame beam column joint construction of U-shaped steel corbel | |
CN104131631A (en) | Structure of top layer end node of anti-seismic framework and construction method of structure | |
CN112983465A (en) | Fully-prefabricated internal structure of shield tunnel and construction method | |
CN111002432A (en) | Prefabricated constructional column template and using method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |