CN114897265A - Multi-factor-considered energy storage location and volume optimization method, system, terminal and medium - Google Patents

Multi-factor-considered energy storage location and volume optimization method, system, terminal and medium Download PDF

Info

Publication number
CN114897265A
CN114897265A CN202210647731.XA CN202210647731A CN114897265A CN 114897265 A CN114897265 A CN 114897265A CN 202210647731 A CN202210647731 A CN 202210647731A CN 114897265 A CN114897265 A CN 114897265A
Authority
CN
China
Prior art keywords
energy storage
power
output value
risk
substation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210647731.XA
Other languages
Chinese (zh)
Other versions
CN114897265B (en
Inventor
胡远江
钟行
黄德青
刘睿
任振祥
张文宇
秦娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Lingan Intelligent Technology Co ltd
Southwest Jiaotong University
Original Assignee
Sichuan Lingan Intelligent Technology Co ltd
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Lingan Intelligent Technology Co ltd, Southwest Jiaotong University filed Critical Sichuan Lingan Intelligent Technology Co ltd
Priority to CN202210647731.XA priority Critical patent/CN114897265B/en
Publication of CN114897265A publication Critical patent/CN114897265A/en
Application granted granted Critical
Publication of CN114897265B publication Critical patent/CN114897265B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for AC mains or AC distribution networks
    • H02J3/28Arrangements for balancing of the load in a network by storage of energy
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Health & Medical Sciences (AREA)
  • Educational Administration (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The invention discloses a multi-factor considered energy storage site selection constant volume optimization method, a system, a terminal and a medium, which relate to the technical field of power systems, and the technical scheme key points are as follows: obtaining the load rate of each node of the power system according to the maximum load and rated capacity of annual operation in the power system, and analyzing the influence of the load rate of each node of the power system on the power supply guarantee of a power supply area to obtain the risk electric quantity; analyzing an output value corresponding to the risk electric quantity according to economic output value data of each region to obtain a risk output value; and inputting the risk output value and the total energy storage configuration amount of each region into a pre-constructed energy storage location constant volume model for optimization analysis to obtain the energy storage power and the energy storage capacity of each node of the power system. The invention simultaneously considers two factors of regional economic development and peak clipping and valley filling improvement of the power system, not only improves and supports the power system, but also comprehensively considers the electricity utilization support of energy storage to local residents and industrial and commercial users.

Description

考虑多因素的储能选址定容优化方法、系统、终端及介质Optimization method, system, terminal and medium of energy storage site selection and capacity considering multiple factors

技术领域technical field

本发明涉及电力系统技术领域,更具体地说,它涉及考虑多因素的储能选址定容优化方法、系统、终端及介质。The invention relates to the technical field of electric power systems, and more particularly, to an optimization method, system, terminal and medium for energy storage location selection and capacity determination considering multiple factors.

背景技术Background technique

随着新能源在国内外的蓬勃发展,新能源出力的随机不确定性给电力系统的安全平稳运行带来了严重影响,主要影响包括新能源出力的高峰低谷与用电侧的高峰低谷时间不对应、电力功率不平衡等问题,其次由新能源出力的随机不确定性导致的新能源出力的预测难、精度低、可预测分辨率低等问题,最后为了促进新能源的消纳显著减少了传统火电机组的出力规划,导致系统稳定供电资源显著减少,从而引起限电、电荒、用电难等问题。With the vigorous development of new energy at home and abroad, the random uncertainty of the output of new energy has brought a serious impact on the safe and stable operation of the power system. Correspondence, power imbalance and other problems, followed by the difficulty of predicting new energy output caused by the random uncertainty of new energy output, low precision, low predictable resolution and other problems, and finally, in order to promote the consumption of new energy is significantly reduced. The output planning of traditional thermal power units has led to a significant reduction in the stable power supply resources of the system, resulting in problems such as power cuts, power shortages, and difficulty in power consumption.

现有的储能规划主要从电力系统角度出发,鲜有考虑地区经济发展需求;而从政府角度开展的储能规划技术重点考虑了用地成本、地方经济发展、产业链构建和开展综合示范应用等因素,缺乏对电力系统的分析。然而,储能的规划布局中不仅需要考虑对电力系统的改善和支撑,还需要统筹考虑储能对当地居民、工商业用户的用电支撑,保障用户用电可靠性社会效益最大化。The existing energy storage planning mainly starts from the perspective of the power system, and seldom considers the needs of regional economic development; while the energy storage planning technology developed from the perspective of the government focuses on the cost of land use, local economic development, industrial chain construction, and comprehensive demonstration applications. factors, lack of analysis of the power system. However, in the planning and layout of energy storage, it is not only necessary to consider the improvement and support of the power system, but also to consider the power consumption support of energy storage for local residents, industrial and commercial users, and to ensure the maximum social benefits of users' power reliability.

因此,如何研究设计一种能够克服上述缺陷的储能选址定容优化方法、系统、终端及介质是我们目前急需解决的问题。Therefore, how to research and design an optimization method, system, terminal and medium for energy storage location and capacity that can overcome the above defects is an urgent problem that we need to solve at present.

发明内容SUMMARY OF THE INVENTION

为解决现有技术中的不足,本发明的目的是提供考虑多因素的储能选址定容优化方法、系统、终端及介质,同时考虑了地区经济发展和电力系统削峰填谷改善两种因素,不仅对电力系统有改善和支撑效果,还能统筹考虑储能对当地居民、工商业用户的用电支撑,兼顾不同规划方的侧重点,有利于规划方案的落地和执行,保障用户用电可靠性以及社会效益最大化。In order to solve the deficiencies in the prior art, the purpose of the present invention is to provide an optimization method, system, terminal and medium for energy storage site selection and capacity determination that consider multiple factors, and consider both regional economic development and power system peak shaving and valley filling improvement. Factors, not only have the effect of improving and supporting the power system, but also consider the power support of energy storage to local residents, industrial and commercial users, and take into account the priorities of different planners, which is conducive to the implementation and implementation of planning schemes and ensures users’ power consumption. Reliability and social benefits are maximized.

本发明的上述技术目的是通过以下技术方案得以实现的:The above-mentioned technical purpose of the present invention is achieved through the following technical solutions:

第一方面,提供了考虑多因素的储能选址定容优化方法,包括以下步骤:In the first aspect, an optimization method for energy storage site selection and capacity determination considering multiple factors is provided, including the following steps:

根据电力系统中年度运行的最大负荷和额定容量得到电力系统各节点的负载率,并分析电力系统各节点的负载率对供电区域供电保障性的影响,得到风险电量;According to the annual maximum load and rated capacity of the power system, the load rate of each node of the power system is obtained, and the influence of the load rate of each node of the power system on the security of power supply in the power supply area is analyzed to obtain the risk electricity;

依据各地区的经济产值数据对风险电量所对应的产值进行分析,得到风险产值;According to the economic output value data of each region, the output value corresponding to the risk electricity is analyzed to obtain the risk output value;

将风险产值以及各区域的储能配置总量输入预构建的储能选址定容模型进行优化分析,得到电力系统各节点的储能功率和储能容量。The risk output value and the total energy storage configuration of each region are input into the pre-built energy storage location and capacity model for optimization analysis, and the energy storage power and energy storage capacity of each node of the power system are obtained.

进一步的,所述风险产值的获得过程具体为:Further, the process of obtaining the risk output value is as follows:

依据经济产值数据确定过负载变电站所在区域的度电产值;Determine the kWh output value of the area where the overloaded substation is located according to the economic output value data;

以风险电量与度电产值的乘积确定相应过负载变电站的风险产值。The risk output value of the corresponding overloaded substation is determined by the product of the risk quantity and the kWh output value.

进一步的,所述度电产值为经济产值数据与相应区域内全社会用电量的比值。Further, the kWh output value is the ratio of the economic output value data to the electricity consumption of the whole society in the corresponding area.

进一步的,所述风险电量为各地区节点超出安全负载率所对应的供电电量。Further, the risk power is the power supply power corresponding to the nodes in each region exceeding the safe load rate.

进一步的,所述安全负载率依据各变电站额定容量的百分比与对应变电站的配置系数的乘积确定。Further, the safe load rate is determined according to the product of the percentage of the rated capacity of each substation and the configuration coefficient of the corresponding substation.

进一步的,所述储能功率的计算公式具体为:Further, the calculation formula of the energy storage power is specifically:

Figure BDA0003686675400000021
Figure BDA0003686675400000021

其中,

Figure BDA0003686675400000022
表示变电站j优化分析后应配置的储能功率;fj表示变电站j的风险产值;fi表示变电站i的风险产值;N表示变电站数量;P0表示各区域内储能允许配置的总功率。in,
Figure BDA0003686675400000022
represents the energy storage power that should be configured after the optimization analysis of substation j; f j represents the risk output value of substation j; f i represents the risk output value of substation i; N represents the number of substations;

进一步的,所述储能容量的计算公式具体为:Further, the calculation formula of the energy storage capacity is specifically:

Figure BDA0003686675400000023
Figure BDA0003686675400000023

其中,

Figure BDA0003686675400000024
表示变电站j优化分析后应配置的储能容量;t0表示配置的储能所允许的最大充电时间;
Figure BDA0003686675400000025
表示变电站j优化分析后应配置的储能功率;Ees,j,T表示变电站j第T天的储能容量需求,max(Ees,j,T)表示变电站j在全年中储能容量需求的最大值。in,
Figure BDA0003686675400000024
Represents the energy storage capacity that should be configured after the optimization analysis of substation j; t 0 represents the maximum charging time allowed by the configured energy storage;
Figure BDA0003686675400000025
Represents the energy storage power that should be configured after the optimization analysis of substation j; E es,j,T represents the energy storage capacity demand of substation j on the T day, and max(E es,j,T ) represents the energy storage capacity of substation j in the whole year maximum demand.

第二方面,提供了考虑多因素的储能选址定容优化系统,包括:In the second aspect, it provides an energy storage site selection and capacity optimization system that considers multiple factors, including:

电量分析模块,用于根据电力系统中年度运行的最大负荷和额定容量得到电力系统各节点的负载率,并分析电力系统各节点的负载率对供电区域供电保障性的影响,得到风险电量;The power analysis module is used to obtain the load rate of each node of the power system according to the annual maximum load and rated capacity of the power system, and analyze the influence of the load rate of each node of the power system on the security of power supply in the power supply area to obtain the risk power;

产值分析模块,用于依据各地区的经济产值数据对风险电量所对应的产值进行分析,得到风险产值;The output value analysis module is used to analyze the output value corresponding to the risk electricity according to the economic output value data of each region, and obtain the risk output value;

定容分析模块,用于将风险产值以及各区域的储能配置总量输入预构建的储能选址定容模型进行优化分析,得到电力系统各节点的储能功率和储能容量。The fixed capacity analysis module is used to input the risk output value and the total energy storage configuration of each region into the pre-built energy storage location and fixed capacity model for optimization analysis, and obtain the energy storage power and energy storage capacity of each node of the power system.

第三方面,提供了一种计算机终端,包含存储器、处理器及存储在存储器并可在处理器上运行的计算机程序,所述处理器执行所述程序时实现如第一方面中任意一项所述的考虑多因素的储能选址定容优化方法。In a third aspect, a computer terminal is provided, comprising a memory, a processor and a computer program stored in the memory and executable on the processor, when the processor executes the program, any one of the first aspect can be implemented. The optimization method of energy storage site selection and capacity considering multiple factors mentioned above.

第四方面,提供了一种计算机可读介质,其上存储有计算机程序,所述计算机程序被处理器执行可实现如第一方面中任意一项所述的考虑多因素的储能选址定容优化方法。In a fourth aspect, there is provided a computer-readable medium on which a computer program is stored, the computer program being executed by a processor to implement the multi-factor energy storage location selection as described in any one of the first aspect capacity optimization method.

与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

1、本发明提出的考虑多因素的储能选址定容优化方法,同时考虑了地区经济发展和电力系统削峰填谷改善两种因素,不仅对电力系统有改善和支撑效果,还能统筹考虑储能对当地居民、工商业用户的用电支撑,兼顾不同规划方的侧重点,有利于规划方案的落地和执行,保障用户用电可靠性以及社会效益最大化;1. The multi-factor energy storage site selection and capacity-determining optimization method proposed by the present invention also takes into account two factors: regional economic development and the improvement of peak shaving and valley filling of the power system, which not only improves and supports the power system, but also makes overall planning Considering the power support of energy storage for local residents, industrial and commercial users, and taking into account the priorities of different planners, it is conducive to the implementation and implementation of the planning scheme, ensuring the reliability of power consumption of users and maximizing social benefits;

2、本发明依据各变电站额定容量的百分比与对应变电站的配置系数的乘积来确定安全负载率,考虑了变电站在整个电力系统的布置情况,使得风险电量的确定更加准确、可靠。2. The present invention determines the safe load rate according to the product of the percentage of the rated capacity of each substation and the configuration coefficient of the corresponding substation, and considers the layout of the substation in the entire power system, making the determination of the risk power more accurate and reliable.

附图说明Description of drawings

此处所说明的附图用来提供对本发明实施例的进一步理解,构成本申请的一部分,并不构成对本发明实施例的限定。在附图中:The accompanying drawings described herein are used to provide further understanding of the embodiments of the present invention, and constitute a part of the present application, and do not constitute limitations to the embodiments of the present invention. In the attached image:

图1是本发明实施例中的流程图;Fig. 1 is the flow chart in the embodiment of the present invention;

图2是本发明实施例中的流程图;Fig. 2 is the flow chart in the embodiment of the present invention;

图3是本发明实施例中的系统框图。FIG. 3 is a system block diagram in an embodiment of the present invention.

具体实施方式Detailed ways

为使本发明的目的、技术方案和优点更加清楚明白,下面结合实施例和附图,对本发明作进一步的详细说明,本发明的示意性实施方式及其说明仅用于解释本发明,并不作为对本发明的限定。In order to make the purpose, technical solutions and advantages of the present invention clearer, the present invention will be further described in detail below with reference to the embodiments and the accompanying drawings. as a limitation of the present invention.

实施例1:考虑多因素的储能选址定容优化方法,如图1所示,包括以下步骤:Embodiment 1: The optimization method for energy storage location selection and capacity determination considering multiple factors, as shown in Figure 1, includes the following steps:

步骤一,根据电力系统中年度运行的最大负荷和额定容量得到电力系统各节点的负载率,并分析电力系统各节点的负载率对供电区域供电保障性的影响,得到风险电量;Step 1: Obtain the load rate of each node of the power system according to the annual maximum load and rated capacity of the power system, and analyze the influence of the load rate of each node of the power system on the security of power supply in the power supply area to obtain the risk electricity;

步骤二,依据各地区的经济产值数据对风险电量所对应的产值进行分析,得到风险产值;Step 2, analyze the output value corresponding to the risk electricity according to the economic output value data of each region, and obtain the risk output value;

步骤三,将风险产值以及各区域的储能配置总量输入预构建的储能选址定容模型进行优化分析,得到电力系统各节点的储能功率和储能容量。Step 3: Input the risk output value and the total energy storage configuration of each region into the pre-built energy storage location and capacity model for optimization analysis, and obtain the energy storage power and energy storage capacity of each node of the power system.

风险产值的获得过程具体为:依据经济产值数据确定过负载变电站所在区域的度电产值;以风险电量与度电产值的乘积确定相应过负载变电站的风险产值。The specific process of obtaining the risk output value is as follows: determine the kWh output value of the area where the overloaded substation is located according to the economic output value data; determine the risk output value of the corresponding overload substation by the product of the risk electricity and the kWh output value.

具体的,风险产值的计算公式为:Specifically, the calculation formula of risk output value is:

fi=CGDP,uErisk,i f i =C GDP,u E risk,i

Figure BDA0003686675400000031
Figure BDA0003686675400000031

其中,fi表示变电站i的风险产值;CGDP,u表示过负载变电站i所在区域u的度电产值;Erisk,i表示变电站i的风险电量;Mu表示区域u的经济产值数据,例如GDP总值;Eu表示区域u的全社会用电量。Among them, f i represents the risk output value of substation i; C GDP,u represents the kWh output value of the area u where the overloaded substation i is located; E risk,i represents the risky electricity of the substation i; M u represents the economic output value data of the area u, for example Gross GDP; E u represents the electricity consumption of the whole society in region u.

如图2所示,为缓解各区域内过载变电站高负载率的情况,以各区域各变电站为对象,选取各变电站额定容量的某特定百分比作为安全运行阈值,例如,80%的额定容量作为变电站安全运行阈值,那么额定容量为100MW的变电站安全运行阈值为80MW,选取最大负载率超过安全运行阈值的变电站进行储能容量配置,节点3最大负载率超出了80%,那么需要安装储能削减这部分风险电量,风险电量为各地区节点超出安全负载率所对应的供电电量。As shown in Figure 2, in order to alleviate the high load rate of overloaded substations in each area, take each substation in each area as the object, select a certain percentage of the rated capacity of each substation as the safe operation threshold, for example, 80% of the rated capacity as the substation Safe operation threshold, then the safe operation threshold of a substation with a rated capacity of 100MW is 80MW. Select a substation whose maximum load rate exceeds the safe operation threshold for energy storage capacity configuration. If the maximum load rate of node 3 exceeds 80%, then it is necessary to install energy storage to reduce this. Part of the risk power, the risk power is the power supply corresponding to the nodes in each region exceeding the safe load rate.

在本实施例中,储能功率的计算公式具体为:In this embodiment, the calculation formula of energy storage power is specifically:

Figure BDA0003686675400000041
Figure BDA0003686675400000041

其中,

Figure BDA0003686675400000042
表示变电站j优化分析后应配置的储能功率;fj表示变电站j的风险产值;N表示变电站数量;P0表示各区域内储能允许配置的总功率。in,
Figure BDA0003686675400000042
represents the energy storage power that should be configured after the optimization analysis of substation j; f j represents the risk output value of substation j; N represents the number of substations; P 0 represents the total power allowed to configure energy storage in each area.

此外,储能容量的计算公式具体为:In addition, the calculation formula of energy storage capacity is as follows:

Figure BDA0003686675400000043
Figure BDA0003686675400000043

其中,

Figure BDA0003686675400000044
表示变电站j优化分析后应配置的储能容量;t0表示配置的储能所允许的最大充电时间;Ees,j,T表示变电站j第T天的储能容量需求,max(Ees,j,T)表示变电站j在全年中储能容量需求的最大值。in,
Figure BDA0003686675400000044
Represents the energy storage capacity that should be configured after the optimization analysis of substation j; t 0 represents the maximum charging time allowed by the configured energy storage; E es, j, T represents the energy storage capacity demand of substation j on the T day, max(E es, j,T ) represents the maximum energy storage capacity demand of substation j in the whole year.

另外,储能功率和储能容量需满足以下条件:In addition, the energy storage power and energy storage capacity must meet the following conditions:

Figure BDA0003686675400000045
Figure BDA0003686675400000045

Figure BDA0003686675400000046
Figure BDA0003686675400000046

其中,Pes,i,T表示变电站i第T天的储能功率需求;Si表示变电站i的额定容量;ρi,t表示变电站i在t时刻的实时采集负载率;ρ0表示变电站的安全负载率,依据各变电站额定容量的百分比与对应变电站的配置系数的乘积确定安全负载率,本实施例中设置为85%;Ees,i,T表示变电站i第T天的储能容量需求;Δt为采样间隔,在本实施例中可设置为5分钟;K为采样总时间。Among them, P es,i,T represents the energy storage power demand of substation i on the T day; S i represents the rated capacity of substation i; ρ i,t represents the real-time acquisition load rate of substation i at time t; ρ 0 represents the The safe load rate is determined according to the product of the percentage of the rated capacity of each substation and the configuration coefficient of the corresponding substation, which is set to 85% in this embodiment; E es,i,T represents the energy storage capacity demand of the substation i on the T day ; Δt is the sampling interval, which can be set to 5 minutes in this embodiment; K is the total sampling time.

实施例2:考虑多因素的储能选址定容优化系统,该系统用于实现实施例1中所记载的储能选址定容优化方法,如图3所示,包括电量分析模块、产值分析模块和定容分析模块。Embodiment 2: An energy storage location and capacity optimization system considering multiple factors, the system is used to implement the energy storage location and capacity optimization method described in Embodiment 1, as shown in Figure 3, including a power analysis module, output value Analysis module and constant volume analysis module.

电量分析模块,用于根据电力系统中年度运行的最大负荷和额定容量得到电力系统各节点的负载率,并分析电力系统各节点的负载率对供电区域供电保障性的影响,得到风险电量;The power analysis module is used to obtain the load rate of each node of the power system according to the annual maximum load and rated capacity of the power system, and analyze the influence of the load rate of each node of the power system on the security of power supply in the power supply area to obtain the risk power;

产值分析模块,用于依据各地区的经济产值数据对风险电量所对应的产值进行分析,得到风险产值;The output value analysis module is used to analyze the output value corresponding to the risk electricity according to the economic output value data of each region, and obtain the risk output value;

定容分析模块,用于将风险产值以及各区域的储能配置总量输入预构建的储能选址定容模型进行优化分析,得到电力系统各节点的储能功率和储能容量。The fixed capacity analysis module is used to input the risk output value and the total energy storage configuration of each region into the pre-built energy storage location and fixed capacity model for optimization analysis, and obtain the energy storage power and energy storage capacity of each node of the power system.

工作原理:本发明同时考虑了地区经济发展和电力系统削峰填谷改善两种因素,不仅对电力系统有改善和支撑效果,还能统筹考虑储能对当地居民、工商业用户的用电支撑,兼顾不同规划方的侧重点,有利于规划方案的落地和执行,保障用户用电可靠性以及社会效益最大化;此外,本发明依据各变电站额定容量的百分比与对应变电站的配置系数的乘积来确定安全负载率,考虑了变电站在整个电力系统的布置情况,使得风险电量的确定更加准确、可靠。Working principle: The present invention takes into account both the regional economic development and the improvement of the peak and valley filling of the power system, which not only improves and supports the power system, but also considers the power support of the energy storage for local residents, industrial and commercial users. Taking into account the priorities of different planners, it is conducive to the implementation and execution of the planning scheme, ensuring the reliability of users' electricity consumption and maximizing social benefits; in addition, the present invention is determined according to the product of the percentage of the rated capacity of each substation and the configuration coefficient of the corresponding substation The safe load rate takes into account the layout of the substation in the entire power system, which makes the determination of the risk power more accurate and reliable.

本领域内的技术人员应明白,本申请的实施例可提供为方法、系统、或计算机程序产品。因此,本申请可采用完全硬件实施例、完全软件实施例、或结合软件和硬件方面的实施例的形式。而且,本申请可采用在一个或多个其中包含有计算机可用程序代码的计算机可用存储介质(包括但不限于磁盘存储器、CD-ROM、光学存储器等)上实施的计算机程序产品的形式。As will be appreciated by those skilled in the art, the embodiments of the present application may be provided as a method, a system, or a computer program product. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, etc.) having computer-usable program code embodied therein.

本申请是参照根据本申请实施例的方法、设备(系统)、和计算机程序产品的流程图和/或方框图来描述的。应理解可由计算机程序指令实现流程图和/或方框图中的每一流程和/或方框、以及流程图和/或方框图中的流程和/或方框的结合。可提供这些计算机程序指令到通用计算机、专用计算机、嵌入式处理机或其他可编程数据处理设备的处理器以产生一个机器,使得通过计算机或其他可编程数据处理设备的处理器执行的指令产生用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的装置。The present application is described with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the present application. It will be understood that each flow and/or block in the flowchart illustrations and/or block diagrams, and combinations of flows and/or blocks in the flowchart illustrations and/or block diagrams, can be implemented by computer program instructions. These computer program instructions may be provided to the processor of a general purpose computer, special purpose computer, embedded processor or other programmable data processing device to produce a machine such that the instructions executed by the processor of the computer or other programmable data processing device produce Means for implementing the functions specified in a flow or flow of a flowchart and/or a block or blocks of a block diagram.

这些计算机程序指令也可存储在能引导计算机或其他可编程数据处理设备以特定方式工作的计算机可读存储器中,使得存储在该计算机可读存储器中的指令产生包括指令装置的制造品,该指令装置实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能。These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing apparatus to function in a particular manner, such that the instructions stored in the computer-readable memory result in an article of manufacture comprising instruction means, the instructions The apparatus implements the functions specified in the flow or flow of the flowcharts and/or the block or blocks of the block diagrams.

这些计算机程序指令也可装载到计算机或其他可编程数据处理设备上,使得在计算机或其他可编程设备上执行一系列操作步骤以产生计算机实现的处理,从而在计算机或其他可编程设备上执行的指令提供用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的步骤。These computer program instructions can also be loaded on a computer or other programmable data processing device to cause a series of operational steps to be performed on the computer or other programmable device to produce a computer-implemented process such that The instructions provide steps for implementing the functions specified in the flow or blocks of the flowcharts and/or the block or blocks of the block diagrams.

以上的具体实施方式,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上仅为本发明的具体实施方式而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above specific embodiments further describe the purpose, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above are only specific embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Within the spirit and principle of the present invention, any modifications, equivalent replacements, improvements, etc. made should be included within the protection scope of the present invention.

Claims (10)

1. The energy storage site selection constant volume optimization method considering the multiple factors is characterized by comprising the following steps of:
obtaining the load rate of each node of the power system according to the maximum load and rated capacity of annual operation in the power system, and analyzing the influence of the load rate of each node of the power system on the power supply guarantee of a power supply area to obtain the risk electric quantity;
analyzing an output value corresponding to the risk electric quantity according to economic output value data of each region to obtain a risk output value;
and inputting the risk output value and the total energy storage configuration amount of each region into a pre-constructed energy storage location constant volume model for optimization analysis to obtain the energy storage power and the energy storage capacity of each node of the power system.
2. The method for energy storage site selection and volume optimization considering multiple factors according to claim 1, wherein the risk output value is obtained by the following specific steps:
determining the kilowatt-hour power generation value of the area where the overload transformer substation is located according to the economic power generation value data;
and determining the risk output value of the corresponding overload substation according to the product of the risk electric quantity and the kilowatt-hour power output value.
3. The method for optimizing energy storage, site selection, volume determination and the like by considering multiple factors according to claim 2, wherein the kilowatt-hour power generation value is a ratio of economic power generation value data to the power consumption of the whole society in the corresponding area.
4. The method for optimizing the location and the volume of the energy storage system based on the multi-factor consideration of claim 1, wherein the risk electric quantity is a power supply electric quantity corresponding to the exceeding of the safe load rate of each regional node.
5. The method of claim 1, wherein the safe load rate is determined by a product of a percentage of rated capacity of each substation and a configuration coefficient of the corresponding substation.
6. The method for optimizing the location and volume of the energy storage system based on the multi-factor consideration of claim 1, wherein the calculation formula of the energy storage power is as follows:
Figure FDA0003686675390000011
wherein,
Figure FDA0003686675390000012
representing the energy storage power which should be configured after the optimized analysis of the transformer substation j; f. of j Representing a risk value of substation j; f. of i Representing a risk value of substation i; n represents the number of substations; p 0 Indicating the total power of the energy storage allowable configuration in each region.
7. The method for optimizing the location and volume of the energy storage system based on the multi-factor consideration of claim 1, wherein the formula for calculating the energy storage capacity is as follows:
Figure FDA0003686675390000013
wherein,
Figure FDA0003686675390000014
representing the energy storage capacity which should be configured after the optimized analysis of the transformer substation j; t is t 0 Representing a maximum charge time allowed by the configured stored energy;
Figure FDA0003686675390000015
representing the energy storage power which should be configured after the optimized analysis of the transformer substation j; e es,j,T Represents the energy storage capacity requirement, max (E), of substation j on day T es,j,T ) Representing the maximum energy storage capacity demand of substation j throughout the year.
8. The energy storage locating and sizing optimization system considering the multiple factors is characterized by comprising the following components:
the electric quantity analysis module is used for obtaining the load rate of each node of the power system according to the maximum load and rated capacity of annual operation in the power system, analyzing the influence of the load rate of each node of the power system on the power supply guarantee of a power supply area and obtaining the risk electric quantity;
the output value analysis module is used for analyzing the output value corresponding to the risk electric quantity according to the economic output value data of each region to obtain a risk output value;
and the constant volume analysis module is used for inputting the risk output value and the total energy storage configuration amount of each region into a pre-constructed energy storage site selection constant volume model for optimization analysis to obtain the energy storage power and the energy storage capacity of each node of the power system.
9. A computer terminal comprising a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements the method of multi-factor considered energy storage siting volume optimization as claimed in any one of claims 1 to 7 when executing the program.
10. A computer-readable medium, on which a computer program is stored, the computer program being executable by a processor to implement the method of multi-factor considered energy storage siting volume optimization according to any of claims 1 to 7.
CN202210647731.XA 2022-06-09 2022-06-09 Energy storage site selection and capacity optimization method, system, terminal and medium considering multiple factors Active CN114897265B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210647731.XA CN114897265B (en) 2022-06-09 2022-06-09 Energy storage site selection and capacity optimization method, system, terminal and medium considering multiple factors

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210647731.XA CN114897265B (en) 2022-06-09 2022-06-09 Energy storage site selection and capacity optimization method, system, terminal and medium considering multiple factors

Publications (2)

Publication Number Publication Date
CN114897265A true CN114897265A (en) 2022-08-12
CN114897265B CN114897265B (en) 2025-06-20

Family

ID=82729166

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210647731.XA Active CN114897265B (en) 2022-06-09 2022-06-09 Energy storage site selection and capacity optimization method, system, terminal and medium considering multiple factors

Country Status (1)

Country Link
CN (1) CN114897265B (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021098352A1 (en) * 2019-11-22 2021-05-27 国网福建省电力有限公司 Active power distribution network planning model establishment method taking into consideration site selection and capacity determination of electric vehicle charging stations
CN113034205A (en) * 2021-04-20 2021-06-25 上海交通大学 Energy storage station and transformer substation combined planning method considering capacity-to-load ratio dynamic adjustment
CN114039351A (en) * 2022-01-10 2022-02-11 国网江西省电力有限公司电力科学研究院 A kind of energy storage capacity configuration method and device
CN114725959A (en) * 2022-04-22 2022-07-08 国网江苏省电力有限公司经济技术研究院 Energy storage planning comprehensive evaluation system model based on system economic and safe operation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021098352A1 (en) * 2019-11-22 2021-05-27 国网福建省电力有限公司 Active power distribution network planning model establishment method taking into consideration site selection and capacity determination of electric vehicle charging stations
CN113034205A (en) * 2021-04-20 2021-06-25 上海交通大学 Energy storage station and transformer substation combined planning method considering capacity-to-load ratio dynamic adjustment
CN114039351A (en) * 2022-01-10 2022-02-11 国网江西省电力有限公司电力科学研究院 A kind of energy storage capacity configuration method and device
CN114725959A (en) * 2022-04-22 2022-07-08 国网江苏省电力有限公司经济技术研究院 Energy storage planning comprehensive evaluation system model based on system economic and safe operation

Also Published As

Publication number Publication date
CN114897265B (en) 2025-06-20

Similar Documents

Publication Publication Date Title
CN103545832B (en) A kind of photovoltaic system energy accumulation capacity configuration based on generating predicated error
Zhao et al. Cyber-resilient multi-energy management for complex systems
CN104268800B (en) Wind-electricity integration peak regulation balance decision method based on scene library
Bracale et al. Analysis of the Italian distribution system evolution through reference networks
JP2015507913A (en) Adapting power generation capacity and determining energy storage size
CN102982394A (en) Power distribution network load parameter identification method and system
CN106899035B (en) Method and device for evaluating operation efficiency of power distribution network after inverter system participates in grid connection
CN107274054B (en) Evaluation method of distribution network operation efficiency based on the maximum available capacity of equipment on the same floor
CN102904248A (en) Power system dispatching method based on wind power output uncertainty set
CN110752602A (en) An evaluation method for load response and energy storage to the system's ability to absorb new energy
CN117474286B (en) Carbon reduction management method for renewable energy grid-connected power generation project
CN118607938A (en) A method and device for optimizing capacity configuration of a virtual power plant including wind, solar, and water storage
CN114897265A (en) Multi-factor-considered energy storage location and volume optimization method, system, terminal and medium
CN116029468B (en) Grid risk assessment and advanced scheduling method and system considering electric vehicle access
CN116885750A (en) Energy storage optimization configuration method and system considering thermal power flexibility transformation
CN110135619A (en) Method and system for forecasting medium and long-term electric heating demand
CN115712658A (en) Power grid stable calculation big data depth mining method
CN115186963A (en) A risk classification assessment method for distribution network with distributed new energy with high penetration rate
Ying et al. A statistical approach of wind power forecasting for grid scale
CN118300105B (en) A comprehensive monitoring method for power generation and electricity user data based on power plant management
Qxungu et al. Optimization and Management of Residential Energy Systems: Forecasting Methods, Energy Efficiency Models, and Renewable Integration
AU2020200492A1 (en) Operation plan creating apparatus, operation plan creating method, and program
CN103455953A (en) Method and device for predicting bus loads
CN104182643A (en) Peak shaving gap calculation and analysis method of electric power system with wind power
CN115238246B (en) Park energy low-carbon quantification method and device, computer equipment and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant