CN114876190A - Method and device for intercepting high-strength concrete in beam - Google Patents

Method and device for intercepting high-strength concrete in beam Download PDF

Info

Publication number
CN114876190A
CN114876190A CN202210588005.5A CN202210588005A CN114876190A CN 114876190 A CN114876190 A CN 114876190A CN 202210588005 A CN202210588005 A CN 202210588005A CN 114876190 A CN114876190 A CN 114876190A
Authority
CN
China
Prior art keywords
concrete
deformed
intercepting
steel bar
strength concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210588005.5A
Other languages
Chinese (zh)
Inventor
费勤波
李建成
叶和永
周毅
孟庆武
王伟
李磊
梅红
许小龙
凌友和
杜磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Second Construction Engineering Co ltd
Original Assignee
Anhui Second Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Second Construction Engineering Co ltd filed Critical Anhui Second Construction Engineering Co ltd
Priority to CN202210588005.5A priority Critical patent/CN114876190A/en
Publication of CN114876190A publication Critical patent/CN114876190A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/04Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for lintels, beams, or transoms to be encased separately; Special tying or clamping means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/001Corner fastening or connecting means for forming or stiffening elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The invention discloses a method and a device for intercepting high-strength concrete in a beam, wherein the method comprises the following steps: determining an interception position: the part which is half of the height of the column boundary beam and is not less than 500mm is used as the joint surface of high-strength and low-strength grade concrete; installing an intercepting device: selecting one beam stirrup as a positioning stirrup; after the stirrups are installed, a plurality of deformed steels are arranged between two beam main reinforcements which are adjacent in the transverse direction, the deformed steels are arranged at the positions of the reinforcement protection layers on the two sides of the beam respectively, the deformed steels are installed in an inclined mode, the deformed steels and the stirrups are installed at an angle of 45 degrees, and the upper portions of the deformed steels are fixed with the stirrups; reinforcing steel bars which are smaller than the beam main bars by one grade are arranged between two vertically adjacent beam main bars; installing a screw at the lower opening of the template: a screw is arranged at the bottom of the beam and traverses the beam template, and the lower part of the deformed steel bar is abutted against the screw; and (6) pouring concrete. The invention can avoid the disordered flowing of the high-strength concrete and improve the interception quality of the high-strength concrete.

Description

一种梁内对高强度混凝土拦截方法及其装置Method and device for intercepting high-strength concrete in beam

技术领域technical field

本发明涉及一种建筑施工领域,具体涉及一种梁内对高强度混凝土拦截方法及其装置。The invention relates to the field of building construction, in particular to a method and a device for intercepting high-strength concrete in a beam.

背景技术Background technique

随着建筑行业的快速发展,为保证“强柱弱梁强节点”的设计要求,在结构梁柱节点区设计不同强度等级混凝土,从而确保结构抗震的要求。为提高对梁内高强度混凝土的拦截施工质量,保证梁柱节点区的结构施工质量和混凝土的美观,但是现有的施工方法会使节点区混凝土发生流淌和开裂现象,影响混凝土结构质量和观感效果。With the rapid development of the construction industry, in order to ensure the design requirements of "strong columns, weak beams and strong joints", concrete of different strength grades are designed in the beam-column joint area of the structure to ensure the seismic resistance of the structure. In order to improve the construction quality of intercepting high-strength concrete in the beam and ensure the structural construction quality of the beam-column joint area and the aesthetics of the concrete, the existing construction method will cause the concrete to flow and crack in the joint area, affecting the quality and appearance of the concrete structure. Effect.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种梁内对高强度混凝土拦截方法及其装置,其可以避免高强度混凝土无序流淌,提高对高强度混凝土的拦截质量。The purpose of the present invention is to provide a method and device for intercepting high-strength concrete in a beam, which can avoid disorderly flow of high-strength concrete and improve the interception quality of high-strength concrete.

为实现上述目的,本发明提供如下技术方案:To achieve the above object, the present invention provides the following technical solutions:

一种梁内对高强度混凝土拦截方法,包括以下步骤:A method for intercepting high-strength concrete in a beam, comprising the following steps:

(1)确定拦截位置:在距柱边梁高的一半距离且不小于500mm处做为高低强度等级混凝土的交接面,即拦截面;(1) Determine the interception position: the half distance from the column side beam height and not less than 500mm is used as the interface of high and low strength grade concrete, that is, the interception surface;

(2)拦截装置安装:选择位于距柱边梁高的一半距离且不小于500mm处的其中一道梁箍筋作为定位箍筋;在箍筋安装结束后,横向上相邻的两个梁主筋之间设置多根螺纹钢,在梁两侧的钢筋保护层位置分别设置一根螺纹钢,螺纹钢倾斜进行安装,螺纹钢与箍筋呈45°安装,螺纹钢上部与箍筋固定;竖向上相邻两个梁主筋之间设有比梁主筋小一个等级的钢筋;(2) Installation of intercepting device: select one of the beam stirrups located at half the distance from the column side beam height and not less than 500mm as the positioning stirrup; after the stirrup installation is completed, the horizontally adjacent two beam main bars A plurality of rebars are arranged between the two sides of the beam, and one rebar is set at the position of the steel bar protection layer on both sides of the beam. The rebar is installed at an inclination, the rebar and the stirrup are installed at 45°, and the upper part of the rebar is fixed with the stirrup; Between the main reinforcement of two adjacent beams, there is a steel bar one grade smaller than the main reinforcement of the beam;

(3)模板下口螺杆安装:在梁底设置一道螺杆,螺杆横穿梁模板,螺纹钢下部与螺杆相抵;(3) Installation of screw at the bottom of the template: a screw is set at the bottom of the beam, the screw traverses the beam template, and the lower part of the rebar is in contact with the screw;

(4)混凝土浇筑:先用混凝土泵输送柱等级的混凝土就位并分层振捣,在楼面梁板处预留45°斜面,在混凝土将初凝时将拦截装置和螺杆拆除,随之泵送浇筑梁板的混凝土。(4) Concrete pouring: first, use a concrete pump to transport the column grade concrete in place and vibrate it in layers, reserve a 45° inclined plane at the floor beam slab, remove the intercepting device and the screw when the concrete is initially set, and then Pump concrete for pouring beam slabs.

优选地,所述步骤(2)中,箍筋设置在距柱边30cm处。Preferably, in the step (2), the stirrups are arranged at a distance of 30 cm from the edge of the column.

优选地,所述步骤(2)中,箍筋用扎丝进行绑扎,绑扎间距为10cm一道。Preferably, in the step (2), the stirrups are bound with binding wires, and the binding spacing is 10 cm.

优选地,所述步骤(2)中,螺纹钢为φ16mm的三级螺纹钢,螺纹钢上部与箍筋通过扎丝绑扎牢固。Preferably, in the step (2), the threaded steel is a third-grade threaded steel with a diameter of 16 mm, and the upper part of the threaded steel and the stirrup are firmly bound by binding wires.

优选地,所述步骤(2)中,螺纹钢上口长度要高出梁顶面50mm。Preferably, in the step (2), the length of the upper opening of the rebar should be 50mm higher than the top surface of the beam.

优选地,所述步骤(2)中,钢筋与其两侧的螺纹钢绑扎。Preferably, in the step (2), the steel bars are bound with the threaded steel bars on both sides thereof.

优选地,所述步骤(3)中,螺杆直径为18mm。Preferably, in the step (3), the diameter of the screw is 18 mm.

优选地,所述步骤(3)中,螺杆外套设有塑料套管。Preferably, in the step (3), the outer casing of the screw is provided with a plastic sleeve.

优选地,所述步骤(4)中,拦截装置和螺杆拆除方法如下,将螺纹钢上口和箍筋绑扎的扎丝松开,用锤子敲打高出混凝土上口50mm处的螺纹钢,让螺纹钢松动,方便取出螺纹钢,然后再将螺杆拆除。Preferably, in the step (4), the method of removing the intercepting device and the screw is as follows: loosen the tie wire that binds the upper opening of the rebar and the stirrup, and hit the rebar 50mm higher than the upper opening of the concrete with a hammer to let the thread The steel is loose, and it is convenient to take out the rebar, and then remove the screw.

一种梁内对高强度混凝土拦截装置,包括梁主筋和梁模板,还包括:A high-strength concrete interception device in a beam, comprising a beam main reinforcement and a beam formwork, and further comprising:

定位箍筋,选择位于距柱边梁高的一半距离且不小于500mm处的其中一道梁箍筋作为定位箍筋;For positioning stirrups, select one of the beam stirrups located at half the distance from the column side beam height and not less than 500mm as the positioning stirrup;

螺纹钢,横向上相邻的两个梁主筋之间设置多根螺纹钢,在梁两侧的钢筋保护层位置分别设置一根螺纹钢;螺纹钢与箍筋呈45°倾斜安装,螺纹钢上部与箍筋固定;Rebar, multiple rebars are arranged between the main bars of two adjacent beams in the transverse direction, and one rebar is set at the position of the steel bar protection layer on both sides of the beam; the rebar and the stirrup are installed at an inclination of 45°, and the upper part of the rebar is installed. fixed with stirrups;

钢筋,所述钢筋分别设置在竖向上相邻两个梁主筋之间;Reinforcing bars, the reinforcing bars are respectively arranged between the main bars of two adjacent beams in the vertical direction;

螺杆,所述螺杆设置在梁底,螺杆横穿梁模板,螺纹钢下部与螺杆相抵。The screw rod is arranged at the bottom of the beam, the screw rod traverses the beam template, and the lower part of the threaded steel is in contact with the screw rod.

与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:

1)本发明合理布置拦截装置,在模板上设置阻拦设施,避免高强度混凝土无序流淌,提高对高强度混凝土的拦截质量。1) The present invention reasonably arranges the intercepting device, and sets up blocking facilities on the formwork to avoid disorderly flow of high-strength concrete and improve the interception quality of high-strength concrete.

2)本发明保证了节点区部位的混凝土强度,避免了节点区混凝土的流淌和开裂,提高了混凝土结构的观感效果。2) The present invention ensures the strength of the concrete in the node area, avoids the flow and cracking of the concrete in the node area, and improves the visual effect of the concrete structure.

3)拦截装置制作简单,安拆方便,提高了工作效率,具有较强的适用性,可在复杂的梁柱节点区广泛应用。3) The intercepting device is simple to manufacture, easy to install and disassemble, improves work efficiency, has strong applicability, and can be widely used in complex beam-column joint areas.

4)本发明适用于框架结构和框架剪力墙结构中梁柱节点区由不同强度等级混凝土施工的工程。4) The present invention is suitable for the project in which the beam-column node area in the frame structure and the frame shear wall structure is constructed by concrete of different strength grades.

附图说明Description of drawings

图1是本发明实施例1中拦截装置位置定位图;Fig. 1 is the position location diagram of intercepting device in Embodiment 1 of the present invention;

图2是本发明实施例1和2中拦截装置立面图;2 is an elevation view of the intercepting device in Embodiments 1 and 2 of the present invention;

图3是本发明实施例1和2中拦截装置侧面图;3 is a side view of the intercepting device in Embodiments 1 and 2 of the present invention;

图4是本发明实施例1中阻拦螺杆安装图;Fig. 4 is the installation diagram of the blocking screw in Embodiment 1 of the present invention;

图5是本发明实施例1中梁内对高强度混凝土拦截图;Fig. 5 is the intercepting diagram of high-strength concrete in the beam in the embodiment 1 of the present invention;

图中,1、柱高强度混凝土,2、梁板低强度混凝土,3、螺纹钢,4、螺杆,5、框架柱,6、梁主筋,7、定位箍筋,8、钢筋。In the figure, 1. High-strength concrete for columns, 2. Low-strength concrete for beams and slabs, 3. Rebars, 4. Screws, 5. Frame columns, 6. Beam main bars, 7. Positioning stirrups, 8. Steel bars.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

实施例1Example 1

一种梁内对高强度混凝土拦截方法,施工工艺流程如下:A method for intercepting high-strength concrete in a beam, and the construction process is as follows:

施工准备→确定拦截装置位置→拦截装置制作→拦截装置安装→梁模板下口阻拦螺杆安装→高强度混凝土浇筑→拦截装置拆除→梁板混凝土浇筑。Construction preparation → determine the position of the intercepting device → production of the intercepting device → installation of the intercepting device → installation of the blocking screw at the lower mouth of the beam formwork → high-strength concrete pouring → removal of the intercepting device → concrete pouring of the beam and slab.

1、施工准备1. Construction preparation

(1)为保证工程质量,施工人员应事先熟悉施工图纸,了解施工内容,熟悉国家规范、标准和图集的梁柱节点区不同强度混凝土的相关要求。(1) In order to ensure the quality of the project, the construction personnel should be familiar with the construction drawings in advance, understand the construction content, and be familiar with the relevant requirements for concrete of different strengths in the beam-column joint area of the national codes, standards and atlases.

(2)配置必要的施工设备及做好施工机具、安装材料的准备,做好施工结束后的产品保护工作。(2) Configure necessary construction equipment, prepare construction equipment and installation materials, and do a good job in product protection after construction.

(3)施工前由技术负责人对现场施工人员进行技术交底,从而更好的控制质量,达到规范要求。(3) Before construction, the technical person in charge shall make technical disclosure to the on-site construction personnel, so as to better control the quality and meet the specification requirements.

2、确定拦截装置位置2. Determine the location of the interceptor

(1)如图1所示,为了增强柱节点核心区的抗剪能力,在距柱边梁高的一半距离(h/2)且≥500mm处做为高低强度等级混凝土的交接面(拦截装置安装处)。(1) As shown in Figure 1, in order to enhance the shear resistance of the core area of the column node, a distance (h/2) from the column side beam height and ≥ 500mm is used as the interface of high and low strength grade concrete (intercepting device). installation).

(2)现场人员根据图纸计算出高低强度等级混凝土的交接面位置,然后在梁钢筋上用红漆做好标记(拦截装置的上下都要做好标记),梁钢筋放入模板后再次复核相关数据,以免因钢筋下放过程中出现较大误差。(2) The on-site personnel calculate the position of the interface of high and low strength grade concrete according to the drawings, and then mark the beam steel bar with red paint (marks should be made on the top and bottom of the intercepting device), and the beam steel bar is placed in the formwork and re-check the relevant data, so as to avoid large errors in the process of lowering the steel bars.

3、拦截装置制作和安装3. Intercepting device production and installation

(1)如图4所示,选择距柱(框架柱5)边30cm的梁箍筋作为定位箍筋7。(1) As shown in Figure 4, select the beam stirrup 30cm away from the side of the column (frame column 5) as the positioning stirrup 7.

(2)定位箍筋7用扎丝进行绑扎,绑扎间距为10cm一道。(2) The positioning stirrups 7 are bound with binding wires, and the binding spacing is 10cm.

(3)如图2-3所示,在定位箍筋7安装结束后,进行拦截装置的安装,拦截装置的钢筋骨架为φ16的三级螺纹钢3。(3) As shown in Figure 2-3, after the installation of the positioning stirrup 7 is completed, the installation of the intercepting device is carried out.

(4)螺纹钢3设置在横向上相邻的两个梁主筋6之间,安装时将φ16mm的三级螺纹钢3竖向45°安装在定位箍筋7上用扎丝绑扎牢固。(4) The threaded steel 3 is arranged between the two adjacent beam main bars 6 in the lateral direction. During installation, the third-grade threaded steel 3 with a diameter of 16mm is installed vertically at 45° on the positioning stirrup 7 and tied firmly with binding wires.

(5)拦截装置的三级螺纹钢3上口长度要高出梁顶面50mm,保证混凝土将初凝前拦截装置可以较为方便的取出。(5) The length of the upper mouth of the tertiary rebar 3 of the intercepting device should be 50mm higher than the top surface of the beam to ensure that the intercepting device can be easily taken out before the concrete is initially set.

(6)在梁两侧的钢筋保护层位置必须设置两根φ16mm的三级螺纹钢3,避免混凝土浇筑时侧边出现漏浆现象。竖向相邻两个梁主筋6之间用比梁主筋小一个等级的钢筋8和螺纹钢3绑扎。(6) Two 3-grade rebars 3 of φ16mm must be installed at the position of the steel bar protection layer on both sides of the beam to avoid the phenomenon of slurry leakage on the side during concrete pouring. Vertically adjacent two beam main bars 6 are bound with steel bars 8 and rebars 3 that are one grade smaller than the beam main bars.

4、梁模板下口螺杆安装4. Installation of the screw at the bottom of the beam formwork

(1)如图4所示,为保证拦截装置的稳定性,避免混凝土浇筑时出现松动,需要在梁底设置一道φ18mm的螺杆4,将骨架钢筋下部固定。(1) As shown in Figure 4, in order to ensure the stability of the intercepting device and avoid loosening during concrete pouring, it is necessary to set a screw 4 of φ18mm at the bottom of the beam to fix the lower part of the skeleton steel bar.

(2)螺杆4安装位置为钢筋骨架下口位置,螺杆位于梁底筋下方,拦截装置的下口抵住下口螺杆4,保证混凝土浇筑时钢筋骨架的稳定性。(2) The installation position of the screw 4 is the lower port of the steel skeleton, the screw is located below the bottom rib of the beam, and the lower port of the intercepting device is against the lower screw 4 to ensure the stability of the steel skeleton during concrete pouring.

5、高强度混凝土浇筑、拦截装置拆除和梁板混凝土浇筑5. High-strength concrete pouring, interception device removal and beam-slab concrete pouring

(1)梁柱节点区的混凝土浇捣方法为:先用混凝土泵输送柱等级的混凝土(即柱高强度混凝土1)就位并分层振捣,在楼面梁板处留出45°斜面,在混凝土将初凝时将拦截装置(包括螺纹钢3和钢筋8)和螺杆4拆除,并对螺杆4洞处的梁模板进行修补,随之泵送浇筑梁板的混凝土(即梁板低强度混凝土2)。梁内对高强度混凝土拦截如图5所示。(1) The concrete pouring and tamping method in the beam-column joint area is as follows: first, use a concrete pump to transport the column-grade concrete (ie, column high-strength concrete 1) in place and vibrate in layers, leaving a 45° inclined plane at the floor beam slab. , when the concrete is initially set, the intercepting device (including the rebar 3 and the steel bar 8) and the screw rod 4 are removed, and the beam formwork at the hole of the screw rod 4 is repaired, and then the concrete for pouring the beam plate (that is, the beam plate is low strength concrete 2). The interception of high-strength concrete in the beam is shown in Figure 5.

(2)在浇捣楼层柱、梁板混凝土时,应重点控制高强度等级混凝土的流淌和高低强度邻接面冷缝问题。(2) When pouring and ramming floor column, beam and slab concrete, the flow of high-strength grade concrete and the problem of cold joints of high and low strength adjoining surfaces should be controlled.

(3)梁柱混凝土标号相差较大时应进行配合比设计,以便满足混凝土强度等级及可泵性的要求。(3) When the concrete labels of beams and columns differ greatly, the mix ratio design should be carried out to meet the requirements of concrete strength grade and pumpability.

(4)混凝土浇筑完毕后,应在12h内进行覆盖和浇水养护。(4) After the concrete is poured, it should be covered and watered within 12 hours.

6、梁内高强度混凝土浇筑后拦截装置拆除6. After the high-strength concrete in the beam is poured, the intercepting device is removed

(1)在混凝土达到初凝前将拦截装置拆除,将螺纹钢3上口和定位箍筋7绑扎的扎丝松开,用锤子敲打高出混凝土上口50mm处的螺纹钢3,让螺纹钢3松动,方便取出钢筋骨架。(1) Before the concrete reaches the initial setting, remove the intercepting device, loosen the binding wire of the upper opening of the rebar 3 and the positioning stirrup 7, and hit the rebar 3 50mm above the upper opening of the concrete with a hammer to let the rebar 3 3 Loose, easy to take out the steel frame.

(2)拦截装置拆除前要先拆除螺杆4,为了方便螺杆4的拆除,螺杆4外可加设塑料套管,塑料套管不需要进行拆除。拆除后的相关材料可清理干净后备下一次继续使用。(2) Before removing the intercepting device, the screw 4 should be removed first. In order to facilitate the removal of the screw 4, a plastic sleeve can be added outside the screw 4, and the plastic sleeve does not need to be removed. The related materials after dismantling can be cleaned up for the next use.

7、质量控制标准7. Quality control standards

(1)施工前对原材料进行检查,需有合格证及见证取样的复试报告,对施工工序、工艺流程、检测过程进行检查。(1) Check the raw materials before construction, and have a certificate of conformity and a re-test report witnessing sampling, and check the construction process, technological process, and testing process.

(2)拦截装置制作和安装允许偏差应符合表1的规定。(2) The allowable deviation of the production and installation of the intercepting device shall comply with the provisions of Table 1.

表1拦截装置制作和安装允许偏差(mm)Table 1 Interceptor fabrication and installation allowable deviation (mm)

Figure BDA0003663922240000051
Figure BDA0003663922240000051

Figure BDA0003663922240000061
Figure BDA0003663922240000061

实施例2Example 2

如图2和3所示,一种梁内对高强度混凝土拦截装置,包括梁主筋6和梁模板,还包括:As shown in Figures 2 and 3, an in-beam interception device for high-strength concrete includes beam main bars 6 and beam formwork, and also includes:

定位箍筋7,选择位于距柱边梁高的一半距离且不小于500mm处的其中一道梁箍筋作为定位箍筋7;Positioning stirrup 7, select one of the beam stirrups located at half the distance from the column side beam height and not less than 500mm as the positioning stirrup 7;

螺纹钢3,横向上相邻的两个梁主筋6之间设置多根螺纹钢3,在梁两侧的钢筋保护层位置分别设置一根螺纹钢3;螺纹钢3与箍筋7呈45°倾斜安装,螺纹钢3上部与定位箍筋7固定;Threaded steel 3, a plurality of threaded steels 3 are arranged between two adjacent beam main bars 6 in the transverse direction, and a threaded steel 3 is respectively set at the position of the reinforcing bar protection layer on both sides of the beam; the threaded steel 3 and the stirrup 7 are at 45° Inclined installation, the upper part of the threaded steel 3 is fixed with the positioning stirrup 7;

钢筋8,钢筋8分别设置在竖向上相邻两个梁主筋6之间;Reinforcing bars 8, the reinforcing bars 8 are respectively arranged between the two adjacent beam main bars 6 in the vertical direction;

螺杆4,螺杆4设置在梁底,螺杆4横穿梁模板,螺纹钢3下部与螺杆4相抵。The screw 4, the screw 4 is arranged at the bottom of the beam, the screw 4 traverses the beam template, and the lower part of the screw steel 3 is in contact with the screw 4.

原理:在梁柱节点区不同强度等级混凝土施工过程中,按混凝土强度先高后低、先柱后梁板的原则进行浇筑,因此,在梁柱核心区梁内设置拦截装置进行封堵,待柱及梁柱核心区混凝土浇筑结束后,将拦截装置拆除,再浇筑梁板混凝土,从而确保了梁柱节点区混凝土强度,避免了梁柱节点区因高强度混凝土流淌而发生剪切破坏出现裂缝。Principle: During the construction of concrete with different strength grades in the beam-column joint area, the concrete is poured according to the principle of high concrete strength first, then low, and column first, then beam slab. After the concrete pouring in the beam-column core area is completed, the intercepting device is removed, and the beam-slab concrete is poured, thereby ensuring the concrete strength of the beam-column joint area and avoiding shear damage and cracks in the beam-column joint area due to the flow of high-strength concrete.

以上内容仅仅是对本发明结构所作的举例和说明,所属本技术领域的技术人员对所描述的具体实施例做各种各样的修改或补充或采用类似的方式替代,只要不偏离本发明的结构或者超越本权利要求书所定义的范围,均应属于本发明的保护范围。The above content is only an example and description of the structure of the present invention. Those skilled in the art can make various modifications or supplements to the specific embodiments described or replace them in a similar manner, as long as they do not deviate from the structure of the present invention. Or beyond the scope defined by the claims, all belong to the protection scope of the present invention.

Claims (10)

1. A method for intercepting high-strength concrete in a beam is characterized by comprising the following steps:
(1) determining an interception position: the part which is half of the height of the pillar boundary beam and is not less than 500mm is used as the interface of high-strength and low-strength concrete, namely a blocking section;
(2) installing an intercepting device: selecting one beam stirrup which is positioned at a half distance from the height of the column boundary beam and is not less than 500mm as a positioning stirrup; after the stirrups are installed, a plurality of deformed steels are arranged between two beam main reinforcements which are adjacent in the transverse direction, the deformed steels are arranged at the positions of the reinforcement protection layers on the two sides of the beam respectively, the deformed steels are installed in an inclined mode, the deformed steels and the stirrups are installed at an angle of 45 degrees, and the upper portions of the deformed steels are fixed with the stirrups; reinforcing steel bars which are smaller than the beam main bars by one grade are arranged between two vertically adjacent beam main bars;
(3) installing a screw at the lower opening of the template: a screw is arranged at the bottom of the beam and traverses the beam template, and the lower part of the deformed steel bar is abutted against the screw;
(4) pouring concrete: the concrete pump is used for conveying the concrete of the column grade to be in place and vibrating in layers, a 45-degree inclined plane is reserved at the beam slab of the floor, the intercepting device and the screw rod are removed when the concrete is initially set, and then the concrete for pouring the beam slab is pumped.
2. The method for intercepting high-strength concrete in a beam according to claim 1, wherein the method comprises the following steps: in the step (2), the stirrups are arranged at the positions 30cm away from the column sides.
3. The method for intercepting high-strength concrete in a beam according to claim 1, wherein the method comprises the following steps: in the step (2), the stirrups are bound by binding wires, and the binding distance is 10 cm.
4. The method for intercepting high-strength concrete in a beam according to claim 1, wherein the method comprises the following steps: in the step (2), the deformed steel bar is a three-level deformed steel bar with the diameter of 16mm, and the upper part of the deformed steel bar is firmly bound with the stirrup through the binding wire.
5. The method for intercepting high-strength concrete in a beam according to claim 1, wherein the method comprises the following steps: in the step (2), the length of the upper opening of the deformed steel bar is 50mm higher than the top surface of the beam.
6. The method for intercepting high-strength concrete in a beam according to claim 1, wherein the method comprises the following steps: and (3) binding the steel bars with the deformed steel bars on the two sides in the step (2).
7. The method for intercepting high-strength concrete in a beam according to claim 1, wherein the method comprises the following steps: in the step (3), the diameter of the screw is 18 mm.
8. The method for intercepting high-strength concrete in a beam according to claim 1, wherein the method comprises the following steps: and in the step (3), a plastic sleeve is sleeved outside the screw rod.
9. The method for intercepting high-strength concrete in a beam according to claim 1, wherein: in the step (4), the intercepting device and the screw rod dismounting method are that the binding wires for binding the upper opening of the deformed steel bar and the stirrups are loosened, the deformed steel bar 50mm higher than the upper opening of the concrete is knocked by a hammer to loosen the deformed steel bar, the deformed steel bar is conveniently taken out, and then the screw rod is dismounted.
10. The utility model provides an in roof beam to high strength concrete intercepting device, includes girder main muscle and beam formwork, its characterized in that still includes:
positioning stirrups, wherein one beam stirrup positioned at a position which is half of the height of the column boundary beam and not less than 500mm is selected as the positioning stirrup;
the beam comprises deformed steel bars, a plurality of deformed steel bars and a plurality of reinforcing steel bars, wherein the plurality of deformed steel bars are arranged between two beam main bars which are adjacent in the transverse direction; the deformed steel bar and the stirrup are obliquely arranged at an angle of 45 degrees, and the upper part of the deformed steel bar is fixed with the stirrup;
the reinforcing steel bars are respectively arranged between two vertically adjacent beam main reinforcements;
and the screw rod is arranged at the bottom of the beam, the screw rod transversely penetrates through the beam template, and the lower part of the deformed steel bar abuts against the screw rod.
CN202210588005.5A 2022-05-26 2022-05-26 Method and device for intercepting high-strength concrete in beam Pending CN114876190A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210588005.5A CN114876190A (en) 2022-05-26 2022-05-26 Method and device for intercepting high-strength concrete in beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210588005.5A CN114876190A (en) 2022-05-26 2022-05-26 Method and device for intercepting high-strength concrete in beam

Publications (1)

Publication Number Publication Date
CN114876190A true CN114876190A (en) 2022-08-09

Family

ID=82678525

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210588005.5A Pending CN114876190A (en) 2022-05-26 2022-05-26 Method and device for intercepting high-strength concrete in beam

Country Status (1)

Country Link
CN (1) CN114876190A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107724680A (en) * 2016-08-11 2018-02-23 五冶集团上海有限公司 A kind of high-storey building frame structure beam-column node construction method
US20200040564A1 (en) * 2016-10-17 2020-02-06 South China University Of Technology Reinforced compound concrete beam-column joint containing demolished concrete lumps and a construction method
JP2020063634A (en) * 2018-10-19 2020-04-23 株式会社安藤・間 Junction structure and junction method for precast concrete beam member
CN214575767U (en) * 2020-12-04 2021-11-02 中建五局土木工程有限公司 Isolating device for high-low grade concrete
CN214615477U (en) * 2021-02-01 2021-11-05 中建八局第三建设有限公司 Different intensity concrete construction joint interception tools of beam column node
CN214658892U (en) * 2021-04-22 2021-11-09 中建八局第一建设有限公司 High-low grade concrete intercepting device
CN217420496U (en) * 2022-05-26 2022-09-13 安徽省第二建筑工程有限公司 Device for intercepting high-strength concrete in beam

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107724680A (en) * 2016-08-11 2018-02-23 五冶集团上海有限公司 A kind of high-storey building frame structure beam-column node construction method
US20200040564A1 (en) * 2016-10-17 2020-02-06 South China University Of Technology Reinforced compound concrete beam-column joint containing demolished concrete lumps and a construction method
JP2020063634A (en) * 2018-10-19 2020-04-23 株式会社安藤・間 Junction structure and junction method for precast concrete beam member
CN214575767U (en) * 2020-12-04 2021-11-02 中建五局土木工程有限公司 Isolating device for high-low grade concrete
CN214615477U (en) * 2021-02-01 2021-11-05 中建八局第三建设有限公司 Different intensity concrete construction joint interception tools of beam column node
CN214658892U (en) * 2021-04-22 2021-11-09 中建八局第一建设有限公司 High-low grade concrete intercepting device
CN217420496U (en) * 2022-05-26 2022-09-13 安徽省第二建筑工程有限公司 Device for intercepting high-strength concrete in beam

Similar Documents

Publication Publication Date Title
CN104695557B (en) Steel structure building construction method for one-step pre-burying of foundation bolts
CN105604208B (en) A kind of precast shear wall using cast-in-place connection type
CN108130837A (en) A kind of prefabricated road plate and its construction method
CN112049143B (en) Large-sized concrete bearing platform construction method for large-sized low-temperature storage tank
CN111894204A (en) Steel pipe concrete composite column construction method
CN104912320A (en) Synchronous construction method of shear walls on the two sides of settlement joint
CN107083804B (en) A kind of wall structure column joint bar construction method
CN113202222A (en) Construction method for assembled type superposed beam slab
CN109235891A (en) A kind of Large Span Prestressed Beam concrete pitched roof jump storehouse method construction method
CN206337676U (en) Rigidly connected assembled steel frame wall filled with masonry system can be resetted
CN113829493A (en) Processing method of prefabricated greening retaining wall
CN116910854A (en) Large-span arch concrete structure construction method based on digital construction
CN207363251U (en) A kind of track-type facilities for being used to control the pitched roof gradient and thickness
CN110593477B (en) Construction method of cast-in-situ reinforced concrete special-shaped inclined plate
CN114482344A (en) Cast-in-place concrete sandwich outer wall construction method capable of improving construction efficiency
CN110259114A (en) The construction method of the mould bases of beam slab rod structure
CN105544832B (en) Shell roof and construction method thereof
CN114876190A (en) Method and device for intercepting high-strength concrete in beam
CN104675138B (en) A kind of slab balcony reinforcement means for sound insulation and noise reducing transformation
CN209194694U (en) A kind of reinforcing concrete drain pipe building
CN110184864A (en) A method of reducing double-block ballastless track bed board cracking rate
CN105804274A (en) Novel light connecting structure of block filling wall and frame structure and construction technique
CN115613769A (en) BIM technology-based construction method and structure for large-gradient multi-V-surface special-shaped inclined roof
CN205691309U (en) A kind of big than chi assembled integral Shear wall tube structure structure
CN112482322A (en) Split gate pier construction complete device and construction process

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20220809

RJ01 Rejection of invention patent application after publication