CN114718074A - Excavation method for foundation pit in soft soil stratum - Google Patents

Excavation method for foundation pit in soft soil stratum Download PDF

Info

Publication number
CN114718074A
CN114718074A CN202210152172.5A CN202210152172A CN114718074A CN 114718074 A CN114718074 A CN 114718074A CN 202210152172 A CN202210152172 A CN 202210152172A CN 114718074 A CN114718074 A CN 114718074A
Authority
CN
China
Prior art keywords
foundation pit
pile
excavation
support
along
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210152172.5A
Other languages
Chinese (zh)
Inventor
回恒酉
姜聪宇
吴松华
包江
杨中锋
方路
刘宇飞
吴春勇
胡玉龙
贾洪斌
李嘉振
陈志刚
王强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Shanghai Dredging Co Ltd.
Original Assignee
CCCC Shanghai Dredging Co Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Shanghai Dredging Co Ltd. filed Critical CCCC Shanghai Dredging Co Ltd.
Priority to CN202210152172.5A priority Critical patent/CN114718074A/en
Publication of CN114718074A publication Critical patent/CN114718074A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/10Travelling bridges, i.e. roller bridges; Sliding bridges; Rotary cylinder bridges, i.e. rotating about longitudinal axis to invert and raise the road
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D18/00Bridges specially adapted for particular applications or functions not provided for elsewhere, e.g. aqueducts, bridges for supporting pipe-lines
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/005Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F7/00Equipment for conveying or separating excavated material

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a method for excavating a foundation pit in a soft soil stratum, which is characterized by comprising the following steps of: the method comprises the following steps: 1) constructing a foundation pit supporting pile: the pile-up position of the support pile is measured according to the size of the foundation pit, the vertical columnar pile is firstly arranged according to the measurement position, the columnar pile exceeds the ground by a certain height, vertical sheet piles are arranged between the columnar piles, the sinking height of the sheet piles is consistent with the sinking elevation of the columnar pile, and the purlin is arranged on the outer side of the support pile. According to the invention, the trestle along the width direction of the foundation pit is erected on the support pile, the trestle can move relative to the foundation pit along the length direction of the foundation pit, the excavator is hoisted to the trestle by adopting a crane to perform foundation pit excavation, the advancing and retreating of the excavator are realized by moving the trestle, the excavator is prevented from being sunk due to the fact that the excavator is not directly contacted with a soft soil layer, the traditional excavation-sunning-excavation process is not needed, the construction period is shortened, the utilization rate of equipment is improved, the operation space of the excavator on the trestle is increased, and the excavation of the foundation pit is more facilitated.

Description

Excavation method of soft soil stratum foundation pit
Technical Field
The invention belongs to the technical field of engineering, and particularly relates to a method for excavating a foundation pit in a soft soil stratum.
Background
The soft clay and sludge stratum are collectively called as soft soil stratum, in coastal areas and areas near rivers, the soft clay and sludge stratum are widely distributed, and the stratum characteristics are mainly shown in that the stratum soil is in a flow plastic shape, has high water content, large pore ratio, high sensitivity, high compressibility and low strength, has thixotropic and rheological properties, and has extremely poor self-stability capability.
Excavation foundation ditch on soft clay, silt stratum, technical requirement is higher, usually does earlier make and struts, then excavates, and to the great soil layer of moisture content, for avoiding digging machine and transport vechicle and soil layer direct contact back deep sinking, excavation generally adopts and digs the limit and shines, wait to dig again after moisture loss forms the dry soil and transport. The sun drying process in the digging-sun drying-digging construction process needs longer downtime waiting time and larger uncertainty, which not only can not meet the construction period requirement of the project, but also has lower efficiency of construction machinery equipment. For a soft clay stratum, under the condition of well supporting, due to the rheological property of soft soil, the displacement deformation of the foundation pit support structure is larger along with the longer exposure time of the foundation pit, and meanwhile, the lateral pressure influence generated by the excavator and the transport vehicle is larger and larger along with the increase of the depth of the foundation pit in the excavation process, so that the foundation pit support structure is damaged and deformed, and the instability of the foundation pit is easily caused. For a silt stratum, the larger the load is, the larger the sedimentation is, the excavator and the transport vehicle are difficult to excavate to a proper position, and meanwhile, the problems of small width of a foundation pit, deep excavation depth of the foundation pit, various horizontal supports and the like restrict the operation space of the excavator and are difficult to excavate. The excavation of the foundation pit in the soft clay and sludge stratum is easily disturbed, the strength can be rapidly reduced, large resilience can be generated during unloading, and the construction of the enclosure structure and the excavation of the foundation pit are very unfavorable, so that the disturbance to the soil body at the periphery of the foundation pit and in the foundation pit is reduced as much as possible in the construction process.
Therefore, a further improvement is needed for the existing excavation method of the foundation pit in the soft soil stratum.
Disclosure of Invention
The invention aims to solve the technical problem of providing the excavation method of the soft soil stratum foundation pit, which has the advantages that the excavator is not directly contacted with the soft soil stratum, the side pressure of the foundation pit is reduced, and the excavation is facilitated.
The technical scheme adopted by the invention for solving the technical problems is as follows: a method for excavating a foundation pit in a soft soil stratum is characterized by comprising the following steps: the method comprises the following steps:
1) constructing a foundation pit supporting pile: measuring the driving position of a support pile according to the size of a foundation pit, driving a vertical columnar pile according to the measuring position, driving a vertical sheet pile between the columnar piles, driving the vertical sheet pile to be consistent with the sinking elevation of the columnar pile, and arranging a purlin outside the support pile;
2) erecting a trestle and excavating a foundation pit: the trestle is erected on the support pile along the width direction of the foundation pit, and can move relative to the foundation pit along the length direction of the foundation pit, the excavator is hoisted to the trestle by adopting a crane to perform foundation pit excavation, and the advancing and retreating of the excavator are realized by the movement of the trestle;
3) setting a muck conveyer and muck conveying: and placing the residue soil conveyor to the periphery of the foundation pit, conveying the residue soil to the residue soil conveyor by the excavator, and conveying the residue soil to a transport vehicle positioned on one side of the residue soil conveyor, which is far away from the foundation pit, through the residue soil conveyor.
There are various design ways of trestle, and preferably, the trestle comprises:
the two rails are respectively arranged above supporting piles at two sides of the foundation pit along the length direction of the foundation pit, and the supporting piles are inserted into the slots at the bottom of the rails;
the bridge body is erected on the two rails along the width direction of the foundation pit and used for placing the excavator;
the rotating wheels are arranged at the bottom of the bridge body and positioned at two sides of the bridge body, and the rotating wheels are positioned in the grooves at the top of the track;
and the driving device is connected with the rotating wheel in a driving way and drives the rotating wheel to move in the track along the length direction of the foundation pit.
Further, preferably, the driving device is a motor arranged on the bridge body, and a transmission belt is wound on a motor shaft of the motor; be provided with coupling assembling between the pontic and the rotation wheel, coupling assembling includes bracing piece, bearing and axis of rotation, the bracing piece sets up in the pontic bottom, the bearing sets up the bottom at the bracing piece, the bracing piece is fixed with the lateral wall of bearing, the axis of rotation is worn to establish in the bearing and is fixed with the inside wall of bearing, the rotation wheel is fixed in the axis of rotation, be connected through drive belt transmission between axis of rotation and the motor shaft.
In order to be beneficial to positioning of the bridge body and excavation of the excavator, preferably, a brake device is arranged between the track and the rotating wheel, the brake device comprises a first brake hole formed in the track, a second brake hole formed in the rotating wheel and a fixing pin, and the fixing pin penetrates through the first brake hole and the second brake hole to position the rotating wheel on the track.
In order to be beneficial to adapting to foundation pits with different widths, the bridge body is preferably of a telescopic structure and can be telescopically adjusted along the width direction of the foundation pit. Through the adjustment to the bridge body width, keep the running wheel to be located the recess at track top all the time.
Further, as preferred, the bridge body includes two and the support frame that sets up along foundation ditch width direction interval, is provided with hydraulic jack between two support frames, and this hydraulic jack sets up and adjusts the interval between two support frames along foundation ditch width direction. The distance between the two support frames is controlled by the extension and retraction of the hydraulic jack, so that the width of the bridge body is adjusted.
The design of dregs conveyer has a plurality of, and as preferred, dregs conveyer includes:
the shell is of a closed hollow structure, and a feed hopper and a discharge port are arranged on the shell;
the conveying device is arranged in the shell, one end of the conveying device extends out of the discharge hole, and the residue soil added into the feed hopper is discharged from the discharge hole;
the first driving device is in driving connection with the conveying device;
the crawler-type travelling mechanisms are arranged at the bottom of the shell and positioned at two sides of the shell;
and the second driving device is in driving connection with the crawler-type travelling mechanism.
Further, preferably, the first driving device is arranged on the housing, and the first driving device comprises a first motor, a first output shaft arranged on the first motor, and a first transmission belt wound on the first output shaft; conveyer includes and links to each other with the casing, along the feeder hopper to the bearing that discharge gate direction interval set up, wear to establish in the bearing and with bearing fixed connection's first transmission shaft, around establishing the conveyer belt in the first transmission shaft outside, first transmission shaft is connected through a drive belt transmission with first output shaft.
Further, preferably, the second driving device is arranged on the housing, and the second driving device comprises a second motor, a second output shaft arranged on the second motor, and a second transmission belt wound on the second output shaft; the crawler-type travelling mechanism comprises rollers arranged on one side of the bottom of the shell, a second transmission shaft connected with the rollers and a crawler wound on the outer side of the rollers, and the second transmission shaft is in transmission connection with a second output shaft through a second transmission belt.
Preferably, in the step 2), the excavation of the foundation pit adopts layered excavation, and after the excavation, a longitudinal enclosing purlin along the length direction of the foundation pit is arranged on the inner side of the support pile; be provided with the horizontal support along foundation ditch width direction in the foundation ditch, the both ends of support are fixed with enclosing the purlin, support for a plurality of and set up along the length direction interval of foundation ditch, interval between the adjacent support is at 4 ~ 6m, the elevation difference of support is not more than 30mm, the difference in elevation of supporting both ends is not more than 20mm and supports 1/600 of length, the straightness deviation of hanging down of column stake is not more than the 1/100 of foundation ditch excavation degree of depth, the axis deviation of support and column stake is not more than 50mm, it is not more than 30mm to support horizontal axis deviation.
Compared with the prior art, the invention has the advantages that: according to the invention, the trestle along the width direction of the foundation pit is erected on the support pile, the trestle can move relative to the foundation pit along the length direction of the foundation pit, the excavator is hung on the trestle by adopting a crane to perform foundation pit excavation, the advancing and retreating of the excavator are realized by the movement of the trestle, the excavator is not directly contacted with a soft soil stratum, the deep sinking of the excavator is avoided, the traditional 'digging-drying-digging' process is not needed, the construction period is shortened, the utilization rate of equipment is improved, the operation space of the excavator on the trestle is increased, and the excavation of the foundation pit is more facilitated. Set up the dregs conveyer in foundation ditch periphery, the excavator delivers to the dregs conveyer with the dregs on, carry the dregs to the transport vechicle that is located dregs conveyer and keeps away from foundation ditch one side through the dregs conveyer on, compare with the transport vechicle, the weight of dregs conveyer will be light a lot, the setting of dregs conveyer has reduced foundation ditch support side direction soil pressure, prevent that the dregs transport vechicle from being absorbed in silt, reduced the destruction deformation to foundation ditch fender pile, the security that has improved whole work progress.
Drawings
Fig. 1 is a cross-sectional view of a trestle in an embodiment of the invention.
FIG. 2 is a schematic structural diagram of a bridge according to an embodiment of the present invention.
Fig. 3 is a schematic structural diagram of a brake device according to an embodiment of the present invention.
Fig. 4 is a schematic structural view of a muck conveyor in an embodiment of the present invention.
Fig. 5 is a schematic structural view of a muck conveyor in an embodiment of the invention.
Fig. 6 is a schematic layout view of a trestle and a muck conveyor on a construction site in the embodiment of the invention.
Fig. 7 is a schematic structural view of a support pile in the embodiment of the present invention.
Figure 8 is a schematic illustration of the excavation of an excavator according to an embodiment of the present invention (excavation to the first floor).
Figure 9 is a schematic illustration of the excavation of the excavator (excavation to the second floor) in an embodiment of the present invention.
Fig. 10 is a schematic view of the excavation of the excavator according to the embodiment of the present invention (excavation to the third floor).
Detailed Description
The invention is described in further detail below with reference to the accompanying examples.
The excavation method of the soft soil stratum foundation pit in the embodiment comprises the following steps:
1) constructing a foundation pit supporting pile 9: the driving position of the support pile 9 is measured according to the size of a foundation pit, a vertical columnar pile 91 is firstly driven according to the measured position, the columnar pile 91 exceeds the ground by a certain height, vertical sheet piles 92 are driven between the columnar piles 91, the sinking height of the sheet piles 92 is consistent with the sinking elevation of the columnar piles 91, and a surrounding purlin 93 is arranged on the outer side of the support pile 9. Referring to fig. 7, in this embodiment, the support pile 9 adopts a PC construction method combined pile, and the construction method adopts a steel pipe pile (columnar pile 91) and a larsen steel sheet pile (sheet pile 93) to be combined and connected to form an integral steel continuous wall body combined structure, which is a recyclable steel continuous wall body in green construction.
2) Erecting a trestle and excavating a foundation pit: referring to fig. 6, a trestle 1a is erected on a support pile 9 along the width direction of a foundation pit 1c, the trestle 1a can move relative to the foundation pit along the length direction of the foundation pit 1c, an excavator 1d is hung on the trestle 1a by a crane to perform excavation of the foundation pit 1c, and the advancing and retreating of the excavator 1d are realized by the movement of the trestle 1 a; referring to fig. 8-10, the excavation of the foundation pit adopts layered excavation, and after the excavation, a longitudinal enclosing purlin along the length direction of the foundation pit 1c is arranged on the inner side of the support piles 9; be provided with in foundation ditch 1c along foundation ditch 1c width direction's horizontal support 94, support 94's both ends are fixed with enclosing the purlin, support 94 is a plurality of and sets up along foundation ditch 1 c's length direction interval, the interval between the adjacent support 94 is at 5m, the elevation difference of support 94 is not more than 30mm, the difference in elevation of support 94 both ends is not more than 20mm and supports 1/600 of 94 length, the straightness deviation of straightness of pile 91 is not more than 1/100 of foundation ditch 1c excavation depth, the axis deviation of support 94 and columnar pile 91 is not more than 50mm, support 94 horizontal axis deviation is not more than 30 mm.
3) Setting a muck conveyer and muck conveying: the muck conveyor 1b is placed on the periphery of the foundation pit 1c, the excavator 1d conveys the muck to the muck conveyor 1b, and the muck is conveyed to a transport vehicle 1e located on one side, far away from the foundation pit 1c, of the muck conveyor 1b through the muck conveyor 1b, see fig. 6.
Referring to fig. 1, 2 and 3, a preferred embodiment of the trestle 1a of the invention is shown, and the trestle 1a comprises a track 1, a trestle body 2, a rotating wheel 3, a driving device 4, a connecting assembly 5 and a brake device 8.
The tracks 1 are H-shaped, the number of the tracks is two, and the two tracks 1 are respectively arranged above the supporting piles 9 on the two sides of the foundation pit 1c along the length direction of the foundation pit 1 c. The track 1 comprises a plurality of sections of rails 11 connected end to end along the length of the foundation pit 1c, and the rails 11 are preferably detachably connected. The height of the upper groove and the lower groove of the track 1 is 5cm, the upper end of the combined pile in the PC construction method can be clamped into the groove at the bottom of the track 1, the combined pile in the PC construction method bears the load of the track 1, each section of steel rail 11 is 5m, and the combined pile is erected in sections.
The pontic 2 is established on two tracks 1 along foundation ditch 1 c's width direction, the both ends of pontic 2 are established respectively on two tracks 1, pontic 2 supplies digging placing of machine 1d, pontic 2 is extending structure, pontic 2 includes two and the support frame 21 that sets up along foundation ditch 1c width direction interval, be provided with hydraulic jack 6 between two support frames 21, this hydraulic jack 6 sets up and adjusts the interval between two support frames 21 along foundation ditch 1c width direction, hydraulic jack 6's quantity is a plurality of, set up along foundation ditch 1 c's length direction interval. The width of the trestle 1a is adjusted to the extent that the rotating wheel 3 is just clamped into the top clamping groove of the track 1. A steel plate 22 is laid above the bridge body 2, the surface of the steel plate 22 is rough, the excavator 1d is placed above the steel plate, the crawler of the excavator 1d is in direct contact with the excavator, and the rough surface prevents the excavator from slipping.
The rotating wheels 3 are arranged at the bottom of the bridge body 2 and located at two sides of the bridge body 2, in this embodiment, two rotating wheels 3 (not shown in the figure) are arranged at each side of the bridge body 2, and the rotating wheels 3 are located in grooves at the top of the track 1.
The drive means 4 is a motor arranged on the bridge 2, the motor shaft 42 of which is provided with a drive belt 41 around it.
A connecting assembly 5 is arranged between the axle body 2 and the turning wheel 3, the connecting assembly 5 comprising a support rod 51, a bearing 52 and a turning shaft 53. The support rod 51 is arranged at the bottom of the bridge body 2, the bearing 52 is arranged at the bottom end of the support rod 51, the support rod 51 is welded and fixed with the outer side wall of the bearing 52, the rotating shaft 53 is arranged in the bearing 52 in a penetrating mode and is welded and fixed with the inner side wall of the bearing 52, the rotating shaft 53 is in transmission connection with the motor shaft 42 through the transmission belt 41, and the rotating wheel 3 is driven to move on the track 1 along the length direction of the foundation pit.
The brake device 8 includes a first braking hole 81 formed in the rail 1, a second braking hole 82 formed in the rotating wheel 3, and a fixing pin 83, and the fixing pin 83 is inserted into the first braking hole 81 and the second braking hole 82 to position the rotating wheel 3 on the rail 1. The first braking holes 81 are provided at intervals in the longitudinal direction of the rail 1, and the second braking holes 82 are provided at intervals in the circumferential direction of the rotating wheel 3.
Referring to fig. 5 and 6, a preferred embodiment of the mobile muck conveyor of the invention is shown, comprising: the device comprises a shell 10, a conveying device 20, a first driving device 30, a crawler-type walking mechanism 40, a second driving device 50, a fixing device 70 and a lifting device 80.
The shell 10 is a closed hollow structure, a feed hopper 101 is arranged at the top of the shell 10, and a discharge hole is formed in the side wall of the shell.
The conveying device 20 is arranged in the shell 10, one end of the conveying device 20 extends out of the discharge hole, the residue soil added into the feed hopper 101 is discharged from the discharge hole, and the conveying device 20 is arranged in the shell 10 to avoid the residue soil from spilling during conveying. The conveying device 20 comprises a bearing 201 connected with the housing 10 and arranged at intervals along the direction from the feeding hopper 101 to the discharging port, a first transmission shaft 202 arranged in the bearing 201 in a penetrating way and fixedly connected with the bearing 201, and a conveyor belt 203 arranged outside the bearing 201 in a winding way. In this embodiment, the number of the bearings 201 is two, and the bearings are a first bearing 2001 and a second bearing 2002, the first bearing 2001 is located inside the housing 10, the outer side of the first bearing 2001 is welded and fixed with the housing 10, the second bearing 2002 is located outside the discharge port and connected with the lifting device 80, the second bearing 2002 can move up and down relative to the housing 10, and the first transmission shaft 202 is welded inside the first bearing 2001 and the second bearing 2002.
The first driving device 30 is disposed on the housing 10, and the first driving device 30 includes a first motor 303, a first output shaft 31 disposed on the first motor 303, and a first transmission belt 302 wound on the first output shaft 301, wherein a first transmission shaft 202 is in transmission connection with the first output shaft 31 through the first transmission belt 302.
The crawler-type traveling mechanism 40 is disposed at the bottom of the housing 10 and located at both sides of the housing 10, and the crawler-type traveling mechanism 40 includes a roller 401 disposed at one side of the bottom of the housing 10, a second transmission shaft 402 connected to the roller 401, and a crawler 403 wound around the outer side of the roller 401. In this embodiment, the number of the rollers 401 on each side of the bottom of the housing 10 is two, and accordingly, the number of the second transmission shafts 402 is 2.
The second driving device 50 is disposed on the housing 10, and the second driving device 50 includes a second motor 503, a second output shaft 501 disposed on the second motor 503, and a second transmission belt 502 wound on the second output shaft 501, wherein a second transmission shaft 402 is in transmission connection with the second output shaft 501 through the second transmission belt 502.
The lifting device 80 is arranged on the outer side of the shell 10, the lifting device 80 is a hydraulic jack in the embodiment, the hydraulic jack is connected with the second bearing 2002 through a connecting rod 90, specifically, the second bearing 2002 is welded with the connecting rod 90, the lifting device 80 controls the lifting of the connecting rod 90 to drive the second bearing 2002 to move up and down relative to the shell 10, the height of one end, extending out of the discharge port, of the conveying device 20 away from the ground is adjusted, and transport vehicles with different heights are met.
The fixing device 70 comprises a fixing rod 701 hinged with the housing 10, a fixing plate 702 connected with the bottom end of the fixing rod 701, and an anchor 703 arranged on the fixing plate 702 in a penetrating manner to fix the fixing plate 702 and the ground together, wherein the number of the fixing devices 70 is four, and the four fixing devices are arranged at four corners of the housing 10.

Claims (10)

1. A method for excavating a foundation pit in a soft soil stratum is characterized by comprising the following steps: the method comprises the following steps:
1) constructing a foundation pit supporting pile: measuring the driving position of a support pile according to the size of a foundation pit, driving a vertical columnar pile according to the measuring position, driving a vertical sheet pile between the columnar piles, driving the vertical sheet pile to be consistent with the sinking elevation of the columnar pile, and arranging a purlin outside the support pile;
2) erecting a trestle and excavating a foundation pit: the trestle is erected on the support pile along the width direction of the foundation pit and can move relative to the foundation pit along the length direction of the foundation pit, the excavator is hung on the trestle by adopting a crane to perform foundation pit excavation, and the advancing and retreating of the excavator are realized by the movement of the trestle;
3) setting a muck conveyor and transporting muck: and placing the residue soil conveyor to the periphery of the foundation pit, conveying the residue soil to the residue soil conveyor by the excavator, and conveying the residue soil to a transport vehicle positioned on one side of the residue soil conveyor, which is far away from the foundation pit, through the residue soil conveyor.
2. The excavation method of the soft soil formation foundation pit according to claim 1, characterized in that: the trestle comprises:
the two rails (1) are arranged above supporting piles at two sides of the foundation pit along the length direction of the foundation pit, and the supporting piles are inserted into the slots at the bottom of the rails (1);
the bridge body (2) is erected on the two rails (1) along the width direction of the foundation pit and used for placing an excavator;
the rotating wheels (3) are arranged at the bottom of the bridge body (2) and positioned on two sides of the bridge body (2), and the rotating wheels (3) are positioned in the grooves in the top of the track (1);
and the driving device (4) is connected with the rotating wheel (3) in a driving way, and drives the rotating wheel (3) to move in the track (1) along the length direction of the foundation pit.
3. The excavation method of the soft soil formation foundation pit according to claim 2, characterized in that: the driving device (4) is a motor arranged on the bridge body (2), and a transmission belt (41) is wound on a motor shaft (42) of the motor; the utility model discloses a bearing, including the axle body (2), the axle body (2) and the rotation wheel (3) between be provided with coupling assembling (5), coupling assembling (5) are including bracing piece (51), bearing (52) and axis of rotation (53), bracing piece (51) set up in axle body (2) bottom, bearing (52) set up the bottom at bracing piece (51), bracing piece (51) are fixed with the lateral wall of bearing (52), axis of rotation (53) are worn to establish in bearing (52) and are fixed with the inside wall of bearing (52), it fixes on axis of rotation (53) to rotate wheel (3), axis of rotation (53) are connected through drive belt (41) transmission with motor shaft (42).
4. The excavation method of the soft soil formation foundation pit according to claim 2, characterized in that: track (1) and rotate and be provided with brake equipment (8) between wheel (3), brake equipment (8) are including offering first brake hole (81) on track (1), offering second brake hole (82) and fixed pin (83) on rotating wheel (3), fixed pin (83) are worn to establish and are rotated wheel (3) location on track (1) in first brake hole (81), second brake hole (82).
5. The excavation method of the soft soil formation foundation pit according to claim 2, characterized in that: the bridge body (2) is of a telescopic structure, and the bridge body (2) can be telescopically adjusted along the width direction of the foundation pit.
6. The excavation method of a soft soil formation foundation pit according to claim 5, wherein: bridge (2) include two and support frame (21) that set up along foundation ditch width direction interval, are provided with hydraulic jack (6) between two support frames (21), and this hydraulic jack (6) set up and adjust the interval between two support frames (21) along foundation ditch width direction.
7. The excavation method of the soft soil formation foundation pit according to claim 1, characterized in that: the muck conveyor comprises:
the shell (10) is of a closed hollow structure, and a feed hopper (101) and a discharge hole are arranged on the shell (10);
the conveying device (20) is arranged in the shell (10), one end of the conveying device (20) extends out of the discharge hole, and the residue soil added into the feed hopper (101) is discharged from the discharge hole;
the first driving device (30) is in driving connection with the conveying device (20);
the crawler-type travelling mechanisms (40) are arranged at the bottom of the shell (10) and are positioned at two sides of the shell (10);
and the second driving device (50) is in driving connection with the crawler type travelling mechanism (40).
8. The excavation method of a soft soil formation foundation pit according to claim 7, characterized in that: the first driving device (30) is arranged on the shell (10), and the first driving device (30) comprises a first motor (303), a first output shaft (301) arranged on the first motor (303), and a first transmission belt (302) wound on the first output shaft (301); conveyer (20) including with casing (10) link to each other, along feeder hopper (101) bearing (201) to the discharge gate direction interval setting, wear to establish in bearing (201) and with bearing (201) fixed connection's first transmission shaft (202), around establishing conveyer belt (203) in first transmission shaft (202) outside, first transmission shaft (202) are connected through first drive belt (302) transmission with first output shaft (301).
9. The mobile muck conveyor of claim 7, wherein: the second driving device (50) is arranged on the shell (10), and the second driving device (50) comprises a second motor (503), a second output shaft (501) arranged on the second motor (503), and a second transmission belt (502) wound on the second output shaft (501); the crawler-type travelling mechanism (40) comprises rollers (401) arranged on one side of the bottom of the shell (10), a second transmission shaft (402) connected with the rollers (401) and a crawler (403) wound on the outer side of the rollers (401), and the second transmission shaft (402) is in transmission connection with a second output shaft (501) through a second transmission belt (502).
10. The excavation method of a soft soil formation foundation pit according to claim 1, wherein: in the step 2), the excavation of the foundation pit adopts layered excavation, and after the excavation, a longitudinal enclosing purlin along the length direction of the foundation pit is arranged on the inner side of the support pile; be provided with the horizontal support along foundation ditch width direction in the foundation ditch, the both ends of support are fixed with enclosing the purlin, support for a plurality of and set up along the length direction interval of foundation ditch, interval between the adjacent support is at 4 ~ 6m, the elevation difference of support is not more than 30mm, the difference in elevation of supporting both ends is not more than 20mm and supports 1/600 of length, the straightness deviation of hanging down of column stake is not more than the 1/100 of foundation ditch excavation degree of depth, the axis deviation of support and column stake is not more than 50mm, it is not more than 30mm to support horizontal axis deviation.
CN202210152172.5A 2022-02-18 2022-02-18 Excavation method for foundation pit in soft soil stratum Pending CN114718074A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210152172.5A CN114718074A (en) 2022-02-18 2022-02-18 Excavation method for foundation pit in soft soil stratum

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210152172.5A CN114718074A (en) 2022-02-18 2022-02-18 Excavation method for foundation pit in soft soil stratum

Publications (1)

Publication Number Publication Date
CN114718074A true CN114718074A (en) 2022-07-08

Family

ID=82235877

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210152172.5A Pending CN114718074A (en) 2022-02-18 2022-02-18 Excavation method for foundation pit in soft soil stratum

Country Status (1)

Country Link
CN (1) CN114718074A (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0974702A2 (en) * 1998-07-24 2000-01-26 Hitachi Construction Machinery Co., Ltd. Automotive soil treating machine
CN107012872A (en) * 2017-05-26 2017-08-04 中国十九冶集团有限公司 Mud construction method of deep foundation ditch
CN108193663A (en) * 2018-01-24 2018-06-22 浙江立鹏建设有限公司 The foundation stabilization equipment that the processing method and this method of deep foundation base are formed
CN109356130A (en) * 2018-12-10 2019-02-19 中国电建集团贵阳勘测设计研究院有限公司 A kind of locking means and device of tailrace tunnel bulkhead gate
CN110004934A (en) * 2019-04-11 2019-07-12 中国葛洲坝集团第一工程有限公司 Foundation excavation of silt excavation construction method
CN209812301U (en) * 2019-05-10 2019-12-20 惠州市小球科技有限公司 Novel robot walking transmission device
CN210113321U (en) * 2019-05-27 2020-02-25 孙振岩 River channel dredging dredger convenient to operate and used for hydraulic engineering construction
CN211285220U (en) * 2019-09-25 2020-08-18 上海建工集团股份有限公司 Automatic landing stage device
CN112673980A (en) * 2021-01-15 2021-04-20 熊银 Agricultural is bred and feeds water device with livestock
CN112814061A (en) * 2021-01-25 2021-05-18 三峡国际能源投资集团有限公司 Continuous operation device and method for channel construction
CN213684129U (en) * 2020-10-20 2021-07-13 北京住总第一开发建设有限公司 Tunnel slag-tapping auxiliary transportation equipment
CN113502824A (en) * 2021-07-08 2021-10-15 中国建筑第八工程局有限公司 Construction method for quickly unearthing annular road in deep foundation pit by combining trestle with construction method
WO2021218078A1 (en) * 2020-04-30 2021-11-04 深圳市工勘岩土集团有限公司 Construction method for foundation pit earthwork transportation and crushing

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0974702A2 (en) * 1998-07-24 2000-01-26 Hitachi Construction Machinery Co., Ltd. Automotive soil treating machine
CN107012872A (en) * 2017-05-26 2017-08-04 中国十九冶集团有限公司 Mud construction method of deep foundation ditch
CN108193663A (en) * 2018-01-24 2018-06-22 浙江立鹏建设有限公司 The foundation stabilization equipment that the processing method and this method of deep foundation base are formed
CN109356130A (en) * 2018-12-10 2019-02-19 中国电建集团贵阳勘测设计研究院有限公司 A kind of locking means and device of tailrace tunnel bulkhead gate
CN110004934A (en) * 2019-04-11 2019-07-12 中国葛洲坝集团第一工程有限公司 Foundation excavation of silt excavation construction method
CN209812301U (en) * 2019-05-10 2019-12-20 惠州市小球科技有限公司 Novel robot walking transmission device
CN210113321U (en) * 2019-05-27 2020-02-25 孙振岩 River channel dredging dredger convenient to operate and used for hydraulic engineering construction
CN211285220U (en) * 2019-09-25 2020-08-18 上海建工集团股份有限公司 Automatic landing stage device
WO2021218078A1 (en) * 2020-04-30 2021-11-04 深圳市工勘岩土集团有限公司 Construction method for foundation pit earthwork transportation and crushing
CN213684129U (en) * 2020-10-20 2021-07-13 北京住总第一开发建设有限公司 Tunnel slag-tapping auxiliary transportation equipment
CN112673980A (en) * 2021-01-15 2021-04-20 熊银 Agricultural is bred and feeds water device with livestock
CN112814061A (en) * 2021-01-25 2021-05-18 三峡国际能源投资集团有限公司 Continuous operation device and method for channel construction
CN113502824A (en) * 2021-07-08 2021-10-15 中国建筑第八工程局有限公司 Construction method for quickly unearthing annular road in deep foundation pit by combining trestle with construction method

Similar Documents

Publication Publication Date Title
KR970001724B1 (en) Trench excavating machine for underground retaining wall
JPS62233328A (en) Method and apparatus for setting retaining wall by excavator
CN107288171A (en) Bore support integral type shaft pore-forming device
CN112144951A (en) Crawler-type line pole erecting equipment
US5403125A (en) Method and apparatus for providing underground barrier
CN114718074A (en) Excavation method for foundation pit in soft soil stratum
JP3356048B2 (en) Construction method of elevated structure using building girder
CN216130939U (en) Two linings of walking, cable duct side wall integration platform trucks for tunnel
CN113187954B (en) Construction method of large-caliber nodular cast iron water supply pipe in valley zone
CN112323729B (en) Pile foundation bearing platform river-facing deep foundation pit supporting system and construction method
CN115584744A (en) Slag discharging and transporting method for four-rail three-line variable cross-section tunnel anchor
CN114673209A (en) Hard rock ditching machine and hard rock ditching method
CN209941687U (en) Heavy-duty equipment hoisting device based on proximity deep foundation pit construction environment
WO2013162408A1 (en) Shaft lining, system for constructing such a lining and method for constructing such a lining
CN113200300A (en) Automatic earthwork conveying and loading system with self-adaptive adjustment of excavation depth
CN208486883U (en) A kind of tunnel circumferential direction french drain cutting trolley
CN217536980U (en) Trestle applied to soft soil foundation pit
CN112554783A (en) Dry hole-forming drilling machine for construction in underground narrow space and construction method
JP5865760B2 (en) Steel pipe press-fitting device moving device and steel pipe press-fitting device installation method
CN111456143A (en) Open excavation construction equipment for comprehensive pipe gallery and construction method thereof
CN215206838U (en) Automatic earthwork conveying and loading system with self-adaptive adjustment of excavation depth
CN217811285U (en) Movable-roof hydraulic caisson excavator
CN114396073B (en) Coal yard foundation structure, construction method thereof and coal yard structure
JP4080226B2 (en) Mobile jetty
CN218562366U (en) Underground continuous wall and TRD link up stagnant water architecture

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination