CN114704059A CN202210321522.6A CN202210321522A CN114704059A CN 114704059 A CN114704059 A CN 114704059A CN 202210321522 A CN202210321522 A CN 202210321522A CN 114704059 A CN114704059 A CN 114704059A
Authority
CN
China
Prior art keywords
nail
bamboo
driving
piece
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210321522.6A
Other languages
Chinese (zh)
Other versions
CN114704059B (en
Inventor
朱贤刚
林蔚
牧启灯
康聪颖
蒋森淼
黄小平
李�远
顾水波
黄磊磊
吴立峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Xiaoshan Water Construction Engineering Co ltd
Original Assignee
Hangzhou Xiaoshan Water Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Xiaoshan Water Construction Engineering Co ltd filed Critical Hangzhou Xiaoshan Water Construction Engineering Co ltd
Priority to CN202210321522.6A priority Critical patent/CN114704059B/en
Publication of CN114704059A publication Critical patent/CN114704059A/en
Application granted granted Critical
Publication of CN114704059B publication Critical patent/CN114704059B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/20Implements for finishing work on buildings for laying flooring
    • E04F21/22Implements for finishing work on buildings for laying flooring of single elements, e.g. flooring cramps ; flexible webs

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Floor Finish (AREA)
  • Portable Nailing Machines And Staplers (AREA)

Abstract

The application relates to quick bamboo floor mounting equipment for embankment engineering, which comprises a rack, wherein a moving member for facilitating the movement of the rack is arranged on the rack, a plate bin and a discharge box are fixedly arranged on the rack, a connector communicated with the discharge box is formed in the inner side wall of the plate bin and used for allowing plates to pass through, an opening in the bottom wall of the discharge box is formed, and a pushing member used for pushing the plates in the plate bin to the discharge box is arranged on the rack; an installation frame is arranged in the discharge box in a sliding mode along the length direction of the discharge box, a first driving piece for driving the installation frame to slide is arranged on the discharge box, a fixing piece is arranged on the installation frame, and the fixing piece is used for fixing the plate on the framework; still be provided with drive assembly on the mounting bracket, drive assembly is used for ordering about the mounting and fixes panel on the skeleton. This application has bamboo-wood floor's effect that installation effectiveness is high.

Description

Quick erection equipment of bamboo-wood floor for dyke engineering
Technical Field
The application relates to the technical field of floor laying, in particular to a quick bamboo floor installation device for embankment engineering.
Background
The bamboo floor is a compound regenerated product of bamboo and wood; in the production and manufacturing process of the bamboo-wood floor, the bamboo-wood floor needs to be processed by a series of procedures of corrosion prevention, moisture prevention, high pressure, high temperature, gluing, rotary grinding and the like by means of fine machinery and equipment, advanced science and technology and standard production process flows, so that the bamboo-wood floor has the characteristics of moisture prevention, corrosion prevention, strong toughness, high stability, firmness, durability and the like, and is widely applied to different working conditions or environments such as indoor or outdoor and the like.
At present, bamboo and wood floors are usually paved on outdoor landscape roads to prevent the situations of muddy ground and the like; when the bamboo floor is installed, the framework needs to be fixed on the ground, and then the plates are laid on the framework and fixed.
The related art described above has the following drawbacks: when the bamboo floor is laid, workers need to lay the plates on the framework one by one and fix the plates respectively, so that the bamboo floor is low in installation efficiency.
Disclosure of Invention
In order to improve bamboo floor's installation effectiveness, this application provides a dyke is quick erection equipment of bamboo floor for engineering.
The application provides a pair of dyke engineering is with quick erection equipment of bamboo-wood floor adopts following technical scheme:
a bamboo floor rapid installation device for embankment engineering comprises a rack, wherein a moving member used for facilitating the movement of the rack is arranged on the rack, a plate bin and a discharge box are fixedly arranged on the rack, a connecting port communicated with the discharge box is formed in the inner side wall of the plate bin and used for allowing plates to pass through, an opening in the bottom wall of the discharge box is formed, and a pushing member used for pushing the plates in the plate bin to the discharge box is arranged on the rack; a mounting frame is arranged in the discharge box in a sliding manner along the length direction of the discharge box, a first driving piece for driving the mounting frame to slide is arranged on the discharge box, and a fixing piece is arranged on the mounting frame and used for fixing the plate on the framework; still be provided with drive assembly on the mounting bracket, drive assembly is used for ordering about the mounting and fixes panel on the skeleton.
By adopting the technical scheme, when the bamboo floor plate conveying device is used, plates of a bamboo floor are placed in the plate bin, the framework is fixed at the mounting position of the bamboo floor, the rack is moved to the mounting position of the bamboo floor, the rack is pushed by the moving piece to slide, after the rack moves for a certain distance, the plates in the plate bin are pushed into the discharge box by the pushing piece, and the plates are conveyed to the framework by the discharge box; meanwhile, the first driving piece is started to order about the mounting frame to be pressed downwards, the fixing piece is ordered about through the driving assembly to fix the plate on the framework, then the moving piece enables the rack to move to the next node, the plate continues to be installed, the whole installation process is convenient and fast, and the installation efficiency of the bamboo floor is greatly improved.
Optionally, the moving member includes the gyro wheel, the bottom of frame is rotated and is provided with a plurality of supports, just the support is used for erectting on the skeleton, every all rotate on the support and be provided with the gyro wheel, just the gyro wheel is used for supporting the surface of skeleton tightly.
By adopting the technical scheme, the frame is erected on the framework through the bracket, and the roller is abutted against the surface of the framework, so that the friction force between the bracket and the framework is reduced; when the bamboo floor is installed, the bamboo floor can be quickly installed under different shapes or environments by using the installation equipment only by installing and fixing the framework, and the adaptability of the installation equipment is greatly improved.
Optionally, the mounting includes the screw, the fixed nail section of thick bamboo that is provided with on the mounting bracket, the both ends opening setting of a nail section of thick bamboo, be connected with on the nail section of thick bamboo and store up the nail box, it has the screw to store up in the nail box, it is used for carrying the pay-off subassembly to a nail section of thick bamboo with the screw to store up to be provided with in the nail box, be provided with the clamping component who is used for pressing from both sides tight screw in the nail section of thick bamboo, drive assembly is used for fixing panel in the skeleton with screw in panel.
By adopting the technical scheme, the screws are stored in the screw storage box, when the plate and the framework are required to be fixed, the screws in the screw storage box are conveyed into the screw barrel through the feeding assembly, and are clamped through the clamping assembly, so that the screws are prevented from falling from the screw barrel to a certain extent; then, the first driving piece drives the mounting frame to move, so that the screw moves to the position above the plate and is abutted against the upper end face of the plate, the screw is screwed into the plate through the driving assembly, and the plate is fixed on the framework; during the manufacturing of the plate, a hole for inserting a screw can be formed in the plate, so that the later installation of the screw is facilitated.
Optionally, the clamping assembly comprises a top bead and a first elastic piece, a placing groove is formed in the inner wall of the nail barrel along the axial direction perpendicular to the nail barrel, the top bead is arranged in the placing groove in a sliding mode, the first elastic piece is used for driving the top bead to move towards the direction far away from the bottom wall of the placing groove, and a first limiting piece used for preventing the top bead from being separated from the placing groove is arranged in the placing groove.
Through adopting above-mentioned technical scheme, the width of screwhead is greater than other positions of screw usually, and the screw is after getting into a nail section of thick bamboo, pushes away the top pearl through first elastic component and slides to keeping away from standing groove diapire direction to block the screwhead, thereby under the condition that does not receive external force to influence, prevent that the screw from droing in the nail section of thick bamboo.
Optionally, the pay-off subassembly includes push pedal and second elastic component, the push pedal slides and sets up in storing up the nail box, store up the lateral wall of nail box and seted up out the nail mouth, the lateral wall of a nail section of thick bamboo is offered and is used for supplying the nail mouth that advances that the screw got into, just go out the nail mouth and advance nail mouth intercommunication, the second elastic component is used for ordering about the push pedal and slides to being close to out the nail mouth direction.
Through adopting above-mentioned technical scheme, order about the push pedal through the second elastic component and slide to being close to out the nail mouth direction to with the screw from the nail mouth propelling movement to a nail section of thick bamboo of storing up the nail box, when having the screw in a nail section of thick bamboo, adjacent screw is located stores up the nail box, and have all the time to the gliding trend of a nail section of thick bamboo, order about the screw and break away from and fix the back to panel in a nail section of thick bamboo when drive assembly, next screw gets into a nail section of thick bamboo under the spring action of second elastic component in, and continue the installation of follow-up panel.
Optionally, the nail storage box is detachably connected with the nail barrel.
By adopting the technical scheme, the nail storage box is detachably connected with the nail barrel, and when the screws in the nail storage box are used up, the nail storage box is detached, so that new screws can be conveniently supplemented into the nail storage box; and, can also prepare a plurality of storage nail boxes to store up nail box and carry out quick replacement, further improve the efficiency of construction.
Optionally, the lateral wall of storing up the nail box and being located the both sides of going out the nail mouth and all fixedly being provided with the installation piece, the lateral wall of a nail section of thick bamboo and being located the fixed block that is provided with in both sides of advancing the nail mouth, two the mounting groove has all been seted up along the axial of a nail section of thick bamboo to the one end that is close to each other on the fixed block, just the mounting groove is used for supplying the installation piece to insert.
By adopting the technical scheme, the nail storage box can be arranged on the nail barrel by inserting the mounting block into the mounting groove on the fixing block, and the nail outlet on the nail storage box is communicated with the nail inlet on the nail barrel; the nail storage box and the nail barrel can be disassembled and assembled more conveniently and rapidly.
Optionally, drive assembly includes screwdriver head, driving source and second driving piece, the endwise slip along a nail section of thick bamboo on the mounting bracket is provided with the installation sleeve, just the installation sleeve is just right with a nail section of thick bamboo, screwdriver head coaxial rotation sets up in the installation sleeve, the driving source sets up on the installation sleeve and is used for ordering about the screwdriver head rotation, the second driving piece is used for ordering about the installation sleeve and slides and drive in the screwdriver head inserts a nail section of thick bamboo.
Through adopting above-mentioned technical scheme, when needs are fixed panel and skeleton, make the screw contradict with the upper surface of panel through first driving piece, order about the installation sleeve through the second driving piece and slide and drive screwdriver head and insert a nail section of thick bamboo in, make screwdriver head and the last tightening groove of screwhead cooperate, later, start the driving source and order about screwdriver head and rotate, and meanwhile, the second driving piece slowly drives the installation sleeve and moves down to in with screw in panel, and make panel fix on the skeleton.
Optionally, the discharge box is provided with limiting grooves on two opposite side walls, the limiting grooves are formed between the opening end and the connector of the discharge box, the limiting grooves are provided with limiting blocks in a sliding mode, the limiting grooves are provided with two limiting blocks, the upper end faces of the limiting blocks are flushed and separated from the connector, the sliding directions of the limiting blocks are close to or far away from each other, and a third driving piece used for driving the limiting blocks to slide is arranged in the discharge box.
Through adopting above-mentioned technical scheme, panel prevents through the stopper that panel breaks away from the storage incasement after getting into out the workbin, because the up end of two stoppers flushes to carry out the leveling to the panel that gets into out the workbin, later, install panel on the skeleton again, improve the installation quality of panel.
Optionally, the third driving piece includes the pressure spring, the pressure spring sets up at the spacing inslot, the one end of pressure spring and the diapire butt of spacing groove, the other end and stopper butt, the spacing inslot is provided with and is used for preventing the stopper from following the second locating part that the spacing inslot breaks away from, the stopper is kept away from the one end of keeping away from the spacing groove diapire and is kept away from the diapire of spacing groove gradually along the direction of keeping away from the play workbin roof, be provided with on the mounting bracket and be used for following ejecting piece of ejection in the play workbin with panel.
By adopting the technical scheme, after the limiting block is used for leveling the plate, the ejection part is contacted with the surface of the plate in the process of driving the mounting frame to move downwards through the first driving part, the mounting frame is continuously driven to move downwards, and the limiting block gradually slides towards the limiting groove through the inclined surface on the limiting block, so that the plate is ejected out of the discharge box; in addition, in the ejection process of the plate, the pressure spring pushes the limiting block to be always abutted against the side edge of the plate, so that the plate is more stable in the gliding process.
In summary, the present application includes at least one of the following beneficial technical effects:
1. after the rack moves for a certain distance, the plate in the plate bin is pushed into the discharge box through the material pushing part, and the plate is conveyed to the framework through the discharge box; meanwhile, the first driving piece is started to drive the mounting frame to be pressed downwards, the driving assembly drives the fixing piece to fix the plate on the framework, then the rack is moved to the next node through the moving piece, and the plate is continuously mounted, so that the whole mounting process is convenient and rapid, and the mounting efficiency of the bamboo floor is greatly improved;
2. the frame is erected on the framework through the bracket, and the roller is abutted against the surface of the framework, so that the friction force between the bracket and the framework is reduced; when the bamboo floor is installed, the bamboo floor can be quickly installed under different shapes or environments by using the installation equipment only by installing and fixing the framework, so that the adaptability of the installation equipment is greatly improved;
3. after the plate is leveled through the limiting block, the ejection part is contacted with the surface of the plate in the process of driving the mounting frame to move downwards through the first driving part, the mounting frame is continuously driven to move downwards, the limiting block is gradually slid into the limiting groove through the inclined surface on the limiting block, and the plate is ejected out of the discharge box; in addition, in the ejection process of the plate, the pressure spring pushes the limiting block to always abut against the side edge of the plate, so that the plate can slide down more stably.
Drawings
FIG. 1 is a schematic diagram of the overall structure of an embodiment of the present application;
FIG. 2 is an enlarged view of portion A of FIG. 1;
FIG. 3 is a partial sectional structural view of the embodiment of the present application, which is mainly used for expressing the internal structure of the discharge box;
FIG. 4 is an enlarged view of portion B of FIG. 3;
FIG. 5 is an enlarged view of portion C of FIG. 3;
FIG. 6 is a schematic diagram of a portion of an embodiment of the present application;
fig. 7 is an enlarged view of a portion D in fig. 6.
Description of reference numerals: 1. a frame; 11. a roller; 12. a support; 121. a clamping groove; 13. pushing the material piece; 2. a board stock bin; 21. a connecting port; 22. a containing groove; 23. a top block; 3. a discharging box; 31. an operation port; 32. a box cover; 33. a limiting groove; 34. a limiting block; 35. an anti-drop block; 36. a drop-proof groove; 37. a pressure spring; 38. a first driving member; 4. a mounting frame; 41. a sleeve; 411. a connecting rod; 4111. connecting blocks; 412. connecting grooves; 413. a return spring; 42. a top plate; 43. a fixing member; 44. a nail barrel; 441. a nail inlet; 442. a placement groove; 443. a baffle plate; 4431. a through hole; 444. a fixed block; 4441. mounting grooves; 45. a nail storage box; 451. a nail outlet; 452. mounting blocks; 453. a first positioning plate; 454. a second positioning plate; 46. a fixed mount; 47. installing a sleeve; 5. a clamping assembly; 51. a top bead; 52. a first elastic member; 6. a feeding assembly; 61. pushing the plate; 62. a second elastic member; 7. a drive assembly; 71. a screwdriver bit; 72. a drive source; 73. a second driving member.
Detailed Description
The present application is described in further detail below with reference to figures 1-7.
The embodiment of the application discloses dyke engineering is with quick erection equipment of bamboo-wood floor. Refer to fig. 1, including frame 1, fixed board feed bin 2 and the play workbin 3 of being provided with in frame 1, the roof opening setting of board feed bin 2, it is located one side of board feed bin 2 to handle the case, the length and the width of 2 inside in board feed bin and the length and the width looks adaptation of sheet material, the connector 21 with the inside intercommunication of play workbin 3 is seted up to the inside wall in board feed bin 2, connector 21 is used for supplying the sheet material to pass through, connector 21's the thickness that highly is greater than a sheet material, and be less than the thickness of two sheet materials.
Referring to fig. 2, a moving member for facilitating the movement of the rack 1 on the framework is arranged on the rack 1, the moving member includes a roller 11, four brackets 12 are rotatably arranged on the bottom wall of the rack 1, the four brackets 12 are distributed in a rectangular shape, a clamping groove 121 is arranged on one side of each bracket 12 far away from the rack 1, the brackets 12 are erected on the framework through the clamping groove 121, a roller 11 is arranged on each bracket 12, the roller 11 is rotatably arranged on the side wall close to the rack 1, and the surface of the roller 11 is used for abutting against the upper surface of the framework; when the bamboo floor is installed, only the framework needs to be installed and fixed, the rack 1 is erected on the framework through the support 12, the roller 11 is abutted against the surface of the framework, and the friction force between the support 12 and the framework is reduced; the installation equipment can be used for quickly installing the bamboo-wood floor in different shapes or environments, so that the adaptability of the installation equipment is greatly improved.
Referring to fig. 1, be provided with in the frame 1 and be used for promoting the pushing material 13 to play workbin 3 with panel feed bin 2 interior panel, pushing material 13 is including driving actuating cylinder, it welds in frame 1 to drive actuating cylinder, storage tank 22 has been seted up along the horizontal direction on the inside wall that connector 21 was kept away from in panel feed bin 2, it is provided with kicking block 23 to slide in the storage tank 22, the lateral wall of connector 21 has been seted up on the slip direction perpendicular to panel feed bin 2 of kicking block 23, the piston rod that drives actuating cylinder extends to in the panel feed bin 2 and welds with kicking block 23, drive actuating cylinder through the start-up, it slides to being close to connector 21 direction to drive actuating cylinder to drive kicking block 23, thereby with panel from connector 21 department of panel feed bin 2 to push to play workbin 3.
Refer to fig. 1, 3, the bottom opening of play workbin 3 sets up, operation mouth 31 has been seted up to the lateral wall of play workbin 3, the operation mouth 31 department of play workbin 3 articulates there is case lid 32, and the length and the width of the inside length of play workbin 3 and width and sheet material are corresponding, spacing groove 33 has all been seted up along the direction of perpendicular this lateral wall on the lateral wall of play workbin 3 and the lateral wall that is located connector 21 both sides, and spacing groove 33 sets up between the open end of play workbin 3 and connector 21, it is provided with stopper 34 all to slide in two spacing grooves 33, and the up end of two stopper 34 flushes.
Referring to fig. 4, a second limiting member for preventing the limiting block 34 from being separated from the limiting groove 33 is arranged in the limiting groove 33, the second limiting member includes an anti-falling block 35, an anti-falling groove 36 is formed in the side wall of the limiting groove 33 along the sliding direction of the limiting block 34, the anti-falling block 35 is slidably arranged in the anti-falling groove 36, and the anti-falling block 35 is welded to the limiting block 34.
Referring to fig. 4, a third driving member for driving the limiting block 34 to slide is arranged in the discharge box 3, the third driving member includes a pressure spring 37, the pressure spring 37 is arranged in the limiting groove 33, one end of the pressure spring 37 is welded to the bottom wall of the limiting groove 33, and the other end of the pressure spring is abutted to the limiting block 34; one end of the limiting block 34 far away from the bottom wall of the limiting groove 33 is gradually far away from the bottom wall of the limiting groove 33 along the direction far away from the top wall of the discharging box 3; the panel is after getting into ejection of compact case 3, prevents through stopper 34 that panel breaks away from the storage incasement, because the up end of two stoppers 34 flushes to the panel that gets into ejection of compact case 3 carries out the leveling, later, installs panel on the skeleton again, improves the installation quality of panel.
Referring to fig. 3, an installation frame 4 is slidably disposed in the discharge box 3 along the length direction of the discharge box 3, a first driving member 38 for driving the installation frame 4 to slide is disposed on the discharge box 3, the first driving member 38 includes a first cylinder, the first cylinder is fixed at the top end of the discharge box 3, a piston rod of the first cylinder extends into the discharge box 3 and is welded to the installation frame 4, a sleeve 41 is welded to the installation frame 4, the axial direction of the sleeve 41 is parallel to the sliding direction of the installation frame 4, and an opening is disposed at one end of the sleeve 41 away from the installation frame 4; in this embodiment, two bushings 41 are provided, and in other embodiments, any number of bushings 41 may be provided.
Referring to fig. 3 and 5, an ejector used for ejecting the plate from the discharging box 3 is arranged on the mounting frame 4, the ejector comprises a top plate 42, a connecting rod 411 is arranged in the sleeve 41 in a sliding manner, the length direction of the connecting rod 411 is perpendicular to the top plate 42, and the connecting rod 411 is welded with the top plate 42; connecting groove 412 has been seted up along the axial of sleeve 41 to the inner wall of sleeve 41, and the welding of the lateral wall of connecting rod 411 has connecting block 4111, and connecting block 4111 slides and sets up in connecting groove 412, is provided with reset spring 413 in the sleeve 41, and the one end of reset spring 413 and the inner wall butt of sleeve 41, the other end and connecting rod 411 butt, and be used for promoting connecting rod 411 to keeping away from sleeve 41 direction motion.
After the limiting block 34 levels the plate, the mounting frame 4 is driven to move downwards through the first air cylinder, the top plate 42 is contacted with the surface of the plate, the mounting frame 4 is continuously driven to move downwards, the limiting block 34 gradually slides towards the limiting groove 33 through the inclined plane on the limiting block 34, and the plate is ejected out of the material box 3; in addition, in the ejection process of the plate, the pressure spring 37 pushes the limiting block 34 to always abut against the side edge of the plate, so that the plate can slide down more stably.
Referring to fig. 6 and 7, a fixing member 43 for fixing the plate on the framework is arranged on the mounting frame 4, the fixing member 43 includes a screw, a nail barrel 44 is fixedly arranged on the mounting frame 4, the nail barrel 44 penetrates through the mounting frame 4, the axial direction of the nail barrel 44 is parallel to the axial direction of the sleeve 41, openings at two ends of the nail barrel 44 are arranged, a nail inlet 441 communicated with the inside of the nail barrel 44 is formed in the side wall of the nail barrel 44, the top wall of the nail barrel 44 is formed in the nail inlet 441, a nail storage box 45 is connected to the side wall of the nail barrel 44, the screw is stored in the nail storage box 45, and a nail outlet 451 communicated with the nail inlet 441 on the nail barrel 44 is formed in the side wall of the nail storage box 45.
Referring to fig. 7, a clamping assembly 5 for clamping a screw is arranged in the nail barrel 44, the clamping assembly 5 includes a top bead 51 and a first elastic member 52, two placing grooves 442 are formed in the inner wall of the nail barrel 44 along the axial direction perpendicular to the nail barrel 44, the two placing grooves 442 are respectively arranged on two sides of the nail inlet 441 and symmetrically arranged along the central axis of the nail barrel 44, and the top bead 51 is arranged in each of the two placing grooves 442 in a sliding manner.
Referring to fig. 7, a first limiting member for preventing the top bead 51 from being separated from the placement groove 442 is disposed in the placement groove 442, the first limiting member includes a blocking plate 443, the blocking plate 443 is welded at a notch end of the placement groove 442, a through hole 4431 is formed in the blocking plate 443, the diameter of the through hole 4431 is smaller than that of the top bead 51, and a portion of the top bead 51 can slide into the nail barrel 44 through the through hole 4431; the first elastic member 52 includes a first spring, one end of which abuts against the bottom wall of the placement groove 442 and the other end of which abuts against the top bead 51; the width of the screw head is generally larger than the rest of the screw, and the screw enters the nail barrel 44 and then is clamped by the top bead 51, so that the screw is prevented from falling out of the nail barrel 44 under the condition of no external force.
Referring to fig. 6 and 7, the mounting blocks 452 are fixedly arranged on the side wall of the nail storage box 45 and on both sides of the nail outlet 451, the fixing blocks 444 are fixedly arranged on the side wall of the nail barrel 44 and on both sides of the nail inlet 441, mounting grooves 4441 are respectively formed in the fixing blocks 444 at ends close to each other along the axial direction of the nail barrel 44, the mounting grooves 4441 penetrate through the top walls of the fixing blocks 444, and the mounting grooves 4441 are used for the mounting blocks 452 to insert; the nail storage box 45 can be arranged on the nail barrel 44 by inserting the mounting block 452 into the mounting groove 4441 on the fixing block 444, and the nail outlet 451 on the nail storage box 45 is communicated with the nail inlet 441 on the nail barrel 44, so that the nail storage box 45 can be arranged on the nail barrel 44; after the screws in the nail storage box 45 are used up, the nail storage box 45 can be detached by sliding the upper nail storage box 45, so that new screws can be conveniently supplemented into the nail storage box 45.
Referring to fig. 6, a first positioning plate 453 and a second positioning plate 454 are welded in the nail storage box 45, the first positioning plate 453 and the second positioning plate 454 are respectively arranged on two opposite side walls of the nail storage box 45, the first positioning plate 453 is parallel to the second positioning plate 454, the first positioning plate 453 and the second positioning plate 454 are arranged at intervals, a plurality of screws are arranged between the first positioning plate 453 and the second positioning plate 454, the nail outlet 451 is arranged at one side of the first positioning plate 453 and the second positioning plate 454 and is located at the interval between the first positioning plate 453 and the second positioning plate 454.
Referring to fig. 6, a feeding assembly 6 for feeding screws into the nail barrel 44 is arranged in the nail storage box 45, the feeding assembly 6 includes a push plate 61 and a second elastic member 62, the push plate 61 is slidably arranged at a space between the first positioning plate 453 and the second positioning plate 454, the second elastic member 62 includes a second spring, one end of the second spring is welded to an inner side wall of the nail storage box 45 far away from the nail outlet 451, and the other end of the second spring is welded to the top plate 42; the push plate 61 is driven by the second spring to slide towards the direction close to the nail outlet 451, so that the screws are pushed into the nail barrel 44 from the nail outlet 451 of the nail storage box 45, when the nails are arranged in the nail barrel 44, the adjacent screws are positioned in the nail storage box 45 and always have the tendency of sliding towards the nail barrel 44, and after the screws in the nail barrel 44 are completely separated, new screws are continuously fed into the nail barrel 44 under the action of the elastic force of the second spring.
Referring to fig. 6, the mounting frame 4 is further provided with a driving assembly 7 for screwing screws into the plate and fixing the plate on the framework, a screwdriver bit 71, a driving source 72 and a second driving piece 73 of the driving assembly 7, the mounting frame 4 is welded with a fixing frame 46, a mounting sleeve 47 is arranged on the fixing frame 46 in a sliding manner along the axial direction of the nail barrel 44, the mounting sleeve 47 is opposite to the nail barrel 44, the screwdriver bit 71 is coaxially and rotatably arranged in the mounting sleeve 47, the driving source 72 comprises a driving motor, the driving motor is welded on the top wall of the mounting sleeve 47, and an output shaft of the driving motor is coaxially welded with the screwdriver bit 71; the second drive element 73 comprises a second cylinder welded to the mounting frame 4, the piston rod of which is welded to the mounting sleeve 47.
When the plate and the framework need to be fixed, the nail barrel 44 is enabled to be abutted against the surface of the plate, then the second air cylinder is started to drive the mounting sleeve 47 to slide and drive the screwdriver bit 71 to be inserted into the nail barrel 44, the screwdriver bit 71 is enabled to be inserted into the tightening groove on the head of the screw, the driving motor is started to drive the screwdriver bit 71 to rotate and drive the screwdriver bit 71 to rotate, meanwhile, the second air cylinder slowly drives the mounting sleeve 47 to move downwards, so that the screw is screwed into the plate, and the plate is enabled to be fixed on the framework; during the manufacturing of the plate, a hole for inserting a screw can be formed in the plate, so that the later installation of the screw is facilitated.
The implementation principle of the quick installation equipment of bamboo-wood floor for embankment engineering of the embodiment of the application is as follows: during the use, the skeleton is fixed at the mounted position on bamboo-wood floor, remove frame 1 to the mounted position department on bamboo-wood floor, erect on the skeleton through four supports 12, and make gyro wheel 11 support the upper surface of tight skeleton, place the panel on bamboo-wood floor in sheet material storehouse 2, and promote frame 1 and slide on the skeleton, after frame 1 removes the certain distance, start and drive actuating cylinder and go out panel from connector 21 of board storehouse 2 and push out to ejection of compact case 3 in, start first cylinder, ejecting ejection of compact case 3 with panel through roof 42, and carry panel to the skeleton on.
After the plate is conveyed to the framework, the first air cylinder continues to push the mounting frame 4 to slide, so that the screw cylinder 44 is abutted against the surface of the plate, then the second air cylinder is started to drive the mounting sleeve 47 to slide and drive the screwdriver bit 71 to be inserted into the screw cylinder 44, the screwdriver bit 71 is inserted into the screwing groove in the head of the screw, the driving motor is started to drive the screwdriver bit 71 to rotate and drive the screwdriver bit 71 to rotate, meanwhile, the second air cylinder slowly drives the mounting sleeve 47 to move downwards, so that the screw is screwed into the plate, and the plate is fixed on the framework; afterwards, make frame 1 remove to next node through the moving member, continue to install the panel, whole installation, convenient and fast has improved bamboo-wood floor's installation effectiveness greatly.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (10)

1. The utility model provides a dyke engineering is with quick erection equipment of bamboo-wood floor which characterized in that: the plate pushing device comprises a rack (1), wherein a moving member used for facilitating the movement of the rack (1) is arranged on the rack (1), a plate bin (2) and a discharge box (3) are fixedly arranged on the rack (1), a connecting port (21) communicated with the discharge box (3) is formed in the inner side wall of the plate bin (2), the connecting port (21) is used for allowing plates to pass through, an opening is formed in the bottom wall of the discharge box (3), and a pushing member (13) used for pushing the plates in the plate bin (2) to the discharge box (3) is arranged on the rack (1); an installation frame (4) is arranged in the discharge box (3) in a sliding manner along the length direction of the discharge box (3), a first driving piece (38) for driving the installation frame (4) to slide is arranged on the discharge box (3), a fixing piece (43) is arranged on the installation frame (4), and the fixing piece (43) is used for fixing the plate on the framework; still be provided with drive assembly (7) on mounting bracket (4), drive assembly (7) are used for driving about mounting (43) and fix panel on the skeleton.
2. The quick installation apparatus of bamboo floor for embankment engineering according to claim 1, characterized in that: the moving member includes gyro wheel (11), the bottom of frame (1) is rotated and is provided with a plurality of supports (12), just support (12) are used for erectting on the skeleton, every all rotate on support (12) and be provided with gyro wheel (11), just gyro wheel (11) are used for supporting the surface of skeleton tightly.
3. The quick installation apparatus of bamboo floor for embankment engineering according to claim 1, characterized in that: the fixing piece (43) comprises screws, a screw cylinder (44) is fixedly arranged on the mounting rack (4), two end openings of the screw cylinder (44) are arranged, a screw storage box (45) is connected to the screw cylinder (44), screws are stored in the screw storage box (45), a feeding assembly (6) used for conveying the screws into the screw cylinder (44) is arranged in the screw storage box (45), a clamping assembly (5) used for clamping the screws is arranged in the screw cylinder (44), and the driving assembly (7) is used for screwing the screws into the plates and fixing the plates on the framework.
4. The quick installation equipment of bamboo-wood floor for embankment engineering according to claim 3, characterized in that: the clamping assembly (5) comprises a top bead (51) and a first elastic piece (52), a placing groove (442) is formed in the inner wall of the nail barrel (44) along the axial direction perpendicular to the nail barrel (44), the top bead (51) is arranged in the placing groove (442) in a sliding mode, the first elastic piece (52) is used for driving the top bead (51) to move towards the direction away from the bottom wall of the placing groove (442), and a first limiting piece used for preventing the top bead (51) from being separated from the placing groove (442) is arranged in the placing groove (442).
5. The quick installation apparatus of bamboo floor for embankment engineering according to claim 3, wherein: the feeding assembly (6) comprises a push plate (61) and a second elastic piece (62), the push plate (61) is arranged in the nail storage box (45) in a sliding mode, a nail outlet (451) is formed in the side wall of the nail storage box (45), a nail inlet (441) used for allowing a screw to enter is formed in the side wall of the nail barrel (44), the nail outlet (451) is communicated with the nail inlet (441), and the second elastic piece (62) is used for driving the push plate (61) to slide towards the direction close to the nail outlet (451).
6. The quick installation apparatus of bamboo floor for embankment engineering according to claim 5, wherein: the nail storage box (45) is detachably connected with the nail barrel (44).
7. The quick installation device of bamboo-wood floors for embankment engineering according to claim 6, characterized in that: the lateral wall of storing up nail box (45) and the both sides that are located nail mouth (451) all fixedly are provided with installation piece (452), the lateral wall of nail section of thick bamboo (44) and the both sides that are located into nail mouth (441) are fixed and are provided with fixed block (444), two mounting groove (4441) have all been seted up along the axial of nail section of thick bamboo (44) to the one end that is close to each other on fixed block (444), just mounting groove (4441) are used for supplying installation piece (452) to insert.
8. The quick installation apparatus of bamboo floor for embankment engineering according to claim 3, wherein: drive assembly (7) include screwdriver bit (71), driving source (72) and second driving piece (73), the axial slip of following a nail section of thick bamboo (44) on mounting bracket (4) is provided with installation sleeve (47), just installation sleeve (47) are just right with a nail section of thick bamboo (44), screwdriver bit (71) coaxial rotation sets up in installation sleeve (47), driving source (72) set up on installation sleeve (47) and are used for driving screwdriver bit (71) to rotate, second driving piece (73) are used for driving installation sleeve (47) and slide and drive screwdriver bit (71) and insert in a nail section of thick bamboo (44).
9. The quick installation equipment of bamboo-wood floor for embankment engineering according to claim 1, characterized in that: all seted up spacing groove (33) in ejection of compact case (3) and on being located two opposite side lateral walls of ejection of compact case (3), spacing groove (33) are seted up between the open end and connector (21) of ejection of compact case (3), two equal slip is provided with stopper (34), two in spacing groove (33 the up end of stopper (34) flushes, two the slip direction of stopper (34) is close to each other or keeps away from, be provided with in ejection of compact case (3) and be used for ordering about the gliding third driving piece of stopper (34).
10. The rapid installation apparatus of bamboo floor for embankment engineering according to claim 9, wherein: the third driving piece comprises a pressure spring (37), the pressure spring (37) is arranged in a limiting groove (33), one end of the pressure spring (37) is abutted against the bottom wall of the limiting groove (33), the other end of the pressure spring is abutted against a limiting block (34), a second limiting part used for preventing the limiting block (34) from being separated from the limiting groove (33) is arranged in the limiting groove (33), one end, far away from the bottom wall of the limiting groove (33), of the limiting block (34) is gradually far away from the bottom wall of the limiting groove (33) along the direction of the top wall of the discharging box (3), and a jacking piece used for jacking plates in the discharging box (3) is arranged on the mounting frame (4).
CN202210321522.6A 2022-03-30 2022-03-30 Dyke engineering is with quick erection equipment of bamboo-wood floor Active CN114704059B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210321522.6A CN114704059B (en) 2022-03-30 2022-03-30 Dyke engineering is with quick erection equipment of bamboo-wood floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210321522.6A CN114704059B (en) 2022-03-30 2022-03-30 Dyke engineering is with quick erection equipment of bamboo-wood floor

Publications (2)

Publication Number Publication Date
CN114704059A true CN114704059A (en) 2022-07-05
CN114704059B CN114704059B (en) 2023-02-10

Family

ID=82170681

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210321522.6A Active CN114704059B (en) 2022-03-30 2022-03-30 Dyke engineering is with quick erection equipment of bamboo-wood floor

Country Status (1)

Country Link
CN (1) CN114704059B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011093030A (en) * 2009-10-28 2011-05-12 Isamu Kataoka Mounting tool for plate material
CN203701542U (en) * 2013-12-08 2014-07-09 湖南长笛龙吟竹业有限公司 Quick mounting mechanism of bamboo-wood floor
CN207749804U (en) * 2017-10-26 2018-08-21 浙江荣鹏气动工具有限公司 A kind of bamboo-wood floor nail gun
CN210232908U (en) * 2019-05-15 2020-04-03 汤积洪 Nailing machine with automatic nail feeding function
CN111749445A (en) * 2020-07-09 2020-10-09 张美� Construction process for paving plastic wood material on ground
CN112252688A (en) * 2020-10-23 2021-01-22 温州根旭电子科技有限公司 Automatic laying device for anti-static raised floor
CN213329914U (en) * 2020-06-29 2021-06-01 苏州苏明装饰股份有限公司 Outdoor wood floor mounting structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011093030A (en) * 2009-10-28 2011-05-12 Isamu Kataoka Mounting tool for plate material
CN203701542U (en) * 2013-12-08 2014-07-09 湖南长笛龙吟竹业有限公司 Quick mounting mechanism of bamboo-wood floor
CN207749804U (en) * 2017-10-26 2018-08-21 浙江荣鹏气动工具有限公司 A kind of bamboo-wood floor nail gun
CN210232908U (en) * 2019-05-15 2020-04-03 汤积洪 Nailing machine with automatic nail feeding function
CN213329914U (en) * 2020-06-29 2021-06-01 苏州苏明装饰股份有限公司 Outdoor wood floor mounting structure
CN111749445A (en) * 2020-07-09 2020-10-09 张美� Construction process for paving plastic wood material on ground
CN112252688A (en) * 2020-10-23 2021-01-22 温州根旭电子科技有限公司 Automatic laying device for anti-static raised floor

Also Published As

Publication number Publication date
CN114704059B (en) 2023-02-10

Similar Documents

Publication Publication Date Title
CN111729996B (en) Steel bar batch bending machine and bending method
CN212053668U (en) Disk buckle type external scaffold
CN210121758U (en) Automatic assembling machine for bolt and nut
US20140021236A1 (en) Installation Tool for Universal Fastener
CN114704059B (en) Dyke engineering is with quick erection equipment of bamboo-wood floor
CN210209551U (en) Full-automatic corner brace sawing machine for aluminum alloy energy-saving fireproof window
SE514582C2 (en) Tray for screws
CN2761374Y (en) Accessory box-assembly
CN213418141U (en) Indoor sound inorganic fossil fragments combination formula partition wall structure of inhaling of customization hardcover space
CN108914395A (en) A kind of automatic feeding of button-sewing machine
US11969839B2 (en) Mobile fastener machine platform
TWI478790B (en) A magazine for use with a nail driving tool
CN214329449U (en) Light gauge steel partition wall structure of quick installation
CN110103009B (en) Building steel chain riveting split equipment
CN114687504A (en) Assembled special-shaped curved surface aluminum plate ceiling and mounting method
CN212026583U (en) Mounting structure of bracket in ancient building
CN217990135U (en) Prefabricated plate steel bar bender of assembled building
CN216340700U (en) Quick processingequipment in negative and positive angle
US6401772B1 (en) System and method for forming dovetail joints
CN216787718U (en) Modularization installed part of wood link plate
CN216939338U (en) Quick pre-locking screw mechanism
CN217514244U (en) Concrete aggregate bin
CN211192809U (en) Nut and screw automatic assembly mechanism and filter panel assembly equipment
CN220297372U (en) Lath frame pressing machine
CN207273591U (en) A kind of concrete wall cutter device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant