CN114673356A - BIM technology-based infilled wall masonry complex pipeline alternate reverse construction method - Google Patents

BIM technology-based infilled wall masonry complex pipeline alternate reverse construction method Download PDF

Info

Publication number
CN114673356A
CN114673356A CN202210516889.3A CN202210516889A CN114673356A CN 114673356 A CN114673356 A CN 114673356A CN 202210516889 A CN202210516889 A CN 202210516889A CN 114673356 A CN114673356 A CN 114673356A
Authority
CN
China
Prior art keywords
pipeline
construction
masonry
lining
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210516889.3A
Other languages
Chinese (zh)
Other versions
CN114673356B (en
Inventor
范正波
吴鑫
李佳林
张波
张雷
高恒
任昭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Bureau Third Construction Co Ltd
Original Assignee
China Construction Fifth Bureau Third Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Bureau Third Construction Co Ltd filed Critical China Construction Fifth Bureau Third Construction Co Ltd
Priority to CN202210516889.3A priority Critical patent/CN114673356B/en
Publication of CN114673356A publication Critical patent/CN114673356A/en
Application granted granted Critical
Publication of CN114673356B publication Critical patent/CN114673356B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2113/00Details relating to the application field
    • G06F2113/14Pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Architecture (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Geometry (AREA)
  • Marketing (AREA)
  • Computer Hardware Design (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Civil Engineering (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Structural Engineering (AREA)
  • Computational Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Mathematical Optimization (AREA)
  • Educational Administration (AREA)
  • Mathematical Analysis (AREA)
  • Game Theory and Decision Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Operations Research (AREA)
  • Development Economics (AREA)
  • Evolutionary Computation (AREA)
  • Pure & Applied Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Sewage (AREA)
  • Retaining Walls (AREA)

Abstract

The invention discloses a BIM technology-based complex pipeline interpenetration reverse construction method for a filler wall masonry, which comprises the following steps: A. building a BIM model B, constructing a pipeline C, deeply typesetting a masonry D and constructing the masonry. According to the BIM technology-based complex pipeline insertion reverse construction method for the filler wall masonry, collision detection is carried out on the pipeline direction, the elevation and the masonry position through the BIM technology, conflict points are found in advance, the position and the elevation are adjusted and then are constructed in advance by an electromechanical specialty, the pipeline construction is carried out on the masonry after the pipeline construction is finished, and subsequent equipment and debugging construction are carried out after the civil construction is finished by inserting again. The defects of wall damage, repeated transfer of a working face, slow insertion of subsequent decoration and fitment and the like caused by the traditional method are effectively overcome, the construction safety is ensured, and a large number of construction periods are saved.

Description

BIM technology-based infilled wall masonry complex pipeline interpenetration reverse construction method
Technical Field
The invention relates to the field of building construction, in particular to a complex pipeline interpenetration reverse construction method for a filler wall masonry based on a BIM technology.
Background
With the gradual advance of the construction industry to the general contract management mode, the professional alternation and matching of construction projects are more and more compact, and the process alternation between the secondary structure and the electromechanical construction also frequently appears in each construction project.
In the process of alternating construction of an electromechanical and secondary structure, a reserved hole is often required to be arranged according to the direction of a pipeline during secondary structure construction, but due to the complexity of the pipeline in the electromechanical profession and the difference of the profession, the problem of misplacement or omission occurs in the reserved process very easily during secondary structure construction. So, then need again according to the pipeline trend after secondary structure construction completion open the hole construction on secondary structure brickwork, wait to carry out the repair binding off once more after the electric pipeline construction of standby completes.
On one hand, the method prolongs the construction period, the working face handover times are more, the procedures are complicated, and the cost waste of the construction period is larger; on the other hand, the opening of the masonry causes the increase of the workload and the increase of the danger of safe civilized construction in the floor, and the operation space for opening and repairing the worker during the ascending operation is difficult to ensure.
Therefore, a construction method is needed to solve the above problems in the electromechanical construction and the secondary structure insertion construction process in the prior art.
Disclosure of Invention
The invention aims to: aiming at the problems that in the prior art, in the process of alternate construction of electromechanical and secondary structures, due to the complexity and professional difference of pipelines in electromechanical specialties, the secondary structure is easy to leave by mistake or leave by mistake in the reservation process during construction, so that the construction period and the cost are wasted, and the like, the complex pipeline alternate reverse construction method for the filler wall masonry based on the BIM technology is provided.
In order to achieve the purpose, the invention adopts the technical scheme that:
a filler wall masonry complex pipeline interpenetration reverse construction method based on a BIM technology comprises the following steps:
A. building a BIM model: establishing a three-dimensional building model according to a building construction drawing and an electromechanical construction drawing, and optimizing and adjusting the arrangement of pipelines according to the established model;
B. pipeline construction: b, generating a pipeline layout according to the BIM established in the step A, and performing pipeline construction after the site constructors are handed over;
C. deeply typesetting the masonry: b, typesetting the masonry wall and generating a masonry layout according to the BIM established in the step A and the actual trend of the pipeline after the pipeline construction in the step B is completed;
D. and (3) masonry construction: and C, according to the masonry layout generated in the step C, performing masonry wall construction after the site constructors meet the bottom.
Preferably, different layers are correspondingly established according to different functions of the pipeline when the pipeline model is established in the step a.
Preferably, naming rules for the different functional pipelines and the components of the different functional pipelines are established.
Preferably, the trend of the pipeline during construction is established, and all the components of the pipeline are numbered in sequence according to the established trend.
Preferably, according to the trend of pipeline construction, a plurality of running water construction sections are divided, and the boundary between the adjacent running water construction sections is determined.
Preferably, the dimensions of the components of the pipeline are noted, as well as the relative dimensions between the components of the pipeline and the building body.
Preferably, the pipeline construction sequence of the step B is bracket erection, main pipe erection, branch pipe erection and cable erection.
Preferably, when the main pipe is erected and the branch pipe is erected, the pipeline close to the wall and/or the beam is constructed firstly, and then the pipeline far away from the wall and/or the beam is constructed; the upper layer pipeline is constructed firstly, and then the lower layer pipeline is constructed.
Preferably, the wall bushing is arranged at a position crossing the main structure when the branch pipe is erected.
Preferably, the wall bushing comprises a bushing body and a bushing lining, the bushing lining surrounds the inner wall of the bushing body and forms an internal cavity structure, the bushing lining is made of flexible materials, the branch pipe penetrates into the wall bushing, and the bushing lining covers the branch pipe to prevent the branch pipe from contacting with the bushing body.
Preferably, the end of the casing liner is disposed at a distance from the end of the casing body.
Preferably, the thickness of the bottom of the sleeve liner is greater than the thickness of the top.
Preferably, the sleeve liner includes a first liner portion, a second liner portion and a third liner portion, the second liner portion is disposed between the first liner portion and the third liner portion, an elastic deformation coefficient of the second liner portion is smaller than those of the first liner portion and the third liner portion, and a length of the second liner portion is greater than those of the first liner portion and the third liner portion.
Preferably, the diameter of the second liner portion cavity is smaller than the diameter of the first and third liner portion cavities.
Preferably, the second lining portion is provided apart from the first lining portion and the third lining portion.
Preferably, the wall bushing is plugged after the branch pipe is erected.
Preferably, the pressure test experiment of the pipeline is carried out after the erection of the main pipe and the branch pipe is finished.
Preferably, the erection of the cable is carried out after the pressure test experiment is qualified.
Preferably, the masonry row layout generated in the step C is to clearly determine the size and the quantity of the building blocks, the position of the pipeline hole and the specific size.
In summary, due to the adoption of the technical scheme, the invention has the beneficial effects that:
1. according to the BIM technology-based complex pipeline insertion reverse construction method for the filler wall masonry, collision detection is carried out on the pipeline direction, the elevation and the masonry position through the BIM technology, conflict points are found in advance, the position and the elevation are adjusted and then are constructed in advance by an electromechanical specialty, the pipeline construction is carried out on the masonry after the pipeline construction is finished, and subsequent equipment and debugging construction are carried out after the civil construction is finished by inserting again. The defects of wall damage, repeated transfer of a working surface, slow insertion of subsequent decoration and fitment and the like caused by the traditional method are effectively overcome, the construction safety is ensured, and a large amount of construction period is saved;
2. the invention relates to a BIM technology-based complex pipeline insertion reverse construction method for a filler wall masonry. The branch pipe body is directly contacted with the concrete structure in the mode of erecting the branch pipe by passing through the main body structure, so that the damage of the branch pipe body is avoided, secondary construction caused by unqualified quality in the process of erecting the branch pipe is avoided, and the construction period is further shortened. Meanwhile, after the arrangement, the service life of the branch pipe is prolonged to a certain extent, and the running stability of a pipeline system is improved;
3. the invention relates to a BIM technology-based infilled wall masonry complex pipeline insertion reverse construction method, wherein the elastic deformation coefficient of a second lining part material is set to be smaller than the elastic deformation coefficients of a first lining part and a third lining part, and the length of the second lining part is larger than the length of the first lining part and the length of the third lining part. The part of the branch pipe or the sleeve body, which applies pressure to the building main body, is transferred to the middle part of the main structure through which the branch pipe passes by reinforcing the limiting force of the second lining part on the branch pipe, so that the force is effectively prevented from being transmitted to the end part of the main structure through which the branch pipe passes by the branch pipe or the sleeve body, and the acting force transmitted to the main structure can be effectively offset at the middle part of the main structure through which the branch pipe passes by the main structure due to the large contact area with the sleeve body and the high structural strength of the main structure, so that the building main body is effectively prevented from being damaged, and the later maintenance cost is further reduced;
4. according to the filler wall masonry complex pipeline insertion reverse construction method based on the BIM technology, the diameter of the cavity of the second lining portion is smaller than the diameter of the cavities of the first lining portion and the third lining portion. By adopting the structure, the limiting force of the second lining part on the branch pipe is further improved, so that the branch pipe or the sleeve body can better transmit the force to the middle position of the branch pipe passing through the main body structure, the building main body is effectively prevented from being damaged, and the later maintenance cost is further reduced;
5. according to the invention, the second lining part, the first lining part and the third lining part are arranged in a disconnected mode. The second lining portion is separated from the first lining portion and the third lining portion by actively arranging the gap on the sleeve liner, so that the situation that uncontrollable cracking occurs at the joint of the second lining portion and the first lining portion and the third lining portion is effectively avoided, and the reliability of the wall bushing in practical application is improved.
Drawings
FIG. 1 is a schematic flow chart of a complex pipeline insertion reverse construction method for a filler wall masonry based on a BIM technology;
FIG. 2 is a schematic structural view of a wall bushing;
FIG. 3 is a schematic cross-sectional view of a wall bushing;
fig. 4 is a side view of a wall bushing.
The mark in the figure is: 1-a wall bushing, 2-a bushing body, 3-a bushing inner liner, 4-a first inner liner portion, 5-a second inner liner portion, 6-a third inner liner portion.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Example 1
As shown in fig. 1 to 4, the complicated pipe threading reverse construction method for filler wall masonry based on the BIM technique of the present invention includes the following steps:
A. building a BIM model: establishing a three-dimensional building model according to a building construction drawing and an electromechanical construction drawing, and optimizing and adjusting the arrangement of pipelines according to the established model;
B. pipeline construction: b, generating a pipeline layout according to the BIM established in the step A, and performing pipeline construction after the site constructors are handed over;
C. deeply typesetting the masonry: b, typesetting the masonry wall and generating a masonry row layout according to the BIM established in the step A and the actual trend of the pipeline after the pipeline construction in the step B is completed;
D. and (3) masonry construction: and C, according to the masonry layout generated in the step C, performing masonry wall construction after the site constructors meet the bottom.
By adopting the BIM technology-based complex pipeline interpenetration reverse construction method for the filler wall masonry, disclosed by the invention, collision detection is carried out on the pipeline trend, the elevation and the masonry position through the BIM technology, conflict points are found in advance, the position and the elevation are adjusted and then are constructed by an electromechanical specialty in advance, the pipeline construction is handed over to the masonry for construction, and after the civil construction is completed, subsequent equipment is inserted again for debugging and construction. The defects of wall damage, repeated transfer of a working face, slow insertion of subsequent decoration and fitment and the like caused by the traditional method are effectively overcome, the construction safety is ensured, and a large number of construction periods are saved.
Specifically, the method comprises the steps of performing collision detection on the direction, the elevation and the position of a masonry by using CAD (computer-aided design) and Revit software, finding a conflict point in advance, performing advanced construction by electromechanical specialties after the position and the elevation are adjusted, performing support and main pipeline construction according to procedures, reserving the length of an interface when the construction is carried out to the position of end equipment, performing masonry construction after the pipeline construction is finished, and inserting subsequent equipment and debugging construction again after the civil construction is finished.
After the electromechanical construction is completed, the masonry is typeset according to the trend and the elevation of a field pipeline, the positions of ring beams, lintels and constructional columns are reasonably arranged by combining the relevant specifications of the masonry, a manager carries out bottom crossing on field operators according to the masonry layout, and the position of a pipeline opening can be constructed at one time. By adopting the construction method, on one hand, the defects of wall damage, repeated transfer of working surfaces, slow insertion of subsequent decoration and fitment and the like caused by the traditional method are effectively overcome, the construction safety is ensured, and a large number of construction periods are saved. On the other hand, the problems that in a traditional construction method, due to the fact that masonry is constructed in advance, an electromechanical construction operation surface is small, and installation quality cannot be guaranteed are well solved, the construction period is saved, and meanwhile construction quality is guaranteed.
Example 2
As shown in fig. 1 to 4, based on the above manner, in the complicated pipeline insertion reverse construction method for filler wall masonry based on the BIM technique, further, different layers are correspondingly established according to different functions of the pipeline when the pipeline model is established in the step a.
Specifically, in this embodiment, different layers are correspondingly established according to different functions of the pipeline. On one hand, the pipeline arrangement on a certain layer can be quickly checked, and the interference of other incoherent models is avoided. On the other hand, the graph files can be managed to be drawn conveniently, each graph layer can be opened or closed independently, and therefore the problem that output pipeline layout is disordered due to mutual interference among different pipelines in the process of drawing can be avoided.
In a preferred embodiment, in addition to the above-mentioned manner, naming rules of different functional pipelines and components of different functional pipelines are further established. By adopting the method, the operations of retrieval, modification, statistics and the like of each pipeline component in the BIM model are facilitated, the connection from the BIM model to the site construction is more compact, and the construction period is further saved.
In the pipeline construction, the construction characteristics of abnormal and complex pipelines and high difficulty in comprehensive arrangement of multi-professional pipelines exist, and corresponding naming rules are not established when the BIM model is established, so that great troubles are brought to modification of the BIM model and data retrieval in the later construction process. The naming of the pipeline in this embodiment can adopt a classification coding mode to customize a plurality of key fields for later query and statistics. For example, the naming rule of the water pipe may include fields such as type name, type, material, pipe diameter, etc., and may further include fields such as pipe thickness, special description, etc.
In a preferred embodiment, in addition to the above-mentioned mode, a building direction of the pipeline is established, and each component of the pipeline is numbered in sequence according to the building direction.
Specifically, the trend of putting up of pipeline can be established according to the direction of liquid flow in the pipeline in this embodiment, and perhaps the direction of reverse flow is established, and the serial number adopts digital coding, and it can to each component numbering of pipeline in proper order according to the trend of putting up established. During the processing process in the production of the pipeline, the identification of the corresponding product is made according to the code in the BIM model.
In the embodiment, the inventor considers that in the actual construction of the pipeline, the number of the components of the pipeline is large, the structural form is various, and workers are difficult to work clearly and orderly when installing the pipeline. Therefore, when the worker installs, the worker finds the products corresponding to the codes according to the codes in the BIM model and installs the products in sequence. By adopting the method, the working efficiency of workers during the construction and installation of the pipeline is improved, and the construction period is further saved.
In a preferred embodiment, in addition to the above-mentioned method, a plurality of running water construction sections are further divided according to the trend of pipeline construction, and boundaries between adjacent running water construction sections are defined. By adopting the method, a plurality of construction teams can simultaneously enter the field for construction during the installation of the pipeline, thereby saving the construction time of pipeline installation and further saving the construction period.
In addition to the above-described modes, the dimensions of the components of the pipeline and the relative dimensions between the components of the pipeline and the building main body are further marked as preferred embodiments. By adopting the method, the positioning of the installation position of the pipeline is convenient for workers during construction, so that the construction period is further saved.
Example 3
As shown in fig. 1 to 4, the complex pipeline insertion reverse construction method for the filler wall masonry based on the BIM technology of the present invention further includes the steps of B, sequentially erecting a support, erecting a main pipe, erecting a branch pipe and erecting a cable.
The construction sequence of the first trunk and the second branch in the pipeline road can make the completed part of the project play a role rapidly. If the construction of branch and pipeline roads is carried out first, the pipeline roads can not play the engineering benefit because the pipeline roads are not communicated with the main pipe, the main line and the main road, the water supply of the upper water channel can not be realized, the water of the sewer can not be discharged, the gas, the steam and the electric power can not be obtained, and the roads can not be fully utilized. The construction of pipeline roadworks entails first completing the trunk, the road gradually passing from the junction with the adjacent trunk to the site.
The support frame is specifically as follows:
1. after the construction of the main structure is completed, the floor is positioned by paying off according to the bottom-crossing content, the position of the floor line of one meter and the position of the wall body are determined, and the support is positioned on site.
2. The support and hanger frame is processed in a processing plant, numbers in the BIM model are corresponded, corresponding numbers are carried out on each auxiliary support, the welding forming quality of the support is ensured, the welding seam is full, no quality defect exists, and galvanizing treatment is carried out after welding.
3. Transport finished product support to construction floor, according to the unwrapping wire position, with the support mounting that corresponds the serial number on the position, after the construction is accomplished, carry out the retest of support, guarantee the in bank line of support, the pipeline guarantee pipeline that needs the slope of putting has the correct slope along the rivers direction.
The main pipe frame is specifically as follows:
1. and according to the BIM model and the floor construction conditions, correspondingly cutting and processing the pipeline in a factory, and determining a reasonable transportation mode.
2. The size of the pipeline is larger than 100mm, groove treatment is carried out, corrosion and rust removal are completed in a processing plant in advance, the small air pipe enters the processing plant after assembly is completed, and the air pipe with the size larger than 630mm is assembled on site by adopting a semi-finished product.
3. And constructing the main pipe corresponding to the direction of the bottom crossing pipeline, constructing layer by layer from top to bottom, reserving a tee joint position on the main pipe, verifying the elevation, and performing real-time comparison between the model and the site.
The branch frame comprises the following concrete components:
1. and after the construction of the main pipe is finished, installing the branch pipe, and reserving the length of the equipment connecting pipe from the construction of the branch pipe to the tail end.
2. The wall bushing 1 is arranged at the wall penetrating position of the branch pipe, and primary plugging of the bushing is performed, so that the influence of displacement on the bushing during later-stage masonry construction is avoided.
3. The positions of the masonry and the structure construction are influenced, reservation is carried out, and the sleeve is embedded along with the masonry.
4. A drain valve for pressure test is reserved at the tail end of the branch pipe.
5. And after the pipeline construction is finished, protecting the finished product of the pipeline.
The cable erection specifically is as follows:
1. and after the last procedure of civil engineering construction is finished, carrying out pressure test on a pipeline system, and then laying cables and carrying out heat preservation construction.
2. And (4) timely processing the water leakage position after pressure test, mainly checking the positions of the interface, the welding seam and the valve, and performing paint repair processing on the welding seam after no water leakage exists.
3. And after the cable laying and heat preservation construction is finished, transferring and fine-assembling.
As a preferred embodiment, in addition to the above-mentioned mode, further, when the main pipe is erected and the branch pipe is erected, the pipeline close to the wall and/or the beam is constructed firstly, and then the pipeline far away from the wall and/or the beam is constructed; the upper layer pipeline is constructed firstly, and then the lower layer pipeline is constructed. By adopting the method, the space used by the building during construction can be increased to the maximum extent, and secondary construction caused by pipeline conflict is reduced, so that the construction period is further saved.
In a preferred embodiment, in addition to the above-described embodiment, the wall bushing 1 is provided at a portion that passes through the main structure during the installation of the branch pipe.
In the embodiment, the inventor considers the erection mode that the branch pipe passes through the main structure, and the branch pipe is easy to rub against the main structure in the installation process, so that the branch pipe is damaged. And in later use, the pipe flutter due to the "water hammer effect" further exacerbates branch damage. In this respect, in the present embodiment, the inventor provided the wall bushing 1 at a portion crossing the main structure when installing the branch pipe. In the mode of avoiding such branch pipe erection, the branch pipe body directly contacts with the concrete structure, causes its own damage to avoided the branch pipe to erect because of the unqualified secondary construction of quality, further practiced thrift construction period again. Meanwhile, after the arrangement, the service life of the branch pipe is prolonged to a certain extent, and the operation stability of a pipeline system is improved.
In a preferred embodiment, in addition to the above-described embodiment, the wall bushing 1 is further subjected to a plugging treatment after the completion of the branch erection.
Specifically, the inventor in this embodiment considers that, in the process of installing the branch pipe, the installed branch pipe may shake, and if the wall bushing 1 is plugged along with the installation of the branch pipe, the shake generated in the installation process may cause the plugging failure of the wall bushing 1, so that a secondary rework situation may occur. In this embodiment, the wall bushing 1 is plugged after the branch pipe is erected. The problems are effectively avoided, and the construction period is further saved.
In a preferred embodiment, in addition to the above-described embodiment, a pressure test experiment of the pipeline is performed after the erection of the trunk pipe and the branch pipe is completed.
In a preferred embodiment, in addition to the above-described embodiment, the cable is erected after the pressure test is passed. By adopting the method, the cable is prevented from being damaged in the pressure test process of the pipeline, so that the pipeline is prevented from being reworked for the second time. Meanwhile, the cable is prevented from being reworked for the second time due to unqualified pipeline pressure test.
Example 4
As shown in fig. 1 to 4, based on the above manner, the wall bushing 1 according to the present invention includes a bushing body 2 and a bushing lining 3, the bushing lining 3 is disposed around an inner wall of the bushing body 2 and forms an internal cavity structure, the bushing lining 3 is made of a flexible material, a branch pipe penetrates into the wall bushing 1, and the bushing lining 3 covers the branch pipe to prevent the branch pipe from contacting the bushing body 2.
In this embodiment, the inventor considers that the pipe may have a "water hammer effect" due to sudden power failure or when the valve is closed too fast in later use, which may cause the branch pipe to shake. When the branch pipe shakes, the branch pipe may contact with the wall bushing 1 and transmit force to the building main body, so that the branch pipe itself or the building main body is damaged. Based on this, in this embodiment the inventor set up the sleeve inside lining 3 in the sleeve body 2, sleeve inside lining 3 adopts flexible material to make, can absorb the shake that the branch pipe produced, has avoided branch pipe contact wall bushing 1 to transmit power to the building main part to the stability after the operation of pipeline system has been improved.
In a preferred embodiment, in addition to the above, an end of the jacket lining 3 is provided at a distance from an end of the jacket main body 2.
In the above scheme, the inventor has avoided the branch pipe to contact with sleeve body 2 when producing the shake and transmit power to the main building body through setting up sleeve inside lining 3, causes the damage of branch pipe itself or the damage of main building body. Thereby improving the stability of the pipeline system after operation. However, the defects still exist, only for the branch pipe passing through the main structure part, when the 'water hammer effect' is generated, the shaking amplitude of the end part of the branch pipe in the shaking transmission process is often larger than that of the middle part of the branch pipe, and the situation that the end part of the branch pipe continuously impacts the wall bushing 1 occurs, and for the main structure of the area where the wall bushing 1 is arranged, the acting force transmitted by the wall bushing 1 just falls on the part with relatively weak structural strength, so that the part is easy to crack. Based on this, in the present embodiment, the inventors set the end of the jacket lining 3 at a distance from the end of the jacket body 2. Therefore, the acting force applied to the two sides of the end part of the building main body which is penetrated by the branch pipe or the sleeve pipe body 2 is weakened, so that the building main body is prevented from being damaged to the greatest extent, and the later maintenance cost is reduced.
In a preferred embodiment, in addition to the above manner, the thickness of the bottom of the casing liner 3 is larger than that of the top.
In the present embodiment, the inventor considers that the pipe branch itself has a certain mass, which may cause a certain compression on the casing lining 3, resulting in a reduced ability of the casing lining 3 to absorb pipe branch shaking, and particularly when the pipe branch is filled with liquid, the casing lining 3 compressed by the compression portion may be greatly deformed, and almost lose the ability to absorb pipe branch shaking. Also, and the inventors considered that the counter-force of the pipe branch in the presence of whipping is mainly concentrated at the bottom of the casing lining 3. In this embodiment, the inventors set the thickness of the bottom of the casing liner 3 to be greater than the thickness of the top. Through improving the ability that the shake of branch pipe is absorbed at 3 bottoms of sleeve pipe inside linings, overcome the oppression that the branch pipe caused to it to avoided branch pipe contact wall bushing 1 to transmit power for the building main part, further improved the stability after pipeline system's the operation.
In a preferred embodiment, in addition to the above aspect, the sleeve liner 3 further includes a first liner portion 4, a second liner portion 5, and a third liner portion 6, the second liner portion 5 is provided between the first liner portion 4 and the third liner portion 6, an elastic deformation coefficient of the second liner portion 5 is smaller than those of the first liner portion 4 and the third liner portion 6, and a length of the second liner portion 5 is larger than those of the first liner portion 4 and the third liner portion 6.
In the present embodiment, the inventor considered that in the above-described embodiment, the end of the jacket liner 3 is disposed at a distance from the end of the jacket body 2. The acting force applied to the two sides of the end part of the building main body which is penetrated by the branch pipe or the sleeve pipe body 2 is weakened, so that the building main body is prevented from being damaged to the greatest extent, and the later maintenance cost is reduced. However, there is still a disadvantage that in the above-described solution, when the branch pipe is shaken to a large extent, there is a case where the branch pipe or the socket body 2 presses both sides of the end portion of the building main body where it passes. In view of this, in the present embodiment, the elastic deformation coefficient of the second liner portion 5 is set smaller than the elastic deformation coefficients of the first liner portion 4 and the third liner portion 6, and the length of the second liner portion 5 is set larger than the lengths of the first liner portion 4 and the third liner portion 6. Through strengthening the restriction force of the second lining part 5 on the branch pipe, the part of the branch pipe or the sleeve pipe body 2 applying pressure to the building main body is transferred to the middle part of the main structure through which the branch pipe passes, so that the situation that the branch pipe or the sleeve pipe body 2 transmits the force to the end part of the branch pipe passing through the main structure is effectively avoided, and the middle part of the main structure is passed through by the branch pipe, because the contact area between the branch pipe or the sleeve pipe body 2 and the structure strength of the branch pipe is large and the structure strength of the branch pipe or the sleeve pipe body is high, the acting force transmitted to the branch pipe or the sleeve pipe body can be effectively offset, the building main body is effectively prevented from being damaged, and the later maintenance cost is further reduced.
In a preferred embodiment, in addition to the above-described embodiment, the diameter of the cavity of the second lining portion 5 is smaller than the diameter of the cavity of the first lining portion 4 and the third lining portion 6.
In this embodiment, the amount of ineffective deformation of the casing liner 3 can be effectively consumed by the pressing of the casing liner 3 by the branch pipe after the penetration. The ineffective deformation amount, that is, the deformation amount which cannot suppress the continuation of the shaking when the shaking is generated in the branch pipe, in the present embodiment, the diameter of the cavity of the second liner portion 5 is set smaller than the diameter of the cavities of the first liner portion 4 and the third liner portion 6. The second lining part 5 can be made to consume more ineffective deformation by the branch pipe, so that the limiting force of the second lining part 5 on the branch pipe is further improved, the branch pipe or the sleeve pipe body 2 can better transmit the force to the branch pipe to penetrate through the middle position of the main structure, the building main body is effectively prevented from being damaged, and the later maintenance cost is further reduced.
In a preferred embodiment, in addition to the above-described aspect, the second lining portion 5 is provided so as to be separated from the first lining portion 4 and the third lining portion 6.
In the present embodiment, the inventor considers that the deformation amount of the casing liner 3 absorbing the pipe shaking may be different due to the difference between the deformation coefficients of the second liner portion 5 and the first liner portion 4 and the third liner portion 6, and thus an uncontrollable cracking may occur at the joint of the second liner portion 5 and the first liner portion 4 and the third liner portion 6, so that the first liner portion 4 and/or the second liner portion 5 and/or the third liner portion 6 may lose the capability of absorbing the pipe shaking. Based on this, in the present embodiment, the inventors disconnected the second lining portion 5 from the first lining portion 4 and the third lining portion 6. The second lining portion 5 is separated from the first lining portion 4 and the third lining portion 6 by actively arranging a gap on the sleeve liner 3, so that the situation that uncontrollable cracking occurs at the joint of the second lining portion 5 and the first lining portion 4 and the third lining portion 6 is effectively avoided, and the reliability of the wall bushing 1 in practical application is improved.
Example 5
As shown in fig. 1 to 4, the complex pipeline insertion reverse construction method for the filler wall masonry based on the BIM technology is further characterized in that the masonry layout generated in the step C defines the size and the number of the building blocks, the position of the pipeline opening and the specific size based on the above manner.
Specifically, the position of the opening is checked by combining the building drawing and the electromechanical construction drawing, and the building drawing is well marked. And then typesetting the filler wall masonry according to the position of the pipeline hole, wherein the size and the number of the building blocks need to be determined in the layout, and the position and the size of the pipeline hole are accurately marked. And finally, intersecting the masonry team according to the typesetting drawing.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (10)

1. A filler wall masonry complex pipeline alternate reverse construction method based on a BIM technology is characterized by comprising the following steps:
A. building a BIM model: establishing a three-dimensional building model according to a building construction drawing and an electromechanical construction drawing, and optimizing and adjusting the arrangement of pipelines according to the established model;
B. pipeline construction: b, generating a pipeline layout according to the BIM established in the step A, and performing pipeline construction after the site constructors are handed over;
C. deeply typesetting the masonry: b, typesetting the masonry wall and generating a masonry layout according to the BIM established in the step A and the actual trend of the pipeline after the pipeline construction in the step B is completed;
D. and (3) masonry construction: and C, according to the masonry layout generated in the step C, performing masonry wall construction after the site constructors meet the bottom.
2. The BIM technology-based complex pipeline insertion reverse construction method for the filler wall masonry based on the claim 1 is characterized in that different layers are correspondingly established according to different functions of pipelines when a pipeline model is established in the step A, and naming rules of different functional pipelines and all components of the different functional pipelines are formulated.
3. The BIM technology-based complex pipeline insertion reverse construction method for the filler wall masonry, according to claim 2, is characterized in that the direction of the built pipeline is established, and all components of the pipeline are numbered in sequence according to the built direction.
4. The BIM technology-based complex pipeline insertion reverse construction method for the filler wall masonry, according to claim 3, is characterized in that a plurality of running water construction sections are divided according to the direction of pipeline construction, and boundaries between adjacent running water construction sections are defined.
5. The BIM technology-based insertion reverse construction method for the complex pipelines of the filler walls and the brickwork according to claim 4, wherein the sizes of all components of the pipelines and the relative sizes between all the components of the pipelines and the building main body are marked.
6. The BIM technology-based complex pipeline insertion reverse construction method for the filler wall masonry, according to claim 1, is characterized in that the pipeline construction sequence of the step B is bracket erection, main pipe erection, branch pipe erection and cable erection, and a wall insertion sleeve is arranged at a position penetrating through a main structure during the branch pipe erection.
7. The BIM technology-based complex pipeline insertion reverse construction method for the filler wall masonry, according to claim 6, characterized in that the wall bushing comprises a bushing body and a bushing lining, the bushing lining is arranged around the inner wall of the bushing body and forms an internal cavity structure, the bushing lining is made of a flexible material, the branch pipe penetrates into the wall bushing, and the bushing lining covers the branch pipe to prevent the branch pipe from contacting with the bushing body.
8. The BIM technology-based infilled wall masonry complex pipeline insertion reverse construction method according to claim 7, characterized in that the casing lining comprises a first lining portion, a second lining portion and a third lining portion, the second lining portion is arranged between the first lining portion and the third lining portion, the elastic deformation coefficient of the second lining portion is smaller than the elastic deformation coefficient of the materials of the first lining portion and the third lining portion, and the length of the second lining portion is greater than the length of the first lining portion and the third lining portion.
9. The BIM technology-based infilled wall masonry complex pipeline penetration reverse construction method according to claim 8, characterized in that the diameter of the second lining portion cavity is smaller than the diameter of the first and third lining portion cavities.
10. The BIM technology-based infilled wall masonry complex pipeline insertion reverse construction method according to any one of claims 8-9, characterized in that the second lining portion is disconnected from the first lining portion and the third lining portion.
CN202210516889.3A 2022-05-13 2022-05-13 BIM technology-based construction method for inserting complex pipelines of filled wall masonry into reverse construction Active CN114673356B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210516889.3A CN114673356B (en) 2022-05-13 2022-05-13 BIM technology-based construction method for inserting complex pipelines of filled wall masonry into reverse construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210516889.3A CN114673356B (en) 2022-05-13 2022-05-13 BIM technology-based construction method for inserting complex pipelines of filled wall masonry into reverse construction

Publications (2)

Publication Number Publication Date
CN114673356A true CN114673356A (en) 2022-06-28
CN114673356B CN114673356B (en) 2024-03-01

Family

ID=82080911

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210516889.3A Active CN114673356B (en) 2022-05-13 2022-05-13 BIM technology-based construction method for inserting complex pipelines of filled wall masonry into reverse construction

Country Status (1)

Country Link
CN (1) CN114673356B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050087980A1 (en) * 2002-01-26 2005-04-28 Howard Brett P. Connection of internally lined pipelines
US20140288890A1 (en) * 2013-03-15 2014-09-25 Aditazz, Inc. System and method for realizing a building system that involves computer based matching of form to function
CN109614723A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of comprehensive construction method based on BIM technology
CN109915676A (en) * 2019-04-19 2019-06-21 杭州温格科技有限公司 Pipe connecting structure
CN111539060A (en) * 2020-05-21 2020-08-14 广州市第四装修有限公司 BIM-based building masonry construction method, device, equipment and medium

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20050087980A1 (en) * 2002-01-26 2005-04-28 Howard Brett P. Connection of internally lined pipelines
US20140288890A1 (en) * 2013-03-15 2014-09-25 Aditazz, Inc. System and method for realizing a building system that involves computer based matching of form to function
CN109614723A (en) * 2018-12-14 2019-04-12 中建二局第建筑工程有限公司 A kind of comprehensive construction method based on BIM technology
CN109915676A (en) * 2019-04-19 2019-06-21 杭州温格科技有限公司 Pipe connecting structure
CN111539060A (en) * 2020-05-21 2020-08-14 广州市第四装修有限公司 BIM-based building masonry construction method, device, equipment and medium

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张鑫全: "砌体结构配电箱体及进出线管免剔凿施工技术研究", 房建工程, pages 161 - 174 *

Also Published As

Publication number Publication date
CN114673356B (en) 2024-03-01

Similar Documents

Publication Publication Date Title
JP6533842B2 (en) Joints used as final connections in submerged tunnels
US20200256498A1 (en) Trenchless integrative repair method for concrete drainage pipeline with cracking, corrosion and subsidence
EP3434951A1 (en) Box-type pipeline with circumferential obtuse angle connection
CN114017554B (en) Pipe orifice butt joint method and device for concrete pipeline
CN105672355A (en) Plate type prefabricated concrete comprehensive pipe gallery
CN106088293A (en) A kind of small-bore sewage conduct restorative procedure
CN105756088A (en) Combined prefabricated assembled multi-cabin comprehensive pipe rack
CN108149685B (en) Method for repairing and reinforcing pile head of concrete pipe pile
CN103993691A (en) Integrated floor module and assembling method thereof
CN114673356A (en) BIM technology-based infilled wall masonry complex pipeline alternate reverse construction method
KR102083378B1 (en) Reinforcement member and construction method to reinforce concrete box
JPH08120754A (en) Split box culvert and method for assembling same
CN204080864U (en) A kind of splice type monitor well
CN209799983U (en) Pipe jacking pipe joint prefabricated part with slotted hole
KR200444865Y1 (en) Closeing Tool for Penetration Sleeve
CN114087421A (en) Construction method for laying pressure pipeline in box culvert
JP5827102B2 (en) Precast member installation method and precast member used therefor
TWM587719U (en) Pre-buried water inspection and leakage detection pipe plug head
CN202834386U (en) Three-dimensional hyperbolic steel pipe jacking axis formed transitional device
CN111441239A (en) Prefabricated cover beam prestress deep-buried anchor sleeve and installation process thereof
KR102609258B1 (en) Hybrid collaboration recovering method
CN113374503B (en) Method for embedding and arranging assembled lining monitoring and measuring components
KR101586801B1 (en) Appatatus for rpair and reinforcement of concrete structure and method for rpair and reinforcement using the same
CN109944605B (en) Pipe-jacking pipe joint prefabricated part with slotted holes and pipe-jacking construction method
CN213836546U (en) Pre-embedding device for fixing end nut of rear-assembling rubber waterstop

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant