CN114673089A - Walking type pushing construction control method for non-thrust arch bridge steel box girder - Google Patents

Walking type pushing construction control method for non-thrust arch bridge steel box girder Download PDF

Info

Publication number
CN114673089A
CN114673089A CN202210242486.4A CN202210242486A CN114673089A CN 114673089 A CN114673089 A CN 114673089A CN 202210242486 A CN202210242486 A CN 202210242486A CN 114673089 A CN114673089 A CN 114673089A
Authority
CN
China
Prior art keywords
steel box
box girder
section
bridge deck
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210242486.4A
Other languages
Chinese (zh)
Other versions
CN114673089B (en
Inventor
王雨舟
赵思淇
褚部
丁仕洪
周宏庚
李猛超
刘果
方满成
易高睿
郎宗启
高永峰
朱雨佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Steel Structure Construction Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Steel Structure Construction Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Steel Structure Construction Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN202210242486.4A priority Critical patent/CN114673089B/en
Publication of CN114673089A publication Critical patent/CN114673089A/en
Application granted granted Critical
Publication of CN114673089B publication Critical patent/CN114673089B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/06Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/23Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a walking type pushing construction control method for a non-thrust arch bridge steel box girder, which is used for controlling the local stress of a bridge deck system and ensuring the line shape of assembly. Before the jacking of the bridge deck system, the erected bridge deck system line shape is combined, and the elevation adjustment condition of each fulcrum in the jacking advancing process is simulated, so that the bridge deck system is in the theoretical bridge forming line shape. After the pushing of the bridge deck system is finished, according to a linear positioning mode, measuring a tangent line of the tail end of the steel box girder at the previous section, taking the tangent line as a positioning reference, adjusting the station position of the hoisting machinery in the hoisting process, welding and fixing after meeting the requirement, and performing other operations on the subsequent hoisting machinery. The method ensures that the internal force and the line shape of the bridge deck system are consistent with the design in the pushing process, is simple and practical to operate, and has popularization value in pushing construction of the asymmetric thrust-free arch bridge.

Description

Walking type pushing construction control method for non-thrust arch bridge steel box girder
Technical Field
The invention relates to the field of non-thrust arch bridge construction, in particular to a walking type pushing construction control method for a steel box girder of a non-thrust arch bridge.
Background
With the rapid development of design construction level and construction equipment, the incremental launching construction can be completely realized by a bridge line shape or a space curve bridge with a certain arc line. Therefore, the walking type pushing construction method can be adopted to carry out pushing construction on the arch bridge steel box girder which has no thrust in the self-stress form and has a certain radian.
The existing pushing construction methods are all translation type pushing, pushing construction of an arch bridge steel box girder cannot be carried out according to linearity of an arch bridge, in the pushing construction of the thrust-free arch bridge steel box girder, in order to ensure that fulcrum reaction force is within a calculation design value, relative linear dynamic change of the fulcrum reaction force needs to be adjusted at any time, and curvature and precision of steel box girder erection are ensured.
Disclosure of Invention
The invention aims to provide a walking type pushing construction control method for a thrust-free arch bridge steel box girder, which ensures that all sections of the steel box girder are erected in place, and has accurate linearity and high precision.
The technical scheme of the invention is as follows:
a walking type pushing construction control method for a thrust-free arch bridge steel box girder specifically comprises the following steps:
(1) before incremental launching construction, simulating the design line shape of a bridge according to a design drawing, dividing the steel box girder into a main span section and a side span section according to the design line shape of the bridge, dividing each section of the steel box girder into a plurality of incremental launching parts according to the total incremental launching length of the steel box girder, sequentially simulating the working condition of incremental launching operation of each section of the steel box girder through engineering simulation software, and calculating the theoretical reaction value of the three-dimensional jack for lifting the bridge deck system in the incremental launching process;
(2) Before jacking of the bridge deck system, completing installation of a jacking bracket, arranging a three-dimensional jack and a temporary protection pier on the jacking bracket, hoisting and welding a main span section of the steel box girder, and before jacking, placing the main span section of the steel box girder on the temporary protection pier and being higher than the three-dimensional jack;
(3) before pushing, according to the line shape of the bridge deck system of the erected main span section of the steel box girder and combining the line shape of the bridge deck, based on each part in the bridge deck system of the main span section of the steel box girder, lofting in the pushing process is carried out, and an adjusting numerical value of the bridge deck height of the main span section of the steel box girder in the pushing advancing process is obtained;
(4) setting theoretical reaction range values of all parts in the bridge deck system of the main span section of the steel box girder, and in the jacking process of the bridge deck system of the main span section of the steel box girder, when the actual reaction value of any part on the fulcrum of the three-dimensional jack exceeds the theoretical reaction range value, adjusting the elevation of the fulcrum of the part of the bridge deck system of the main span section of the steel box girder in time, and then further adjusting the elevation according to the lofting elevation value; the theoretical reaction range value is a range value obtained by adding a set positive and negative error value to the theoretical reaction value;
(5) after the pushing of the bridge deck system of the main span section of the steel box girder is finished, measuring the coordinates of a plurality of measuring points on the rear end part of the main span section of the steel box girder, calculating the angle value of the tangential angle of each measuring point, finally obtaining the tangential angle of the tail end of the main span section of the steel box girder through the fitting of the tangential angles of the plurality of measuring points, and then taking the tangential angle of the tail end of the main span section of the steel box girder as a positioning reference;
(6) After the jacking of the bridge deck system of the main span section of the steel box girder is finished, the hoisting machine enters the ground, the mechanical station position is adjusted, the side span section of the steel box girder is hoisted to the jacking bracket, jacking operation is carried out according to the steps (3) to (5) until the steel box girder of the next section is jacked to the place by taking the tangential angle of the tail end of the steel box girder of the previous section as a positioning reference, and after the jacking of the steel box girder of the next section is finished, the front end of the steel box girder of the next section is welded and fixed with the tail end of the steel box girder of the previous section.
In the step (1), the design line shape of the bridge is simulated by using AutoCAD software, and the working condition that each section of the steel box girder is partially pushed is simulated in sequence by finite element analysis software.
After erecting and pushing each section of steel box girder, all the sections of steel box girder are placed on the temporary protection piers, and the number of the pushing supports, the temporary protection piers and the three-dimensional jacks is synchronously increased along with the increase of the splicing length of the whole steel box girder bridge deck system; compared with the theoretical line shape of the same section for forming the bridge, the line shape of the bridge deck system of each section steel box girder after the erection and the pushing is consistent with the longitudinal slope, the transverse slope and the mileage of the bridge deck system of the same section steel box girder, but the elevation of the bridge deck system of each section steel box girder after the actual erection and the pushing is slightly higher than the theoretical elevation of the same section for forming the bridge, the height of each section steel box girder at the temporary protection pier supporting point of each pushing support is higher than the theoretical elevation by a certain value, and the actual line and the theoretical line of each section steel box girder bridge deck system are in a space parallel state.
The main longitudinal beam at the front end of the bridge deck system of the main span section of the steel box girder serves as a partial pushing guide beam, namely the pushing guide beam of the main span section of the steel box girder comprises a guide beam, a variable cross-section box-type transition beam and a longitudinal beam at the front end of the main span section of the steel box girder which are sequentially connected.
And displacement sensors of the three-dimensional jacks on the pushing support are connected with a PLC (programmable logic controller), the PLC displays three-dimensional coordinates of the fulcrums on the three-dimensional jacks in real time, and the mileage of the bridge deck system and the lifting height of each three-dimensional jack fulcrum in the pushing process are adjusted at any time according to the lofting elevation value.
In the step (5), the steel box girder of the next section is pushed to the right position by taking the tangential angle of the tail end of the steel box girder of the previous section as a positioning reference, namely, the front end part of the steel box girder of the next section is provided with a plurality of measuring points, the angle value of the tangential angle of each measuring point is calculated, and finally the tangential angle of the head end of the steel box girder of the next section is obtained through the fitting of the tangential angles of the measuring points, when the tangential angle of the head end of the steel box girder of the next section is consistent with the tangential angle of the tail end of the steel box girder of the previous section, and the elevation meets the design requirement, the pushing is pushed to the right position.
And (5) after the angle value of the tangential angle of each measuring point is calculated, rechecking the mileage and elevation measured values of the bridge deck system after the pushing is finished according to the angle value of the tangential angle of each measuring point, adjusting the elevation of the supporting point again by using the three-dimensional jack, and fitting the tangential angle of each adjusted measuring point to obtain the tangential angle of the tail end of the main span section of the steel box girder after rechecking and adjusting.
The invention has the advantages that:
(1) before the pushing construction, a theoretical counter force value of the three-dimensional jack for lifting the bridge deck system in the pushing process is obtained through engineering simulation software simulation, then during the pushing construction, an actual counter force value on a fulcrum of the three-dimensional jack is compared with a theoretical counter force range value, and the elevation of the fulcrum is adjusted in time, so that the displacement accuracy of the steel box girder in the pushing process in sections and in parts is realized;
(2) the main longitudinal beam at the front end of the bridge deck system of the main span section of the steel box girder is used as a partial pushing guide girder, so that the length of the guide girder is reduced;
(3) the displacement sensors of the three-dimensional jack on the pushing support are connected with the PLC, and can be further adjusted by adopting a lofting elevation numerical value, so that the pushing precision of the steel box girder in the pushing process is further improved;
(4) the tangential angles of a plurality of measuring points are adopted to fit the curvature of the top end of the actual steel box girder after the top end of the actual steel box girder is in place, then the tangential angle of the tail end of the steel box girder is obtained according to the curvature and is used as a positioning reference for pushing the steel box girder in place of the next section, the integrity of splicing the steel box girders of the plurality of sections is guaranteed, and meanwhile the accuracy of the linearity of the steel box girder of the thrust-free arch bridge is guaranteed.
Drawings
FIG. 1 is a schematic view of the pushing construction of the present invention.
Fig. 2 is a top view of the push guide beam of the present invention.
Fig. 3 is a measuring point layout diagram of the steel box girder of the previous section of the present invention.
Fig. 4 is a layout diagram of measuring points of the steel box girder of the latter section of the present invention.
The method comprises the following steps of reference numeral 1-pushing support, 2-three-dimensional jack, 3-temporary protection pier, 4-steel box girder main span section, 5-guide beam, 6-variable cross section box type transition beam, 7-longitudinal beam at the front end part of steel box girder main span section, 8-first measuring point, 9-second measuring point, 10-third measuring point 10, 11-fourth measuring point, 12-fifth measuring point, 13-sixth measuring point, 14-seventh measuring point 10, 15-eighth measuring point and 16-steel box girder of the next section.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
A walking type pushing construction control method for a non-thrust arch bridge steel box girder specifically comprises the following steps:
(1) Before incremental launching construction, simulating the design line shape of a bridge by using AutoCAD software according to a design drawing, dividing a steel box girder into a plurality of sections according to the design line shape of the bridge, dividing each section of the steel box girder into a plurality of incremental launching parts according to the total incremental launching length of the steel box girder, sequentially simulating the working condition of incremental launching operation of each section of the steel box girder through finite element analysis software, and calculating the theoretical reaction force value of the three-dimensional jack for lifting the bridge deck system in the incremental launching process;
(2) before jacking, the bridge deck system finishes mounting of a jacking bracket 1, a three-dimensional jack 2 and a temporary protection pier 3 are arranged on the jacking bracket 1, hoisting and welding of a main span section 4 of the steel box girder are carried out, and before jacking, the main span section 4 of the steel box girder is arranged on the temporary protection pier 3 and is 5-10cm higher than the three-dimensional jack;
(3) before pushing, according to the erected first section steel box, the bridge deck systems are linear and combined into a bridge line shape, based on each part in the bridge deck system of the main span section of the steel box girder, lofting in the pushing process is carried out, and an adjusting numerical value of the bridge deck height of the main span section of the steel box girder in the pushing advancing process is obtained;
(4) setting theoretical reaction range values of all parts in the bridge deck system of the main span section of the steel box girder, and timely adjusting the elevations of the fulcrums of the part of the bridge deck system of the main span section of the steel box girder when the actual reaction value of any part on the three-dimensional jack fulcrum 2 exceeds the theoretical reaction range values in the jacking process of the bridge deck system of the main span section of the steel box girder; displacement sensors of three-dimensional jacks 2 on the pushing support are connected with a PLC (programmable logic controller), the PLC displays three-dimensional coordinates of fulcrums on the three-dimensional jacks 2 in real time, and then the mileage of the bridge deck system and the lifting height of each three-dimensional jack 2 fulcrum in the pushing process are adjusted at any time according to the lofting elevation value; the theoretical reaction range value is a range value obtained by adding a set positive and negative error value to the theoretical reaction value; referring to fig. 2, the main longitudinal beam at the front end of the bridge deck system in the main span section of the steel box girder serves as a partial pushing guide beam, that is, the pushing guide beam in the main span section of the steel box girder comprises a guide beam 5, a variable cross-section box-shaped transition beam 6 and a longitudinal beam 7 at the front end of the main span section of the steel box girder, which are connected in sequence, so that the length of the guide beam 5 is reduced.
(5) After jacking of the bridge deck system of the main span section 4 of the steel box girder is finished, coordinates of four measuring points (a first measuring point 8, a second measuring point 9, a third measuring point 10 and a fourth measuring point 11) on the rear end part of the main span section 4 of the steel box girder are measured, an angle value of a tangential angle of each measuring point is calculated, mileage and elevation measuring values of the bridge deck system after jacking is finished are rechecked according to the angle value of the tangential angle of each measuring point, a three-dimensional jack is used for adjusting the elevation of a fulcrum again, after rechecking and adjusting, the tangential angle of each measuring point after adjusting is fitted to obtain the tangential angle of the tail end of the main span section of the steel box girder, and then the tangential angle of the tail end of the main span section of the steel box girder is used as a positioning reference;
(6) after the jacking of the bridge deck system of the main span section of the steel box girder is finished, hoisting machinery enters a field, adjusting a mechanical station, hoisting the side span section of the steel box girder to a jacking bracket 1, jacking according to the steps (3) to (5), jacking the steel box girder 16 of the next section to the position in place by taking the tangential angle of the tail end of the steel box girder of the previous section as a positioning reference, namely, the front end part of the steel box girder 16 of the next section is provided with four measuring points (a fifth measuring point 12, a sixth measuring point 13, a seventh measuring point 14 and an eighth measuring point 15), calculating the angle value of the tangential angle of each measuring point, finally obtaining the tangential angle of the head end of the steel box girder 16 of the next section through the tangential angles fitting of the four measuring points, when the tangential angle of the head end of the steel box girder 16 of the next section is consistent with the tangential angle of the tail end of the steel box girder of the previous section and the elevation meets the design requirement, namely pushing in place; and after the pushing of the steel box girder 16 of the next section is finished, welding and fixing the front end of the steel box girder 16 of the next section and the tail end of the steel box girder of the previous section.
After erecting and pushing each section of steel box girder, all the sections of steel box girder are placed on the temporary protection piers 3, and along with the increase of the assembling length of the whole steel box girder bridge deck system, the number of the pushing supports 1, the number of the temporary protection piers 3 and the number of the three-dimensional jacks 2 are synchronously increased; compared with the theoretical line shape of the same section for forming the bridge, the line shape of the bridge deck system of each section steel box girder after the erection and the pushing is consistent with the longitudinal slope, the transverse slope and the mileage of the bridge deck system of each section steel box girder, after the actual erection and the pushing are completed, the level of the bridge deck system of each section steel box girder is slightly higher than the level of the theoretical same section for forming the bridge, but the height of each section steel box girder at the 3-branch point of each pushing support temporary protection pier is consistent with the value higher than the theoretical level, namely the actual line and the theoretical line of the bridge deck system of each section steel box girder are in a space parallel state.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. A walking type pushing construction control method for a thrust-free arch bridge steel box girder is characterized by comprising the following steps: the method specifically comprises the following steps:
(1) Before incremental launching construction, simulating the design line shape of a bridge according to a design drawing, dividing the steel box girder into a main span section and a side span section according to the design line shape of the bridge, dividing each section of the steel box girder into a plurality of incremental launching parts according to the total incremental launching length of the steel box girder, sequentially simulating the working condition of incremental launching operation of each section of the steel box girder through engineering simulation software, and calculating the theoretical reaction value of a three-dimensional jack for lifting a bridge deck system in the incremental launching process;
(2) before jacking of the bridge deck system, completing installation of a jacking support, arranging a three-dimensional jack and a temporary protection pier on the jacking support, hoisting and welding a main span section of the steel box girder, and before jacking, arranging the main span section of the steel box girder on the temporary protection pier and being higher than the three-dimensional jack;
(3) before pushing, according to the line shapes of the bridge deck systems of the main span sections of the erected steel box girders and combining the line shapes into a bridge line shape, based on each part in the bridge deck systems of the main span sections of the steel box girders, lofting is carried out in the pushing process, and an adjustment numerical value of the height of the bridge deck systems of the main span sections of the steel box girders in the pushing advancing process is obtained;
(4) setting theoretical reaction range values of all parts in the bridge deck system of the main span section of the steel box girder, and in the jacking process of the bridge deck system of the main span section of the steel box girder, when the actual reaction value of any part on the supporting point of the three-dimensional jack exceeds the theoretical reaction range value, adjusting the elevation of the supporting point of the bridge deck system of the main span section of the steel box girder in time, and then further adjusting the elevation by the lofting elevation value; the theoretical reaction range value is a range value obtained by adding a set positive and negative error value to the theoretical reaction value;
(5) After the jacking of the bridge deck system of the main span section of the steel box girder is finished, measuring the coordinates of a plurality of measuring points on the rear end part of the main span section of the steel box girder, calculating the angle value of the tangential angle of each measuring point, finally fitting the tangential angles of the plurality of measuring points to obtain the tangential angle of the tail end of the main span section of the steel box girder, and then taking the tangential angle of the tail end of the main span section of the steel box girder as a positioning reference;
(6) after the jacking of the bridge deck system of the main span section of the steel box girder is finished, the hoisting machine enters the ground, the mechanical station position is adjusted, the side span section of the steel box girder is hoisted to the jacking bracket, jacking operation is carried out according to the steps (3) to (5) until the steel box girder of the next section is jacked to the place by taking the tangential angle of the tail end of the steel box girder of the previous section as a positioning reference, and after the jacking of the steel box girder of the next section is finished, the front end of the steel box girder of the next section is welded and fixed with the tail end of the steel box girder of the previous section.
2. The walking type pushing construction control method for the steel box girder of the thrust-free arch bridge as recited in claim 1, wherein: in the step (1), the design line shape of the bridge is simulated by using AutoCAD software, and the working condition that each section of the steel box girder is partially pushed is simulated in sequence by finite element analysis software.
3. The walking type pushing construction control method for the steel box girder of the thrust-free arch bridge as recited in claim 1, wherein: after erecting and pushing of each section steel box girder, all the sections of the section steel box girder are placed on the temporary protection piers, and the number of the pushing supports, the temporary protection piers and the three-dimensional jacks is synchronously increased along with the increase of the splicing length of the whole steel box girder bridge deck system; compared with the theoretical line shape of the same section for forming the bridge, the line shape of the bridge deck system of each section steel box girder after erection and jacking is consistent with the longitudinal slope, the transverse slope and the mileage of the bridge deck system of each section steel box girder, but the elevation of the bridge deck system of each section steel box girder after actual erection and jacking is slightly higher than the elevation of the theoretical same section for forming the bridge, but the height of each section steel box girder at the temporary protection pier supporting point of each jacking bracket is higher than the theoretical elevation by a consistent value, namely the actual line and the theoretical line of the bridge deck system of each section steel box girder are in a space parallel state.
4. The walking type pushing construction control method for the thrust-free arch bridge steel box girder according to claim 1, is characterized in that: the main longitudinal beam at the front end of the bridge deck system of the main span section of the steel box girder serves as a partial pushing guide beam, namely the pushing guide beam of the main span section of the steel box girder comprises a guide beam, a variable cross-section box-type transition beam and a longitudinal beam at the front end of the main span section of the steel box girder which are sequentially connected.
5. The walking type pushing construction control method for the steel box girder of the thrust-free arch bridge as recited in claim 1, wherein: and displacement sensors of the three-dimensional jacks on the pushing support are connected with the PLC, the PLC displays three-dimensional coordinates of fulcrums on the three-dimensional jacks in real time, and the mileage of the bridge deck system and the lifting height of each three-dimensional jack fulcrum in the pushing process are adjusted at any time according to the lofting elevation value.
6. The walking type pushing construction control method for the steel box girder of the thrust-free arch bridge as recited in claim 1, wherein: in the step (5), the steel box girder of the next section is pushed to the place by taking the tangential angle of the tail end of the steel box girder of the previous section as a positioning reference, namely, a plurality of measuring points are arranged at the front end part of the steel box girder of the next section, the angle value of the tangential angle of each measuring point is calculated, finally, the tangential angle of the head end of the steel box girder of the next section is obtained through fitting the tangential angles of the measuring points, when the tangential angle of the head end of the steel box girder of the next section is consistent with the tangential angle of the tail end of the steel box girder of the previous section, and the elevation meets the design requirement, the steel box girder of the next section is pushed to the place.
7. The walking type pushing construction control method for the steel box girder of the thrust-free arch bridge as recited in claim 1, wherein: and (5) after the angle value of the tangential angle of each measuring point is calculated, rechecking the mileage and elevation measured values of the bridge deck system after jacking is finished according to the angle value of the tangential angle of each measuring point, adjusting the elevation of the fulcrum again by using the three-dimensional jack, and fitting the tangential angle of the tail end of the main span section of the steel box girder by using the tangential angle of each adjusted measuring point after rechecking and adjusting.
CN202210242486.4A 2022-03-11 2022-03-11 Walking type pushing construction control method for non-thrust arch bridge steel box girder Active CN114673089B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210242486.4A CN114673089B (en) 2022-03-11 2022-03-11 Walking type pushing construction control method for non-thrust arch bridge steel box girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210242486.4A CN114673089B (en) 2022-03-11 2022-03-11 Walking type pushing construction control method for non-thrust arch bridge steel box girder

Publications (2)

Publication Number Publication Date
CN114673089A true CN114673089A (en) 2022-06-28
CN114673089B CN114673089B (en) 2023-04-18

Family

ID=82074799

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210242486.4A Active CN114673089B (en) 2022-03-11 2022-03-11 Walking type pushing construction control method for non-thrust arch bridge steel box girder

Country Status (1)

Country Link
CN (1) CN114673089B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000290933A (en) * 1999-04-07 2000-10-17 Yokogawa Bridge Corp Method for controlling form of precast segment, and method for erecting bridge by precast segment construction method
CN102877421A (en) * 2012-09-17 2013-01-16 长沙理工大学 Construction control method capable of realizing unstressed line shapes of pushing construction beam bodies at high accuracy
CN105970832A (en) * 2016-05-24 2016-09-28 西安公路研究院 Jacking system for closure section of continuous rigid frame bridge and jacking deviation rectifying method
CN109518607A (en) * 2018-11-23 2019-03-26 云南建投基础工程有限责任公司 A kind of oblique jack-up construction method of bridge based on FEM Simulation
CN109629442A (en) * 2019-01-15 2019-04-16 中铁三局集团有限公司 A kind of large span stayed-cable bridge steel case trusses line type control construction method
CN110318341A (en) * 2019-07-02 2019-10-11 武船重型工程股份有限公司 A kind of turning-over working method
JP2020057266A (en) * 2018-10-03 2020-04-09 日立造船株式会社 Erection process presentation device, erection process presentation program, and recording media
CN113591186A (en) * 2021-07-21 2021-11-02 中铁大桥勘测设计院集团有限公司 Steel truss manufacturing configuration determining method and system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000290933A (en) * 1999-04-07 2000-10-17 Yokogawa Bridge Corp Method for controlling form of precast segment, and method for erecting bridge by precast segment construction method
CN102877421A (en) * 2012-09-17 2013-01-16 长沙理工大学 Construction control method capable of realizing unstressed line shapes of pushing construction beam bodies at high accuracy
CN105970832A (en) * 2016-05-24 2016-09-28 西安公路研究院 Jacking system for closure section of continuous rigid frame bridge and jacking deviation rectifying method
JP2020057266A (en) * 2018-10-03 2020-04-09 日立造船株式会社 Erection process presentation device, erection process presentation program, and recording media
CN109518607A (en) * 2018-11-23 2019-03-26 云南建投基础工程有限责任公司 A kind of oblique jack-up construction method of bridge based on FEM Simulation
CN109629442A (en) * 2019-01-15 2019-04-16 中铁三局集团有限公司 A kind of large span stayed-cable bridge steel case trusses line type control construction method
CN110318341A (en) * 2019-07-02 2019-10-11 武船重型工程股份有限公司 A kind of turning-over working method
CN113591186A (en) * 2021-07-21 2021-11-02 中铁大桥勘测设计院集团有限公司 Steel truss manufacturing configuration determining method and system

Also Published As

Publication number Publication date
CN114673089B (en) 2023-04-18

Similar Documents

Publication Publication Date Title
CN109680615B (en) Three-dimensional coordinate measuring construction method of short-line method section beam
CN107391793B (en) Building structure dismantling method based on 3D scanning technology and MR mixed reality technology
CN101725255A (en) Segmental slipping and assembling process of overhead large-span steel structure
CN110847375B (en) Large-span truss construction method and large-span truss structure
CN112016147B (en) Revit platform-based steel truss girder pre-assembly precision detection method
CN111254835A (en) Continuous matching construction method for steel box girder segments in factory
CN112084561A (en) Construction control method for long-span railway steel box composite beam bridge through incremental launching construction
CN112900266B (en) Steel truss girder splicing linear control method
CN107336346A (en) A kind of beam making bench
CN113374282A (en) Method for controlling embedded bolt by adopting assumed coordinate system
CN108519782B (en) Automatic control system for prefabricated line shape of segmental bridge
CN114673089B (en) Walking type pushing construction control method for non-thrust arch bridge steel box girder
CN110700083A (en) Installation measurement control method for prefabricated bridge pier stud
CN114319121A (en) Long and large steel box girder segment linear control method
CN110145159B (en) Welding connection contact net hard cross beam and construction method thereof
CN111946070A (en) Skirt-swing type installation method for spatial irregular steel grids
CN107881914B (en) Wire-dividing tube type cable saddle back field assembly type positioning device and assembly method
CN113065183B (en) Optimization method, optimization device and optimization system of construction scheme
CN115198664A (en) Construction method of mountainous area high pier extra-small curvature radius continuous steel box girder
CN210622423U (en) Welded connection's hard crossbeam of contact net
CN115544618B (en) Method for controlling space assembly precision of large-span deformed steel truss structure module
CN114310162B (en) Method for manufacturing large-section whole hole of curved steel box girder
CN111809885A (en) Large-span steel truss hydraulic jacking system and construction method thereof
CN114809652B (en) BIM-based roof arc truss positioning and hoisting method
CN109629429B (en) Method for determining construction control elevation of cable-stayed bridge cantilever

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant