CN114622492B - Ultrahigh hollow thin-wall pier large-section diaphragm plate and construction method - Google Patents

Ultrahigh hollow thin-wall pier large-section diaphragm plate and construction method Download PDF

Info

Publication number
CN114622492B
CN114622492B CN202210350447.6A CN202210350447A CN114622492B CN 114622492 B CN114622492 B CN 114622492B CN 202210350447 A CN202210350447 A CN 202210350447A CN 114622492 B CN114622492 B CN 114622492B
Authority
CN
China
Prior art keywords
diaphragm
hollow thin
cast
plate
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210350447.6A
Other languages
Chinese (zh)
Other versions
CN114622492A (en
Inventor
贺志威
李旭东
王先平
袁平顺
胡伟麟
姬海鹏
殷本林
邱文昌
陈旭东
荣元华
欧旗
黄维磊
陈凤翔
王再强
王峻
李霞
李莺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 7 Co Ltd
Original Assignee
Sinohydro Bureau 7 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 7 Co Ltd filed Critical Sinohydro Bureau 7 Co Ltd
Priority to CN202210350447.6A priority Critical patent/CN114622492B/en
Publication of CN114622492A publication Critical patent/CN114622492A/en
Application granted granted Critical
Publication of CN114622492B publication Critical patent/CN114622492B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Abstract

A pier column diaphragm plate of a flat plate structure is split into a strip diaphragm beam and a diaphragm plate cast-in-situ part, the diaphragm beam is prefabricated on the ground in a lattice-jumping mode, reserved steel bars are arranged on the periphery of the diaphragm beam, a hoisting ring is arranged at the top of the diaphragm beam, the diaphragm beams are sequentially arranged on inner chamfers of the hollow thin-wall pier, and the width of the diaphragm plate cast-in-situ part is reserved between adjacent diaphragm beams; the transverse reserved steel bars of the adjacent diaphragm beams are connected by adopting connecting steel bars, and then an anchoring beam, an anchoring bolt, a pull rod and a bottom template buckled at the bottoms of the two adjacent prefabricated diaphragm beams are used for forming a diaphragm cast-in-place part casting space, and a diaphragm cast-in-place part concrete is cast to form a complete diaphragm with an ultrahigh hollow thin-wall pier large cross section. By adopting the method for diaphragm construction, the single hoisting weight is reduced, and a bracket or other supporting systems are not required to be additionally erected, so that the construction cost is reduced, and the construction period is saved.

Description

Ultrahigh hollow thin-wall pier large-section diaphragm plate and construction method
Technical field:
the invention belongs to the technical field of construction engineering concrete construction, in particular to the technical field of construction of hollow thin-wall piers of highway and railway bridges, and particularly relates to the technical field of construction of large-section diaphragm plates of ultrahigh hollow thin-wall piers.
The background technology is as follows:
along with the rapid development of high speed and high iron in China, the bridge construction level is gradually improved. In the design of mountain area bridge, often there will be the appearance of superelevation mound, in superelevation hollow thin wall mound, often can set up the diaphragm to reinforcing pier stud's wholeness, stability prevent pier stud unstability. The ultra-high hollow thin-wall pier diaphragm is different from the prefabricated T-beam diaphragm and the box-beam diaphragm, and the ultra-high hollow thin-wall pier diaphragm is thick in thickness, large in overall size and extremely high in construction difficulty. The conventional pier column diaphragm plate is generally constructed by adopting integral prefabrication and hoisting, or erecting a floor type scaffold inside a hollow pier to serve as a bearing system, or erecting an air supporting platform by adopting materials such as pre-buried brackets, section steel and the like to serve as a supporting system, and then constructing in an integral cast-in-situ mode. Along with the increase of bridge structure size, the conventional mode has the problems of large engineering quantity of auxiliary measures, difficult later disassembly, narrow space in the pier, high safety risk, long construction period and the like. Therefore, a safe, reliable and economical construction method for the ultra-high hollow thin-wall pier diaphragm plate is needed at present.
The invention comprises the following steps:
the invention aims to solve the technical problem of providing a large-section diaphragm plate of an ultrahigh hollow thin-wall pier, which is safe, reliable and economical.
In order to solve the problems, the invention adopts the following technical scheme:
the invention provides a diaphragm plate with a large section of an ultrahigh hollow thin-wall pier, which is of a flat plate structure and is arranged at an inner chamfer of a pier column of a poured part of the hollow thin-wall pier, wherein the diaphragm plate of the flat plate structure is divided into a prefabricated diaphragm beam and a diaphragm plate cast-in-situ part which are uniformly distributed at intervals; the method comprises the steps that a diaphragm beam is prefabricated on the ground in a jumping mode, the diaphragm beam is of a strip-shaped concrete structure, reserved steel bars are arranged on the periphery of the diaphragm beam, lifting rings are arranged at the tops of the diaphragm beam, and the reserved steel bars are reserved with enough welding lengths; the cast-in-situ part of the diaphragm plate is of a strip structure, a certain width is reserved between adjacent diaphragm beams, and finally casting is performed; installing a prefabricated diaphragm Liang Yici on an inner chamfer of the poured part of the hollow thin-wall pier, and leaving the width of the cast-in-place part of the diaphragm in the middle; the transverse reserved steel bars of the adjacent diaphragm beams are connected by adopting connecting steel bars, and then form a diaphragm cast-in-place part casting space by an anchor beam placed at the top of the diaphragm beams, a steel backing plate at the top of the anchor beam, anchor bolts, pull rods and bottom templates buckled at the bottoms of the two adjacent prefabricated diaphragm beams, and cast-in-place part concrete of the diaphragm is cast to form a complete diaphragm with an ultrahigh hollow thin-wall pier large section.
The bottom template is made of a steel plate with delta=10mm.
The hoisting ring arranged on the diaphragm beam is made of HPB300 smooth round steel bars with phi=16mm.
The transverse diaphragm is provided with a plurality of transverse and longitudinal reserved steel bars which are uniformly spaced and symmetrically arranged.
The anchoring beam is made of double-limb [100 channel steel ].
The pull rod is made of finish-rolled deformed steel bar with phi=28mm.
The steel backing plate is made of a steel plate with delta=10mm.
The anchor bolt is a fastening bolt matched with the finish-rolled deformed steel bar.
And a sleeve is sleeved on the pull rod, and the sleeve is made of PVC (polyvinyl chloride) tubes.
A construction method of a diaphragm plate with a large section of an ultrahigh hollow thin-wall pier comprises the following construction steps:
1) Constructing pier columns of the poured parts of the hollow thin-wall piers to the bottom surface of the diaphragm plate, and arranging inner chamfers;
2) Dividing a diaphragm plate of a flat plate structure into a strip-shaped diaphragm beam and a diaphragm plate cast-in-situ part, prefabricating and forming the diaphragm beam on the ground, wherein reserved steel bars are arranged on the periphery of the diaphragm beam, and a hoisting ring is reserved on the top surface of the diaphragm beam;
3) Hoisting and placing the precast beam on the corresponding position of the inner chamfer of the pier column of the poured part of the hollow thin-wall pier after prefabrication of the diaphragm;
4) After the diaphragm beams are installed, the pull rods penetrate through the bottom templates and are screwed by anchor bolts, the whole diaphragm beams obliquely penetrate through cast-in-place parts of the diaphragm plates, and are buckled at the bottoms of two adjacent diaphragm beams; sleeving a sleeve on the pull rod, placing an anchoring beam on the top of the transverse beam, clamping the pull rod, and anchoring the top by adopting a steel backing plate;
5) Connecting adjacent transverse reserved steel bars of the diaphragm beams by adopting connecting steel bars, pouring partial concrete of the diaphragm plates in-situ, and forming a complete diaphragm plate with an ultrahigh hollow thin-wall pier and a large section;
6) And (5) dismantling the pull rod and the anchoring beam, and continuously pouring the non-intersected part of the hollow thin-wall pier of the next section.
Compared with the prior art, the invention has the following beneficial effects:
1. according to the invention, the diaphragm plate with the flat plate structure in the original design is split into the strip-shaped structure, the diaphragm is prefabricated into the diaphragm beam in the jumping mode, the diaphragm Liang Zhuge is hoisted in place and is used as a supporting system, the construction difficulty of the diaphragm plate with the large section of the ultrahigh hollow thin-wall pier is solved by adopting a mode of post-pouring construction joints through a hanging die method, and the construction requirement is met.
2. By adopting the invention to construct the diaphragm, the single hoisting weight is greatly reduced, the hoisting capacity requirement of hoisting equipment is reduced, the construction cost is saved, and the safety is improved.
3. According to the invention, a bracket or other supporting systems are not required to be additionally erected, so that the engineering quantity of auxiliary measures is reduced, the construction cost is reduced, and the construction period is saved.
Description of the drawings:
FIG. 1 is a schematic view of the general structure of the present invention;
FIG. 2 is a schematic view of the diaphragm plate of the present invention in a split mode;
FIG. 3 is a cross-sectional view of a prefabricated cross beam of the present invention;
FIG. 4 is a cross-sectional view of a cast-in-place section of a diaphragm plate of the present invention;
FIG. 5 is a plan view of a cast-in-place section of a diaphragm plate of the present invention.
Reference numerals in the drawings:
the casting device comprises a 1-diaphragm plate, a 2-hollow thin-wall pier cast part, a 3-hollow thin-wall pier non-cast part, a 4-hoisting ring, a 5-diaphragm beam, a 6-diaphragm plate cast-in-situ part, a 7-bottom template, 8-reserved steel bars, 9-anchor beams, 10-pull rods, 11-steel backing plates, 12-anchor bolts, 13-sleeves and 14-connecting steel bars.
The specific embodiment is as follows:
the present invention is further described in connection with the following detailed description, which is a further illustration of the principles of the present invention and not in any way intended to limit the invention, nor is the same or similar technique to the present invention beyond the scope of the present invention.
Referring to fig. 1-5, the invention provides a large-section diaphragm plate of an ultrahigh hollow thin-wall pier, wherein the diaphragm plate 1 with the large section is of a flat plate structure, is arranged at an inner chamfer of a pier column of a poured part 2 of the hollow thin-wall pier, the diaphragm plate 1 with the flat plate structure is split into a strip-shaped structure, and is divided into a prefabricated diaphragm beam 5 and a diaphragm plate cast-in-situ part 6, which are uniformly distributed at intervals, the diaphragm beam 5 is a prefabricated member and is of a strip-shaped concrete structure, the diaphragm beam 5 is prefabricated in a ground-lattice mode, a plurality of transverse and longitudinal reserved steel bars 8 are arranged around the diaphragm beam 5, the reserved steel bars 8 are uniformly and symmetrically arranged at intervals, two layers of reserved steel bars 8 are arranged up and down, and enough welding lengths are reserved for the reserved steel bars 8 around the diaphragm beam 5 so as to meet the lap welding length, and the reserved steel bars 8 are horizontal steel bars of the pier column diaphragm plate in the original design. The top of the diaphragm beam 5 is provided with a hoisting ring 4, and the hoisting ring 4 is made of HPB300 plain round steel bars with phi=16mm. The diaphragm cast-in-situ part 6 is of a strip structure, a certain width is reserved between the adjacent diaphragm beams 5, and finally casting is performed. The prefabricated diaphragm beams 5 are sequentially arranged on the inner chamfer angles of the poured part 2 of the hollow thin-wall pier, and the width of the cast-in-situ part 6 of the diaphragm plate is reserved in the middle. The transverse reserved steel bars 8 of the adjacent diaphragm beams 5 are connected by adopting connecting steel bars 14, and then the diaphragm cast-in-situ part 6 casting space is formed by the anchor beams 9 placed at the tops of the diaphragm beams 5, the steel backing plates 11 at the tops of the anchor beams 9, the anchor bolts 12, the pull rods 10 and the bottom templates 7 buckled at the bottoms of the two adjacent prefabricated diaphragm beams 5, and the diaphragm cast-in-situ part 6 concrete is cast to form the diaphragm 1 with a complete ultrahigh hollow thin-wall pier large section.
The construction steps of the large-section diaphragm plate of the ultrahigh hollow thin-wall pier are as follows:
1) The pier column of the poured part 2 of the hollow thin-wall pier is constructed to the position of the bottom surface of the diaphragm plate 1, and an inner chamfer is arranged (see figure 1).
2) Dividing the diaphragm plate 1 with a flat plate structure into a strip-shaped prefabricated diaphragm beam 5 and a diaphragm plate cast-in-situ part 6, prefabricating and forming the diaphragm beam 5 on the ground, and arranging reserved steel bars 8 around the diaphragm beam 5 and reserving a hoisting ring 4 on the top surface.
3) After the diaphragm beam 5 is prefabricated, when the strength and the elastic modulus of the concrete exceed 85% of the design, the prefabricated diaphragm beam 5 is hoisted and placed on the corresponding position of the inner chamfer of the pier column of the poured part 2 of the hollow thin-wall pier through hoisting equipment such as a tower crane (see figure 2).
4) After the diaphragm beams 5 are installed, the pull rod 10 passes through the bottom template 7 and is screwed by adopting the anchor bolts 12, the whole body obliquely passes through the diaphragm cast-in-situ part 6 and is buckled at the bottoms of the two adjacent diaphragm beams 5, the pull rod 10 is made of finish-rolled screw steel with phi=28 mm, the bottom template 7 is made of steel plate with delta=10 mm, and the anchor bolts 12 are fastening bolts matched with the finish-rolled screw steel. The pull rod 10 is sleeved with a sleeve 13, and the sleeve 13 is made of PVC pipe. The anchoring beam 9 is placed on the top of the diaphragm beam 5 and clamps the pull rod 10, the top is anchored by adopting a steel backing plate 11, then the anchoring bolt 12 on the top is fastened (see fig. 4), the anchoring beam 9 is made of double-limb [100 channel steel ], and the steel backing plate 11 is made of delta=10mm steel plate.
5) The transverse reserved steel bars 8 of the adjacent diaphragm beams 5 are connected by adopting connecting steel bars 14, and concrete of the cast-in-situ part 6 of the diaphragm is poured to form the diaphragm 1 with a complete ultrahigh hollow thin-wall pier and large cross section.
6) And removing the pull rod 10 and the anchoring beam 9, and continuously pouring the non-intersected part 3 of the hollow thin-wall pier of the next section.

Claims (10)

1. A large-section diaphragm plate of an ultrahigh hollow thin-wall pier is characterized in that: the diaphragm plate (1) with the large section is of a flat plate structure and is arranged at the inner chamfer of the pier column of the poured part (2) of the hollow thin-wall pier, and the diaphragm plate (1) of the flat plate structure is divided into a prefabricated diaphragm beam (5) and a diaphragm plate cast-in-situ part (6) which are uniformly distributed at intervals; the method comprises the steps that (1) a diaphragm beam (5) is prefabricated on the ground in a jumping mode, the diaphragm beam (5) is of a strip-shaped concrete structure, reserved steel bars (8) are arranged on the periphery of the diaphragm beam (5), a hoisting ring (4) is arranged on the top of the diaphragm beam, and the reserved steel bars (8) are reserved for a sufficient welding length; the diaphragm cast-in-situ part (6) is of a strip structure, a certain width is reserved between adjacent diaphragm beams (5), and finally casting is performed; sequentially installing prefabricated diaphragm beams (5) on the inner chamfer angles of the poured parts (2) of the hollow thin-wall piers, and reserving the width of a diaphragm cast-in-place part (6) in the middle; the transverse reserved steel bars (8) of the adjacent diaphragm beams (5) are connected by adopting connecting steel bars (14), and then the diaphragm plates are cast in place in casting spaces of diaphragm plate cast-in-situ parts (6) through an anchor beam (9) placed at the top of the diaphragm beams (5), a steel backing plate (11) at the top of the anchor beam (9), anchor bolts (12), pull rods (10) and bottom templates (7) buckled at the bottoms of the two adjacent prefabricated diaphragm beams (5), so that a complete diaphragm plate (1) with an ultrahigh hollow thin-wall pier large cross section is formed.
2. The ultra-high hollow thin wall pier large cross section diaphragm according to claim 1, characterized in that: the bottom template (7) is made of a steel plate with delta=10mm.
3. The ultra-high hollow thin wall pier large cross section diaphragm according to claim 1, characterized in that: the hoisting ring (4) arranged on the diaphragm (5) is made of HPB300 smooth round steel bars with phi=16mm.
4. The ultra-high hollow thin wall pier large cross section diaphragm according to claim 1, characterized in that: the transverse diaphragm (5) is provided with a plurality of transverse and longitudinal reserved steel bars (8) which are uniformly spaced and symmetrically arranged.
5. The ultra-high hollow thin wall pier large cross section diaphragm according to claim 1, characterized in that: the anchoring beam (9) is made of double-limb [100 channel steel ].
6. The ultra-high hollow thin wall pier large cross section diaphragm according to claim 1, characterized in that: the pull rod (10) is made of finish rolled deformed steel bar with phi=28mm.
7. The ultra-high hollow thin wall pier large cross section diaphragm according to claim 1, characterized in that: the steel backing plate (11) is made of a steel plate with delta=10mm.
8. The ultra-high hollow thin wall pier large cross section diaphragm according to claim 1, characterized in that: the anchoring bolt (12) is a fastening bolt matched with the finish rolling screw steel.
9. The ultra-high hollow thin wall pier large cross section diaphragm according to claim 1, characterized in that: a sleeve (13) is sleeved on the pull rod (10), and the sleeve (13) is made of PVC (polyvinyl chloride) tubes.
10. A construction method of a diaphragm plate with a large section of an ultrahigh hollow thin-wall pier is characterized by comprising the following steps: the construction steps are as follows:
1) Constructing pier columns of the poured part (2) of the hollow thin-wall pier to the bottom surface of the diaphragm plate (1), and arranging an inner chamfer;
2) Dividing a diaphragm plate (1) with a flat plate structure into a strip-shaped diaphragm beam (5) and a diaphragm plate cast-in-situ part (6), prefabricating and forming the diaphragm beam (5) on the ground, arranging reserved steel bars (8) around the diaphragm beam (5), and reserving a hoisting ring (4) on the top surface;
3) Hoisting and placing the transverse beam (5) at the corresponding position of the inner chamfer of the pier column of the poured part (2) of the hollow thin-wall pier after prefabrication is completed;
4) After the diaphragm beams (5) are installed, a pull rod (10) passes through the bottom template (7) and is screwed by adopting an anchor bolt (12), the whole diaphragm beam passes through the diaphragm cast-in-situ part (6) in an inclined way, and the pull rod is buckled at the bottoms of two adjacent diaphragm beams (5); sleeving a sleeve (13) on the pull rod (10), placing an anchoring beam (9) at the top of the diaphragm beam (5) and clamping the pull rod (10), wherein the top is anchored by adopting a steel backing plate (11);
5) The transverse reserved steel bars (8) of the adjacent diaphragm beams (5) are connected by adopting connecting steel bars (14), and concrete is poured into a cast-in-place part (6) of the diaphragm to form a complete diaphragm (1) with an ultrahigh hollow thin-wall pier and a large cross section;
6) And (3) dismantling the pull rod (10) and the anchoring beam (9), and continuously pouring the non-poured part (3) of the hollow thin-wall pier of the next section.
CN202210350447.6A 2022-04-02 2022-04-02 Ultrahigh hollow thin-wall pier large-section diaphragm plate and construction method Active CN114622492B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210350447.6A CN114622492B (en) 2022-04-02 2022-04-02 Ultrahigh hollow thin-wall pier large-section diaphragm plate and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210350447.6A CN114622492B (en) 2022-04-02 2022-04-02 Ultrahigh hollow thin-wall pier large-section diaphragm plate and construction method

Publications (2)

Publication Number Publication Date
CN114622492A CN114622492A (en) 2022-06-14
CN114622492B true CN114622492B (en) 2023-11-10

Family

ID=81906851

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210350447.6A Active CN114622492B (en) 2022-04-02 2022-04-02 Ultrahigh hollow thin-wall pier large-section diaphragm plate and construction method

Country Status (1)

Country Link
CN (1) CN114622492B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115787504B (en) * 2022-12-16 2023-09-12 中铁二局集团有限公司 Hanger platform and construction method of hollow tower pier top solid section

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104060738A (en) * 2014-06-30 2014-09-24 沈阳建筑大学 Reserved cast-in-situ strip assembly integral concrete floor slab
CN108457411A (en) * 2018-05-31 2018-08-28 杭州通达集团有限公司 A kind of laminated floor slab and its construction method of assembled architecture
CN109403200A (en) * 2018-11-22 2019-03-01 上海市政交通设计研究院有限公司 The construction method and its small box girder bridge of the small box girder bridge poured after a kind of partition
CN113174862A (en) * 2021-04-29 2021-07-27 中交路桥建设有限公司 Construction method of diaphragm plate in high pier and diaphragm plate structure system in high pier
CN215104773U (en) * 2021-07-09 2021-12-10 中铁十一局集团第五工程有限公司 Hollow mound baffle of bridge does not have support construction support system
CN215889347U (en) * 2020-11-27 2022-02-22 广东龙越建筑工程有限公司 Post-cast strip formwork device

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2015131334A1 (en) * 2014-03-04 2015-09-11 东莞市石西智能机器制造有限公司 Building structure and construction method for same

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104060738A (en) * 2014-06-30 2014-09-24 沈阳建筑大学 Reserved cast-in-situ strip assembly integral concrete floor slab
CN108457411A (en) * 2018-05-31 2018-08-28 杭州通达集团有限公司 A kind of laminated floor slab and its construction method of assembled architecture
CN109403200A (en) * 2018-11-22 2019-03-01 上海市政交通设计研究院有限公司 The construction method and its small box girder bridge of the small box girder bridge poured after a kind of partition
CN215889347U (en) * 2020-11-27 2022-02-22 广东龙越建筑工程有限公司 Post-cast strip formwork device
CN113174862A (en) * 2021-04-29 2021-07-27 中交路桥建设有限公司 Construction method of diaphragm plate in high pier and diaphragm plate structure system in high pier
CN215104773U (en) * 2021-07-09 2021-12-10 中铁十一局集团第五工程有限公司 Hollow mound baffle of bridge does not have support construction support system

Also Published As

Publication number Publication date
CN114622492A (en) 2022-06-14

Similar Documents

Publication Publication Date Title
CN108505433B (en) Pier structure and construction method thereof
CN108265885B (en) Construction method of high-large non-orthogonal large-inclination-angle special-shaped concrete inclined column
CN110886227B (en) Main tower cast-in-place lower cross beam support system and construction method
CN208917702U (en) Fish-bellied type concrete box girder cast-in-place construction formwork-support
CN112502714B (en) Assembled shaft barrel structure and design and construction method
CN114622492B (en) Ultrahigh hollow thin-wall pier large-section diaphragm plate and construction method
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN111877129B (en) Arch ring construction method of continuous arch bridge
CN110067206B (en) Construction method of egg-shaped underpass bridge
CN206769199U (en) After wear formula post stretching vertical prestressing cast-in-place concrete rod structure
CN216108007U (en) Concrete beam type bridge and cast-in-situ hidden cover beam thereof
CN217974018U (en) Large-section diaphragm plate of ultrahigh hollow thin-wall pier
CN213233106U (en) Arch ring support
CN110792282B (en) Transformation method of frame column without support underpinning
KR100351135B1 (en) Method of constructing arch ring of steel framed reinforced concrete arch bridge
JP3098359B2 (en) Column base structure and construction method thereof
CN218989872U (en) Hollow pier diaphragm plate assembled by trapezoid cross-section beams
CN110714613B (en) Reinforcing device for ultra-high large-span steel reinforced concrete cast-in-place beam template and construction method
CN114086479B (en) Tower foot anchoring structure for assembling tower and tower building method
CN217151146U (en) Super 5 meters girder steel subassembly of encorbelmenting of concrete form support system that encorbelments
CN216947881U (en) Formwork support of I-shaped composite beam cast-in-situ bridge deck
CN219887655U (en) Reinforcing structure of steel structure sliding beam
CN211522880U (en) Wet seam hanging mould for prefabricated bridge deck
CN116556567B (en) Design and construction method of large-span steel bar truss floor support plate deflection limiting system
CN112323640B (en) Construction method for temporary cable-stayed corrugated steel web bridge advanced closure web

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant