CN114520996A CN202210129122.5A CN202210129122A CN114520996A CN 114520996 A CN114520996 A CN 114520996A CN 202210129122 A CN202210129122 A CN 202210129122A CN 114520996 A CN114520996 A CN 114520996A
Authority
CN
China
Prior art keywords
mgl
ssb
determining
burst set
measurement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210129122.5A
Other languages
Chinese (zh)
Other versions
CN114520996B (en
Inventor
景伟
张金成
张姚姚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Xiaomi Mobile Software Co Ltd
Original Assignee
Beijing Xiaomi Mobile Software Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Xiaomi Mobile Software Co Ltd filed Critical Beijing Xiaomi Mobile Software Co Ltd
Priority to CN202210129122.5A priority Critical patent/CN114520996B/en
Publication of CN114520996A publication Critical patent/CN114520996A/en
Application granted granted Critical
Publication of CN114520996B publication Critical patent/CN114520996B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W24/00Supervisory, monitoring or testing arrangements
    • H04W24/08Testing, supervising or monitoring using real traffic
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W24/00Supervisory, monitoring or testing arrangements
    • H04W24/10Scheduling measurement reports ; Arrangements for measurement reports
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W56/00Synchronisation arrangements
    • H04W56/001Synchronization between nodes
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02DCLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
    • Y02D30/00Reducing energy consumption in communication networks
    • Y02D30/70Reducing energy consumption in communication networks in wireless communication networks

Abstract

The disclosure relates to a method and a device for configuring measurement gap length, which are applied to User Equipment (UE), and the method comprises the following steps: acquiring a sending period of a SSB burst set of a synchronous signal block; acquiring a first measurement gap length MGL configured for the UE by a base station; determining a second MGL for completing the measurement of the set of SSB bursts in response to determining that the measurement of the set of SSB bursts cannot be completed within the first MGL according to a transmission period of the set of SSB bursts; measuring the set of SSB bursts based on the second MGL. According to the present disclosure, if the first MGL configured by the base station for the UE cannot cover the transmission period of the SSB burst set, the UE may modify the MGL configured by the base station for the UE, so that the measurement of the SSB burst set may be completed based on the modified second MGL, thereby reducing the time duration for the UE to switch to the endec mode or the NR cell.

Description

Measurement gap length configuration method and device
Technical Field
The present disclosure relates to the field of communications technologies, and in particular, to a method and an apparatus for configuring a measurement gap length.
Background
In a system in which LTE (Long Term Evolution) and NR (New Radio, New air interface) coexist or an NR system, a cell may transmit a SSB (Synchronization Signal block) burst Set (Set) at a certain period to repeatedly perform beam scanning; and a UE (User Equipment) may measure the SSB burst set within a measurement Gap (measgap) configured for it by the base station to switch to an endec (E-UTRA NR Dual-Connectivity, E-UTRA NR Dual Connectivity) mode or an NR cell.
In the related art, the actual transmission period of the SSB burst set may be different, for example, the actual transmission period of the SSB burst set may be 5, 10, 20, 40, 80, 160ms, etc.; while the MGL (measgap Length) configured for the UE in the LTE cell is typically fixed, e.g., the MGL may be 6ms, etc. Therefore, in the related art, if the MGL configured by the base station for the UE cannot cover the actual transmission period of the SSB burst set, the UE may not measure the SSB burst set in the measurement gap, and the UE may not be quickly switched to the endec mode or the NR cell.
Disclosure of Invention
The present disclosure provides a method and an apparatus for configuring a measurement gap length to solve the deficiencies of the related art.
According to a first aspect of the embodiments of the present disclosure, a method for configuring a measurement gap length is provided, where the method is applied to a user equipment UE, and the method includes:
acquiring a sending period of a SSB burst set of a synchronous signal block;
acquiring a first measurement gap length MGL configured for the UE by a base station;
determining a second MGL for completing the measurement of the set of SSB bursts in response to determining that the measurement of the set of SSB bursts cannot be completed within the first MGL according to a transmission period of the set of SSB bursts;
measuring the set of SSB bursts based on the second MGL.
Optionally, the determining that the measurement of the SSB burst set cannot be completed within the first MGL according to the transmission period of the SSB burst set includes:
and if the sum of a first time length corresponding to the sending period of the SSB burst set and a preset time length is greater than a second time length corresponding to the first MGL, determining that the measurement of the SSB burst set cannot be completed in the first MGL.
Optionally, the determining a second MGL for completing the measurement of the SSB burst set includes:
and determining a second MGL corresponding to the obtained sending period of the SSB burst set according to the corresponding relation between the sending period of the SSB burst set and the second MGL.
Optionally, the obtaining a sending period of the SSB burst set includes:
and acquiring the sending period of the SSB burst set based on the system information issued by the base station.
Optionally, before the obtaining the sending period of the SSB burst set based on the system message delivered by the base station, the method further includes:
determining a transmission period of the set of SSB bursts indicated in the system message.
Optionally, the determining that the system message indicates a sending period of the SSB burst set includes:
determining that the transmission period of the set of SSB bursts is indicated in the system message in response to determining that a parameter indicating the transmission period of the set of SSB bursts is included in the system message.
Optionally, the method further comprises:
in response to determining that the transmission period of the set of SSB bursts is not indicated in the system message, determining that the transmission period of the set of SSB bursts is a specified period.
Optionally, the method further comprises:
determining a third MGL corresponding to the designated period;
measuring the set of SSB bursts based on the third MGL.
Optionally, the method further comprises:
measuring the set of SSB bursts based on the first MGL in response to determining that the measurement of the set of SSB bursts can be completed within the first MGL according to a transmission period of the set of SSB bursts.
Optionally, the acquiring the first MGL configured by the base station for the UE includes:
and acquiring a first MGL configured for the UE by the base station based on a Radio Resource Control (RRC) reconfiguration signaling issued by the base station.
According to a second aspect of the embodiments of the present disclosure, an apparatus for configuring measurement gap length is provided, which is applied to a user equipment UE, and the apparatus includes:
the first acquisition module is used for acquiring the sending period of the SSB burst set of the synchronous signal block;
a second obtaining module, configured to obtain a first measurement gap length MGL configured by a base station for the UE;
a first determining module, configured to determine a second MGL for completing measurement of the SSB burst set in response to determining that the measurement of the SSB burst set cannot be completed within the first MGL according to a transmission period of the SSB burst set;
a first measurement module to measure the set of SSB bursts based on the second MGL.
According to a third aspect of the embodiments of the present disclosure, there is provided a user equipment, including:
a processor;
a memory for storing processor-executable instructions;
wherein, the processor is used for executing the measurement gap length configuration method.
According to a fourth aspect of embodiments of the present disclosure, there is provided a computer-readable storage medium having stored thereon a computer program for executing the above-described measurement gap length configuration method.
The technical scheme provided by the embodiment of the disclosure at least has the following beneficial effects:
according to the embodiment of the present disclosure, in response to determining that measurement of the SSB burst set cannot be completed within the first MGL configured by the base station for the UE according to the obtained sending period of the SSB burst set, the UE may determine a second MGL used for completing measurement of the SSB burst set, and may measure the SSB burst set based on the second MGL. Therefore, if the first MGL configured by the base station for the UE cannot cover the transmission period of the SSB burst set, the UE may modify the MGL configured by the base station for the UE, so that the measurement on the SSB burst set may be completed based on the modified second MGL, thereby reducing the time duration for the UE to switch to the endec mode or the NR cell.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present disclosure, the drawings needed to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present disclosure, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without inventive labor.
Fig. 1 is a schematic diagram illustrating a correspondence relationship between a beam sweep and an SSB burst set according to an embodiment of the disclosure.
Fig. 2 is a schematic flow chart diagram illustrating a measurement gap length configuration method according to an embodiment of the present disclosure.
Fig. 3 is a schematic flow chart diagram illustrating another measurement gap length configuration method in accordance with an embodiment of the present disclosure.
Fig. 4 is a schematic flow chart diagram illustrating another measurement gap length configuration method in accordance with an embodiment of the present disclosure.
Fig. 5 is a schematic flow chart diagram illustrating another measurement gap length configuration method in accordance with an embodiment of the present disclosure.
Fig. 6 is a schematic flow chart diagram illustrating another measurement gap length configuration method in accordance with an embodiment of the present disclosure.
Fig. 7 is a schematic flow chart diagram illustrating another measurement gap length configuration method in accordance with an embodiment of the present disclosure.
Fig. 8 is a schematic flow chart diagram illustrating another measurement gap length configuration method in accordance with an embodiment of the present disclosure.
Fig. 9 is a schematic flow chart diagram illustrating another measurement gap length configuration method in accordance with an embodiment of the present disclosure.
Fig. 10 is a schematic block diagram illustrating a measurement gap length configuration apparatus according to an embodiment of the present disclosure.
Fig. 11 is a schematic block diagram illustrating another measurement gap length configuration apparatus in accordance with an embodiment of the present disclosure.
Fig. 12 is a schematic block diagram illustrating another measurement gap length configuration apparatus in accordance with an embodiment of the present disclosure.
Fig. 13 is a schematic block diagram illustrating another measurement gap length configuration apparatus in accordance with an embodiment of the present disclosure.
Fig. 14 is a schematic block diagram illustrating another measurement gap length configuration apparatus in accordance with an embodiment of the present disclosure.
Fig. 15 is a schematic block diagram illustrating another measurement gap length configuration apparatus in accordance with an embodiment of the present disclosure.
Fig. 16 is a schematic block diagram illustrating another measurement gap length configuration apparatus in accordance with an embodiment of the present disclosure.
Fig. 17 is a schematic block diagram illustrating a configuration apparatus for measuring gap length in accordance with an embodiment of the present disclosure.
Detailed Description
The technical solutions in the embodiments of the present disclosure will be clearly and completely described below with reference to the drawings in the embodiments of the present disclosure, and it is obvious that the described embodiments are only a part of the embodiments of the present disclosure, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments disclosed herein without making any creative effort, shall fall within the protection scope of the present disclosure.
In the process of mobility management, a UE (User Equipment) needs to measure signals of neighboring cells and signals of other carriers. Due to manufacturing cost, a UE generally has only one RF (Radio Frequency) module, and thus the UE can measure or transmit data using only a single RF module. When needing to measure the adjacent cell signals with the same frequency, the UE can transmit data in the current service cell at the same time; when the signals of the inter-frequency neighboring cell or other RAT (Radio Access Technology) cell need to be measured, the UE may suspend communication with the current serving cell, adjust the RF module for measurement, readjust the RF module after a period of time, and resume communication with the serving cell. Wherein the UE suspends communication with the serving cell to measure a time interval of an inter-frequency neighbor cell or other wireless neighbor cells, which may be referred to as a measurement Gap (measgap).
Referring to fig. 1, fig. 1 is a schematic diagram illustrating a correspondence relationship between a beam sweep and an SSB burst set according to an embodiment of the disclosure. In a system where LTE (Long Term Evolution) and NR (New Radio) coexist or an NR system, a cell may transmit an SSB
(Synchronization Signal block, synchronous Signal block) burst Set to realize one-time beam scanning and cover the service range of the whole cell; the SSB burst set may be sent at a certain period to repeatedly perform beam scanning; and the UE may measure the SSB burst set within a measurement gap configured for it by the base station to switch to an endec (E-UTRA NR Dual-Connectivity) mode or NR cell.
When the network configures the sending period of the SSB burst set, factors such as system resource consumption, UE access delay and the like need to be considered; for example, configuring a shorter sending period of the SSB burst set may reduce UE access delay, reduce time and power consumption required for the UE to measure the SSB burst set, but consume more system resources; for another example, configuring a longer transmission period of the SSB burst set may reduce consumption of system resources, but may increase UE access delay. In the related art, the actual transmission period of the SSB burst set may be different, for example, the actual transmission period of the SSB burst set may be 5, 10, 20, 40, 80, 160ms, and the like.
Whereas in an LTE cell, the MGL (measgap Length) configured for a UE is typically fixed, e.g., the MGL may be 6ms or the like.
It can be seen that, in the related art, if the MGL configured by the base station for the UE cannot cover the actual transmission period of the SSB burst set, the UE may not measure the SSB burst set in the measurement gap, and thus the UE may not be quickly switched to the endec mode or the NR cell.
Referring to fig. 2, fig. 2 is a schematic flow chart illustrating a method for configuring a measurement gap length according to an embodiment of the disclosure.
In the embodiments of the present disclosure, the measurement gap length configuration method may be applied to UEs including, but not limited to, mobile phones, tablet computers, wearable devices, sensors, internet of things devices, and other electronic devices. The UE may communicate with a base station. The base stations may include, but are not limited to, 4G base stations, 5G base stations, 6G base stations, or base stations of any generation communication system.
In one embodiment, the UE may be in an RRC CONNECTED state (RRC _ CONNECTED); the UE may reside in an LTE network.
In one embodiment, when performing the initial cell search, the UE may determine a transmission period of the SSB burst set to be 20ms specified in 3GPP (3rd Generation Partnership Project) protocol. After the initial cell search is completed, the UE may register in the LTE network, and may also receive a system message broadcasted in the current serving cell, and parse the system message to obtain an actual transmission period of the SSB burst set.
As shown in fig. 2, the method for configuring the length of the measurement gap may include the following steps:
in step 202, a transmission period of a set of bursts of synchronization signal blocks SSB is acquired.
For example, the UE may obtain a transmission period of an SSB burst set; the transmission period of the SSB burst set may specifically be 5ms, 10ms, 20ms, 40ms, 80ms, 160ms, and the like.
In step 204, a first measurement gap length MGL configured by the base station for the UE is obtained.
Wherein the first MGL may include an MGL configured by the base station for the UE.
For example, the UE may acquire a first MGL configured for it by the base station; wherein the first MGL configured for the UE in the LTE cell may be 6 ms. It should be noted that this is merely an exemplary description, and the disclosure is not limited with respect to a specific time duration of the first MGL.
In step 206, in response to determining that the measurement of the set of SSB bursts cannot be completed within the first MGL according to the transmission period of the set of SSB bursts, a second MGL for completing the measurement of the set of SSB bursts is determined.
Wherein the second MGL may include an MGL determined by the UE; that is, the UE may modify the first MGL for which the base station is configured to obtain the second MGL used to complete the measurement of the set of SSB bursts.
For example, the UE may acquire a transmission period of an SSB burst set as 10ms, and may acquire the first MGL as 6 ms; in response to determining that the measurement of the set of SSB bursts cannot be completed within the first MGL according to a transmission period of the set of SSB bursts, the UE may determine a second MGL for completing the measurement of the set of SSB bursts; when the obtained sending period of the SSB burst set is 10ms, the determined second MGL may be 11ms, or may be other time lengths that can be used to complete measurement of the SSB burst set, which is not limited in this disclosure.
In step 208, the set of SSB bursts is measured based on the second MGL.
For example, after determining that the second MGL may be 11ms in response to determining that the measurement of the set of SSB bursts cannot be completed within the first MGL according to the transmission period of the set of SSB bursts, the set of SSB bursts may be measured based on the determined second MGL.
As can be seen from the foregoing embodiments, in response to determining that measurement of the SSB burst set cannot be completed within the first MGL configured by the base station for the UE according to the obtained sending period of the SSB burst set, the UE may determine a second MGL used for completing measurement of the SSB burst set, and may measure the SSB burst set based on the second MGL. Therefore, if the first MGL configured by the base station for the UE cannot cover the transmission period of the SSB burst set, the UE may modify the MGL configured by the base station for the UE, so that the measurement of the SSB burst set may be completed based on the modified second MGL, thereby reducing the time duration for the UE to switch to the endec mode or the NR cell.
Referring to fig. 3, fig. 3 is a schematic flow chart of another measurement gap length configuration method based on the embodiment shown in fig. 2. As shown in fig. 3, the obtaining a sending period of the SSB burst set may include:
in step 302, a sending period of the SSB burst set is obtained based on a system message issued by the base station.
Optionally, before the step 302, the UE may receive a system message sent by the base station. For a specific implementation manner that the base station indicates the sending period of the SSB burst set to the UE through the system message, please refer to related technologies, which is not described herein again.
For example, the UE may receive a system message sent by the base station, and obtain a sending period of the SSB burst set based on the received system message; the transmission period of the SSB burst set may specifically be 5ms, 10ms, 20ms, 40ms, 80ms, 160ms, and the like.
Optionally, before the step 302, the method may further include:
in step 304, a transmission period of the set of SSB bursts is determined to be indicated in the system message.
For example, the UE, in response to receiving the system message, may determine whether a transmission period of the set of SSB bursts is indicated in the system message; if it is determined that the system message indicates the sending period of the SSB burst set, the sending period of the SSB burst set may be obtained based on the received system message.
Optionally, in the step 304, the determining that the system message indicates the sending period of the SSB burst set may specifically include: determining that the transmission period of the set of SSB bursts is indicated in the system message in response to determining that a parameter indicating the transmission period of the set of SSB bursts is included in the system message.
For example, the UE may determine whether a system message sent by the base station includes a parameter for indicating a transmission period of the SSB burst set; in response to determining that the system message includes a parameter indicating a transmission period of the set of SSB bursts, determining that the transmission period of the set of SSB bursts is indicated in the system message; further, a sending period of the SSB burst set may be obtained based on the system message.
Optionally, in the step 304, the system message may specifically include a SIB1 message in the LTE network. Optionally, the parameter for indicating the sending period of the SSB burst set may specifically include a period serviceservingcellsib parameter included in the SIB1 message, or may also include other parameters that can be used to indicate the sending period of the SSB burst set and are included in the system message, which is not limited in this disclosure. Optionally, the obtaining the sending period of the SSB burst set based on the system message issued by the base station may specifically include: and acquiring the sending period of the SSB burst set based on the value of the parameter which is included in the system message and used for indicating the sending period of the SSB burst set.
Optionally, since the step 202 and the step 204 may be performed non-consecutively, for the convenience of subsequent processing, at the same time or after the step 302, the method may further include:
in step 306, in response to determining that the system message indicates the sending period of the SSB burst set, determining a value of a first flag and a value of a second flag; when the first flag takes a first value, the first flag may be used to indicate a transmission period of the SSB burst set indicated in the system message; when the first flag takes a second value, the first flag may be used to indicate that the transmission period of the SSB burst set is not indicated in the system message; the value of the second flag may be used to indicate the obtained sending period of the SSB burst set.
For example, the first flag may be denoted as X, the second flag may be denoted as Y, the first value may be 1, and the second value may be 0; in response to determining that the transmission period of the SSB burst set is indicated in the system message, the first flag X may be determined to be 1, and the second flag Y may be determined to be 10ms according to the transmission period (e.g., 10ms) of the SSB burst set indicated by the value of the parameter. It should be noted that, in the above illustrated embodiment, the first flag may be denoted as X, the second flag may be denoted as Y, the first numerical value may be 1, and the second numerical value may be 0, which is only an exemplary description manner and is not limited by the present disclosure.
As can be seen from the foregoing embodiment, by determining that the sending period of the SSB burst set is indicated in the system message sent by the base station, the sending period of the SSB burst set may be obtained based on the system message. Therefore, the accuracy of acquiring the sending period of the SSB burst set by the UE can be improved, and the accuracy of determining the MGL used for measuring the SSB burst set according to the sending period of the SSB burst set can be further improved, that is, the accuracy of performing MGL configuration for the UE can be improved.
Referring to fig. 4, fig. 4 is a schematic flow chart of another measurement gap length configuration method based on the embodiment shown in fig. 3. As shown in fig. 4, the method may further include:
in step 402, in response to determining that the sending period of the SSB burst set is not indicated in the system message, determining the sending period of the SSB burst set to be a specified period.
The specified period may include a transmission period of an SSB burst set preconfigured for the UE.
For example, in response to receiving a system message sent by the base station, the UE may determine whether a sending period of the SSB burst set is indicated in the system message; if it is determined that the sending period of the SSB burst set is not indicated in the system message, it may be determined that the sending period of the SSB burst set is a designated period; the specified period may be 5ms, which is to be noted that this is merely an exemplary description, and the disclosure is not limited with respect to the specific duration of the specified period.
Optionally, in the step 402, the determining that the sending period of the SSB burst set is not indicated in the system message may specifically include: determining that the transmission period of the set of SSB bursts is not indicated in the system message in response to determining that the parameter indicating the transmission period of the set of SSB bursts is not included in the system message.
For example, the UE may determine whether a system message sent by the base station includes a parameter for indicating a transmission period of the SSB burst set; in response to determining that the parameter indicating the transmission period of the set of SSB bursts is not included in the system message, determining that the transmission period of the set of SSB bursts is not indicated in the system message; a transmission period of the set of SSB bursts may be determined to be the specified period preconfigured for the UE.
Optionally, in the step 402, the system message may specifically include a SIB1 message in the LTE network. Optionally, the parameter for indicating the sending period of the SSB burst set may specifically include a period serviceservingcellsib parameter included in the SIB1 message, or may also include other parameters that can be used to indicate the sending period of the SSB burst set and are included in the system message, which is not limited in this disclosure. Optionally, the obtaining the sending period of the SSB burst set based on the system message issued by the base station may specifically include: and acquiring the sending period of the SSB burst set based on the value of the parameter which is included in the system message and used for indicating the sending period of the SSB burst set.
Optionally, since the step 202 and the step 204 may be performed non-consecutively, for the convenience of subsequent processing, at the same time or after the step 402, the method may further include:
in step 404, in response to determining that the sending period of the SSB burst set is not indicated in the system message, determining a value of a first flag and a value of a second flag; when the first flag takes a first value, the first flag may be used to indicate a transmission period of the SSB burst set indicated in the system message; when the first flag takes a second value, the first flag may be used to indicate that the transmission period of the SSB burst set is not indicated in the system message; the value of the second flag may be used to indicate the designated period.
For example, the first flag may be denoted as X, the second flag may be denoted as Y, the first value may be 1, and the second value may be 0; in response to determining that a transmission period of the set of SSB bursts is not indicated in the system message, the first flag X may be determined to be 0, and the second flag Y may be determined to be 5ms according to the specified period (e.g., 5 ms).
Optionally, after the step 402, the method may further include:
in step 406, determining a third MGL corresponding to the specified period;
wherein the third MGL may include a specific MGL corresponding to the specific period, which is configured in advance for the UE.
For example, the designated period may be 5ms, and the third MGL corresponding to the designated period may be determined to be 21 ms.
In step 408, the set of SSB bursts is measured based on the third MGL.
For example, in response to determining that the sending period of the SSB burst set is not indicated in the system message sent by the base station, the UE may determine that the sending period of the SSB burst set is the designated period, where the designated period may be 5 ms; a third MGL corresponding to the designated period may be determined, and the third MGL corresponding to the designated period may be 21 ms; further, the set of SSB bursts may be measured based on the third MGL.
It should be noted that, in the above illustrated embodiment, when the specified period is 5ms, the third MGL corresponding to the specified period may be 21ms, which is merely an exemplary description and is not limited by the present disclosure; when implemented, the skilled person can flexibly configure the duration of the third MGL according to the requirements. For example, in a certain application scenario, in order to reduce the access delay of the UE and reduce the power consumption of the SSB burst set measured by the UE, the transmission period of the SSB burst set is usually not too long; if the probability that the transmission period of the acquired SSB burst set exceeds 40ms is small, the third MGL corresponding to a specified period of 5ms may be configured in advance to be 41 ms. For another example, the UE may be further configured with a correspondence between another duration of the specified period and another duration of the third MGL.
As can be seen from the foregoing embodiment, by determining that the sending period of the SSB burst set is not indicated in the system message delivered by the base station, the sending period of the SSB burst set may be determined to be the specified period. Therefore, the reliability of acquiring the sending period of the SSB burst set by the UE can be improved, and the reliability of determining the MGL for measuring the SSB burst set according to the sending period of the SSB burst set, that is, the reliability of performing MGL configuration for the UE can be improved.
Further, as can be seen from the foregoing embodiments, in response to determining that the transmission period of the SSB burst set is the specified period, a third MGL corresponding to the specified period may be determined, and the SSB burst set may be measured based on the third MGL, so that accuracy of MGL configuration for the UE may be improved.
Referring to fig. 5, fig. 5 is a schematic flow chart of another measurement gap length configuration method based on the embodiment shown in fig. 2. As shown in fig. 5, the determining that the measurement of the SSB burst set cannot be completed within the first MGL according to the transmission period of the SSB burst set includes:
in step 502, if a sum of a first duration corresponding to a sending period of the SSB burst set and a preset duration is greater than a second duration corresponding to the first MGL, it is determined that the measurement of the SSB burst set cannot be completed within the first MGL.
Wherein, the first duration may include a duration corresponding to a transmission period of at least one SSB burst set; the preset duration may include a sum of durations required for the RF module carried by the UE to adjust at the start and end of the measurement gap; the second duration may include a duration corresponding to the first MGL.
For example, the sending period of the obtained SSB burst set may be 10ms, and the first duration may be 10 ms; the time length required for adjusting the RF module carried by the UE at the beginning and the end of the measurement gap may be 0.5ms, respectively, and then the preset time length may be 1 ms; the obtained first MGL configured by the base station for the UE may be 6ms, and the second duration may be 6 ms; since the sum of the first duration and the preset duration (10+1 ═ 11ms) is greater than the second duration (6ms), it may be determined that the measurement of the SSB burst set cannot be completed within the first MGL; a second MGL for completing measurement of the set of SSB bursts may be determined (e.g., the second MGL may be 11ms), and the set of SSB bursts may be measured based on the determined second MGL.
As can be seen from the foregoing embodiment, if a sum of a first duration corresponding to a sending period of the SSB burst set and a preset duration is greater than a second duration corresponding to the first MGL, the UE may determine that measurement on the SSB burst set cannot be completed in the first MGL. Therefore, whether the measurement of the SSB burst set can be completed in the first MGL is determined by judging whether the first MGL configured by the base station for the UE can cover the sending period of the SSB burst set, and then the UE can determine whether the first MGL needs to be modified, so that the time length for the UE to switch to an ENDC mode or an NR cell is reduced.
Referring to fig. 6, fig. 6 is a schematic flow chart of another measurement gap length configuration method based on the embodiment shown in fig. 2. As shown in fig. 6, the determining a second MGL for completing the measurement of the SSB burst set includes:
in step 602, according to a correspondence relationship between a transmission period of an SSB burst set and a second MGL, the second MGL corresponding to the acquired transmission period of the SSB burst set is determined.
Optionally, in step 602, a corresponding relationship between a transmission period of the SSB burst set and the second MGL may be preconfigured for the UE. For example, please refer to table 1, where table 1 shows a correspondence relationship between a transmission period of an SSB burst set and a second MGL according to an embodiment of the present disclosure.
Transmission period of SSB burst set Second MGL
5ms 6ms
10ms 11ms
20ms 21ms
40ms 41ms
80ms 81ms
160ms 161ms
TABLE 1
For example, if the UE can acquire the SSB burst set with a transmission period of 10ms, and can acquire the first MGL with a transmission period of 6 ms; in response to determining that the measurement on the SSB burst set cannot be completed in the first MGL according to the sending period of the SSB burst set, the UE may determine that the second MGL corresponding to the obtained sending period of the SSB burst set may be 11ms according to a correspondence between the sending period of the SSB burst set and the second MGL shown in table 1; further, the UE may measure the set of SSB bursts based on the second MGL.
It should be noted that, in the above illustrated embodiment, the correspondence relationship between the transmission period of the SSB burst set and the second MGL shown in table 1 is merely an exemplary description, and the present disclosure is not limited thereto, and a person skilled in the art may flexibly set the second MGL corresponding to the transmission period of the SSB burst set according to needs. For example, the second MGL corresponding to the transmission cycle of the SSB burst set of 10ms may be any time length longer than 11ms, in addition to 11ms, which is not listed here.
As can be seen from the foregoing embodiments, in response to determining that the measurement on the SSB burst set cannot be completed in the first MGL according to the transmission period of the SSB burst set, a second MGL used for completing the measurement on the SSB burst set may be determined according to a corresponding relationship between the transmission period of the SSB burst set and the second MGL. Therefore, the accuracy of determining the second MGL by the UE, that is, the accuracy of MGL configuration for the UE can be improved.
Referring to fig. 7, fig. 7 is a schematic flow chart of another measurement gap length configuration method based on the embodiment shown in fig. 2. As shown in fig. 7, the method further comprises:
in step 702, the set of SSB bursts is measured based on the first MGL in response to determining that the measurement of the set of SSB bursts can be completed within the first MGL according to a transmission period of the set of SSB bursts.
For example, the UE may obtain a transmission cycle of an SSB burst set as 5ms, and may obtain the first MGL configured for it by the base station as 6 ms; in response to determining that the measurement of the set of SSB bursts can be completed within the first MGL according to a transmission period of the set of SSB bursts, the UE may measure the set of SSB bursts directly based on the first MGL without re-determining the second MGL.
In the step 702, the determining that the measurement on the SSB burst set can be completed in the first MGL according to the sending period of the SSB burst set may specifically include: and if the sum of a first time length corresponding to the sending period of the SSB burst set and a preset time length is less than or equal to a second time length corresponding to the first MGL, determining that the measurement of the SSB burst set can be completed in the first MGL.
Wherein, the first duration may include a duration corresponding to a transmission period of at least one SSB burst set; the preset duration may include a sum of durations required for adjusting, by an RF module carried by the UE, a start position and an end position of a measurement gap; the second duration may include a duration corresponding to the first MGL.
For example, the sending period of the acquired SSB burst set may be 5ms, and then the first time duration may be 5 ms; the time length required for adjusting the RF module carried by the UE at the beginning and the end of the measurement gap may be 0.5ms, respectively, and then the preset time length may be 1 ms; the obtained first MGL configured by the base station for the UE may be 6ms, and the second duration may be 6 ms; since the sum of the first duration and the preset duration (5+1 ═ 6ms) is equal to the second duration (6ms), it may be determined that the measurement of the SSB burst set can be completed within the first MGL; further, the set of SSB bursts may be measured based on the first MGL.
For another example, the sending period of the obtained SSB burst set may be 10ms, and the first duration may be 10 ms; the time length required for adjusting the RF module carried by the UE at the beginning and the end of the measurement gap may be 0.5ms, respectively, and then the preset time length may be 1 ms; the first MGL may be 21ms, and the second duration may be 21 ms; since the sum of the first duration and the preset duration (10+1 ═ 11ms) is less than the second duration (21ms), it may be determined that the measurement of the SSB burst set can be completed within the first MGL; further, the set of SSB bursts may be measured based on the first MGL.
As can be seen from the foregoing embodiments, by determining that the measurement of the SSB burst set can be completed in the first MGL according to the transmission period of the SSB burst set, the SSB burst set can be measured directly based on the first MGL without modifying the first MGL by a UE, so that the accuracy of MGL configuration for the UE can be improved, and the communication efficiency can be improved.
Further, as can be seen from the foregoing embodiment, if a sum of a first duration corresponding to a sending period of the SSB burst set and a preset duration is less than or equal to a second duration corresponding to the first MGL, the UE may determine that the measurement of the SSB burst set can be completed in the first MGL. Therefore, whether the measurement of the SSB burst set can be completed in the first MGL is determined by judging whether the first MGL configured by the base station for the UE can cover the sending period of the SSB burst set, and then the UE can determine whether the first MGL needs to be modified, so that the time length for the UE to switch to an ENDC mode or an NR cell is reduced.
Referring to fig. 8, fig. 8 is a schematic flow chart of another measurement gap length configuration method based on the embodiment shown in fig. 2. As shown in fig. 8, the obtaining a first measurement gap length MGL configured by the base station for the UE includes:
in step 802, a first MGL configured by the base station for the UE is obtained based on a radio resource control RRC reconfiguration signaling sent by the base station.
Optionally, before step 802, the UE may receive an RRC (Radio Resource Control) reconfiguration signaling sent by the base station. For a specific implementation manner of the first MGL configured for the base station to indicate to the UE through the RRC reconfiguration signaling, please refer to related art, which is not described herein again.
For example, in response to receiving an RRC reconfiguration signaling sent by the base station, the UE may obtain the first MGL configured for the UE by the base station based on the RRC reconfiguration signaling.
As can be seen from the foregoing embodiment, the first MGL configured by the base station for the UE is obtained through an RRC reconfiguration signaling sent by the base station. Therefore, the accuracy of acquiring the first MGL by the UE may be improved, and the accuracy of determining the MGL used for measuring the SSB burst set according to the acquired transmission period of the SSB burst set may be further improved, that is, the accuracy of performing MGL configuration for the UE may be improved.
Referring to fig. 9, fig. 9 is a schematic flow chart of another measurement gap length configuration method based on the embodiment shown in fig. 2.
In step 901, registering in an LTE network;
in step 902, a transmit period for a set of SSB bursts is obtained.
In step 903, a first MGL configured by a base station for a UE is obtained;
in step 904, determining whether a transmission period of the set of SSB bursts is indicated in a system message; if so, go to step 905; if not, go to step 908-step 909;
in step 905, determining whether the measurement on the SSB burst set can be completed in the first MGL according to a transmission period of the SSB burst set; if so, go to step 906; if not, go to step 907;
in step 906, the first MGL is maintained; continuing to execute step 910;
in step 907, determining a second MGL for completing the measurement of the set of SSB bursts; continuing to execute step 910;
in step 908, determining the sending period of the SSB burst set as a specified period;
in step 909, the third MGL corresponding to the specified period is determined; continuing to execute step 910;
in step 910, the set of SSB bursts is measured.
In the embodiment of the present disclosure, for specific implementation manners of the steps 901 to 910, please refer to specific implementation manners of related steps in the foregoing embodiments, which are not described herein again.
Optionally, in the above-illustrated embodiment, after measuring the SSB burst set based on the first MGL, the second MGL, or the third MGL, the method may further include:
in step 911, reporting a measurement event report to the base station, so that the base station determines whether to allow the UE to switch to an endec mode or an NR cell according to the measurement event report;
in step 912, in response to receiving the network configuration information sent by the base station, switching to an endec mode or an NR cell.
For example, the UE may measure the SSB burst set based on the first MGL or the second MGL or the third MGL, and may send a corresponding measurement event report to the base station; the base station may issue SCG (Secondary Cell group) configuration information to the UE according to the measurement event report; the UE may switch to an endec mode in response to receiving the SCG configuration information.
For another example, the UE may measure the SSB burst set based on the first MGL, the second MGL, or the third MGL, and report a corresponding measurement event report to the base station; the base station may send an RRC Connection Release message to the UE in response to receiving the measurement event report, where the RRC Connection Release message may carry redirected Carrier Info information for providing one or more optional NR network frequency point information; the UE may Release the currently established RRC Connection to be in an RRC IDLE state (RRC _ IDLE) again in response to receiving the RRC Connection Release message, and may perform an RRC Connection establishment procedure again in the NR to switch to the NR cell.
It should be noted that, in the above illustrated embodiment, the specific implementation manner of the UE switching to the endec mode or the NR cell after completing the measurement of the SSB burst set is merely an exemplary description, and the disclosure is not limited thereto.
As can be seen from the foregoing embodiments, in response to determining that measurement of the SSB burst set cannot be completed within the first MGL configured by the base station for the UE according to the obtained sending period of the SSB burst set, the UE may determine a second MGL used for completing measurement of the SSB burst set, and may measure the SSB burst set based on the second MGL. Therefore, if the first MGL configured by the base station for the UE cannot cover the transmission period of the SSB burst set, the UE may modify the MGL configured by the base station for the UE, so that the measurement of the SSB burst set may be completed based on the modified second MGL, thereby reducing the time duration for the UE to switch to the endec mode or the NR cell.
Corresponding to the foregoing embodiments of the measurement gap length configuration method, the present disclosure also provides embodiments of a measurement gap length configuration apparatus.
Referring to fig. 10, fig. 10 is a schematic block diagram illustrating a measurement gap length configuration apparatus according to an embodiment of the present disclosure, which is applied to the UE. As shown in fig. 10, the apparatus may include:
a first obtaining module 1002, configured to obtain a sending period of an SSB burst set;
a second obtaining module 1004, configured to obtain a first MGL configured by a base station for the UE;
a first determining module 1006, configured to determine a second MGL for completing the measurement of the set of SSB bursts in response to determining that the measurement of the set of SSB bursts cannot be completed within the first MGL according to a transmission period of the set of SSB bursts;
a first measurement module 1008 configured to measure the set of SSB bursts based on the second MGL.
Referring to fig. 11, fig. 11 is a schematic block diagram of another measurement gap length configuration apparatus based on the embodiment shown in fig. 10. As shown in fig. 11, the first obtaining module 1002 may include:
the first obtaining sub-module 1102 is configured to obtain a sending period of the SSB burst set based on a system message issued by the base station.
Optionally, the first obtaining module 1002 may further include:
a first determining sub-module 1104, configured to determine a sending period of the SSB burst set indicated in the system message.
Optionally, the first determining sub-module 1104 is configured to:
determining that the transmission period of the set of SSB bursts is indicated in the system message in response to determining that a parameter indicating the transmission period of the set of SSB bursts is included in the system message.
Referring to fig. 12, fig. 12 is a schematic block diagram of another measurement gap length configuration apparatus based on the embodiment shown in fig. 11. As shown in fig. 12, the first obtaining module 1002 may further include:
a second determining sub-module 1202, configured to determine, in response to determining that the sending period of the SSB burst set is not indicated in the system message, that the sending period of the SSB burst set is a specified period.
Optionally, the second obtaining module 1004 may further include:
a third determining submodule 1204, configured to determine a third MGL corresponding to the specified period;
the apparatus may further include:
a second measurement module 1206 for measuring the set of SSB bursts based on the third MGL.
Referring to fig. 13, fig. 13 is a schematic block diagram of another measurement gap length configuration apparatus based on the embodiment shown in fig. 10. As shown in fig. 13, the first determining module 1006 may include:
a fourth determining sub-module 1302, configured to determine that measurement on the SSB burst set cannot be completed in the first MGL if a sum of a first duration corresponding to a sending period of the SSB burst set and a preset duration is greater than a second duration corresponding to the first MGL.
Referring to fig. 14, fig. 14 is a schematic block diagram of another measurement gap length configuration apparatus based on the embodiment shown in fig. 10. As shown in fig. 14, the first determining module 1006 may include:
a fifth determining sub-module 1402, configured to determine, according to a correspondence between a sending period of an SSB burst set and a second MGL, the second MGL corresponding to the obtained sending period of the SSB burst set.
Referring to fig. 15, fig. 15 is a schematic block diagram of another measurement gap length configuration apparatus based on the embodiment shown in fig. 10. As shown in fig. 15, the second obtaining module 1004 includes:
a second obtaining sub-module 1502, configured to obtain, based on a radio resource control RRC reconfiguration signaling sent by the base station, a first MGL configured by the base station for the UE.
Referring to fig. 16, fig. 16 is a schematic block diagram of another measurement gap length configuration apparatus based on the embodiment shown in fig. 10. As shown in fig. 16, the apparatus may further include:
a third measuring module 1602 for measuring the set of SSB bursts based on the first MGL in response to determining that the measurement of the set of SSB bursts can be completed within the first MGL according to a transmission period of the set of SSB bursts.
With regard to the apparatus in the above embodiments, the specific manner in which each module performs operations has been described in detail in the embodiments of the related method, and will not be described in detail here.
For the device embodiments, since they substantially correspond to the method embodiments, reference may be made to the partial description of the method embodiments for relevant points. The above-described embodiments of the apparatus are merely illustrative, wherein the modules described as separate parts may or may not be physically separate, and the parts displayed as modules may or may not be physical modules, may be located in one place, or may be distributed on a plurality of network modules. Some or all of the modules can be selected according to actual needs to achieve the purpose of the disclosed solution. One of ordinary skill in the art can understand and implement it without inventive effort.
Correspondingly, the present disclosure also provides a user equipment, including:
a processor;
a memory for storing processor-executable instructions;
wherein, the processor is used for executing the measurement gap length configuration method.
Accordingly, the present disclosure also provides a computer-readable storage medium storing a computer program for executing the above measurement gap length configuration method.
As shown in fig. 17, fig. 17 is a schematic block diagram illustrating a configuration apparatus 1700 for measuring a gap length according to an embodiment of the present disclosure. For example, the apparatus 1700 may be a mobile phone, a computer, a digital broadcast terminal, a messaging device, a game console, a tablet device, a medical device, an exercise device, a personal digital assistant, and the like.
Referring to fig. 17, apparatus 1700 may include one or more of the following components: processing component 1702, memory 1704, power component 1706, multimedia component 1708, audio component 1710, input/output (I/O) interface 1712, sensor component 1714, and communications component 1716.
The processing component 1702 generally controls the overall operation of the apparatus 1700, such as operations associated with display, telephone calls, data communications, camera operations, and recording operations. Processing component 1702 may include one or more processors 1720 to execute instructions to perform all or a portion of the steps of the above-described method. Further, processing component 1702 may include one or more modules that facilitate interaction between processing component 1702 and other components. For example, processing component 1702 may include a multimedia module to facilitate interaction between multimedia component 1708 and processing component 1702.
The memory 1704 is configured to store various types of data to support operations at the apparatus 1700. Examples of such data include instructions for any application or method operating on the apparatus 1700, contact data, phonebook data, messages, pictures, videos, and so forth. The memory 1704 may be implemented by any type or combination of volatile or non-volatile memory devices such as Static Random Access Memory (SRAM), electrically erasable programmable read-only memory (EEPROM), erasable programmable read-only memory (EPROM), programmable read-only memory (PROM), read-only memory (ROM), magnetic memory, flash memory, magnetic or optical disks.
The power supply component 1706 provides power to the various components of the device 1700. The power components 1706 may include a power management system, one or more power supplies, and other components associated with generating, managing, and distributing power for the apparatus 1700.
The multimedia component 1708 includes a screen providing an output interface between the device 1700 and a user. In some embodiments, the screen may include a Liquid Crystal Display (LCD) and a Touch Panel (TP). If the screen includes a touch panel, the screen may be implemented as a touch screen to receive an input signal from a user. The touch panel includes one or more touch sensors to sense touch, slide, and gestures on the touch panel. The touch sensor may not only sense the boundary of a touch or slide action, but also detect the duration and pressure associated with the touch or slide operation. In some embodiments, the multimedia component 1708 includes a front facing camera and/or a rear facing camera. The front camera and/or the rear camera may receive external multimedia data when the apparatus 1700 is in an operation mode, such as a photographing mode or a video mode. Each front camera and rear camera may be a fixed optical lens system or have a focal length and optical zoom capability.
Audio component 1710 is configured to output and/or input audio signals. For example, audio component 1710 includes a Microphone (MIC) configured to receive external audio signals when apparatus 1700 is in an operating mode, such as a call mode, a record mode, and a voice recognition mode. The received audio signal may further be stored in the memory 1704 or transmitted via the communication component 1716. In some embodiments, audio component 1710 also includes a speaker for outputting audio signals.
The I/O interface 1712 provides an interface between the processing component 1702 and peripheral interface modules, such as a keyboard, click wheel, buttons, and the like. These buttons may include, but are not limited to: a home button, a volume button, a start button, and a lock button.
The sensor assembly 1714 includes one or more sensors for providing various aspects of state assessment for the apparatus 1700. For example, sensor assembly 1714 may detect an open/closed state of apparatus 1700, the relative positioning of components, such as a display and keypad of apparatus 1700, the change in position of apparatus 1700 or a component of apparatus 1700, the presence or absence of user contact with apparatus 1700, the orientation or acceleration/deceleration of apparatus 1700, and the change in temperature of apparatus 1700. The sensor assembly 1714 may include a proximity sensor configured to detect the presence of nearby objects without any physical contact. The sensor assembly 1714 may also include a light sensor, such as a CMOS or CCD image sensor, for use in imaging applications. In some embodiments, the sensor assembly 1714 may also include an acceleration sensor, a gyroscope sensor, a magnetic sensor, a pressure sensor, or a temperature sensor.
The communication component 1716 is configured to facilitate communications between the apparatus 1700 and other devices in a wired or wireless manner. The apparatus 1700 may access a wireless network based on a communication standard, such as WiFi, 2G or 3G, 4G LTE, 5G NR, or a combination thereof. In an exemplary embodiment, the communication component 1716 receives broadcast signals or broadcast related information from an external broadcast management system via a broadcast channel. In an exemplary embodiment, the communication component 1716 further includes a Near Field Communication (NFC) module to facilitate short-range communications. For example, the NFC module may be implemented based on Radio Frequency Identification (RFID) technology, infrared data association (IrDA) technology, Ultra Wideband (UWB) technology, Bluetooth (BT) technology, and other technologies.
In an exemplary embodiment, the apparatus 1700 may be implemented by one or more Application Specific Integrated Circuits (ASICs), Digital Signal Processors (DSPs), Digital Signal Processing Devices (DSPDs), Programmable Logic Devices (PLDs), Field Programmable Gate Arrays (FPGAs), controllers, micro-controllers, microprocessors or other electronic components for performing the methods described in any of the above embodiments.
In an exemplary embodiment, a non-transitory computer readable storage medium comprising instructions, such as the memory 1704 comprising instructions, executable by the processor 1720 of the apparatus 1700 to perform the above-described method is also provided. For example, the non-transitory computer readable storage medium may be a ROM, a Random Access Memory (RAM), a CD-ROM, a magnetic tape, a floppy disk, an optical data storage device, and the like.
Other embodiments of the disclosure will be apparent to those skilled in the art from consideration of the specification and practice of the disclosure disclosed herein. This application is intended to cover any variations, uses, or adaptations of the disclosure following, in general, the principles of the disclosure and including such departures from the present disclosure as come within known or customary practice within the art to which the disclosure pertains. It is intended that the specification and examples be considered as exemplary only, with a true scope and spirit of the disclosure being indicated by the following claims.
It will be understood that the present disclosure is not limited to the precise arrangements described above and shown in the drawings and that various modifications and changes may be made without departing from the scope thereof. The scope of the present disclosure is limited only by the appended claims.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. The terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
The method and apparatus provided by the embodiments of the present disclosure are described in detail above, and the principles and embodiments of the present disclosure are explained herein by applying specific examples, and the above description of the embodiments is only used to help understanding the method and core ideas of the present disclosure; meanwhile, for a person skilled in the art, according to the idea of the present disclosure, there may be variations in the specific embodiments and the application scope, and in summary, the content of the present specification should not be construed as a limitation to the present disclosure.

Claims (13)

1. A method for configuring measurement gap length is applied to User Equipment (UE), and comprises the following steps:
acquiring a sending period of a SSB burst set of a synchronous signal block;
acquiring a first measurement gap length MGL configured for the UE by a base station;
in response to determining that the measurement of the set of SSB bursts cannot be completed within the first MGL according to a transmission period of the set of SSB bursts, determining a second MGL for completing the measurement of the set of SSB bursts;
measuring the set of SSB bursts based on the second MGL.
2. The method of claim 1, wherein the determining that the measurement of the set of SSB bursts cannot be completed within the first MGL according to a transmission period of the set of SSB bursts comprises:
and if the sum of a first time length corresponding to the sending period of the SSB burst set and a preset time length is greater than a second time length corresponding to the first MGL, determining that the measurement of the SSB burst set cannot be completed in the first MGL.
3. The method of claim 1, wherein the determining a second MGL for completing the measurement of the set of SSB bursts comprises:
and determining a second MGL corresponding to the obtained sending period of the SSB burst set according to the corresponding relation between the sending period of the SSB burst set and the second MGL.
4. The method of claim 1, wherein obtaining the sending period of the SSB burst set comprises:
and acquiring the sending period of the SSB burst set based on the system information issued by the base station.
5. The method of claim 4, wherein before the obtaining the sending period of the SSB burst set based on the system message sent by the base station, the method further comprises:
determining a transmission period of the set of SSB bursts indicated in the system message.
6. The method of claim 5, wherein the determining that the transmission period of the set of SSB bursts is indicated in the system message comprises:
determining that the transmission period of the set of SSB bursts is indicated in the system message in response to determining that a parameter indicating the transmission period of the set of SSB bursts is included in the system message.
7. The method of claim 5, further comprising:
in response to determining that the transmission period of the set of SSB bursts is not indicated in the system message, determining that the transmission period of the set of SSB bursts is a specified period.
8. The method of claim 7, further comprising:
determining a third MGL corresponding to the designated period;
measuring the set of SSB bursts based on the third MGL.
9. The method of claim 1, further comprising:
measuring the set of SSB bursts based on the first MGL in response to determining that the measurement of the set of SSB bursts can be completed within the first MGL according to a transmission period of the set of SSB bursts.
10. The method of claim 1, wherein the obtaining the first MGL configured by the base station for the UE comprises:
and acquiring a first MGL configured for the UE by the base station based on a Radio Resource Control (RRC) reconfiguration signaling issued by the base station.
11. An apparatus for configuring measurement gap length, applied to a User Equipment (UE), the apparatus comprising:
the first acquisition module is used for acquiring the sending period of the SSB burst set of the synchronous signal block;
a second obtaining module, configured to obtain a first measurement gap length MGL configured by a base station for the UE;
a first determining module, configured to determine a second MGL for completing measurement of the SSB burst set in response to determining that the measurement of the SSB burst set cannot be completed within the first MGL according to a transmission period of the SSB burst set;
a first measurement module to measure the set of SSB bursts based on the second MGL.
12. A user equipment, the user equipment comprising:
a processor;
a memory for storing processor-executable instructions;
wherein the processor is configured to perform the method of any one of claims 1 to 10.
13. A computer-readable storage medium, on which a computer program is stored, characterized in that the computer program is adapted to perform the method of any of claims 1 to 10.
CN202210129122.5A 2022-02-11 2022-02-11 Measurement gap length configuration method and device Active CN114520996B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210129122.5A CN114520996B (en) 2022-02-11 2022-02-11 Measurement gap length configuration method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210129122.5A CN114520996B (en) 2022-02-11 2022-02-11 Measurement gap length configuration method and device

Publications (2)

Publication Number Publication Date
CN114520996A true CN114520996A (en) 2022-05-20
CN114520996B CN114520996B (en) 2024-01-16

Family

ID=81596133

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210129122.5A Active CN114520996B (en) 2022-02-11 2022-02-11 Measurement gap length configuration method and device

Country Status (1)

Country Link
CN (1) CN114520996B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110546984A (en) * 2017-11-15 2019-12-06 Lg电子株式会社 Method and user equipment for performing measurements in EN-DC case
US20200100131A1 (en) * 2017-04-28 2020-03-26 Lg Electronics Inc. Method and wireless device for performing measurement in nr for 5g
WO2020207300A1 (en) * 2019-04-08 2020-10-15 华为技术有限公司 Method and device for measuring and sending measurement configuration information
CN113473549A (en) * 2020-03-31 2021-10-01 荣耀终端有限公司 Measurement gap configuration method and device
WO2021249001A1 (en) * 2020-06-12 2021-12-16 华为技术有限公司 Cell measurement method and device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20200100131A1 (en) * 2017-04-28 2020-03-26 Lg Electronics Inc. Method and wireless device for performing measurement in nr for 5g
CN110546984A (en) * 2017-11-15 2019-12-06 Lg电子株式会社 Method and user equipment for performing measurements in EN-DC case
WO2020207300A1 (en) * 2019-04-08 2020-10-15 华为技术有限公司 Method and device for measuring and sending measurement configuration information
CN111800797A (en) * 2019-04-08 2020-10-20 华为技术有限公司 Method and equipment for measuring and sending measurement configuration information
CN113473549A (en) * 2020-03-31 2021-10-01 荣耀终端有限公司 Measurement gap configuration method and device
WO2021249001A1 (en) * 2020-06-12 2021-12-16 华为技术有限公司 Cell measurement method and device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
""R4-2011364 CR38133 General introduction of NR positioning measurements"", 3GPP TSG_RAN\\WG4_RADIO *
苗苗;周渭;李智奇;刘晨;: "用于时间同步的高精度短时间间隔测量方法", 北京邮电大学学报, no. 04 *

Also Published As

Publication number Publication date
CN114520996B (en) 2024-01-16

Similar Documents

Publication Publication Date Title
CN112954761B (en) Method, device and user equipment for cell switching
CN108513737B (en) Information transmission method and information transmission device
CN109314972B (en) Method and device for triggering switching of bandwidth part and method and device for configuring information
US11178637B2 (en) Paging message receiving method and device, and paging configuration method and device
US20210377812A1 (en) Method, apparatus and system for acquiring control information
CN109076620B (en) Random access control method and random access control device
US11076311B2 (en) Methods and devices for measuring cell signal quality
CN110622616A (en) Control method and device of inactivity timer
US11968557B2 (en) MDT information notifying method and MDT information receiving method
CN110383891B (en) Network switching resource determining method and network switching resource configuration method
CN113825196A (en) Network switching resource determining method and network switching resource configuration method
CN108702689B (en) Cell access method, device and storage medium
CN110574410A (en) method and device for indicating in-device coexistence interference and method and device for receiving in-device coexistence interference
CN107592645B (en) Method, device and system for switching base stations
CN110574403B (en) Information acquisition method and device, and information sending method and device
CN111837411A (en) Information sending method, base station switching method, information receiving method and device
CN110100478B (en) Network configuration method, network measurement method and device
CN109451827B (en) Method and device for determining moving speed of user equipment, base station and user equipment
CN114520996B (en) Measurement gap length configuration method and device
CN113726494A (en) Method and device for determining transmission direction
CN108781390B (en) Synchronization block receiving method and device, and system information transmission method and device
CN114666858B (en) Network registration method, device, terminal and storage medium
EP4319476A1 (en) Capability information acquisition method and apparatus, and configuration sending method and apparatus
CN116939797A (en) Signal detection method and device and storage medium
CN112689319B (en) Network access method and device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant