CN114398699A - Grouting pipe curtain deformation calculation method based on inter-pipe soil arch characteristics - Google Patents
Grouting pipe curtain deformation calculation method based on inter-pipe soil arch characteristics Download PDFInfo
- Publication number
- CN114398699A CN114398699A CN202111602961.6A CN202111602961A CN114398699A CN 114398699 A CN114398699 A CN 114398699A CN 202111602961 A CN202111602961 A CN 202111602961A CN 114398699 A CN114398699 A CN 114398699A
- Authority
- CN
- China
- Prior art keywords
- grouting pipe
- pipe curtain
- section
- curtain
- load
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2119/00—Details relating to the type or aim of the analysis or the optimisation
- G06F2119/14—Force analysis or force optimisation, e.g. static or dynamic forces
Abstract
The invention provides a grouting pipe curtain deformation calculation method based on the characteristics of soil arches among pipes, which comprises the steps of firstly analyzing the transverse soil arch characteristics of a grouting pipe curtain to determine a supporting load; analyzing the axial beam forming effect of the grouting pipe curtain to determine a control equation; then establishing a grouting pipe curtain long beam theoretical model to determine load distribution; and then solving the flexural deformation by a slip casting pipe curtain difference calculation method. The invention provides a calculation theory of the deflection deformation of the grouting pipe curtain, can quantitatively analyze the mechanical response of the grouting pipe curtain in the actual working state, has less dependence on engineering experience, has good universality and provides scientific basis for design and construction; a grouting pipe curtain stress calculation method considering soil arch characteristics is established, the inter-pipe soil arch bearing span reduction effect is mathematically analyzed and expressed, the existing design concept deviating from danger is avoided, and the construction safety is guaranteed; meanwhile, a double-parameter Passternak model is adopted, the transverse shearing action of a foundation spring, the foundation bed coefficient difference, the load release sectionalization and the foundation elastoplasticity are considered more reasonably, so that the grouting pipe curtain is continuously deformed, the distribution and release of tunnel excavation loads are simulated more reliably, the pipe body deformation of the tunnel grouting pipe curtain at a certain position is predicted, and a theoretical basis is provided for the design and construction of the grouting pipe curtain.
Description
Technical Field
The invention relates to the technical field of tunnels and underground engineering, in particular to a grouting pipe curtain deformation calculation method based on the characteristics of soil arches between pipes.
Background
When a large-span tunnel passes through a bad stratum or passes through an existing building, if effective engineering protection measures are not taken, serious accidents such as extrusion instability of a tunnel face, collapse damage of the tunnel and the like are easily caused. Therefore, in specific construction, in order to guarantee engineering safety, the grouting pipe curtain is generally adopted to pre-reinforce the front rock-soil body, namely, the grouting pipe curtain is supported in advance, the grouting pipe curtain bears the load of loose rock-soil, and the excessive deformation of surrounding rock is prevented, so that the risk potential is reduced.
In the prior art, the action mode and the deformation mechanism of a large grouting pipe curtain are not completely clear, the design and construction still excessively depend on engineering experience, and the engineering quality is difficult to ensure. For the law of deformation of grouting pipe curtain, some studies have been carried out in the academic world: in the aspect of theoretical derivation, an elastic foundation beam model is generally adopted to analyze a single grouting pipe curtain, and the grouting pipe curtain is considered to act on beams of mutually independent Winkler springs, so that the loaded deformation of the grouting pipe curtain is researched; in the aspect of field actual measurement, a steel bar strain gauge or an inclinometer is generally utilized to obtain real-time data of grouting pipe curtain deformation in the excavation process; in the aspect of numerical simulation, conventionally, a grouting pipe curtain is simulated by means of an entity unit, a grouting stratum is equivalently reinforced, and the space-time displacement of the grouting pipe curtain under three-dimensional excavation is analyzed.
However, most of the existing researches only qualitatively describe the supporting effect of the grouting pipe curtain, and the quantitative analysis of the stress mechanism and the deflection distribution of the grouting pipe curtain is less involved. In addition, in the past, the deformation calculation theory of the grouting pipe curtain considers that the bearing range of the grouting pipe curtain is only the upper area of the pipe diameter projection, and the soil arch characteristic between adjacent grouting pipe curtains is not considered, so that the obvious limitation is caused, and the difference from the actual situation is large.
Disclosure of Invention
The invention aims to provide a grouting pipe curtain deformation calculation method based on the characteristics of soil arches between pipes, so as to solve the problems in the background technology.
In order to achieve the purpose, the invention adopts the following technical scheme:
a grouting pipe curtain deformation calculation method based on the characteristics of soil arches between pipes comprises the following steps:
s1, analyzing the transverse soil arch characteristic of the grouting pipe curtain and determining a supporting load;
s2, analyzing the axial beam forming effect of the grouting pipe curtain, and determining a control equation;
s3, establishing a grouting pipe curtain long beam theoretical model, and determining load distribution;
and S4, solving the flexural deformation through a slip casting tube curtain difference calculation method.
Further, the step S1 is specifically implemented by the following method:
s11, according to the Purchase pressure arch theory, considering the soil arch characteristic between adjacent grouting pipe curtains, and establishing a corresponding mechanical model: the grouting pipe curtains are regarded as cylindrical steel pipes and are distributed in the circumferential direction of the outer ring of the tunnel arch part at equal intervals; htAnd BtThe height and the span of the excavated tunnel are respectively, the outer diameter of the tunnel is R, the gravity of the surrounding rock is gamma, the outer diameter of the grouting pipe curtain is D, and the distance between two adjacent grouting pipe curtains is D1A clear spacing of D2The included angle between two adjacent grouting pipe curtains is alpha,the friction angle of the surrounding rock is R + g, and the radius of the circular arc of the grouting pipe curtain is R + g;
s12, numbering each grouting pipe curtain from the vault to two sides in sequence, and regarding the gravity of the loose rock mass in the pressure arch area as the load of the grouting pipe curtains, wherein any one number is CnThe corresponding load height of the grouting pipe curtain is HdnAnd C isnThe serial numbers of two adjacent grouting pipe curtains are marked as Cn-1And Cn+1And with CnThe horizontal included angle of the grouting pipe curtain is recorded as thetan-1And thetan+1;
S13, in the mechanical model of grouting pipe curtains, defining the central connecting line of two adjacent grouting pipe curtains as an x axis, defining the vertical central line of two adjacent grouting pipe curtains as a y axis, establishing a plurality of rectangular coordinate systems, analyzing the load height corresponding to the grouting pipe curtains by establishing a soil arch axis in each coordinate system, and analyzing the soil arch axis by the equation y-mx without considering the tensile strength of rock mass2A parabola denoted by + n;
s14 grouting pipe curtain Cn-1And CnIn a rectangular coordinate system, the soil arch axis and the grouting pipe curtain Cn-1And CnHas a crossing point of V1And V2Are each independently of V1And grouting pipe curtain Cn-1Line connecting the centers of circles, V2And grouting pipe curtain CnThe intersection points of the segment perpendicular to the connecting line of the circle centers and the x axis are respectively M1And M2Suppose line segment V1Cn-1、V2CnAre all tangent with the soil arch axis and have included angles with the x axisThen line segment V1M1、V2M2At an angle to the x-axis ofThen V2The coordinates of the points can be expressed as
S15, mixing V2The coordinates of the points are brought into the soil arch axis equation, and the following are obtained by solution:
uniform load q above the earth arch axisn-1And q isn-1Obtained by the following analytical formula:
vertical concentrated load p of soil arch axisn-1And pn+1Can be expressed as:
averaging the two to obtain a grouting pipe curtain CnVertical load p aboven:
Further, the step S2 is specifically implemented by the following method:
s21, regarding the surrounding rock as a homogeneous and continuous elastic-plastic entity, wherein the flexural deformation of the grouting pipe curtain has the mechanical characteristics of a Bernoulli-Euler beam, so that a grouting pipe curtain mechanical model based on the Passternak elastic-plastic foundation beam is obtained, and the grouting pipe curtain mechanical model is obtained according to the reaction analytical formula of the Passternak foundation beam by the following formula:
wherein: p (x) is the resistance of the surrounding rock foundation, k is the coefficient of the surrounding rock bed, w (x) is the flexural deformation of the grouting pipe curtain, GpIs the shear modulus of the surrounding rock foundation;
s22, considering tunnel support hysteresis, foundation bed coefficient change, stress release and stratum elastoplasticity factors, and sequentially dividing the grouting pipe curtain into a support closed section OA, a support non-closed section AB, a non-support section BC, a plastic disturbance section CD, an elastic disturbance section DE and a non-disturbance section EF from back to front along the advancing direction of the excavation face;
s23, obtaining the following results due to the balanced stress of the units:
wherein V (x) is shearing force of grouting pipe curtain, M (x) is bending moment of grouting pipe curtain, q (x) is load borne by grouting pipe curtain, b is width of surrounding rock foundation beam, b*Is equivalent surrounding rock foundationWidth, b*=b[1+(Gp/k)1/2/b];
S24, based on Bernoulli-Euler beam theory, the mechanical response of the grouting pipe curtain can be obtained, including the differential analytic formula of grouting pipe curtain deflection angle theta (x), longitudinal strain epsilon (x), grouting pipe curtain shear force V (x), grouting pipe curtain bending moment M (x) and grouting pipe curtain deflection deformation W (x):
solving a differential balance equation for controlling the deformation of the grouting pipe curtain through the formulas (9) to (13):
further, the step S3 is specifically implemented by the following method:
the mechanical model of the grouting pipe curtain of the Passternak foundation beam is obtained by considering the soil arch characteristic of the grouting pipe curtain and the space-time effect of stratum load:
the primary support closed section OA has a length of a, and the load borne by the grouting pipe curtain in the section is static load, namely q (x) q0,q0Calculating values according to a Prov theory formula; resistance of the zone surrounding rock foundationThe differential balance of the control in this section is formulated as
The initial branch unblocked section AB has the length of b, and the external load q (x) borne by the grouting pipe curtain of the section is [1+ (eta)1-1)(x-a)/(b+s)]q0Time-space coefficient eta of stress release of surrounding rock load1Taking 0.5; resistance of the primary support surrounding rock foundation of the sectionSurrounding rock foundation coefficient k in formulac(x)=-kcx/b+(a+b)kcB, and k at point B cmin0; the differential balance of control for that segment is formulated as
For the unsupported section BC with the length of c, the distribution form of external load borne by the grouting pipe curtain of the section is the same as that of the section AB, and because the initial support of the section BC is not applied, the load p (x) is also taken to be 0, the differential balance formula controlled by the section is as follows
Plastic perturbation zone CD of lengthWherein h isuIs the height of the tunnel step,the friction angle is calculated for the surrounding rock. In addition, the front of the excavation surface has a remarkable stress concentration phenomenon, and the space-time coefficient eta of the release of the load stress of the surrounding rock at the D point is taken2Take 1.2, the section bears the external load q (x) ═ η2-η1)[x-(a+b+c)]q0/d+η1q0(ii) a Resistance of the zone surrounding rock foundationk0(x)=[x-(a+b+c+d)](k0-k0min)/s+k0minWhere s is the length of the rock mass before the excavation face, k0Constant coefficient of rock mass bed, k, without disturbance0minIs a ground reduction factor, and k0min=0.6k0(ii) a The differential balance of the control in this section is formulated as
The elastic disturbance section DE is of length e, and the total length of the elastic disturbance section and the undisturbed section of the large-span tunnel grouting pipe curtain is taken as 2huThe segment slip casting tube bears the load q (x) ═ η2[x-(a+b+c+d)]q0/s+η2q0The resistance of the surrounding rock foundation of the section is consistent with the CD section, and the section is takenThe differential balance of the control in this section is formulated as
An undisturbed section EF with the length f, which is the length of the residual grouting pipe curtain after deducting each section in front; the section grouting pipe curtain is not subjected to any external load, and if q (x) is 0, the resistance of the section surrounding rock foundation is obtainedThe differential balance of the control in this section is formulated as
Further, the step S4 is specifically implemented by the following method:
s41, equally dividing the grouting pipe curtain with the length of L into n sections, and according to the sequence from left to right, each node is compiled into 0, 1 … i … n-1, n, and the length of each section is divided into L0The deflection deformation of the grouting pipe curtain of the node i is wi, and in order to adapt to the analytic degree of freedom of the grouting pipe curtain, two different virtual nodes-2, -1, n +1 and n +2 are respectively arranged on the left side and the right side;
and S42, carrying out Taylor formula expansion on the deformation of the left and right adjacent nodes of the node i, and taking the four polynomials in front of the Taylor expansion formula to ensure the analysis accuracy.
This enables the derivation of the various derivatives:
s43, combining the above formulas to solve the grouting tube curtain deflection difference formula:
Ci(wi-2-4wi-1+6wi-4wi+1+wi+2)+Biwi-Di(-wi-2+16wi-1-30wi+16wi+1-wi+2)=qi (23)
analyzing and expressing mechanical boundary conditions on two sides of the grouting pipe curtain:
simultaneous implementation of the above formula yields:
when i is 0, 1, n-1, n, the simplified slip casting curtain deflection difference formula can be converted into:
C0(w-2-4w-1+6w0-4w1+w2)+B0w0-D0(-w-2+16w-1-30w0+16w1-w2)=q0
C1(w-1-4w0+6w1-4w2+w3)+B1w1-D1(-w-1+16w0-30w1+16w2-w3)=q1
Cn-1(wn-3-4wn-2+6wn-1-4wn+wn+1)+Dn-1wn-1
-Dn-1(-wn-3+16wn-2-30wn-1+16wn-wn+1)=qn-1
Cn(wn-2-4wn-1+6wn-4wn+1+wn+2)+Bnwn-Dn(-wn-2+16wn-1-30wn+16wn+1-wn+2)=qn
handle w-2、w-1、w1、w2Substituting, one can get:
s44, the above equation is expressed in a matrix form to obtain:
{[B]+[C]-[D]}{w}={p}
wherein the matrix dimensions of [ B ], [ C ] and [ D ] are all N +1, and the expression is as follows:
in addition, the grouting pipe curtain bears the expression of the load matrix { p }:
{p}={p0 p1 p2 … pn-1 pn}T
and then the expression of the grouting pipe screen deflection matrix { w } can be obtained:
{w}={w0 w1 w2 … wn-1 wn}T
and S45, writing a Matlab program, and solving the flexural deformation wi of each node of the grouting pipe curtain.
According to the technical scheme, the invention provides a calculation theory of the deflection deformation of the grouting pipe curtain, can quantitatively analyze the mechanical response of the grouting pipe curtain in the actual working state, is less dependent on engineering experience, has good universality and provides scientific basis for design and construction; a grouting pipe curtain stress calculation method considering soil arch characteristics is established, the inter-pipe soil arch bearing span reduction effect is mathematically analyzed and expressed, the existing design concept deviating from danger is avoided, and the construction safety is guaranteed; meanwhile, a double-parameter Passternak model is adopted, the transverse shearing action of a foundation spring, the foundation bed coefficient difference, the load release sectionalization and the foundation elastoplasticity are considered more reasonably, so that the grouting pipe curtain is continuously deformed, the distribution and release of tunnel excavation loads are simulated more reliably, the pipe body deformation of the tunnel grouting pipe curtain at a certain position is predicted, and a theoretical basis is provided for the design and construction of the grouting pipe curtain.
Drawings
FIG. 1 is a schematic flow chart of the steps of the present invention;
FIG. 2 is a schematic diagram of the mechanical model of step S1 according to the present invention;
FIG. 3 is a schematic sectional view of the grouting pipe curtain of the present invention;
FIG. 4 is a schematic view of the nodal division of the grouting pipe curtain of the present invention;
FIG. 5 is a comparison graph of the measured distribution and the theoretical distribution of the measured deflection deformation of the grouting pipe curtain of the present invention.
Detailed Description
A preferred embodiment of the present invention will be described in detail below with reference to the accompanying drawings.
As shown in fig. 1, a grouting pipe curtain deformation calculation method based on characteristics of soil arches between pipes includes the following steps:
s1, analyzing the transverse soil arch characteristic of the grouting pipe curtain and determining a supporting load;
the method is realized by the following steps:
s11, according to the Purchase pressure arch theory, considering the soil arch characteristic between adjacent grouting pipe curtains, and establishing a corresponding mechanical model: the grouting pipe curtains are regarded as cylindrical steel pipes and are distributed in the circumferential direction of the outer ring of the tunnel arch part at equal intervals; htAnd BtThe height and the span of the excavated tunnel are respectively, the outer diameter of the tunnel is R, the gravity of the surrounding rock is gamma, the outer diameter of the grouting pipe curtain is D, and the distance between two adjacent grouting pipe curtains is D1A clear spacing of D2The included angle between two adjacent grouting pipe curtains is alpha,the friction angle of the surrounding rock is R + g, and the radius of the circular arc of the grouting pipe curtain is R + g;
s12, numbering each grouting pipe curtain from the vault to two sides in sequence, and regarding the gravity of the loose rock mass in the pressure arch area as the load of the grouting pipe curtains, wherein any one number is CnThe corresponding load height of the grouting pipe curtain is HdnAnd C isnThe serial numbers of two adjacent grouting pipe curtains are marked as Cn-1And Cn+1And with CnThe horizontal included angle of the grouting pipe curtain is recorded as thetam-1And thetan+1;
S13, in the mechanical model of the grouting pipe curtains, the central connecting line of two adjacent grouting pipe curtains is defined as an x axis, and two adjacent grouting pipe curtains are connectedThe vertical center line of the pipe curtain is defined as a y axis, a plurality of rectangular coordinate systems are established, the load height corresponding to the grouting pipe curtain is analyzed by establishing a soil arch axis in each coordinate system, and the soil arch axis is formed by the equation y-mx without considering the tensile strength of the rock mass2A parabola denoted by + n;
s14 grouting pipe curtain Cn-1And CnIn a rectangular coordinate system, the soil arch axis and the grouting pipe curtain Cn-1And CnHas a crossing point of V1And V2Are each independently of V1And grouting pipe curtain Cn-1Line connecting the centers of circles, V2And grouting pipe curtain CnThe intersection points of the segment perpendicular to the connecting line of the circle centers and the x axis are respectively M1And M2Suppose line segment V1Cn-1、V2CnAre all tangent with the soil arch axis and have included angles with the x axisThen line segment V1M1、V2M2At an angle to the x-axis ofThen V2The coordinates of the points can be expressed as
S15, mixing V2The coordinates of the points are brought into the soil arch axis equation, and the following are obtained by solution:
uniform load q above the earth arch axisn-1And q isn-1Analysis was conducted byThe formula is obtained:
vertical concentrated load p of soil arch axisn-1And pn+1Can be expressed as:
averaging the two to obtain a grouting pipe curtain CnVertical load p aboven:
S2, analyzing the axial beam forming effect of the grouting pipe curtain, and determining a control equation;
the method is realized by the following steps:
s21, regarding the surrounding rock as a homogeneous and continuous elastic-plastic entity, wherein the flexural deformation of the grouting pipe curtain has the mechanical characteristics of a Bernoulli-Euler beam, so that a grouting pipe curtain mechanical model based on the Passternak elastic-plastic foundation beam is obtained, and the grouting pipe curtain mechanical model is obtained according to the reaction analytical formula of the Passternak foundation beam by the following formula:
wherein: p (x) is the resistance of the surrounding rock foundation, k is the coefficient of the surrounding rock bed, w (x) is the flexural deformation of the grouting pipe curtain, GpShear modulus of the surrounding rock foundation;
S22, as shown in figure 3, considering factors such as tunnel support hysteresis, foundation bed coefficient change, stress release and stratum elastoplasticity, sequentially dividing the grouting pipe curtain into a support closed section OA, a support non-closed section AB, a non-support section BC, a plastic disturbance section CD, an elastic disturbance section DE and a non-disturbance section EF from back to front along the advancing direction of the excavation face;
s23, obtaining the following results due to the balanced stress of the units:
wherein V (x) is shearing force of grouting pipe curtain, M (x) is bending moment of grouting pipe curtain, q (x) is load borne by grouting pipe curtain, b is width of surrounding rock foundation beam, b*Is equivalent to the width of the surrounding rock foundation, b*=b[1+(Gp/k)1/2/b];
S24, based on Bernoulli-Euler beam theory, the mechanical response of the grouting pipe curtain can be obtained, including the differential analytic formula of grouting pipe curtain deflection angle theta (x), longitudinal strain epsilon (x), grouting pipe curtain shear force V (x), grouting pipe curtain bending moment M (x) and grouting pipe curtain deflection deformation W (x):
solving a differential balance equation for controlling the deformation of the grouting pipe curtain through the formulas (9) to (13):
s3, establishing a grouting pipe curtain long beam theoretical model, and determining load distribution;
specifically, the mechanical model of the grouting pipe curtain of the Passternak foundation beam is obtained by considering the soil arch characteristic of the grouting pipe curtain and the stratum load space-time effect:
the primary support closed section OA has a length of a, and the load borne by the grouting pipe curtain in the section is static load, namely q (x) q0,q0Calculating values according to a Prov theory formula; resistance of the zone surrounding rock foundationThe differential balance of the control in this section is formulated as
The initial branch unblocked section AB has the length of b, and the external load q (x) borne by the grouting pipe curtain of the section is [1+ (eta)1-1)(x-a)/(b+s)]q0Time-space coefficient eta of stress release of surrounding rock load1Taking 0.5; resistance of the primary support surrounding rock foundation of the sectionSurrounding rock foundation coefficient k in formulac(x)=-kcx/b+(a+b)kcB, and k at point B cmin0; the differential balance of control for that segment is formulated as
For the unsupported section BC with the length of c, the distribution form of external load borne by the grouting pipe curtain of the section is the same as that of the section AB, and because the initial support of the section BC is not applied, the load p (x) is also taken to be 0, the differential balance formula controlled by the section is as follows
Plasticity ofA perturbation zone CD of lengthWherein h isuIs the height of the tunnel step,the friction angle is calculated for the surrounding rock. In addition, the front of the excavation surface has a remarkable stress concentration phenomenon, and the space-time coefficient eta of the release of the load stress of the surrounding rock at the D point is taken2Take 1.2, the section bears the external load q (x) ═ η2-η1)[x-(a+b+c)]q0/d+η1q0(ii) a Resistance of the zone surrounding rock foundationk0(x)=[x-(a+b+c+d)](k0-k0min)/+k0minWhere s is the length of the rock mass before the excavation face, k0Constant coefficient of rock mass bed, k, without disturbance0minIs a ground reduction factor, and k0min=0.6k0(ii) a The differential balance of the control in this section is formulated as
The elastic disturbance section DE is of length e, and the total length of the elastic disturbance section and the undisturbed section of the large-span tunnel grouting pipe curtain is taken as 2huThe segment slip casting tube bears the load q (x) ═ η2[x-(a+b+c+d)]q0/s+η2q0The resistance of the surrounding rock foundation of the section is consistent with the CD section, and the section is takenThe differential balance of the control in this section is formulated as
An undisturbed section EF with the length f, which is the length of the residual grouting pipe curtain after deducting each section in front; the section grouting pipe curtain is not subjected to any external load, and q (x) is 0, thenResistance of the zone surrounding rock foundationThe differential balance of the control in this section is formulated as
And S4, solving the flexural deformation through a slip casting tube curtain difference calculation method.
The method is realized by the following steps:
s41, as shown in FIG. 4, equally dividing the grouting pipe curtain with the length of L into n sections, and according to the sequence from left to right, each node is coded into 0, 1 … i … n-1, n, and the length of each section is divided into L0The deflection deformation of the grouting pipe curtain of the node i is wi, and in order to adapt to the analytic degree of freedom of the grouting pipe curtain, two different virtual nodes-2, -1, n +1 and n +2 are respectively arranged on the left side and the right side;
and S42, carrying out Taylor formula expansion on the deformation of the left and right adjacent nodes of the node i, and taking the four polynomials in front of the Taylor expansion formula to ensure the analysis accuracy.
This enables the derivation of the various derivatives:
s43, combining the above formulas to solve the grouting tube curtain deflection difference formula:
Ci(wi-2-4wi-1+6wi-4wi+1+wi+2)+Biwi-Di(-wi-2+16wi-1-30wi+16wi+1-wi+2)=qi (23)
analyzing and expressing mechanical boundary conditions on two sides of the grouting pipe curtain:
simultaneous implementation of the above formula yields:
when i is 0, 1, n-1, n, the simplified slip casting curtain deflection difference formula can be converted into:
C0(w-2-4w-1+6w0-4w1+w2)+B0w0-D0(-w-2+16w-1-30w0+16w1-w2)=q0
C1(w-1-4w0+6w1-4w2+w3)+B1w1-D1(-w-1+16w0-30w1+16w2-w3)=q1
Cn-1(wn-3-4wn-2+6wn-1-4wn+wn+1)+Bn-1wn-1
-Dn-1(-wn-3+16wn-2-30wn-1+16wn-wn+1)=qn-1
Cn(wn-2-4wn-1+6wn-4wn+1+wn+2)+B2wn-n(-wn-2+16wn-1-30wn+16wn+1-wn+2)=qn
handle w-2、w-1、w1、w2Substituting, one can get:
s44, the above equation is expressed in a matrix form to obtain:
{[B]+[C]-[D]}{w}={p}
wherein the matrix dimensions of [ B ], [ C ] and [ D ] are all N +1, and the expression is as follows:
in addition, the grouting pipe curtain bears the expression of the load matrix { p }:
{p}={p0 p1 p2 … pn-1 pn}T
and then the expression of the grouting pipe screen deflection matrix { w } can be obtained:
{w}={w0 w1 w2 … wn-1 wn}T
and S45, writing a Matlab program, and solving the flexural deformation wi of each node of the grouting pipe curtain.
The invention provides a calculation theory of the deflection deformation of the grouting pipe curtain, can quantitatively analyze the mechanical response of the grouting pipe curtain in the actual working state, has less dependence on engineering experience, has good universality and provides scientific basis for design and construction; a grouting pipe curtain stress calculation method considering soil arch characteristics is established, the inter-pipe soil arch bearing span reduction effect is mathematically analyzed and expressed, the existing design concept deviating from danger is avoided, and the construction safety is guaranteed; meanwhile, a double-parameter Passternak model is adopted, and the transverse shearing action of a foundation spring, the foundation bed coefficient difference, the load release sectionalization and the foundation elastoplasticity are considered more reasonably, so that the grouting pipe curtain deformation is continuous, and the distribution release of the tunnel excavation load can be simulated more reliably.
The calculation method of the present invention is explained below by specific examples:
a certain mountain tunnel adopts a grouting pipe curtain advanced support; according to geological survey data, the surrounding rock foundation coefficient k of the tunnel engineering045MPa/m, shear modulus Grp2.5kN/m, primary bedding coefficient kc150MPa/m, shear modulus Gcp5kN/m, the weight of the surrounding rock is 18.5kN/m3Width of tunnel Bt15.15m, tunnel height Ht12.78m, angle of friction of surrounding rockCohesive force c of surrounding rockn50 kPa. The total length L of the grouting pipe curtain is 30m, the outer diameter D of the steel pipe is 0.089m, the wall thickness t of the steel pipe is 0.006m, and the grouting pipe curtain is equally spaced by a distance D10.4 m. Dividing according to theoretical sections to obtain a grouting pipe curtain support unsealed section b being 5m, an unbuttled section c being 1.6m and a plastic disturbance sectionAt the same time, the elastic disturbance section e can be obtained as 2.0hu-c;
By adopting the method steps, a matlab program is compiled, stratum and grouting pipe curtain parameters are substituted, and an analytic solution of the flexural deformation of the grouting pipe curtain is solved; comparing and analyzing the calculated deformation value of the grouting pipe curtain with the existing theoretical value and the field measured value according to the actually measured distribution and the theoretical distribution comparison diagram of the actually measured deflection deformation of the grouting pipe curtain shown in fig. 5;
according to the theoretical curve and the on-site actual measurement scatter points, the grouting pipe curtain deflection deformation distribution obtained by the calculation method is basically consistent with the actual measurement result, the reliable prediction performance is displayed, and guidance can be provided for design and construction; in addition, the invention reasonably considers the distribution change characteristic of the stratum foundation bed coefficient along with excavation, and can more accurately reflect the axial beam forming effect of the grouting pipe curtain.
The above-mentioned embodiments are merely illustrative of the preferred embodiments of the present invention, and do not limit the scope of the present invention, and various modifications and improvements made to the technical solution of the present invention by those skilled in the art without departing from the spirit of the present invention should fall within the protection scope defined by the claims of the present invention.
Claims (5)
1. A grouting pipe curtain deformation calculation method based on the characteristics of soil arches between pipes is characterized by comprising the following steps:
s1, analyzing the transverse soil arch characteristic of the grouting pipe curtain and determining a supporting load;
s2, analyzing the axial beam forming effect of the grouting pipe curtain, and determining a control equation;
s3, establishing a grouting pipe curtain long beam theoretical model, and determining load distribution;
and S4, solving the flexural deformation through a slip casting tube curtain difference calculation method.
2. The grouting pipe curtain deformation calculation method based on the characteristics of the soil arch between pipes as claimed in claim 1, wherein the step S1 is specifically realized by the following method:
s11, according to the Purchase pressure arch theory, considering the soil arch characteristic between adjacent grouting pipe curtains, and establishing a corresponding mechanical model: the grouting pipe curtains are regarded as cylindrical steel pipes and are distributed in the circumferential direction of the outer ring of the tunnel arch part at equal intervals; htAnd BtRespectively the height and the span of the excavated tunnel, the outer diameter of the tunnel is R, the gravity of the surrounding rock is gamma, and the outer diameter of the grouting pipe curtainD, the distance between two adjacent grouting pipe curtains is D1A clear spacing of D2The included angle between two adjacent grouting pipe curtains is alpha,the friction angle of the surrounding rock is R + g, and the radius of the circular arc of the grouting pipe curtain is R + g;
s12, numbering each grouting pipe curtain from the vault to two sides in sequence, and regarding the gravity of the loose rock mass in the pressure arch area as the load of the grouting pipe curtains, wherein any one number is CnThe corresponding load height of the grouting pipe curtain is HdnAnd C isnThe serial numbers of two adjacent grouting pipe curtains are marked as Cn-1And Cn+1And with CnThe horizontal included angle of the grouting pipe curtain is recorded as thetan-1And thetan+1;
S13, in the mechanical model of grouting pipe curtains, defining the central connecting line of two adjacent grouting pipe curtains as an x axis, defining the vertical central line of two adjacent grouting pipe curtains as a y axis, establishing a plurality of rectangular coordinate systems, analyzing the load height corresponding to the grouting pipe curtains by establishing a soil arch axis in each coordinate system, and analyzing the soil arch axis by the equation y-mx without considering the tensile strength of rock mass2A parabola denoted by + n;
s14 grouting pipe curtain Cn-1And CnIn a rectangular coordinate system, the soil arch axis and the grouting pipe curtain Cn-1And CnHas a crossing point of V1And V2Are each independently of V1And grouting pipe curtain Cn-1Line connecting the centers of circles, V2And grouting pipe curtain CnThe intersection points of the segment perpendicular to the connecting line of the circle centers and the x axis are respectively M1And M2Suppose line segment V1Cn-1、V2CnAre all tangent with the soil arch axis and have included angles with the x axisThen line segment V1M1、V2M2At an angle to the x-axis ofThen V2The coordinates of the points can be expressed as
S15, mixing V2The coordinates of the points are brought into the soil arch axis equation, and the following are obtained by solution:
uniform load q above the earth arch axisn-1And q isn-1Obtained by the following analytical formula:
vertical concentrated load p of soil arch axisn-1And pn+1Can be expressed as:
averaging the two to obtain a grouting pipe curtain CnUpper side ofVertical load p ofn:
3. The grouting pipe curtain deformation calculation method based on the characteristics of the soil arch between pipes as claimed in claim 1, wherein the step S2 is specifically realized by the following method:
s21, regarding the surrounding rock as a homogeneous and continuous elastic-plastic entity, so that the flexural deformation of the grouting pipe curtain has the mechanical characteristics of Bernoulli-Euler beam, thereby obtaining a grouting pipe curtain mechanical model based on the Pasternak elastic-plastic foundation beam, and obtaining the grouting pipe curtain mechanical model according to the reaction analytical formula of the Pastemak foundation beam by the following formula:
wherein: p (x) is the resistance of the surrounding rock foundation, k is the coefficient of the surrounding rock bed, w (x) is the flexural deformation of the grouting pipe curtain, GpIs the shear modulus of the surrounding rock foundation;
s22, considering tunnel support hysteresis, foundation bed coefficient change, stress release and stratum elastoplasticity factors, and sequentially dividing the grouting pipe curtain into a support closed section OA, a support non-closed section AB, a non-support section BC, a plastic disturbance section CD, an elastic disturbance section DE and a non-disturbance section EF from back to front along the advancing direction of the excavation face;
s23, obtaining the following results due to the balanced stress of the units:
wherein V (x) is shearing force of grouting pipe curtain, M (x) is bending moment of grouting pipe curtain, q (x) is load borne by grouting pipe curtain, b is width of surrounding rock foundation beam, b*Is equivalent to the width of the surrounding rock foundation, b*=b[1+(Gp/k)1/2/b];
S24, based on Bernoulli-Euler beam theory, the mechanical response of the grouting pipe curtain can be obtained, including the differential analytic formula of grouting pipe curtain deflection angle theta (x), longitudinal strain epsilon (x), grouting pipe curtain shear force V (x), grouting pipe curtain bending moment M (x) and grouting pipe curtain deflection deformation W (x):
solving a differential balance equation for controlling the deformation of the grouting pipe curtain through the formulas (9) to (13):
4. the grouting pipe curtain deformation calculation method based on the characteristics of the soil arch between pipes as claimed in claim 1, wherein the step S3 is specifically realized by the following method:
and (3) obtaining a grouting pipe curtain mechanical model of the Pastemak foundation beam by considering the soil arch characteristic of the grouting pipe curtain and the space-time effect of stratum load:
the primary support closed section OA has a length of a, and the load borne by the grouting pipe curtain in the section is static load, namely q (x) q0,q0Calculating values according to a Prov theory formula; resistance of the zone surrounding rock foundationThe differential balance of the control in this section is formulated as
The initial branch unblocked section AB has the length of b, and the external load q (x) borne by the grouting pipe curtain of the section is [1+ (eta)1-1)(x-a)/(b+s)]q0Time-space coefficient eta of stress release of surrounding rock load1Taking 0.5; resistance of the primary support surrounding rock foundation of the sectionSurrounding rock foundation coefficient k in formulac(x)=-kcx/b+(a+b)kcB, and k at point Bcmin0; the differential balance of control for that segment is formulated as
For the unsupported section BC with the length of c, the distribution form of external load borne by the grouting pipe curtain of the section is the same as that of the section AB, and because the initial support of the section BC is not applied, the load p (x) is also taken to be 0, the differential balance formula controlled by the section is as follows
Plastic perturbation zone CD of lengthWherein h isuIs the height of the tunnel step,the friction angle is calculated for the surrounding rock. In addition, the front of the excavation surface has a remarkable stress concentration phenomenon, and the space-time coefficient eta of the release of the load stress of the surrounding rock at the D point is taken2Take 1.2, the section bears the external load q (x) ═ η2-η1)[x-(a+b+c)]q0/d+η1q0(ii) a Resistance of the zone surrounding rock foundationk0(x)=[x-(a+b+c+d)](k0-k0min)/s+k0minWhere s is the length of the rock mass before the excavation face, k0Constant coefficient of rock mass bed, k, without disturbance0minIs a ground reduction factor, and k0min=0.6k0(ii) a The differential balance of the control in this section is formulated as
The elastic disturbance section DE is of length e, and the total length of the elastic disturbance section and the undisturbed section of the large-span tunnel grouting pipe curtain is taken as 2huThe segment slip casting tube bears the load q (x) ═ η2[x-(a+b+c+d)]q0/s+η2q0The resistance of the surrounding rock foundation of the section is consistent with the CD section, and the section is takenThe differential balance of the control in this section is formulated as
An undisturbed section EF with the length f, which is the length of the residual grouting pipe curtain after deducting each section in front; the section grouting pipe curtain is not subjected to any external load, and if q (x) is 0, the resistance of the section surrounding rock foundation is obtainedThe differential balance of the control in this section is formulated as
5. The grouting pipe curtain deformation calculation method based on the characteristics of the soil arch between pipes as claimed in claim 1, wherein the step S4 is specifically realized by the following method:
s41, equally dividing the grouting pipe curtain with the length of L into n sections, and according to the sequence from left to right, each node is compiled into 0, 10The deflection deformation of the grouting pipe curtain of the node i is wi, and in order to adapt to the analytic degree of freedom of the grouting pipe curtain, two different virtual nodes-2, -1, n +1 and n +2 are respectively arranged on the left side and the right side;
and S42, carrying out Taylor formula expansion on the deformation of the left and right adjacent nodes of the node i, and taking the four polynomials in front of the Taylor expansion formula to ensure the analysis accuracy.
This enables the derivation of the various derivatives:
s43, combining the above formulas to solve the grouting tube curtain deflection difference formula:
Ci(wi-2-4wi-1+6wi-4wi+1+wi+2)+Biwi-Di(-wi-2+16wi-1-30wi+16wi+1-wi+2)=qi (23)
analyzing and expressing mechanical boundary conditions on two sides of the grouting pipe curtain:
simultaneous implementation of the above formula yields:
when i is 0, 1, n-1, n, the simplified slip casting curtain deflection difference formula can be converted into:
C0(w-2-4w-1+6w0-4w1+w2)+B0w0-D0(-w-2+16w-1-30w0+16w1-w2)=q0
C1(w-1-4w0+6w1-4w2+w3)+B1w1-D1(-w-1+16w0-30w1+16w2-w3)=q1
Cn-1(wn-3-4wn-2+6wn-1-4wn+wn+1)+Bn-1wn-1-Dn-1(-wn-3+16wn-2-30wn-1+16wn-wn+1)=qn-1
Cn(wn-2-4wn-1+6wn-4wn+1+wn+2)+Bnwn-Dn(-wn-2+16wn-1-30wn+16wn+1-wn+2)=qn
handle w-2、w-1、w1、w2Substituting, one can get:
s44, the above equation is expressed in a matrix form to obtain:
{[B]+[C]-[D]}{w}={p}
wherein the matrix dimensions of [ B ], [ C ] and [ D ] are all N +1, and the expression is as follows:
in addition, the grouting pipe curtain bears the expression of the load matrix { p }:
{p}={p0 p1 p2…pn-1 pn}T
and then the expression of the grouting pipe screen deflection matrix { w } can be obtained:
{w}={w0 w1 w2…wn-1 wn}T
and S45, writing a Matlab program, and solving the flexural deformation wi of each node of the grouting pipe curtain.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111602961.6A CN114398699A (en) | 2021-12-24 | 2021-12-24 | Grouting pipe curtain deformation calculation method based on inter-pipe soil arch characteristics |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111602961.6A CN114398699A (en) | 2021-12-24 | 2021-12-24 | Grouting pipe curtain deformation calculation method based on inter-pipe soil arch characteristics |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114398699A true CN114398699A (en) | 2022-04-26 |
Family
ID=81226043
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111602961.6A Pending CN114398699A (en) | 2021-12-24 | 2021-12-24 | Grouting pipe curtain deformation calculation method based on inter-pipe soil arch characteristics |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114398699A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116579057A (en) * | 2023-04-24 | 2023-08-11 | 山东建筑大学 | Prediction and control method for deformation of transverse pipe curtain or pipe shed of pilot tunnel excavation |
CN117852313A (en) * | 2024-03-07 | 2024-04-09 | 山东大学 | Advanced sectional pre-grouting rapid numerical simulation method and system for underground engineering |
CN117852313B (en) * | 2024-03-07 | 2024-05-10 | 山东大学 | Advanced sectional pre-grouting rapid numerical simulation method and system for underground engineering |
-
2021
- 2021-12-24 CN CN202111602961.6A patent/CN114398699A/en active Pending
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116579057A (en) * | 2023-04-24 | 2023-08-11 | 山东建筑大学 | Prediction and control method for deformation of transverse pipe curtain or pipe shed of pilot tunnel excavation |
CN116579057B (en) * | 2023-04-24 | 2024-03-08 | 山东建筑大学 | Prediction and control method for deformation of transverse pipe curtain or pipe shed of pilot tunnel excavation |
CN117852313A (en) * | 2024-03-07 | 2024-04-09 | 山东大学 | Advanced sectional pre-grouting rapid numerical simulation method and system for underground engineering |
CN117852313B (en) * | 2024-03-07 | 2024-05-10 | 山东大学 | Advanced sectional pre-grouting rapid numerical simulation method and system for underground engineering |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Wang et al. | Comparative study of model tests on automatically formed roadway and gob-side entry driving in deep coal mines | |
Lai et al. | Settlement behaviors of existing tunnel caused by obliquely under-crossing shield tunneling in close proximity with small intersection angle | |
Zhang et al. | Analytical solution for the response of an existing tunnel to a new tunnel excavation underneath | |
Zheng et al. | Experimental investigation of mechanical characteristics for linings of twins tunnels with asymmetric cross-section | |
Yang et al. | Ground movement prediction for tunnels using simplified procedure | |
Ma et al. | Responses of pipeline to side-by-side twin tunnelling at different depths: 3D centrifuge tests and numerical modelling | |
Liu et al. | Large deformation mechanism and concrete-filled steel tubular support control technology of soft rock roadway-A case study | |
Li et al. | An improved numerical simulation approach for arch-bolt supported tunnels with large deformation | |
CN114398698A (en) | Method for evaluating support effect of deep-buried pipe curtain based on inter-pipe soil arch characteristics | |
CN114398699A (en) | Grouting pipe curtain deformation calculation method based on inter-pipe soil arch characteristics | |
Luo et al. | Mechanical responses of surrounding rock mass and tunnel linings in large-span triple-arch tunnel | |
Huang et al. | Structural behavior of segmental tunnel linings for a large stormwater storage tunnel: insight from full-scale loading tests | |
Zhu et al. | The angle for setting foot reinforcement bolt based on the failure mode of shallow tunnel in loess | |
Liu et al. | Study on soil gap formation beneath existing underground structures due to new excavation below | |
Zhang et al. | Experimental study on mechanical behavior of the skew joints of shield tunnels under large eccentric compressive loading | |
Feng et al. | Analysis on the stiffness iteration of segmental joints in segmental linings: Method and sensitivity analysis | |
Qi et al. | Structural deformation of existing horseshoe-shaped tunnels by shield overcrossing | |
Xu et al. | Displacement ratio dichotomy back analysis of surrounding rock-initial support system of weathered rock tunnel | |
Liu et al. | Seismic response of underground structure–soil–aboveground structure coupling system: Current status and future prospects | |
Hu et al. | Effects of discontinuities on stress redistribution and rock failure: A case of underground caverns | |
Ledyaev et al. | An assessment of the sewer tunnel stress-strain behavior during the reconstruction of an object of cultural heritage | |
Tian et al. | Disaster-inducing mechanism in a roadway roof near the driving face and its safety-control criteria | |
CN109681251B (en) | Design method of full-section excavated soft soil tunnel face glass fiber anchor rod | |
Nomikos et al. | Nonlinear simulation of lattice girder segment tests | |
Su et al. | A case study of the failure of Liziping tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |