CN114369976A - Method for laying ground track supported at intervals - Google Patents
Method for laying ground track supported at intervals Download PDFInfo
- Publication number
- CN114369976A CN114369976A CN202111592726.5A CN202111592726A CN114369976A CN 114369976 A CN114369976 A CN 114369976A CN 202111592726 A CN202111592726 A CN 202111592726A CN 114369976 A CN114369976 A CN 114369976A
- Authority
- CN
- China
- Prior art keywords
- rail
- pressing device
- steel
- track
- bolt
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B29/00—Laying, rebuilding, or taking-up tracks; Tools or machines therefor
- E01B29/16—Transporting, laying, removing, or replacing rails; Moving rails placed on sleepers in the track
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B35/00—Applications of measuring apparatus or devices for track-building purposes
- E01B35/02—Applications of measuring apparatus or devices for track-building purposes for spacing, for cross levelling; for laying-out curves
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B35/00—Applications of measuring apparatus or devices for track-building purposes
- E01B35/06—Applications of measuring apparatus or devices for track-building purposes for measuring irregularities in longitudinal direction
- E01B35/08—Applications of measuring apparatus or devices for track-building purposes for measuring irregularities in longitudinal direction for levelling
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B9/00—Fastening rails on sleepers, or the like
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B9/00—Fastening rails on sleepers, or the like
- E01B9/60—Rail fastenings making use of clamps or braces supporting the side of the rail
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The invention provides a ground track laying method of interval support, belonging to the technical field of track transportation, wherein an adjusting nut of an anchor bolt is adjusted to a set height; mounting the support steel plate to the anchor bolt using a first fastening nut; measuring the track installation position of the paying-off mark above the supporting steel plate, and hoisting the steel rail on the supporting steel plate according to the track installation position; welding a rail pressing device bottom plate on the support steel plates on the two sides of the steel rail, and pre-installing a rail pressing device cover plate and the rail pressing device bottom plate through rail pressing device bolts; removing the first fastening nut and fastening the rail pressing device bolt until the steel rail is tightly pressed with the supporting steel plate; adjusting the adjusting nut until the top surface of the steel rail is on a horizontal plane with a set height; and completely fastening the foundation bolt by using a first fastening nut. The invention achieves the technical effect of quickly and efficiently laying the track.
Description
Technical Field
The invention relates to the technical field of rail transportation, in particular to a ground rail laying method of interval support.
Background
The ground rail transportation has the characteristics of large carrying capacity, stable operation and safe operation, is a common mode for transporting materials and finished products in a factory, and is generally a straight line transportation path.
The common ground track steel rail installation mode is that support steel plates are laid on a strip track foundation at intervals along the longitudinal direction of the steel rail, and the support steel plates are fixed with the strip track foundation through foundation bolts. And (3) performing secondary grouting between the support steel plate and the strip-shaped track foundation, then paving the steel rail on the fixed support steel plate and welding a rail pressing device to complete the installation of the ground track steel rail. But has the following disadvantages:
the requirement on the installation tightness of the steel rail and the supporting steel plate is higher because the load of the ground track steel rail is larger; however, the number of the supporting steel plates is large, all the supporting steel plates are required to be fixed in the same horizontal plane, and the construction difficulty is large.
Therefore, a need exists for a method of quickly and efficiently laying spaced-apart ground rails.
Disclosure of Invention
The invention aims to provide a ground track laying method for interval support, and the technical effect of improving track laying efficiency is achieved.
A method for laying spaced-apart supported ground rails includes the steps of,
adjusting an adjusting nut of the foundation bolt to a set height;
mounting the support steel plate to the anchor bolt using a first fastening nut;
measuring the track installation position of the paying-off mark above the supporting steel plate, and hoisting the steel rail on the supporting steel plate according to the track installation position;
welding a rail pressing device bottom plate on the support steel plates on the two sides of the steel rail, and pre-installing a rail pressing device cover plate and the rail pressing device bottom plate through rail pressing device bolts;
removing the first fastening nut and fastening the rail pressing device bolt until the steel rail is tightly pressed with the supporting steel plate;
adjusting the adjusting nut until the top surface of the steel rail is on a horizontal plane with a set height;
and completely fastening the foundation bolt by using a first fastening nut.
Further, preferably, the rail mounting position includes a rail center line and a rail edge line.
Further, preferably, the rail pressing devices are symmetrically and uniformly arranged along two sides of the steel rail at a distance not more than 500-600 mm.
Further, it is preferable that a second fastening nut for reinforcement is installed above the first fastening nut after the anchor bolt is completely fastened using the first fastening nut.
Further, preferably, a T-shaped slot is formed in the rail pressing device bottom plate, and the rail pressing device bolt penetrates through the T-shaped slot and sinks a bolt head of the rail pressing device bolt in the slot.
Further, preferably, adjusting the adjusting nut until the top surface of the rail is on a level of a set height comprises,
and arranging an electronic level gauge on the top surface of the steel rail, detecting the height of the top surface of the steel rail through the precise level gauge, and adjusting the adjusting nut until the top surface of the steel rail is on a horizontal plane with a set height.
As described above, according to the ground track laying method of the interval bearing, the rail pressing device bottom plate is welded firstly, then the supporting steel plate and the steel rail are assembled, and secondary grouting is performed after the installation and alignment of the steel rail; the technical effect of eliminating the installation deviation of the supporting steel plates is achieved by adjusting the installation sequence; in addition, the strength waiting period of the rail press bottom plate after secondary grouting is saved, and the heat influence on a secondary grouting layer in the welding process of the rail press is further avoided; thereby achieving the technical effects of rapid and efficient track laying.
Drawings
Other objects and results of the present invention will become more apparent and more readily appreciated as the same becomes better understood by reference to the following description and appended claims, taken in conjunction with the accompanying drawings. In the drawings:
FIG. 1 is a logic schematic of a spaced-apart supported ground track laying method according to an embodiment of the present invention;
FIG. 2 is a schematic view of an installation scenario of a spaced-apart supported ground track laying method according to an embodiment of the present invention;
fig. 3 is a side view of fig. 1.
Wherein the content of the first and second substances,
1. a steel rail; 2. a rail pressing device; 3. fastening a nut; 4. adjusting the nut; 5. anchor bolts; 6. a support steel plate; 7. secondary grouting layer; 8. and (4) a track foundation.
Detailed Description
In the following description, for purposes of explanation, numerous specific details are set forth in order to provide a thorough understanding of one or more embodiments. It may be evident, however, that such embodiment(s) may be practiced without these specific details. In other instances, well-known structures and devices are shown in block diagram form in order to facilitate describing one or more embodiments.
It is to be understood that the terms "horizontal," "vertical," "upper," "lower," "top," "middle," "length," "inner," "bottom," and the like are used merely for convenience in describing the invention and to simplify the description, and do not indicate or imply that the components or elements so referred to must be in a particular orientation, constructed and operated in a particular orientation, and thus are not to be considered limiting of the invention.
Unless expressly stated or limited otherwise, the terms "mounted," "connected," "secured," and the like are intended to be inclusive and mean that, for example, they may be fixedly connected or detachably connected or integrally formed; may be mechanically coupled, may be electrically coupled or may be in communication with each other; they may be directly connected or indirectly connected through intervening media, or they may be connected internally or in any other suitable relationship, unless expressly stated otherwise. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
In the prior art, the problem that the installation precision of a support steel plate cannot be effectively controlled in the whole construction process, so that gaps of different degrees exist between a rail bottom and the support steel plate in the later period, and the stability of a transport vehicle for bearing capacity of a track is further influenced exists; the invention provides a ground track laying method of interval bearing, through welding the bottom plate of the rail pressing device first, then assemble supporting steel plate and rail, carry on the secondary grouting after the installation alignment to the rail; the technical effect of eliminating the installation deviation of the supporting steel plates is achieved by adjusting the installation sequence; in addition, the strength waiting period of the rail press bottom plate after secondary grouting is saved, and the technical effect of avoiding the heat influence on the secondary grouting layer in the welding process of the rail press is achieved.
Example 1
Various embodiments of the present invention will be described in detail below with reference to the accompanying drawings.
Fig. 1 illustrates the logical principle of the method for laying a spaced-apart ground rail. Specifically, fig. 1 is a logic schematic diagram of a spaced-apart supported ground track laying method according to an embodiment of the present invention.
The method for laying the ground track supported at intervals comprises the steps S110 to S160.
S110, adjusting the adjusting nut 4 of the foundation bolt 5 to a set height; the anchor bolts 5 are pre-installed to the supporting steel plate 6 using the first fastening nuts 3.
Specifically, the adjusting nuts 4 of the anchor bolts 5 are adjusted to a uniform elevation, the bolt holes of the support steel plates 6 are inserted through the anchor bolts 5, and then the support steel plates 5 are roughly leveled by screwing one of the fastening nuts 3 above the support steel plates 6. The pre-mounting here is only to manually tighten the first fastening nut 3. That is, the anchor bolts are through bolts, and the impact force from the rail 1 is transmitted to the ground by the through bolts, thereby extending the life of the rail.
S120, measuring the track installation position of the paying-off mark above the supporting steel plate 6, and hoisting the steel rail 1 on the supporting steel plate 6 according to the track installation position.
Fig. 2 and 3 illustrate a scene structure of the spaced-apart ground track laying method as a whole. Specifically, fig. 2 is a schematic structural view of a spaced-apart support ground track laying method according to embodiment 1 of the present invention. Fig. 3 is a side view of fig. 2.
As shown in fig. 2 and 3, the rail mounting locations include a rail centerline and a rail edge line. That is, the center line and the edge line of the rail are popped out with ink lines above the respective supporting steel plates 6. Then the steel rail 1 is hoisted on each supporting steel plate 6, and rail pressing device bottom plates are welded on the supporting steel plates 6 at the two sides of the rail after the edges are aligned.
S130, welding the rail pressing device bottom plate 2 on the supporting steel plates on the two sides of the steel rail, and pre-installing the rail pressing device cover plate and the rail pressing device bottom plate through rail pressing device bolts.
The rail pressing device 2 comprises a rail pressing device bottom plate, a rail pressing device bolt and a rail pressing device cover plate; the rail pressing device cover plate and the steel rail are fixed on the rail pressing device bottom plate through the rail pressing device bolts. The rail pressing devices are symmetrically and uniformly arranged along two sides of the steel rail at a distance not more than 500-600 mm. The rail pressing device is characterized in that a T-shaped groove hole is formed in the rail pressing device bottom plate, the rail pressing device bolt penetrates through the T-shaped groove hole and enables a bolt head of the rail pressing device bolt to be sunk in the groove hole.
That is to say, set up relative through-hole on pressing the rail ware bottom plate and the rail ware apron, wear to establish rail ware bolt from pressing the rail ware bottom plate upwards, press the rail ware bolt to fasten in rail ware apron department. Since the ballast plate is welded to the rail base below it, the head of the ballast bolt must be sunk into the interior of the ballast base. In the specific implementation process, a stepped hole is formed in the rail pressing device base, and the size of an inner ring of the stepped hole is smaller than that of the head of a rail pressing device bolt. During installation, the screw rod of the rail pressing device bolt penetrates through the stepped hole, the head of the rail pressing device bolt is accommodated on the stepped platform, the bolt head of the rail pressing device bolt is sunk into the rail pressing device bottom plate, and the bolt head of the rail pressing device bolt is clamped and fixed.
In a word, after the rail pressing device bottom plate is firmly welded, the rail pressing device cover plate is pressed, the rail pressing device bolt of the rail pressing device cover plate is screwed down by hands, and a certain gap is formed between the steel rail and each supporting steel plate. It should be noted that, the rail pressing device cover plate and the rail pressing device bottom plate are pre-installed by manually tightening the bolts, so that a gap is reserved between the steel rail and the support steel plate.
In specific implementation process, an elastic base plate can be arranged between the steel rail and the supporting steel plate, imbalance caused by small gaps can be eliminated by arranging the elastic base plate, and the service life of the steel rail can be prolonged by increasing buffering.
S140, the first fastening nut 3 is removed, and the rail pressing device bolt is fastened until the steel rail 1 is tightly pressed with the support steel plate 6. That is, the fastening nut above the supporting steel plate 6 is loosened, and then the rail presser bolt is further tightened with a tool such as a wrench, to eliminate the gap between the rail and the supporting steel plate.
The rail pressing device bottom plate is welded firstly, then the supporting steel plate and the steel rail are assembled, and secondary grouting is carried out after the steel rail is installed and aligned. Namely, after the support steel plate 6 of the steel rail and the steel rail 1 are connected into a whole through the rail pressing device 2, the installation and the alignment are simple and convenient. The rail pressing devices on two sides of the steel rail do not need to be adjusted left and right, and secondary adjustment caused by slippage of the rail pressing devices which are not flat on the road surface can not be generated. The multiple adjustment processes of steel rail installation are saved, and the efficiency of track laying is improved.
S150, adjusting the adjusting nut 4 until the top surface of the steel rail 1 is on a horizontal plane with a set height.
Specifically, the adjusting nut 4 is adjusted until the top surface of the steel rail 1 is on the level of the set height, and the adjusting nut is adjusted until the top surface of the steel rail is on the level of the set height by arranging an electronic level gauge on the top surface of the steel rail, detecting the height of the top surface of the steel rail through a precision level gauge and adjusting the adjusting nut until the top surface of the steel rail is on the level of the set height.
And S160, completely fastening the foundation bolt by using the first fastening nut 3.
After the anchor bolt is completely tightened using the first fastening nut, a second fastening nut for reinforcement is installed above the first fastening nut. That is, after the top surface level of the steel rail reaches the design requirement by adjusting the adjusting nuts 4 below the supporting steel plates 6, the fastening nuts above the supporting steel plates 6 are tightened and the backup nuts are pressed to form double nut fixing. That is, the adjustment of the rail and the supporting steel plate is performed in two times of the pre-adjustment and the re-adjustment.
In conclusion, the invention relates to a ground track laying method of interval bearing, which eliminates the mounting error of a support steel plate by changing the mounting sequence, fastening a rail pressing device and the self rigidity of a track, and then performs secondary grouting, thereby achieving the technical effect of improving the mounting precision of the track.
However, it will be appreciated by those skilled in the art that various modifications may be made to the above-described spaced-apart support ground track laying method provided by the present invention without departing from the spirit and scope of the invention. Therefore, the scope of the present invention should be determined by the contents of the appended claims.
Claims (6)
1. A method for laying a ground track supported at intervals is characterized in that,
adjusting an adjusting nut of the foundation bolt to a set height;
mounting the support steel plate to the anchor bolt using a first fastening nut;
measuring the track installation position of the paying-off mark above the supporting steel plate, and hoisting the steel rail on the supporting steel plate according to the track installation position;
welding a rail pressing device bottom plate on the support steel plates on the two sides of the steel rail, and pre-installing a rail pressing device cover plate and the rail pressing device bottom plate through rail pressing device bolts;
removing the first fastening nut and fastening the rail pressing device bolt until the steel rail is tightly pressed with the supporting steel plate;
adjusting the adjusting nut until the top surface of the steel rail is on a horizontal plane with a set height;
and completely fastening the foundation bolt by using a first fastening nut.
2. The spaced apart supported ground track laying method of claim 1, wherein the track mounting locations include a track centerline and a track edge line.
3. The method of laying a spaced-apart supported ground track according to claim 1 wherein the rail presses are symmetrically and uniformly spaced along both sides of the rail by a distance of not more than 500 mm to 600 mm.
4. The spaced apart supported ground track laying method according to claim 1, wherein after the anchor bolts are completely fastened by the first fastening nuts, second fastening nuts for reinforcement are installed above the first fastening nuts.
5. The method of laying a spaced-apart supported ground rail according to claim 1, wherein a T-shaped slot is provided in the rail press base plate, the rail press bolt is inserted through the T-shaped slot and a bolt head of the rail press bolt is sunk into the slot.
6. The method of laying spaced apart supported ground rails according to claim 1, wherein adjusting the adjustment nut until the top surface of the rail is at a set height level comprises,
and arranging an electronic level gauge on the top surface of the steel rail, detecting the height of the top surface of the steel rail through the precise level gauge, and adjusting the adjusting nut until the top surface of the steel rail is on a horizontal plane with a set height.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111592726.5A CN114369976B (en) | 2021-12-23 | 2021-12-23 | Method for laying ground rail with interval support |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111592726.5A CN114369976B (en) | 2021-12-23 | 2021-12-23 | Method for laying ground rail with interval support |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114369976A true CN114369976A (en) | 2022-04-19 |
CN114369976B CN114369976B (en) | 2023-08-22 |
Family
ID=81141900
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111592726.5A Active CN114369976B (en) | 2021-12-23 | 2021-12-23 | Method for laying ground rail with interval support |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114369976B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114934413A (en) * | 2022-06-29 | 2022-08-23 | 中核华辰建筑工程有限公司 | Group ground steel rail construction method |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201158786Y (en) * | 2008-01-21 | 2008-12-03 | 武汉冶建安装工程有限责任公司 | Ground rail installation apparatus |
CN202414979U (en) * | 2011-10-28 | 2012-09-05 | 上海宝钢工业检测公司 | Base-adjustable track connecting device on concrete base |
CN103321111A (en) * | 2013-07-01 | 2013-09-25 | 中冶交通(沈阳)建设工程有限公司 | Tramcar track continuous-laying construction method |
CN106758562A (en) * | 2017-04-08 | 2017-05-31 | 中国二十二冶集团有限公司 | The installation method that track foundation built-in fitting is integrally fixed with track |
WO2017121044A1 (en) * | 2016-01-11 | 2017-07-20 | 北京城建设计发展集团股份有限公司 | Precast slab railway track structural system for vibration mitigation and associated construction method |
JP2018127768A (en) * | 2017-02-06 | 2018-08-16 | 公益財団法人鉄道総合技術研究所 | Sleeper replacement method |
-
2021
- 2021-12-23 CN CN202111592726.5A patent/CN114369976B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201158786Y (en) * | 2008-01-21 | 2008-12-03 | 武汉冶建安装工程有限责任公司 | Ground rail installation apparatus |
CN202414979U (en) * | 2011-10-28 | 2012-09-05 | 上海宝钢工业检测公司 | Base-adjustable track connecting device on concrete base |
CN103321111A (en) * | 2013-07-01 | 2013-09-25 | 中冶交通(沈阳)建设工程有限公司 | Tramcar track continuous-laying construction method |
WO2017121044A1 (en) * | 2016-01-11 | 2017-07-20 | 北京城建设计发展集团股份有限公司 | Precast slab railway track structural system for vibration mitigation and associated construction method |
JP2018127768A (en) * | 2017-02-06 | 2018-08-16 | 公益財団法人鉄道総合技術研究所 | Sleeper replacement method |
CN106758562A (en) * | 2017-04-08 | 2017-05-31 | 中国二十二冶集团有限公司 | The installation method that track foundation built-in fitting is integrally fixed with track |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114934413A (en) * | 2022-06-29 | 2022-08-23 | 中核华辰建筑工程有限公司 | Group ground steel rail construction method |
Also Published As
Publication number | Publication date |
---|---|
CN114369976B (en) | 2023-08-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US7938379B2 (en) | Three axis adjustable mounting system | |
EP2893082B1 (en) | Adjustable rail fastening assembly | |
CN114369976A (en) | Method for laying ground track supported at intervals | |
US7257925B2 (en) | Floor-mounted rail for a mobile storage system | |
JP5346523B2 (en) | Mounting method and joint structure | |
CN202416097U (en) | Supporting and adjusting equipment | |
WO2022241936A1 (en) | Seamless track railway structure for normal conductive short stator magnetic levitation system | |
CN213139797U (en) | Fixing device of superimposed sheet transportation frame | |
KR20200032550A (en) | No-welding prefabricated anchor base system | |
JP5412307B2 (en) | Installation method of bridge support device and fixing jig used in the method | |
JP3908024B2 (en) | Magnetically levitated linear motor car track | |
JP2004026372A (en) | Installing method for emergency stop devices of elevator | |
CN109914851B (en) | Assembled bracket for being mounted at top of steel pipe pile | |
CN111439525B (en) | Pressing and fixing device and method for conveying roller supporting beam | |
JP2006336231A (en) | Composite floor slab | |
CN219951570U (en) | Quick-dismantling structure for inspection pit track | |
JP2589046Y2 (en) | Rail frame bearing device | |
CN112124521A (en) | Installation method of transverse ring insulation module of liquid cargo tank of LNG ship | |
CN217078232U (en) | A track subassembly that is used for fixed track's subassembly and has it | |
CN213389541U (en) | Adjusting device for wear-resisting plate of non-driving track | |
CN114852488B (en) | Railway vehicle body storage and transportation integrated tool, railway vehicle and method | |
CN108316072B (en) | Temporary fixing device for steel rail | |
JPS644884Y2 (en) | ||
CN218318371U (en) | Bridge deck transportation tool | |
CN220184633U (en) | Beam bottom limiting beam side template supporting size adjusting assembly |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |