CN114290513A CN202111439506.9A CN202111439506A CN114290513A CN 114290513 A CN114290513 A CN 114290513A CN 202111439506 A CN202111439506 A CN 202111439506A CN 114290513 A CN114290513 A CN 114290513A
Authority
CN
China
Prior art keywords
block
wall
groove
arc
annular
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111439506.9A
Other languages
Chinese (zh)
Other versions
CN114290513B (en
Inventor
张小亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202111439506.9A priority Critical patent/CN114290513B/en
Publication of CN114290513A publication Critical patent/CN114290513A/en
Application granted granted Critical
Publication of CN114290513B publication Critical patent/CN114290513B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a concrete pipe pile pouring die which comprises a cylindrical rotating block, a first annular stop block and a second annular stop block, wherein the inner wall of the cylindrical rotating block is rotatably connected with a rotating shaft, the upper end of the rotating shaft penetrates through the upper end of the cylindrical rotating block, the cylindrical rotating block is fixedly connected with the first annular stop block through a fixed block, the inner wall of the cylindrical rotating block penetrates through a sliding groove, the inner wall of the sliding groove is slidably connected with a connecting block, two ends of the connecting block are respectively fixed with the second annular stop block and the rotating shaft, and sealing grooves are formed in the inner walls of the first annular stop block and the second annular stop block. Through setting up spacing chucking device, can realize the installation of pairing of a plurality of moulds that fill, conveniently pour the concrete pipe pile of co-altitude not, can effectively increase the suitability of the mould that fills, set up the less and mould that fills that can splice of a plurality of volumes moreover, can conveniently fill the transportation of mould, reducible cost of transportation can make things convenient for the use that the concrete was filled.

Description

Concrete pipe pile filling mould
Technical Field
The invention relates to the technical field of concrete pipe piles, in particular to a concrete pipe pile pouring mold.
Background
The pretensioned prestressed concrete pipe piles are beginning to be applied to railway systems in a large number, and are expanded to the fields of industry, civil construction, municipal administration, metallurgy, ports, highways and the like, in particular regions, as the geological conditions are suitable for the use characteristics of the pipe piles, the demand of the pipe piles is increased rapidly, so that a new industry is formed rapidly, and most of the pipe piles are formed by pouring by using a pipe pile pouring mold;
and traditional concrete pipe pile fills mould structure comparatively fixed, only can realize filling the tubular pile of corresponding height, and the suitability is relatively poor, and the mould volume is general great, can have the inconvenient problem of transportation, and the form removal in-process is comparatively complicated moreover, can influence its concrete pipe pile's machining efficiency greatly, for this reason, we have provided the concrete pipe pile that the suitability is higher and be convenient for transport fills the mould.
The invention aims to solve the problems of low applicability and inconvenient transportation in the prior art, and provides a concrete pipe pile pouring mould.
In order to achieve the purpose, the invention adopts the following technical scheme: a concrete pipe pile pouring die comprises a cylindrical rotating block, a first annular stop block and a second annular stop block, wherein the inner wall of the cylindrical rotating block is rotatably connected with a rotating shaft, the upper end of the rotating shaft penetrates to the upper end of the cylindrical rotating block, the cylindrical rotating block is fixedly connected with the first annular stop block through a fixed block, the inner wall of the cylindrical rotating block penetrates through a sliding groove, the inner wall of the sliding groove is slidably connected with a connecting block, two ends of the connecting block are respectively fixed with the second annular stop block and the rotating shaft, the inner walls of the first annular stop block and the second annular stop block are respectively provided with a sealing groove, a sealing strip is fixed on the inner wall of each sealing groove, an arc-shaped cavity is formed inside the second annular stop block, the inner wall of the arc-shaped cavity is slidably connected with a sliding block, one end of the sliding block is connected with the inner wall of the arc-shaped cavity through a reset spring, and an arc-shaped limiting rod is fixed at the other end of the sliding block, the end wall of the first annular stop block is provided with an arc-shaped groove, the arc-shaped limiting rod corresponds to the arc-shaped groove, a stabilizing device is arranged inside the arc-shaped groove, and the first annular stop block and the second annular stop block are both provided with a plurality of limiting clamping devices.
In foretell concrete pipe pile pouring die, the end fixing of slider has the rope, the tip of rope runs through to the outside of second annular dog, the rope is located the outside one side of second annular dog and is fixed with the pull ring, seal groove on first annular dog and the second annular dog corresponds each other, the sealing strip adopts rubber materials to make.
In foretell concrete pipe pile filling die, stabilising arrangement is including seting up the rotation groove in arc gag lever post tip, the inner wall that rotates the groove is rotated through the torsional spring and is connected with the bull stick, the circumference lateral wall of bull stick is fixed with the rotor plate, the inner wall of arc wall is fixed with the pin, the upper end of arc gag lever post is run through and has been seted up the guide way, the guide way is the arcuation groove, the guide way corresponds with the pin.
In the above concrete pipe pile pouring mold, the inner wall of the arc-shaped groove is fixed with a permanent magnet, the side walls of the two ends of the rotating plate are both fixed with magnetic plates, the two magnetic plates have opposite magnetism, and the permanent magnet corresponds to the rotating plate.
In the above concrete pipe pile pouring mold, a plurality of pairing blocks are fixed at the upper ends of the first annular stop block and the second annular stop block, a plurality of pairing grooves are formed in the bottoms of the first annular stop block and the second annular stop block, and the pairing blocks are in one-to-one correspondence with the pairing grooves.
In foretell concrete pipe pile filling die, spacing chucking device is including seting up in the vertical chamber of pairing part inside, the inner wall sliding connection in vertical chamber has the clamp plate, the upper end of clamp plate is passed through coupling spring with the interior top in vertical chamber and is connected, a plurality of horizontal grooves have been seted up to the inner wall in vertical chamber, every the equal sliding connection in inside of horizontal groove has the stopper, every the lateral wall of stopper all rotates through the round pin axle and is connected with the connecting rod, and is a plurality of the upper end of connecting rod all rotates through the round pin axle with the bottom of clamp plate and is connected.
In foretell concrete pipe pile filling die, the storage tank has all been seted up to the circumference lateral wall of first annular dog and second annular dog, the interior bottom screw thread of storage tank rotates and is connected with the regulation pole, the bottom of adjusting the pole runs through to the inside of mating groove, the bottom of adjusting the pole is fixed with the polished rod.
In the concrete pipe pile pouring mold, a plurality of limiting grooves are formed in the inner wall of the pairing groove and correspond to the limiting blocks, the upper end of the vertical cavity is penetrated and provided with a through groove, the polished rod corresponds to the through groove, the bottom of the polished rod is abutted to the upper end of the pressing plate, and the inner wall of each storage groove is rotatably connected with a sealing baffle.
Compared with the prior art, the invention has the advantages that:
1. according to the invention, the movement of the sliding block can be realized by arranging the pull ring and the rope, so that the stable connection of the concrete pouring mould can be quickly realized by utilizing the arc-shaped limiting rod attached to the arc-shaped groove, the installation efficiency of the concrete pouring mould can be effectively increased, and the concrete pouring mould can be conveniently used;
2. in the invention, in the process that the arc-shaped limiting rod moves along the arc-shaped groove, the rotation of the rotating plate can be realized under the blocking action and the repulsion action of the permanent magnet of the stop lever, so that the opposite attraction of the permanent magnet and the magnetic plate can be realized, the stability of the arc-shaped limiting rod can be ensured, the stability of the installed pouring mold can be better, and the use effect of the pouring mold can be effectively enhanced;
3. according to the invention, the limiting clamping device is arranged, so that the matched installation of a plurality of pouring molds can be realized, the pouring of concrete pipe piles with different heights can be facilitated, the applicability of the pouring molds can be effectively increased, and the plurality of pouring molds which are small in size and can be spliced are arranged, so that the transportation of the pouring molds can be facilitated, the transportation cost can be reduced, and the use of concrete pouring can be facilitated;
4. according to the invention, the form removal work of the concrete pouring mould is simple and convenient, the concrete pouring mould can be completely detached without tools, the operation and the use of the concrete pouring mould are more convenient, and the use efficiency of the concrete pouring mould can be effectively increased.
Drawings
Fig. 1 is a schematic structural view of a concrete pipe pile pouring mold according to the present invention;
FIG. 2 is an enlarged view of portion A of FIG. 1;
fig. 3 is a front view of a concrete pipe pile pouring mold according to the present invention;
fig. 4 is a side sectional view of a concrete pipe pile pouring mold according to the present invention;
fig. 5 is a schematic structural view of a matching block part in the concrete pipe pile pouring mold according to the present invention;
fig. 6 is a partial structural schematic view of a concrete pipe pile pouring mold according to the present invention in a mated state.
In the figure: 1 column shape commentaries on classics piece, 2 first annular dog, 3 second annular dogs, 4 pivots, 5 fixed blocks, 6 sliding tray, 7 connecting blocks, 8 seal grooves, 9 sealing strips, 10 arc chamber, 11 sliders, 12 reset springs, 13 arc gag lever posts, 14 arc grooves, 15 ropes, 16 pull rings, 17 rotating grooves, 18 bull stick, 19 rotating plates, 20 magnetic plates, 21 pin, 22 guide way, 23 permanent magnet, 24 pairing block, 25 pairing groove, 26 vertical chamber, 27 clamp plate, 28 connecting spring, 29 horizontal slot, 30 stopper, 31 connecting rod, 32 through groove, 33 storage tank, 34 adjusting rod, 35 polished rod, 36 seal baffle, 37 spacing groove.
Detailed Description
The following examples are for illustrative purposes only and are not intended to limit the scope of the present invention.
Examples
Referring to fig. 1-6, a concrete pipe pile pouring mold comprises a cylindrical rotating block 1, a first annular stop block 2 and a second annular stop block 3, wherein the inner wall of the cylindrical rotating block 1 is rotatably connected with a rotating shaft 4, the upper end of the rotating shaft 4 penetrates to the upper end of the cylindrical rotating block 1, the cylindrical rotating block 1 is fixedly connected with the first annular stop block 2 through a fixed block 5, the inner wall of the cylindrical rotating block 1 is provided with a sliding groove 6 in a penetrating manner, the inner wall of the sliding groove 6 is slidably connected with a connecting block 7, two ends of the connecting block 7 are respectively fixed with the second annular stop block 3 and the rotating shaft 4, the inner walls of the first annular stop block 2 and the second annular stop block 3 are respectively provided with a sealing groove 8, the inner wall of each sealing groove 8 is fixed with a sealing strip 9, an arc-shaped cavity 10 is formed inside the second annular stop block 3, the inner wall of the arc-shaped cavity 10 is slidably connected with a slide block 11, one end of the slide block 11 is connected with the inner wall of the arc-shaped cavity 10 through a reset spring 12, the other end of slider 11 is fixed with arc gag lever post 13, and arc wall 14 has been seted up to the end wall of first annular dog 2, and arc gag lever post 13 corresponds with arc wall 14, and the inside of arc wall 14 is provided with stabilising arrangement, all is provided with a plurality of spacing chucking devices on first annular dog 2 and the second annular dog 3.
A rope 15 is fixed at the end of the sliding block 11, the end of the rope 15 penetrates to the outside of the second annular stop block 3, a pull ring 16 is fixed at one side of the rope 15, which is positioned at the outside of the second annular stop block 3, the sealing grooves 8 on the first annular stop block 2 and the second annular stop block 3 correspond to each other, and the sealing strip 9 is made of rubber materials; the stabilizing device comprises a rotating groove 17 formed in the end part of the arc-shaped limiting rod 13, the inner wall of the rotating groove 17 is rotatably connected with a rotating rod 18 through a torsion spring, a rotating plate 19 is fixed on the circumferential side wall of the rotating rod 18, a stop lever 21 is fixed on the inner wall of the arc-shaped groove 14, a guide groove 22 is formed in the upper end of the arc-shaped limiting rod 13 in a penetrating mode, the guide groove 22 is an arc-shaped groove, and the guide groove 22 corresponds to the stop lever 21; the inner wall of arc wall 14 is fixed with permanent magnet 23, and the both ends lateral wall of rotor plate 19 all is fixed with magnetic sheet 20, and two magnetic sheet 20 magnetism are opposite, and permanent magnet 23 corresponds with rotor plate 19, utilizes permanent magnet 23 and magnetic sheet 20's opposite poles to inhale the effect, can guarantee arc gag lever post 13's stability, can make to pour into mould installation back stability better, can effectively strengthen its result of use.
A plurality of matching blocks 24 are fixed at the upper ends of the first annular stop block 2 and the second annular stop block 3, a plurality of matching grooves 25 are formed at the bottoms of the first annular stop block 2 and the second annular stop block 3, and the matching blocks 24 correspond to the matching grooves 25 one by one; the limiting clamping device comprises a vertical cavity 26 arranged inside the pairing block 24, the inner wall of the vertical cavity 26 is connected with a pressing plate 27 in a sliding mode, the upper end of the pressing plate 27 is connected with the inner top of the vertical cavity 26 through a connecting spring 28, the inner wall of the vertical cavity 26 is provided with a plurality of horizontal grooves 29, the inside of each horizontal groove 29 is connected with a limiting block 30 in a sliding mode, the side wall of each limiting block 30 is rotatably connected with a connecting rod 31 through a pin shaft, and the upper ends of the connecting rods 31 are rotatably connected with the bottom of the pressing plate 27 through pin shafts; storage grooves 33 are formed in the circumferential side walls of the first annular stop block 2 and the second annular stop block 3, an adjusting rod 34 is connected to the inner bottom of each storage groove 33 in a threaded rotating mode, the bottom of each adjusting rod 34 penetrates into the corresponding groove 25, and a polished rod 35 is fixed to the bottom of each adjusting rod 34; pairing groove 25's inner wall and having seted up a plurality of spacing grooves 37, spacing groove 37 corresponds with stopper 30, vertical cavity 26's upper end is run through and has been seted up logical groove 32, polished rod 35 corresponds with logical groove 32, polished rod 35's bottom offsets with clamp plate 27's upper end, every storage tank 33's inner wall all rotates and is connected with seal baffle 36, through setting up limit chucking device, can realize the installation of superposing in proper order of a plurality of moulds, can conveniently pour the concrete pipe stake of co-altitude, can effectively increase the suitability of pouring the mould, and set up the less and pouring mould that splices of a plurality of volumes, can conveniently pour the transportation of mould, reducible cost of transportation, can make things convenient for the use that the concrete was poured.
In the invention, in the process of pouring the concrete pipe pile, the pull ring 16 needs to be pulled firstly, so that the rope 15 drives the slide block 11 to move towards the inner wall of the arc-shaped cavity 10, and simultaneously, the return spring 12 is extruded, so that the return spring 12 is in a compressed state, when the arc-shaped limiting rod 13 completely enters the second annular stop block 3, the rotating shaft 4 is rotated, so that the rotating shaft 4 drives the connecting block 7 and the second annular stop block 3 to rotate, so that the first annular stop 2 and the second annular stop 3 are tightly attached, and at the moment, the pull ring 16 is released, the slide block 11 returns to the original position under the action of the return spring 12 in a compressed state, therefore, the arc-shaped limiting rod 13 can enter the arc-shaped groove 14, the stable connection of the concrete pouring mould can be quickly realized by utilizing the arc-shaped limiting rod 13 attached to the arc-shaped groove 14, the installation efficiency of the concrete pouring mould can be effectively increased, and the concrete pouring mould can be conveniently used;
in the process that the arc-shaped limiting rod 13 moves along the inner part of the arc-shaped groove 14, when the rotating plate 19 abuts against the stop lever 21, the magnetic plate 20 with the same magnetism as the permanent magnet 23 is close to the permanent magnet 23 at the moment, under the combined action of blocking of the stop lever 21, pushing of the reset spring 12 and repulsion of the same magnetism, the rotation of the rotating rod 18 and the rotating plate 19 can be realized, meanwhile, the torsion of the torsion spring can be realized, so that the permanent magnet 23 is close to the magnetic plate 20 with the opposite magnetism, the stability of the arc-shaped limiting rod 13 can be ensured by utilizing the opposite attraction effect of the permanent magnet 23 and the magnetic plate 20, the stability of the injection mold after being installed can be better, and the use effect of the injection mold can be effectively enhanced;
then, a plurality of injection molds are sequentially stacked by aligning the mating blocks 24 and the mating grooves 25, then the sealing flapper 36 is opened, by rotating the adjusting lever 34, so that the polish rod 35 is moved downward, in the process that the polish rod 35 moves downwards, the pressing plate 27 is pushed to move, and the limiting block 30 can move under the action of the connecting rod 31 which can rotate at both ends, so that the limiting block 30 enters the limiting groove 37, meanwhile, the connecting spring 28 is elongated, so that the connecting spring 28 is in a stretching state, stable connection of a plurality of pouring molds can be realized by utilizing the matching of the limiting block 30 and the limiting groove 37, concrete pipe piles with different heights can be conveniently poured, the applicability of the pouring molds can be effectively increased, the plurality of spliced pouring molds with small volume are arranged, so that the pouring molds can be conveniently transported, the transportation cost can be reduced, and the use of concrete pouring can be facilitated;
the sealing strips 9 made of rubber materials are arranged at the contact parts of the first annular stop block 2 and the second annular stop block 3, so that the sealing property of the connection part of the pouring mould can be improved, the sealing pouring of the mould can be ensured, and the concrete pouring effect of the tubular pile can be better;
after the tubular pile is poured and solidified, the adjusting rod 34 and the polished rod 35 can move upwards by rotating the adjusting rod 34 in the opposite direction, so that the polished rod 35 and the pressing plate 27 can be separated, the pressing plate 27 is driven to return to the original position under the action of the connecting spring 28 in a stretching state, the limiting blocks 30 and the limiting grooves 37 can be separated under the action of the connecting rods 31 which can rotate at the two ends, the connection of a plurality of pouring molds can be quickly released, and the use of the concrete pouring molds can be facilitated;
then the concrete pouring mould is lifted in sequence, so that the pairing groove 25 is separated from the pairing block 24, at the moment, the pull ring 16 is pulled, so that the pull ring 16 drives the rope 15 and the sliding block 11 to move, the arc limiting rod 13 can be driven to slide outwards along the inside of the arc groove 14, the distance is gradually increased in the sliding process of the arc limiting rod 13, the magnetic force corresponding to each other is gradually reduced, the rotation of the rotating plate 19 can be realized under the blocking effect of the stop lever 21 and the combined action of the torsion spring, so that the magnetic plate 20 with the magnetism opposite to that of the permanent magnet 23 is close to the direction of the permanent magnet 23, the permanent magnet 23 and the magnetic plate 20 are mutually repelled, the taking-out work of the arc limiting rod 13 can be more convenient, and after the arc limiting rod 13 is completely separated from the arc groove 14, the rotating shaft 4 is rotated, so that the rotating shaft 4 drives the connecting block 7 and the second annular stop block 3 to rotate, thereby can realize the separation of first annular dog 2 and second annular dog 3, can realize fast that the mould removal work to the concrete pouring mould need not with the help of the instrument, it is more convenient to operate, can make the concrete pouring mould availability factor higher.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents, improvements and the like that fall within the spirit and principle of the present invention are intended to be included therein.

Claims (8)

1. The concrete pipe pile pouring mold comprises a cylindrical rotating block (1), a first annular stop block (2) and a second annular stop block (3), and is characterized in that a rotating shaft (4) is connected to the inner wall of the cylindrical rotating block (1) in a rotating mode, the upper end of the rotating shaft (4) penetrates through the upper end of the cylindrical rotating block (1), the cylindrical rotating block (1) is fixedly connected with the first annular stop block (2) through a fixing block (5), a sliding groove (6) is formed in the inner wall of the cylindrical rotating block (1) in a penetrating mode, a connecting block (7) is connected to the inner wall of the sliding groove (6) in a sliding mode, two ends of the connecting block (7) are fixed with the second annular stop block (3) and the rotating shaft (4) respectively, sealing grooves (8) are formed in the inner walls of the first annular stop block (2) and the second annular stop block (3), and sealing strips (9) are fixed to the inner walls of each sealing groove (8), arc chamber (10) have been seted up to the inside of second annular dog (3), the inner wall sliding connection in arc chamber (10) has slider (11), the one end of slider (11) passes through reset spring (12) with the inner wall in arc chamber (10) and is connected, the other end of slider (11) is fixed with arc gag lever post (13), arc wall (14) have been seted up to the end wall of first annular dog (2), arc gag lever post (13) correspond with arc wall (14), the inside of arc wall (14) is provided with stabilising arrangement, all be provided with a plurality of spacing chucking devices on first annular dog (2) and second annular dog (3).
2. The concrete pipe pile pouring mold according to claim 1, wherein a rope (15) is fixed to an end of the sliding block (11), the end of the rope (15) penetrates to the outside of the second annular stopper (3), a pull ring (16) is fixed to one side of the rope (15) located outside the second annular stopper (3), the sealing grooves (8) on the first annular stopper (2) and the second annular stopper (3) correspond to each other, and the sealing strip (9) is made of a rubber material.
3. The concrete pipe pile pouring mold according to claim 1, wherein the stabilizing device comprises a rotating groove (17) formed in the end portion of the arc-shaped limiting rod (13), the inner wall of the rotating groove (17) is rotatably connected with a rotating rod (18) through a torsion spring, a rotating plate (19) is fixed on the circumferential side wall of the rotating rod (18), a stop lever (21) is fixed on the inner wall of the arc-shaped groove (14), a guide groove (22) is formed in the upper end of the arc-shaped limiting rod (13) in a penetrating mode, the guide groove (22) is an arc-shaped groove, and the guide groove (22) corresponds to the stop lever (21).
4. A concrete pipe pile pouring mould according to claim 3, wherein a permanent magnet (23) is fixed on the inner wall of the arc-shaped groove (14), magnetic plates (20) are fixed on the side walls of both ends of the rotating plate (19), the two magnetic plates (20) have opposite magnetism, and the permanent magnet (23) corresponds to the rotating plate (19).
5. The concrete pipe pile pouring mold according to claim 1, wherein a plurality of matching blocks (24) are fixed at the upper ends of the first annular stop block (2) and the second annular stop block (3), a plurality of matching grooves (25) are formed at the bottoms of the first annular stop block (2) and the second annular stop block (3), and the matching blocks (24) correspond to the matching grooves (25) in a one-to-one manner.
6. The concrete pipe pile pouring mold according to claim 5, wherein the limiting clamping device comprises a vertical cavity (26) arranged inside the pairing block (24), a pressing plate (27) is connected to the inner wall of the vertical cavity (26) in a sliding mode, the upper end of the pressing plate (27) is connected with the inner top of the vertical cavity (26) through a connecting spring (28), a plurality of horizontal grooves (29) are formed in the inner wall of the vertical cavity (26), limiting blocks (30) are connected to the inside of each horizontal groove (29) in a sliding mode, a connecting rod (31) is connected to the side wall of each limiting block (30) in a rotating mode through a pin shaft, and the upper ends of the connecting rods (31) are connected with the bottom of the pressing plate (27) in a rotating mode through pin shafts.
7. The concrete pipe pile pouring mold according to claim 6, wherein the circumferential side walls of the first annular stopper (2) and the second annular stopper (3) are both provided with a storage groove (33), the inner bottom of the storage groove (33) is in threaded rotation connection with an adjusting rod (34), the bottom of the adjusting rod (34) penetrates through the inside of the mating groove (25), and a polished rod (35) is fixed at the bottom of the adjusting rod (34).
8. The concrete pipe pile pouring mold according to claim 7, wherein a plurality of limiting grooves (37) are formed in the inner wall of the matching groove (25), the limiting grooves (37) correspond to the limiting blocks (30), a through groove (32) is formed in the upper end of the vertical cavity (26) in a penetrating manner, the polish rod (35) corresponds to the through groove (32), the bottom of the polish rod (35) abuts against the upper end of the pressing plate (27), and a sealing baffle plate (36) is rotatably connected to the inner wall of each storage groove (33).
CN202111439506.9A 2021-11-30 2021-11-30 Concrete pipe pile pouring die Active CN114290513B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111439506.9A CN114290513B (en) 2021-11-30 2021-11-30 Concrete pipe pile pouring die

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111439506.9A CN114290513B (en) 2021-11-30 2021-11-30 Concrete pipe pile pouring die

Publications (2)

Publication Number Publication Date
CN114290513A true CN114290513A (en) 2022-04-08
CN114290513B CN114290513B (en) 2024-02-02

Family

ID=80965059

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111439506.9A Active CN114290513B (en) 2021-11-30 2021-11-30 Concrete pipe pile pouring die

Country Status (1)

Country Link
CN (1) CN114290513B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005003552A1 (en) * 2005-01-26 2006-08-03 Man B & W Diesel A/S Crosshead engine e.g. two-stroke large diesel engine has central sleeve, whose outer diameter is larger compared to outer diameter of input pipe, which corresponds to diameter of through-bore
CN207901400U (en) * 2018-02-06 2018-09-25 湖南小枰建材有限责任公司 Portable concrete drain tile mold processed
CN208099900U (en) * 2018-02-07 2018-11-16 新昌县七星街道炜德机械厂 A kind of convenient and fast machine tool chief axis of installation and removal
CN208309255U (en) * 2018-05-02 2019-01-01 天津市远洋纺织品有限公司 A kind of piece of carpet cuts device
CN209823349U (en) * 2019-05-23 2019-12-20 深圳市精艺安达五金制品有限公司 Rotary snap ring
CN110833562A (en) * 2019-12-21 2020-02-25 安徽省小山卫生材料有限公司 Preparation method of chitosan povidone iodine composite disinfectant
CN211420618U (en) * 2019-12-31 2020-09-04 江苏美森洗涤设备有限公司 Novel cloth ironing machine
CN112440375A (en) * 2020-11-23 2021-03-05 何文恺 Concrete pipe pile pouring die with barb structure on inner wall
CN213320836U (en) * 2020-09-03 2021-06-01 张国会 Concrete pipe pile filling device
CN214712732U (en) * 2021-01-11 2021-11-16 西昌市人民医院 Device for taking out foreign matters in stomach for digestive system department

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102005003552A1 (en) * 2005-01-26 2006-08-03 Man B & W Diesel A/S Crosshead engine e.g. two-stroke large diesel engine has central sleeve, whose outer diameter is larger compared to outer diameter of input pipe, which corresponds to diameter of through-bore
CN207901400U (en) * 2018-02-06 2018-09-25 湖南小枰建材有限责任公司 Portable concrete drain tile mold processed
CN208099900U (en) * 2018-02-07 2018-11-16 新昌县七星街道炜德机械厂 A kind of convenient and fast machine tool chief axis of installation and removal
CN208309255U (en) * 2018-05-02 2019-01-01 天津市远洋纺织品有限公司 A kind of piece of carpet cuts device
CN209823349U (en) * 2019-05-23 2019-12-20 深圳市精艺安达五金制品有限公司 Rotary snap ring
CN110833562A (en) * 2019-12-21 2020-02-25 安徽省小山卫生材料有限公司 Preparation method of chitosan povidone iodine composite disinfectant
CN211420618U (en) * 2019-12-31 2020-09-04 江苏美森洗涤设备有限公司 Novel cloth ironing machine
CN213320836U (en) * 2020-09-03 2021-06-01 张国会 Concrete pipe pile filling device
CN112440375A (en) * 2020-11-23 2021-03-05 何文恺 Concrete pipe pile pouring die with barb structure on inner wall
CN214712732U (en) * 2021-01-11 2021-11-16 西昌市人民医院 Device for taking out foreign matters in stomach for digestive system department

Also Published As

Publication number Publication date
CN114290513B (en) 2024-02-02

Similar Documents

Publication Publication Date Title
CN106493919B (en) A kind of injection mold concentric contraction Two Steps Core Pulling stripper apparatus
CN110672421B (en) Rock tension-compression shear seepage coupling rheological experiment device
CN114290513A (en) Concrete pipe pile filling mould
US9157208B2 (en) Adjustable raked pile driver using the push pull method
CN104708773B (en) Flared pipe fitting core-pulling mechanism for injection mold
CN112554010A (en) Positioning plate connecting device for road laying
CN110629791B (en) Built-in lateral telescopic supporting box type external mold
CN208607062U (en) Portable laboratory fast demolding device
CN117071779A (en) Assembled wall system and construction method thereof
CN216594430U (en) Automatic marshall test piece hits real appearance
CN114487365B (en) Concrete slump measuring device
CN207128211U (en) Lock core injection mold
CN212314404U (en) Ribbon fixing device is used in commodity circulation packing
CN209858301U (en) Cylindrical ground sample making devices
CN210940255U (en) Five-way pipe injection mold
CN112518977A (en) Centrifugal forming equipment for preparing prestressed high-strength concrete pipe pile
CN205326118U (en) Plastic mold magnetism metal insert 's automatic filling device
CN114986690B (en) Preparation process of reinforced concrete telegraph pole
CN214377277U (en) Lean player sand table with practical training function
CN207028092U (en) A kind of side core-drawing mechanism for injection mold
CN216447669U (en) Auxiliary assembly is used in butt joint of PVC drain pipe
CN210262723U (en) Positioner is used in road bridge construction
CN213681733U (en) Combined bridge formwork
CN112323787B (en) Cement stirring pile with built-in sand core
CN220550555U (en) A sleeve pipe extraction device for lid digs reverse construction method construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant