- CN114182965A CN114182965A CN202111579803.3A CN202111579803A CN114182965A CN 114182965 A CN114182965 A CN 114182965A CN 202111579803 A CN202111579803 A CN 202111579803A CN 114182965 A CN114182965 A CN 114182965A
- Authority
- CN
- China
- Prior art keywords
- sliding support
- sliding
- support
- sliding body
- deviation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Abstract
本发明公开了一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法,采用滑移支座进行预偏安装,所述滑移支座包括相互滑动连接的下部滑移体和上部滑移体。本发明规避了现有滑移支座安装方法的不足之处,摩擦阻力小,拥有较好的自复位能力,可有效减小滑移支座安装时对下部结构柱产生的水平推力,安全性能高。
Description
技术领域
本发明涉及建筑钢结构施工领域,更具体涉及一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法。
背景技术
随着建筑结构的高速发展,越来越多的大跨拱形钢结构屋盖被应用;对于拱形屋盖受荷过程中产生的水平推力,常在拱脚位置设置滑移支座进行释放,以结构自身受荷来平衡水平推力,用以减小其对下部结构的影响。
在滑移支座安装时,支座受结构卸载影响将发生较大的水平位移,偏离安装位置,导致下部结构柱偏心受力。为解决该问题,常采用下述方法进行支座的安装:先临时固定滑移支座的上下支座体,避免运输及施工过程中滑动破坏,然后将支座整体预偏安装至柱顶,并将支座与上部屋盖结构按设计要求连接固定,在支座底板和柱顶间涂抹黄油或做其他滑移面,通过支座与柱顶之间的滑移,实现支座在结构卸载过程中的水平推力作用下复位。采用黄油做摩擦面时,由于黄油的润滑性有限,在较大竖向压力荷载作用下,下支座板底板和柱顶间摩擦力仍较大,屋盖卸载后,常出现支座无法复位到设计位置,以及较大的水平摩擦力会对下部结构柱产生较大的水平推力,产生与设计状态的不符合带来的安全问题;当在支座与柱顶之间设置其他摩擦面时,会带来施工工序繁琐以及施工成本的增加。
发明内容
针对现有技术的不足,本发明提供了一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法,利用支座内部摩擦面滑移,摩擦系数小,摩擦阻力小;操作简便,施工过程安全可控;支座安装精度高,同时经济性好。
为实现上述目的,本发明提供了如下技术方案:一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法,采用滑移支座进行预偏安装,所述滑移支座包括相互滑动连接的下部滑移体和上部滑移体,具体实施主要包括如下步骤,
(1)根据计算分析得到得到屋盖预变形方案及支座需预偏尺寸L;
(2)根据预偏尺寸L,在深化加工阶段调整支座附近1~3个节间的杆件长度,以适应滑移支座预偏安装;
(3)滑移支座加工阶段,根据预偏尺寸L将滑移支座上部滑移体与下部滑移体进行预偏处理,同时采用指针进行标记,然后采用限位工装将滑移支座上部滑移体和下部滑移体进行限位固定;
(4)滑移支座现场安装时,将滑移支座按设计要求进行安装,即滑移支座下部滑移体中心与柱中心对齐;然后按要求将滑移支座与下部结构柱焊接固定,最后按常规方式进行屋盖结构施工安装,以及与滑移支座的连接固定;
(5)大跨钢屋盖安装完毕后,整体卸载前,拆除滑移支座上部滑移体、下部滑移体之间的限位工装;
(6)屋盖卸载时,结构在重力荷载作用下将在滑移支座处产生水平变形,滑移支座上部滑移体将沿着预偏反方向移动并接近中心位置,以此实现滑移支座的自复位;
(7)测量上部滑移体居中情况,如未居中,及时进行调整。
综上所述,本发明规避了现有滑移支座安装方法的不足之处,摩擦阻力小,拥有较好的自复位能力,安全性能高,具有如下有益效果:
(1)可实施性强;
(2)滑移支座安装精度高;
(3)可有效减小滑移支座安装时对下部结构柱产生的水平推力,安全性好;
(4)无新增措施量,整体经济性高。
附图说明
图1为本发明所述滑移支座预偏位置剖视图;
图2为本发明所述滑移支座预偏位置侧视图;
图3为本发明所述滑移支座预偏位置俯视图;
图4为本发明所述滑移支座自复位至设计位置剖视图;
图5为本发明所述滑移支座自复位至设计位置侧视图;
图6为本发明所述滑移支座自复位至设计位置俯视图。
具体实施方式
参照图1至图6对本发明一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法的具体实施方式做进一步的说明。
一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法,采用滑移支座进行预偏安装,所述滑移支座包括相互滑动连接的下部滑移体和上部滑移体,具体实施主要包括如下步骤:
(1)滑移支座加工前,首先按照1.0倍自重荷载作用,计算分析得到屋盖预变形方案及支座需预偏尺寸L;
(2)根据预偏尺寸L,在深化加工阶段调整支座附近1~3个节间内杆件4长度,以适应滑移支座预偏安装;
(3)滑移支座加工阶段,在下部滑移体2外表面贴上刻度表6,刻度表6中心与下部滑移体2中心对齐,在上部滑移体3外表面同侧中心处贴上标定指针5,然后将滑移支座上部滑移体3与下部滑移体2进行组装,至标定指针5所示读数与预偏尺寸L相同的位置后,在滑移支座平行滑移方向两侧外表面安装限位工装7,以此实现支座的临时固定;
(4)滑移支座现场安装时,将滑移支座按设计要求进行安装,即滑移支座下部滑移体2中心与结构柱1中心对齐,然后按要求将下部滑移体2与结构柱1焊接固定,之后按常规方式进行屋盖结构施工安装,最后将上部滑移体3与杆件4焊接固定;
(5)大跨钢屋盖安装完毕后,整体卸载前,拆除滑移支座限位工装7;
(6)屋盖卸载时,结构在重力荷载作用下将在滑移支座处产生水平变形,滑移支座上部滑移体3将沿着预偏反方向移动并接近中心位置,以此实现滑移支座的自复位;
(7)测量上部滑移体3居中情况,如未居中,及时进行调整。
本发明实施方式规避了现有滑移支座安装方法的不足之处,摩擦阻力小,拥有较好的自复位能力,安全性能高。
以上所述仅是本发明的优选实施方式,本发明的保护范围并不仅局限于上述实施例,凡属于本发明思路下的技术方案均属于本发明的保护范围。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理前提下的若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。
Claims (1)
1.一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法,其特征在于:采用滑移支座进行预偏安装,所述滑移支座包括相互滑动连接的下部滑移体和上部滑移体,具体实施主要包括如下步骤,
(1)根据计算分析得到得到屋盖预变形方案及支座需预偏尺寸L;
(2)根据预偏尺寸L,在深化加工阶段调整支座附近1~3个节间的杆件长度,以适应滑移支座预偏安装;
(3)滑移支座加工阶段,根据预偏尺寸L将滑移支座上部滑移体与下部滑移体进行预偏处理,同时采用指针进行标记,然后采用限位工装将滑移支座上部滑移体和下部滑移体进行限位固定;
(4)滑移支座现场安装时,将滑移支座按设计要求进行安装,即滑移支座下部滑移体中心与柱中心对齐;然后按要求将滑移支座与下部结构柱焊接固定,最后按常规方式进行屋盖结构施工安装,以及与滑移支座的连接固定;
(5)大跨钢屋盖安装完毕后,整体卸载前,拆除滑移支座上部滑移体、下部滑移体之间的限位工装;
(6)屋盖卸载时,结构在重力荷载作用下将在滑移支座处产生水平变形,滑移支座上部滑移体将沿着预偏反方向移动并接近中心位置,以此实现滑移支座的自复位;
(7)测量上部滑移体居中情况,如未居中,及时进行调整。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111579803.3A CN114182965A (zh) | 2021-12-22 | 2021-12-22 | 一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111579803.3A CN114182965A (zh) | 2021-12-22 | 2021-12-22 | 一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114182965A true CN114182965A (zh) | 2022-03-15 |
Family
ID=80544752
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111579803.3A Pending CN114182965A (zh) | 2021-12-22 | 2021-12-22 | 一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114182965A (zh) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101029520A (zh) * | 2007-04-04 | 2007-09-05 | 中国京冶工程技术有限公司 | 钢桁架拱支座无推力整体滑移施工方法 |
CN105804412A (zh) * | 2016-03-14 | 2016-07-27 | 中冶天工集团有限公司 | 一种用于快速纠正滑移施工侧向超限位移的方法 |
CN206784602U (zh) * | 2017-03-30 | 2017-12-22 | 同济大学 | 一种自复位滑移隔震支座 |
CN207244440U (zh) * | 2017-09-28 | 2018-04-17 | 陕西中咨土木工程技术研究院有限公司 | 一种具有自适应调整初始变形功能的叠层橡胶支座组件 |
JP6457141B1 (ja) * | 2018-08-28 | 2019-01-23 | 新日鉄住金エンジニアリング株式会社 | 施工時の滑り免震支承構造、及び免震建物の施工方法 |
CN111663660A (zh) * | 2020-05-20 | 2020-09-15 | 北京市建筑设计研究院有限公司 | 一种滑移支座 |
-
2021
- 2021-12-22 CN CN202111579803.3A patent/CN114182965A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101029520A (zh) * | 2007-04-04 | 2007-09-05 | 中国京冶工程技术有限公司 | 钢桁架拱支座无推力整体滑移施工方法 |
CN105804412A (zh) * | 2016-03-14 | 2016-07-27 | 中冶天工集团有限公司 | 一种用于快速纠正滑移施工侧向超限位移的方法 |
CN206784602U (zh) * | 2017-03-30 | 2017-12-22 | 同济大学 | 一种自复位滑移隔震支座 |
CN207244440U (zh) * | 2017-09-28 | 2018-04-17 | 陕西中咨土木工程技术研究院有限公司 | 一种具有自适应调整初始变形功能的叠层橡胶支座组件 |
JP6457141B1 (ja) * | 2018-08-28 | 2019-01-23 | 新日鉄住金エンジニアリング株式会社 | 施工時の滑り免震支承構造、及び免震建物の施工方法 |
CN111663660A (zh) * | 2020-05-20 | 2020-09-15 | 北京市建筑设计研究院有限公司 | 一种滑移支座 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109190309B (zh) | 老化钢筋混凝土梁桥抗剪承载力评价方法 | |
Loh et al. | The effects of partial shear connection in the hogging moment regions of composite beams: Part I—Experimental study | |
EP2288753B1 (en) | Bearings acting as energy dissipating devices | |
US5811686A (en) | Test fixture for determination of energy absorbing capabilities of composite materials | |
CN108204918A (zh) | 一种复合材料动态剪切试验方法 | |
CN114182965A (zh) | 一种大跨钢屋盖滑移支座预偏安装和卸载自复位施工方法 | |
CN111737807A (zh) | 一种考虑混凝土脱空的角钢连接件承载力的确定方法 | |
Ingkiriwang et al. | Numerical investigation of the design of single‐span steel portal frames using the effective length and direct analysis methods | |
Aggarwal et al. | Moment-rotation characteristics of bolted beam-column connections | |
CN108581319A (zh) | 一种铁轨用h型钢门焊工艺的支撑架 | |
Pham et al. | Experimental investigation of the member buckling of cold-rolled aluminium alloy 5052 Channel columns | |
CN210720117U (zh) | 一种自平衡式钢筋与混凝土粘结滑移测试装置 | |
Lv et al. | A stress distribution of thin rectangular steel wall under a uniform compression | |
CN210375929U (zh) | 一种混凝土徐变多功能试验测试系统 | |
CN201096513Y (zh) | 传感器的销式限位保护机构 | |
CN111535492A (zh) | 一种大吨位钢梁拉索压块夹持式组合节点及其方法 | |
EP1275943A2 (en) | Device for weighing a load | |
CN214884967U (zh) | 一种装配式建筑混凝土预制楼梯安装施工装置 | |
Wang et al. | 08.19: Tests on concrete‐filled double skin tubular beams with circular stainless steel outer tubes | |
CN114134798B (zh) | 高架桥自复位、抗倾覆、高效减震系统及其施工方法 | |
CN116481936B (zh) | 基于恒定法向中心约束的低摩阻剪切试验装置及试验方法 | |
CN109781502A (zh) | 一种踏板垫耐磨工装 | |
KR200464779Y1 (ko) | 보 형태의 굽힘 시험편의 4점 굽힘 시험용 지그 | |
KR101291009B1 (ko) | 가새 실험용 지그기구 | |
Al-Chaar et al. | Seismic behavior of a multistory and multibay frame-infill system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |