CN114168245A - Construction project supervision management method and system - Google Patents

Construction project supervision management method and system Download PDF

Info

Publication number
CN114168245A
CN114168245A CN202111408796.0A CN202111408796A CN114168245A CN 114168245 A CN114168245 A CN 114168245A CN 202111408796 A CN202111408796 A CN 202111408796A CN 114168245 A CN114168245 A CN 114168245A
Authority
CN
China
Prior art keywords
supervision
project
planning template
management method
planning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202111408796.0A
Other languages
Chinese (zh)
Inventor
自朝阳
张家荣
谢干
魏海怡
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Shenfeng Engineering Construction Supervision Co ltd
Original Assignee
Shanghai Shenfeng Engineering Construction Supervision Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Shenfeng Engineering Construction Supervision Co ltd filed Critical Shanghai Shenfeng Engineering Construction Supervision Co ltd
Priority to CN202111408796.0A priority Critical patent/CN114168245A/en
Publication of CN114168245A publication Critical patent/CN114168245A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F9/00Arrangements for program control, e.g. control units
    • G06F9/06Arrangements for program control, e.g. control units using stored programs, i.e. using an internal store of processing equipment to receive or retain programs
    • G06F9/44Arrangements for executing specific programs
    • G06F9/451Execution arrangements for user interfaces
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/95Retrieval from the web
    • G06F16/953Querying, e.g. by the use of web search engines
    • G06F16/9535Search customisation based on user profiles and personalisation
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/90Details of database functions independent of the retrieved data types
    • G06F16/95Retrieval from the web
    • G06F16/953Querying, e.g. by the use of web search engines
    • G06F16/9538Presentation of query results
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F40/00Handling natural language data
    • G06F40/10Text processing
    • G06F40/166Editing, e.g. inserting or deleting
    • G06F40/186Templates

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • Databases & Information Systems (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Software Systems (AREA)
  • Data Mining & Analysis (AREA)
  • Human Computer Interaction (AREA)
  • Health & Medical Sciences (AREA)
  • Artificial Intelligence (AREA)
  • Audiology, Speech & Language Pathology (AREA)
  • Computational Linguistics (AREA)
  • General Health & Medical Sciences (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The application relates to a construction project supervision management method and a system, which comprises a response starting instruction and an output inquiry instruction; responding to the query instruction, querying the type and the corresponding times of the used supervision planning template of the user, and outputting the times of the used supervision planning template; calling the used supervision planning template and sequencing at least according to the number of use times; inducing similar parts in the used supervision planning template with more times; screening similar words in the used supervision planning template in the existing supervision planning template, and calling out the supervision planning template with the similar words; the result of screening is from top to bottom shown according to the similarity, and the output shows the result, and this application has the user of being convenient for can convenient and fast find corresponding supervision planning template, saves the effect of looking up the time.

Description

Construction project supervision management method and system
Technical Field
The application relates to the field of construction project supervision, in particular to a construction project supervision management method and system.
Background
Project supervision refers to the entrust of a supervision unit with related qualification by a party A, and represents a specialized service activity for monitoring the project construction of a party B by the party A according to project construction documents approved by the country, laws and regulations related to the project construction, project construction supervision contracts and other project construction contracts. The construction supervision and control system is a legal basic system in the field of engineering construction in China, and the supervision position in the engineering construction is important.
At present, supervision units develop construction project supervision management system software, and provide a powerful, flexible, stable and safe full-professional engineering construction support platform for users. The system completely follows various international open technical standards and related standards and specifications established by the national and telecommunication industries, and can provide a plurality of complete sets of supervision planning templates for users to refer to.
For the related technologies, the inventor thinks that when a user searches for the existing supervision planning template, the supervision planning template appears randomly, and when the user selects the supervision planning template which needs to be used, a large amount of time is consumed for looking up, so that the labor is consumed, and the working efficiency is reduced.
Disclosure of Invention
In order to facilitate a user to conveniently and quickly find a corresponding supervision planning template and save the reference time, the construction project supervision management method and system are provided.
The construction project supervision management method provided by the application adopts the following technical scheme:
a supervision and management method for construction projects comprises responding to a starting instruction and outputting a query instruction; responding to the query instruction, querying the type and the corresponding times of the used supervision planning template of the user, and outputting the times of the used supervision planning template; calling the used supervision planning template and sequencing at least according to the number of use times; inducing similar parts in the used supervision planning template with more times; screening similar words in the used supervision planning template in the existing supervision planning template, and calling out the supervision planning template with the similar words; and displaying the screening result from top to bottom according to the similarity, and outputting the display result.
By adopting the technical scheme, when the user uses the system, the query instruction queries the type and the corresponding times of the used supervision planning template of the user, the queried results are sequenced from at least one time in sequence, after the used supervision planning template is sequenced, similar words in the used supervision planning template with multiple times are summarized, then the related supervision planning template is called out according to the similar words, the client can clearly check the used template before the client, and the similar supervision planning template is recommended for the client according to the use habit of the user, so that the time for the user to look up and search is saved.
Optionally, after the screening result is displayed from top to bottom according to the similarity, responding to the monitoring instruction and outputting a reminding instruction; responding to a reminding instruction, searching an area with a problem of word eye breaking in the supervision process, and searching the layering condition of word eyes distributed in groups; analyzing the problems, analyzing the distribution condition of the word eye breaking separation layers and generating a solving report; resolving reports are disassembled step by step according to the resolving sequence; displaying the solving steps in sequence; recording and storing the solved problems; the unresolved issues are recorded and sent to the software provider.
By adopting the technical scheme, when the user uses the monitoring planning template, the user searches for the place where the word eyes are separated or should be grouped word eyes are layered, a solving report for solving the problem is generated according to the distribution condition of the word eye problem, and the user operates according to the solving steps in the report, so that the word eye problem can be solved; if the problem is not solved effectively, the software supplier can receive feedback records of relevant problems and solve the problems.
Optionally, after the types and the corresponding times of the proctoring plan templates used by the user are inquired, when a plurality of proctoring plan templates occur the same times, the proctoring contents in the plurality of proctoring plan templates with the same times are summarized, and the proctoring contents are arranged in front of the proctoring plan templates with high matching degree with the input word eyes and the number of times of occurrence of the word eyes.
By adopting the technical scheme, when the user uses the supervision planning template, the matching degree is determined according to the comparison between the supervision content and the word eyes when the use times of the supervision planning template are the same, and the supervision planning template with high matching degree and multiple occurrence of the word eyes is arranged in front. The rationality of the sorting is guaranteed.
Optionally, the resolution steps are displayed in different colors.
By adopting the technical scheme, when the user uses the method, the solution steps are displayed by different colors, so that the user can distinguish the intervals among different steps, and the user is prevented from operating too many steps at one time.
Alternatively, the colors are set to red, blue and yellow, respectively, with the solution step indicated by red being most important, followed by blue and yellow.
By adopting the technical scheme, when the user uses the system, the user can clearly understand different importance of different steps by setting the three colors of red, blue and yellow.
Optionally, a pre-stored instruction is started, the used supervision planning template and related real-time project information data are stored, the adaptive project data range information is called according to the classification of different projects, the real-time project information data and the project data range information are compared, and an information report is generated according to the compared result.
By adopting the technical scheme, when the user uses the system, the corresponding project data range information is called according to the current real-time project information data, the project data range information and the project data range information are compared, and then a report is generated according to the comparison result of the project data range information and the project data range information, so that the user can conveniently know the current real-time project information data.
Optionally, when the real-time project information data and the project data range information are compared, the range value of the real-time project information data is compared with the project data range information, unqualified real-time project information data is screened out, and then a difference report between the unqualified real-time project information data and the project data range information is derived.
Through adopting above-mentioned technical scheme, when the user used, unqualified real-time project information data directly appeared on the difference report, guaranteed that the user can convenient and fast's understanding this problem that appears in the work progress, and the user of being convenient for carries out key check and justment to relevant problem.
Optionally, the real-time item information data which just reach the standard is early-warned, and a critical value report is derived, wherein the critical value report and the difference value report are both information reports.
Through adopting above-mentioned technical scheme, when the user used, the real-time project information data that just reach standard directly reflects on the critical value report, guarantees that the user can convenient and fast know which processes operation is careful not enough in this work progress, guarantees that the user can pay attention to these processes constantly, prevents the emergence of next mistake.
The application provides a construction project supervision and management system, adopts following technical scheme: comprising a memory and a processor, said memory having stored thereon a computer program which can be loaded by the processor and which performs the method of any of claims 1 to 8.
By adopting the technical scheme, when the user uses the intelligent supervision system, the memory stores the existing supervision planning template and the used supervision planning template, the supervision planning template is convenient to call at any time, and the processor processes and controls various instructions to ensure the normal operation of the system.
The application provides a computer-readable storage medium, which adopts the following technical scheme: a computer program which can be loaded by a processor and which performs the method according to any one of claims 1 to 8.
By adopting the above technical solutions, when the user uses the method, it should be understood that the content described in the summary of the invention section is not intended to limit the key or important features of the embodiments of the present application, nor is it intended to limit the scope of the present application. Other features of the present application will become apparent from the following description.
In summary, the present application includes at least one of the following beneficial technical effects:
the inquiry command inquires the types and the corresponding times of the used supervision planning templates of the user, the inquired results are sequenced from at least one time in sequence, the used supervision planning templates are sequenced, similar words in the used supervision planning templates with multiple times are summarized, then the related supervision planning templates are called out according to the similar words, the client can clearly check the used templates before the client, the similar supervision planning templates are recommended to the client according to the use habits of the user, and the searching time of the user is saved.
Drawings
FIG. 1 is an overall flowchart of a construction project supervision and management method according to the present application;
fig. 2 is a flowchart of construction project supervision and management methods S1, S2, and S3 according to the present application.
Detailed Description
The present application is described in further detail below with reference to figures 1-2.
The embodiment of the application discloses a construction project supervision management method and system. Referring to fig. 1 and 2, a construction project supervision and management method includes:
s1: and a starting instruction, wherein the query instruction is output after the starting instruction runs.
S11: when the user uses the query instruction, the word eye of the type of the proctoring plan template needing to be queried is input, so that the type and the corresponding times of the proctoring plan template used by the user are queried, and the times of the used proctoring plan template are output.
S12: and calling the used supervision plan template and sequencing the used supervision plan templates according to the number of times of use.
When the system is used, after used supervision planning templates are arranged in sequence, a client can clearly check the used templates before the client looks up the templates, and the time for looking up and searching is saved.
S121: when the use times of the supervision planning templates are sequenced, according to the input words, when the use times of a plurality of supervision planning templates are the same, the supervision contents in the supervision planning templates with the same number of times are summarized, and the supervision planning templates with high matching degree between the supervision contents and the input words and the number of times of occurrence of the words are arranged in front. And outputting the sorted display result.
When the user uses the method, the sorting mode adopts the mode of searching word eyes, and the sorting is carried out according to the times of corresponding word eyes and similar word eyes appearing in the proctoring content in the proctoring planning template, so that the user can accurately find out the corresponding proctoring planning template.
S2: after the screening result is displayed from top to bottom according to the similarity, a monitoring instruction is called, the monitoring instruction monitors and scans input word eyes, then a reminding instruction is operated, the reminding instruction searches an area with the problem of word eye breaking in the supervision process, and the situation that the word eyes distributed in groups are layered is searched at the same time.
S21: and analyzing the problems, analyzing the distribution condition of the word-eye fracture separation layer, and generating a corresponding solution report according to the distribution condition.
S22: and disassembling the solving sequence in the solving report, and displaying the solving steps in sequence according to the solving sequence.
S23: recording and storing the solved problems; the unresolved issues are recorded and sent to the software provider.
When the user uses the system, the system may split the grouped words into single words for retrieval, so that a large number of situations which do not meet the retrieval requirements occur, and the query speed of the user is influenced. And generating a solution report according to the distribution condition which does not accord with the retrieval condition, and directly sending the problem system which does not accord with the retrieval requirement and can not be solved to the software supplier by the user through step-by-step operation according to the well-ordered solution steps in the solution report.
S221: the resolution steps are shown in terms of red, blue and yellow, respectively. The resolution step indicated in red is most important, followed by blue and yellow. When the user uses the method, the importance of the solving steps is distinguished through different colors, and the rigor of the user in operation is improved.
S3: and (4) running a pre-stored instruction, and storing the used supervision planning template and related real-time project information data.
S31: and calling the adaptive project data range information according to the classification of different projects, comparing the current real-time project information data with the project data range information, comparing the range value of the real-time project information data with the project data range information, and screening the unqualified real-time project information data.
S32: differential reports between the non-qualified real-time project information data and the project data range information are then derived.
S33: and early warning is carried out on the real-time item information data which just reach the standard, a critical value report is derived, and the critical value report and the difference value report form an information report together.
When the user uses, come to compare with real-time project information data through normative project data range information, through reading the difference report, the user can convenient and fast know which processes need be emphatically consolidated this work progress, through reading the critical value report, the user can convenient and fast know which processes need constantly pay attention to this work progress, the prevention is made mistakes.
Example 2: a construction project supervision management system comprises a storage module and a processing module, wherein the storage module comprises a memory. The storage module is used for storing the information of the supervision planning template, the word eye problem information and the real-time project information data.
The processing module comprises a processor and is used for processing actions sent by the starting instruction, the query instruction and the monitoring instruction.
Example 3: the computer readable media described herein may be computer readable signal media or computer readable storage media or any combination of the two. A computer readable storage medium may be, for example, but not limited to, an electronic, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any combination of the foregoing. More specific examples of the computer readable storage medium may include, but are not limited to: an electrical connection having one or more wires, a portable computer diskette, a hard disk, a Random Access Memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disc read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing. In the present application, a computer readable storage medium may be any tangible medium that can contain, or store a program for use by or in connection with an instruction execution system, apparatus, or device. In this application, however, a computer readable signal medium may include a propagated data signal with computer readable program code embodied therein, for example, in baseband or as part of a carrier wave. Such a propagated data signal may take many forms, including, but not limited to, electro-magnetic, optical, or any suitable combination thereof. A computer readable signal medium may also be any computer readable medium that is not a computer readable storage medium and that can communicate, propagate, or transport a program for use by or in connection with an instruction execution system, apparatus, or device. Program code embodied on a computer readable medium may be transmitted using any appropriate medium, including but not limited to: wireless, wire, fiber optic cable, RF, etc., or any suitable combination of the foregoing.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (10)

1. A construction project supervision management method is characterized by comprising the following steps: comprises that
Responding to the starting instruction and outputting a query instruction;
responding to the query instruction, querying the type and the corresponding times of the used supervision planning template of the user, and outputting the times of the used supervision planning template;
calling the used supervision planning template and sequencing at least according to the number of use times;
inducing similar parts in the used supervision planning template with more times;
screening similar words in the used supervision planning template in the existing supervision planning template, and calling out the supervision planning template with the similar words;
and displaying the screening result from top to bottom according to the similarity, and outputting the display result.
2. The construction project supervision and management method according to claim 1, characterized in that: after the screening result is displayed from top to bottom according to the similarity, responding to the monitoring instruction and outputting a reminding instruction;
responding to a reminding instruction, searching an area with a problem of word eye breaking in the supervision process, and searching the layering condition of word eyes distributed in groups;
analyzing the problems, analyzing the distribution condition of the word eye breaking separation layers and generating a solving report;
resolving reports are disassembled step by step according to the resolving sequence;
displaying the solving steps in sequence;
recording and storing the solved problems;
the unresolved issues are recorded and sent to the software provider.
3. The construction project supervision and management method according to claim 1, characterized in that: after the types and the corresponding times of the proctoring planning templates used by the user are inquired, when the plurality of proctoring planning templates have the same times, the proctoring contents in the plurality of proctoring planning templates with the same times are summarized, and the proctoring contents are arranged in front of the proctoring planning templates with high matching degree with the input word eyes and more times of occurrence of the word eyes.
4. The construction project supervision and management method according to claim 2, characterized in that: the resolution steps are displayed in different colors.
5. The construction project supervision and management method according to claim 4, characterized in that: the colors are set to red, blue and yellow, respectively, with the solution step indicated by red being most important, followed by blue and yellow.
6. The construction project supervision and management method according to claim 1, characterized in that: and starting a pre-stored instruction, storing the supervision planning template used this time and related real-time project information data, calling the adaptive project data range information according to the classification of different projects, comparing the real-time project information data with the project data range information, and generating an information report according to the compared result.
7. The construction project supervision and management method according to claim 6, characterized in that: when the real-time project information data and the project data range information are compared, the range value of the real-time project information data is compared with the project data range information, unqualified real-time project information data is screened out, and then a difference report between the unqualified real-time project information data and the project data range information is derived.
8. The construction project supervision and management method according to claim 7, characterized in that: and early warning is carried out on the real-time item information data which just reach the standard, and a critical value report is derived, wherein the critical value report and the difference value report are information reports.
9. The construction project supervision and management system according to claim 1, characterized in that: comprising a memory and a processor, said memory having stored thereon a computer program which can be loaded by the processor and which performs the method of any of claims 1 to 8.
10. A computer-readable storage medium, in which a computer program is stored which can be loaded by a processor and which executes the method of any one of claims 1 to 8.
CN202111408796.0A 2021-11-24 2021-11-24 Construction project supervision management method and system Withdrawn CN114168245A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111408796.0A CN114168245A (en) 2021-11-24 2021-11-24 Construction project supervision management method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111408796.0A CN114168245A (en) 2021-11-24 2021-11-24 Construction project supervision management method and system

Publications (1)

Publication Number Publication Date
CN114168245A true CN114168245A (en) 2022-03-11

Family

ID=80480734

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111408796.0A Withdrawn CN114168245A (en) 2021-11-24 2021-11-24 Construction project supervision management method and system

Country Status (1)

Country Link
CN (1) CN114168245A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116993296A (en) * 2023-08-15 2023-11-03 深圳市中联信信息技术有限公司 Intelligent supervision management system and method applied to engineering design interaction platform

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116993296A (en) * 2023-08-15 2023-11-03 深圳市中联信信息技术有限公司 Intelligent supervision management system and method applied to engineering design interaction platform
CN116993296B (en) * 2023-08-15 2024-04-16 深圳市中联信信息技术有限公司 Intelligent supervision management system and method applied to engineering design interaction platform

Similar Documents

Publication Publication Date Title
US11941137B2 (en) Use of multi-faceted trust scores for decision making, action triggering, and data analysis and interpretation
KR100877461B1 (en) Real time data warehousing
CN106371984B (en) A kind of data monitoring method, equipment and system
US6542881B1 (en) System and method for revealing necessary and sufficient conditions for database analysis
US8615516B2 (en) Grouping similar values for a specific attribute type of an entity to determine relevance and best values
US20030158944A1 (en) Software control in a business transaction environment
CN111913860B (en) Operation behavior analysis method and device
CN113010484A (en) Log file management method and device
CN112799722A (en) Command recognition method, device, equipment and storage medium
CN112148968A (en) Scientific and technological innovation service platform control system and control method
CN110728453A (en) Big data based policy automatic matching analysis system and method
CN114168245A (en) Construction project supervision management method and system
CN112256871B (en) Material fulfillment system and method
JP5140509B2 (en) Design case search device, design case search program
CN114676231A (en) Target information detection method, device and medium
JP4905247B2 (en) Legal compliance support system
US7263519B2 (en) Process for searching a repository of resources
US20220043849A1 (en) Document processing program and information processing apparatus
CN106528590B (en) Query method and device
US7146378B2 (en) Methods, systems and computer program products for segmented presentation of service order status information
CN115293682A (en) Abnormal logistics order monitoring method and related device
CN112883739A (en) Abnormal warning method and device for rating system, electronic equipment and storage medium
US20110029493A1 (en) Generic Method To Build Catalogs For Change Management
CN106126633A (en) The processing method of noble metal data, device and system
CN113742116A (en) Abnormity positioning method, abnormity positioning device, abnormity positioning equipment and storage medium

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20220311