CN114148644A - Shield construction muck storage device - Google Patents
Shield construction muck storage device Download PDFInfo
- Publication number
- CN114148644A CN114148644A CN202111318905.XA CN202111318905A CN114148644A CN 114148644 A CN114148644 A CN 114148644A CN 202111318905 A CN202111318905 A CN 202111318905A CN 114148644 A CN114148644 A CN 114148644A
- Authority
- CN
- China
- Prior art keywords
- bounding wall
- base
- storage device
- long side
- wall mechanism
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 22
- 230000007246 mechanism Effects 0.000 claims abstract description 80
- 238000007789 sealing Methods 0.000 claims description 12
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 239000002689 soil Substances 0.000 description 7
- 238000000034 method Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000007613 environmental effect Effects 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000006978 adaptation Effects 0.000 description 1
- 230000004075 alteration Effects 0.000 description 1
- 238000009412 basement excavation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65D—CONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
- B65D90/00—Component parts, details or accessories for large containers
- B65D90/02—Wall construction
- B65D90/08—Interconnections of wall parts; Sealing means therefor
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B65—CONVEYING; PACKING; STORING; HANDLING THIN OR FILAMENTARY MATERIAL
- B65D—CONTAINERS FOR STORAGE OR TRANSPORT OF ARTICLES OR MATERIALS, e.g. BAGS, BARRELS, BOTTLES, BOXES, CANS, CARTONS, CRATES, DRUMS, JARS, TANKS, HOPPERS, FORWARDING CONTAINERS; ACCESSORIES, CLOSURES, OR FITTINGS THEREFOR; PACKAGING ELEMENTS; PACKAGES
- B65D90/00—Component parts, details or accessories for large containers
Abstract
The invention relates to a shield construction muck storage device which comprises a bottom plate mechanism and two long side wall plate mechanisms positioned above the bottom plate mechanism, wherein the front part and the rear part of the top of the bottom plate mechanism are fixedly arranged with the bottom of the long side wall plate mechanism, the left side and the right side of the two long side wall plate mechanisms are fixedly provided with short side wall plate mechanisms, the tops of the two short side wall plate mechanisms are fixedly provided with upper covers, and the bottoms of the upper covers are fixedly connected with the tops of the long side wall plate mechanisms. According to the invention, the two long side enclosing plates and the two short side enclosing plates are fixed through the bolts, and the first side base, the second side base and the middle base are fixed through the bolts, so that a box body is formed, the storage device can be conveniently spliced and disassembled, the size of the storage device can be well adjusted according to the site position, the operation and the use are convenient and fast, and the shield construction requirements are met.
Description
Technical Field
The invention relates to the technical field of shield construction, in particular to a temporary muck storage and collection box for shield construction.
Background
A temporary structure soil collection pit for storing excavated muck during shield construction generally adopts a reinforced concrete structure, the traditional manufacturing process needs to be carried out through earthwork excavation, axis measurement and establishment, reinforced bar engineering, template engineering, concrete engineering and other steps, the manufacturing process is high in control requirement, the repeated circulation and utilization can not be carried out, the period is longer, quick splicing and disassembly can not be carried out, the use is not convenient enough, the use can not be enough to achieve good economic and environmental protection, the shield method soil pressure balance shield construction standardization and standardization can not be met.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides a shield construction muck storage device, which solves the problems of quick assembly and disassembly; the modularized and standardized customization can meet the requirements of arrangement of various shield sites and meet the requirements of shield construction unearthing.
In order to achieve the purpose, the invention is realized by the following technical scheme:
the utility model provides a shield constructs construction dregs storage device, includes bottom plate mechanism and two long side bounding wall mechanisms that are located bottom plate mechanism top, bottom plate mechanism top front portion and rear portion all with the bottom fixed mounting of long side bounding wall mechanism, two the equal fixed mounting in the left and right sides of long side bounding wall mechanism has short side bounding wall mechanism, two the equal fixed mounting in top of short side bounding wall mechanism has the upper cover, the bottom of upper cover and the top fixed connection of long side bounding wall mechanism.
Preferably, long side bounding wall mechanism and short side bounding wall mechanism all include a plurality of gusset, the top of long side bounding wall mechanism and short side bounding wall mechanism all passes through the rear portion fixed connection of angle steel and a plurality of gusset with the bottom, a plurality of the bottom fixedly connected with side pipe of gusset is located two from top to bottom fixed mounting has first stand between the relative one side of side pipe, the equal fixed mounting in the left and right sides of side pipe has a triangle gusset, the equal fixed mounting in rear portion of long side bounding wall mechanism and short side bounding wall mechanism has a first shrouding.
Preferably, the bottom plate mechanism comprises a first side base, a second side base and a middle base, the first side base, the second side base and the middle base are respectively composed of a plurality of second triangular rib plates, a rectangular pipe, a panel and square rib plates, the left side and the right side of the rectangular pipe are fixedly connected with the second triangular rib plates, the bottom of the panel is fixedly connected with the top of the square rib plates, and a second sealing plate is fixedly mounted at the top of the middle base.
Preferably, the right side of first side base and the right side of middle base have all been seted up the dimple, the left side of second side base and the equal fixed mounting in left side of middle base have with the convex seat of dimple looks adaptation.
Preferably, the upper cover consists of a second upright post and a third sealing plate, and the top of the second upright post is fixedly connected with the bottom of the third sealing plate.
Preferably, the long side enclosing plate mechanism and the short side enclosing plate mechanism are fixedly connected through a bolt assembly, and the bolt assembly comprises a bolt, a nut and a gasket.
Compared with the prior art, the shield construction muck storage device provided by the invention has the following beneficial effects:
(1) this storage device fixes through the bolt at two long side bounding walls and two short side bounding walls, and rethread bolt fastening first side base, second side base and middle base enclose into a box, can be convenient splice and dismantle the soil box, and the size according to place position control soil box that can be fine operates convenient and fast that gets up, has satisfied the use of trade company.
(2) This storage device through at long side bounding wall, short side bounding wall and bottom plate mechanism concatenation integration soil box, uses can be fine reach economic environmental protection, fine satisfying shield method earth pressure balance shield construction's standardization and standardization, more firm of structure.
Drawings
FIG. 1 is a schematic external view of the present invention;
FIG. 2 is a right side view of the short side panel mechanism and structure of the present invention;
FIG. 3 is a top view of the long side enclosure mechanism, short side enclosure mechanism and upper cover structure of the present invention;
FIG. 4 is a schematic structural view of a long side boarding mechanism of the present invention;
FIG. 5 is a schematic view of a first sealing plate of the present invention;
FIG. 6 is a schematic view of a short side panel construction of the present invention;
FIG. 7 is a schematic view of a first side base structure of the present invention;
FIG. 8 is a schematic diagram of the structure of the panel, rectangular tube and square rib of the present invention;
FIG. 9 is a schematic view of the dimple arrangement of the present invention;
FIG. 10 is a schematic view of a second side base structure of the present invention;
FIG. 11 is a schematic view of the boss structure of the present invention;
FIG. 12 is a schematic view of an intermediate base structure of the present invention;
FIG. 13 is a schematic view of the structure of the upper cover of the present invention;
FIG. 14 is a schematic diagram of a third sealing plate structure according to the present invention;
in the figure: 1. a bottom plate mechanism; 2. a long side panel mechanism; 3. short side enclosing plate mechanisms; 4. an upper cover; 5. a first side base; 6. a second side base; 7. a middle base; 8. a rib plate; 9. a square tube; 10. a first upright post; 11. a first seal plate; 12. a second triangular rib plate; 13. a rectangular tube; 14. a panel; 15. a square rib plate; 16. a second seal plate; 17. a recess; 18. a boss; 19. a second upright post; 20. a third seal plate; 21. a first triangular rib plate.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1 to 14, the shield construction muck storage device of the invention comprises a bottom plate mechanism 1 and two long side wall plate mechanisms 2 located above the bottom plate mechanism 1, wherein the front part and the rear part of the top of the bottom plate mechanism 1 are fixedly mounted with the bottoms of the long side wall plate mechanisms 2, the left side and the right side of the two long side wall plate mechanisms 2 are fixedly mounted with short side wall plate mechanisms 3, the tops of the two short side wall plate mechanisms 3 are fixedly mounted with an upper cover 4, the bottom of the upper cover 4 is fixedly connected with the top of the long side wall plate mechanism 2, the bottom plate mechanism 1 comprises a first side base 5, a second side base 6 and a middle base 7, the storage device can be conveniently spliced and disassembled, the size of a soil collecting box can be well adjusted according to the site position, the operation and use are convenient and fast, the use of a merchant is satisfied, the long side wall plate mechanisms 2 and the short side wall plate mechanisms 3 both comprise a plurality of rib plates 8, the top and the bottom of the long side wall plate mechanism 2 and the short side wall plate mechanism 3 are fixedly connected with the rear parts of a plurality of rib plates 8 through angle steels, the bottom parts of the plurality of rib plates 8 are fixedly connected with a square pipe 9, a first upright post 10 is fixedly arranged between one side opposite to the upper square pipe 9 and the lower square pipe 9, the left side and the right side of the square pipe 9 are fixedly provided with a first triangular rib plate 21, the rear parts of the long side wall plate mechanism 2 and the short side wall plate mechanism 3 are fixedly provided with a first sealing plate 11, the first side base 5, the second side base 6 and the middle base 7 are respectively composed of a plurality of second triangular rib plates 12, rectangular pipes 13, panels 14 and square rib plates 15, the left side and the right side of the rectangular pipes 13 are fixedly connected with the second triangular rib plates 12, the bottom part of the panels 14 is fixedly connected with the top parts of the square rib plates 15, the top part of the middle base 7 is fixedly provided with a second sealing plate 16, the left side of the second side base 6 and the left side of the middle base 7 are both fixedly provided with convex seats 18 matched with the concave seats 17, the upper cover 4 consists of a second upright column 19 and a third sealing plate 20, the top of the second upright column 19 is fixedly connected with the bottom of the third sealing plate 20, the standardization and the standardization of the shield method earth pressure balance shield construction are well met, and the structure is more stable.
During the use, with two long side bounding wall mechanisms 2 about together through bolt assembly installation, splice into a big long side bounding wall mechanism 2, two big long side bounding wall mechanisms 2 around setting up, two short side bounding wall mechanisms 3 about will be installed into a big short side bounding wall mechanism 3 through the bolt again, two big long side bounding wall mechanisms 2 and two big short side bounding wall mechanisms 3 of the left and right sides are installed through the bolt again, upper cover 4 passes through the bolt and installs in the top of long side bounding wall mechanism 2, the rethread is installed bottom plate mechanism 1 in the bottom of long side bounding wall mechanism 2 and short side bounding wall mechanism 3, it is whole to enclose into a soil box.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (6)
1. The utility model provides a shield constructs construction dregs storage device, includes bottom plate mechanism (1) and two long side boarding mechanisms (2) that are located bottom plate mechanism (1) top, its characterized in that: bottom plate mechanism (1) top, front portion and rear portion all with the bottom fixed mounting of long side bounding wall mechanism (2), two the equal fixed mounting in both sides has short side bounding wall mechanism (3), two about long side bounding wall mechanism (2) the equal fixed mounting in top of short side bounding wall mechanism (3) has upper cover (4), the bottom of upper cover (4) and the top fixed connection of long side bounding wall mechanism (2).
2. The shield construction muck storage device of claim 1, wherein: long side bounding wall mechanism (2) and short side bounding wall mechanism (3) all include a plurality of gusset (8), the top and the bottom of long side bounding wall mechanism (2) and short side bounding wall mechanism (3) all are through the rear portion fixed connection of angle steel with a plurality of gusset (8), a plurality of bottom fixedly connected with side pipe (9) of gusset (8) are located two from top to bottom fixed mounting has first stand (10) between the relative one side of side pipe (9), the equal fixed mounting in the left and right sides of side pipe (9) has first triangle gusset (21), the equal fixed mounting in rear portion of long side bounding wall mechanism (2) and short side bounding wall mechanism (3) has first shrouding (11).
3. The shield construction muck storage device of claim 1, wherein: the bottom plate mechanism (1) comprises a first side base (5), a second side base (6) and a middle base (7), wherein the first side base (5), the second side base (6) and the middle base (7) are formed by a plurality of second triangular rib plates (12), rectangular tubes (13), a panel (14) and square rib plates (15), the left side and the right side of each rectangular tube (13) are fixedly connected with the second triangular rib plates (12), the bottom of the panel (14) is fixedly connected with the top of each square rib plate (15), and the top of the middle base (7) is fixedly provided with a second sealing plate (16).
4. The shield construction muck storage device of claim 3, wherein: concave seats (17) are respectively arranged on the right side of the first side base (5) and the right side of the middle base (7), and convex seats (18) matched with the concave seats (17) are respectively fixedly arranged on the left side of the second side base (6) and the left side of the middle base (7).
5. The shield construction muck storage device of claim 1, wherein: the upper cover (4) is composed of a second upright post (19) and a third sealing plate (20), and the top of the second upright post (19) is fixedly connected with the bottom of the third sealing plate (20).
6. The shield construction muck storage device of claim 1, wherein: and the long side enclosing plate mechanism and the short side enclosing plate mechanism are fixedly connected through a bolt assembly, and the bolt assembly comprises a bolt, a nut and a gasket.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111318905.XA CN114148644A (en) | 2021-11-09 | 2021-11-09 | Shield construction muck storage device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111318905.XA CN114148644A (en) | 2021-11-09 | 2021-11-09 | Shield construction muck storage device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114148644A true CN114148644A (en) | 2022-03-08 |
Family
ID=80459980
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111318905.XA Pending CN114148644A (en) | 2021-11-09 | 2021-11-09 | Shield construction muck storage device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114148644A (en) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105691833A (en) * | 2016-04-16 | 2016-06-22 | 利欧集团浙江泵业有限公司 | Packaging box |
CN205931911U (en) * | 2016-06-28 | 2017-02-08 | 天津天纺高新物流有限公司 | Convertible volume's concatenation thing flow box |
CN206128787U (en) * | 2016-10-17 | 2017-04-26 | 中建交通建设集团有限公司 | Assembled dregs strorage device |
CN109051197A (en) * | 2018-08-17 | 2018-12-21 | 普雷沃流体控制科技(芜湖)有限公司 | A kind of adjustable instrument and meter transport case and its assembling and application method |
CN110630074A (en) * | 2019-08-30 | 2019-12-31 | 上海市基础工程集团有限公司 | Prefabricated assembled soil collection box for shield tunnel engineering construction |
CN212428253U (en) * | 2020-05-29 | 2021-01-29 | 中铁十八局集团第一工程有限公司 | Detachable shield constructs dregs pond structure |
CN212867028U (en) * | 2020-07-23 | 2021-04-02 | 苏州业广集成房屋有限公司 | Quick-assembly box frame structure of container house |
CN214242282U (en) * | 2021-01-12 | 2021-09-21 | 新疆绿洲机械有限公司 | Special awl concatenation frock in powdery material storage storehouse |
-
2021
- 2021-11-09 CN CN202111318905.XA patent/CN114148644A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105691833A (en) * | 2016-04-16 | 2016-06-22 | 利欧集团浙江泵业有限公司 | Packaging box |
CN205931911U (en) * | 2016-06-28 | 2017-02-08 | 天津天纺高新物流有限公司 | Convertible volume's concatenation thing flow box |
CN206128787U (en) * | 2016-10-17 | 2017-04-26 | 中建交通建设集团有限公司 | Assembled dregs strorage device |
CN109051197A (en) * | 2018-08-17 | 2018-12-21 | 普雷沃流体控制科技(芜湖)有限公司 | A kind of adjustable instrument and meter transport case and its assembling and application method |
CN110630074A (en) * | 2019-08-30 | 2019-12-31 | 上海市基础工程集团有限公司 | Prefabricated assembled soil collection box for shield tunnel engineering construction |
CN212428253U (en) * | 2020-05-29 | 2021-01-29 | 中铁十八局集团第一工程有限公司 | Detachable shield constructs dregs pond structure |
CN212867028U (en) * | 2020-07-23 | 2021-04-02 | 苏州业广集成房屋有限公司 | Quick-assembly box frame structure of container house |
CN214242282U (en) * | 2021-01-12 | 2021-09-21 | 新疆绿洲机械有限公司 | Special awl concatenation frock in powdery material storage storehouse |
Non-Patent Citations (1)
Title |
---|
李继业等: "《水暖工程基础知识与施工技术》", vol. 1, 北京理工大学出版社, pages: 223 - 225 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207714108U (en) | A kind of support system of the more arcading arched aqueducts of large span or bridge | |
CN114148644A (en) | Shield construction muck storage device | |
CN210238780U (en) | Adopt assembled beam column node of I-steel high strength bolt connection | |
CN206495550U (en) | The tower-like communication base station of single tube | |
CN214695657U (en) | Foundation pit supporting coaming convenient to dismantle | |
CN109707042A (en) | A kind of Self-resetting frame center support system with L-type part connecting node | |
CN213539894U (en) | Reinforcing device for angle steel of main column of angle steel tower | |
CN110318420B (en) | Prefabricated assembled underground utility tunnel | |
CN210562299U (en) | Prefabricated assembled underground comprehensive pipe gallery | |
CN207314905U (en) | Roofing steel purlin bar ruggedized construction for portal frame house | |
CN208167750U (en) | The modular steel sheet pile of regularization is to supporting system | |
CN209495852U (en) | A kind of anti-buckling steel plate shear force wall slidably fixed device of cross-brace | |
CN218958846U (en) | Fixed photovoltaic module support of variable cross section post | |
CN216586187U (en) | Rapid dismounting's interim buttress steel pipe of big steel pipe is flat to be connected and is constructed | |
CN215716115U (en) | Connecting device for connecting reinforced concrete beam and profile steel concrete column | |
CN215717230U (en) | Tent with frame structure | |
CN217414337U (en) | High-speed railway beam-making pedestal structure suitable for unfavorable geology | |
CN217379720U (en) | Structure for improving erection efficiency of steel column operating platform | |
CN220035686U (en) | Frame structure suitable for avoidance-free equipment | |
CN215948237U (en) | Highway bridge construction cofferdam device | |
CN212019251U (en) | Auxiliary jig frame for manufacturing reinforcing mesh | |
CN214363589U (en) | Assembled frame foundation for steel structure tower | |
CN219033730U (en) | Assembled building steel structure roof truss | |
CN220580295U (en) | Inner inclined honeycomb aluminum plate glass combined curtain wall mounting structure | |
CN211312835U (en) | Through bolt assembly structure of square steel connecting column and square steel tubular beam |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220308 |
|
RJ01 | Rejection of invention patent application after publication |