CN114135321A - Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method - Google Patents

Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method Download PDF

Info

Publication number
CN114135321A
CN114135321A CN202111598849.XA CN202111598849A CN114135321A CN 114135321 A CN114135321 A CN 114135321A CN 202111598849 A CN202111598849 A CN 202111598849A CN 114135321 A CN114135321 A CN 114135321A
Authority
CN
China
Prior art keywords
grouting
pipe
section
vacuum
pipe section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111598849.XA
Other languages
Chinese (zh)
Inventor
王玥
徐启鹏
卓越
宋妍
马召林
王�华
李广跃
高广义
倪汉杰
皮乾勇
赵爽
贺雄飞
史继尧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRTG Survey and Design Institute Co Ltd
Original Assignee
CRTG Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRTG Survey and Design Institute Co Ltd filed Critical CRTG Survey and Design Institute Co Ltd
Priority to CN202111598849.XA priority Critical patent/CN114135321A/en
Publication of CN114135321A publication Critical patent/CN114135321A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a step-by-step sectional type tunnel curtain grouting construction pipe group, a device and a construction method, wherein the device comprises a plurality of groups of construction kits, each construction kit comprises two grouting pipes and a vacuum pipe, and the construction kits are inserted into grouting holes with different depths; each grouting pipe is formed by sequentially connecting a plurality of first grouting pipe sections; the vacuum pipe is formed by connecting a plurality of vacuum pipe sections and a plurality of isolation pipe sections which are communicated at intervals, each isolation pipe section is of a double-layer sleeve structure and comprises a second grouting pipe section and an isolation bag sleeve which are sleeved together, and two ends of the isolation bag sleeve are attached to outer walls of two ends of the second grouting pipe section in a closed mode to form an expansion bag cavity with two closed ends. By using the device and the method, the cement slurry is ensured to be fully injected into the surrounding rock stratum, the injection amount of the slurry is increased, uniform network-shaped slurry veins are formed in the surrounding rock, the reinforcing effect is good, the slurry diffusion range is effectively controlled, and waste caused by disordered diffusion of materials is avoided.

Description

Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method
Technical Field
The invention belongs to the technical field of tunnel grouting reinforcement, and particularly relates to a step-by-step sectional type tunnel curtain grouting construction pipe group, a device and a construction method.
Background
In the process of tunnel construction, tunnel engineering encounters more and more unfavorable geology, and tunnel curtain grouting construction is one of the most effective means for improving the stratum and is increasingly widely applied. However, in many undisturbed fine-grained soil formations, such as fine sand, fine sand with clay, fine sand with gravel, and the like, the formations are easy to permeate water and have poor self-stability, and meanwhile, as the fine particles are compact and dense, the conventional cement slurry (suspension) is extremely difficult to inject, even if expensive chemical slurry (solution) is adopted, the diffusion radius is difficult to break through 1m, the strength of the slurry vein concretion body is very low and is usually less than 0.5MPa (the strength of the cement slurry concretion body is usually more than 10MPa), and the grouting and reinforcing effects of the formations are difficult to achieve.
In actual tunnel curtain grouting construction, methods such as encrypted drilling, high-pressure grouting, repeated grouting and the like are often forced to be adopted, but the problems of small grouting amount, conglomeration of slurry vein concretes and uneven reinforcement still exist, severe extrusion and disturbance are easily generated on peripheral strata, large deformation is generated, and the safety of buildings (structures) is endangered.
Therefore, a feasible tunnel curtain grouting method is needed to solve the problem that slurry in an undisturbed fine-grained soil stratum is difficult to inject, so that slurry vein concretes which are uniformly distributed and have sufficient strength are formed, and severe disturbance to the peripheral stratum is reduced as much as possible.
Disclosure of Invention
The invention aims to provide a step-by-step sectional type tunnel curtain grouting construction pipe group, a device and a construction method, which ensure that cement grout is fully injected into a surrounding rock stratum, improve the injection amount of the grout, form uniform network-shaped grout veins in the surrounding rock, have good reinforcing effect, effectively control the grout diffusion range and avoid waste caused by disordered diffusion of materials.
The invention adopts the following technical scheme: a step-by-step sectional type tunnel curtain grouting construction pipe group is characterized by comprising a plurality of groups of construction kits, wherein each construction kit comprises two grouting pipes and a vacuum pipe and is used for being inserted into grouting holes with different depths; wherein:
each grouting pipe is formed by sequentially connecting a plurality of first grouting pipe sections;
the vacuum pipe is formed by connecting a plurality of vacuum pipe sections and a plurality of isolation pipe sections which are communicated at intervals, the vacuum pipe section is connected at the foremost end, and the middle part of each vacuum pipe section is communicated with the grouting hole; each isolation pipe section is of a double-layer sleeve structure and comprises a second grouting pipe section and an isolation bag sleeve which are sleeved together inside and outside, and two ends of the isolation bag sleeve are attached to and sealed with the outer walls of two ends of the second grouting pipe section to form an expansion bag cavity with two sealed ends; the front ends of the first grouting pipe section and the vacuum pipe section at the foremost end are closed;
the middle sections of the first grouting pipe section and the second grouting pipe section are small-diameter sections, and rubber reset sleeves are sleeved on the small-diameter sections; a plurality of grout overflow holes are circumferentially arranged on the outer wall of the small-diameter section at intervals, each grout overflow hole is in a circular truncated cone shape with a large outer end and a small inner end from outside to inside, and a one-way plug in accordance with the shape of each grout overflow hole is arranged in each grout overflow hole; under the grouting pressure, all the one-way plugs can move outwards in the grout overflow holes, and the outer ends of the one-way plugs jack up the rubber reset sleeves to form grout overflow channels with two ends communicated with the grouting holes; when no grouting pressure exists, the rubber reset sleeve contracts to close the grout overflow channel;
in the isolation pipe section, the slurry overflow channel is communicated with the expansion bag cavity, slurry fills the expansion bag cavity, the outer wall of the expansion bag cavity is attached to block a grouting hole of the section where the expansion bag cavity is located, the grouting hole sections where two vacuum pipe sections which are arranged at intervals are isolated, and the grouting hole is divided into a plurality of isolation sections.
The invention also discloses a step-by-step sectional type tunnel curtain grouting construction device, which comprises the step-by-step sectional type tunnel curtain grouting construction pipe group and a plurality of built-in gun pipes, wherein each built-in gun pipe is used for being inserted into a corresponding vacuum pipe and a corresponding grouting pipe, and each built-in gun pipe comprises:
the connecting pipes are of multi-section detachably connected pipe body structures, are inserted into the corresponding pipes, have front ends facing the pipe bottoms and can move back and forth in the pipes;
the gun head is a hard tube body and is detachably arranged at the front end of the connecting tube; the front section of the pipe body is solid and closed, and the pipe body in the middle section is provided with a plurality of communicating holes;
the isolation pistons are sleeved at the front end and the rear end of the gun head at intervals, the outer diameter of the isolation pistons is consistent with the inner diameter of the inserted pipe, and the isolation pistons are tightly attached to the pipe wall so as to seal the vacuum pipe or the grouting pipe section between the isolation pistons into a sealed space;
the built-in gun tube is used for sequentially injecting water or grout into the first grouting pipe section, sequentially grouting into each isolation pipe section and vacuumizing each vacuum pipe section.
Further, the vacuum suction device is connected with an internal gun tube inserted into the vacuum tube;
the vacuum pumping device comprises a vacuum pumping barrel, the vacuum pumping barrel comprises a liquid storage barrel which is a vertically placed steel sealed barrel and is used for temporarily storing pumped liquid; the upper end of the liquid storage barrel is provided with a vacuum pump and a negative pressure meter;
the upper part and the lower part of the side wall of the liquid storage barrel are respectively provided with a liquid inlet pipe and a liquid outlet pipe which are communicated with the inner cavity of the barrel, and a liquid inlet valve is arranged on the liquid inlet pipe; a drain valve is arranged on the drain pipe; when water is injected to wash the surrounding rock, the liquid inlet pipe is connected with the rear end of a connecting pipe, and water flow and fine particles are sucked into the liquid storage barrel;
an observation window is arranged on the side wall of the liquid storage barrel and in the area where the liquid inlet pipe is located, and is used for observing the color, the property and the flow of liquid flowing into the barrel from the liquid inlet valve and the height of the liquid level in the barrel.
Further, the lengths of the two grouting pipes are not equal.
The invention also discloses a step-by-step sectional type tunnel curtain grouting construction method, which uses the step-by-step sectional type tunnel curtain grouting construction device and comprises the following steps:
step one, grouting holes are formed:
on the grout stop wall, taking the center of the tunnel as the center of a circle, arranging a plurality of radial extensions at intervals along the direction of contour lines of the vault and the side walls of the tunnel, designing three orifices of grouting holes at the inner side, the middle part and the outer side at intervals from inside to outside on each same radial extension, and designing the angle and the depth of each grouting hole; selecting a radially extending grouting hole orifice to be used as a grouting hole, and obtaining the final hole position of the grouting hole in the surrounding rock; wherein: the final holes of the middle and outer grouting holes are positioned at the cross section of the terminal of the section to be reinforced of the tunnel, and the final hole of the inner grouting hole is positioned at the cross section of the middle of the section to be reinforced of the tunnel;
step two, setting vacuum isolation sections in sections:
inserting a vacuum tube into the inner side grouting hole to the bottom of the hole, sequentially retreating from a second grouting pipe section at the bottom of the hole to the orifice, sequentially injecting grout into each second grouting pipe section, enabling the grout to overflow the rubber reset sleeve through the one-way plug under the action of grouting pressure and enter the expansion bladder cavity, and enabling the isolation bladder sleeve to expand to block the grouting hole at the section so as to complete the blocking of the grouting hole at each isolation pipe section;
step three, injecting water to wash the surrounding rock, and forming a water flow channel in the surrounding rock:
the grouting pipes in the middle and outer grouting holes are respectively inserted with a built-in gun barrel to the bottom, a built-in gun barrel is inserted in the vacuum pipe to the bottom, and the orifice end of the vacuum pipe is connected with a vacuum suction device; synchronously backing the two built-in gun barrel sections of the middle grouting pipe and the vacuum pipe to the orifice end, and injecting clear water into the first grouting pipe section in each section; pumping each vacuum pipe section into a negative pressure state, forming a negative pressure region between the vacuum pipe section and the grouting holes, guiding pressurized clean water to wrap fine particles to flow to the negative pressure region, flowing into the vacuum pipe section, discharging the fine particles out of the vacuum pipe section, and forming a plurality of water flow channels in surrounding rocks between the middle grouting holes and the inner side grouting holes in the flowing process of the clean water;
repeating the operation, and forming a plurality of water flow channels in the surrounding rock between the outer side grouting holes and the inner side grouting holes;
injecting chemical grout to form primary grout veins:
sequentially moving from a first grouting pipe section at the bottom of a grouting pipe in the middle grouting hole and the outer grouting hole in sections to retreat towards an orifice end, and sequentially injecting chemical grout into each section of grouting pipe; simultaneously, synchronously injecting chemical grout, sequentially moving back from the vacuum pipe section at the bottom of the hole in a segmented manner, vacuumizing each vacuum pipe section, and enabling the chemical grout in the grouting pipe section on the same cross section with the vacuum pipe section to flow into and fill a water flow channel in the surrounding rock and solidify to form primary grout veins;
and fifthly, repeating the first step to the fourth step to finish the grouting of the tunnel curtain.
Further, in the fourth step, after the primary slurry veins are formed, cement slurry is injected to form composite slurry veins, which specifically comprises the following steps: and injecting the chemical grout into the channel with the injected chemical grout to form a composite grout vein coated with the cement grout and the primary grout vein.
Further, the arrangement of the grouting holes and the orifices is as follows: the inner side, the middle and the outer side grouting holes are all multiple in orifices, the number of the orifices is the same, and the orifices of the inner side, the middle and the outer side grouting holes are all arranged in an arch shape along the contour lines of the vault and the side walls of the tunnel.
Further, the specific process of the second step is as follows: inserting a built-in gun tube into the vacuum tube, wherein the gun head is positioned at a second grouting pipe section at the bottom of the hole, and the orifice end of the built-in gun tube is connected with a grouting device; the gun head sequentially retreats from the bottom of the hole to the orifice and is sequentially positioned in each second grouting pipe section; in each second grouting pipe section, two isolation pistons are tightly attached to the inner wall of the second grouting pipe section, and a closed space is formed between the two isolation pistons; and injecting grout into each second grouting pipe section by the gun head, wherein the grout enters the expansion bladder cavity under the action of grouting pressure.
Further, the specific process of the third step is as follows:
inserting a built-in gun barrel into the middle grouting pipe, enabling the gun head to reach a first grouting pipe section at the bottom, and enabling the gun head to sequentially retreat towards the orifice end from the first grouting pipe section at the bottom end and to be sequentially and respectively positioned in each first grouting pipe section; injecting water into the built-in gun barrel, injecting the water into the first grouting pipe section through the gun head, and ejecting the one-way plug to enter the grouting hole from the grout overflow hole;
meanwhile, the vacuum suction device is connected with a built-in gun barrel in the vacuum pipe, the gun head is positioned in the vacuum pipe section at the bottom of the hole and is synchronous with the injection of clear water, and the gun head retreats towards the orifice end in sequence and is respectively positioned in each vacuum pipe section in sequence; in each vacuum pipe section, a closed space is formed between the two isolation pistons and the section of the vacuum pipe section, which is provided with the vent holes, the vacuum suction device sucks the vacuum pipe section, a negative pressure area is formed between the closed space and the grouting holes, pressurized clean water at the first grouting pipe section of the corresponding section is guided to wrap fine particles under pressure and flow to the negative pressure area, the fine particles flow to the vacuum pipe section and are discharged out of the vacuum pipe section, and a plurality of water flow channels are formed in surrounding rocks between the grouting holes on the inner side of the middle grouting hole in the flowing process of the clean water.
Further, the specific process of the fourth step is as follows:
inserting a built-in gun barrel into a grouting pipe in the middle grouting hole, wherein the gun head is positioned in a first grouting pipe section at the bottom end, two isolation pistons are tightly attached to the inner wall of the first grouting pipe section, and a closed space is formed between the two isolation pistons; meanwhile, the other built-in gun tube is inserted into the vacuum tube, the gun head is positioned in the vacuum tube section at the bottom end, and in each vacuum tube section, a closed space is formed between the two isolation pistons and the section of the vacuum tube section, which is provided with the vent hole;
two built-in gun barrels drive the gun heads to synchronously retreat to the orifice end in sequence from the bottom of the hole to the orifice, and the following operations are carried out in the first grouting pipe section and the vacuum pipe section of each section in sequence: injecting chemical grout into the first grouting pipe section, simultaneously sucking by using a vacuum suction device, vacuumizing the closed space, enabling the chemical grout to flow into the water flow channel, and when the water flow channel is filled with the chemical grout, sucking the grout into the vacuum suction device, and completing grouting of the chemical grout;
by adopting the above operation, cement slurry grouting is completed.
The invention has the beneficial effects that: 1. the formed water flow channel is used as a subsequent grouting channel for sectional grouting, after chemical grout is injected firstly, the contact surface of a chemical grout stone body and a stratum becomes a weak surface, and the cement grout generates stress concentration along the surface under the action of grouting pressure and then is easy to split and flow, so that the resistance of an original stratum is overcome, and the injection amount of the grout is greatly increased. 2. The grout vein formed by hardening the grout is network-shaped, replaces the massive block-shaped grout vein which is often generated in the conventional grouting scheme, and has more uniform strengthening on the stratum and better grouting effect. 3. The grout is injected into the grouting channel and enters the stratum from the grouting channel, so that the grouting range is better controlled, the effective utilization rate of the grout is improved, and the cost is saved. 4. A certain amount of stratum fine particles are washed out from the water flow channel and replaced by slurry filling, so that the disturbance to the stratum during grouting is relatively small, and the safety of surrounding buildings (structures) is ensured.
Drawings
FIG. 1 is a schematic structural view of a step-by-step sectional type tunnel curtain grouting construction pipe set;
FIG. 2 is a schematic structural view of a tube head;
FIG. 3 is a schematic view of the construction of a first and second section of grout;
FIG. 4 is a schematic diagram of a vacuum tube segment;
FIG. 5 is a schematic view of the structure of an isolated pipe section;
FIG. 6 is a schematic view of a built-in gun barrel;
FIG. 7 is a schematic structural view of a vacuum suction apparatus;
FIG. 8 is a 3D schematic view of a step-wise staged tunnel curtain grouting;
FIG. 9 is a schematic diagram of a step-by-step sectional tunnel curtain grouting scheme showing the arrangement of grouting holes and orifices in a longitudinal cross-sectional view;
FIG. 10 is a longitudinal sectional view of a grout tube and vacuum tube inserted into the grout hole;
FIG. 11 is a schematic view of the formation of a water flow channel in the surrounding rock;
FIG. 12 is a schematic diagram of the structure of the chemical grout injected into the surrounding rock;
FIG. 13 is a schematic view of the structure of the surrounding rock injected with cement slurry;
wherein: 1. a grouting pipe;
2. a vacuum tube;
3. a pipe head;
4. a slurry overflow hole; 4-1, a first grouting pipe section; 4-2, a second grouting pipe section; 41. a one-way plug; 42. a rubber reset sleeve;
5. a vacuum pipe section; 51. a vent hole; 52. an isolation net;
6. an isolation capsule sleeve; 6a, isolating the pipe section; 61. a sealing band; 62. an expansion sleeve;
7. a barrel is arranged inside; 71. a gun head; 72. an isolation piston; 73. a connecting pipe; 74. a quick coupling; 75. a communicating hole;
8. a vacuum pumping barrel; 81. a liquid storage barrel; 82. a vacuum pump; 83. a negative pressure gauge; 84. a liquid inlet valve; 85. a drain valve; 86. and (4) an observation window.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.
The invention discloses a step-by-step sectional type tunnel curtain grouting construction pipe set, which comprises a plurality of groups of construction kits as shown in figure 1, wherein each construction kit comprises two grouting pipes 1 and a vacuum pipe 2, and the construction kits are used for being inserted into grouting holes with different depths; the lengths of the two grouting pipes 1 are not equal. Wherein: each grouting pipe 1 is formed by sequentially connecting a plurality of first grouting pipe sections 4-1.
As shown in fig. 3 and 5, the vacuum tube 2 is composed of a plurality of vacuum tube segments 5 and a plurality of isolation tube segments 6a which are communicated with each other, the vacuum tube segment 5 is connected with the foremost end, and the middle part of each vacuum tube segment 5 is communicated with the grouting hole; each isolation pipe section 6a is of a double-layer sleeve structure and comprises a second grouting pipe section 4-2 and an isolation bag sleeve 6 which are sleeved together from inside to outside, and two ends of the isolation bag sleeve 6 are attached to and sealed with outer walls of two ends of the second grouting pipe section 4-2 to form an expansion bag cavity with two closed ends; as shown in fig. 2, a tapered closed pipe head 3 is connected to each of the front ends of the first grouting pipe section 4-1 and the vacuum pipe section 5 at the foremost end, and the front end of the pipe head 3 is closed. When inserting slip casting pipe 1 and vacuum tube 2 in the injected hole, the setting of toper tube head 3 more makes things convenient for the guide to move ahead, is difficult to damaged. As shown in FIG. 4, a vent hole 51 is arranged in the middle of the vacuum pipe section 5, and an isolation net 52 is wrapped on the outer side of the pipe wall for preventing large-particle silt from entering the vacuum pipe section.
Each isolation capsule sleeve 6 comprises an expansion sleeve 62 and two sealing hoops 61, which are both in a hollow cylinder structure, wherein the sealing hoops 61 are made of PVC hard plastic material, the expansion sleeve 62 is made of high-elasticity rubber material, the sealing hoops 61 are positioned on the expansion sleeve 62, and the ends of the sealing hoops 61 are tightly bonded together through hot processing to form the integral hollow isolation capsule sleeve 6 with the sealing hoops 61 at the two ends and the expansion sleeve 62 in the middle.
The inner diameter of the sealing hoop 61 is matched with the outer diameter of the second grouting pipe section 4-2, the sealing hoop can be sleeved outside the second grouting pipe section 4-2 to slide, the isolating bag sleeve 6 is sleeved from one end of the second grouting pipe section 4-2 to finally wrap the second grouting pipe section 4-2, glue is smeared on the outer diameters of two ends of the second grouting pipe section 4-2, and the sealing hoop 61 is bonded and fixed to enable the sealing hoop not to slide and form sealing.
As shown in fig. 3, the first grouting pipe section 4-1 and the second grouting pipe section 4-2 are both made of PVC hard plastic material, each full pipe section is a through uniform inner diameter, one end of the pipe is provided with an external thread, and the other end of the pipe is provided with an internal thread for the combined connection of each pipe section. One section of the middle part of each of the first grouting pipe section 4-1 and the second grouting pipe section 4-2 is a small-diameter section, a rubber reset sleeve 42 is sleeved on the small-diameter section, and the small-diameter section is arranged to limit the sliding of the rubber reset sleeve 42. And for the second grouting pipe section 4-2, the overall outer diameter of the second grouting pipe section 4-2 after the rubber reset sleeve 42 is installed is reduced, so that the isolation capsule sleeve 6 can be conveniently sleeved in a subsequent process.
On the outer wall of the small-diameter section, a plurality of grout overflow holes 4 are circumferentially arranged at intervals, each grout overflow hole 4 is in a circular truncated cone shape with a large outer end and a small inner end from outside to inside, a one-way plug 41 consistent with the shape of each grout overflow hole 4 is arranged in each grout overflow hole 4, and each one-way plug 41 is made of rubber. Under the grouting pressure, each one-way plug 41 can move outwards in the grout overflow hole 4, and the outer end jacks up the rubber reset sleeve 42 to form a grout overflow channel with two communicated ends; when no grouting pressure exists, the rubber reset sleeve 42 contracts to close the grout overflow channel;
in the isolation pipe section 6a, the slurry overflow channel is communicated with the expansion bag cavity, slurry fills the expansion bag cavity, the outer wall of the expansion bag cavity is attached to block the grouting hole of the section where the expansion bag cavity is located, the grouting hole sections where the two vacuum pipe sections 5 which are arranged at intervals are isolated, and the grouting hole is divided into a plurality of isolation sections.
The invention also discloses a step-by-step sectional type tunnel curtain grouting construction device, which comprises the step-by-step sectional type tunnel curtain grouting construction pipe group, as shown in fig. 6, and further comprises a plurality of built-in gun pipes 7, wherein each built-in gun pipe 7 is used for being inserted into a corresponding vacuum pipe 2 and a corresponding grouting pipe 1, and each built-in gun pipe 7 comprises: the connecting pipes 73 are used for being inserted into the corresponding pipes, the front ends of the connecting pipes face the pipe bottoms, and the connecting pipes can move back and forth in the pipes; the connecting pipe 73 is connected with each other through a quick connector 74; the gun head 71 is a hard pipe body and is detachably arranged at the front end of the connecting pipe 73; the front end section is solid and closed, and the pipe body in the middle section is provided with a plurality of communicating holes 75.
The number of the isolation pistons 72 is two, the isolation pistons are sleeved at the front end and the rear end of the gun head 71 at intervals, namely, the part of the gun head 71, which is provided with the communicating hole 75, is positioned between the two isolation pistons 72, the outer diameter of each isolation piston 72 is consistent with the inner diameter of the pipe into which the isolation piston is inserted, and the isolation pistons 72 are tightly attached to the pipe wall so as to seal the vacuum pipe 2 or the grouting pipe 1 section positioned between the isolation pistons 72 into a closed space, and the isolation pistons 72 move along with the movement of the connecting pipe 73 so as to sequentially seal different sections of the vacuum pipe 2 or the grouting pipe 1 into closed spaces;
the built-in gun tube 7 is used for sequentially injecting water or grout into the first grouting pipe section 4-1, sequentially grouting into each isolation pipe section 6a and vacuumizing each vacuum pipe section 5.
As shown in FIG. 7, the stepped sectional type grouting apparatus for a tunnel curtain further comprises a vacuum suction device for connecting with the built-in gun tube 7 inserted into the vacuum tube 2.
The vacuum pumping device comprises a vacuum pumping barrel 8, the vacuum pumping barrel 8 comprises a liquid storage barrel 81 which is a vertically placed steel sealing barrel, the barrel can resist the external atmospheric pressure without deformation when vacuum is formed in the barrel, and the volume of the barrel is not less than 1m3For temporarily storing the pumped liquid; a vacuum pump 82 and a negative pressure gauge 83 are arranged at the upper end of the liquid storage barrel 81; the vacuum pump 82 is communicated with the interior of the liquid storage barrel 81 and is used for pumping air in the barrel to form vacuum negative pressure. The negative pressure gauge 83 is communicated with the interior of the liquid storage barrel 81 and is used for monitoring the vacuum degree in the barrel.
The upper part and the lower part of the side wall of the liquid storage barrel 81 are respectively provided with a liquid inlet pipe and a liquid outlet pipe which are communicated with the inner cavity of the barrel, and a liquid inlet valve 84 is arranged on the liquid inlet pipe; a drain valve 85 is installed on the drain pipe, and the drain valve 85 is a large-diameter ball valve. When water is injected to wash the surrounding rock, the liquid inlet pipe is connected with the rear end of the connecting pipe 73, and water flow and fine particles are sucked into the liquid storage barrel 81.
An observation window 86 is arranged on the side wall of the liquid storage barrel 81 and in the area where the liquid inlet pipe is located, and is used for observing the color, the property and the flow rate of liquid flowing into the barrel from the liquid inlet valve 84 and the height of the liquid level in the barrel.
The invention discloses a step-by-step sectional type tunnel curtain grouting construction method, which uses the step-by-step sectional type tunnel curtain grouting construction device and comprises the following steps:
step one, grouting holes are formed:
on the grout stop wall, taking the center of the tunnel as the center of a circle, arranging a plurality of radial extensions at intervals along the direction of contour lines of the vault and the side walls of the tunnel, designing three orifices of grouting holes at the inner side, the middle part and the outer side at intervals from inside to outside on each same radial extension, and designing the angle and the depth of each grouting hole; selecting a radially extending grouting hole orifice to be used as a grouting hole, and obtaining the final hole position of the grouting hole in the surrounding rock; wherein: the final holes of the middle and outer grouting holes are positioned at the cross section of the terminal of the section to be reinforced of the tunnel, and the final hole of the inner grouting hole is positioned at the cross section of the middle of the section to be reinforced of the tunnel. The included angle between each two adjacent radial extensions is the same, and as shown in fig. 9, the grouting holes are arranged as follows: the inner side, the middle and the outer side grouting holes are all multiple in orifices, the number of the orifices is the same, and the orifices of the inner side, the middle and the outer side grouting holes are all arranged in an arch shape along the contour lines of the vault and the side walls of the tunnel.
The method is characterized in that three grouting hole orifices on the inner side, the middle side and the outer side on the same radial extension are used as a group, the length of the circulating grouting reinforcement section is 20m, the cross section of a tunnel at the end point of the reinforcement section is a final length cross section, the cross section of the tunnel at the middle (namely 10m) of the length of the circulating grouting reinforcement section is a middle cross section, the end hole position of the inner side hole is an intersection point of a radial plane of the group and a tunnel excavation contour line in the final length cross section, the end hole position of the middle hole is an intersection point of a radial plane and a radial reinforcement range contour line in the final length cross section, and the end hole position of the outer side grouting hole is an intersection point of a reinforcement range contour line in the radial plane and the middle cross section of the group.
Step two, setting vacuum isolation sections in sections:
the vacuum pipe 2 is inserted into the inner grouting hole to the bottom of the hole, the second grouting pipe section 4-2 at the bottom of the hole sequentially retreats to the end of the hole, grout is sequentially injected into each second grouting pipe section 4-2, the grout overflows the rubber reset sleeve 42 through the one-way plug 41 under the action of grouting pressure and enters the expansion bladder cavity, and the isolation bladder sleeve 6 expands to plug the grouting hole at the section, so that the plugging of the grouting hole at each isolation pipe section 6a is completed.
The specific process of the second step is as follows: inserting a built-in gun tube 7 into the vacuum tube 2, wherein the gun head 71 is positioned at the second grouting tube section 4-2 at the bottom of the hole, and the orifice end of the built-in gun tube 7 is connected with a grouting device; the gun head 71 sequentially retreats from the bottom of the hole to the orifice and is sequentially positioned in each second grouting pipe section 4-2; in each second grouting pipe section 4-2, two isolation pistons 72 are tightly attached to the inner wall of the second grouting pipe section 4-2, and a closed space is formed between the two isolation pistons 72; in each second grouting pipe section 4-2, grout is injected by the gun head 71, the grout is cement-water glass double-grout, under the action of grouting pressure, the grout enters and fills the expansion bladder cavity, the isolation bladder sleeve 6 expands to plug the grouting hole of the section where the isolation bladder sleeve is located, so that the grouting hole outside the vacuum pipe 2 forms a plurality of sections which are isolated from each other, namely the grouting hole sections where two vacuum pipe sections 5 which are arranged alternately are isolated.
The purpose of the subsection that the slip casting hole outside the vacuum tube 2 formed the mutual isolation of multistage lies in, when the vacuum suction drainage, can divide into the multistage with the gravitation source, draws close distance with each section slip casting water source, strengthens the vacuum pumping effect, makes the country rock in the full length within range can not appear losing the leakage region, also is convenient for better control slip casting construction overall process's influence scope, avoids the material extravagant.
Step three, injecting water to wash the surrounding rock, and forming a water flow channel in the surrounding rock:
the grouting pipes 1 in the middle and the outer grouting holes are respectively inserted with a built-in gun barrel 7 to the bottom, the vacuum pipe 2 is inserted with a built-in gun barrel 7 to the bottom, and the orifice end of the vacuum pipe is connected with a vacuum suction device; synchronously backing the two built-in gun pipes 7 of the middle grouting pipe 1 and the vacuum pipe 2 to the orifice end in sections, and injecting clear water into the first grouting pipe section 4-1 in each section; pumping each vacuum pipe section 5 into a negative pressure state, forming a negative pressure region between the vacuum pipe section 5 and the grouting holes, guiding pressurized clean water to wrap fine particles to flow to the negative pressure region, flowing into the vacuum pipe section 5 and discharging the fine particles out of the vacuum pipe 2, and forming a plurality of water flow channels in surrounding rocks between the middle grouting holes and the inner side grouting holes in the flowing process of the clean water; and repeating the operation to form a plurality of water flow channels in the surrounding rock between the outer side grouting holes and the inner side grouting holes. The formed water flow channel is used as a channel for subsequent grouting and is formed by washing out a certain amount of stratum fine particles, and subsequent grouting is used for filling and replacing, so that the disturbance to the stratum is relatively small, and the safety of surrounding buildings (structures) is ensured.
The concrete process of the third step is as follows:
inserting a built-in gun barrel 7 into the middle grouting pipe 1, enabling the gun head 71 to reach a first grouting pipe section 4-1 at the bottom, sequentially retreating the gun head 71 from the first grouting pipe section 4-1 at the bottom end to the orifice end, sequentially and respectively locating in each first grouting pipe section 4-1, and enabling two isolation pistons 72 to be tightly attached to the inner wall of the first grouting pipe section 4-1 in each first grouting pipe section 4-1 to form a closed space between the two isolation pistons 72; injecting water into the built-in gun barrel 7, and injecting the water into a closed space in the first grouting pipe section 4-1 through a gun head 71; as the water injection pressure rises, the water flow backs up the one-way plug 41 and the rubber reset sleeve 41 and is injected into the surrounding rock, and a water outlet source with pressure is formed at the point.
Meanwhile, the vacuum suction device is connected with the built-in gun barrel 7 in the vacuum tube 2, the gun head 7 is positioned in the vacuum tube section 5 at the bottom of the hole, and the gun head 71 sequentially retreats towards the orifice end and is sequentially positioned in each vacuum tube section 5 respectively in synchronization with water injection; in each vacuum pipe section 5, a closed space is formed between two isolation pistons 72 and the section of the vacuum pipe section 5 provided with the vent hole 51, a liquid inlet pipe of the vacuum pumping and discharging barrel 8 is connected with the built-in gun barrel 7, the vacuum pump 82 is started to pump and discharge, the vacuum negative pressure is controlled to be about 1MPa according to the indication number of the negative pressure meter 83, and the position of the gun head 71 is communicated with the surrounding rock through the vent hole 51 and the isolation net 52. The surrounding rock at the grouting hole of the section forms a vacuum negative pressure source, clean water output by the gun head 71 is guided to flow to the surrounding rock in a single direction, meanwhile, water flow is utilized for wrapping, some fine particles pass through the separation net 52 to be sucked into the built-in gun barrel 7 and finally flow into the vacuum exhaust barrel 8, a plurality of water flow channels are formed in the surrounding rock between the middle grouting hole and the inner side grouting hole, and the water flow channels are further enlarged and unobstructed along with continuous loss of the fine particles in the surrounding rock.
Focusing on the flow of water into the reservoir 81 through the inlet valve 84 through the observation window 86, when the water is relatively clear and free of fine particles such as silt, and the flow rate of the pumped water exceeds 1/2 of the flow rate of the injected water, a sufficiently clear flow path is formed in the formation. When the subsection moves backwards, the grouting machine is closed, water injection is suspended, and the liquid inlet valve 84 of the vacuum exhaust barrel 8 is closed. The inner barrel 7 is pulled towards the port to the next adjacent section of pipe, forming a plurality of water flow channels in the surrounding rock between the outer and inner grout holes. As shown in fig. 8, 10 and 11.
During the operation, the observation window 86 is used for observing, if the water level in the liquid storage barrel 81 exceeds 2/3, the water injection and pumping operation is suspended, the liquid discharge valve 85 is opened to discharge water and silt, then the liquid discharge valve 85 is closed, and the pumping operation is resumed.
Injecting chemical grout to form primary grout veins:
as shown in fig. 12, from the first grouting pipe segment 4-1 at the bottom of the grouting pipe 1 in the middle and outside grouting holes, respectively, it is sequentially stepped back toward the orifice end, and chemical grout is sequentially injected into each section of grouting pipe; meanwhile, in synchronization with the injection of chemical grout, the vacuum pipe sections 5 at the bottom of the hole are sequentially and sectionally retreated, each vacuum pipe section 5 is vacuumized, and then the chemical grout in the grouting pipe section on the same cross section as the vacuum pipe section 5 flows into and fills a water flow channel in the surrounding rock and is solidified to form primary grout veins. In the third step, by utilizing the sectional retreating type under-pressure grouting and vacuum negative pressure suction, the surrounding rock is fully filled with chemical grout with low strength and slightly poor diffusivity along a water flow channel, an extended network-shaped grout vein is formed after hardening, meanwhile, the grout vein and the surrounding rock form a contact surface, but the mechanical property is weak, and cement grout needs to be injected for better stability of the surrounding rock.
As shown in fig. 13, after the chemical grout is solidified to form a primary grout vein, the cement grout is injected to form a composite grout vein, specifically: and injecting the cement slurry into a channel filled with the chemical slurry from the grouting pipe 1 in the middle grouting hole to the grouting pipe 1 in the outer grouting hole by adopting a method for injecting the chemical slurry to form a composite slurry vein coated by the cement slurry and the primary slurry vein. The cement slurry has high strength and poor diffusivity, when the cement slurry is contacted with the surface of the chemical slurry vein, the cleavage grouting is carried out on the surface of the chemical slurry vein, the fluidity is good, the grouting amount is improved, and the surrounding rock is extruded and compacted in the surrounding rock to form the composite network-shaped slurry vein externally wrapped with the cement slurry vein and internally sandwiched with the chemical slurry vein.
The concrete process of the step four is as follows:
inserting a built-in gun barrel 7 into a grouting pipe 1 in a middle grouting hole, wherein a gun head 71 is positioned at a first grouting pipe section 4-1 at the bottom end, two isolation pistons 72 are tightly attached to the inner wall of the first grouting pipe section 4-1, and a closed space is formed between the two isolation pistons 72; meanwhile, another built-in gun tube 7 is inserted into the vacuum tube 2, the gun head 71 is positioned at the vacuum tube section 5 at the bottom end, and in each vacuum tube section 5, a closed space is formed between two isolation pistons 72 and the section of the vacuum tube section 5 provided with the vent hole 51;
the two built-in gun barrels 7 drive the gun heads 71 to synchronously and sequentially retreat to the orifice ends from the hole bottoms to the orifices, and the following operations are sequentially carried out in the first grouting pipe sections 4-1 and the vacuum pipe sections 5 of each section: and injecting chemical grout into the first grouting pipe section 4-1, simultaneously sucking by a vacuum suction device, vacuumizing the closed space, enabling the chemical grout to flow into the water flow channel, and sucking the grout into the vacuum suction device when the water flow channel is filled with the chemical grout, so that grouting of the chemical grout is finished. Specifically, the liquid flowing into the liquid storage barrel 81 through the liquid inlet valve 84 is focused through the observation window 86, and when the chemical slurry flows out, the water flow channel of the stratum is filled with the chemical slurry. During operation, if the water level in the liquid storage barrel 81 exceeds 2/3 by observation through the observation window 86, grouting and pumping are suspended, the drainage valve 85 is opened to drain water and waste slurry, and then the drainage valve 85 is closed to resume operation.
And step five, repeating the step one to the step four to finish the grouting of the tunnel curtain. And finally, forming an arch-shaped reinforced area along the outer area of the tunnel excavation contour line.
In the invention, the following modes are adopted: setting an isolation section, injecting water, injecting chemical slurry and injecting slurry, and distributing sectional type tunnel curtain slurry injection, wherein after the chemical slurry is solidified, a slurry stone body and a stratum form a contact surface, but because the strength of the chemical slurry stone body is very low (the unconfined compressive strength is about 0.5MPa), the surrounding rock reinforcing effect is poor at the moment, further treatment is needed, and then injecting the cement slurry to form a composite slurry vein, specifically: and injecting the cement slurry into the channel with the injected chemical slurry by adopting a method of injecting the chemical slurry to form a composite slurry vein coated by the cement slurry and the primary slurry vein. After the chemical grout is injected, the contact surface of the chemical grout stone body and the stratum becomes a weak surface, and the cement grout generates stress concentration along the surface under the action of grouting pressure, so that splitting and flowing are easy to occur, the resistance of an original stratum is overcome, the injection amount of the grout is greatly improved, a composite grout vein externally wrapped with a grout vein and internally sandwiched with a chemical grout vein is formed, and the grouting reinforcement of the stratum is finished.

Claims (10)

1. A step-by-step sectional type tunnel curtain grouting construction pipe group is characterized by comprising a plurality of groups of construction kits, wherein each construction kit comprises two grouting pipes (1) and a vacuum pipe (2) and is used for being inserted into grouting holes with different depths; wherein:
each grouting pipe (1) is formed by sequentially connecting a plurality of first grouting pipe sections (4-1);
the vacuum pipe (2) is formed by connecting a plurality of vacuum pipe sections (5) and a plurality of isolation pipe sections (6a) which are communicated at intervals, the vacuum pipe section (5) is connected at the foremost end, and the middle part of each vacuum pipe section (5) is communicated with the grouting hole; each isolation pipe section (6a) is of a double-layer sleeve structure and comprises a second grouting pipe section (4-2) and an isolation bag sleeve (6), wherein the second grouting pipe section (4-2) and the isolation bag sleeve are sleeved together, and two ends of the isolation bag sleeve (6) are attached to and sealed with the outer walls of two ends of the second grouting pipe section (4-2) to form an expansion bag cavity with two closed ends; the front ends of the first grouting pipe section (4-1) and the vacuum pipe section (5) at the foremost end are closed;
the middle sections of the first grouting pipe section (4-1) and the second grouting pipe section (4-2) are small-diameter sections, and rubber reset sleeves (42) are sleeved on the small-diameter sections; a plurality of slurry overflow holes (4) are circumferentially arranged on the outer wall of the small-diameter section at intervals, each slurry overflow hole (4) is in a circular truncated cone shape with a large outer end and a small inner end from outside to inside, and a one-way plug (41) which is consistent with the shape of each slurry overflow hole (4) is arranged in each slurry overflow hole; under the grouting pressure, each one-way plug (41) can move outwards in the grout overflow hole (4), and the outer end of the one-way plug jacks up the rubber reset sleeve (42) to form a grout overflow channel with two communicated ends, which is communicated with the grouting hole; when no grouting pressure exists, the rubber reset sleeve (42) contracts to close the slurry overflow channel;
in the isolation pipe section (6a), a slurry overflow channel is communicated with the expansion bladder cavity, slurry fills the expansion bladder cavity, the outer wall of the expansion bladder cavity is attached to seal the grouting hole of the section where the expansion bladder cavity is located, the grouting hole sections where two vacuum pipe sections (5) which are arranged at intervals are isolated, and the grouting hole is divided into a plurality of isolation sections.
2. A sectional type grouting construction device for a tunnel curtain, which comprises the sectional type grouting construction pipe set for the tunnel curtain as claimed in claim 1, and further comprises a plurality of built-in gun pipes (7), wherein each built-in gun pipe (7) is used for being inserted into a corresponding vacuum pipe (2) and a corresponding grouting pipe (1), and each built-in gun pipe (7) comprises:
the connecting pipe (73) is of a multi-section detachably connected pipe body structure, is inserted into the corresponding pipe, has the front end facing the pipe bottom, and can move back and forth in each pipe;
the gun head (71) is a hard pipe body and is detachably arranged at the front end of the connecting pipe (73); a section of the front end of the tube body is solid and closed, and a plurality of communicating holes (75) are formed in the tube body at the middle section;
the isolation pistons (72) are sleeved at the front end and the rear end of the gun head (71) at intervals, the outer diameters of the isolation pistons are consistent with the inner diameters of the inserted pipes, the isolation pistons are tightly attached to the pipe walls, so that the sections of the vacuum pipes (2) or the grouting pipes (1) positioned between the isolation pistons (72) are sealed into closed spaces, the isolation pistons (72) move along with the movement of the connecting pipes (73), and different sections of the vacuum pipes (2) or the grouting pipes (1) are sequentially sealed into closed spaces;
the built-in gun tube (7) is used for sequentially injecting water or grout into the first grouting pipe section (4-1), sequentially grouting into each isolation pipe section (6a) and vacuumizing each vacuum pipe section (5).
3. A stepwise segmented tunnel curtain grouting construction device according to claim 2, further comprising a vacuum suction device for connecting with a built-in gun tube (7) inserted into the vacuum tube (2);
the vacuum pumping device comprises a vacuum pumping barrel (8), wherein the vacuum pumping barrel (8) comprises a liquid storage barrel (81) which is a vertically-arranged steel sealed barrel and is used for temporarily storing pumped liquid; a vacuum pump (82) and a negative pressure meter (83) are arranged at the upper end of the liquid storage barrel (81);
the upper part and the lower part of the side wall of the liquid storage barrel (81) are respectively provided with a liquid inlet pipe and a liquid outlet pipe which are communicated with the inner cavity of the barrel, and a liquid inlet valve (84) is arranged on the liquid inlet pipe; a drain valve (85) is arranged on the drain pipe; when water is injected to wash the surrounding rock, the liquid inlet pipe is connected with the rear end of a connecting pipe (73), and water flow and fine particles are pumped into the liquid storage barrel (81);
an observation window (86) is arranged on the side wall of the liquid storage barrel (81) and in the area where the liquid inlet pipe is located and used for observing the color, the property and the flow of liquid flowing into the barrel from the liquid inlet valve (84) and the height of the liquid level in the barrel.
4. A stepwise segmented tunnel curtain grouting construction device according to claim 3, wherein the lengths of the two grouting pipes (1) are not equal.
5. A step-by-step sectional type tunnel curtain grouting construction method, characterized in that a step-by-step sectional type tunnel curtain grouting construction device according to any one of claims 1 to 5 is used, and the construction method is as follows:
step one, grouting holes are formed:
on the grout stop wall, taking the center of the tunnel as the center of a circle, arranging a plurality of radial extensions at intervals along the direction of contour lines of the vault and the side walls of the tunnel, designing three orifices of grouting holes at the inner side, the middle part and the outer side at intervals from inside to outside on each same radial extension, and designing the angle and the depth of each grouting hole; selecting a radially extending grouting hole orifice to be used as a grouting hole, and obtaining the final hole position of the grouting hole in the surrounding rock; wherein: the final holes of the middle and outer grouting holes are positioned at the cross section of the terminal of the section to be reinforced of the tunnel, and the final hole of the inner grouting hole is positioned at the cross section of the middle of the section to be reinforced of the tunnel;
step two, setting vacuum isolation sections in sections:
inserting a vacuum tube (2) into the inner grouting hole to the bottom of the hole, sequentially retreating from the second grouting tube section (4-2) at the bottom of the hole to the orifice, sequentially injecting grout into each second grouting tube section (4-2), enabling the grout to overflow the rubber reset sleeve (42) through the one-way plug (41) under the action of grouting pressure and enter the expansion bladder cavity, and expanding and plugging the grouting hole at the section by the isolation bladder sleeve (6) to finish plugging the grouting hole at each isolation tube section (6 a);
step three, injecting water to wash the surrounding rock, and forming a water flow channel in the surrounding rock:
the grouting pipes (1) in the middle and the outer grouting holes are respectively inserted with an inner gun pipe (7) to the bottom, an inner gun pipe (7) is inserted in the vacuum pipe (2) to the bottom, and the port end of the inner gun pipe is connected with a vacuum suction device; synchronously retreating the two built-in gun pipes (7) of the middle grouting pipe (1) and the vacuum pipe (2) to the orifice end in sections, and injecting clear water into the first grouting pipe section (4-1) in each section; pumping each vacuum pipe section (5) to be in a negative pressure state, forming a negative pressure area between the vacuum pipe section (5) and the grouting holes, guiding pressurized clean water to wrap fine particles to flow to the negative pressure area, flowing into the vacuum pipe section (5), and discharging to the outside of the vacuum pipe (2), wherein a plurality of water flow channels are formed in surrounding rocks between the middle grouting holes and the inner side grouting holes in the flowing process of the clean water;
repeating the operation, and forming a plurality of water flow channels in the surrounding rock between the outer side grouting holes and the inner side grouting holes;
injecting chemical grout to form primary grout veins:
sequentially and sectionally retreating from a first grouting pipe section (4-1) at the bottom of the grouting pipe (1) in the middle grouting hole and the outer grouting hole to the orifice end, and sequentially injecting chemical slurry into the grouting pipes; meanwhile, in synchronization with the injection of chemical grout, the chemical grout sequentially retreats from the vacuum pipe section (5) at the bottom of the hole in a segmented manner, and the vacuum pipe section (5) at each segment is vacuumized, so that the chemical grout in the grouting pipe section on the same cross section as the vacuum pipe section (5) flows into and fills a water flow channel in the surrounding rock and is solidified to form primary grout veins;
and fifthly, repeating the first step to the fourth step to finish the grouting of the tunnel curtain.
6. The step-by-step segmented tunnel curtain grouting construction method of claim 5, wherein in the fourth step, after the primary slurry veins are formed, cement slurry is injected to form composite slurry veins, and specifically: and injecting the chemical grout into the channel with the injected chemical grout to form a composite grout vein coated with the cement grout and the primary grout vein.
7. The step-by-step segmented tunnel curtain grouting construction method of claim 6, wherein the grouting hole orifices are arranged as follows: the inner side, the middle and the outer side grouting holes are all multiple in orifices, the number of the orifices is the same, and the orifices of the inner side, the middle and the outer side grouting holes are all arranged in an arch shape along the contour lines of the vault and the side walls of the tunnel.
8. The step-by-step segmented tunnel curtain grouting construction method as claimed in claim 7, wherein the specific process of the second step is as follows: inserting a built-in gun tube (7) into the vacuum tube (2), wherein the gun head (71) is positioned on a second grouting tube section (4-2) at the bottom of the hole, and the orifice end of the built-in gun tube (7) is connected with a grouting device; the gun heads (71) sequentially retreat to the orifices from the bottom of the hole and are sequentially positioned in the second grouting pipe sections (4-2); in each second grouting pipe section (4-2), two isolation pistons (72) are tightly attached to the inner wall of the second grouting pipe section (4-2), and a closed space is formed between the two isolation pistons (72); in each second grouting pipe section (4-2), grout is injected by a gun head (71), and enters the expansion bladder cavity under the action of grouting pressure.
9. The step-by-step segmented tunnel curtain grouting construction method as claimed in claim 8, wherein the concrete process of the third step is as follows:
inserting a built-in gun barrel (7) into the middle grouting pipe (1), enabling a gun head (71) to reach a first grouting pipe section (4-1) at the bottom, and sequentially retreating the gun head (71) from the first grouting pipe section (4-1) at the bottom to be sequentially positioned in each first grouting pipe section (4-1) respectively, wherein in each first grouting pipe section (4-1), two isolation pistons (72) are tightly attached to the inner wall of the first grouting pipe section (4-1), and a closed space is formed between the two isolation pistons (72); injecting water into the built-in gun barrel (7), injecting the water into the first grouting pipe section (4-1) through the gun head (71), and ejecting the one-way plug (41) to enter the grouting hole through the grout overflow hole (4);
meanwhile, a vacuum suction device is connected with a built-in gun barrel (7) in the vacuum tube (2), the gun head (7) is positioned in the vacuum tube section (5) at the bottom of the hole, and when clean water is injected, the gun head (71) sequentially retreats towards the orifice end and is sequentially positioned in each vacuum tube section (5) respectively; in each vacuum pipe section (5), a closed space is formed between the two isolation pistons (72) and the vacuum pipe section (5) provided with the vent holes (51), a vacuum suction device sucks the vacuum pipe section to form a negative pressure area between the closed space and the grouting holes, pressurized clean water at the first grouting pipe section (4-1) of the corresponding section is guided to wrap fine particles under pressure and flow to the negative pressure area and flow into the vacuum pipe section (5) and is discharged out of the vacuum pipe (2), and a plurality of water flow channels are formed in surrounding rocks between the grouting holes at the inner side of the middle grouting hole in the flowing process of the clean water.
10. The step-by-step segmented tunnel curtain grouting construction method as claimed in claim 9, wherein the concrete process of the fourth step is as follows:
inserting a built-in gun barrel (7) into a grouting pipe (1) in a middle grouting hole, wherein a gun head (71) is positioned at a first grouting pipe section (4-1) at the bottom end, two isolation pistons (72) are tightly attached to the inner wall of the first grouting pipe section (4-1), and a closed space is formed between the two isolation pistons (72); meanwhile, the other built-in gun tube (7) is inserted into the vacuum tube (2), the gun head (71) is positioned at the vacuum tube section (5) at the bottom end, and in each vacuum tube section (5), a closed space is formed between the two isolation pistons (72) and the section of the vacuum tube section (5) provided with the vent hole (51);
the two built-in gun pipes (7) drive the gun heads (71) to synchronously and sequentially retreat to the orifice end from the bottom of the hole to the orifice, and the following operations are sequentially carried out in the first grouting pipe section (4-1) and the vacuum pipe section (5) of each section: injecting chemical grout into the first grouting pipe section (4-1), simultaneously sucking by a vacuum suction device, vacuumizing the closed space, enabling the chemical grout to flow into the water flow channel, and sucking the grout into the vacuum suction device when the water flow channel is filled with the chemical grout, so that grouting of the chemical grout is finished;
by adopting the above operation, cement slurry grouting is completed.
CN202111598849.XA 2021-12-24 2021-12-24 Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method Pending CN114135321A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111598849.XA CN114135321A (en) 2021-12-24 2021-12-24 Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111598849.XA CN114135321A (en) 2021-12-24 2021-12-24 Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method

Publications (1)

Publication Number Publication Date
CN114135321A true CN114135321A (en) 2022-03-04

Family

ID=80383199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111598849.XA Pending CN114135321A (en) 2021-12-24 2021-12-24 Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method

Country Status (1)

Country Link
CN (1) CN114135321A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115538414A (en) * 2022-11-03 2022-12-30 华北有色工程勘察院有限公司 Double-liquid grouting device for deep hole of flowing water curtain
CN115962000A (en) * 2022-12-12 2023-04-14 中铁西北科学研究院有限公司 Sleeve valve type negative pressure moisture absorption system capable of controlling deformation of swelling rock tunnel bottom drum

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115538414A (en) * 2022-11-03 2022-12-30 华北有色工程勘察院有限公司 Double-liquid grouting device for deep hole of flowing water curtain
CN115538414B (en) * 2022-11-03 2023-08-04 华北有色工程勘察院有限公司 Deep hole double-liquid grouting device for dynamic water curtain
CN115962000A (en) * 2022-12-12 2023-04-14 中铁西北科学研究院有限公司 Sleeve valve type negative pressure moisture absorption system capable of controlling deformation of swelling rock tunnel bottom drum
CN115962000B (en) * 2022-12-12 2023-09-19 中铁西北科学研究院有限公司 Sleeve valve type negative pressure moisture absorption system capable of controlling deformation of bottom drum of expanded rock tunnel

Similar Documents

Publication Publication Date Title
CN114135321A (en) Step-by-step sectional type tunnel curtain grouting construction pipe set, device and construction method
CN106761835B (en) A kind of Karst Tunnel leak segmenting slip casting construction method
CN100510274C (en) Construction method of enclosing level rotary-jet pile hole-mouth using double-liquid slip jection method
WO2017000622A1 (en) Storage-type precise quantitative injection system for injection of underground oil or gas well operating agent and injection method thereof
CN110259383B (en) Advancing drilling and grouting integrated device and using method
CN105350953A (en) Measuring method for coal seam gas pressure in complicated geological condition
CN105350519A (en) Advanced pre-grouting device suitable for shallow-buried tunnel construction in sand soil layer and construction process
CN105888673A (en) Deep-hole plastic pipe high-pressure grouting anti-explosion device in soft water-rich surrounding rock and operation method
CN111549757B (en) Grouting reinforcement method suitable for soft filler karst cave
CN107524455A (en) Multistage densification formula mini-valve tube and its grouting method
KR102233686B1 (en) Multi-step grouting device and underground grouting construction method using it
CN202730769U (en) Shock tube for grouting by Soletanche method
CN107313472A (en) Pile for prestressed pipe bearing capacity of pile tip test device and method
CN208456572U (en) Packaged type hydraulic fracturing and injection hole sealing integrated apparatus
CN216894429U (en) Step-by-step sectional type tunnel curtain grouting construction device
CN111549756B (en) Grouting reinforcement equipment for karst soft filler
CN112502675A (en) Forward filling tool
CN110529155A (en) A kind of drill bit only starches drilling rod and is segmented retrusive grouting method
CN111155932A (en) Drill bit for high-pressure jet grouting pile machine
CN210509112U (en) Quick slip casting device of segmentation marching type drilling rod, system
CN207161107U (en) Multistage densification formula mini-valve tube
CN109838274A (en) The suitable seam inclination drilling gas controlling device and method taken out after note before a kind of
CN216691379U (en) Vacuum suction device for step-by-step sectional type tunnel curtain grouting
CN110513142A (en) The polyurethane sealing aperture apparatus and its construction method of Underwell anti-injection hole anti-leak
CN210068073U (en) Selective profile control and flooding tubular column for multilayer heterogeneous oil reservoir

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination