CN114069689A - Three-stage topology operation optimization method based on load importance - Google Patents

Three-stage topology operation optimization method based on load importance Download PDF

Info

Publication number
CN114069689A
CN114069689A CN202111136803.6A CN202111136803A CN114069689A CN 114069689 A CN114069689 A CN 114069689A CN 202111136803 A CN202111136803 A CN 202111136803A CN 114069689 A CN114069689 A CN 114069689A
Authority
CN
China
Prior art keywords
load
power
stage
transfer
distribution network
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111136803.6A
Other languages
Chinese (zh)
Inventor
钱钢
章立宗
罗刚
张锋明
金鑫
谢栋
唐志琼
郭勤慧
张文青
金渊文
翟旭
陆献传
赵峰
蒋玮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
Southeast University
Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University, Shaoxing Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical Southeast University
Priority to CN202111136803.6A priority Critical patent/CN114069689A/en
Publication of CN114069689A publication Critical patent/CN114069689A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/381Dispersed generators
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • H02J3/14Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
    • H02J3/144Demand-response operation of the power transmission or distribution network
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/388Islanding, i.e. disconnection of local power supply from the network
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B70/00Technologies for an efficient end-user side electric power management and consumption
    • Y02B70/30Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
    • Y02B70/3225Demand response systems, e.g. load shedding, peak shaving
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S20/00Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
    • Y04S20/20End-user application control systems
    • Y04S20/222Demand response systems, e.g. load shedding, peak shaving

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The embodiment of the application provides a three-stage topology operation optimization method based on load importance, which comprises the steps of collecting operation data of a power distribution network after a fault, and establishing a topology structure for fault identification; establishing a load importance evaluation model according to the power loss charge in the distribution network operation data; searching a distributed power generation device with adjustable power in a distribution network island region, and performing one-stage topology optimization; establishing a two-stage topological optimization model, and carrying out load transfer on the standby feeder line and the distributed power generation device; after load transfer is carried out, if a target substation in an overload operation state exists, a secondary transfer model is established, and the optimal transfer load of the target substation is obtained. The decision of the optimal operation mode of the distribution topology under the fault can be effectively processed, the power supply reliability of the power distribution network is improved, the maintenance mode of the power distribution network can be checked and optimized, the comprehensive analysis of the load of the power distribution network of the cloud platform can be favorably regulated and controlled, and the optimal utilization of the capacity of the power distribution network system can be favorably realized.

Description

Three-stage topology operation optimization method based on load importance
Technical Field
The application relates to the field of network optimization, in particular to a three-stage topology operation optimization method based on load importance.
Background
At present, methods related to topology operation mode optimization when a fault occurs include: the method comprises a load method, a main transformer interconnection transfer method and a comprehensive transfer matrix method, wherein secondary transfer and 'distribution on demand' of overload main transformers in a station are considered to improve the maximum transfer capacity and load balance degree of a distribution network, the topological operation mode is optimized according to the main transformer interconnection relation and an N-1 criterion, and the maximum load recovery amount is used as a target to transfer power failure load to other transformer stations through manual switching-on or distribution automatic switching action to achieve the optimal operation mode of station topology under faults; however, in the optimization process, the load importance and the influence of the access of the distributed energy on the topology optimization are not considered, so that the optimal topology operation mode decision under the fault is influenced.
Disclosure of Invention
The embodiment of the application provides a three-stage topology operation optimization method based on load importance, can effectively process the decision of a topology optimal operation mode under the fault, improves the power supply reliability of a power distribution network, and can check and optimize the maintenance mode of the power distribution network.
Specifically, the three-stage topology operation optimization method based on load importance provided by the embodiment of the present application includes:
s1, collecting operation data of the power distribution network after the fault, and establishing a topological structure for fault identification;
s2, establishing a load importance evaluation model according to the power loss electric charge in the distribution network operation data;
s3, searching a distributed power generation device with adjustable power in a distribution network island region, and performing one-stage topology optimization;
s4, establishing a two-stage topological optimization model, and carrying out load transfer on the spare feeder line and the distributed power generation device;
and S5, after the load transfer is carried out, if the target transformer substation in an overload operation state exists, establishing a secondary transfer model to obtain the optimal transfer load of the target transformer substation.
Optionally, the S1 includes:
collecting the number and positions of a transformer substation, a distribution transformer node, a connection feeder line, a breaker switch and a connection switch in a power distribution network;
constructing a topological structure according to the positions of the transformer substation, the distribution transformer node, the interconnection feeder line, the breaker switch and the interconnection switch, and adjusting the state of each device in the topological structure;
and determining the connection relation between the directly-connected transformer substation and the secondary connected transformer substation according to the adjusted topological structure.
Optionally, the S2 includes:
fitting power failure loss functions of different types of loads by adopting a minimum bisection method, and calculating a weight coefficient of the load by using the power failure loss function according to the load type and the estimated power failure duration, wherein the calculation formula is as follows:
Figure BDA0003282680390000021
in the formula, ωi,tRepresents the weight coefficient, alpha, of the load i at the time of power failure tiAnd betaiThe fitting parameters of the load power failure loss function are determined by the characteristics of the load.
Optionally, the S3 includes:
for power-loss loads L1 and L2, no standby feeder is used for recovering power supply;
the distributed power generation device with continuous power regulation capability operates in an island mode to supply power to power loss loads L1 and L2.
Optionally, the S4 includes:
for the second-stage standby feeder line and the load of the distributed power generation device from grid connection to power loss, the power support of the grid-connected distributed power generation device is considered;
the load transfer result mainly comprises the recovery rate of the power-loss load, a transfer path and transfer time;
after the load transfer is completed, acquiring the load rate of the directly connected transformer substation;
and if the load rate is higher than a preset value, judging that the directly-connected transformer substation is in a dangerous operation state.
Optionally, the S5 includes:
according to the third-stage transfer model, a secondary transfer strategy is adopted, namely, the third-stage optimization is carried out to solve the problem that the load rate of the directly-connected transformer substation is too high;
and updating the load rate of the directly-connected substation in the dangerous operation state according to the optimization result, and repeating the iteration of the second-stage and third-stage optimization until the directly-connected substation in the dangerous operation state disappears or cannot perform secondary transfer.
Has the advantages that:
on one hand, the scheme considers the influence of the load importance degree on the optimization of the topology operation mode, and further improves the feasibility of the topology optimization decision; on the other hand, a three-stage topological operation optimization strategy is provided, normal power supply load on the weak link is transferred to other transformer substations, the power supply recovery amount of the power failure area is increased, the provided topological operation optimization mode can effectively guarantee stable operation of the distribution network system, and the superiority of the topological optimization mode is further improved.
Drawings
In order to more clearly illustrate the technical solutions of the present application, the drawings needed to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present application, and it is obvious for those skilled in the art to obtain other drawings without creative efforts.
Fig. 1 is a flowchart of a three-stage topology operation mode optimization considering load importance according to an embodiment of the present application;
FIG. 2 is a wiring diagram of an example power distribution network;
fig. 3 is a fitted graph of load importance.
Detailed Description
To make the structure and advantages of the present application clearer, the structure of the present application will be further described with reference to the accompanying drawings.
Specifically, the three-stage topology operation optimization method based on load importance according to the embodiment of the present application, as shown in fig. 1, includes:
s1, collecting operation data of the power distribution network after the fault, and establishing a topological structure for fault identification;
s2, establishing a load importance evaluation model according to the power loss electric charge in the distribution network operation data;
s3, searching a distributed power generation device with adjustable power in a distribution network island region, and performing one-stage topology optimization;
s4, establishing a two-stage topological optimization model, and carrying out load transfer on the spare feeder line and the distributed power generation device;
and S5, after the load transfer is carried out, if the target transformer substation in an overload operation state exists, establishing a secondary transfer model to obtain the optimal transfer load of the target transformer substation.
In implementation, when a substation full-stop accident occurs, a load transfer path can be optimized on the basis of considering load importance, the recovery rate of the power failure load is effectively improved on the basis of ensuring the system reliability, on one hand, the influence of the load importance on the optimization of a topological operation mode is considered in the scheme, and the feasibility of a topological optimization decision is further improved; on the other hand, a three-stage topological operation optimization strategy is provided, normal power supply load on the weak link is transferred to other transformer substations, the power supply recovery amount of the power failure area is increased, the provided topological operation optimization mode can effectively guarantee stable operation of the distribution network system, and the superiority of the topological optimization mode is further improved.
The implementation of the invention can effectively process the decision of the optimal operation mode of the distribution topology under the fault, improve the power supply reliability of the power distribution network, check and optimize the maintenance mode of the power distribution network, contribute to the comprehensive analysis of the load of the power distribution network of the regulation and control cloud platform and simultaneously contribute to the optimal utilization of the system capacity of the power distribution network; the method can provide lean planning tools and assessment tools for distribution network planning personnel of a power grid company, provides technical support for improving the reliability of the distribution network, reasonably assessing the supply and delivery capacity of the distribution network in a fault mode and improving the operation benefits of the distribution network, and has great economic and social benefits.
Optionally, the S1 includes:
collecting the number and positions of a transformer substation, a distribution transformer node, a connection feeder line, a breaker switch and a connection switch in a power distribution network;
constructing a topological structure according to the positions of the transformer substation, the distribution transformer node, the interconnection feeder line, the breaker switch and the interconnection switch, and adjusting the state of each device in the topological structure;
and determining the connection relation between the directly-connected transformer substation and the secondary connected transformer substation according to the adjusted topological structure.
In the implementation, taking an actual distribution network in a certain area as an example, as shown in fig. 2 after simplification, the distribution network is composed of 5 substations, 32 distribution nodes, 22 tie feeders, 3 distributed power generation devices (connected to distribution nodes 2, 9 and 11, respectively), 18 breaker switches and 14 tie switches. In order to simulate the actual load fluctuations, the distribution power uses the historical load curve of the distribution transformers in the urban network, assuming that the substation P is 12 pm2SCSA takes place with a load L1-L8All power is lost, wherein switch S5、S9、S12And S14In a closed state and the remaining switches are in an open state.
Step a: and collecting the running state and running data of the distribution network after the fault, wherein the running state and running data comprise a grid structure, a topological running mode, the power loss load, the feeder line load rate, the transformer substation load rate and the like.
In this case, substation P2The SCSA occurs, so the direct-connected substation and the secondary-connected substation under the SCSA can be determined according to the contact relationship between the substations in fig. 2, with the following results:
Figure BDA0003282680390000061
Figure BDA0003282680390000062
in the formula, Pdc-P2And Psc-P2Respectively represent P2And generating a direct-connected transformer substation and a corresponding secondary-connected transformer substation under the SCSA. Furthermore, in the power distribution network of FIG. 2 for recovering L1-L8The STP and MTP sets of (A) are as follows:
FSTP={F(1)→F(2),F(3)→F(30),F(7,8)→F(9,12),F(20)→F(29),F(15,19)}
FMTP={{F(4)→F(31,32),F(4)→F(21,24)},{F(5,6)→F(13),F(5,6)→F(17)}{F(18,27)→F(22),F(18,27)→F(23,28)}}
in the formula, F(i)Representing the line containing load i.
Optionally, the S2 includes:
fitting power failure loss functions of different types of loads by adopting a minimum bisection method, and calculating a weight coefficient of the load by using the power failure loss function according to the load type and the estimated power failure duration, wherein the calculation formula is as follows:
Figure BDA0003282680390000063
in the formula, ωi,tRepresents the weight coefficient, alpha, of the load i at the time of power failure tiAnd betaiThe fitting parameters of the load power failure loss function are determined by the characteristics of the load.
In practice, the power outage loss functions for different types of loads are fitted using the least squares method based on the survey data, as shown in fig. 3. Therefore, the weight coefficient of the load can be calculated by using the power failure loss function according to the load type and the estimated power failure duration time, and the calculation formula is as follows:
Figure BDA0003282680390000064
in the formula, ωi,tRepresents the weight coefficient, alpha, of the load i at the time of power failure tiAnd betaiThe fitting parameters for the load blackout loss functions are determined by the load characteristics, and the detailed parameters are shown in table 2.
TABLE 1 Power outage cost historical data (Unit: $/kW)
Figure BDA0003282680390000071
TABLE 2 fitting parameters for different types of loads
Figure BDA0003282680390000072
Optionally, the S3 includes:
for power-loss loads L1 and L2, no standby feeder is used for recovering power supply;
a distributed power plant with continuous power regulation capability operates in islanding mode to supply power to dead loads L1 and L2,
in implementation, a distributed power generation device with adjustable power in an isolated area is searched, and one-stage topology optimization is carried out. For power-off load L1And L2Distributed power generation device with continuous power regulation capability due to no spare feeder for recovering power supply1The device can run under an island mode to lose power load L1And L2The results of the phase optimization with power supply are shown in table 3.
TABLE 3 first stage optimization results
Figure BDA0003282680390000081
Optionally, the S4 includes:
for the second-stage standby feeder line and the load of the distributed power generation device from grid connection to power loss, the power support of the grid-connected distributed power generation device is considered;
the load transfer result mainly comprises the recovery rate of the power-loss load, a transfer path and transfer time;
after the load transfer is completed, acquiring the load rate of the directly connected transformer substation;
and if the load rate is higher than a preset value, judging that the directly-connected transformer substation is in a dangerous operation state.
In the implementation, for the second-stage standby feeder and the load of the distributed power generation device from grid connection to power loss, grid connection and branch connection are considered simultaneouslyThe results of the power support and the two-stage load transfer of the distributed power generation device are shown in table 4. In table 4, the result of load transfer mainly includes the recovery rate of the power-loss load, the transfer path and the transfer time. However, under the transfer load L5And L6Rear, direct-connected substation P1And P4Is 0.92 and 1.0, respectively, beyond its maximum allowable load rate, will be in a hazardous operating state, so these two substations will be defined as HLRTS.
TABLE 4 second stage optimization results
Load at power cut Type of load Recovery rate Supply time/min Restoration path
L3 Load of residents 78.8% 5 L3→S2→P1
L4 Load of residents 82.2% 16 L4→S3→S5→P1
L5 Commercial load 100% 17 L5→S6→S9→P4
L6 Load of residents 67.6% 12 L6→S6→S9→P4
L7 Industrial load 100% 6 L7→S7→P3
L8 Load of residents 83.8% 7 L8→S7→P3
Optionally, the S5 includes:
according to the third-stage transfer model, a secondary transfer strategy is adopted, namely, the third-stage optimization is carried out to solve the problem that the load rate of the directly-connected transformer substation is too high;
and updating the load rate of the directly-connected substation in the dangerous operation state according to the optimization result, and repeating the iteration of the second-stage and third-stage optimization until the directly-connected substation in the dangerous operation state disappears or cannot perform secondary transfer.
In implementation, the step is used for researching a three-stage topology optimization model on the basis of one-stage and two-stage topology optimization. According to the third-stage transfer model, a secondary transfer strategy is adopted, namely, third-stage optimization is carried out to solve the problem of overhigh load rate of the directly-connected transformer substation, and the third-stage optimization result is shown in table 5. After this stage, the load rate of the HLRTS is updated according to the optimization result, and iteration of the second-stage and third-stage optimization is performed again until the HLRTS disappears or secondary transfer cannot be performed, and the final load transfer scheme is shown in table 6.
TABLE 5 third stage optimization results
Power-off load Action switch Transfer path
L29 S14 L29→S14→P5
L26 S11,S12 L26→S11→P5
L27 S13 L27→S13→P5
TABLE 6 optimal load transfer results
Figure BDA0003282680390000091
Figure BDA0003282680390000101
The above description is only exemplary of the present application and should not be taken as limiting the present application, as any modification, equivalent replacement, or improvement made within the spirit and principle of the present application should be included in the protection scope of the present application.

Claims (6)

1. The three-stage topology operation optimization method based on load importance is characterized by comprising the following steps of:
s1, collecting operation data of the power distribution network after the fault, and establishing a topological structure for fault identification;
s2, establishing a load importance evaluation model according to the power loss electric charge in the distribution network operation data;
s3, searching a distributed power generation device with adjustable power in a distribution network island region, and performing one-stage topology optimization;
s4, establishing a two-stage topological optimization model, and carrying out load transfer on the spare feeder line and the distributed power generation device;
and S5, after the load transfer is carried out, if the target transformer substation in an overload operation state exists, establishing a secondary transfer model to obtain the optimal transfer load of the target transformer substation.
2. The three-stage topology operation optimization method based on load importance according to claim 1, wherein the S1 comprises:
collecting the number and positions of a transformer substation, a distribution transformer node, a connection feeder line, a breaker switch and a connection switch in a power distribution network;
constructing a topological structure according to the positions of the transformer substation, the distribution transformer node, the interconnection feeder line, the breaker switch and the interconnection switch, and adjusting the state of each device in the topological structure;
and determining the connection relation between the directly-connected transformer substation and the secondary connected transformer substation according to the adjusted topological structure.
3. The three-stage topology operation optimization method based on load importance according to claim 1, wherein the S2 comprises:
fitting power failure loss functions of different types of loads by adopting a minimum bisection method, and calculating a weight coefficient of the load by using the power failure loss function according to the load type and the estimated power failure duration, wherein the calculation formula is as follows:
Figure FDA0003282680380000011
in the formula, ωi,tRepresents the weight coefficient, alpha, of the load i at the time of power failure tiAnd betaiThe fitting parameters of the load power failure loss function are determined by the characteristics of the load.
4. The three-stage topology operation optimization method based on load importance according to claim 1, wherein the S3 comprises:
for power-loss loads L1 and L2, no standby feeder is used for recovering power supply;
the distributed power generation device with continuous power regulation capability operates in an island mode to supply power to power loss loads L1 and L2.
5. The three-stage topology operation optimization method based on load importance according to claim 1, wherein the S4 comprises:
for the second-stage standby feeder line and the load of the distributed power generation device from grid connection to power loss, the power support of the grid-connected distributed power generation device is considered;
the load transfer result mainly comprises the recovery rate of the power-loss load, a transfer path and transfer time;
after the load transfer is completed, acquiring the load rate of the directly connected transformer substation;
and if the load rate is higher than a preset value, judging that the directly-connected transformer substation is in a dangerous operation state.
6. The three-stage topology operation optimization method based on load importance according to claim 1, wherein the S5 comprises:
according to the third-stage transfer model, a secondary transfer strategy is adopted, namely, the third-stage optimization is carried out to solve the problem that the load rate of the directly-connected transformer substation is too high;
and updating the load rate of the directly-connected substation in the dangerous operation state according to the optimization result, and repeating the iteration of the second-stage and third-stage optimization until the directly-connected substation in the dangerous operation state disappears or cannot perform secondary transfer.
CN202111136803.6A 2021-09-27 2021-09-27 Three-stage topology operation optimization method based on load importance Pending CN114069689A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111136803.6A CN114069689A (en) 2021-09-27 2021-09-27 Three-stage topology operation optimization method based on load importance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111136803.6A CN114069689A (en) 2021-09-27 2021-09-27 Three-stage topology operation optimization method based on load importance

Publications (1)

Publication Number Publication Date
CN114069689A true CN114069689A (en) 2022-02-18

Family

ID=80233747

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111136803.6A Pending CN114069689A (en) 2021-09-27 2021-09-27 Three-stage topology operation optimization method based on load importance

Country Status (1)

Country Link
CN (1) CN114069689A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117937498A (en) * 2024-03-25 2024-04-26 天津中电华利电器科技集团有限公司 Substation operation load optimization control method and system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117937498A (en) * 2024-03-25 2024-04-26 天津中电华利电器科技集团有限公司 Substation operation load optimization control method and system

Similar Documents

Publication Publication Date Title
Yazdaninejadi et al. Impact of inverter-based DERs integration on protection, control, operation, and planning of electrical distribution grids
Zhao et al. Service restoration for a renewable-powered microgrid in unscheduled island mode
Shirazi et al. Autonomous self-healing in smart distribution grids using agent systems
Millar et al. Impact of MV connected microgrids on MV distribution planning
Poudel et al. A generalized framework for service restoration in a resilient power distribution system
CN109787224B (en) Method for generating regional power grid load transfer strategy for preventing cascading overload
CN107332236B (en) Power grid load transfer method based on global search
CN107147146B (en) A kind of distributed energy management solutions optimization method and device based on the more microgrids of joint
CN102290798A (en) Quick power supply restoring rule based on distribution network wire connecting way
Ramaswamy et al. Relevance of voltage control, grid reconfiguration and adaptive protection in smart grids and genetic algorithm as an optimization tool in achieving their control objectives
CN112907051B (en) Intelligent maintenance plan generation method based on allocation cooperation
Bian et al. Service restoration for resilient distribution systems coordinated with damage assessment
CN109004639B (en) Power distribution network partition power supply recovery strategy optimization method based on completely distributed algorithm
CN112217214B (en) Coordinated transfer optimization method for multistage high-voltage power distribution network
CN109768544A (en) Area power grid load transfer method
CN105391030A (en) Planned island division method through load gradual loading and aggregation based on network topology structure
CN114069689A (en) Three-stage topology operation optimization method based on load importance
CN113991653A (en) Three-stage topological operation mode optimization method considering load importance degree
CN111353682B (en) Multi-power-supply power grid reliability assessment method
CN112398129B (en) Auxiliary decision-making method, device and storage medium for risk control after power grid accident
Fatemi et al. Allocation of renewables, switches, and relays considering relays actual operation time
Lin et al. Research on Fault Recovery Coordination Strategy of Transmission and Distribution Network Based on Multi-Source Data
Arias Planning Models for Distribution Grid: A Brief Review
Ataee-Kachoee et al. Optimal protective coordination of microgrids considering N-1 contingency using dual characteristics directional overcurrent relays
CN103532109B (en) A kind of for the distribution network failure restoration methods containing microgrid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination