CN114033429A - Construction process for tunnel passing through rockburst section and low-gas-area superposed section - Google Patents

Construction process for tunnel passing through rockburst section and low-gas-area superposed section Download PDF

Info

Publication number
CN114033429A
CN114033429A CN202111339477.9A CN202111339477A CN114033429A CN 114033429 A CN114033429 A CN 114033429A CN 202111339477 A CN202111339477 A CN 202111339477A CN 114033429 A CN114033429 A CN 114033429A
Authority
CN
China
Prior art keywords
tunnel
gas
blastholes
section
anchor rod
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202111339477.9A
Other languages
Chinese (zh)
Inventor
林李前
陈航博
蔡斌
陈浩
侯硕智
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Sanya Xiamen Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Original Assignee
Cccc Sanya Xiamen Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Sanya Xiamen Engineering Co ltd, CCCC Third Harbor Engineering Co Ltd, CCCC Third Harbor Engineering Co Ltd Xiamen Branch filed Critical Cccc Sanya Xiamen Engineering Co ltd
Priority to CN202111339477.9A priority Critical patent/CN114033429A/en
Publication of CN114033429A publication Critical patent/CN114033429A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/18Special adaptations of signalling or alarm devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F7/00Methods or devices for drawing- off gases with or without subsequent use of the gas for any purpose

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a construction process of a tunnel passing through a rock burst section and a low gas area superposed section, which adopts an upper and lower step excavation method and comprises the following steps: the method comprises the following steps that firstly, an advanced drilling method is adopted to carry out advanced geological forecast verification before tunnel main tunnel excavation; secondly, stress release is carried out on the rock burst section which is not excavated through the advance probe hole, the gas concentration of the tunnel face and the operation position is detected by using a portable gas detector, and high-pressure water spraying is carried out on the tunnel face and the tunnel wall before normal excavation; firstly, drilling eleven ultra-deep blastholes; fourthly, firstly, gas detection is carried out by using the ultra-deep blastholes, and then eleven ultra-deep blastholes and a common blasthole are filled with explosives for blasting after the requirements are met; fifthly, performing primary support after the tunnel face is excavated; sixthly, constructing a gas isolation layer; and seventhly, performing secondary lining on the inner surface of the gas isolation layer by adopting C35 concrete doped with the air-tight agent. The invention can effectively reduce the risk of accidents and ensure safe construction.

Description

Construction process for tunnel passing through rockburst section and low-gas-area superposed section
Technical Field
The invention relates to a construction process of a tunnel passing through a rockburst section and a low-gas-area superposed section.
Background
In recent years, the construction of highways and high-speed railways in the southwest area of China is vigorously developed, a large number of tunnel projects are generated, the tunnel is inevitably subjected to various unfavorable geological sections in the tunneling process, the safety of tunnel operators is threatened, the normal operation of the tunnel is influenced, and serious hidden dangers are brought to the life and property safety of people. The unfavorable geology is manifested by fracture zones, rock bursts, water-bursting mud-bursting, karsts, gas, and the like, among others. When multiple unfavorable geological overlaps occur, technical and management risks are increased for the construction of the tunnel.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provide a construction process for a tunnel passing through a rock burst section and a low gas area superposed section, which can effectively reduce the risk of accidents and ensure safe construction.
The purpose of the invention is realized as follows: a construction process for a tunnel passing through a rockburst section and a low gas area superposed section is constructed by adopting an upper step and a lower step excavation method and comprises the following steps:
before a tunnel main tunnel at a rock burst section and a low-gas area overlapping section is excavated, adopting a geological radar method and a forepoling method to carry out forepoling verification, and preliminarily judging whether a front part contains a coal bed or gas, wherein the forepoling method is to uniformly drill five forepoling holes on a tunnel face by adopting a full-hydraulic tunnel drilling machine for a coal mine, uniformly distributing four forepoling holes along an excavation contour line, distributing a forepoling hole on a tunnel center line, the camber angle of the four forepoling holes on the excavation contour line is 10 degrees, and one forepoling hole on the tunnel center line is vertical to the tunnel face; the length of the pilot hole is 100m each time, and 20m of the pilot hole is reserved for the next excavation cyclic drilling;
secondly, stress release is carried out on the rock burst section which is not excavated through the advanced probing hole, the gas concentration of the tunnel face and the working position is detected at any time by utilizing the advanced probing hole and the portable gas detector, and normal excavation can be carried out if no gas exists or the gas concentration is less than 0.5%; before normal excavation, spraying water at high pressure on a tunnel face and a tunnel wall to soften the rock wall;
step three, before carrying out blasthole drilling in each excavation cycle, at least eleven blastholes are selected for deepening to form ultra-deep blastholes; firstly, adopting a wet rock drill to drill eleven ultra-deep blastholes, wherein the diameter of the ultra-deep blastholes is the same as that of a common blasthole, and the depth of the ultra-deep blastholes is not less than 5.0 m;
step four, firstly, carrying out gas detection by using the ultra-deep blastholes, detecting whether the gas concentration of the excavation working face reaches the standard, when the ultra-deep blastholes detect that the gas concentration is lower than 0.5%, then, adopting a wet rock drill to strike other common blastholes, then, starting to charge explosives for eleven ultra-deep blastholes and all the common blastholes for blasting, adopting an explosion-proof special exploder for electric explosion, adopting forward explosion during explosion, and then, carrying out tunnel face excavation;
fifthly, after the tunnel face is excavated, carrying out primary support, firstly spraying C25 airtight sprayed concrete to the rock wall, erecting a reinforcing mesh and a steel arch after the spraying thickness is 2-4 cm, and then spraying C25 airtight sprayed concrete again to cover the steel arch; the total thickness of the C25 airtight sprayed concrete is not less than the design thickness, and the air permeability coefficient of the C25 airtight sprayed concrete is not more than 10-10~-11cm/s; then adopt againDrilling an anchor rod hole by using a special anchor rod machine, wherein the anchor rod hole is vertical to a rock surface, the diameter of the anchor rod hole is 15mm larger than that of an anchor rod, after the hole is formed, high-pressure air is used for blowing floating soil and broken stones in the anchor rod hole clean, the depth, the angle and the distance of the anchor rod hole are checked, if the depth, the angle and the distance of the anchor rod hole do not meet the standard requirements, a remedial measure is adopted to ensure that the depth of the anchor rod hole meets the design requirements, then the anchor rod is quickly inserted into the bottom of the anchor rod hole after the anchor rod hole is filled with mortar, the anchor rod hole is fully squeezed with the mortar, and after the mortar reaches certain strength, an anchor rod base plate is installed and screwed down by using a nut;
constructing a gas isolation layer, wherein the gas isolation layer adopts a full-enclosed structure, namely an inverted arch, a side wall and an arch part are annularly and fully enclosed; the gas isolation layer consists of geotextile and a waterproof plate; the lap width of the geotextile is not less than 5cm, and the geotextile is required to be closely attached to the surface of concrete when being laid; the waterproof board is a PVC board; fixing the geotextile to a preset position by using a cloth hanging trolley, and fixing the geotextile on an initial support surface by using a hot-melt liner and a shooting nail, wherein the hot-melt liner and the shooting nail are arranged according to a quincunx shape; the waterproof board is laid without nails, namely, the plastic washer is fixed on the outer surface of the geotextile by shooting nails, and then the waterproof board is welded on the plastic washer; the joint of the waterproof boards is formed by adopting an automatic welding line of a heat sealing machine, and is welded by adopting double welding lines through hot ironing, the effective welding line width of a single welding line is not less than 2.5cm, and the edge lapping width of the two layers of waterproof boards is not less than 12 cm;
and seventhly, performing secondary lining on the inner surface of the waterproof board, constructing by adopting a full-section one-step forming method, and adopting C35 concrete doped with the air-tight agent and having the anti-permeability grade not less than P8.
In the construction process of the tunnel passing through the rockburst section and the low-gas-area superposed section, the eleven ultra-deep blastholes are arranged in the following mode when the step three is carried out: six and five are arranged on the upper part and the lower part of the excavation boundary of the upper step and the lower step in a one-to-one correspondence mode.
And in the construction process of the tunnel passing through the rockburst section and the low-gas-area superposed section, in the sixth step, the air tightness of each welding line of the waterproof plate is checked, the inflation is stopped when the pressure reaches 0.25MPa, the pressure is kept for more than 15 minutes, the pressure is reduced within 10 percent, and the quality of the welding line is qualified.
And the construction process of the tunnel passing through the rockburst section and the low-gas area superposed section comprises the step seven, concrete is poured in a layered and windowing mode, pumped concrete is poured from bottom to top in a warehouse in a layered and symmetrical mode from the joint of the poured section to the non-pouring direction, and the deformation of the template caused by bias pressure is prevented.
The construction method of the construction process of the tunnel penetrating through the rock burst section and the low gas area superposed section has the following characteristics:
1) the detection mode combining drilling advanced hole detection and a gas automatic monitoring system is adopted, so that all-dimensional and all-weather detection is realized, the risk of accidents can be effectively reduced, and safe construction is ensured;
2) stress release of a rock burst section is carried out by utilizing the advanced exploration hole, a damage zone is formed in the surrounding rock, stress of a tunnel wall and a tunnel face is reduced, namely a low-elasticity area is formed, high stress is transferred to the deep part of the surrounding rock, meanwhile, plasticity of a rock body is increased by sprinkling water on the tunnel face, brittleness of the rock body is weakened, the intensity of rock burst is reduced, collision sparks are avoided, secondary disasters caused by rock burst are reduced, and construction safety is improved;
3) through increasing the gas isolation layer with low costs that comprises geotechnological cloth and waterproof board on initial stage retaining surface, the gas isolation layer adopts full package structure to add means such as air-tight agent in secondary lining's concrete, effectively block the gaseous outward transmission passageway of gas, ensure the safety of tunnel during construction and operation, can also accelerate the construction progress.
Drawings
FIG. 1 is a diagram of the arrangement of advanced exploration holes in the construction process of a tunnel passing through a rockburst section and a low gas zone overlapping section according to the invention;
FIG. 2 is a view taken along line A-A of FIG. 1;
FIG. 3 is a layout diagram of ultra-deep blastholes in the third step of the construction process of the tunnel passing through the rock burst section and the low gas zone superposed section;
FIG. 4 is a cross-sectional view of the tunnel after seven steps of the construction process of the tunnel passing through the rockburst section and the low gas zone overlapping section are performed.
Detailed Description
The invention will be further explained with reference to the drawings.
Referring to fig. 1 to 4, the construction process of the tunnel passing through the rock burst section and the low gas zone overlapping section of the invention adopts an upper and lower step excavation method for construction, and comprises the following steps:
firstly, before a tunnel main tunnel of a rock burst section and a low gas area superposition section is excavated, a geological radar method is combined with a advanced drilling method to carry out advanced geological forecast verification, and whether a front part contains a coal bed or gas is preliminarily judged; the advanced drilling method is that a full-hydraulic tunnel drilling machine for coal mines is adopted to uniformly drill five advanced probing holes 11, 12, 13, 14 and 15 on the tunnel face, the aperture of the advanced probing hole is phi 76mm, four advanced probing holes 11, 12, 13 and 14 are uniformly distributed along the excavation contour line, one advanced probing hole 15 is arranged on the tunnel center line, the camber angle of the four advanced probing holes 11, 12, 13 and 14 on the excavation contour line is 10 degrees, and one advanced probing hole 15 on the tunnel center line is vertical to the tunnel face; drilling a pilot hole with the length of 100m each time, and reserving the length of 20m for the next excavation cycle drilling (see figure 1);
stress release is carried out on the rock burst section which is not excavated through the five advanced probing holes, the gas concentration of the tunnel face and the working position is detected at any time by utilizing the advanced probing holes and the portable gas detector, and normal excavation can be carried out if no gas exists or the gas concentration is less than 0.5%; before normal excavation, high-pressure water spraying is carried out on the tunnel face and the tunnel wall so as to increase the plasticity of the rock mass, weaken the brittleness of the rock mass, reduce the rockburst intensity, avoid collision sparks and avoid the possibility of gas explosion;
step three, before carrying out blasthole drilling in each excavation cycle, deepening at least eleven blastholes to form ultra-deep blastholes 20; the eleven ultra-deep blastholes 20 are arranged in the following manner: six and five excavation boundary lines are correspondingly arranged at the upper part and the lower part of the excavation boundary line of the upper step and the lower step one by one; firstly, adopting a wet rock drill to drill eleven ultra-deep blastholes 20, wherein the diameter of the ultra-deep blastholes 20 is the same as that of a common blasthole, the diameter is phi 42mm, and the depth of the ultra-deep blastholes 20 is not less than 5.0 m;
step four, firstly, the ultra-deep blast hole 20 is used for gas detection, whether the gas concentration of the excavated working face reaches the standard or not is detected, the surrounding rock and gas content conditions of the next circulating face can be further judged, and pre-judgment measures are favorably adopted; when the ultra-deep blastholes 20 detect that the gas concentration is lower than 0.5%, then adopting a wet rock drill to drill other common blastholes, then starting to blast the eleven ultra-deep blastholes 20 and all the common blastholes with explosives, adopting an explosion-proof special exploder to perform electric explosion, and adopting forward explosion during explosion so as to effectively prevent gas explosion caused by gas preheated by gaseous explosives; then, excavating the tunnel face;
fifthly, after the tunnel face is excavated, carrying out primary support, firstly spraying C25 airtight sprayed concrete to the rock wall, erecting a reinforcing mesh and a steel arch after the spraying thickness is 2-4 cm, and then spraying C25 airtight sprayed concrete again to cover the steel arch; the total thickness of the C25 airtight sprayed concrete is not less than the design thickness, and the air permeability coefficient of the C25 airtight sprayed concrete is not more than 10-10~-11cm/s; drilling an anchor rod hole by adopting a special anchor rod machine, wherein the anchor rod hole is vertical to the rock surface, the diameter of the anchor rod hole is phi 42mm and is 15mm larger than the diameter of the anchor rod, after the hole is formed, floating soil and broken stones in the anchor rod hole are blown clean by high-pressure air, the depth, the angle and the distance of the anchor rod hole are checked, if the depth, the angle and the distance of the anchor rod hole do not meet the standard requirements, a remedial measure is adopted to ensure that the depth of the anchor rod hole meets the design requirements, then the anchor rod is rapidly inserted into the bottom of the anchor rod hole after the anchor rod hole is filled with mortar, the mortar is squeezed into the anchor rod hole, and after the mortar reaches certain strength, an anchor rod base plate is installed and is screwed by using a nut;
constructing a gas isolation layer, wherein the gas isolation layer adopts a full-enclosed structure, namely, the gas isolation layer is annularly and fully enclosed on an inverted arch, a side wall and an arch part of the tunnel; the gas isolation layer is composed of geotextile and waterproof board which are laid on the primary support surface in sequence; the geotextile adopts 400g/m2The overlapping width of the geofabric is not less than 5cm, and the geofabric is required to be closely attached to the initial support surface when being laid; the waterproof board is a PVC board with the thickness of 1.5 mm; first, the geotextile is fixed to a preset position by using a cloth hanging trolleyThe position, then fix geotechnological cloth on the initial stage retaining surface with hot melt liner and penetrating the nail, hot melt liner and penetrating the nail and arrange according to the quincunx type, the interval is: the arch part is 0.5m, the side wall is 0.7m, the bottom is 1.0m, and the arch part is properly encrypted in the concave part; the waterproof board is laid without nails, namely, the plastic washer is fixed on the outer surface of the geotextile by shooting nails, and then the waterproof board is welded on the plastic washer; the joint of the waterproof boards is formed by adopting an automatic welding line of a heat sealing machine, and is welded by adopting double welding lines through hot ironing, the effective welding line width of a single welding line is not less than 2.5cm, and the edge lapping width of the two layers of waterproof boards is not less than 12 cm; then, performing air tightness inspection on each welding line of the waterproof plate, namely, aligning the welding line position to inflate, stopping inflating when the pressure reaches 0.25MPa, keeping the pressure for more than 15 minutes, and reducing the pressure within 10 percent, namely, indicating that the welding line quality is qualified; the transmission channel of the gas can be effectively blocked, and the gas is prevented from permeating into the tunnel; ensuring the safety of the tunnel during construction and operation;
step seven, performing secondary lining on the inner surface of the waterproof board, constructing by adopting a full-section one-step forming method, and adopting C35 concrete (shown in figure 4) which has the impermeability grade not less than P8 and is doped with an air sealing agent, so that a gas isolation layer can be formed preliminarily, and free gas is prevented from diffusing into the tunnel; the concrete is poured in layers and in windows, the pumped concrete is poured symmetrically from the joint of the poured section to the non-pouring direction from bottom to top in layers, and the deformation of the template caused by bias pressure is prevented.
According to different grades of surrounding rocks, in the excavation footage process of a tunnel gas work area, in order to reduce the gas overflow length, when the tunnel surrounding rocks are good, full-section excavation is adopted, and the excavation footage is not more than 3 m; when the tunnel surrounding rock is poor, excavating by adopting a short step method, wherein the excavation footage is 1.2-1.6 m (two trusses), and the step length is 15-20 m; the lining range of the emergency parking area adopts three-step excavation, and the excavation depth is 0.6-0.8 m (one roof).
Distance from secondary lining to tunnel face: the III-grade surrounding rock is not more than 100 m; the IV-grade surrounding rock is not more than 90m, and the V-grade surrounding rock is not more than 70 m.
The above embodiments are provided only for illustrating the present invention and not for limiting the present invention, and those skilled in the art can make various changes and modifications without departing from the spirit and scope of the present invention, and therefore all equivalent technical solutions should also fall within the scope of the present invention, and should be defined by the claims.

Claims (4)

1. A construction process for a tunnel passing through a rockburst section and a low gas area superposed section is constructed by adopting an upper step and a lower step excavation method, and is characterized by comprising the following steps:
before a tunnel main tunnel at a rock burst section and a low-gas area overlapping section is excavated, adopting a geological radar method and a forepoling method to carry out forepoling verification, and preliminarily judging whether a front part contains a coal bed or gas, wherein the forepoling method is to uniformly drill five forepoling holes on a tunnel face by adopting a full-hydraulic tunnel drilling machine for a coal mine, uniformly distributing four forepoling holes along an excavation contour line, distributing a forepoling hole on a tunnel center line, the camber angle of the four forepoling holes on the excavation contour line is 10 degrees, and one forepoling hole on the tunnel center line is vertical to the tunnel face; the length of the pilot hole is 100m each time, and 20m of the pilot hole is reserved for the next excavation cyclic drilling;
secondly, stress release is carried out on the rock burst section which is not excavated through the advanced probing hole, the gas concentration of the tunnel face and the working position is detected at any time by utilizing the advanced probing hole and the portable gas detector, and normal excavation can be carried out if no gas exists or the gas concentration is less than 0.5%; before normal excavation, spraying water at high pressure on a tunnel face and a tunnel wall to soften the rock wall;
step three, before carrying out blasthole drilling in each excavation cycle, at least eleven blastholes are selected for deepening to form ultra-deep blastholes; firstly, adopting a wet rock drill to drill eleven ultra-deep blastholes, wherein the diameter of the ultra-deep blastholes is the same as that of a common blasthole, and the depth of the ultra-deep blastholes is not less than 5.0 m;
step four, firstly, carrying out gas detection by using the ultra-deep blastholes, detecting whether the gas concentration of the excavation working face reaches the standard, when the ultra-deep blastholes detect that the gas concentration is lower than 0.5%, then, adopting a wet rock drill to strike other common blastholes, then, starting to charge explosives for eleven ultra-deep blastholes and all the common blastholes for blasting, adopting an explosion-proof special exploder for electric explosion, adopting forward explosion during explosion, and then, carrying out tunnel face excavation;
fifthly, after the tunnel face is excavated, carrying out primary support, firstly spraying C25 airtight sprayed concrete to the rock wall, erecting a reinforcing mesh and a steel arch after the spraying thickness is 2-4 cm, and then spraying C25 airtight sprayed concrete again to cover the steel arch; the total thickness of the C25 airtight sprayed concrete is not less than the design thickness, and the air permeability coefficient of the C25 airtight sprayed concrete is not more than 10-10-11cm/s; drilling an anchor rod hole by adopting a special anchor rod machine, wherein the anchor rod hole is vertical to the rock surface, the diameter of the anchor rod hole is 15mm larger than that of the anchor rod, after the hole is formed, high-pressure air is used for blowing away floating soil and broken stones in the anchor rod hole, the depth, the angle and the distance of the anchor rod hole are checked, if the depth, the angle and the distance of the anchor rod hole do not meet the standard requirements, a remedial measure is adopted to ensure that the depth of the anchor rod hole meets the design requirements, then the anchor rod is quickly inserted into the bottom of the anchor rod hole after the anchor rod hole is filled with mortar, the anchor rod hole is fully squeezed with the mortar, and after the mortar reaches certain strength, an anchor rod base plate is installed and screwed tightly by using a nut;
constructing a gas isolation layer, wherein the gas isolation layer adopts a full-enclosed structure, namely an inverted arch, a side wall and an arch part are annularly and fully enclosed; the gas isolation layer consists of geotextile and a waterproof plate; the lap width of the geotextile is not less than 5cm, and the geotextile is required to be closely attached to the surface of concrete when being laid; the waterproof board is a PVC board; fixing the geotextile to a preset position by using a cloth hanging trolley, and fixing the geotextile on an initial support surface by using a hot-melt liner and a shooting nail, wherein the hot-melt liner and the shooting nail are arranged according to a quincunx shape; the waterproof board is laid without nails, namely, the plastic washer is fixed on the outer surface of the geotextile by shooting nails, and then the waterproof board is welded on the plastic washer; the joint of the waterproof boards is formed by adopting an automatic welding line of a heat sealing machine, and is welded by adopting double welding lines through hot ironing, the effective welding line width of a single welding line is not less than 2.5cm, and the edge lapping width of the two layers of waterproof boards is not less than 12 cm;
and seventhly, performing secondary lining on the inner surface of the waterproof board, constructing by adopting a full-section one-step forming method, and adopting C35 concrete doped with the air-tight agent and having the anti-permeability grade not less than P8.
2. The construction process of the tunnel passing through the rockburst section and the low-gas-area superposed section according to claim 1, wherein in the third step, eleven ultra-deep blastholes are arranged in the following manner: six and five are arranged on the upper part and the lower part of the excavation boundary of the upper step and the lower step in a one-to-one correspondence mode.
3. The construction process of the tunnel passing through the rockburst section and the low-gas-area overlapped section according to claim 1, wherein in the sixth step, the air tightness of each welding line of the waterproof plate is checked, when the pressure reaches 0.25MPa, the inflation is stopped, the pressure is maintained for more than 15 minutes, the pressure is reduced within 10%, and the quality of the welding line is qualified.
4. The construction process of a tunnel passing through a rockburst section and a low gas area superposition section according to claim 1, wherein in the seventh step, concrete is poured in layers and in windows, and pumped from bottom to top and symmetrically poured in layers from a joint of a poured section to a non-pouring direction, so as to prevent the deformation of the template due to bias pressure.
CN202111339477.9A 2021-11-12 2021-11-12 Construction process for tunnel passing through rockburst section and low-gas-area superposed section Withdrawn CN114033429A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111339477.9A CN114033429A (en) 2021-11-12 2021-11-12 Construction process for tunnel passing through rockburst section and low-gas-area superposed section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111339477.9A CN114033429A (en) 2021-11-12 2021-11-12 Construction process for tunnel passing through rockburst section and low-gas-area superposed section

Publications (1)

Publication Number Publication Date
CN114033429A true CN114033429A (en) 2022-02-11

Family

ID=80144239

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111339477.9A Withdrawn CN114033429A (en) 2021-11-12 2021-11-12 Construction process for tunnel passing through rockburst section and low-gas-area superposed section

Country Status (1)

Country Link
CN (1) CN114033429A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114544908A (en) * 2022-04-24 2022-05-27 山西和运能源服务有限公司 Coal mine low-concentration gas heating device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536250A (en) * 2010-12-31 2012-07-04 中铁二局股份有限公司 Construction method for tunnels with karst and gas simultaneously
JP2017025618A (en) * 2015-07-24 2017-02-02 信也 馬場 Advanced boring method
CN106968675A (en) * 2017-03-20 2017-07-21 中铁十五局集团有限公司 Construction method of gas tunnel goaf
CN108316929A (en) * 2018-01-29 2018-07-24 中国水利水电第十工程局有限公司 A kind of water conservancy and hydropower gas Tunnel Construction
CN110056360A (en) * 2019-05-10 2019-07-26 中交二航局第四工程有限公司 A kind of construction method in highway stone matter tunnel
CN209724368U (en) * 2018-12-11 2019-12-03 中国铁路设计集团有限公司 A kind of improved metro built by mining method water proof structure
CN110748359A (en) * 2019-12-06 2020-02-04 中铁十八局集团建筑安装工程有限公司 Tunnel water-proof and drainage construction process
CN111237006A (en) * 2020-02-17 2020-06-05 中煤科工集团重庆研究院有限公司 Method for preventing and controlling rock burst and gas emission in linkage manner of high-length and short-distance drilling

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536250A (en) * 2010-12-31 2012-07-04 中铁二局股份有限公司 Construction method for tunnels with karst and gas simultaneously
JP2017025618A (en) * 2015-07-24 2017-02-02 信也 馬場 Advanced boring method
CN106968675A (en) * 2017-03-20 2017-07-21 中铁十五局集团有限公司 Construction method of gas tunnel goaf
CN108316929A (en) * 2018-01-29 2018-07-24 中国水利水电第十工程局有限公司 A kind of water conservancy and hydropower gas Tunnel Construction
CN209724368U (en) * 2018-12-11 2019-12-03 中国铁路设计集团有限公司 A kind of improved metro built by mining method water proof structure
CN110056360A (en) * 2019-05-10 2019-07-26 中交二航局第四工程有限公司 A kind of construction method in highway stone matter tunnel
CN110748359A (en) * 2019-12-06 2020-02-04 中铁十八局集团建筑安装工程有限公司 Tunnel water-proof and drainage construction process
CN111237006A (en) * 2020-02-17 2020-06-05 中煤科工集团重庆研究院有限公司 Method for preventing and controlling rock burst and gas emission in linkage manner of high-length and short-distance drilling

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
朱新勇;: "地铁隧道全包式分区防水施工技术", 山西建筑, vol. 34, no. 5, pages 192 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114544908A (en) * 2022-04-24 2022-05-27 山西和运能源服务有限公司 Coal mine low-concentration gas heating device

Similar Documents

Publication Publication Date Title
CN108661643B (en) It a kind of coal working face end adopts return channel and cuts top release shield lane method
CN113494299B (en) Tunnel rockburst grading prevention and control method using NPR material
CN103527198B (en) Cut a tight roof/top coal hydraulic fracture control method
CN110374600B (en) Non-offset arrangement method for mining roadway of extremely-close coal seam group
CN111335892A (en) Strong-impact coal seam pressure relief prevention and control method
CN109339786A (en) A kind of prefabricated Fracture orientation hydraulic fracturing cracking method
CN110700883A (en) Gob-side entry driving prevention and control method for large-dip-angle coal seam composite disaster small coal pillar
CN111271120A (en) Coal mine rock burst dynamic and static load source-based danger relieving method
CN105423832B (en) Blast construction method of orientation window of thick-wall brick chimney
CN114320318B (en) In-situ modification anti-scour method for coal mine roadway surrounding rock
CN107060773B (en) A kind of underground chamber drilling and blasting method damping excavation method of static(al) explosion presplitting shock insulation
CN113482725B (en) Tunnel high-ground-stress section prevention and control construction method
CN105021096B (en) A kind of five-part form millisecond electric detonator secondary blasting construction method applied in high methane large cross-section tunnel explosion
CN107862106B (en) Without coal column along empty caving at lane feasibility discrimination method
CN115680658A (en) Rock burst source prevention and control method
CN107956500A (en) A kind of gasbag-type active explosion suppression explosion isolation device and method
CN114033429A (en) Construction process for tunnel passing through rockburst section and low-gas-area superposed section
CN105953671A (en) Construction method for excavating siliceous slate stone side slope
CN111780633A (en) Step-by-step rapid excavation method for IV-V-level surrounding rock lower step of double-track tunnel
CN112879009A (en) Forced caving method for two ends of working face based on presplitting directional blasting
CN112432566A (en) Full-section rapid excavation method for large-section tunnel
CN111457804A (en) Method for blasting IV-grade massive crushed rock with disordered development and wide fracture surface
Zhu et al. Key technology of gob-side entry retained by roof cutting without coal pillar for hard main roof: A typical case study
CN113605971B (en) Filling structure for preventing filling body from being unstable and mining method applying filling structure
CN115822719A (en) Fine comprehensive outburst coal uncovering prevention method for high-gas tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road

Applicant after: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Applicant after: CCCC Third Aviation Bureau Sixth Engineering (Xiamen) Co.,Ltd.

Applicant after: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Address before: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road

Applicant before: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Applicant before: CCCC Sanya (Xiamen) Engineering Co.,Ltd.

Applicant before: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

CB02 Change of applicant information
WW01 Invention patent application withdrawn after publication

Application publication date: 20220211

WW01 Invention patent application withdrawn after publication