CN114033246A - Assembled temporary enclosure for construction of constructional engineering - Google Patents
Assembled temporary enclosure for construction of constructional engineering Download PDFInfo
- Publication number
- CN114033246A CN114033246A CN202111521039.4A CN202111521039A CN114033246A CN 114033246 A CN114033246 A CN 114033246A CN 202111521039 A CN202111521039 A CN 202111521039A CN 114033246 A CN114033246 A CN 114033246A
- Authority
- CN
- China
- Prior art keywords
- baffle
- rack
- gear
- shaped rods
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 18
- 230000000903 blocking effect Effects 0.000 claims description 5
- 238000013016 damping Methods 0.000 claims description 5
- 230000004888 barrier function Effects 0.000 claims 1
- 238000009434 installation Methods 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 3
- FGRBYDKOBBBPOI-UHFFFAOYSA-N 10,10-dioxo-2-[4-(N-phenylanilino)phenyl]thioxanthen-9-one Chemical compound O=C1c2ccccc2S(=O)(=O)c2ccc(cc12)-c1ccc(cc1)N(c1ccccc1)c1ccccc1 FGRBYDKOBBBPOI-UHFFFAOYSA-N 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H17/00—Fencing, e.g. fences, enclosures, corrals
- E04H17/14—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
- E04H17/16—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts using prefabricated panel-like elements, e.g. wired frames
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H17/00—Fencing, e.g. fences, enclosures, corrals
- E04H17/14—Fences constructed of rigid elements, e.g. with additional wire fillings or with posts
- E04H17/20—Posts therefor
- E04H17/23—Posts therefor lateral supporting elements, e.g. braces, tie downs, or cables
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
The invention provides an assembled temporary enclosure for constructional engineering construction, which relates to the technical field of constructional engineering construction and comprises a baffle plate, wherein the bottom of the baffle plate is fixedly connected with an installation bottom plate, one end of the baffle plate is provided with two groups of L-shaped rods, each group comprises two L-shaped rods, the two L-shaped rods are symmetrically arranged, one ends, close to each other, of the two L-shaped rods are fixedly connected with first gears, the two first gears are meshed with each other, one of the first gears is meshed with a second gear, and the baffle plate is provided with a driving assembly for rotating the second gear; when connecting two rails together, make the one end of baffle paste the one end of another baffle, then make the second gear rotatory through drive assembly to make first gear rotatory, thereby make the one end of two L shape poles draw close each other, thereby make two L shape poles grasp the connecting rod, link together with this two rails that make, consequently convenient to detach and equipment.
Description
Technical Field
The invention relates to the technical field of constructional engineering construction, in particular to an assembled temporary enclosure for constructional engineering construction.
Background
The enclosure means measures taken to isolate a construction site from the external environment and make the construction site a relatively closed space, and includes enclosures built by various masonry materials, maintenance bodies formed by various formed plates, and the like.
However, the existing temporary enclosure is very complicated in disassembly and assembly, so that the efficiency in installation is extremely low, and the engineering progress is greatly prolonged.
Disclosure of Invention
The invention aims to provide an assembled temporary enclosure for construction of constructional engineering, and aims to solve the problem that the existing temporary enclosure in the prior art is very complicated in disassembly and assembly, so that the efficiency in installation is extremely low.
In order to achieve the purpose, the invention adopts the following technical scheme: the assembled temporary enclosure for the construction of the constructional engineering comprises a baffle, the bottom fixedly connected with mounting plate of the baffle, two sets of L-shaped rods are installed at one end of the baffle, each set comprises two L-shaped rods, the two L-shaped rods are symmetrically arranged and two are arranged, the L-shaped rods are close to one another, a first gear and a second gear are fixedly connected to one end of each L-shaped rod, the first gears are meshed with one another and one of the gears is meshed with a second gear, a driving assembly used for enabling the second gear to rotate is arranged on the baffle, a cavity capable of enabling the L-shaped rods to enter is formed in the other end of the baffle, and a connecting rod capable of being hooked by the L-shaped rods is arranged in the cavity.
In order to enable the invention to have the function of rotating the second gear, the invention has the further technical scheme that the driving assembly comprises a rack which is connected in the baffle in a sliding manner, a sliding block is fixedly connected on the rack, the rack is meshed with the second gear, and a damping assembly for blocking the movement of the rack is arranged between the rack and the baffle.
In order to enable the damper to have the function of blocking the movement of the rack, the damper has the further technical scheme that a blind hole is formed in one side of the rack, the damper assembly comprises a first elastic piece arranged in the blind hole, a ball is arranged at one end of the first elastic piece, a limiting ring for preventing the ball from sliding out is arranged at the top end of the blind hole, grooves for clamping the ball are formed in one surface, in contact with the rack, of the inner portion of the baffle, and the number of the grooves is twice that of the balls.
According to a further technical scheme of the invention, the first elastic piece is a spring.
In order to enable the adjustable support rod to have the function of conveniently adjusting the support rod, the back of the baffle is provided with a rectangular groove, two side walls in the rectangular groove are provided with sliding grooves, a row of clamping holes are formed in the sliding grooves, the support rod is arranged in the rectangular groove, two sides of one end of the support rod are respectively connected with a rotating shaft in a sliding mode, one end of the rotating shaft is fixedly connected with a moving plate, one end of the moving plate extends out of one side of the support rod, the rotating shaft can be clamped in the clamping holes, and a second elastic piece used for enabling the rotating shaft to pop out is arranged in the support rod.
According to a further technical scheme, the second elastic piece is a spring.
According to a further technical scheme, the other end of the supporting rod is hinged with a fixed seat.
The invention has the beneficial effects that:
1. when the two fences are connected together, one end of each baffle is attached to one end of the other baffle, and then the second gear rotates through the driving assembly, so that the first gear rotates, one ends of the two L-shaped rods are close to each other, the two L-shaped rods grasp the connecting rod, and the two fences are connected together, so that the two fences are convenient to disassemble and assemble.
2. When the adjustable support is used, the support rod is disassembled and then is retracted in the rectangular groove, when the adjustable support is needed, the two moving plates are moved close to each other, so that the rotating shaft is separated from the clamping hole, then the rotating shaft slides in the sliding groove, the position of one end of the support rod in the rectangular groove is adjusted, the moving plates are loosened after the adjusting to the proper position, the rotating shaft enters the clamping hole under the action of the spring, and finally the fixed seat is fixed on the ground, so that the adjustable support is convenient to adjust the support position and is convenient to use.
Drawings
Fig. 1 is a schematic structural diagram of an embodiment of the present invention.
Fig. 2 is a disassembled schematic structure of the embodiment of the invention.
Fig. 3 is a schematic diagram of the internal structure of the embodiment of the present invention.
Fig. 4 is a cross-sectional view of a rack in an embodiment of the invention.
Fig. 5 is a schematic structural diagram of a support rod according to an embodiment of the present invention.
In the figure: 1. a baffle plate; 2. an L-shaped rod; 3. a first gear; 4. a second gear; 5. a connecting rod; 6. a rack; 7. a first elastic member; 8. a ball bearing; 9. a support bar; 10. a rotating shaft; 11. moving the plate; 12. a second elastic member; 13. a slider; 14. a fixed seat.
Detailed Description
The following further describes embodiments of the present invention with reference to the drawings.
As shown in fig. 1-5, an assembled temporary enclosure for construction of building engineering comprises a baffle 1, a bottom fixedly connected with mounting bottom plate of the baffle 1, two sets of L-shaped rods 2 are installed at one end of the baffle 1, each set includes two L-shaped rods 2, two L-shaped rods 2 are symmetrically arranged, two L-shaped rods 2 are respectively fixedly connected with a first gear 3 and a second gear 4 at the end close to each other, the first gears 3 are mutually meshed, one of the first gears 3 is meshed with the second gear 4, a driving assembly for rotating the second gear 4 is arranged on the baffle 1, a cavity for enabling the L-shaped rods 2 to enter is arranged at the other end of the baffle 1, and a connecting rod 5 capable of being hooked by the L-shaped rods 2 is arranged in the cavity.
In this embodiment, when the two rails are connected together, one end of the baffle 1 is attached to one end of the other baffle 1, and then the second gear 4 is rotated by the driving assembly, so that the first gear 3 is rotated, and one ends of the two L-shaped rods 2 are drawn close to each other, so that the two L-shaped rods 2 catch the connecting rod 5, and thus the two rails are connected together, thereby facilitating disassembly and assembly.
Specifically, the driving assembly comprises a rack 6 which is slidably connected in the baffle plate 1, a sliding block 13 is fixedly connected to the rack 6, the rack 6 is meshed with the second gear 4, a damping assembly used for blocking the movement of the rack 6 is arranged between the rack 6 and the baffle plate 1, and the rack 6 moves to enable the second gear 4 to rotate, so that the first gear 3 drives the L-shaped rod 2 to rotate.
Specifically, one side of rack 6 is provided with the blind hole, the damping subassembly is including setting up first elastic component 7 in the blind hole, the one end of first elastic component 7 is provided with ball 8, the top of blind hole is provided with the spacing ring of avoiding the 8 roll-offs of ball, be provided with the recess that is used for blocking ball 8 in the one side that baffle 1 is inside to contact with rack 6, the quantity of recess is the twice of ball 8 quantity, and when rack 6 moved, ball 8 breaks away from the recess, and after rack 6 moved the other end, ball 8 got into in the recess of the other end to avoid rack 6 to move under the condition of no external force.
Preferably, the first elastic member 7 is a spring.
Further, a rectangular groove is formed in the back of the baffle 1, sliding grooves are formed in two side walls of the rectangular groove, a row of clamping holes are formed in the sliding grooves, a supporting rod 9 is arranged in the rectangular groove, two sides of one end of the supporting rod 9 are connected with a rotating shaft 10 in a sliding mode, one end of the rotating shaft 10 is fixedly connected with a moving plate 11, one end of the moving plate 11 extends out of one side of the supporting rod 9, the rotating shaft 10 can be clamped in the clamping holes, and a second elastic part 12 used for enabling the rotating shaft 10 to pop out is installed in the supporting rod 9.
Preferably, the second elastic member 12 is a spring.
Further, the other end of bracing piece 9 articulates there is fixing base 14, the bracing piece 9 receipts are in the rectangular channel after dismantling, when needs use, make two movable plates 11 draw close each other, thereby make axis of rotation 10 break away from the card hole, then make axis of rotation 10 slide in the spout, thereby adjust the position of bracing piece 9 one end in the rectangular channel, loosen movable plate 11 after adjusting suitable position, axis of rotation 10 gets into under the effect of spring in the card hole, fix fixing base 14 subaerial again at last, it conveniently adjusts the holding position to set up like this, and convenient to use.
In the description of the present invention, unless otherwise expressly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (7)
1. An assembled temporary enclosure for construction of constructional engineering is characterized by comprising a baffle (1), the bottom of the baffle (1) is fixedly connected with a mounting bottom plate, one end of the baffle (1) is provided with two groups of L-shaped rods (2), each group comprises two L-shaped rods (2), the two L-shaped rods (2) are symmetrically arranged, one ends of the two L-shaped rods (2) close to each other are fixedly connected with first gears (3), the two first gears (3) are mutually meshed, one of the first gears (3) is engaged with a second gear (4), the baffle (1) is provided with a driving component for rotating the second gear (4), the other end of the baffle (1) is provided with a cavity into which the L-shaped rod (2) can enter, a connecting rod (5) which can be hooked by the L-shaped rod (2) is arranged in the cavity.
2. The assembled temporary enclosure for building engineering construction according to claim 1, wherein the driving assembly comprises a rack (6) slidably connected in the enclosure (1), a sliding block (13) is fixedly connected to the rack (6), the rack (6) is engaged with the second gear (4), and a damping assembly for blocking the movement of the rack (6) is arranged between the rack (6) and the enclosure (1).
3. The assembled temporary enclosure for building engineering construction according to claim 2, wherein a blind hole is formed in one side of the rack (6), the damping assembly comprises a first elastic piece (7) arranged in the blind hole, a ball (8) is arranged at one end of the first elastic piece (7), a limiting ring for preventing the ball (8) from sliding out is arranged at the top end of the blind hole, grooves for clamping the ball (8) are formed in one surface, in contact with the rack (6), of the inner portion of the baffle plate (1), and the number of the grooves is twice that of the ball (8).
4. Assembled temporary barrier for the construction of building engineering according to claim 3, characterized in that said first elastic element (7) is a spring.
5. The assembled temporary enclosure for the building engineering construction according to any one of claims 1 to 4, wherein a rectangular groove is formed in the back of the baffle (1), sliding grooves are formed in two side walls of the rectangular groove, a row of clamping holes are formed in the sliding grooves, a support rod (9) is arranged in the rectangular groove, rotating shafts (10) are slidably connected to two sides of one end of the support rod (9), a moving plate (11) is fixedly connected to one end of each rotating shaft (10), one end of each moving plate (11) extends out of one side of the corresponding support rod (9), the rotating shafts (10) can be clamped in the clamping holes, and second elastic members (12) used for enabling the rotating shafts (10) to pop out are installed in the support rods (9).
6. The assembled temporary fence for construction of building engineering according to claim 5, characterized in that the second elastic member (12) is a spring.
7. The assembled temporary fence for the construction of building engineering according to claim 5, characterized in that the other end of the supporting rod (9) is hinged with a fixed seat (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111521039.4A CN114033246A (en) | 2021-12-13 | 2021-12-13 | Assembled temporary enclosure for construction of constructional engineering |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111521039.4A CN114033246A (en) | 2021-12-13 | 2021-12-13 | Assembled temporary enclosure for construction of constructional engineering |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114033246A true CN114033246A (en) | 2022-02-11 |
Family
ID=80146753
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111521039.4A Pending CN114033246A (en) | 2021-12-13 | 2021-12-13 | Assembled temporary enclosure for construction of constructional engineering |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114033246A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114482692A (en) * | 2022-03-30 | 2022-05-13 | 张军伟 | Water conservancy construction safety facility device |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2792820A2 (en) * | 2013-03-26 | 2014-10-22 | Karl Schmelzer | Fence for catching balls and for delimiting ball game areas |
CN209740164U (en) * | 2019-03-14 | 2019-12-06 | 无锡翔华科技有限公司 | material grabbing device for bar cutting forming equipment |
CN210828614U (en) * | 2019-09-26 | 2020-06-23 | 宋玉亭 | But barrier is enclosed in whole removal probing construction |
CN213297412U (en) * | 2020-07-04 | 2021-05-28 | 安徽创都建设集团有限公司 | Fender is enclosed in swift dismouting of municipal construction |
CN215056096U (en) * | 2021-05-31 | 2021-12-07 | 晏剑明 | Safety protection rail for construction |
-
2021
- 2021-12-13 CN CN202111521039.4A patent/CN114033246A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2792820A2 (en) * | 2013-03-26 | 2014-10-22 | Karl Schmelzer | Fence for catching balls and for delimiting ball game areas |
CN209740164U (en) * | 2019-03-14 | 2019-12-06 | 无锡翔华科技有限公司 | material grabbing device for bar cutting forming equipment |
CN210828614U (en) * | 2019-09-26 | 2020-06-23 | 宋玉亭 | But barrier is enclosed in whole removal probing construction |
CN213297412U (en) * | 2020-07-04 | 2021-05-28 | 安徽创都建设集团有限公司 | Fender is enclosed in swift dismouting of municipal construction |
CN215056096U (en) * | 2021-05-31 | 2021-12-07 | 晏剑明 | Safety protection rail for construction |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114482692A (en) * | 2022-03-30 | 2022-05-13 | 张军伟 | Water conservancy construction safety facility device |
CN114482692B (en) * | 2022-03-30 | 2023-12-01 | 张军伟 | Water conservancy construction safety device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN114033246A (en) | Assembled temporary enclosure for construction of constructional engineering | |
CN110270960A (en) | Mounting plate is used in a kind of production of gearbox | |
CN116581698B (en) | Assembled mechanical interlocking fixed cable bridge and assembling method thereof | |
CN216434321U (en) | LED lamp aging testing equipment | |
CN212210911U (en) | Fixing device capable of adjusting height of solar panel | |
CN115852983A (en) | Subway station is excavation supporting device for construction based on L type ground is wall even | |
CN112482572B (en) | Assembling construction process for assembled steel structure house cross beam | |
CN215631854U (en) | Safety frame for civil engineering safety | |
CN111648479A (en) | Assembled building beam column connecting device | |
CN218510553U (en) | Power amplifier convenient to installation | |
CN219678865U (en) | Split assembled filter structure | |
CN218436795U (en) | Rail guard for municipal works | |
CN217053022U (en) | Large-displacement anti-seismic telescopic device | |
CN221627151U (en) | Column base anti-seismic structure | |
CN219795963U (en) | Effectual supporting structure shocks resistance | |
CN220580582U (en) | Bolt ball net frame combined type installation construction device | |
CN219365665U (en) | Guardrail structure for building construction | |
CN218914273U (en) | Scenic spot operation monitoring platform convenient to maintain | |
CN219832898U (en) | Battery box base | |
CN220644609U (en) | Assembled building frame structure | |
CN220379996U (en) | Split type water heater base of gas heating water heater | |
CN219798104U (en) | Mobilizable electron mark target | |
CN219931236U (en) | Assembled steel construction | |
CN221169018U (en) | Novel windproof movable fence | |
CN216880573U (en) | Cleaning equipment for different-diameter hole walls of deep hole casting die |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220211 |
|
RJ01 | Rejection of invention patent application after publication |