CN114006474A - Equipment control method, device, equipment, medium and system - Google Patents

Equipment control method, device, equipment, medium and system Download PDF

Info

Publication number
CN114006474A
CN114006474A CN202111281657.6A CN202111281657A CN114006474A CN 114006474 A CN114006474 A CN 114006474A CN 202111281657 A CN202111281657 A CN 202111281657A CN 114006474 A CN114006474 A CN 114006474A
Authority
CN
China
Prior art keywords
control
control strategy
remote
auditing
strategy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111281657.6A
Other languages
Chinese (zh)
Inventor
曹德发
李志华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Power Grid Co Ltd
Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangdong Power Grid Co Ltd
Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Power Grid Co Ltd, Meizhou Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangdong Power Grid Co Ltd
Priority to CN202111281657.6A priority Critical patent/CN114006474A/en
Publication of CN114006474A publication Critical patent/CN114006474A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00006Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment
    • H02J13/00016Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network characterised by information or instructions transport means between the monitoring, controlling or managing units and monitored, controlled or operated power network element or electrical equipment using a wired telecommunication network or a data transmission bus
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J13/00Circuit arrangements for providing remote indication of network conditions, e.g. an instantaneous record of the open or closed condition of each circuitbreaker in the network; Circuit arrangements for providing remote control of switching means in a power distribution network, e.g. switching in and out of current consumers by using a pulse code signal carried by the network
    • H02J13/00032Systems characterised by the controlled or operated power network elements or equipment, the power network elements or equipment not otherwise provided for
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/12Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/16Electric power substations
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S40/00Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them
    • Y04S40/12Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment
    • Y04S40/124Systems for electrical power generation, transmission, distribution or end-user application management characterised by the use of communication or information technologies, or communication or information technology specific aspects supporting them characterised by data transport means between the monitoring, controlling or managing units and monitored, controlled or operated electrical equipment using wired telecommunication networks or data transmission busses

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The embodiment of the invention discloses a device control method, a device, equipment, a medium and a system. The method comprises the following steps: obtaining an operation control strategy of a current transformer substation, and auditing the operation control strategy; when the operation control strategy is approved, the equipment remote control information of the equipment corresponding to the operation control strategy is approved; and when the equipment remote regulation remote control information is approved, generating a remote regulation remote control instruction, and sending the remote regulation remote control instruction to the operation system of the current transformer substation so as to respond to the remote regulation remote control instruction. The embodiment of the invention improves the accuracy of voltage control.

Description

Equipment control method, device, equipment, medium and system
Technical Field
The embodiment of the invention relates to an automatic voltage control technology of a power system, in particular to a device control method, a device, equipment, a medium and a system.
Background
An Automatic Voltage Control (AVC) system is an important means for achieving operation of power grid safety (increasing Voltage stability margin), economy (reducing network loss), and high quality (increasing Voltage qualification rate).
At present, a control unit can be formed by dividing equipment in a transformer substation, and the equipment in the transformer substation is controlled by the control unit to realize automatic voltage control.
However, the method cannot ensure the correctness of calculation and decision of the automatic voltage of the control substation, and once the decision is missed, the equipment can be damaged.
Disclosure of Invention
The embodiment of the invention provides a device control method, a device, equipment, a medium and a system, which are used for realizing accurate control on voltage.
In a first aspect, an embodiment of the present invention provides an apparatus control method, including:
obtaining an operation control strategy of a current transformer substation, and auditing the operation control strategy;
when the operation control strategy is approved, the equipment remote control information of the equipment corresponding to the operation control strategy is approved;
and when the equipment remote regulation remote control information is approved, generating a remote regulation remote control instruction, and sending the remote regulation remote control instruction to the operation system of the current transformer substation so as to respond to the remote regulation remote control instruction.
In a second aspect, an embodiment of the present invention further provides an apparatus for controlling a device, where the apparatus includes:
the operation control strategy auditing module is used for acquiring the operation control strategy of the current transformer substation and auditing the operation control strategy;
the remote-control information auditing module is used for auditing the equipment remote-control information of the equipment corresponding to the operation control strategy when the operation control strategy is approved;
and the remote regulation remote control instruction sending module is used for generating a remote regulation remote control instruction when the equipment remote regulation remote control information is approved, and sending the remote regulation remote control instruction to the current operation system of the transformer substation so as to respond to the remote regulation remote control instruction.
In a third aspect, an embodiment of the present invention further provides a computer device, including a memory, a processor, and a computer program stored in the memory and executable on the processor, where the processor executes the computer program to implement the device control method according to any embodiment of the present invention.
In a fourth aspect, the embodiment of the present invention further provides a computer-readable storage medium, on which a computer program is stored, where the program, when executed by a processor, implements the device control method according to any embodiment of the present invention.
In a fifth aspect, an embodiment of the present invention further provides an apparatus control system, including: an operating system of a substation and a computer device for executing the device control method according to any one of the embodiments of the present invention, the computer device being network-connected to the operating system;
the computer equipment is used for generating a remote control instruction and sending the remote control instruction to the operating system;
the operating system is used for responding to the remote control command so as to execute automatic voltage control.
According to the technical scheme provided by the embodiment of the invention, the operation control strategy of the transformer substation and the related control equipment are checked and verified after the operation control strategy is obtained, and the remote regulation remote control command is generated when the verification is passed, so that the operation system of the current transformer substation is instructed to respond to the remote regulation remote control command, the problem that automatic voltage control cannot be accurately realized is solved, and accurate control on voltage is realized.
Drawings
Fig. 1 is a flowchart of an apparatus control method according to an embodiment of the present invention;
fig. 2 is a flowchart of an apparatus control method according to a second embodiment of the present invention;
fig. 3a is a flowchart of an apparatus control method according to a third embodiment of the present invention;
fig. 3b is a flowchart of an apparatus control method according to a third embodiment of the present invention;
fig. 3c is a flowchart of an apparatus control method according to a third embodiment of the present invention;
fig. 4 is a block diagram of a device control apparatus according to a fourth embodiment of the present invention;
FIG. 5 is a schematic structural diagram of a computer device according to a fifth embodiment of the present invention;
fig. 6 is a schematic structural diagram of an apparatus control system according to a seventh embodiment of the present invention;
fig. 7 is a schematic structural diagram of a substation system according to a seventh embodiment of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples. It is to be understood that the specific embodiments described herein are merely illustrative of the invention and are not limiting of the invention. It should be further noted that, for the convenience of description, only some of the structures related to the present invention are shown in the drawings, not all of the structures.
Example one
Fig. 1 is a flowchart of an apparatus control method according to an embodiment of the present invention, where the present embodiment is applicable to a case where a substation performs automatic voltage control, and the method may be executed by an apparatus control device, and the apparatus may be implemented in a software and/or hardware manner. The apparatus can be configured in a terminal device or a server, and the method specifically includes:
and S110, acquiring the operation control strategy of the current transformer substation, and auditing the operation control strategy.
The transformer substation is a place for converting voltage and current, receiving electric energy and distributing electric energy in an electric power system, and mainly has the functions of converting voltage, distributing electric energy, controlling the flow direction of electric energy, adjusting voltage and the like.
The control strategy refers to a strategy and a method for controlling a certain system or instrument. In a transformer substation, a control strategy refers to a strategy of selecting a main transformer tap in the transformer substation for gear shifting or switching a capacitive reactor and the like. The main transformer tap is a tap on a primary side coil or a secondary side coil of the transformer and is used for adjusting secondary side voltage. According to the magnetic field theory, the voltage ratio of two sides of the transformer is in direct proportion to the turn ratio of the two coils, so that the secondary side voltage can be adjusted by adjusting the number of turns of the coils, and the tap is used for adjusting the number of turns of the coils. The control strategy comprises an open-loop control strategy, a semi-closed-loop control strategy and a closed-loop control strategy. The open-loop control strategy refers to outputting a strategy suggestion for controlling the equipment to be controlled. The operation control strategy refers to a control strategy for automatically controlling the transformer substation by the system. And auditing the operation control strategy refers to detecting whether the operation control strategy is accurate or not. The operation control strategy can be audited by adopting an auditing mode corresponding to the type aiming at the type of the operation control strategy.
The operation control strategy comprises a semi-closed loop control strategy and a closed loop control strategy; auditing the operation control strategy, which comprises the following steps: sending the semi-closed loop control strategy to an auditing terminal for auditing, and performing overtime auditing on the execution time of the semi-closed loop control strategy when the auditing terminal passes auditing; and performing overtime audit on the execution time of the closed-loop control strategy.
The semi-closed loop control strategy refers to that an operation control strategy is given and confirmed by monitoring personnel or a remote control remote regulation instruction is sent by an operation system of the current transformer substation after the confirmation of the monitoring personnel and dispatching personnel. The closed-loop control strategy is to give an operation control strategy and send a remote control and remote regulation instruction through an operation system of the current transformer substation. The remote control and remote regulation instruction refers to remote control of some switch control devices and remote regulation of remote control quantity, wherein the switch control devices comprise at least one of the following items: the system comprises a circuit breaker, a reactive power compensation device, a power regulation device, an on-load voltage regulation transformer tap, a hydraulic generator, a thermal power generating unit and the like. In an embodiment of the invention, the switching control device comprises a transformer tap or a capacitive reactor or the like.
In addition, the obtaining of the operation control strategy of the current substation comprises: setting parameters in a strategy calculation server, wherein the parameters at least comprise an automatic voltage control period, a current system control mode, a strategy state check period and a strategy timeout interval; when an automatic voltage control period comes, at least reading a power grid model and real-time measurement data from a monitoring system, constructing a complete topological structure and forming a control unit, wherein the topological structure comprises various devices in a transformer substation and the connection relation among the devices; and generating operation control strategies of all the control units according to the real-time data of the devices in the control units. A monitoring system of the transformer substation, also called as an SCADA (Supervisory Control And Data Acquisition) system, is responsible for acquiring all measurement Data information in the transformer substation. The measurement information is collected to a monitoring system, is correspondingly associated to corresponding equipment, and is displayed on a display screen for a dispatcher to monitor the operation condition of the transformer substation. Meanwhile, the measurement data can be packaged and provided for other module applications to use, for example, the AVC needs basic data collected from the substation when performing calculation, and the source of the basic data collected from the substation is not directly collected from actual equipment of the substation, but is measurement data of the substation obtained from the SCADA system.
In addition, the auditing terminal is used for manually auditing the operation control strategy. The timeout auditing is used for judging whether the processing time for operating the control strategy is too long, specifically, judging whether the time difference between the current time and the strategy generation time is less than the strategy timeout interval, if so, indicating that the time is not exceeded, otherwise, judging that the time is exceeded. If not, the operation control strategy is continuously processed, if yes, the operation control strategy is not continuously processed, and the operation control strategy is discarded and prompted to the user. In the embodiment of the present invention, the state of the operation control policy is configured to indicate whether the audit is passed, for example, whether the audit terminal passes the audit or whether the audit is passed after time out. And meanwhile, updating the current state of the operation control strategy according to the auditing condition.
The operation control strategy is checked manually, the semi-closed loop control strategy and the closed loop control strategy can be confirmed manually, overtime check is carried out on the semi-closed loop control strategy and the closed loop control strategy, the control strategy can be checked, processing time length confirmation can be carried out on the semi-closed loop control strategy and the closed loop control strategy, the operation control strategy is checked from the manual dimension and the time dimension, the accuracy of the operation control strategy can be improved, and accurate control of voltage adjustment is achieved.
And S120, when the operation control strategy is approved, the equipment remote control information of the equipment corresponding to the operation control strategy is approved.
Wherein, the equipment corresponding to the operation control strategy comprises a main transformer tap and/or a capacitive reactor. In the transformer substation, the reactive distribution condition in the transformer substation is changed by selecting main transformer tap gear shifting or capacitor reactor switching, so that the purpose of voltage regulation is also achieved. And the equipment remote control information auditing module is used for judging whether to send a remote control instruction or not so as to control the equipment corresponding to the operation control strategy.
Wherein, examine the equipment remote control information of the equipment that the operation control strategy corresponds to, include: inquiring equipment remote control information of equipment corresponding to the operation control strategy in an operation system of the current transformer substation; and when the equipment remote control information of the corresponding equipment is inquired, determining that the equipment remote control information is approved.
The operation system of the current transformer substation is responsible for collecting all measurement data information in the transformer substation. The measurement information is collected to a monitoring system, is correspondingly associated to corresponding equipment, and is displayed on a display screen for a dispatcher to monitor the operation condition of the transformer substation. The device Remote control information of the device corresponding to the operation control strategy at least includes a Remote control point number, an RTU (Remote Terminal Unit) number and a link number, and a Remote control instruction can be generated according to the information. Inquiring the device remote control information of the device corresponding to the operation control strategy in the operation system of the current transformer substation refers to reading the device remote control information from the operation system of the current transformer substation. And the equipment remote control information audit is used for detecting whether the equipment remote control information is complete or not so as to generate a remote control instruction.
It should be noted that the determination that the device remote control information is approved means that the device remote control information is approved when the corresponding device remote control information is read from the power grid monitoring, and otherwise, the device remote control information is not approved. The state of the operation control strategy configured in the embodiment of the invention can also be used for indicating whether the equipment remote control information is approved or not, and updating the current state of the operation control strategy according to whether the equipment remote control information is approved or not. The equipment remote control information is approved to show that the equipment remote control information can be extracted from the current transformer substation operation system so as to generate a remote control instruction; the device remote control information is not checked, which indicates that the device remote control information extracted from the current transformer substation operation system is empty or incomplete, a remote control command cannot be generated, the current transformer substation operation system cannot be controlled, and voltage control cannot be realized.
By auditing the remote control and remote measurement information of the equipment, the remote control and remote measurement instruction can be accurately generated and the normal operation of the current transformer substation operation system is ensured.
And S130, when the equipment remote regulation remote control information is approved, generating a remote regulation remote control instruction, and sending the remote regulation remote control instruction to the current operation system of the transformer substation so as to respond to the remote regulation remote control instruction.
The remote control command is used for controlling switch control equipment in an operation system of the current transformer substation, and specifically, controlling a transformer tap or a capacitive reactor and the like in the operation system of the current transformer substation. Responding to the remote control remote regulation instruction means that the remote control remote regulation instruction is sent to a rear operation system in an operation system of the current transformer substation and the rear operation system executes the remote control remote regulation instruction. And whether the operation system of the current transformer substation successfully receives the remote control command or not and whether the remote control command is successfully responded can also be detected. The state of the operation control strategy configured in the embodiment of the invention can also be used for indicating whether the remote regulation remote control command is successfully received and whether the remote regulation remote control command is successfully responded, and updating the current state of the operation control strategy according to whether the operation system of the current transformer substation successfully receives the remote regulation remote control command and whether the remote regulation remote control command is successfully responded.
According to the technical scheme provided by the embodiment of the invention, the operation control strategy and related control equipment are checked and verified after the operation control strategy of the transformer substation is obtained, and the remote regulation remote control command is generated when the verification is passed, so that the current operation system of the transformer substation is instructed to respond to the remote regulation remote control command, the problem that automatic voltage control cannot be accurately realized is solved, and accurate control on voltage is realized.
On the basis of the technical scheme, sending the semi-closed loop control strategy to the auditing terminal to audit the preference may include: acquiring the management authority of the current transformer substation; when the management authority is determined to be the monitoring authority, the semi-closed loop control strategy is sent to the monitoring terminal for auditing, and an auditing result of the auditing terminal is determined according to an auditing result fed back by the monitoring terminal; and when the management authority is the scheduling authority, sending the semi-closed loop control strategy to a monitoring terminal for auditing, sending the semi-closed loop control strategy to a scheduling terminal for auditing when the monitoring terminal passes the auditing, and determining an auditing result of the auditing terminal according to an auditing result fed back by the scheduling terminal.
The management authority of the current transformer substation can be read from the control unit, and the management authority comprises a monitoring authority and a scheduling authority. The monitoring authority refers to the functions of debugging, monitoring and the like of remote control quantity which can be realized by monitoring personnel. The scheduling authority refers to the function that scheduling personnel can control some remote switch control devices.
The auditing terminal comprises a monitoring terminal and a scheduling terminal; the monitoring terminal is working equipment provided for monitoring personnel, and can realize the work of debugging, monitoring and the like on remote control quantity; the dispatching terminal is a working device provided for dispatching personnel, and can realize the work of controlling some remote switch control devices and the like. The auditing of the auditing terminal refers to auditing the current state of the strategy, namely, the monitoring personnel or the scheduling personnel select and confirm or cancel the received operation control strategy information by using the monitoring terminal or the scheduling terminal, the terminal feeds back the selection result to the control unit, and the control unit updates the strategy state according to the selection result.
Different management authorities are configured for the transformer substation, the semi-closed loop control strategy is audited under different management authorities, and the auditing mode of the semi-closed loop control strategy is subdivided, so that the auditing flexibility of the semi-closed loop control strategy can be improved, different application scenes are adapted, the correctness of the operation control strategy is improved, and the accurate control of the voltage is realized.
Example two
Fig. 2 is a flowchart of an apparatus control method provided in the second embodiment of the present invention, where on the basis of the foregoing embodiments, this embodiment preferably further adds, before acquiring the operation control policy of the current substation, an operation control policy of the current substation, and further includes: acquiring a control mode associated with a current transformer substation; the control modes include at least one of: the method comprises the following steps that the control mode of an automatic control system, the control mode of a current transformer substation in the automatic control system and the control mode of equipment to be controlled of the current transformer substation in the automatic control system are controlled, wherein the equipment to be controlled comprises a main transformer tap or a capacitive reactor; screening out one control mode from the control modes, and determining the control mode as a target control strategy for the equipment to be controlled; the target control strategy comprises an operation control strategy or an open-loop control strategy; and when the target control strategy is determined to be the operation control strategy, determining the equipment to be controlled as the equipment corresponding to the operation control strategy. The specific method comprises the following steps:
s210, obtaining a control mode associated with the current transformer substation; the associated control modes include at least one of: the control method comprises the steps of controlling the automatic control system, controlling the automatic control system to a current transformer substation and controlling to-be-controlled equipment of the automatic control system to the current transformer substation, wherein the to-be-controlled equipment comprises a main transformer tap or a capacitive reactor.
The obtaining of the control mode associated with the current substation refers to reading the control mode associated with the current substation from the control unit, wherein the control mode at least includes a system level control mode, a site level control mode and an equipment level control mode, and the system level is a control mode of an automatic control system (AVC), the site level is a control mode of the current substation in the AVC, and the equipment level is a control mode of equipment to be controlled of the current substation in the AVC. In this embodiment, each associated control mode includes an open-loop control mode, a semi-closed-loop control mode, and a closed-loop control mode, where the open-loop control mode has the highest priority, the semi-closed-loop control mode is the next, and the closed-loop control mode is the last, but not limited to this setting order.
S220, screening out one control mode from the control modes, and determining the control mode as a target control strategy for the equipment to be controlled; the target control strategy includes an operational control strategy or an open loop control strategy.
In this embodiment, screening out one control mode among the control modes refers to comparing the control modes associated with each control mode associated with the current substation, and selecting one control mode with the highest priority from the control modes associated with each control mode, but is not limited to this selection mode. For example, in each associated control mode, as long as there is an open-loop control mode, the target control strategy is determined to be an open-loop control strategy; if each associated control mode comprises a semi-closed-loop control mode and a closed-loop control mode, determining that the target control strategy is a semi-closed-loop control strategy; and if the control mode associated with each item is one control mode, determining that the control strategy corresponding to the control mode is the target control strategy.
The target control strategy is a control strategy determined according to the control mode, and specifically may be an open-loop control strategy or an operation control strategy, where the operation control strategy includes a semi-closed-loop control strategy or a closed-loop control strategy.
In addition, the open-loop control strategy refers to giving analysis information of the control strategy to obtain a strategy control suggestion, and does not issue a control instruction and need not to control equipment in an operation system of the current transformer substation.
Optionally, when the target control strategy is determined to be the open-loop control strategy, the log information is output.
The log information refers to the operation control policy content. By outputting the log information, the working personnel can clearly know the content of the operation control strategy, the accuracy of the operation control strategy is judged, whether equipment in an operation system of the current transformer substation is controlled or not is conveniently and manually determined, and the accurate control of the voltage is realized.
And S230, when the target control strategy is determined to be the operation control strategy, determining the device to be controlled as the device corresponding to the operation control strategy.
The device to be controlled is user-selected. The equipment to be controlled is the main transformer tap and/or the capacitive reactor. The equipment to be controlled is a main transformer tap and a capacitive reactor, and can be sequentially controlled aiming at the two equipment.
According to the technical scheme, the control modes of the current transformer substation are described from different angles by acquiring the control modes associated with the current transformer substation, and one control mode is selected from the control modes, so that a control strategy, namely a target control strategy, suitable for an operation system of the current transformer substation and equipment to be controlled of the current transformer substation corresponding to the target control strategy are determined, the diversity of the control modes of the equipment to be controlled of the current transformer substation is increased, and the accurate control of voltage is ensured.
EXAMPLE III
Fig. 3a to fig. 3c are flowcharts of an apparatus control method according to a third embodiment of the present invention, and this embodiment describes the apparatus control method through a specific embodiment on the basis of the foregoing embodiments, but is not limited to the case of this embodiment.
An apparatus control method of this embodiment includes the steps of:
1) in a policy calculation server, an automatic voltage control period T is set in a policy calculation threadcThe open loop of the control mode is represented by 1, the semi-closed loop is represented by 2, the closed loop is represented by 3, and the current control mode C of the system is recordedSysSetting a policy state check period T in the policy checking execution threadsAnd T iss<TcSetting a policy timeout interval Tout
2) When the automatic voltage control cycle comes, the policy calculation thread generates an operation control policy, specifically as shown in fig. 3a to 3c, the specific process includes:
2.1) reading a power grid model and real-time measurement data from an operation system of the current transformer substation, wherein the data comprises bus voltage measurement, switch disconnecting link state, transformer active and reactive measurement, reactive measurement of a capacitive reactor and the like, constructing a complete topological structure of the transformer substation, and forming a control unit of the transformer substation;
2.2) generating operation control strategies of all control units according to the real-time data of the equipment in the control units, comprising the following steps:
2.2.1) if the control unit UiIf the internal bus voltage or the main transformer power factor has out-of-limit and controllable equipment exists, generating a strategy S of the control unitjWherein, Ui∈Stm,StmIs a control unit UiSubstationA station; selecting device DkControl is effected, wherein, if DkShifting if the main transformer tap is changed, if DkSwitching is carried out for the capacitive reactor; setting the policy generation time to be expressed as
Figure BDA0003331296880000121
Recording the current control mode of the substation
Figure BDA0003331296880000122
Current control mode of control unit
Figure BDA0003331296880000123
Control mode of equipment to be controlled of current transformer substation
Figure BDA0003331296880000124
Setting the management authority of the transformer substation, wherein monitoring management is represented by 1, dispatching management is represented by 2, and recording the management authority of the transformer substation
Figure BDA0003331296880000125
2.2.2) initializing policy Current State
Figure BDA0003331296880000126
2.2.3) checking the policy operation type, order
Figure BDA0003331296880000127
The operation type of the strategy is the minimum value of AVC, the current transformer substation in AVC and the control mode of the equipment to be controlled of the current transformer substation in AVC;
2.2.4) updating the current state of the strategy if
Figure BDA0003331296880000128
Then order
Figure BDA0003331296880000129
That is, the current state of the strategy is 'open loop, to be issued'; if it is
Figure BDA00033312968800001210
Then order
Figure BDA00033312968800001211
Namely the current state of the strategy is 'semi-closed loop, to be confirmed'; if it is
Figure BDA00033312968800001212
Then order
Figure BDA00033312968800001213
Namely, the current state of the strategy is 'closed loop, to be executed';
3) when the policy state check period comes, the policy checking execution thread processes the existing operation control policy, and the method comprises the following steps:
3.1) checking the current state of the operation control strategy;
3.1.1) if
Figure BDA00033312968800001214
Outputting the operation control strategy content as log information, and updating the current state of the operation control strategy to order
Figure BDA00033312968800001215
That is, the current policy state is "open loop, published";
3.1.2) if
Figure BDA00033312968800001216
Checking the corresponding substation management authority
Figure BDA00033312968800001217
3.1.2.1) if
Figure BDA00033312968800001218
If the station management authority belongs to monitoring, the strategy checking execution thread sends the semi-closed loop control strategy to a monitoring terminal scheduling terminal in a message form and pops up a semi-closed loop control strategy confirmation window, and the monitoring personnel selects to confirm or cancel the strategy, if the monitoring personnel selects to confirm or cancel the strategy, the strategy checking execution thread sends the semi-closed loop control strategy to the monitoring terminal scheduling terminal in a message formThe control personnel confirms the execution of the semi-closed loop control strategy and updates
Figure BDA0003331296880000131
Namely the current state of the strategy is 'semi-closed loop, and monitoring is confirmed'; if the monitoring personnel cancels the strategy execution, the strategy is updated
Figure BDA0003331296880000132
Namely the current state of the strategy is 'semi-closed loop, and monitoring is cancelled'; the monitoring terminal returns the strategy state result to the strategy checking execution thread;
3.1.2.2) if
Figure BDA0003331296880000133
That is, the management authority of the station belongs to scheduling, the strategy checking execution thread sends the semi-closed loop control strategy to the monitoring terminal in a message form and pops up a semi-closed loop control strategy confirmation window, and monitoring personnel confirm and update the semi-closed loop control strategy
Figure BDA0003331296880000134
Namely, the current state of the strategy is 'semi-closed loop, monitoring is confirmed, and scheduling is confirmed'; the monitoring terminal returns the strategy state result to the strategy checking execution thread;
3.1.3) if
Figure BDA0003331296880000135
Checking whether the semi-closed loop control strategy is overtime or not, and recording the current time tNowIf, if
Figure BDA0003331296880000136
Step 3.2) is entered, otherwise update is done
Figure BDA0003331296880000137
I.e. the current state of the policy is "give up overtime";
3.1.4) if
Figure BDA0003331296880000138
The policy check execution thread removes the semi-closed loop control policy fromSending the information form to a dispatching terminal and popping up a semi-closed loop control strategy confirmation window, selecting confirmation or cancellation by a dispatcher, and updating if the dispatcher confirms the strategy execution
Figure BDA0003331296880000139
Namely, the current state of the strategy is 'semi-closed loop, and the scheduling is confirmed'; if the dispatcher cancels the execution of the semi-closed loop control strategy, updating
Figure BDA00033312968800001310
Namely, the current state of the strategy is 'semi-closed loop, and scheduling is cancelled'; the scheduling terminal returns the strategy state result to the strategy checking execution thread;
3.1.5) if
Figure BDA00033312968800001311
Checking whether the semi-closed loop control strategy is overtime or not, and recording the current time tNowIf, if
Figure BDA00033312968800001312
Step 3.2) is entered, otherwise update is done
Figure BDA00033312968800001313
I.e. the current state of the policy is "give up overtime";
3.1.6) if
Figure BDA00033312968800001314
Checking whether the closed-loop control strategy is overtime or not, and recording the current time tNowIf, if
Figure BDA0003331296880000141
Step 3.2) is entered, otherwise update is done
Figure BDA0003331296880000142
I.e. the current state of the policy is "give up overtime";
3.2) checking remote control information of remote regulation of equipment, comprising:
3.2.1) when device DkBeing a main transformer tap, e.g.If the remote adjusting point number, the RTU number and the link number of the equipment can be read from the current transformer substation operation system to form a remote adjusting instruction, then the step 3.3 is carried out; otherwise update
Figure BDA0003331296880000143
That is, the current state of the policy is "transmission failure";
3.2.2) when device DkIf the capacitor reactor is a capacitive reactor, reading a remote regulation point number, an RTU number and a link number of a corresponding switch of the equipment from a current transformer substation operation system to form a remote control instruction, and entering step 3.3); otherwise update
Figure BDA0003331296880000144
That is, the current state of the policy is "transmission failure";
3.3) sending a remote regulation remote control instruction to the current transformer substation operation system, and if the preposed system responds to the received instruction successfully, updating
Figure BDA0003331296880000145
That is, the current state of the policy is "successful transmission"; step 3.4) is entered; otherwise update
Figure BDA0003331296880000146
That is, the current state of the policy is "transmission failure";
3.4) waiting for the execution result of the remote control instruction of the front-end system, and if the execution is successful, updating
Figure BDA0003331296880000147
Namely, the current state of the strategy is 'execution success'; otherwise update
Figure BDA0003331296880000148
Namely, the current state of the strategy is 'execution failure';
according to the technical scheme of the embodiment of the invention, the operation control strategy is generated by reading the power grid model and real-time measurement data, and is checked and executed according to the control modes of the current transformer substation in AVC and the equipment to be controlled of the current transformer substation in AVC, the operation control strategy is monitored and scheduled for two-stage auditing, so that the accuracy of the operation control strategy in the initial stage of automatic voltage control of the current transformer substation in AVC and the control equipment in AVC is ensured.
Example four
Fig. 4 is a schematic structural diagram of an apparatus control device according to a fourth embodiment of the present invention, where the apparatus may execute the apparatus control method according to the foregoing embodiment, and the apparatus may include: the operation control strategy auditing module 410, the remote control information auditing module 420 and the remote control instruction sending module 430.
The operation control strategy auditing module 410 is used for acquiring the operation control strategy of the current transformer substation and auditing the operation control strategy;
the remote control information auditing module 420 is used for auditing the equipment remote control information of the equipment corresponding to the operation control strategy when the operation control strategy is approved;
and the remote regulation remote control instruction sending module 430 is configured to generate a remote regulation remote control instruction when the equipment remote regulation remote control information is approved, and send the remote regulation remote control instruction to the current operation system of the substation so as to respond to the remote regulation remote control instruction.
According to the technical scheme provided by the embodiment of the invention, the operation control strategy and related control equipment are checked and verified after the operation control strategy of the transformer substation is obtained, and the remote regulation remote control command is generated when the verification is passed, so that the current operation system of the transformer substation is instructed to respond to the remote regulation remote control command, the problem that automatic voltage control cannot be accurately realized is solved, and accurate control on voltage is realized.
In the above apparatus, optionally, the operation control strategy includes a semi-closed loop control strategy or a closed loop control strategy;
auditing the operation control strategy, which comprises the following steps:
sending the semi-closed loop control strategy to an auditing terminal for auditing, and performing overtime auditing on the execution time of the semi-closed loop control strategy when the auditing terminal passes auditing;
and performing overtime audit on the execution time of the closed-loop control strategy.
In the above apparatus, optionally, the sending the semi-closed loop control policy to an audit terminal for auditing includes:
acquiring the management authority of the current transformer substation;
when the management authority is determined to be the monitoring authority, the semi-closed loop control strategy is sent to the monitoring terminal for auditing, and an auditing result of the auditing terminal is determined according to an auditing result fed back by the monitoring terminal;
and when the management authority is the scheduling authority, sending the semi-closed loop control strategy to a monitoring terminal for auditing, sending the semi-closed loop control strategy to a scheduling terminal for auditing when the monitoring terminal passes the auditing, and determining an auditing result of the auditing terminal according to an auditing result fed back by the scheduling terminal.
In the above apparatus, optionally, the auditing the device remote control information of the device corresponding to the operation control policy is performed, including:
inquiring equipment remote control information of equipment corresponding to the operation control strategy in an operation system of the current transformer substation;
and when the equipment remote control information of the corresponding equipment is inquired, determining that the equipment remote control information is approved.
In the above apparatus, optionally, before obtaining the operation control policy of the current substation, the method further includes:
obtaining a control mode associated with the current transformer substation, wherein the control mode comprises at least one of the following items: the method comprises the following steps that a control mode of an automatic control system, a control mode of a current transformer substation in the automatic control system and a control mode of equipment to be controlled of the current transformer substation in the automatic control system are set, wherein the equipment to be controlled comprises a main transformer tap or a capacitive reactor;
screening one control mode from the control modes, and determining the control mode as a target control strategy for the equipment to be controlled, wherein the target control strategy comprises an operation control strategy or an open-loop control strategy;
and when the target control strategy is determined to be the operation control strategy, determining the equipment to be controlled as the equipment corresponding to the operation control strategy.
In the above apparatus, optionally, when the target control strategy is determined to be an open-loop control strategy, the log information is output.
The apparatus provided in this embodiment constitutes a module capable of implementing each step in the device control apparatus. The operation control strategy is audited by the operation control strategy auditing module and the equipment remote control information auditing module, so that the correctness of the control strategy is ensured, and the accurate control of the voltage is realized.
EXAMPLE five
Fig. 5 is a schematic structural diagram of a computer apparatus according to a fifth embodiment of the present invention, as shown in fig. 5, the apparatus includes a processor 50, a memory 51, an input device 52, and an output device 53; the number of processors 50 in the device may be one or more, and one processor 50 is taken as an example in fig. 5; the processor 50, the memory 51, the input device 52 and the output device 53 in the apparatus may be connected by a bus or other means, which is exemplified in fig. 5.
The memory 51 is used as a computer-readable storage medium for storing software programs, computer-executable programs, and modules, such as program modules corresponding to the apparatus control method in the embodiment of the present invention (for example, an operation control policy auditing module 410, a remote control information auditing module 420, and a remote control instruction transmitting module 430 in the apparatus control device). The processor 50 executes various functional applications and data processing of the device by executing software programs, instructions, and modules stored in the memory 51, that is, implements the device control method described above.
The memory 51 may mainly include a storage program area and a storage data area, wherein the storage program area may store an operating system, an application program required for at least one function; the storage data area may store data created according to the use of the terminal, and the like. Further, the memory 51 may include high speed random access memory, and may also include non-volatile memory, such as at least one magnetic disk storage device, flash memory device, or other non-volatile solid state storage device. In some examples, the memory 51 may further include memory located remotely from the processor 50, which may be connected to the device over a network. Examples of such networks include, but are not limited to, the internet, intranets, local area networks, mobile communication networks, and combinations thereof.
The input device 52 is operable to receive input numeric or character information and to generate key signal inputs relating to user settings and function controls of the apparatus. The output device 53 may include a display device such as a display screen.
EXAMPLE six
The invention also provides, in a sixth implementation, a storage medium containing computer-executable instructions for performing, when executed by a computer processor, a method for controlling a device, the method comprising:
obtaining an operation control strategy of the current transformer substation, and auditing the operation control strategy; when the operation control strategy is approved, the equipment remote control information of the equipment corresponding to the operation control strategy is audited; and when the equipment remote regulation remote control information is approved, generating a remote regulation remote control instruction, and sending the remote regulation remote control instruction to the current operation system of the transformer substation so as to respond to the remote regulation remote control instruction.
Of course, the storage medium provided by the embodiment of the present invention contains computer-executable instructions, and the computer-executable instructions are not limited to the method operations described above, and may also execute the relevant operations in the device control method provided by any embodiment of the present invention.
From the above description of the embodiments, it is obvious for those skilled in the art that the present invention can be implemented by software and necessary general hardware, and certainly, can also be implemented by hardware, but the former is a better embodiment in many cases. Based on such understanding, the technical solutions of the present invention may be embodied in the form of a software product, which can be stored in a computer-readable storage medium, such as a floppy disk, a Read-Only Memory (ROM), a Random Access Memory (RAM), a FLASH Memory (FLASH), a hard disk or an optical disk of a computer, and includes several instructions for enabling a computer device (which may be a personal computer, a server, or a network device) to execute the methods according to the embodiments of the present invention.
It should be noted that, in the embodiment of the above search apparatus, each included unit and module are merely divided according to functional logic, but are not limited to the above division as long as the corresponding functions can be implemented; in addition, specific names of the functional units are only for convenience of distinguishing from each other, and are not used for limiting the protection scope of the present invention.
EXAMPLE seven
Fig. 6 is a schematic structural diagram of an equipment control system according to a seventh embodiment of the present invention, where the apparatus may execute the equipment control method according to the foregoing embodiment, and the equipment control system includes: a computer device 61 and an operating system 62 of the current substation, the computer device executing the device control method of the above embodiment, the computer device being network-connected to the operating system; the computer equipment is used for generating a remote adjusting remote control instruction and sending the remote adjusting remote control instruction to the operating system; the operation system is used for responding to a remote control command so as to execute automatic voltage control.
Wherein, the computer device executing the device control method of the above embodiment at least comprises a policy calculation server; the operating system of the substation is referred to as the front-end system 75. The computer device 61 and the operating system 62 of the current substation may be connected by a bus or other means, and fig. 6 illustrates the bus connection.
Fig. 7 is a schematic structural diagram of a substation system according to an embodiment of the present invention. The substation System includes a policy calculation server 71, a monitoring terminal 72, a scheduling terminal 73, an EMS System 74(Energy Management System), and a front-end System 75. The main work of the EMS system includes power system stabilization, voltage and voltage regulation, power system operation, power grid dispatching automation, power system communication and the like, and specifically, the EMS system controls devices mounted on a bus and provides energy. It should be noted that the policy calculation server 71, the monitoring terminal 72, the scheduling terminal 73, the EMS system 74, and the front-end system 75 may be connected by a bus or other means, and fig. 7 illustrates the connection by a bus as an example. The front-end system 75 is the aforementioned operating system of the current substation. The policy calculation server 71 is a computer device that executes the device control method of the above-described embodiment.
The equipment control system provided by the embodiment of the invention can realize the acquisition of the operation control strategy of the transformer substation, the verification and the audit of the operation control strategy and related control equipment, and the generation of the remote regulation remote control command when the audit is passed, and the indication of the current operation system of the transformer substation to respond to the remote regulation remote control command, thereby solving the problem that the automatic voltage control cannot be accurately realized and realizing the accurate control of the voltage.
It is to be noted that the foregoing is only illustrative of the preferred embodiments of the present invention and the technical principles employed. It will be understood by those skilled in the art that the present invention is not limited to the particular embodiments described herein, but is capable of various obvious changes, rearrangements and substitutions as will now become apparent to those skilled in the art without departing from the scope of the invention. Therefore, although the present invention has been described in greater detail by the above embodiments, the present invention is not limited to the above embodiments, and may include other equivalent embodiments without departing from the spirit of the present invention, and the scope of the present invention is determined by the scope of the appended claims.

Claims (10)

1. An apparatus control method characterized by comprising:
obtaining an operation control strategy of a current transformer substation, and auditing the operation control strategy;
when the operation control strategy is approved, the equipment remote control information of the equipment corresponding to the operation control strategy is approved;
and when the equipment remote regulation remote control information is approved, generating a remote regulation remote control instruction, and sending the remote regulation remote control instruction to the operation system of the current transformer substation so as to respond to the remote regulation remote control instruction.
2. The method of claim 1, wherein the operational control strategy comprises a semi-closed loop control strategy or a closed loop control strategy;
the auditing the operation control strategy comprises:
sending the semi-closed loop control strategy to an auditing terminal for auditing, and performing overtime auditing on the execution time of the semi-closed loop control strategy when the auditing terminal passes auditing;
and performing overtime audit on the execution time of the closed-loop control strategy.
3. The method according to claim 2, wherein the sending the semi-closed loop control strategy to an audit terminal for auditing comprises:
acquiring the management authority of the current transformer substation;
when the management authority is determined to be the monitoring authority, the semi-closed loop control strategy is sent to a monitoring terminal for auditing, and an auditing result of the auditing terminal is determined according to an auditing result fed back by the monitoring terminal;
and when the management authority is a scheduling authority, sending the semi-closed loop control strategy to the monitoring terminal for auditing, sending the semi-closed loop control strategy to the scheduling terminal for auditing when the monitoring terminal passes the auditing, and determining an auditing result of the auditing terminal according to an auditing result fed back by the scheduling terminal.
4. The method of claim 1, wherein the reviewing of the device telemetry remote control information of the device corresponding to the operation control policy comprises:
inquiring equipment remote control information of equipment corresponding to the operation control strategy in the operation system of the current transformer substation;
and when the equipment remote control information of the corresponding equipment is inquired, determining that the equipment remote control information is approved.
5. The method of claim 1, further comprising, prior to obtaining the operational control strategy for the current substation:
acquiring a control mode associated with the current transformer substation; the associated control pattern comprises at least one of: the method comprises the following steps that the control mode of an automatic control system, the control mode of a current transformer substation in the automatic control system and the control mode of equipment to be controlled of the current transformer substation in the automatic control system are controlled, wherein the equipment to be controlled comprises a main transformer tap or a capacitive reactor;
screening out one control mode from the associated control modes, and determining the control mode as a target control strategy for the equipment to be controlled; the target control strategy comprises an operation control strategy or an open-loop control strategy;
and when the target control strategy is determined to be the operation control strategy, determining the equipment to be controlled as the equipment corresponding to the operation control strategy.
6. The method of claim 5, further comprising:
and outputting log information when the target control strategy is determined to be an open-loop control strategy.
7. An apparatus control device, characterized by comprising:
the operation control strategy auditing module is used for acquiring the operation control strategy of the current transformer substation and auditing the operation control strategy;
the remote-control information auditing module is used for auditing the equipment remote-control information of the equipment corresponding to the operation control strategy when the operation control strategy is approved;
and the remote regulation remote control instruction sending module is used for generating a remote regulation remote control instruction when the equipment remote regulation remote control information is approved, and sending the remote regulation remote control instruction to the current operation system of the transformer substation so as to respond to the remote regulation remote control instruction.
8. A computer device, comprising:
one or more processors;
storage means for storing one or more programs which, when executed by the one or more processors, cause the one or more processors to implement the device control method according to any one of claims 1 to 6.
9. A computer-readable storage medium on which a computer program is stored, the program, when being executed by a processor, implementing the device control method according to any one of claims 1 to 6.
10. An appliance control system, comprising: an operating system of a substation and a computer device performing the device control method of any of claims 1-6, the computer device being network connected to the operating system;
the computer equipment is used for generating a remote control instruction and sending the remote control instruction to the operating system;
the operating system is used for responding to the remote control command so as to execute automatic voltage control.
CN202111281657.6A 2021-11-01 2021-11-01 Equipment control method, device, equipment, medium and system Pending CN114006474A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111281657.6A CN114006474A (en) 2021-11-01 2021-11-01 Equipment control method, device, equipment, medium and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111281657.6A CN114006474A (en) 2021-11-01 2021-11-01 Equipment control method, device, equipment, medium and system

Publications (1)

Publication Number Publication Date
CN114006474A true CN114006474A (en) 2022-02-01

Family

ID=79926022

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111281657.6A Pending CN114006474A (en) 2021-11-01 2021-11-01 Equipment control method, device, equipment, medium and system

Country Status (1)

Country Link
CN (1) CN114006474A (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104750092A (en) * 2013-12-31 2015-07-01 上海可鲁系统软件有限公司 Automatic diagnosis method for remote control/ remote transferring instruction transmission fault of industrial control system
CN109217472A (en) * 2018-09-21 2019-01-15 国网福建省电力有限公司 A kind of monitoring information verification automated closed-loop joint debugging method
CN109687583A (en) * 2018-12-24 2019-04-26 国网北京市电力公司 A kind of power grid AVC automatic control Interlocking Methods
CN109782724A (en) * 2019-02-25 2019-05-21 国家电网有限公司 The control method and terminal device of anti-misoperation locking

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104750092A (en) * 2013-12-31 2015-07-01 上海可鲁系统软件有限公司 Automatic diagnosis method for remote control/ remote transferring instruction transmission fault of industrial control system
CN109217472A (en) * 2018-09-21 2019-01-15 国网福建省电力有限公司 A kind of monitoring information verification automated closed-loop joint debugging method
CN109687583A (en) * 2018-12-24 2019-04-26 国网北京市电力公司 A kind of power grid AVC automatic control Interlocking Methods
CN109782724A (en) * 2019-02-25 2019-05-21 国家电网有限公司 The control method and terminal device of anti-misoperation locking

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李世群;宋巍;郭飞;康莹;: "变电站SVG接入AVC系统控制策略及改进应用", 电气工程学报, no. 10, 25 October 2017 (2017-10-25) *

Similar Documents

Publication Publication Date Title
AU2011238726B2 (en) Systems and method for obtaining a load model and related parameters based on load dynamics
CN108879706A (en) A kind of automatic voltage control system
CN112700144B (en) Transformer substation operation state risk assessment method, device, equipment and storage medium
CN111461579B (en) Full-voltage-grade power grid real-time risk assessment system and method
CN104407577A (en) Intelligent check anti-maloperation method based on real-time trend
CN116859768A (en) Energy scheduling method and device applied to smart home
CN117578740B (en) Digital intelligent electricity management system and method
CN114006474A (en) Equipment control method, device, equipment, medium and system
CN112596651A (en) Acceptance method, device, equipment and storage medium for power distribution terminal debugging
KR20100007159A (en) System and method for acquiring power monitoring data using distributed network protocol
Schuett et al. Graphical User Interface of an Aggregation System to control a Multitude of Distributed Generation during Power System Restoration
JPH10164756A (en) Method and apparatus for controlling power system
Partinen et al. Tuning of power plant voltage and reactive power controllers considering equivalent short circuit ratio
CN110707759B (en) Safety and stability control method for wind power high-proportion power grid
CN114330865A (en) Power grid reserve capacity prediction method and system, computer equipment and storage medium
CN110376944B (en) Sequence control abnormal interrupt processing method
CN104268694B (en) A kind of active distribution network control system evaluation method and active distribution network planing method
JP2022544633A (en) Methods and systems for an overall framework of parameter tuning for disasters in interconnected microgrid systems
KR102232965B1 (en) System and method for autonomous operation of microgrids in emergency situation
KR102057643B1 (en) Method for Managing Visit Repair Service of Distribution Board Device in Network, and Managing Server Used Therein
EP3330850A1 (en) Apparatus for compiling script
CN113991694B (en) Reactive compensation equipment operation method, device, equipment and storage medium
CN115358630A (en) Space mission control method and system based on intelligent closed-loop control
Narvaez Implementation and tuning of the automatic generation control in the Energy National Control Center of Ecuador-CENACE
JP2678258B2 (en) Power system voltage / reactive power control method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination