CN114000656A - Partially unbonded grouting sleeve prefabricated assembly connecting structure and construction method - Google Patents

Partially unbonded grouting sleeve prefabricated assembly connecting structure and construction method Download PDF

Info

Publication number
CN114000656A
CN114000656A CN202111430337.2A CN202111430337A CN114000656A CN 114000656 A CN114000656 A CN 114000656A CN 202111430337 A CN202111430337 A CN 202111430337A CN 114000656 A CN114000656 A CN 114000656A
Authority
CN
China
Prior art keywords
sleeve
pier
grouting sleeve
grouting
steel bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111430337.2A
Other languages
Chinese (zh)
Inventor
张霁颜
陈乐纯
张鹏辉
吴成峻
郝晨宇
高奇
侯力元
王志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN202111430337.2A priority Critical patent/CN114000656A/en
Publication of CN114000656A publication Critical patent/CN114000656A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/162Connectors or means for connecting parts for reinforcements
    • E04C5/163Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
    • E04C5/165Coaxial connection by means of sleeves
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the technical field of bridge engineering, in particular to a partially unbonded grouting sleeve prefabricated assembly connecting structure and a construction method. The invention coats a layer of anti-corrosive lubricating grease on the outwards extending reinforcing steel bar of a bearing platform with a certain length in the grouting sleeve, coats the sleeve with a corresponding length, and uses flexible sealant to carry out water sealing treatment on two ends of the sleeve so as to enable the outwards extending reinforcing steel bar of the bearing platform in the grouting sleeve to form a reinforcing steel bar non-adhesive section with a certain length. The invention not only ensures the connection stress of the pier and the bearing platform under normal use, but also can improve the energy consumption capability of the pier through the sliding friction of the outward extending reinforcing steel bars of the bearing platform in the grouting sleeve under the action of an earthquake. Meanwhile, the whole system has the advantages of simple structure, convenience in construction, high economical efficiency and the like, and is convenient to popularize and apply.

Description

Partially unbonded grouting sleeve prefabricated assembly connecting structure and construction method
Technical Field
The invention relates to the technical field of bridge engineering, in particular to a partially unbonded grouting sleeve prefabricated assembly connecting structure and a construction method.
Background
With the application of the prefabrication and assembly technology to the bridge substructure, the connection structure of the splicing seams of the piers becomes a key technical problem when the section assembly piers are applied to a high earthquake danger area. The grouting sleeve connection can be used for connecting prefabricated assembled piers and bearing platforms, piers and capping beams or pier sections, and the connection mode is that reliable bonding is formed among the sleeve, the reinforcing steel bars and the grouting material to work after the grouting material is condensed and hardened. The bridge pier is one of the categories of prefabricated assembled connecting structures which are most widely applied at present, and the performance of the bridge pier under the earthquake directly influences the earthquake-resistant performance of the whole bridge pier. The existing research shows that under the action of earthquake, the bearing capacity of the prefabricated pier is similar to that of a cast-in-place pier, when the sleeve is arranged at the bottom of the pier, deformation is mainly concentrated at the position of the splicing seam, the displacement ductility of the sleeve is usually relatively low, and the application of the prefabricated spliced pier connected by the grouting sleeve in high earthquake risk areas is influenced.
Disclosure of Invention
In order to solve the problems, the invention aims to provide a partially unbonded grouting sleeve prefabricated splicing connection structure and a construction method; the novel splicing connection mode can meet the connection requirement of the normal use performance of the prefabricated spliced pier, and can improve the energy dissipation capacity and certain self-resetting capacity of the pier under an earthquake by utilizing the friction between the outwards extending reinforcing steel bars of the bearing platform and the grouting material in the grouting sleeve and matching the unbonded prestressed reinforcing steel bars.
The invention relates to a partially unbonded grouting sleeve prefabricated splicing connection structure, which coats a layer of anticorrosive lubricating grease on a bearing platform overhanging steel bar with a certain length in a grouting sleeve, coats a sleeve with a corresponding length externally, and uses flexible sealing glue to carry out water sealing treatment on the upper end and the lower end of the sleeve so as to enable the bearing platform overhanging steel bar in the grouting sleeve to form a steel bar unbonded section with a certain length. The invention not only ensures the connection stress of the pier and the bearing platform under normal use, but also can improve the energy consumption capability of the pier through the sliding friction of the outward extending reinforcing steel bars of the bearing platform in the grouting sleeve under the action of an earthquake. Meanwhile, the partial unbonded grouting sleeve prefabricated assembling connection structure has the advantages of simple structure, convenience in construction, high economical efficiency and the like, and is convenient to popularize and apply.
The purpose of the invention can be realized by the following technical scheme:
the invention provides a partially unbonded grouting sleeve prefabricated assembly connecting structure which is fixed in a pier and a bearing platform from top to bottom and comprises main pier reinforcements, outward extending reinforcing steel bars of the bearing platform, a sleeve, a grouting sleeve and unbonded prestressed reinforcing steel bars,
the grouting sleeve is arranged at the bottom of the pier; the upper part of the grouting sleeve is a main reinforcing steel bar section of a pier of the grouting sleeve, and the lower part of the grouting sleeve is an outward extending reinforcing steel bar section of a bearing platform of the grouting sleeve; the main bridge pier ribs are inserted into the main bridge pier rib sections of the grouting sleeves; grouting material is introduced into the grouting sleeve;
the upper part of the outwards extending reinforcing steel bar of the bearing platform is a reinforcing steel bar non-bonding section, and the lower part of the outwards extending reinforcing steel bar of the bearing platform is a reinforcing steel bar bonding section; the reinforcing steel bar non-bonding section and a section of reinforcing steel bar bonding section of the cushion cap overhanging reinforcing steel bar are inserted into the grouting sleeve cushion cap overhanging reinforcing steel bar section, and the other end of the cushion cap overhanging reinforcing steel bar is pre-embedded in the cushion cap;
the outside of the non-adhesive section of the reinforcing steel bar is sleeved with a sleeve to form the non-adhesive section in the grouting sleeve;
the unbonded prestressed tendon is positioned in the center of the bridge pier and penetrates through the bridge pier;
under the action of seismic load of the pier, the unbonded section in the grouting sleeve allows the overhanging steel bars of the bearing platform to slide in the grouting sleeve, the overall rigidity is reduced by the sliding generated between the overhanging steel bars of the bearing platform and the grouting material to realize vibration isolation, and the shock absorption is realized by the friction energy dissipation effect between the overhanging steel bars of the bearing platform and the grouting material; the unbonded prestressed ribs and the unbonded sections in the grouting sleeve are arranged to provide restoring force for piers, so that residual deformation is reduced, and the condition that the outward extending reinforcing steel bars of the bearing platform in the grouting sleeve only slide and cannot be pulled out under the action of an earthquake is ensured.
In one embodiment of the invention, the main pier reinforcement and the outer extension reinforcement have the same diameter.
In one embodiment of the present invention, a pad layer is provided on the bottom of the pier and the top of the cap.
In one embodiment of the invention, the unbonded prestressed tendon penetrates through the center positions of the pier, the cushion layer and the bearing platform from top to bottom; the unbonded prestressed tendon is provided with a non-stretching anchoring end in the bearing platform, and the middle part is not grouted.
In one embodiment of the present invention, the grouting sleeve is provided in plurality along an outer edge of the pier.
In one embodiment of the invention, a grout outlet is arranged on the side surface of the upper end of a main reinforcement section of a grouting sleeve pier of the grouting sleeve, and a grout pressing outlet is arranged on the side surface of the lower end of an overhanging reinforcement section of a grouting sleeve bearing platform of the grouting sleeve.
In one embodiment of the invention, the grout sleeve comprises a full grout sleeve or a half grout sleeve.
In one embodiment of the invention, the grout sleeve is selected from the group consisting of a ductile iron sleeve, a premium carbon steel sleeve, a low alloy high strength structural steel sleeve, an alloy structural steel sleeve, or a machined sleeve.
In one embodiment of the invention, the minimum inner diameter of the grouting sleeve is preferably 40mm larger than the diameter of the outside steel bar of the bearing platform.
In one embodiment of the invention, the length of the steel bar bonding section of the pile cap overhanging steel bar inserted into the grouting sleeve is more than or equal to 4 times the diameter of the pile cap overhanging steel bar;
preferably, the length of the bonding section of the pile cap overhanging steel bar inserted into the grouting sleeve is 6 times of the diameter of the pile cap overhanging steel bar.
In one embodiment of the invention, the length of the abutment overhanging steel bar inserted into the grouting sleeve is 10 times the diameter of the abutment overhanging steel bar.
In one embodiment of the invention, the main pier rib and the grouting sleeve are connected through grouting material anchoring.
In one embodiment of the invention, a layer of anti-corrosion grease is coated outside the non-bonded section of the reinforcing steel bar, a sleeve is sleeved on the non-bonded section of the reinforcing steel bar, and the upper end and the lower end of the sleeve are subjected to water sealing treatment by using flexible sealant.
In one embodiment of the invention, the flexible sealant comprises a paste sealant or a hot melt sealant.
The second purpose of the invention is to provide a construction method of the prefabricated assembled connecting structure of the partial unbonded grouting sleeve, which comprises the following steps:
(S1) binding a pier reinforcement cage, connecting a pier main reinforcement with a grouting sleeve, pouring pier body concrete by a formwork, reserving an unbonded prestressed reinforcement hole channel, and maintaining for 28 days;
(S2) constructing a bearing platform, wherein corrosion-resistant lubricating grease is coated at the non-bonded sections of reinforcing steel bars of the outwards extending reinforcing steel bars of the bearing platform, which are connected with grouting sleeves in piers, sleeves with corresponding lengths are sleeved outside the non-bonded sections, flexible sealing glue is used for performing water sealing treatment on the upper end and the lower end of each sleeve, the sleeves are fixed by spring clamps, and simultaneously non-bonded prestressed ribs and non-tensioned anchoring ends are pre-embedded in the bearing platform;
(S3) removing the spring clamp, hoisting the pier to the position above the bearing platform, inserting the outward extending reinforcing steel bars of the bearing platform into the grouting sleeve, enabling the unbonded prestressed reinforcing steel bars to penetrate through the reserved hole of the pier body, sequentially injecting grouting materials into the grouting sleeve after the pier is installed by a mortar setting method, completing connection after the unbonded prestressed reinforcing steel bars are hardened, and finally tensioning and anchoring the unbonded prestressed reinforcing steel bars at the top of the pier.
In one embodiment of the present invention, the sleeve is fixed by a spring clip before bridge abutment erection.
In one embodiment of the invention, the spring clip is formed by wrapping a rubber layer with a non-slip function around the spring wire.
Under the normal use condition, the reinforcing bar bonding section that the overhanging reinforcing bar of cushion cap inserts more than or equal to 4 times overhanging reinforcing bar diameter of cushion cap in the grout sleeve can provide sufficient bonding anchor effect for the normal atress of pier is assembled in the prefabrication. Under the action of an earthquake, the traditional grouting sleeve is connected with the pier bottom of the pier to form a plastic hinge, the joint of the pier bottom and the bearing platform is gradually opened, and finally, the damage form of the steel bar breaking is mainly used. After the unbonded section is arranged in the grouting sleeve, the phenomenon of slippage of the outwards extending reinforcing steel bars of the bearing platform provided with the unbonded section during earthquake is allowed due to the reduction of the anchoring length of the reinforcing steel bars. Therefore, the overall rigidity is reduced by debonding the overhanging steel bars of the bearing platform and the grouting material under the action of earthquake, the dynamic characteristic of the structure is changed, and the purpose of shock insulation is realized; the sliding friction between the outward extending steel bars of the bearing platform and the grouting material provides friction-type energy consumption for the bridge pier, and shock absorption is realized; the arrangement of the unbonded prestressed tendons provides effective restoring force for pier bodies of piers, reduces residual deformation, and ensures that the bearing platform overhanging steel bars in the grouting sleeve only slide and cannot be pulled out under the action of an earthquake; and the combination of the unbonded prestressed tendons and the outward extending reinforcing steel bars of the bearing platform ensures that the strength of the grouting sleeve connected with the outward extending reinforcing steel bars of the bearing platform is reduced and is not too large after the outward extending reinforcing steel bars of the bearing platform are debonded, thereby ensuring the ductility of the structure. The overall design concept of the scheme is not the equivalent cast-in-place design of the traditional grouting sleeve connected pier, but is close to the design concept of a self-resetting system.
Compared with the prior art, the invention has the following beneficial effects:
(1) according to the partially unbonded grouting sleeve prefabricated assembly connecting structure, the reinforcing steel bar bonding section with the diameter which is larger than or equal to 4 times of the diameter of the overhanging reinforcing steel bar of the bearing platform is inserted into the grouting sleeve, so that a sufficient bonding anchoring effect can be provided for the normal stress of the prefabricated assembly pier;
(2) according to the partially unbonded grouting sleeve prefabricated splicing connection structure, after the unbonded section is arranged in the grouting sleeve, the phenomenon that the outwards extending reinforcing steel bars of the bearing platform in the grouting sleeve slide relative to the grouting material in the grouting sleeve during an earthquake is allowed due to the reduction of the anchoring length of the reinforcing steel bars.
(3) According to the partially unbonded grouting sleeve prefabricated assembly connecting structure, the relative sliding between the extending reinforcing steel bars of the bearing platform and the grouting material under the action of an earthquake reduces the overall rigidity, the dynamic characteristic of the structure is changed, and the purpose of shock insulation is achieved; the sliding friction between the outward extending steel bars of the bearing platform and the grouting material provides friction-type energy consumption for the bridge pier, and shock absorption is realized;
(4) according to the partially unbonded grouting sleeve prefabricated assembly connecting structure, the unbonded prestressed ribs and the unbonded sections in the grouting sleeve are arranged to provide effective restoring force for piers, so that residual deformation is reduced, the residual deformation of the prefabricated assembly piers is smaller than that of common reinforced concrete piers provided with the unbonded prestressed ribs, and the extending reinforcing steel bars of the bearing platform in the grouting sleeve only slide and cannot be pulled out under the earthquake action; and the combination of the unbonded prestressed tendons and the main pier tendons ensures that the strength of the grouting sleeve connected with the main pier tendons is not reduced to be too large after the main pier tendons are debonded, and the ductility of the structure is ensured.
(5) The partially unbonded grouting sleeve prefabricated splicing connection structure has the advantages of simple structure, convenience in construction, high economy and the like, and is convenient to popularize and apply.
Drawings
FIG. 1 is a schematic view of the overall structure of a partially unbonded grouting sleeve prefabricated assembly connection structure of the invention;
FIG. 2 is a cross-sectional view of a pier in the overall structural schematic diagram of the partially unbonded grouting sleeve prefabricated assembly connecting structure of the invention, taken along the line I-I;
FIG. 3 is a schematic view of a grouting sleeve structure in a partially unbonded grouting sleeve prefabricated assembly connection structure according to the invention;
FIG. 4 is a schematic view of an overhanging steel bar of a bearing platform in a partially unbonded grouting sleeve prefabricated assembly connection structure of the invention;
reference numbers in the figures: 1 is a main bridge pier rib; 2, outwards extending reinforcing steel bars of the bearing platform; 3 is a sleeve; 4, a grouting sleeve; 5 is a cushion layer; 6 is a pier; 7 is a bearing platform; 8 is a spring clip; 9 is a reinforcing steel bar bonding section; 10 is a reinforcing steel bar non-adhesive section; 11 is an unbonded prestressed tendon; 12 are non-tensioned anchor ends.
Detailed Description
The invention provides a partially unbonded grouting sleeve prefabricated assembly connecting structure which is fixed in a pier and a bearing platform from top to bottom and comprises main pier reinforcements, outwards extending reinforcing steel bars of the bearing platform, a sleeve, a grouting sleeve and unbonded prestressed reinforcements,
the grouting sleeve is arranged at the bottom of the pier; the upper part of the grouting sleeve is a main reinforcing steel bar section of a pier of the grouting sleeve, and the lower part of the grouting sleeve is an outward extending reinforcing steel bar section of a bearing platform of the grouting sleeve; the main bridge pier ribs are inserted into the main bridge pier rib sections of the grouting sleeves; grouting material is introduced into the grouting sleeve;
the upper part of the outwards extending reinforcing steel bar of the bearing platform is a reinforcing steel bar non-bonding section, and the lower part of the outwards extending reinforcing steel bar of the bearing platform is a reinforcing steel bar bonding section; the reinforcing steel bar non-bonding section and a section of reinforcing steel bar bonding section of the cushion cap overhanging reinforcing steel bar are inserted into the grouting sleeve cushion cap overhanging reinforcing steel bar section, and the other end of the cushion cap overhanging reinforcing steel bar is pre-embedded in the cushion cap;
the outside of the non-adhesive section of the reinforcing steel bar is sleeved with a sleeve to form the non-adhesive section in the grouting sleeve;
the unbonded prestressed tendon is positioned in the center of the bridge pier and penetrates through the bridge pier;
under the action of seismic load of the pier, the unbonded section in the grouting sleeve allows the overhanging steel bars of the bearing platform to slide in the grouting sleeve, the overall rigidity is reduced by the sliding generated between the overhanging steel bars of the bearing platform and the grouting material to realize vibration isolation, and the shock absorption is realized by the friction energy dissipation effect between the overhanging steel bars of the bearing platform and the grouting material; the unbonded prestressed ribs and the unbonded sections in the grouting sleeve are arranged to provide restoring force for piers, so that residual deformation is reduced, and the condition that the outward extending reinforcing steel bars of the bearing platform in the grouting sleeve only slide and cannot be pulled out under the action of an earthquake is ensured.
In one embodiment of the invention, the main pier reinforcement and the outer extension reinforcement have the same diameter.
In one embodiment of the present invention, a pad layer is provided on the bottom of the pier and the top of the cap.
In one embodiment of the invention, the unbonded prestressed tendon penetrates through the center positions of the pier, the cushion layer and the bearing platform from top to bottom; the unbonded prestressed tendon is provided with a non-stretching anchoring end in the bearing platform, and the middle part is not grouted.
In one embodiment of the present invention, the grouting sleeve is provided in plurality along an outer edge of the pier.
In one embodiment of the invention, a grout outlet is arranged on the side surface of the upper end of a main reinforcement section of a grouting sleeve pier of the grouting sleeve, and a grout pressing outlet is arranged on the side surface of the lower end of an overhanging reinforcement section of a grouting sleeve bearing platform of the grouting sleeve.
In one embodiment of the invention, the grout sleeve comprises a full grout sleeve or a half grout sleeve.
In one embodiment of the invention, the grout sleeve is selected from the group consisting of a ductile iron sleeve, a premium carbon steel sleeve, a low alloy high strength structural steel sleeve, an alloy structural steel sleeve, or a machined sleeve.
In one embodiment of the invention, the minimum inner diameter of the grouting sleeve is preferably 40mm larger than the diameter of the outside steel bar of the bearing platform.
In one embodiment of the invention, the length of the steel bar bonding section of the pile cap overhanging steel bar inserted into the grouting sleeve is more than or equal to 4 times the diameter of the pile cap overhanging steel bar;
preferably, the length of the bonding section of the pile cap overhanging steel bar inserted into the grouting sleeve is 6 times of the diameter of the pile cap overhanging steel bar.
In one embodiment of the invention, the length of the abutment overhanging steel bar inserted into the grouting sleeve is 10 times the diameter of the abutment overhanging steel bar.
In one embodiment of the invention, the main pier rib and the grouting sleeve are connected through grouting material anchoring.
In one embodiment of the invention, a layer of anti-corrosion grease is coated outside the non-bonded section of the reinforcing steel bar, a sleeve is sleeved on the non-bonded section of the reinforcing steel bar, and the upper end and the lower end of the sleeve are subjected to water sealing treatment by using flexible sealant.
In one embodiment of the invention, the flexible sealant comprises a paste sealant or a hot melt sealant.
The second purpose of the invention is to provide a construction method of the prefabricated assembled connecting structure of the partial unbonded grouting sleeve, which comprises the following steps:
(S1) binding a pier reinforcement cage, connecting a pier main reinforcement with a grouting sleeve, pouring pier body concrete by a formwork, reserving an unbonded prestressed reinforcement hole channel, and maintaining for 28 days;
(S2) constructing a bearing platform, wherein corrosion-resistant lubricating grease is coated at the non-bonded sections of reinforcing steel bars of the outwards extending reinforcing steel bars of the bearing platform, which are connected with grouting sleeves in piers, sleeves with corresponding lengths are sleeved outside the non-bonded sections, flexible sealing glue is used for performing water sealing treatment on the upper end and the lower end of each sleeve, the sleeves are fixed by spring clamps, and simultaneously non-bonded prestressed ribs and non-tensioned anchoring ends are pre-embedded in the bearing platform;
(S3) removing the spring clamp, hoisting the pier to the position above the bearing platform, inserting the outward extending reinforcing steel bars of the bearing platform into the grouting sleeve, enabling the unbonded prestressed reinforcing steel bars to penetrate through the reserved hole of the pier body, sequentially injecting grouting materials into the grouting sleeve after the pier is installed by a mortar setting method, completing connection after the unbonded prestressed reinforcing steel bars are hardened, and finally tensioning and anchoring the unbonded prestressed reinforcing steel bars at the top of the pier.
In one embodiment of the present invention, the sleeve is fixed by a spring clip before bridge abutment erection.
In one embodiment of the invention, the spring clip is formed by wrapping a rubber layer with a non-slip function around the spring wire.
The invention is described in detail below with reference to the figures and specific embodiments.
Example 1
The embodiment provides a partially unbonded grouting sleeve prefabricated splicing connection structure.
As shown in fig. 1-4, a partially unbonded grouting sleeve prefabricated assembly connecting structure comprises a main pier reinforcement 1 and a cushion cap overhanging reinforcement 2 which need to be anchored and connected, a sleeve 3 for performing unbonded treatment on the cushion cap overhanging reinforcement 2, and a grouting sleeve 4 pre-buried at the bottom of a pier 6.
The bottom of the pier 6 and the top of the bearing platform 7 are provided with cushion layers 5, and the pier 6, the cushion layers 5 and the bearing platform 7 are sequentially arranged from top to bottom;
the prefabricated assembly connecting structure of the partial unbonded grouting sleeve is fixed on the pier 6, the cushion layer 5 and the bearing platform 7;
the upper part of the grouting sleeve 4 is a main reinforcing steel bar section of a grouting sleeve pier, and the lower part of the grouting sleeve 4 is an outward extending reinforcing steel bar section of a grouting sleeve bearing platform; the pier main rib 1 is inserted into the pier main rib section of the grouting sleeve; grouting material is filled into the grouting sleeve 4;
the upper part of the outwards extending reinforcing steel bar 2 of the bearing platform is provided with a reinforcing steel bar non-bonding section 10, and the lower part is provided with a reinforcing steel bar bonding section 9; the reinforcing steel bar non-bonding section 10 and a section of reinforcing steel bar bonding section 9 of the cushion cap overhanging reinforcing steel bar 2 are inserted into the grouting sleeve cushion cap overhanging reinforcing steel bar section; the other end of the out-extending steel bar 2 of the bearing platform is embedded in the bearing platform 7; the sleeve 3 is sleeved outside the reinforcement unbonded section 10 to form an unbonded section in the grouting sleeve 4; the unbonded prestressed tendon 11 is positioned at the center of the pier 6 and penetrates through the center of the pier 6, the cushion layer 5 and the bearing platform 7 from top to bottom; the unbonded prestressed tendon 11 is provided with a non-stretching anchoring end 12 in the bearing platform 7, and no grouting is performed in the middle.
A plurality of grouting sleeves 4 are arranged along the outer edge of the pier 6; a grout outlet is formed in the side face of the upper end of a main reinforcing steel bar section of a grouting sleeve pier of the grouting sleeve 4, and a grout pressing port is formed in the side face of the lower end of an overhanging reinforcing steel bar section of a grouting sleeve bearing platform of the grouting sleeve 4; the length of the reinforcing steel bar bonding section 9 of the extending reinforcing steel bar of the bearing platform inserted into the grouting sleeve 4 is more than or equal to 4 times of the diameter of the extending reinforcing steel bar of the bearing platform. The grouting sleeve 4 comprises a full grouting sleeve or a half grouting sleeve; the grouting sleeve 4 is selected from a nodular cast iron sleeve, a high-quality carbon steel sleeve, a low-alloy high-strength structural steel sleeve, an alloy structural steel sleeve or a machining sleeve; after the main bridge pier ribs 1 are inserted into the grouting sleeves, grouting material is poured from the grouting opening at the lower part until the grouting material overflows from the grouting opening at the upper part, and connection and anchoring are completed;
coating a layer of anticorrosive lubricating grease on the reinforcement unbonded section 10 of the cushion cap overhanging reinforcement 2, sleeving a sleeve 3 with a corresponding length outside, performing water seal treatment on the upper end and the lower end of the sleeve 3 by using flexible sealing glue, and fixing by using a spring clamp 8 before assembling the pier 6 so as to enable the cushion cap overhanging reinforcement 2 in the grouting sleeve 4 to form the reinforcement unbonded section 10 with a certain length; the flexible sealant comprises a paste sealant or a hot-melt sealant; the length of the outward extending steel bar 2 of the bearing platform inserted into the grouting sleeve 4 is 10 times of the diameter of the outward extending steel bar 2 of the bearing platform; the minimum inner diameter of the grouting sleeve 4 is preferably 40mm larger than the diameter of the support platform overhanging steel bar 2.
Spring clamp 8 is made for spring wire outsourcing one deck rubber layer that plays anti-skidding effect, cuts unnecessary straightway after accomplishing sleeve pipe 3 location, and the reinforcing bar 2 of being convenient for gets into grout sleeve 4.
Under the action of earthquake load, the unbonded section in the grouting sleeve 4 of the pier 6 allows the outward extending steel bar 2 of the bearing platform to slide in the grouting sleeve 4, the overall rigidity is reduced by the sliding generated between the outward extending steel bar 2 of the bearing platform and the grouting material to realize vibration isolation, and the friction energy dissipation effect between the outward extending steel bar 2 of the bearing platform and the grouting material realizes shock absorption; the unbonded prestressed ribs 11 and the unbonded sections in the grouting sleeve 4 are arranged to provide restoring force for the piers 6, so that residual deformation is reduced, and the condition that the cushion cap overhanging steel bars 2 in the grouting sleeve 4 only slide and cannot be pulled out under the action of an earthquake is ensured.
Example 2
The embodiment provides a construction method for a partially unbonded grouting sleeve prefabricated splicing connection structure.
A construction method for a partially unbonded grouting sleeve prefabricated splicing connection structure comprises the following steps:
(S1) binding a pier reinforcement cage, connecting the pier main reinforcement 1 with the grouting sleeve 4, pouring pier body concrete of a pier 6 by using a formwork, reserving a hole channel of the unbonded prestressed reinforcement 11, and maintaining for 28 days;
(S2) constructing a bearing platform 7, wherein anticorrosion lubricating grease is coated on the non-bonded section 10 of the reinforcing steel bar of the bearing platform overhanging reinforcing steel bar 2 connected with the grouting sleeve 4 in the pier 6, the sleeve 3 with the corresponding length is sleeved outside, the upper end and the lower end of the sleeve 3 are subjected to water sealing treatment by flexible sealing glue, the sleeve 3 is fixed by a spring clamp 8, and the non-bonded prestressed bar 11 and the non-tensioned anchoring end 12 are pre-embedded in the bearing platform 7;
(S3) removing the spring clamp 8, hoisting the pier 6 to the position above the bearing platform, inserting the outward extending reinforcing steel bar 2 of the bearing platform into the grouting sleeve 4, enabling the unbonded prestressed tendon 11 to penetrate through the reserved hole of the pier body, sequentially injecting grouting material into the grouting sleeve 4 after the pier 6 is installed by a setting grouting method, completing connection after the unbonded prestressed tendon is hardened, and finally tensioning and anchoring the unbonded prestressed tendon 11 at the top of the pier 6.
In this embodiment, preparation before construction: and cleaning the construction site according to a design drawing, and organizing construction materials, machinery and personnel in place.
The embodiments described above are described to facilitate an understanding and use of the invention by those skilled in the art. It will be readily apparent to those skilled in the art that various modifications to these embodiments may be made, and the generic principles described herein may be applied to other embodiments without the use of the inventive faculty. Therefore, the present invention is not limited to the above embodiments, and those skilled in the art should make improvements and modifications within the scope of the present invention based on the disclosure of the present invention.

Claims (10)

1. A partially unbonded grouting sleeve prefabricated assembly connecting structure is fixed in a pier (6) and a bearing platform (7) from top to bottom and is characterized by comprising main pier reinforcements (1), outward extending reinforcing steel bars (2) of the bearing platform, a sleeve (3), a grouting sleeve (4) and unbonded prestressed reinforcements (11),
the grouting sleeve (4) is arranged at the bottom of the pier (6); the upper part of the grouting sleeve (4) is a main steel bar section of a grouting sleeve pier, and the lower part of the grouting sleeve is an outward extending steel bar section of a grouting sleeve bearing platform; the pier main rib (1) is inserted into the pier main rib section of the grouting sleeve; grouting material is introduced into the grouting sleeve (4);
the upper part of the outwards extending reinforcing steel bar (2) of the bearing platform is provided with a reinforcing steel bar non-bonding section (10), and the lower part of the outwards extending reinforcing steel bar is provided with a reinforcing steel bar bonding section (9); a reinforcing steel bar non-bonding section (10) and a reinforcing steel bar bonding section (9) of the cushion cap overhanging reinforcing steel bar (2) are inserted into the grouting sleeve cushion cap overhanging reinforcing steel bar section, and the other end of the cushion cap overhanging reinforcing steel bar (2) is pre-embedded in the cushion cap (7);
the sleeve (3) is sleeved outside the non-adhesive section (10) of the reinforcing steel bar to form the non-adhesive section in the grouting sleeve (4);
the unbonded prestressed tendon (11) is positioned at the center of the pier (6) and penetrates through the pier (6);
under the action of earthquake load, the unbonded section in the grouting sleeve (4) of the pier (6) allows the bearing platform overhanging steel bar (2) to slide in the grouting sleeve (4), the overall rigidity is reduced by the sliding generated between the bearing platform overhanging steel bar (2) and the grouting material to realize vibration isolation, and the friction energy dissipation effect between the bearing platform overhanging steel bar (2) and the grouting material realizes shock absorption; the unbonded prestressed ribs (11) and the unbonded sections in the grouting sleeve (4) are arranged to provide restoring force for the piers (6), so that residual deformation is reduced, and the condition that the cushion cap overhanging steel bars (2) in the grouting sleeve (4) only slide and cannot be pulled out under the action of an earthquake is ensured.
2. The partially unbonded grouting sleeve prefabricated assembly connecting structure as claimed in claim 1, wherein the bottom of the pier (6) and the top of the bearing platform (7) are provided with cushion layers (5).
3. The partially unbonded grouting sleeve prefabricated assembly connecting structure as claimed in claim 1, wherein the unbonded prestressed tendons (11) penetrate through the center positions of the pier (6), the cushion layer (5) and the bearing platform (7) from top to bottom; the unbonded prestressed tendons (11) are provided with non-tensioning anchoring ends (12) in the bearing platform (7), and the middle part is not grouted.
4. The partially unbonded grouting sleeve prefabricated assembly connecting structure as claimed in claim 1, wherein a grout outlet is formed in the side surface of the upper end of a main reinforcing steel bar section of a grouting sleeve pier of the grouting sleeve (4), and a grout pressing port is formed in the side surface of the lower end of an overhanging reinforcing steel bar section of a grouting sleeve bearing platform of the grouting sleeve (4).
5. The partially unbonded grouting sleeve prefabricated assembly connecting structure as claimed in claim 1, wherein the length of the reinforcing steel bar bonding section (9) of the pile cap overhanging reinforcement (2) inserted into the grouting sleeve (4) is greater than or equal to 4 times the diameter of the pile cap overhanging reinforcement (2).
6. The partially unbonded grouting sleeve prefabricated assembly connecting structure as claimed in claim 1, wherein the length of the protruding reinforcing steel bars (2) inserted into the grouting sleeve (4) is 10 times the diameter of the protruding reinforcing steel bars (2).
7. The partially unbonded grouting sleeve prefabricated assembly connecting structure as claimed in claim 1, wherein the main pier ribs (1) are connected with the grouting sleeves (4) through grouting material anchoring.
8. The partially unbonded grouting sleeve prefabricated assembly connecting structure as claimed in claim 1, wherein a layer of anti-corrosive grease is applied to the exterior of the unbonded reinforcing steel bar section (10), the sleeve (3) is sleeved on the partially unbonded grouting sleeve, and the upper end and the lower end of the sleeve (3) are subjected to water sealing treatment by using flexible sealants.
9. A construction method of the partially unbonded grouted sleeve prefabricated joined structure according to claim 1, comprising the steps of:
(S1) binding a steel reinforcement cage of the pier (6), connecting the main pier reinforcement (1) with the grouting sleeve (4), pouring concrete of the pier body of the pier (6) through a formwork, reserving a hole channel of the unbonded prestressed reinforcement (11), and maintaining for 28 days;
(S2) constructing a bearing platform (7), wherein anticorrosion lubricating grease is coated at a reinforcing steel bar unbonded section (10) of a bearing platform overhanging reinforcing steel bar (2) connected with a grouting sleeve (4) in a pier (6), a sleeve (3) with a corresponding length is sleeved outside the reinforcing steel bar unbonded section, flexible sealing glue is used for performing water sealing treatment on the upper end and the lower end of the sleeve (3), a spring clamp (8) is adopted to fix the sleeve (3), and an unbonded prestressed rib (11) and a non-tensioning anchoring end (12) are pre-embedded in the bearing platform (7) at the same time;
(S3) removing the spring clamp (8), hoisting the pier (6) to the upper side of the bearing platform (7), inserting the outward extending reinforcing steel bar (2) of the bearing platform into the grouting sleeve (4), penetrating the unbonded prestressed reinforcement (11) through the reserved hole of the pier body, installing the pier (6) through a seat grouting method, sequentially injecting grouting material into the grouting sleeve (4), completing connection after hardening of the grouting material, and finally tensioning and anchoring the unbonded prestressed reinforcement (11) at the top of the pier (6).
10. The construction method of the partially unbonded grouted sleeve prefabricated joined structure according to claim 9, wherein the sleeve (3) is fixed by the spring clip (8) before the bridge pier (6) is assembled.
CN202111430337.2A 2021-11-29 2021-11-29 Partially unbonded grouting sleeve prefabricated assembly connecting structure and construction method Pending CN114000656A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111430337.2A CN114000656A (en) 2021-11-29 2021-11-29 Partially unbonded grouting sleeve prefabricated assembly connecting structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111430337.2A CN114000656A (en) 2021-11-29 2021-11-29 Partially unbonded grouting sleeve prefabricated assembly connecting structure and construction method

Publications (1)

Publication Number Publication Date
CN114000656A true CN114000656A (en) 2022-02-01

Family

ID=79930632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111430337.2A Pending CN114000656A (en) 2021-11-29 2021-11-29 Partially unbonded grouting sleeve prefabricated assembly connecting structure and construction method

Country Status (1)

Country Link
CN (1) CN114000656A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114892537A (en) * 2022-07-14 2022-08-12 中国建筑第六工程局有限公司 Pier connection construction equipment is assembled in prefabrication under water
CN115030306A (en) * 2022-04-28 2022-09-09 湖南大学 Column assembly with controllable column end deformation and easily replaced column body
CN115125866A (en) * 2022-08-10 2022-09-30 北京城建设计发展集团股份有限公司 Method for connecting prefabricated vase piers through unbonded prestressed tendons and steel bars

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101936043A (en) * 2010-08-11 2011-01-05 东南大学 Friction energy consumption type node connection device for self-centering pier column structure
CN110042741A (en) * 2019-03-12 2019-07-23 中国矿业大学 A kind of casing constraint Precast Concrete Segmental Bridges pier stud and its construction method
CN111501525A (en) * 2020-03-26 2020-08-07 上海市政工程设计研究总院(集团)有限公司 Prefabricated bridge pier column and bearing platform connecting structure with pier base and construction method thereof
CN112267373A (en) * 2020-09-23 2021-01-26 同济大学 Partially unbonded grouting corrugated pipe prefabricated assembly connecting structure and construction method
CN216865720U (en) * 2021-11-29 2022-07-01 同济大学 Partially unbonded grouting sleeve prefabrication assembling connection structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101936043A (en) * 2010-08-11 2011-01-05 东南大学 Friction energy consumption type node connection device for self-centering pier column structure
CN110042741A (en) * 2019-03-12 2019-07-23 中国矿业大学 A kind of casing constraint Precast Concrete Segmental Bridges pier stud and its construction method
CN111501525A (en) * 2020-03-26 2020-08-07 上海市政工程设计研究总院(集团)有限公司 Prefabricated bridge pier column and bearing platform connecting structure with pier base and construction method thereof
CN112267373A (en) * 2020-09-23 2021-01-26 同济大学 Partially unbonded grouting corrugated pipe prefabricated assembly connecting structure and construction method
CN216865720U (en) * 2021-11-29 2022-07-01 同济大学 Partially unbonded grouting sleeve prefabrication assembling connection structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
葛继平;闫兴非;王志强;: "灌浆套筒和预应力筋连接的预制拼装桥墩的抗震性能", 交通运输工程学报, no. 02, 15 April 2018 (2018-04-15), pages 42 - 52 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115030306A (en) * 2022-04-28 2022-09-09 湖南大学 Column assembly with controllable column end deformation and easily replaced column body
CN114892537A (en) * 2022-07-14 2022-08-12 中国建筑第六工程局有限公司 Pier connection construction equipment is assembled in prefabrication under water
CN115125866A (en) * 2022-08-10 2022-09-30 北京城建设计发展集团股份有限公司 Method for connecting prefabricated vase piers through unbonded prestressed tendons and steel bars

Similar Documents

Publication Publication Date Title
CN114000656A (en) Partially unbonded grouting sleeve prefabricated assembly connecting structure and construction method
US11293183B2 (en) Precast column base joint and construction method therefor
JP6684838B2 (en) Prestressed submerged box structure and its construction method
CN103590322A (en) Shear force connecting part, combination beam comprising same and construction method of combination beam
CN107268425B (en) Construction method of connecting structure for prefabricating and assembling bearing platform
CN104153287A (en) Segmental assembled concrete frame pier system with self-reset function and method
CN111962386A (en) Energy-dissipation and shock-absorption type self-resetting prefabricated segment assembled pier structure and construction method thereof
CN112267373A (en) Partially unbonded grouting corrugated pipe prefabricated assembly connecting structure and construction method
CN107013040A (en) The construction method of floor is poured after a kind of sleeve built-in type
CN111827092A (en) Prefabricated assembled hollow pier suitable for being provided with diaphragm plate and construction method
CN216865720U (en) Partially unbonded grouting sleeve prefabrication assembling connection structure
CN113123332A (en) Post-tensioned slow-setting main reinforcement pressure type uplift action pile and preparation method thereof
JP2013060710A (en) Bridge joint structure
KR100388078B1 (en) Apparatus to repair and reinforce bridge and thereof method
US6026618A (en) Masonry reinforcement system
CN212357961U (en) Partially unbonded grouting corrugated pipe prefabrication, assembling and connecting structure
JP5920774B2 (en) Bonding method and structure of old and new concrete
CN111827091A (en) Prefabricated assembled hollow pier connected through prestress and construction method
CN217869978U (en) Steel-concrete combined bridge deck and wet seam structure thereof
CN110747735A (en) Anchoring connection device for precast concrete bridge deck of steel-concrete composite beam
CN114908661A (en) Rubber energy-consuming self-resetting socket-and-spigot type pier connection structure and assembling method thereof
CN212561123U (en) Combined embedded connection structure between prefabricated pier stud and base
CN212561130U (en) Prefabricated assembled hollow pier connected through prestress
JP7222824B2 (en) Wall balustrade reinforcement method and reinforcement structure
CN206956536U (en) A kind of attachment structure assembled for bearing platform prefabrication

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination