CN113958187A - Supplementary correction of electric power construction line pole anti-tilt is maintained device - Google Patents

Supplementary correction of electric power construction line pole anti-tilt is maintained device Download PDF

Info

Publication number
CN113958187A
CN113958187A CN202111324047.XA CN202111324047A CN113958187A CN 113958187 A CN113958187 A CN 113958187A CN 202111324047 A CN202111324047 A CN 202111324047A CN 113958187 A CN113958187 A CN 113958187A
Authority
CN
China
Prior art keywords
ring
electric power
power construction
clamp
hinged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111324047.XA
Other languages
Chinese (zh)
Inventor
毕守东
侯强
高源�
屈波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tieling Power Supply Co Of State Grid Liaoning Electric Power Co ltd
State Grid Corp of China SGCC
Original Assignee
Tieling Power Supply Co Of State Grid Liaoning Electric Power Co ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tieling Power Supply Co Of State Grid Liaoning Electric Power Co ltd, State Grid Corp of China SGCC filed Critical Tieling Power Supply Co Of State Grid Liaoning Electric Power Co ltd
Priority to CN202111324047.XA priority Critical patent/CN113958187A/en
Publication of CN113958187A publication Critical patent/CN113958187A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • E04H12/2292Holders used for protection, repair or reinforcement of the post or pole
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/20Side-supporting means therefor, e.g. using guy ropes or struts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/22Sockets or holders for poles or posts
    • E04H12/2284Means for adjusting the orientation of the post or pole

Abstract

The invention discloses an anti-inclination auxiliary correction maintenance device for a power construction line pole, which comprises a first ring and a line pole, wherein one end of the first ring is hinged with a second ring, the other end of the second ring is movably provided with a fixed ring plate, a fastening bolt is hinged inside the fixed ring plate, sliding grooves are respectively arranged inside the first ring and the second ring, positioning holes are respectively formed inside the sliding grooves, three sliding sleeves are movably sleeved on the outer sides of the first ring and the second ring, and sliding blocks are respectively arranged inside the three sliding sleeves. Through the level bar that sets up, the corresponding slope volume of three level bar reaction, inclination between two hydraulic stretching post can be reflected to a level bar, and the flexible volume of the operating personnel of being convenient for adjust and change directly perceivedly to because hydraulic stretching post can be followed the inside dismantlement of end hinge sleeve and top hinge sleeve and consequently overall structure can realize opening and closed and do not produce the joint, the hydraulic support pole provides internal force and stabilizes and increase the stress intensity.

Description

Supplementary correction of electric power construction line pole anti-tilt is maintained device
Technical Field
The invention belongs to the technical field of electric power construction, and particularly relates to an anti-inclination auxiliary correction maintenance device for an electric power construction pole.
Background
The telegraph pole is just a pole for erecting the electric wire, appears in various rural areas, fields, roads and streets, and is one of important infrastructures in the early China, various telegraph poles in the early days are started from wood poles, even comprise high-voltage wire poles with not too high voltage levels, and later due to the development of steel and reinforced concrete and technical requirements, most of the wood poles are replaced by the two materials, and applicable wood is gradually scarce, so that the wood poles are basically difficult to see in cities, but the wood poles are also used for erecting the telephone wires in less developed places because the wood poles are light in weight and convenient to erect, the bearing and the tension of the telephone wires are small, the wood poles can be competent, and if the telephone wires are changed, the pole moving is also convenient, so that part of the wood poles of the telephone wires are also available.
In the process of electric power construction, the prior art still generally adopts electric power to erect the pole widely, and this kind of mode of erection has advantages such as maintain convenience and erect the span and is often adopted, and current electric power construction pole in-process, because the geology problem of erectting the matrix, can take place to subside the slope, if not correct in time, can tear the cable because of gravity to cause certain economic loss, we propose an electric power construction pole on the basis of this and prevent inclining to assist correction maintenance device.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide an auxiliary correcting and maintaining device for preventing the inclination of a power construction pole, and solves the problem that the pole cannot be corrected due to settlement inclination and the like.
In order to achieve the purpose, the invention provides the following technical scheme: an electric power construction wire pole anti-inclination auxiliary correction maintenance device comprises a first ring and a wire pole, wherein one end of the first ring is hinged with a second ring, the other end of the second ring is movably provided with a fixed ring plate, the inside of the fixed ring plate is hinged with a fastening bolt, the inside of the first ring and the second ring are respectively provided with a chute, the inside of each chute is provided with a positioning hole, the outside of the first ring and the outside of the second ring are movably sleeved with three sliding sleeves, the inside of the three sliding sleeves are respectively provided with a sliding block, the tops of the three sliding sleeves are respectively hinged with a bottom hinge sleeve, the inside of each bottom hinge sleeve is in threaded connection with a hydraulic telescopic column, the outside of the top end of the hydraulic telescopic column is in threaded connection with a top hinge sleeve, the opposite side of each top hinge sleeve is hinged with a mounting clamp, one side of the mounting clamp is movably provided with a first clamping plate, and the bottom of the mounting clamp is fixedly provided with three support plates, it is three the equal movable mounting in bottom of extension board has the hydraulic support pole, the position sleeve has been cup jointed in the outside activity of hydraulic support pole bottom, and is three the equal fixed mounting in opposite side of sliding sleeve has the axle bed, outer spiral shell section of thick bamboo has been cup jointed in the inside activity of axle bed, the inside threaded connection of outer spiral shell section of thick bamboo has an interior screw rod, the other end fixed mounting of interior screw rod has the L board, the inside threaded connection of the L board other end has positioning bolt, the fixed ring board that has cup jointed in bottom in the wire pole outside, the bottom fixed mounting in the wire pole outside has four voussoirs, the activity clamp has been cup jointed in the outside activity of wire pole, the outside of activity clamp is provided with three level bar, one side movable mounting of activity clamp has the second cardboard clamp.
Preferably, one end of the fixed ring plate, which is far away from the second ring plate, is fixedly arranged inside the first ring.
Through adopting above-mentioned technical scheme, the advantage lies in this design, is convenient for straightening the line pole of equal specification and can open and embolia.
Preferably, the positioning holes are uniformly distributed in the first ring and the second ring in an annular shape, and the bottoms of the positioning holes can be provided with universal wheels movably mounted.
Through adopting above-mentioned technical scheme, the advantage lies in the overall structure's of being convenient for removal, makes its installation that can be swift and prevent inclining the convenience that has increased the device.
Preferably, the sliding block is movably installed inside the sliding groove.
Through adopting above-mentioned technical scheme, the advantage lies in being convenient for increase the internal force at the in-process of straightening, avoids deformation to can increase the dynamics of straightening and make its more perfect reply slightly heavy line pole, increase mechanics stability.
Preferably, the inside of the supporting ring plate is provided with bolt holes, the number of the bolt holes is at least six, and the specification size of the positioning bolt is slightly smaller than that of the bolt holes.
Through adopting above-mentioned technical scheme, the advantage lies in being convenient for fix a position central point and puts, has increased the internal force of straightening and preventing the slope in-process for the structure is more stable, and the moment of being convenient for between the structure is stable, and has increased life indirectly.
Preferably, the bottom of the positioning sleeve is fixedly provided with a positioning column, and the positioning column is inserted into the bolt hole.
Through adopting above-mentioned technical scheme, the advantage lies in that this scheme can carry out inside perpendicular detection at the in-process that stabilizes the internal force and support, and the stability of the structure of being convenient for has increased the convenience of operation.
Preferably, the specification and size of installation clamp and the specification and size looks adaptation of line pole, and the outside of line pole is provided with the ring channel with installation clamp and activity clamp looks adaptation.
Through adopting above-mentioned technical scheme, the advantage lies in that the ring channel provides certain spacing support for installation clamp and activity clamp, and the moment of being convenient for is stable and exert the force point position stability.
Preferably, three the level bar is the annular and distributes in the outside of activity clamp, and is three level bar and top hinge sleeve are alternately evenly distributed, and the position of three level bar is corresponding with the position of hydraulic support pole.
Through adopting above-mentioned technical scheme, the advantage lies in that inclination between two hydraulic telescoping columns can be reflected to a level bar, and the operating personnel of being convenient for adjust and change flexible volume directly perceivedly.
Compared with the prior art, the invention has the beneficial effects that:
1. the installation clamp and the movable clamp are respectively sleeved at preset positions on the outer side of a wire rod through the arranged installation clamp and the movable clamp, the installation clamp and the movable clamp are fixed through hinge bolts on the inner sides of a first clamping plate and a second clamping plate respectively, then a first ring and a second ring are opened and sleeved on the outer side of the wire rod and are positioned at the central position, a fixed ring plate is fixed at the positions of the first ring and the second ring, at the moment, an inner screw rod is rotated, the inner screw rod is connected with an outer screw cylinder in a matched mode through threads, the inner screw rod is similar to a bolt nut, after the inner screw rod is rotated and extended, the inner part of an L plate is rotatably hinged into a positioning bolt and is inserted into a bolt hole, at the moment, the outer screw cylinder is rotated under the action of a shaft seat and is stretched relative to the inner screw rod, so that sliding sleeves on the outer sides of the first ring and the second ring and the outer side of the sliding sleeves are positioned at triangular positions, the whole body is positioned on the outer side of the center of the wire rod, and then two ends of a hydraulic telescopic column are respectively rotatably hinged and in the top hinge sleeve and the bottom hinge sleeve in a matched mode through threads, make it form the triangle structure with the line pole, this scheme is convenient for install and moment is stable to can fix a position and correct straightening the line pole of difference, be convenient for open and install, increased the operating efficiency.
2. Through the locating hole that sets up, at the in-process of straightening, insert the bolt through the locating hole and fix first ring and second ring subaerial, start the flexible of the flexible post of hydraulic pressure this moment, progressively straighten the line pole, and observe the vertical position of line pole through the level bar, and adjust the flexible volume of the flexible post of hydraulic pressure according to the slope volume of level bar, be convenient for straighten the line pole directly perceivedly, then fill pre-buried gap department and fix and pack the concrete position of line pole through the voussoir, and can demolish the line pole vertical fixation back through the support, be convenient for adjust the use according to the condition of difference.
3. Through the level bar that sets up, when the flexible volume difference of three hydraulic stretching post or line pole out of plumb, the slope volume that three level bar reaction corresponds, inclination between two hydraulic stretching posts can be reflected to a level bar, the operating personnel of being convenient for adjust and change flexible volume directly perceivedly, and because hydraulic stretching post can be followed the inside dismantlement of end hinge joint cover and top hinge joint cover and consequently overall structure can realize opening and closed and do not produce the joint, the hydraulic support pole provides internal force and stabilizes and increase the stress intensity.
Drawings
FIG. 1 is a perspective view of the present invention;
FIG. 2 is a schematic perspective view of the rear view of the present invention;
FIG. 3 is a front view of the present invention;
FIG. 4 is a schematic right sectional view of the present invention;
FIG. 5 is a schematic top view of the present invention;
fig. 6 is an enlarged schematic view of a portion a in fig. 1 according to the present invention.
In the figure: 1. a first ring; 2. a wedge block; 3. an inner screw rod; 4. a stationary ring plate; 5. fastening a bolt; 6. an outer barrel; 7. an L plate; 8. a second ring; 9. a hydraulic telescopic column; 10. a wire rod; 11. a hydraulic support rod; 12. a positioning sleeve; 13. a chute; 14. positioning holes; 15. a sliding sleeve; 16. a bottom hinge sleeve; 17. a slider; 18. a support ring plate; 19. positioning the bolt; 20. a shaft seat; 21. a support plate; 22. a movable clamp; 23. a level bar; 24. installing a clamp; 25. a top hinge sleeve; 26. a first clamping plate; 27. a second card.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is apparent that the described embodiments are only a part of the embodiments of the present invention, not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1-6, an electric power construction wire pole anti-tilt auxiliary correction maintenance device comprises a first ring 1 and a wire pole 10, wherein one end of the first ring 1 is hinged with a second ring 8, the other end of the second ring 8 is movably provided with a fixed ring plate 4, the inside of the fixed ring plate 4 is hinged with a fastening bolt 5, the inside of the first ring 1 and the second ring 8 are respectively provided with a chute 13, the inside of the chute 13 is provided with a positioning hole 14, the outside of the first ring 1 and the outside of the second ring 8 are movably sleeved with three sliding sleeves 15, the inside of the three sliding sleeves 15 are respectively provided with a sliding block 17, the top of each sliding sleeve 15 is hinged with a bottom hinge sleeve 16, the inside of each bottom hinge sleeve 16 is in threaded connection with a hydraulic telescopic column 9, the outside of the top end of the hydraulic telescopic column 9 is in threaded connection with a top hinge sleeve 25, the opposite side of the top hinge sleeve 25 is hinged with a mounting clamp 24, one side of the mounting clamp 24 is movably provided with a first clamping plate 26, the bottom fixed mounting of installation clamp 24 has three extension board 21, the equal movable mounting in bottom of three extension board 21 has hydraulic support pole 11, position sleeve 12 has been cup jointed in the outside activity of hydraulic support pole 11 bottom, the equal fixed mounting in opposite side of three sliding sleeve 15 has axle bed 20, outer barrel 6 has been cup jointed in the inside activity of axle bed 20, the internal thread of outer barrel 6 is connected with interior screw rod 3, the other end fixed mounting of interior screw rod 3 has L board 7, the internal thread of the L board 7 other end is connected with positioning bolt 19, the fixed ring board 18 that has been cup jointed in the bottom in the wire pole 10 outside, the bottom fixed mounting in the wire pole 10 outside has four voussoirs 2, movable clamp 22 has been cup jointed in the outside activity of wire pole 10, movable clamp 22's the outside is provided with three level bar 23, one side movable mounting of movable clamp 22 has second cardboard 27.
The working principle of the technical scheme is as follows:
during operation, firstly, the wire rod 10 is pre-buried at an operation position, then the supporting ring plate 18 is positioned on the ground, then when the wire rod 10 is corrected, the installation clamp 24 and the movable clamp 22 are respectively sleeved at preset positions on the outer side of the wire rod 10 and are respectively fixed by the hinge bolts on the inner sides of the first clamping plate 26 and the second clamping plate 27, then the first ring 1 and the second ring 8 are opened and sleeved on the outer side of the wire rod 10 and are positioned at a central position, the fixed ring plate 4 is fixed at the positions of the first ring 1 and the second ring 8, at the moment, the inner screw rod 3 is rotated, the inner screw rod 3 is matched and connected with the outer screw barrel 6 through threads, the inner screw rod 3 is similar to a bolt nut, after the inner screw rod 3 is rotated and extended, the inner part of the L plate 7 is rotatably hinged into the positioning bolt 19 and is inserted into the bolt hole, at the moment, the outer screw barrel 6 is rotated under the action of the shaft seat 20, the hydraulic telescopic column is stretched relative to the inner screw rod 3, so that the first ring 1, the second ring 8 and the sliding sleeves 15 on the outer sides of the first ring 1 and the second ring 8 are positioned at triangular positions, the whole hydraulic telescopic column is positioned on the outer side of the center of the wire rod 10, the two ends of the hydraulic telescopic column 9 are respectively hinged inside the top hinge sleeve 25 and the bottom hinge sleeve 16 in a rotating thread fit mode, so that the hydraulic telescopic column and the wire rod 10 form a triangular structure, the scheme is convenient to install and stable in moment, different wire rods 10 can be positioned and straightened, the opening and the installation are convenient, the operation efficiency is improved, then in the straightening process, the first ring 1 and the second ring 8 are fixed on the ground through inserting bolts into the positioning holes 14, the stretching of the hydraulic telescopic column 9 is started, the wire rods 10 are straightened step by step, the vertical positions of the wire rods 10 are observed through the horizontal ruler 23, the stretching amount of the hydraulic telescopic column 9 is adjusted according to the inclination amount of the horizontal ruler 23, the wire rods 10 are straightened visually, then will bury pre-buried gap department and fix and pack the concrete position of line pole 10 through voussoir 2 to can demolish line pole 10 vertical fixation back through the support, be convenient for adjust the use according to the condition of difference.
In another embodiment, as shown in fig. 1 and 5, the end of the fixed ring plate 4 remote from the second ring plate 8 is fixedly mounted inside the first ring 1.
The fixed ring plate 4 breaks away from when first ring 1 and second ring 8 are opened, inserts during the closure inside spout 13, inserts through fastening bolt 5 will spiral insert with first ring 1 and second ring 8 fix, this design, be convenient for straightening up can open and embolia to the line pole 10 of equal specification.
In another embodiment, as shown in fig. 1, 2 and 5, the positioning holes 14 are uniformly distributed in the inner part of the first ring 1 and the second ring 8 in a ring shape, and the bottom of the positioning holes 14 can be selected from movably-mounted universal wheels.
The locating hole 14 is inside can insert the awl for first ring 1 and 8 nails of second ring are subaerial, provide certain moment and fixed position, can optionally install the universal wheel through locating hole 14 moreover, and the overall structure's of being convenient for removal makes its installation that can be swift and prevent inclining the convenience that has increased the device.
In another embodiment, as shown in fig. 1, 2 and 4, the slider 17 is movably mounted inside the slide groove 13.
The slider 17 slides in the inside of spout 13, and the whole first ring 1 of agreeing with of sliding sleeve 15 in the cooperation outside and the second ring 8 of being convenient for increase the internal force at the in-process of straightening, avoid deformation to can increase the dynamics of straightening and make its more perfect correspond slightly heavy line pole 10, it is stable to have increased mechanics.
In another embodiment, as shown in fig. 1 and 2, the inside of the supporting ring plate 18 is opened with bolt holes, and the number of the bolt holes is at least six, and the size of the positioning bolt 19 is slightly smaller than the bolt holes.
The bolt hole effect of the inside of the supporting ring plate 18 is that firstly, a positioning insertion point is provided for the positioning bolt 19, the positioning center position is convenient to locate, the internal force in the straightening and inclination preventing process is increased, the structure is more stable, the moment between the structures is convenient to stabilize, and the service life is indirectly prolonged.
In another embodiment, as shown in fig. 1 and 2, a positioning column is fixedly installed at the bottom of the positioning sleeve 12, and the positioning column is inserted into the bolt hole.
The reference column that the position sleeve 12 bottom set up can be pegged graft inside the bolt hole, be convenient for adjust the cross condition of hydraulic support pole 11 and positioning bolt 19 according to the circumstances of reality, the moment of being convenient for is stable, and make hydraulic support pole 11 can pull down, and can make installation clamp 24 leave when corresponding groove when using, pole 10 along the line that drives extension board 21 and installation clamp 24 under the perpendicular flexible effect of hydraulic support pole 11 slides, whether it is enough to be used for detecting the straightness that hangs down, if the out of plumb then can produce the mechanics lock with the flexible post 9 of hydraulic pressure, this scheme can carry out inside perpendicular detection at the in-process of stabilizing the internal force and supporting, the stability of the structure of being convenient for, the convenience of operation has been increased.
In another embodiment, as shown in fig. 1-5, the mounting clip 24 is sized to fit the gauge of the wire pole 10, and the outside of the wire pole 10 is provided with an annular groove that fits the mounting clip 24 and the traveling clip 22.
The installation clamp 24 can be movably sleeved on the outer side of the wire rod 10 to provide certain support and positioning for the structure, and the annular groove provides certain limiting support for the installation clamp 24 and the movable clamp 22, so that the moment stability and the force application point position stability are facilitated.
In another embodiment, as shown in fig. 1-5, three levels 23 are annularly disposed on the outside of the movable clamp 22, the three levels 23 are uniformly distributed across the top hinge sleeve 25, and the positions of the three levels 23 correspond to the positions of the hydraulic support rod 11.
When the flexible volume of three hydraulic stretching post 9 is different or line pole 10 is out of plumb, the corresponding deflection of three level bar 23 reaction, a level bar 23 can reflect the inclination between two hydraulic stretching post 9, the operating personnel of being convenient for adjust and change flexible volume directly perceivedly, and because hydraulic stretching post 9 can be followed the inside dismantlement of end hinge joint cover 16 and top hinge joint cover 25 and consequently overall structure can realize opening and closed and do not produce the joint, hydraulic support pole 11 provides that the internal force is stable and increase the stress intensity.
The working principle and the using process of the invention are as follows: during operation, firstly, the wire rod 10 is pre-buried at an operation position, then the supporting ring plate 18 is positioned on the ground, then when the wire rod 10 is corrected, the installation clamp 24 and the movable clamp 22 are respectively sleeved at preset positions on the outer side of the wire rod 10 and are respectively fixed by the hinge bolts on the inner sides of the first clamping plate 26 and the second clamping plate 27, then the first ring 1 and the second ring 8 are opened and sleeved on the outer side of the wire rod 10 and are positioned at a central position, the fixed ring plate 4 is fixed at the positions of the first ring 1 and the second ring 8, at the moment, the inner screw rod 3 is rotated, the inner screw rod 3 is matched and connected with the outer screw barrel 6 through threads, the inner screw rod 3 is similar to a bolt nut, after the inner screw rod 3 is rotated and extended, the inner part of the L plate 7 is rotatably hinged into the positioning bolt 19 and is inserted into the bolt hole, at the moment, the outer screw barrel 6 is rotated under the action of the shaft seat 20, the hydraulic telescopic column is stretched relative to the inner screw rod 3, so that the first ring 1, the second ring 8 and the sliding sleeves 15 on the outer sides of the first ring 1 and the second ring 8 are positioned at triangular positions, the whole hydraulic telescopic column is positioned on the outer side of the center of the wire rod 10, the two ends of the hydraulic telescopic column 9 are respectively hinged inside the top hinge sleeve 25 and the bottom hinge sleeve 16 in a rotating thread fit mode, so that the hydraulic telescopic column and the wire rod 10 form a triangular structure, the scheme is convenient to install and stable in moment, different wire rods 10 can be positioned and straightened, the opening and the installation are convenient, the operation efficiency is improved, then in the straightening process, the first ring 1 and the second ring 8 are fixed on the ground through inserting bolts into the positioning holes 14, the stretching of the hydraulic telescopic column 9 is started, the wire rods 10 are straightened step by step, the vertical positions of the wire rods 10 are observed through the horizontal ruler 23, the stretching amount of the hydraulic telescopic column 9 is adjusted according to the inclination amount of the horizontal ruler 23, the wire rods 10 are straightened visually, then will bury pre-buried gap department and fix and pack the concrete position of line pole 10 through voussoir 2 to can demolish line pole 10 vertical fixation back through the support, be convenient for adjust the use according to the condition of difference.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (8)

1. The utility model provides an electric power construction line pole prevents supplementary correction of slope and maintains device, includes first ring (1) and line pole (10), its characterized in that: one end of the first ring (1) is hinged with a second ring (8), the other end of the second ring (8) is movably provided with a fixed ring plate (4), the inside of the fixed ring plate (4) is hinged with a fastening bolt (5), the insides of the first ring (1) and the second ring (8) are respectively provided with a sliding chute (13), the inside of each sliding chute (13) is provided with a positioning hole (14), the outsides of the first ring (1) and the second ring (8) are movably sleeved with three sliding sleeves (15), the insides of the three sliding sleeves (15) are respectively provided with a sliding block (17), the tops of the three sliding sleeves (15) are respectively hinged with a bottom hinged sleeve (16), the internal thread of each bottom hinged sleeve (16) is connected with a hydraulic telescopic column (9), the external thread of the top end of each hydraulic telescopic column (9) is connected with a top hinged sleeve (25), and the opposite side of each top hinged sleeve (25) is hinged with a mounting clamp (24), a first clamping plate (26) is movably mounted on one side of the installation clamp (24), three support plates (21) are fixedly mounted at the bottom of the installation clamp (24), hydraulic support rods (11) are movably mounted at the bottoms of the three support plates (21), a positioning sleeve (12) is movably sleeved on the outer side of the bottom end of each hydraulic support rod (11), shaft seats (20) are fixedly mounted on the opposite sides of the three sliding sleeves (15), outer barrels (6) are movably sleeved on the inner portions of the shaft seats (20), inner threads of the outer barrels (6) are connected with inner threaded rods (3), L plates (7) are fixedly mounted at the other ends of the inner threaded rods (3), positioning bolts (19) are connected with the inner threads of the other ends of the L plates (7), a supporting ring plate (18) is fixedly sleeved at the bottom of the outer side of the wire rod (10), and four wedge blocks (2) are fixedly mounted at the bottom of the outer side of the wire rod (10), activity clamp (22) have been cup jointed in the outside activity of line pole (10), the outside of activity clamp (22) is provided with three level (23), one side movable mounting of activity clamp (22) has second cardboard (27).
2. The electric power construction mast inclination-prevention auxiliary straightening maintenance device according to claim 1, characterized in that: one end, far away from the second annular plate (8), of the fixed annular plate (4) is fixedly installed inside the first ring (1).
3. The electric power construction mast inclination-prevention auxiliary straightening maintenance device according to claim 1, characterized in that: the positioning holes (14) are uniformly distributed in the first ring (1) and the second ring (8) in an annular shape, and universal wheels which are movably mounted can be selected at the bottoms of the positioning holes (14).
4. The electric power construction mast inclination-prevention auxiliary straightening maintenance device according to claim 1, characterized in that: the sliding block (17) is movably arranged in the sliding groove (13).
5. The electric power construction mast inclination-prevention auxiliary straightening maintenance device according to claim 1, characterized in that: the support ring plate (18) is internally provided with bolt holes, the number of the bolt holes is at least six, and the specification size of the positioning bolt (19) is slightly smaller than that of the bolt holes.
6. The electric power construction mast inclination prevention auxiliary straightening maintenance device according to claim 5, characterized in that: the bottom of the positioning sleeve (12) is fixedly provided with a positioning column, and the positioning column is inserted in the bolt hole.
7. The electric power construction mast inclination-prevention auxiliary straightening maintenance device according to claim 1, characterized in that: the specification and size looks adaptation of installation clamp (24) and wire pole (10), and the outside of wire pole (10) is provided with the ring channel with installation clamp (24) and activity clamp (22) looks adaptation.
8. The electric power construction mast inclination-prevention auxiliary straightening maintenance device according to claim 1, characterized in that: the three level ruler (23) are annularly distributed on the outer side of the movable clamp (22), the three level ruler (23) and the top hinge sleeve (25) are uniformly distributed in a crossed mode, and the positions of the three level ruler (23) correspond to the position of the hydraulic support rod (11).
CN202111324047.XA 2021-11-10 2021-11-10 Supplementary correction of electric power construction line pole anti-tilt is maintained device Pending CN113958187A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111324047.XA CN113958187A (en) 2021-11-10 2021-11-10 Supplementary correction of electric power construction line pole anti-tilt is maintained device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111324047.XA CN113958187A (en) 2021-11-10 2021-11-10 Supplementary correction of electric power construction line pole anti-tilt is maintained device

Publications (1)

Publication Number Publication Date
CN113958187A true CN113958187A (en) 2022-01-21

Family

ID=79469968

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111324047.XA Pending CN113958187A (en) 2021-11-10 2021-11-10 Supplementary correction of electric power construction line pole anti-tilt is maintained device

Country Status (1)

Country Link
CN (1) CN113958187A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115119652A (en) * 2022-07-15 2022-09-30 江苏云梯仙草生物科技有限公司 Three-dimensional culture medium structure that dendrobii officmalis caulis sapling was planted
CN115263067A (en) * 2022-07-20 2022-11-01 青岛昊宇重工有限公司 Supporting framework for chimney periphery
CN116657974A (en) * 2023-07-31 2023-08-29 广东电网有限责任公司佛山供电局 Strong wind resistant device for assembled electric pole and control method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484557A (en) * 2015-12-29 2016-04-13 国家电网公司 Restoration device for inclined telegraph pole
CN110984674A (en) * 2019-11-27 2020-04-10 国网山东省电力公司经济技术研究院 Electric power engineering construction power consumption pole correcting device
CN112681863A (en) * 2020-12-29 2021-04-20 王极强 Electric pole correction device for power engineering and correction method thereof
CN213115759U (en) * 2020-06-29 2021-05-04 河南易能电力工程有限公司 Electric power engineering construction is with device of rectifying
CN213597624U (en) * 2020-09-03 2021-07-02 李申一郎 Auxiliary correcting device for electric power construction line pole

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105484557A (en) * 2015-12-29 2016-04-13 国家电网公司 Restoration device for inclined telegraph pole
CN110984674A (en) * 2019-11-27 2020-04-10 国网山东省电力公司经济技术研究院 Electric power engineering construction power consumption pole correcting device
CN213115759U (en) * 2020-06-29 2021-05-04 河南易能电力工程有限公司 Electric power engineering construction is with device of rectifying
CN213597624U (en) * 2020-09-03 2021-07-02 李申一郎 Auxiliary correcting device for electric power construction line pole
CN112681863A (en) * 2020-12-29 2021-04-20 王极强 Electric pole correction device for power engineering and correction method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115119652A (en) * 2022-07-15 2022-09-30 江苏云梯仙草生物科技有限公司 Three-dimensional culture medium structure that dendrobii officmalis caulis sapling was planted
CN115119652B (en) * 2022-07-15 2023-11-14 江苏云梯仙草生物科技有限公司 Three-dimensional culture medium structure for dendrobium candidum sapling planting
CN115263067A (en) * 2022-07-20 2022-11-01 青岛昊宇重工有限公司 Supporting framework for chimney periphery
CN115263067B (en) * 2022-07-20 2024-01-02 青岛昊宇重工有限公司 Support framework for chimney periphery
CN116657974A (en) * 2023-07-31 2023-08-29 广东电网有限责任公司佛山供电局 Strong wind resistant device for assembled electric pole and control method
CN116657974B (en) * 2023-07-31 2023-12-12 广东电网有限责任公司佛山供电局 Strong wind resistant device for assembled electric pole and control method

Similar Documents

Publication Publication Date Title
CN113958187A (en) Supplementary correction of electric power construction line pole anti-tilt is maintained device
CN111794589B (en) Safety protection bearing structure that town road bed was used
CN211405412U (en) Support frame suitable for electric power capital construction job site interim cable supports
CN108678527B (en) Auxiliary supporting device
CN213390161U (en) Foundation pit enclosure structure
CN215594050U (en) Row pile foundation pit supporting device for building engineering
CN216076412U (en) Steel stand straightness deviation of hanging down handles part
CN109098472A (en) A kind of building girder steel and steel-pipe pile integral supporting structure
CN214994068U (en) Lattice column mounting platform for subway construction
CN108678528B (en) Auxiliary supporting device for preventing telegraph pole from toppling
CN220318544U (en) Structure for auxiliary supporting tube
CN218206187U (en) Guard plate for building be convenient for concatenation
CN217998621U (en) Stainless steel bus shelter stand
CN218425294U (en) Building material device of buckling
CN215572954U (en) Shield constructs total powerstation of guidance system and observes fixed platform
CN216075155U (en) Pit-in-pit edge fender pile mounting structure
CN217128923U (en) Fixed bolster that building engineering used
CN214615809U (en) Civil engineering side slope protection reinforced structure
CN217438950U (en) Novel protection that municipal subway construction used encloses fender structure
CN213923905U (en) Jacking device
CN210439305U (en) Supporting structure in foundation pit row pile enclosure structure
CN214939652U (en) Road rail guard for municipal works
CN217267607U (en) Foundation structure of box-type substation
CN217106310U (en) Crossbeam additional strengthening for steel construction board house
CN217812791U (en) A enclose shelves device for town road construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20220121