CN113944167A - Settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence - Google Patents

Settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence Download PDF

Info

Publication number
CN113944167A
CN113944167A CN202111396122.3A CN202111396122A CN113944167A CN 113944167 A CN113944167 A CN 113944167A CN 202111396122 A CN202111396122 A CN 202111396122A CN 113944167 A CN113944167 A CN 113944167A
Authority
CN
China
Prior art keywords
settlement
soft soil
total
soil layer
consolidation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202111396122.3A
Other languages
Chinese (zh)
Other versions
CN113944167B (en
Inventor
徐传堡
郑俊杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University WHU
Original Assignee
Wuhan University WHU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University WHU filed Critical Wuhan University WHU
Priority to CN202111396122.3A priority Critical patent/CN113944167B/en
Publication of CN113944167A publication Critical patent/CN113944167A/en
Application granted granted Critical
Publication of CN113944167B publication Critical patent/CN113944167B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/23Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Geometry (AREA)
  • Theoretical Computer Science (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Environmental & Geological Engineering (AREA)
  • Agronomy & Crop Science (AREA)
  • Soil Sciences (AREA)
  • Architecture (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a settlement calculation method considering the influence of soft soil foundation prepressing excavation backfill construction, which comprises the following steps: analyzing the pre-pressing treatment depth, the load size and the treated consolidation degree of the site, determining the elevation change conditions of the site after pre-pressing, excavating and backfilling construction, respectively adopting linear and nonlinear compression modulus methods to calculate the total consolidation settlement of the filling layer, the residual total consolidation settlement of the soft soil layer caused by backfilling above the pre-pressing treatment depth and the total consolidation settlement of the soft soil layer below the pre-pressing treatment depth, finally calculating the average consolidation degree of the soft soil layer in different stages according to the backfilling process, calculating the total consolidation settlement and the settlement of each stage, and comparing the average consolidation degree with the site monitoring result. Compared with the existing method for calculating the settlement change in the construction process by considering the complex stress history or a finite element tool, the method can be applied to various complex working conditions considering the influences of pre-compaction backfill and excavation, improves the accuracy, is convenient to implement, and can be widely applied to the technical field of building engineering.

Description

Settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a settlement calculation method considering the influence of soft soil foundation prepressing excavation backfill construction.
Background
Engineering on soft ground often requires ground treatment by surcharge or vacuum preloading to increase its ground bearing capacity and reduce settlement. In general, the foundation treatment depth needs to reach the bottom of a soft soil layer, but in areas with thick coastal soft soil layers, the foundation treatment depth often cannot reach the specified depth, and at the moment, the settlement calculation problem of the soft soil layer in the subsequent excavation and backfilling construction process needs to be considered in a layering manner.
At present, a settlement calculation method considering the influence of soft soil foundation prepressing excavation backfill construction is not mature, and the main problem is focused on the influence of different construction processes on the stress state of the soft soil foundation. For settlement calculation needing to consider complicated stress history, calculation parameters are difficult to obtain, and the stress state of each stage of soil layer cannot be accurately known. When a large finite element tool is used for simulation calculation, the method has certain limitations and is difficult to guide engineering design due to the fact that finite element parameters are numerous, values are difficult to take, and experience and sensitivity are high.
Disclosure of Invention
In view of the above, the invention provides a settlement calculation method considering the influence of soft soil foundation prepressing excavation backfill construction with high accuracy.
The embodiment of the invention determines the elevation change conditions of the site after pre-pressing, excavating and backfilling construction by analyzing the pre-pressing treatment depth, the load size and the treated consolidation degree of the site, respectively adopts a linear and nonlinear compression modulus method to calculate the total consolidation settlement of a filling layer, the residual total consolidation settlement of a soft soil layer caused by backfilling above the pre-pressing treatment depth and the total consolidation settlement of the soft soil layer below the pre-pressing treatment depth, finally calculates the average consolidation degree of the soft soil layer at different stages according to the backfilling process, calculates the total consolidation settlement and the settlement at each stage, and compares the calculation results with the site monitoring results.
The technical scheme provided by the invention is as follows:
a settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence is characterized in that: the method comprises the following steps:
step 1: determining the pre-pressing treatment depth, the load size and the treated consolidation degree of the field, and determining the elevation change condition of the field after pre-pressing, excavation and backfilling construction;
step 2: calculating the total consolidation settlement of the filling layer;
and step 3: calculating the residual total consolidation settlement of the soft soil layer caused by backfilling above the pre-compaction treatment depth;
and 4, step 4: calculating the total consolidation settlement of the soft soil layer below the pre-pressing treatment depth;
and 5: calculating the average consolidation degree of the soft soil layer at different stages according to the backfilling process;
step 6: and calculating the total consolidation settlement and settlement of each stage, comparing with the on-site monitoring result to determine parameters, and recalculating.
Further, the step 1 comprises the following steps:
step 1.1, determining the field prepressing treatment depth to determine settlement calculation soil layer boundary;
step 1.2, determining the size of a pre-pressing treatment load so as to judge the consolidation state of foundation soil in the excavation and backfilling process;
step 1.3, determining the consolidation degree after treatment to calculate the residual total settlement of the soft soil layer caused by backfilling after pre-pressing treatment;
and step 1.4, determining the elevation change condition of the site after pre-pressing, excavating and backfilling construction so as to determine the magnitude of the additional stress acting on the foundation soil.
Further, the step 2 comprises the following steps:
step 2.1, calculating the total thickness of the filling layer, wherein the total thickness of the filling layer is the height from excavation to the bottom surface of the foundation pit to the final backfilled ground;
2.2, selecting proper filling calculation parameters, wherein the filling calculation parameters comprise a settlement calculation empirical coefficient and a compression modulus; the total consolidation settlement is calculated by adopting the compression modulus of the filled soil, and the reduction of the compression modulus value caused by poor filled soil or the improvement of the compression modulus value after layering and rolling needs to be considered;
and 2.3, calculating the total consolidation settlement of the filled soil under the self-weight stress by adopting a compression modulus method without considering the compression amount in the layered rolling construction process.
Furthermore, the calculation formula of the total consolidation settlement of the filling layer in the step 2 is as follows:
Figure BDA0003370402470000021
in the formula, S1Total consolidation settlement of the fill, psis-calculating the empirical coefficient of sedimentation, Esi-compression modulus of the fill, piTaking the dead weight stress of the fill, hi-total thickness of the fill layer.
Further, the step 3 comprises the following steps:
step 3.1, determining the thickness of the filling layer after pre-pressing and unloading, wherein the soft soil layer above the treatment depth is in a normal consolidation state again;
step 3.2, calculating the consolidation total settlement of the soft soil layer above the treatment depth caused by filling by adopting the nonlinear compression modulus;
and 3.3, calculating the residual total settlement of the soft soil layer above the treatment depth.
Furthermore, the compressive modulus under stress states of different depths is obtained through the e-p curve of the normal consolidated soil, the total consolidated settlement of the treated soft soil layer caused by soil filling is calculated, and the calculation formula is as follows:
Esisi)=a1σsi 2+a2σsi+a3
Figure BDA0003370402470000031
the residual total settlement is the product of the total consolidation settlement and the residual consolidation degree, and the calculation formula is as follows:
S2=S2′(1-U2t)
in the formula, Esisi) -nonlinear compressive modulus, σ, of soft soil layers under different stressessi-vertical stress of the soil layer; a is1、a2、a3-a coefficient; s2' calculating the total settlement of consolidation of soft soil layer above the treatment depth caused by filling by adopting nonlinear compression modulus psis-calculating the empirical coefficient of sedimentation, pi-additional stresses causing the soft soil layer to continue to settle; h isi-total thickness of the fill layer; s2-total settlement of the soft soil layer residue above the treatment depth, U2tAnd actually measuring the consolidation degree of the soft soil layer after pre-pressing treatment.
Furthermore, in the step 4, the influence of pre-pressing loading, unloading and foundation pit excavation on the soft soil layer below the pre-pressing treatment depth is not considered, namely the soft soil layer below the pre-pressing treatment depth is normal consolidated soil, and the additional stress causing consolidation settlement is the backfill soil gravity;
the calculation method adopts a nonlinear compression modulus method, and the calculation formula is as follows:
Figure BDA0003370402470000032
in the formula, S3Soft soil layer Total consolidation Settlement below the Pre-compaction treatment depth, psis-calculating the empirical coefficient of sedimentation, piAdditional stress, h, causing the soft soil layer to continue to subsidei-total thickness of the fill layer;
wherein E issisi) The calculation formula is as follows:
Esisi)=a1σsi 2+a2σsi+a3
Esisi) -nonlinear compressive modulus, σ, of soft soil layers under different stressessi-vertical stress of the soil layer; a is1、a2、a3-a coefficient.
Further, the step of step 5 is as follows: and determining the backfill thickness and the construction gap time of each stage of actual construction, and calculating the average consolidation degree in the backfill process of the soft soil layer by adopting an improved high-handsome method.
Further, the step of step 6 is as follows:
step 6.1, the total consolidation settlement is the sum of the total consolidation settlement of the fill layer, the remaining total consolidation settlement of the soft soil layer above the pre-pressing treatment depth and the total consolidation settlement of the soft soil layer below the pre-pressing treatment depth, and the calculation formula is as follows:
S=S1+S2+S3
wherein S is1For total consolidation settlement of the fill, S2For the remaining total consolidation settlement of soft soil layers above the pre-compaction treatment depth, S3The soft soil layer is subjected to total consolidation settlement below the pre-pressing treatment depth;
step 6.2, comparing with the field monitoring result, and calibrating the calculation parameter UtThe settlement calculation of the influence of soft soil foundation prepressing excavation backfill construction is considered again;
the calibration calculation was performed using the following formula:
St=S·Ut
wherein S istFor total consolidation settlement, U, monitored in situtThe average consolidation degree of the soft soil layer at different stages.
Further, in the present invention,
the backfilling is large-area backfilling, and the reduction of a limited area is considered for backfilling positions close to a basement structure and the like by adding stress;
ground rebound caused by preloading unloading is not considered in the calculation;
foundation and superstructure construction is immediately carried out after foundation pit excavation is assumed, and foundation springback caused by foundation pit excavation is not considered;
compared with the soft soil layer below the prepressing treatment depth, the residual total settlement of the soft soil layer above the prepressing treatment depth can be completed within a period of time after the soft soil layer is backfilled to the designed elevation;
when a linear compression modulus method is adopted, the sedimentation empirical coefficient is 1.5; when the nonlinear compression modulus method is employed, the empirical coefficient of sedimentation is 1.0.
The invention has the following beneficial effects:
(1) compared with the existing method for calculating the settlement change in the construction process by considering the complex stress history or a finite element tool, the method can be applied to various complex working conditions considering the influences of pre-compaction backfill and excavation, improves the accuracy and is convenient to implement.
(2) The calculation method disclosed by the invention is clear in mechanical concept, simple and convenient in calculation, stable in calculation result, reliable and simple, solves the problems of complicated settlement calculation and unreliable result considering the influence of the pre-pressing excavation backfill construction, and provides an effective, simple and convenient practical calculation method for soft soil foundation settlement under the complex construction working condition of actual engineering calculation.
Drawings
FIG. 1 is a flow chart of the steps of an embodiment of the present invention;
FIG. 2 is a calculation chart of the total consolidation settlement of the soft soil layer caused by backfilling above the total consolidation settlement and the pre-compaction treatment depth of the fill layer and the total consolidation settlement of the soft soil layer below the pre-compaction treatment depth;
FIG. 3 is a graph of the present invention illustrating the stacking versus time and consolidation versus time;
FIG. 4 is a graph comparing the calculated settlement at each stage of the construction with the actual measurement monitoring result at the site;
fig. 5 is a soft soil layer e-p curve.
Detailed Description
The invention will be further explained and explained with reference to the drawings and the embodiments in the description. The step numbers in the embodiments of the present invention are set for convenience of illustration only, the order between the steps is not limited at all, and the execution order of each step in the embodiments can be adaptively adjusted according to the understanding of those skilled in the art.
Examples
Referring to fig. 1, an embodiment of the present invention provides a settlement calculation method considering the influence of soft soil foundation pre-compaction excavation backfill construction, including the following steps:
step 1: determining the pre-pressing treatment depth, the load size and the treated consolidation degree of the field, and determining the elevation change condition of the field after pre-pressing, excavation and backfilling construction;
step 2: calculating the total consolidation settlement of the filling layer;
and step 3: calculating the residual total consolidation settlement of the soft soil layer caused by backfilling above the pre-compaction treatment depth;
and 4, step 4: calculating the total consolidation settlement of the soft soil layer below the pre-pressing treatment depth;
and 5: calculating the average consolidation degree of the soft soil layer at different stages according to the backfilling process;
step 6: calculating the total consolidation settlement and settlement of each stage, comparing with a field monitoring result to determine parameters, and recalculating;
specifically, the step 1 includes the following steps:
1.1, determining the field prepressing treatment depth to determine settlement calculation soil layer boundary;
1.2, determining the size of the pre-pressing treatment load so as to judge the consolidation state of the foundation soil in the excavation and backfilling process;
1.3, determining the consolidation degree after treatment to calculate the residual total settlement of the soft soil layer caused by backfilling after pre-pressing treatment;
1.4, determining the elevation change condition of the site after pre-pressing, excavating and backfilling construction so as to determine the magnitude of additional stress acting on foundation soil;
specifically, the step 2 includes the following steps:
2.1, calculating the total thickness of the filling layer, wherein the total thickness of the filling layer is the height from excavation to the bottom surface of the foundation pit to the final backfilled ground;
2.2 selecting proper filling calculation parameters, wherein the calculation parameters comprise a settlement calculation empirical coefficient and a compression modulus; the total consolidation settlement is calculated by adopting the compression modulus of the filled soil, and the reduction of the compression modulus value caused by poor filled soil or the improvement of the compression modulus value after layering and rolling needs to be considered;
2.3 calculating the total consolidation settlement of the filling layer;
calculating the total consolidation settlement of the filling layer, wherein the total consolidation settlement of the filling under the dead weight stress is calculated by adopting a compression modulus method without considering the compression amount in the layered rolling construction process, and the calculation formula is as follows:
Figure BDA0003370402470000061
in the formula, S1Total consolidation settlement of the fill, psis-calculating the empirical coefficient of sedimentation, Esi-compression modulus of the fill, piTaking the dead weight stress of the fill, hi-total thickness of the fill layer;
specifically, the step 3 includes the following steps:
3.1 determining the thickness of the filling layer after pre-pressing and unloading, and enabling the soft soil layer above the treatment depth to be in a normal consolidation state again;
3.2 calculating the total consolidation settlement of the soft soil layer above the treatment depth caused by filling by adopting the nonlinear compression modulus;
3.3 calculating the residual total settlement of the soft soil layer above the treatment depth.
As shown in fig. 2, when the additional stress caused by the backfill reaches the pre-compaction pressure, the soft soil continues to settle above the treatment depth at the backfill height;
and (3) solving the compression modulus under different depth stress states through a normal consolidated soil e-p curve, and calculating the total consolidated settlement of the treated soft soil layer caused by soil filling, wherein the calculation formula is as follows:
Esisi)=a1σsi 2+a2σsi+a3
Figure BDA0003370402470000062
the residual total settlement is the product of the total consolidation settlement and the residual consolidation degree, and the calculation formula is as follows:
S2=S2′(1-U2t)
in the formula, Esisi) -nonlinear compressive modulus, σ, of soft soil layers under different stressessi-vertical stress of the soil layer; a is1、a2、a3-a coefficient; s2' calculating the total settlement of consolidation of soft soil layer above the treatment depth caused by filling by adopting nonlinear compression modulus psis-calculating the empirical coefficient of sedimentation, piAdditional stress, h, causing the soft soil layer to continue to subsidei-total thickness of the fill layer; s2-total settlement of the soft soil layer residue above the treatment depth, U2tAnd actually measuring the consolidation degree of the soft soil layer after pre-pressing treatment.
Specifically, in the step 4, the influence of the pre-compaction loading, unloading and foundation pit excavation on the soft soil layer below the pre-compaction treatment depth is not considered, namely the soft soil layer below the pre-compaction treatment depth is normal consolidated soil, the additional stress causing the consolidation settlement is the backfill soil gravity, the calculation method adopts a nonlinear compression modulus method, and the calculation formula is as follows:
Figure BDA0003370402470000063
in the formula, S3Soft soil layer Total consolidation Settlement below the Pre-compaction treatment depth, psis-calculating the empirical coefficient of sedimentation, piAdditional stress, h, causing the soft soil layer to continue to subsidei-total thickness of the fill layer;
wherein E issisi) The calculation formula is as follows:
Esisi)=a1σsi 2+a2σsi+a3
Esisi) -nonlinear compression modulus, σ, of soft soil layers under different stress conditionssi-vertical stress of the soil layer; a is1、a2、a3-a coefficient.
Specifically, in the step 5, as shown in fig. 3, the backfill soil thickness and the construction gap time at each actual construction stage are determined, and the average consolidation degree in the soft soil layer backfilling process is calculated by using an improved handsome method.
Specifically, the step 6, as shown in fig. 4, includes the following steps:
6.1 the total consolidation settlement is equal to the sum of the total consolidation settlement of the filling layer, the remaining total consolidation settlement of the soft soil layer above the prepressing treatment depth and the total consolidation settlement of the soft soil layer below the prepressing treatment depth, and the calculation formula is as follows:
S=S1+S2+S3
wherein S is1For total consolidation settlement of the fill, S2For the remaining total consolidation settlement of soft soil layers above the pre-compaction treatment depth, S3The soft soil layer is subjected to total consolidation settlement below the pre-pressing treatment depth;
6.2 comparing with the on-site monitoring result to calibrate the calculation parameter UtCarrying out settlement calculation considering the influence of soft soil foundation prepressing excavation backfill construction again;
the calibration calculation was performed using the following formula:
St=S·Ut
wherein S istFor total consolidation settlement, U, monitored in situtThe average consolidation degree of the soft soil layer at different stages.
Taking the calculation of total settlement after pre-pressing, foundation pit excavation and backfilling of a certain office building foundation on the soft soil foundation as an example, the pre-pressing treatment depth is known to be 18m, and a soft soil layer with 13.5m is still below the treatment depth. The ground elevation of the field after vacuum preloading treatment is 1.5m, the foundation pit is excavated until the elevation of the pit bottom is-3.75 m, the fertilizer tank of the foundation pit is backfilled to +2.45m, the soil is backfilled to +4.95m for the second time, and finally the field elevation is backfilled to + 5.40- +5.72m through gardens and roads.
Detailed description the concrete implementation steps of the settlement calculation method considering the influence of the soft soil foundation prepressing excavation backfill construction are as follows:
(1) and according to the pre-pressing treatment depth, dividing the whole foundation into three layers of soil for calculation, wherein the three layers of soil are respectively a fill layer, a soft soil layer above the pre-pressing treatment depth and a soft soil layer below the treatment depth. Determining the thickness of the backfill settlement to be 6.1m by taking the excavation bottom elevation of the foundation pit as a standard; and determining the thickness of the filling soil which causes the consolidation and settlement of the lower soft soil layer to be 3.85m based on the elevation of the ground of the field after the vacuum preloading treatment being 1.5 m. When the backfill thickness reaches 3.85m, the lower lying soft soil layer is in a normal consolidation state.
(2) And (5) taking the compression modulus Es of the filling layer as 10MPa, and calculating the self-sedimentation of the filling under the self-weight of the filling.
S1=18.5×6.10/2×6.10/10=34.4mm。
(3) According to the soft soil layer e-p curve, as shown in figure 5.
Calculating the nonlinear relation between the vertical stress sigmaz and the compressive modulus Es as follows:
Esz)=-0.000005σz 2+0.0115σz+0.0112
the layering thickness is 1.0m, and the nonlinear compression modulus results of the upper and lower soft soil layers of the pre-pressing treatment depth are calculated as follows:
Figure BDA0003370402470000091
and calculating the total consolidation settlement of the soft soil layer above the pre-pressing treatment depth by adopting the upper surface nonlinear compression modulus: s2The average value of the soft soil consolidation degree after the field actual measurement prepressing treatment is 85 percent, so the residual total consolidation settlement of the soft soil layer above the prepressing treatment depth is as follows: s2=126.1×(1-85%)=18.9mm。
(4) And (3) calculating by adopting a nonlinear compression modulus to calculate the total consolidation settlement of the soft soil layer with the pre-compaction treatment depth below: s3=713.4mm;
(5) Calculating an average consolidation degree curve in the soft soil layer backfilling process by adopting an improved handsome method, wherein the calculation parameters and the process are as follows:
soil series Severe gamma/kN m-3 Thickness/m Permeability coefficient kv/cm/s Compression modulus Es/MPa
Soft soil layer with more than depth of prepressing treatment 16.8 15.8 - -
Soft soil layer below prepressing treatment depth 16 13.5 1.32×10-7 1.9
For the treated sludge, the remaining settling amount is assumed to be completed within a certain time after the completion of the loading.
For the sludge which is not pre-pressed and is treated in the lower horizontal position, the calculation parameters in the formula are as follows:
α=8/π2=0.8106;
Cv=kvEs1w=0.0217
β=π2×Cv/4H2=0.00117
in the embodiment, the backfill work is started after the foundation pit is excavated to the pit bottom elevation in 7 months in 2017, and the backfill construction process at the section 1 is calculated as follows:
designing the elevation of a foundation pit slope-laying excavation bottom to be 3.75m within 3-7 months in 2017;
② 11-12 months in 2017, backfilling the foundation pit fertilizer groove from +1.50m to +2.45 m;
③ 5-7 months in 2018, and backfilling the foundation pit to +4.95m for the second time;
fourthly, 10-11 months in 2018, and backfilling the garden to a height of +5.35 m;
calculating the average consolidation degree of the soft soil layer at different stages according to the excavation and backfilling process, wherein the calculation result is shown in figure 3;
(6) total consolidated settlementThe total consolidation settlement of the filling layer, the remaining total consolidation settlement of the soft soil layer above the pre-pressing treatment depth and the total consolidation settlement of the soft soil layer below the pre-pressing treatment depth are equal to the sum: s ═ S1+S2+S3=873.9mm;
The calculated results of settlement at each stage are compared with the actual measurement results as shown in FIG. 4.
From the calculation results in the step (6), the total settlement calculated by the settlement calculation method considering the influence of the pre-compaction excavation backfill construction, the settlement calculation results of each construction stage are more consistent with the field actual measurement results, and the calibration of the calculation parameters can be carried out on the deviated actual measurement points to carry out the recalculation.
While the preferred embodiments of the present invention have been illustrated and described, it will be understood by those skilled in the art that various changes in form and details may be made therein without departing from the spirit and scope of the invention as defined by the appended claims.

Claims (10)

1. A settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence is characterized in that: the method comprises the following steps:
step 1: determining the pre-pressing treatment depth, the load size and the treated consolidation degree of the field, and determining the elevation change condition of the field after pre-pressing, excavation and backfilling construction;
step 2: calculating the total consolidation settlement of the filling layer;
and step 3: calculating the residual total consolidation settlement of the soft soil layer caused by backfilling above the pre-compaction treatment depth;
and 4, step 4: calculating the total consolidation settlement of the soft soil layer below the pre-pressing treatment depth;
and 5: calculating the average consolidation degree of the soft soil layer at different stages according to the backfilling process;
step 6: and calculating the total consolidation settlement and settlement of each stage, comparing with the on-site monitoring result to determine parameters, and recalculating.
2. The method according to claim 1, wherein the step 1 comprises the steps of:
step 1.1, determining the field prepressing treatment depth to determine settlement calculation soil layer boundary;
step 1.2, determining the size of a pre-pressing treatment load so as to judge the consolidation state of foundation soil in the excavation and backfilling process;
step 1.3, determining the consolidation degree after treatment to calculate the residual total settlement of the soft soil layer caused by backfilling after pre-pressing treatment;
and step 1.4, determining the elevation change condition of the site after pre-pressing, excavating and backfilling construction so as to determine the magnitude of the additional stress acting on the foundation soil.
3. The method according to claim 1, wherein the step 2 comprises the steps of:
step 2.1, calculating the total thickness of the filling layer, wherein the total thickness of the filling layer is the height from excavation to the bottom surface of the foundation pit to the final backfilled ground;
2.2, selecting proper filling calculation parameters, wherein the filling calculation parameters comprise a settlement calculation empirical coefficient and a compression modulus;
and 2.3, calculating the total consolidation settlement of the filled soil under the self-weight stress by adopting a compression modulus method without considering the compression amount in the layered rolling construction process.
4. The method of claim 3 wherein the total consolidated settlement of the fill is calculated by the formula:
Figure FDA0003370402460000011
in the formula, S1Total consolidation settlement of the fill, psis-calculating the empirical coefficient of sedimentation, Esi-compression modulus of the fill, piTaking the dead weight stress of the fill, hi-total thickness of the fill layer.
5. The method according to claim 1, wherein said step 3 comprises the steps of:
step 3.1, determining the thickness of the filling layer after pre-pressing and unloading, wherein the soft soil layer above the treatment depth is in a normal consolidation state again;
step 3.2, calculating the consolidation total settlement of the soft soil layer above the treatment depth caused by filling by adopting the nonlinear compression modulus;
and 3.3, calculating the residual total settlement of the soft soil layer above the treatment depth.
6. The method of claim 5, wherein: and (3) solving the compression modulus under different depth stress states through a normal consolidated soil e-p curve, and calculating the total consolidated settlement of the treated soft soil layer caused by soil filling, wherein the calculation formula is as follows:
Esisi)=a1σsi 2+a2σsi+a3
Figure FDA0003370402460000021
the residual total settlement is the product of the total consolidation settlement and the residual consolidation degree, and the calculation formula is as follows:
S2=S2′(1-U2t)
in the formula, Esisi) -nonlinear compressive modulus, σ, of soft soil layers under different stressessi-vertical stress of the soil layer; a is1、a2、a3Coefficient, S'2Calculating the total consolidation settlement of the soft soil layer above the treatment depth caused by filling by adopting the nonlinear compression moduluss-calculating the empirical coefficient of sedimentation, piAdditional stress, h, causing the soft soil layer to continue to subsidei-total thickness of the fill layer; s2-total settlement of the soft soil layer residue above the treatment depth, U2tAnd actually measuring the consolidation degree of the soft soil layer after pre-pressing treatment.
7. The method according to claim 1, wherein the step 4 does not consider the influence of the preloading loading, unloading and excavation of the foundation pit on the soft soil layer below the preloading depth, namely the soft soil layer below the preloading depth is normal consolidated soil, and the additional stress causing the consolidation settlement is the heavy degree of the backfill soil; the calculation method adopts a nonlinear compression modulus method, and the calculation formula is as follows:
Figure FDA0003370402460000022
in the formula, S3Soft soil layer Total consolidation Settlement below the Pre-compaction treatment depth, psis-calculating the empirical coefficient of sedimentation, piAdditional stress, h, causing the soft soil layer to continue to subsidei-total thickness of the fill layer;
wherein E issisi) The calculation formula is as follows:
Esisi)=a1σsi 2+a2σsi+a3
Esisi) -nonlinear compressive modulus, σ, of soft soil layers under different stressessi-vertical stress of the soil layer; a is1、a2、a3-a coefficient.
8. The method of claim 1, wherein the step of step 5 is as follows: and determining the backfill thickness and the construction gap time of each stage of actual construction, and calculating the average consolidation degree in the backfill process of the soft soil layer by adopting an improved high-handsome method.
9. The method of claim 1, wherein the step of step 6 is as follows:
step 6.1, the total consolidation settlement is the sum of the total consolidation settlement of the fill layer, the remaining total consolidation settlement of the soft soil layer above the pre-pressing treatment depth and the total consolidation settlement of the soft soil layer below the pre-pressing treatment depth, and the calculation formula is as follows:
S=S1+S2+S3
wherein S is1For total consolidation settlement of the fill, S2For the remaining total consolidation settlement of soft soil layers above the pre-compaction treatment depth, S3The soft soil layer is subjected to total consolidation settlement below the pre-pressing treatment depth;
step 6.2, comparing with the field monitoring result, and calibrating the calculation parameter UtThe settlement calculation of the influence of soft soil foundation prepressing excavation backfill construction is considered again;
the calibration calculation was performed using the following formula:
St=S·Ut
wherein S istFor total consolidation settlement, U, monitored in situtThe average consolidation degree of the soft soil layer at different stages.
10. The method of claim 1,
the backfilling is large-area backfilling, and the reduction of a limited area is considered for backfilling positions close to a basement structure and the like by adding stress;
ground rebound caused by preloading unloading is not considered in the calculation;
foundation and superstructure construction is immediately carried out after foundation pit excavation is assumed, and foundation springback caused by foundation pit excavation is not considered;
compared with the soft soil layer below the prepressing treatment depth, the residual total settlement of the soft soil layer above the prepressing treatment depth can be completed within a period of time after the soft soil layer is backfilled to the designed elevation;
when a linear compression modulus method is adopted, the sedimentation empirical coefficient is 1.5; when the nonlinear compression modulus method is employed, the empirical coefficient of sedimentation is 1.0.
CN202111396122.3A 2021-11-23 2021-11-23 Settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence Active CN113944167B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111396122.3A CN113944167B (en) 2021-11-23 2021-11-23 Settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111396122.3A CN113944167B (en) 2021-11-23 2021-11-23 Settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence

Publications (2)

Publication Number Publication Date
CN113944167A true CN113944167A (en) 2022-01-18
CN113944167B CN113944167B (en) 2022-11-18

Family

ID=79338640

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111396122.3A Active CN113944167B (en) 2021-11-23 2021-11-23 Settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence

Country Status (1)

Country Link
CN (1) CN113944167B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005344412A (en) * 2004-06-04 2005-12-15 Tetra Co Ltd Land subsidence reduction improvement method directly below the existing filling
CN101806056A (en) * 2010-04-28 2010-08-18 郭艳景 Soft-soil foundation treatment method for controlling secondary consolidation settlement
CN102720180A (en) * 2011-12-14 2012-10-10 汪文彬 Soft foundation treatment method employing 'cutting drainage deep-layer preloading and dynamic consolidating'
CN108694286A (en) * 2018-05-25 2018-10-23 中铁第四勘察设计院集团有限公司 A kind of soft soil roadbed settlement after construction computational methods
CN110727988A (en) * 2019-11-06 2020-01-24 中铁第四勘察设计院集团有限公司 Deep soft foundation consolidation settlement layering summation algorithm based on soft soil parameter space anisotropy
CN111898178A (en) * 2019-07-12 2020-11-06 江苏科能岩土工程有限公司 Consolidation degree calculation method for layered foundation combined preloading

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005344412A (en) * 2004-06-04 2005-12-15 Tetra Co Ltd Land subsidence reduction improvement method directly below the existing filling
CN101806056A (en) * 2010-04-28 2010-08-18 郭艳景 Soft-soil foundation treatment method for controlling secondary consolidation settlement
CN102720180A (en) * 2011-12-14 2012-10-10 汪文彬 Soft foundation treatment method employing 'cutting drainage deep-layer preloading and dynamic consolidating'
CN108694286A (en) * 2018-05-25 2018-10-23 中铁第四勘察设计院集团有限公司 A kind of soft soil roadbed settlement after construction computational methods
CN111898178A (en) * 2019-07-12 2020-11-06 江苏科能岩土工程有限公司 Consolidation degree calculation method for layered foundation combined preloading
CN110727988A (en) * 2019-11-06 2020-01-24 中铁第四勘察设计院集团有限公司 Deep soft foundation consolidation settlement layering summation algorithm based on soft soil parameter space anisotropy

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
姚丽娜: "基于e-p曲线的软土地基非线性沉降实用计算方法研究", 《中国优秀博硕士学位论文全文数据库(硕士)工程科技Ⅱ辑》, no. 1, 15 January 2015 (2015-01-15) *
谢中富: "淤泥质粘土层地基处理的方案设计", 《绍兴文理学院学报》, vol. 25, no. 8, 30 June 2005 (2005-06-30), pages 2 - 3 *

Also Published As

Publication number Publication date
CN113944167B (en) 2022-11-18

Similar Documents

Publication Publication Date Title
CN108376188B (en) Evaluation and calculation method for loess collapsibility
CN107315893B (en) Computing method for predicting settlement of ultra-long pile group by adopting composite foundation mode
CN106326552B (en) Dynamic compaction reinforcing method for improving hole collapse stability of cast-in-place pile
CN108252291A (en) The construction method of the coastal backfill super thick foundation of gravelly soil of 25000KN.m heavy tamping treatments
Fatahi et al. Settlement prediction and back analysis of Young’s modulus and dilation angle of stone columns
CN110761264A (en) Secondary dynamic compaction gravel replacement and reinforcement method for coastal sludge soft soil foundation
Mesri et al. Surcharging of soft ground to reduce secondary settlement
CN110727988A (en) Deep soft foundation consolidation settlement layering summation algorithm based on soft soil parameter space anisotropy
CN108643246B (en) The prediction technique that artesian water precipitation influences surrounding enviroment in foundation pit construction
Lam et al. Field trial of a membraneless vacuum preloading system for soft soil improvement
CN113215864B (en) Earth-rock interbed embankment structure and design method thereof
CN102352627B (en) Static pressure reinforcing treatment method for pile with unqualified bearing capacity
CN113944167B (en) Settlement calculation method considering soft soil foundation prepressing excavation backfill construction influence
CN108121831B (en) Vertical bearing capacity calculation method for bearing mode of large-diameter wide-shallow cylindrical foundation cylinder cover
CN108797558A (en) A kind of soft-soil foundation treatment method by controlling secondary consolidation settlement
CN111622202A (en) Method for filling and detecting boulder by dynamic compaction
CN100564697C (en) Horizontal top pipe ground treatment construction method
CN103122631A (en) Soft soil foundation preloading stamping reinforcement method
CN110512582B (en) Layered detection method for roadbed compactness
Stuedlein et al. Shear wave velocity measurements of stone column improved ground and effect on site response
SUN et al. The effect of initial water content on the consolidation of dredged slurry under vacuum preloading
Ruffing et al. Evaluations of lateral earth pressure in a soil-bentonite slurry trench cutoff wall
CN107435345B (en) Method for predicting settling volume of ultra-long pile group by adopting stress diffusion mode
Huang et al. The Influences of soil characteristics on the Negative Skin Friction on a single pile
CN117910265B (en) Ground subsidence calculation method considering total stress and soil parameter change during groundwater level descent

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant