CN113846869B - Engineering site massive body segmentation underpinning translation protection construction method - Google Patents

Engineering site massive body segmentation underpinning translation protection construction method Download PDF

Info

Publication number
CN113846869B
CN113846869B CN202111207746.6A CN202111207746A CN113846869B CN 113846869 B CN113846869 B CN 113846869B CN 202111207746 A CN202111207746 A CN 202111207746A CN 113846869 B CN113846869 B CN 113846869B
Authority
CN
China
Prior art keywords
steel
translation
underpinning
traction
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111207746.6A
Other languages
Chinese (zh)
Other versions
CN113846869A (en
Inventor
吴二军
陆建明
高彬
陆建华
薛志飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Juneng Construction Engineering Technology Co ltd
Original Assignee
Nantong Juneng Construction Engineering Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Juneng Construction Engineering Technology Co ltd filed Critical Nantong Juneng Construction Engineering Technology Co ltd
Priority to CN202111207746.6A priority Critical patent/CN113846869B/en
Publication of CN113846869A publication Critical patent/CN113846869A/en
Application granted granted Critical
Publication of CN113846869B publication Critical patent/CN113846869B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/06Separating, lifting, removing of buildings; Making a new sub-structure
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/06Separating, lifting, removing of buildings; Making a new sub-structure
    • E04G23/065Lifting of buildings
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Abstract

The invention discloses a translation protection technology for large block segmentation underpinning of an engineering site. The technology comprises the working procedures of dam body partition enclosure construction, underpinning structure construction, traction counter-force support construction, translational power equipment installation, dam body unit translation and in-place connection. The dam body unit enclosure adopts a double-layer baffle and a winding rope structure. The underpinning structure consists of closely-arranged steel pipe lower slideways and steel plate trays; the head and the tail of the steel plate tray are connected into a whole. The invention provides a technical scheme of large-block underpinning translation for protecting rammed earth cultural relic relics, can effectively realize more complete protection on the historical landscape, cultural relic value and ancient engineering technical information of rammed earth cultural relics, and has important bearing significance for solving the contradiction between social development planning and building relic protection by popularization and application.

Description

Engineering site massive body segmentation underpinning translation protection construction method
Technical Field
The invention relates to a construction method for protecting translation of a large block partition underpinning of an engineering site, belonging to the technical field of integral translation of buildings.
Background
With the continuous acceleration of city construction in China, a large number of existing buildings need to be dismantled and rebuilt due to old city reconstruction, road planning, track construction and the like. However, due to the cultural relic protection requirement, many ancient sites cannot be dismantled and rebuilt according to the traditional mode, and only can be reserved in situ, which brings little obstruction to the development and utilization of urban space. In order to solve the contradiction between old city reconstruction, new city construction and historical ancient site protection, the concept of relocation protection adopted for ancient sites should be born.
Nowadays, china has many related engineering cases for site relocation protection, such as public bidding: shanghai Mazuo temple relocation protection engineering, shanghai Guanglin culture site relocation protection engineering, xuzhou Mingdian health site integral relocation engineering, and the like. The construction method adopted by the vestige protection projects is as follows: cutting the blocks, wrapping, hoisting and transporting the blocks by using glass fiber reinforced plastic and flexible materials, and finally assembling and restoring at a new site. The method has high cost and low efficiency, has high possibility of damaging historical information and cultural relic values, can not meet the requirements of the existing removal protection of numerous historical sites, and is particularly not suitable for the removal protection of large-sized rammed earth structures. Therefore, the ancient site is preferably moved and protected by adopting the related technical means of integral translation of the building.
The integral translation construction method of the building refers to a construction method for integrally shifting the building from an original site to a proper position for protection and utilization under the condition of not influencing the use function of the building so as to meet the requirements of urban construction planning and the like. The whole translation construction method of the building is mature, the maximum translation building area exceeds 2 ten thousand square meters, the weight reaches 3 ten thousand tons (Xixi bus station rotation translation project behind the mansion door), and the maximum translation construction method exceeds 15 floors (Tugong office building translation in the Laiwu development area of Shandong). However, the existing construction method is not suitable for the relocation protection of rammed earth historic sites which exist in China in large quantity. The construction method is difficult to set underpinning and translation tracks in the foundation, the underpinning structure for translation of a building is mainly underpinning of an upper structure or underpinning of a foundation, the tracks are mostly in the form of strip foundations or sleeper steel rails, the construction methods all need large-area excavation of the building foundation and are difficult to implement in the soil body.
In the protection of some cultural relic buildings, part of projects also adopt a jacking pipe underpinning construction method in a foundation, but only used for jacking projects (such as the jacking protection projects of wonder mountain palace buildings). The lower rail is not needed to be arranged in the jacking engineering, only the jacking counter-force platform with enough bearing capacity is needed to be arranged, and the method is easily realized by applying a pile foundation or an independent column foundation. But the construction of the low-cost underpinning and track double structure in the soil body has great technical difficulty. Meanwhile, a counter-force platform in the jacking engineering does not need to be moved, and when the site area is large and translation is needed for a long distance, a large amount of cost can be generated by arranging the full-length track.
In conclusion, in the research of the existing integral translation construction method of the building, a large research space and potential application value are provided for the relevant construction method of ancient site translation protection. In order to solve the conflict between social development planning and effective protection of the building site, a underpinning translation protection construction method suitable for rammed earth ancient sites is developed based on a whole building translation construction method, so that the historical landscape, cultural relic value and ancient engineering technical information of the rammed earth ancient sites are more completely protected, and the method has important historical culture inheritance significance undoubtedly.
Disclosure of Invention
The invention aims to solve the technical problem of researching and developing a underpinning translation construction method suitable for large blocks of engineering sites based on the conventional integral translation construction method of buildings and based on the related engineering cases of ancient dam translation so as to protect the historical landscape, cultural relic value and ancient engineering technical information of rammed earth type building sites.
The basic idea of the invention is as follows: firstly, constructing a counterforce device and installing a horizontal power device at a preset position; then, carrying out partition enclosing construction on the ancient site, and arranging a horizontal underpinning structure; starting a horizontal power device, and alternately drawing a steel plate and a steel pipe lower slideway to enable the ancient site unit to move horizontally to a target position; finally completing the in-place connection with the new foundation at the target position.
The invention adopts the specific technical scheme that:
a construction method for protecting the translation of a large block in an engineering site by cutting and underpinning. The construction method is characterized by comprising the working procedures of traction reaction force support construction, ancient site body segmentation and enclosure construction, underpinning structure arrangement and installation, translation power equipment installation, ancient site body unit translation, in-place connection and the like. The dam body unit enclosing structure is constructed from the side surface of the soil body of the dam body from inside to outside: the inner baffle, the inner winding rope, the high-through outer baffle (or keel) arranged at intervals and the outer winding rope. The underpinning structure consists of closely-arranged steel pipe lower slideways and a steel plate tray; a traction ring is arranged in front of each steel pipe; the steel plate tray consists of a group of strip steel plates, tail connecting angle steel and a head steel connecting piece, wherein the strip steel plates are long along the moving direction; the bottom steel plate and the strip-shaped steel plate of the head connecting piece are provided with traction cable holes with coincident positions, the diameter of each cable hole is about 40mm, and the traction cable holes are usually arranged in a gap between two steel pipes. The traction counter-force support consists of a steel pipe pile driven into a foundation, a post-prestressed anchor rod, a connecting Hualan screw and a horizontal counter-force beam, wherein a steel cable hole is reserved in the counter-force steel beam.
The construction sequence of the project of the invention is as follows: firstly, constructing a counterforce device at a preset position, and installing a horizontal power device; then carrying out horizontal underpinning structure and ancient site body segmentation and enclosure construction (the sequence of two construction items can be exchanged, but the construction should not be carried out at the same time); then starting a horizontal power device to finish the translation of the ancient site body unit; finally, the in-place connection is completed at the target position.
The construction sequence of the traction counterforce device is as follows: firstly, pressing a steel pipe pile into a set position, wherein the steel pipe pile is required to extend out of the ground to a certain height; then a certain distance away from one side of the dam is driven into a reinforced concrete prestressed anchor rod, and the end part of the anchor rod is preferably just extended out of the ground; connecting the steel pipe pile with the upper end of the anchor rod by using the turn buckle and the steel cable, and rotating the turn buckle to tighten the steel cable; then, a reaction beam is arranged at the position close to the steel pipe pile, and a steel cable hole is reserved in the reaction beam along the translation direction for a traction steel cable to pass through; and finally, a translation power device (a jack or a plate rolling machine) is arranged on the counterforce beam.
The construction sequence of the underpinning structure is as follows: firstly, horizontally jacking densely-arranged steel pipes at the bottom of a translation dam body to serve as a lower slideway, wherein the diameter of each steel pipe is about 800mm, the length of each steel pipe is twice the width of an ancient site body, the distance between two steel pipes is about 1 m, when pipe jacking is difficult, soil guide holes can be dug through a horizontal spiral drill, steel cables penetrate through the guide holes, the front end of each steel pipe is connected to power equipment, and the rear end of each steel pipe is connected with a traction ring at the front end of the corresponding steel pipe and is pulled to be in place by the power equipment; then, strip-shaped steel plates are driven into the steel pipe along the steel pipe upper skin as a platform at intervals, the length of each strip-shaped steel plate is about 2 meters longer than the ancient site body, the front end and the rear end of each strip-shaped steel plate extend out of the underpinned ancient site body unit, the width of each strip-shaped steel plate is preferably just over 2 to 3 steel pipes, and when the strip-shaped steel plates are difficult to drive, a concrete wire cutting saw can be adopted to cut horizontal seams in soil bodies close to the upper parts of the steel pipes; and finally, the head connecting piece and the tail connecting angle steel are connected with the steel plate through bolts to form a whole.
The construction sequence of ancient ruins unit enclosure is as follows: firstly, determining the length of each section of ancient site body unit according to actual requirements, and generally controlling the length to be within the range of 5-10 meters; selecting a segmentation excavation working surface, designing a segmentation slit part between two sections of ancient site body units to form an inverted splayed slope, controlling the length of the top excavation working surface to be about 3.5 meters generally, and gradually reducing an excavation section along with the increase of excavation depth, but ensuring that the distance between two underpinning units is not less than 2.5 meters when the ancient site is excavated to the bottom; then, carrying out layered excavation, installing an inner baffle along the periphery of each layer of excavation, and firmly winding the inner baffle from the periphery by using an inner winding rope, wherein the height of each layer is about 1 m; when the dam is excavated to the bottom of the dam, the inner baffle and the inner winding rope are completely finished, the high-through outer baffles (or keels) are installed on four sides at intervals, and the outer winding rope is used for winding firmly.
The construction sequence of ancient site body unit translation is as follows: firstly, one end of a traction steel cable penetrates through a counter-force beam and is connected to power equipment, and the other end of the traction steel cable is connected to a reserved index hole in the front end of a steel plate tray through a hook; then starting power equipment to enable the steel plate tray and the upper ancient site body unit to integrally translate; after reaching a translation stroke, unhooking the steel cable hook from the front of the steel plate tray, hanging the steel cable hook on a traction ring at the front end of the steel pipe, and translating the steel pipe lower slideway forward by a stroke one by one at intervals; after all the steel pipe lower runners move forwards, unhooking, secondarily connecting the unhooking to the front end of the steel plate tray, and starting the second stroke translation; and repeating the translation stroke until the dam body reaches the designated target position, and finishing the translation operation.
Drawings
FIG. 1 is a general perspective view of a underpin translation device
FIG. 2 is a sectional elevation of ancient site
FIG. 3 is a plan view of the ancient site unit division
FIG. 4 is a side elevation view of ancient site unit partition
FIG. 5 is a perspective view of an inner wrap wire rope and an inner dam
FIG. 6 is a perspective view of an outer wrap cable and outer fenders
FIG. 7 is a front elevation view of the underpinning structure
FIG. 8 is a perspective view of a underpinning structure
FIG. 9 is a detail view of the steel connecting piece at the front end of the steel plate tray
FIG. 10 is a detail view of the angle steel at the rear end of the steel plate pallet
FIG. 11 is a partial plan view of a steel pallet
FIG. 12 is a vertical view of the horizontal power unit and the reaction force carrier
In the above figure: 1-ancient site body; 2-an inner baffle; 3-internally winding a steel cable; 4-an outer baffle; 5-externally winding a steel cable; 6-steel tube glide slope; 7-angle steel; 8-channel steel; 9-a traction wire rope; 10-steel pipe pile; 11-a threaded nail; 12-index hole; 13-bottom strip steel plate; 14-reaction beam; 15-a center-penetrating jack; 16-prestressed anchor rods; 17-turnbuckle; 18-counterforce device wire rope; 19-steel pipe traction ring
Detailed Description
The invention is further described below with reference to the accompanying drawings, which are only used to more clearly illustrate the technical solutions of the invention.
The specific operation of the invention in application comprises six stages: the method comprises the following steps of traction counter-force support construction, traction power equipment installation, ancient site body segmentation and enclosure construction, underpinning structure arrangement and installation, ancient site body unit translation and in-place connection.
The construction process of the traction reaction force support comprises the following steps:
1) And pressing the steel pipe pile into a set position, wherein the diameter of the steel pipe pile is about 800m, and the steel pipe pile is required to extend out of the ground to a certain height.
2) And (3) driving a reinforced concrete prestressed anchor rod into the steel pipe pile at a certain distance away from one side of the dam, wherein the end part of the anchor rod is preferably just extended out of the ground.
3) And the steel pipe pile is connected with the upper end of the anchor rod by using the turn buckle and the steel cable, and the turn buckle is used for tensioning the steel cable.
4) And a reaction beam is arranged at the position close to the steel pipe pile, and a steel cable hole is reserved in the reaction beam along the translation direction for a traction steel cable to pass through.
The installation process of the traction power equipment comprises the following steps:
1) And traction power equipment (a jack or a plate rolling machine) is arranged on the counter-force beam according to the reserved steel cable hole.
2) And (4) passing the traction steel cable through the steel cable hole to be connected with traction power equipment.
The ancient site body segmentation and enclosure construction process comprises the following steps:
1) And determining the length of each section of underpinning unit body and the number of underpinning unit bodies according to actual requirements, and determining the position of an excavation working face. The length of each underpinning unit is usually controlled within the range of 5 to 10 meters, and the length of the top excavation working face is usually controlled to be about 3.5 meters.
2) And (4) excavating the ancient site body downwards to about 1 m depth according to the determined excavation working face.
3) The inner baffle is arranged along the periphery, and the inner winding rope is firmly wound from the periphery.
4) And continuously excavating the dam body downwards to the depth of about 1 meter.
5) And further synchronously reinforcing and protecting the periphery of the excavated ancient site body by using an inner baffle and an inner winding rope.
6) And repeating the steps 4-5 until the distance between the two units and the ancient site bottom is excavated, and confirming that the distance between the two units and the ancient site bottom is not less than 2.5 meters.
7) The four sides are provided with high outer baffles (or keels) at intervals, and are firmly wound by outer winding ropes.
The underpinning structure is arranged and installed as follows:
1) The number of the required steel pipes is determined according to the actual length of each underpinning unit body, the diameter of each steel pipe is about 800mm, the length of each steel pipe is twice the width of the dam body, and the distance between the two steel pipes is controlled to be about 1 meter.
2) The number and the specification of the bottom steel plates are determined according to the arrangement design of the steel pipe downslide, the length of the bottom steel plates is about 2 meters larger than the width of the dam body, and the width of the bottom steel plates is preferably just across 2 to 3 steel pipes.
3) And determining the specifications of channel steel and angle steel according to the arrangement design of the bottom steel plate. The lengths of the channel steel and the angle steel are equal to the total width of the bottom steel plate. The type of the angle steel is preferably 20# hot-rolled double angle steel, the type of the channel steel is preferably 40# c hot-rolled common channel steel, and the types of the channel steel and the angle steel can be automatically determined through relevant mechanics calculation of an actual dam body.
4) And horizontally jacking densely-arranged steel pipes as a lower slideway at the bottom of the translational dam along the translational direction, digging soil guide holes by a horizontal spiral drill when pipe jacking is difficult, penetrating the guide holes by a steel cable, connecting the front end of the guide holes to power equipment, connecting the rear end of the guide holes to a traction ring at the front end of the steel pipes, and drawing the guide holes in place by the power equipment.
5) And (3) punching bar-shaped steel plates into the platform along the steel pipe upper skin at intervals, wherein the front ends and the rear ends of the bar-shaped steel plates extend out of the underpinned ancient site body units, and when punching is difficult, a concrete wire cutting saw can be adopted to cut horizontal seams in soil bodies close to the upper part of the steel pipe.
6) And a head steel connector is arranged at the front end of the dam body along the translation direction and is tightly connected with the steel plate by bolts.
7) And tail angle steel is arranged at the rear end of the dam body along the translation direction and is tightly connected with the steel plate by bolts.
The ancient site body unit translation process comprises the following steps:
1) One end of a traction steel cable penetrates through the counter-force beam and is connected to power equipment, and the other end of the traction steel cable is connected to a reserved index hole in the front end of the steel plate tray through a hook.
2) And starting power equipment to enable the steel plate tray and the upper ancient site body unit to integrally translate.
3) After reaching a translation stroke, the steel cable hook is unhooked from the front of the steel plate tray and hung on a traction ring at the front end of the steel pipe, and the steel pipe lower slideway is translated forwards by a stroke one by one at intervals
4) After the lower runners of all the steel pipes move forwards, the hooks are unhooked and secondarily connected to the front end of the steel plate tray, and the second stroke translation is started
5) And repeating the translation stroke of the step 2-5 until the dam body reaches the designated target position, and finishing the translation operation.

Claims (10)

1. A construction method for protecting the translation of a large block partition underpinned in an engineering site is characterized by comprising the following steps of: firstly, constructing a counterforce device at a preset position, and installing a horizontal power device; then carrying out horizontal underpinning structure and ancient site body segmentation enclosure construction, wherein the sequence of the horizontal underpinning structure and the ancient site body segmentation enclosure construction can be exchanged, but the horizontal underpinning structure and the ancient site body segmentation enclosure construction are not constructed at the same time; then starting translation power equipment to finish the translation of the ancient site body unit; finally, completing in-place connection at the target position; the construction method comprises the following working procedures of traction counter-force support construction, ancient site body segmentation enclosure construction, underpinning structure arrangement and installation, translation power equipment installation, ancient site body unit translation and in-place connection, wherein the dam body unit enclosure structure is constructed from the inside to the outside of the side surface of a dam body soil body: the underpinning structure consists of closely-arranged steel pipe lower slideways and steel plate trays; a traction ring is arranged in front of each steel pipe; the steel plate tray consists of a group of strip steel plates, tail connecting angle steel and a head steel connecting piece, wherein the strip steel plates are long along the moving direction; the bottom steel plate and the strip-shaped steel plate of the head connecting piece are provided with index holes with overlapped positions, the diameter of each index hole is about 40mm, the index holes are arranged in a gap between two steel pipes, the traction counter-force support is composed of a steel pipe pile, a post-prestressed anchor rod, a connecting turn buckle screw and a counter-force beam, and a steel cable hole is reserved in the counter-force beam;
the ancient ruined site body is located on the upper surface of the underpinning structure, the ancient ruined site body is located between the head steel connecting piece and the tail connecting angle steel, the diameter of each steel pipe used for arrangement is about 800mm, the length of each steel pipe is twice of the width of the dam body, the head steel connecting piece is located at the front end of the dam body in the translation direction, the tail connecting angle steel is located at the rear end of the dam body in the translation direction, and the translation power equipment is connected with one end of the traction steel cable.
2. The engineering site massive body segmentation, underpinning and translation protection construction method according to claim 1, characterized in that: the construction steps of the traction counter-force support comprise: firstly, pressing a steel pipe pile into a set position, wherein the diameter of the steel pipe pile is about 800mm, and the steel pipe pile extends out of the ground by a certain height; then, a reinforced concrete prestressed anchor rod is driven into one side of the steel pipe pile, which is far away from the dam, at a certain distance, and the end part of the anchor rod just extends out of the ground; connecting the steel pipe pile with the upper end of the anchor rod by using a turn buckle and a traction steel cable, and rotating the turn buckle to tighten the traction steel cable; then, a counterforce beam is installed in a manner of clinging to the steel pipe pile, and a steel cable hole is reserved in the counterforce beam along the translation direction; and finally, mounting translation power equipment on the counter-force beam.
3. The engineering site massive body segmentation, underpinning and translation protection construction method according to claim 1, characterized in that: the ancient site body segmentation and enclosure construction steps comprise: the length of each section of unit body is 5-10 meters, a slotting part is arranged between two sections of ancient site body units to form an inverted splayed slope, the excavation section is gradually reduced along with the increase of the excavation depth, the length of the upper excavation working face is about 3.5 meters, and the distance between two underpinning units is not less than 2.5 meters when the two underpinning units are excavated to the bottom of the dam.
4. The engineering site massive body segmentation, underpinning and translation protection construction method according to claim 3, characterized in that: the ancient site body segmentation and enclosure construction steps further comprise: the construction method of carrying out layered excavation, excavation and enclosure synchronously is adopted for construction, the height of each layer is about 1 m, an inner baffle is arranged along the periphery of each layer of excavation, and an inner winding rope is used for winding firmly from the periphery; when the dam is excavated to the bottom of the dam, the inner baffle and the inner winding rope are completely finished, the high outer baffles or the keels are arranged on the four sides at intervals, and the outer winding rope is used for winding firmly.
5. The engineering site massive body segmentation, underpinning and translation protection construction method according to claim 1, characterized in that: the underpinning structure arrangement and installation steps comprise: the method comprises the steps of firstly arranging the lower runners of the densely-arranged steel pipes, then installing the bottom strip-shaped steel plates, and finally connecting the tail connecting angle steel and the head steel connecting piece.
6. The engineering site massive body segmentation, underpinning and translation protection construction method according to claim 5, characterized in that: the steel pipe lower slideway arranging step comprises: the distance between the two steel pipes is about 1 meter, when the pipe jacking is difficult, a soil guide hole is dug through a horizontal spiral drill, a traction steel cable penetrates through the guide hole, the front end of the traction steel cable is connected to power equipment, the rear end of the traction steel cable is connected with a traction ring at the front end of the steel pipe, and the traction steel cable is pulled by the power equipment to be in place.
7. The engineering site massive body segmentation, underpinning and translation protection construction method according to claim 5, characterized in that: the bottom steel plate mounting step comprises: the length of the bottom steel plate used for installation is about 2 meters larger than the width of the dam body, the width of the bottom steel plate just spans 2 to 3 steel pipes, and when the strip-shaped steel plate is difficult to drive, a concrete wire cutting saw is adopted to cut horizontal seams in the soil body close to the upper part of the steel pipes.
8. The engineering site massive body segmentation, underpinning and translation protection construction method according to claim 5, characterized in that: afterbody angle of connection includes: the angle steel setting is in the trailing end of underpinning the structure along the translation direction, and angle steel length equals with bottom steel sheet total width, and through bolt and bottom bar steel sheet zonulae occludens.
9. The engineering site massive body segmentation, underpinning and translation protection construction method according to claim 5, characterized in that: the head steel connecting piece comprises the following steps: the head steel connecting piece is arranged at the front end of the underpinning structure along the translation direction and is formed by welding a strip steel plate and a reversed channel steel, an index hole is reserved in the strip steel plate, the strip steel plate bears traction force of a traction steel cable, the length of the strip steel plate is equal to the total width of the bottom steel plate, and the strip steel plate is tightly connected with the bottom strip steel plate through a bolt.
10. The engineering site massive body segmentation, underpinning and translation protection construction method according to claim 1, characterized in that: the ancient site body unit translation step comprises the following steps: the method of alternately implementing a plurality of translation strokes is adopted for operation, firstly, one end of a traction steel cable penetrates through a counterforce beam and is connected to power equipment, and the other end of the traction steel cable is connected to a reserved index hole at the front end of a steel plate tray through a hook; then starting power equipment to enable the steel plate tray and the upper ancient site body unit to integrally translate; after reaching a translation stroke, unhooking the traction steel cable hook from the front of the steel plate tray, hanging the traction steel cable hook on a traction ring at the front end of the steel pipe, and translating the steel pipe lower slideway forward by a stroke one by one at intervals; after all the steel pipe lower runners move forwards, unhooking, secondarily connecting the unhooking to the front end of the steel plate tray, and starting the second stroke translation; and repeating the translation stroke until the dam body reaches the designated target position, and finishing the translation operation.
CN202111207746.6A 2021-10-18 2021-10-18 Engineering site massive body segmentation underpinning translation protection construction method Active CN113846869B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111207746.6A CN113846869B (en) 2021-10-18 2021-10-18 Engineering site massive body segmentation underpinning translation protection construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111207746.6A CN113846869B (en) 2021-10-18 2021-10-18 Engineering site massive body segmentation underpinning translation protection construction method

Publications (2)

Publication Number Publication Date
CN113846869A CN113846869A (en) 2021-12-28
CN113846869B true CN113846869B (en) 2023-04-14

Family

ID=78978657

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111207746.6A Active CN113846869B (en) 2021-10-18 2021-10-18 Engineering site massive body segmentation underpinning translation protection construction method

Country Status (1)

Country Link
CN (1) CN113846869B (en)

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1034881C (en) * 1993-10-09 1997-05-14 阮蔚文 Method for moving house
CN2311564Y (en) * 1997-11-10 1999-03-24 赵启 Integral removing sliding apparatus for building
CA2449159A1 (en) * 2003-01-23 2004-07-23 The Mattamy Corporation Skate, beam and transporter device and system for transferring and aligning manufactured houses
JP3817579B2 (en) * 2003-10-30 2006-09-06 有限会社住環境設計室 Building foundation lifting device, building foundation lifting method using the same, and subsidence building foundation correction method
CN105888292B (en) * 2014-05-10 2017-12-12 河南省建设集团有限公司 Frame structure building is without underpining integral translating method
CN106223641B (en) * 2016-07-25 2018-05-01 河海大学 A kind of the power direction adjusting apparatus and its installation and construction method of the translation of building integral-rotation
CN111255236A (en) * 2020-03-16 2020-06-09 中铁七局集团郑州工程有限公司 Integral moving method for cast-in-situ beam full-space support

Also Published As

Publication number Publication date
CN113846869A (en) 2021-12-28

Similar Documents

Publication Publication Date Title
CN106088149B (en) A kind of mechanization rapid constructing method of precast splice type underground gallery
CN105421463B (en) Longitudinal excavation construction method of long-span dense-support super-long deep foundation pit
CN113482044B (en) Power pipeline relocation method for invading subway station structure
CN106979021A (en) Large-section loess tunnel is excavated and preliminary bracing quick closure looping technique
CN111236241A (en) Weak water-rich stratum subway foundation pit reinforcing excavation method based on half-cover excavation method
CN112983478A (en) Shallow-buried underground tunnel foundation pit construction method under protection of cover plate
CN107740423B (en) Construction method for prefabricated assembled urban underpass tunnel
CA2304533C (en) Arched support structure
CN113846869B (en) Engineering site massive body segmentation underpinning translation protection construction method
CN110439004B (en) Movable inner supporting device for foundation pit support and application method thereof
CN110029653B (en) Method for treating steel pipe pile foundation of riprap seabed foundation
CN205557535U (en) Compound retaining wall of arch campshed formula
CN113389558B (en) TBM (Tunnel boring machine) starting platform for narrow space and construction method thereof
CN211549698U (en) Jacking working pit
CN110965486A (en) Method for constructing frame culvert in existing railway hard overhead
CN218969976U (en) Pushing structure suitable for pushing method construction continuous wall
CN100491696C (en) Method and device for structuring tunnel by propulsion of underground box
CN113898006B (en) Stable and rapid jacking construction method for box culvert under large excavation surface
CN111173523B (en) Method for constructing underground box culvert by using open type shield tunneling machine
CN211648163U (en) Self-propelled open type shield machine system for constructing underground box culvert
CN212054693U (en) Open type shield tunneling machine system for constructing underground box culvert
CN213038426U (en) Extension slide plate for stable and rapid jacking construction of box culvert under large excavation surface
CN219930983U (en) Deep foundation pit combined supporting structure under high side slope condition
CN215948218U (en) A construction support frame for narrow and small space
CN113565522B (en) Tunnel Boring Machine (TBM) station-passing bracket between mountain tunnels and station-passing method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: No. 88 Yuelong South Road, Chongchuan District, Nantong City, Jiangsu Province, 226007

Patentee after: NANTONG JUNENG CONSTRUCTION ENGINEERING TECHNOLOGY Co.,Ltd.

Address before: 226007 room 107, No. 59, Qingnian East Road, Nantong City, Jiangsu Province

Patentee before: NANTONG JUNENG CONSTRUCTION ENGINEERING TECHNOLOGY Co.,Ltd.

CP02 Change in the address of a patent holder