CN113738107A - Steel beam filling method based on inorganic material injection - Google Patents

Steel beam filling method based on inorganic material injection Download PDF

Info

Publication number
CN113738107A
CN113738107A CN202110798757.XA CN202110798757A CN113738107A CN 113738107 A CN113738107 A CN 113738107A CN 202110798757 A CN202110798757 A CN 202110798757A CN 113738107 A CN113738107 A CN 113738107A
Authority
CN
China
Prior art keywords
steel beam
rock wool
web plate
shaped
filling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110798757.XA
Other languages
Chinese (zh)
Inventor
邓竞
赵力
孙宇飞
秦光明
冷园
陈永泉
郦永杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Green Building Integration Technology Co Ltd
Original Assignee
Zhejiang Green Building Integration Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Green Building Integration Technology Co Ltd filed Critical Zhejiang Green Building Integration Technology Co Ltd
Priority to CN202110798757.XA priority Critical patent/CN113738107A/en
Publication of CN113738107A publication Critical patent/CN113738107A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K31/00Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups
    • B23K31/02Processes relevant to this subclass, specially adapted for particular articles or purposes, but not covered by only one of the preceding main groups relating to soldering or welding
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B19/00Machines or methods for applying the material to surfaces to form a permanent layer thereon
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/94Protection against other undesired influences or dangers against fire
    • E04B1/941Building elements specially adapted therefor
    • E04B1/943Building elements specially adapted therefor elongated
    • E04B1/944Building elements specially adapted therefor elongated covered with fire-proofing material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0296Repairing or restoring facades

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Ceramic Engineering (AREA)
  • Building Environments (AREA)

Abstract

The invention relates to a steel beam filling method based on inorganic material injection, which comprises the steps of firstly, pre-filling rock wool layers on two sides of a web plate of an H-shaped steel beam, wherein the filling thickness of the rock wool layers is smaller than the extension widths of upper and lower flanges of the H-shaped steel beam on the two sides of the web plate; welding a plurality of C-shaped stirrups outside the rock wool layer on each side of the web plate along the length direction of the steel beam, welding the top surfaces of upper bending parts of the C-shaped stirrups on the bottom surface of an upper flange of the steel beam, welding the bottom surfaces of lower bending parts of the C-shaped stirrups on the top surface of a lower flange of the steel beam, and jointly forming clamping limit on the rock wool layer by the inner side edge of the upper bending part, the inner side edge of the lower bending part and the web plate; spraying fireproof gypsum mortar to the outside of the rock wool layer on each side to coat the C-shaped stirrup in a construction site, and spraying the fireproof gypsum mortar to be flush with the side end faces of the upper flange and the lower flange; and fiber reinforced fireproof gypsum mortar is sprayed outside the fireproof gypsum mortar on each side. The invention has the characteristics of high construction efficiency, simplified construction operation procedure, low construction cost and avoidance of apparent cracking.

Description

Steel beam filling method based on inorganic material injection
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a steel beam filling method based on inorganic material spraying.
Background
The precast beam is a key component in an assembly type building, an H-shaped steel beam is often adopted, and because two side surfaces of an H-shaped steel web are cavities, inconvenience is brought to indoor decoration in a residential building, and the cavities on the side surfaces of the H-shaped steel are often required to be filled. When the side face of the H-shaped steel web is filled, the filling mode and the selectivity of the filled substances are many, and the selection result is closely related to the construction cost and the functional characteristics of the filled steel beam.
At present, in the building industry, the common method mainly adopts brick blocks for filling, for example, the invention patent with the publication number of CN204826404U discloses 'steel beams filled with the blocks', because the size and the variety of the steel beams are more, the cutting of the aerated block and the gypsum board wastes time and labor, the filling process is quite complicated, the construction period is long, the cost is high, and the noise and the dust generated in the processing process can influence the health of constructors; and, the filling compactness by adopting the building blocks is also poor.
Except for the filling mode and the effect of the precast beam, the fireproof problem of the precast beam also needs to be considered, the existing steel beam usually adopts the mode of spraying fireproof paint and coating mortar to achieve the fireproof purpose, and the two processes need long operation time, so that the operation continuity is poor, and the construction progress is influenced. The inventor proposes a steel beam filling method based on inorganic material spraying, which can simplify the field operation amount and the filling process, and the scheme is generated thereby.
Disclosure of Invention
The invention discloses a steel beam filling method based on inorganic material injection, which has the characteristics of time saving, low cost and simplified workload, and is realized by the following technical scheme:
a steel beam filling method based on inorganic material spraying comprises the following steps:
step 1: rock wool layers are pre-filled on two sides of a web plate of the H-shaped steel girder, the filling thickness of the rock wool layers is smaller than the extending width of upper and lower flanges of the H-shaped steel girder on the two sides of the web plate, and the step is finished in a factory;
step 2: welding a plurality of C-shaped stirrups outside the rock wool layer on each side of the web plate along the length direction of the steel beam, welding the top surfaces of upper bending parts of the C-shaped stirrups on the bottom surface of an upper flange of the steel beam, welding the bottom surfaces of lower bending parts of the C-shaped stirrups on the top surface of a lower flange of the steel beam, and jointly forming clamping limit on the rock wool layer by the inner side edge of the upper bending part, the inner side edge of the lower bending part and the web plate;
and step 3: and fireproof gypsum mortar is sprayed to the outer part of the rock wool layer at each side in a construction site to coat the C-shaped hooping, and the fireproof gypsum mortar is sprayed to be flush with the side end faces of the upper flange and the lower flange.
Further, after the step 3 is finished, spraying fiber reinforced fireproof gypsum mortar outside the fireproof gypsum mortar on each side of the construction site.
Further, before the step 1 is executed, stiffening plates are respectively welded between the upper flange and the lower flange at the two ends of the steel beam, the stiffening plates are respectively vertical to the upper flange, the lower flange and the web plate, and the rock wool layer is filled between the two stiffening plates.
Furthermore, a web plate on the outer side of the stiffening plate is provided with a mounting hole.
The invention adopts the technology of combining factory pre-filling and field spraying of fireproof gypsum mortar to complete the filling of the precast beam, does not need to cut the aerated block and the gypsum board, can reduce the construction noise and dust, and improves the construction efficiency; the filling and the fireproof process are integrally formed, so that the construction operation procedure is simplified, and the construction cost is reduced; the outer layer is sprayed with the fiber reinforced fireproof gypsum mortar, so that the apparent cracking caused by the deformation of the precast beam can be prevented, and the apparent quality is improved.
Drawings
FIG. 1 is a schematic cross-sectional view of a steel beam filled by the filling method of the present invention;
fig. 2 is a front view of fig. 1.
Detailed Description
The technical solution in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention.
The embodiment discloses a steel beam filling method based on inorganic material spraying, and the effect of the steel beam after being filled according to the filling method is shown in figures 1 and 2. The girder steel in this embodiment adopts H shaped steel girder steel, and the girder steel comprises top flange 1, bottom flange 2 and web 3, and top flange 1 and bottom flange 2 parallel arrangement from top to bottom, web 3 are located the middle part and link together top flange 1 and bottom flange 2, and the both sides of web 3 form the cavity structure and need fill. The method for filling the steel beam structure comprises the following specific steps: firstly, in order to connect steel beams, mounting holes 8 need to be formed in the web plates 3 at the end parts of each steel beam, stiffening plates 9 are respectively welded between the upper flanges 1 and the lower flanges 2 at the two ends of each steel beam, the stiffening plates 9 are respectively vertical to the upper flanges, the lower flanges and the web plates 3, and the stiffening plates 9 not only play a role in strengthening the strength of the connecting joints at the end parts of the steel beams, but also can separate filling areas inside the steel beams. And a cavity surrounded by the two stiffening plates 9 and the web plate 3 on each side is filled with a cement-based rock wool layer 4, and the filling thickness of the rock wool layer 4 is smaller than the extension width of the upper flange and the lower flange of the steel beam on the two sides of the web plate 3. Next, a plurality of C-shaped stirrups 5 are welded along the length direction of the steel beam outside the rock wool layer 4 on each side of the web plate 3, the top surface of the upper bending part of the C-shaped stirrups 5 is welded on the bottom surface of the upper flange 1 of the steel beam, the bottom surface of the lower bending part of the C-shaped stirrups 5 is welded on the top surface of the lower flange 2 of the steel beam, the inner side of the upper bending part and the inner side of the lower bending part are clamped and limited by the common formation of the web plate 3, and the steps are all prefabricated in a factory. After the stone wool is transported to a construction site, fireproof gypsum mortar 6 is sprayed outside the rock wool layer 4 on each side to coat the C-shaped stirrup 5, and the fireproof gypsum mortar 6 is sprayed to the positions which are flush with the side end faces of the upper flange and the lower flange. And finally, spraying fiber reinforced fireproof gypsum mortar 7 outside the fireproof gypsum mortar 6 on each side to form an anti-crack protective layer.
The steel beam filling method is high in prefabrication degree, and the pre-filling and spraying processes are combined, so that the construction process can be simplified, the construction period can be shortened, the construction cost can be reduced, and the influence of the construction environment on the health of personnel can be reduced. In the fireproof treatment of the steel beam, the sprayed fireproof gypsum mortar 6 is used for replacing the traditional fireproof coating and plastering mortar structure, so that the construction procedures can be reduced while the fireproof performance is ensured. The invention also utilizes the function of preventing cracks of the fibers in the sprayed fiber reinforced fireproof gypsum mortar 7 to improve the apparent quality of the steel beam.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. A steel beam filling method based on inorganic material spraying is characterized in that: the method comprises the following steps:
step 1: rock wool layers are pre-filled on two sides of a web plate of the H-shaped steel girder, the filling thickness of the rock wool layers is smaller than the extending width of upper and lower flanges of the H-shaped steel girder on the two sides of the web plate, and the step is finished in a factory;
step 2: welding a plurality of C-shaped stirrups outside the rock wool layer on each side of the web plate along the length direction of the steel beam, welding the top surfaces of upper bending parts of the C-shaped stirrups on the bottom surface of an upper flange of the steel beam, welding the bottom surfaces of lower bending parts of the C-shaped stirrups on the top surface of a lower flange of the steel beam, and jointly forming clamping limit on the rock wool layer by the inner side edge of the upper bending part, the inner side edge of the lower bending part and the web plate;
and step 3: and fireproof gypsum mortar is sprayed to the outer part of the rock wool layer at each side in a construction site to coat the C-shaped hooping, and the fireproof gypsum mortar is sprayed to be flush with the side end faces of the upper flange and the lower flange.
2. The method for filling a steel beam based on inorganic material injection as claimed in claim 1, wherein: and after the step 3 is finished, spraying fiber reinforced fireproof gypsum mortar outside the fireproof gypsum mortar on each side of the construction site.
3. The method for filling a steel beam based on inorganic material injection as claimed in claim 1, wherein: before the step 1 is executed, stiffening plates are respectively welded between the upper flange and the lower flange at the two ends of the steel beam, the stiffening plates are respectively vertical to the upper flange, the lower flange and the web plate, and the rock wool layer is filled between the two stiffening plates.
4. The method for filling a steel beam based on inorganic material injection as claimed in claim 3, wherein: the web plate on the outer side of the stiffening plate is provided with a mounting hole.
CN202110798757.XA 2021-07-15 2021-07-15 Steel beam filling method based on inorganic material injection Pending CN113738107A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110798757.XA CN113738107A (en) 2021-07-15 2021-07-15 Steel beam filling method based on inorganic material injection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110798757.XA CN113738107A (en) 2021-07-15 2021-07-15 Steel beam filling method based on inorganic material injection

Publications (1)

Publication Number Publication Date
CN113738107A true CN113738107A (en) 2021-12-03

Family

ID=78728670

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110798757.XA Pending CN113738107A (en) 2021-07-15 2021-07-15 Steel beam filling method based on inorganic material injection

Country Status (1)

Country Link
CN (1) CN113738107A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2829864A1 (en) * 1977-07-12 1979-02-01 Arbed COMPOSITE BEAM
DE102012107087A1 (en) * 2012-08-02 2014-02-06 Lindner Ag Elongated component e.g. steel girder installed in ceiling, has component main portion that is covered with fire protection layer which is provided with network-or grid-shaped reinforcing insert
CN205046685U (en) * 2015-08-29 2016-02-24 长春工程学院 External heated board of prefabricated masonry wall
CN109184076A (en) * 2018-11-09 2019-01-11 福建省建筑设计研究院有限公司 One kind partly combining prefabricated assembled beam and preparation method thereof and design method
CN208545877U (en) * 2018-06-15 2019-02-26 绍兴精工绿筑集成建筑系统工业有限公司 A kind of steel building self-heat conserving beam
CN211775096U (en) * 2020-02-18 2020-10-27 孙叶根 Fire prevention anticorrosive heat preservation decorates integration H shaped steel roof beam
CN112922230A (en) * 2021-03-31 2021-06-08 中国建筑西北设计研究院有限公司 Section steel partially-wrapped concrete composite beam and design and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2829864A1 (en) * 1977-07-12 1979-02-01 Arbed COMPOSITE BEAM
DE102012107087A1 (en) * 2012-08-02 2014-02-06 Lindner Ag Elongated component e.g. steel girder installed in ceiling, has component main portion that is covered with fire protection layer which is provided with network-or grid-shaped reinforcing insert
CN205046685U (en) * 2015-08-29 2016-02-24 长春工程学院 External heated board of prefabricated masonry wall
CN208545877U (en) * 2018-06-15 2019-02-26 绍兴精工绿筑集成建筑系统工业有限公司 A kind of steel building self-heat conserving beam
CN109184076A (en) * 2018-11-09 2019-01-11 福建省建筑设计研究院有限公司 One kind partly combining prefabricated assembled beam and preparation method thereof and design method
CN211775096U (en) * 2020-02-18 2020-10-27 孙叶根 Fire prevention anticorrosive heat preservation decorates integration H shaped steel roof beam
CN112922230A (en) * 2021-03-31 2021-06-08 中国建筑西北设计研究院有限公司 Section steel partially-wrapped concrete composite beam and design and construction method thereof

Similar Documents

Publication Publication Date Title
TWI736482B (en) Construction method of architectural structure
CN108086488B (en) Assembled frame shear structure wall staggered connection structure and assembling method
CN105064196A (en) Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite simple supported girder bridge and construction method thereof
CN110863597A (en) Prefabricated floor slab crack prevention and repair method for assembly type steel frame laminated slab factory building
CN111502080A (en) Steel-concrete composite structure frame-cast-in-place concrete shear wall structure system
CN110820983B (en) Longitudinal connection method for assembled prefabricated superposed wall boards
CN103572884B (en) A kind of hollow precast concrete member
CN113738107A (en) Steel beam filling method based on inorganic material injection
CN218345930U (en) Bridge structure
CN216042164U (en) Spraying mortar precast beam filling structure
CN106759950B (en) Construction process for prefabricated plate wall I-shaped steel welding joint
CN213927078U (en) Prefabricated assembly type steel concrete mixed beam with angle steel connecting piece prefabricated plate part
CN113863679A (en) Construction method of prefabricated house structure
CN210049404U (en) Frame and shear force wall combination assembled structure system
CN109610877B (en) Node and method for improving crack resistance of prefabricated concrete frame structure
CN209780313U (en) Node for improving crack resistance of prefabricated concrete frame structure
KR101382652B1 (en) composite beam having high Strength frame pannel, and method for fabricating and constructing the composite beam
CN210658659U (en) Split level prefabricated window and steel construction connected node of wafing
KR200186307Y1 (en) Deck panel of reinforced concrete slab
CN214402433U (en) Prefabricated and cast-in-place combined clad steel-concrete composite beam
CN217601854U (en) Prefabricated even roof beam of easy die stripping and coincide even roof beam of constituteing thereof
CN219033728U (en) Novel composite floor slab based on UHPC
KR102681486B1 (en) Precast concrete hollow core slab
CN117868370B (en) Prefabricated H-shaped groove recycled concrete floor slab and construction method thereof
KR102606697B1 (en) Method for manufacturing precast concrete hollow core slab

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211203

RJ01 Rejection of invention patent application after publication