CN113622377B - Intelligent control siphon drainage and flexible stilling basin system for check dam - Google Patents

Intelligent control siphon drainage and flexible stilling basin system for check dam Download PDF

Info

Publication number
CN113622377B
CN113622377B CN202110784760.6A CN202110784760A CN113622377B CN 113622377 B CN113622377 B CN 113622377B CN 202110784760 A CN202110784760 A CN 202110784760A CN 113622377 B CN113622377 B CN 113622377B
Authority
CN
China
Prior art keywords
water
dam
pipe
drainage
flexible
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110784760.6A
Other languages
Chinese (zh)
Other versions
CN113622377A (en
Inventor
武颖利
李威
田保宏
郭万里
皇甫英杰
吴冠宇
梁小卫
姜纯伟
龚丽飞
陈海波
孙冰晗
王鹏
刘晓宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Original Assignee
Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources filed Critical Nanjing Hydraulic Research Institute of National Energy Administration Ministry of Transport Ministry of Water Resources
Priority to CN202110784760.6A priority Critical patent/CN113622377B/en
Publication of CN113622377A publication Critical patent/CN113622377A/en
Application granted granted Critical
Publication of CN113622377B publication Critical patent/CN113622377B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B8/00Details of barrages or weirs ; Energy dissipating devices carried by lock or dry-dock gates
    • E02B8/06Spillways; Devices for dissipation of energy, e.g. for reducing eddies also for lock or dry-dock gates
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01FMEASURING VOLUME, VOLUME FLOW, MASS FLOW OR LIQUID LEVEL; METERING BY VOLUME
    • G01F23/00Indicating or measuring liquid level or level of fluent solid material, e.g. indicating in terms of volume or indicating by means of an alarm
    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B21/00Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
    • G08B21/02Alarms for ensuring the safety of persons
    • G08B21/10Alarms for ensuring the safety of persons responsive to calamitous events, e.g. tornados or earthquakes
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast

Abstract

The invention relates to the technical field of drainage of engineering of a silt dam and a tailing dam, and discloses an intelligent control siphon drainage and flexible stilling basin system for the silt dam, which comprises a floating water taking tank, a drainage pipe, a connecting flange, an upward-protruding water injection and gas collection device, a downstream side drainage pipe, a dam body, a flexible corrugated pipe, a flexible stilling basin system and a drainage pipe floater, wherein the floating water taking tank is arranged on the upper part of the floating water taking tank; the water discharging pipe is communicated with the floating water taking tank through a connecting flange, the water discharging pipe floats on the water surface of the reservoir area through a water discharging pipe floater, an upstream water discharging pipe groove, a downstream water discharging pipe groove and a dam top water passing culvert are formed in the dam body, the upward convex type water injection and gas collection device is installed on the dam body, and the water discharging pipe and the downstream water discharging pipe are respectively laid in the upstream water discharging pipe groove and the dam top water passing culvert. The invention is suitable for the technical field of the engineering of the silt dam and the tailing dam, effectively avoids the engineering problem of the existing drainage system, and can well meet the drainage requirement of the silt dam.

Description

Intelligent control siphon drainage and flexible stilling basin system for check dam
Technical Field
The invention relates to the field of drainage of engineering of a check dam and a tailing dam, in particular to an intelligent control siphon drainage and flexible stilling basin system for the check dam.
Background
The silty dam is an important engineering measure for water and soil conservation, silty land field building, traffic improvement and ecological protection in a loess plateau area.
The silty dam is a water and soil conservation project for managing gullies created by the precedents in the northwest region, and the history of the project can be traced back to the Ming dynasty. The pioneers struggle to obtain dry and waterlogged grain for conservation through 'dam-making and field-building', and meanwhile, a part of the trenches become terraces, so that the erosion process of the trenches is restrained. By 11 months in 2019, china has 58776 seats of a silt dam, and the silt area is 927.57km2. The silty dam achieves the effect of workers in the aspects of ecological protection of the yellow river basin and promotion of rural economic development.
Since the silty dams are mostly small hydraulic projects constructed by the masses spontaneously, a considerable number of dams have no flood discharge facilities. Under the condition of extreme rainfall, a part of silt dams are damaged, the functions of sand blocking and field building are not existed, casualties can be caused, and the safe flood work becomes the key point of prevention and control in each year flood season.
Most of the traditional check dam engineering adopts the combination of a through-dam culvert pipe and an upstream water collecting well to drain water in a reservoir area. By adopting the traditional drainage system, the drainage function is lost due to frequent pipeline blockage, so that the dam body is in a dangerous case and even breaks due to incapability of draining water. Meanwhile, the arrangement of the culvert pipes penetrating the dam is adopted, if the pipelines are made of concrete, the pipelines are easy to crack, so that safety hidden danger is caused, and the pipelines made of cast iron are corroded and damaged, so that the safety of the dam body is seriously influenced; the drainage wells are arranged in the upstream reservoir area, silt deposition cannot be effectively prevented, and the drainage wells also need to ascend along with deposition in the upstream reservoir area, so that management and maintenance in the operation period are difficult.
Due to the defects of the drainage system of the check dam, the water damage accident and the dam break risk of the check dam are far more serious than those of the conventional earth-rock dam, and the water damage accident and the dam break risk of the check dam become bottleneck problems restricting the development of the check dam.
Due to the fact that the number of the silty dams is large, the conditions are complex, professional management is lacked, problems cannot be found timely, people and mechanical equipment are needed to go to the site to carry out emergency rescue after dangerous situations are found, and the dangerous situations are further worsened due to information lag. The biggest dangerous condition of the check dam is mainly that the reservoir area is unsmooth in water drainage in the flood season, so that the reservoir water level is rapidly increased, and the safety of a dam body is damaged. Therefore, a set of remote intelligent management early warning system is urgently needed, problems can be found timely, a drainage system can be started remotely while early warning information is sent out, and the development of dangerous cases is slowed down.
The actual engineering problems faced by tailing dam drainage systems are similar to those of land siltation dams, and are not described in detail herein.
In order to solve the problems, the application provides an intelligent siphon drainage and flexible stilling basin system for a check dam.
Disclosure of Invention
Objects of the invention
In order to solve the technical problems in the background art, the invention provides the intelligent siphon drainage and flexible stress relief pool system for the check dam, which is suitable for the technical field of check dam and tailing dam engineering, effectively avoids the engineering problems of the existing drainage system and can well meet the drainage requirements of the check dam.
(II) technical scheme
In order to solve the problems, the invention provides an intelligent control siphon drainage and flexible stilling basin system for a silt dam, which comprises a floating water taking tank, a drainage pipe, a connecting flange, an upward convex water injection and gas collection device, a downstream side drainage pipe, a dam body, a flexible corrugated pipe, a flexible stilling basin system and a drainage pipe floater, wherein the floating water taking tank is arranged on the upper portion of the floating water taking tank;
the water discharge pipe is communicated with the floating water taking tank through a connecting flange, the water discharge pipe floats on the water surface of the reservoir area through a water discharge pipe floater, an upstream water discharge pipe groove, a downstream water discharge pipe groove and a dam top water passing culvert are formed in the dam body, the upward convex water injection and gas collection device is installed on the dam body, the water discharge pipe and the downstream water discharge pipe are respectively laid in the upstream water discharge pipe groove and the dam top water passing culvert and penetrate through the dam top water passing culvert to be connected with the upward convex water injection and gas collection device, the upward convex water injection and gas collection device is communicated with the downstream water discharge pipe, and the downstream water discharge pipe is communicated with the water outlet pipe through a flexible corrugated pipe;
the dam body is provided with a driving mechanism, and the driving mechanism is connected with the flexible corrugated pipe and the water outlet pipe;
an intelligent early warning energy supply system is arranged on the dam body and is connected with the driving mechanism;
the flexible stilling basin system is arranged on the downstream side of the dam body.
Preferably, wisdom early warning energy supply system includes solar PV modules, video monitoring system, rainfall water level monitoring instrument, communication module, controller, the controller is respectively through communication module and solar PV modules, video monitoring system, rainfall water level monitoring instrument and actuating mechanism control connection, solar PV modules and actuating mechanism electric connection.
Preferably, the upward-convex water injection and gas collection device is communicated with an active and passive exhaust pipe through an exhaust port, and the active and passive exhaust pipe is communicated with the water outlet pipe through the active and passive exhaust port;
the upward convex water injection and gas collection device is arranged on the downstream side close to the dam top, the inlet of the upstream side of the device is low, the water outlet position of the downstream side is high, an upward convex structure is formed, a water injection port with a valve is arranged at the top of the structure, an exhaust port is arranged at the top of the structure and is connected with an active exhaust pipe and a passive exhaust pipe, and the water injection port with the valve and the exhaust port are communicated with a drain pipe.
Preferably, the drain pipe is located the inside one end fixed mounting of the floating water tank of getting and has one-way check valve, the mounting hole has been seted up to the bottom of the floating water tank of getting, and mounting hole department fixed mounting has the trash rack, the inside fixed mounting of the floating water tank of getting has the adjustable flotation platform of buoyancy, the adjustable flotation platform of buoyancy has been seted up one side of the adjustable flotation platform of buoyancy and has been annotated/the outlet.
Preferably, the active and passive exhaust pipes are fixed on the downstream drain pipe by adopting flexible plastic pipes, and the joints of the active and passive exhaust pipes and the tail ends of the water outlets are designed by adopting acute angles.
Preferably, the driving mechanism comprises a lifting winch, a lifting fixed pulley, two inhaul cables, a descending winch, a metal hinge frame, a descending fixed pulley and two hanging rings, the lifting winch, the descending winch and the metal hinge frame are all installed on a dam body, a wheel frame of the lifting fixed pulley and a wheel frame of the descending fixed pulley are both fixedly connected with the dam body, the water outlet pipe is connected with one side of the metal hinge frame through a fixing buckle, the two hanging rings are respectively and fixedly installed on two sides of the water outlet pipe, one end of one inhaul cable is fixedly connected with the hanging rings, the other end of the inhaul cable bypasses the lifting fixed pulley and is wound on a winding roller of the lifting winch, one end of the other inhaul cable is fixedly connected with the hanging rings, the other end of the inhaul cable bypasses the descending fixed pulley and is wound on a winding roller of the descending winch, the lifting winch and the descending winch are both in communication connection with the controller, and the functions of controlling the drainage speed and stopping and starting can be realized by adjusting the height of a downstream water outlet.
Preferably, the flexible stress relief pool system is assembled by filling pebbles into super-weather-resistant polypropylene geomembrane bags, assembled in a layer and provided with an impermeable membrane between upper and lower bag bodies.
Preferably, the dam top water channel is connected with a downstream drainage pipe groove, and the downstream drainage pipe groove is provided with a downstream force eliminating step.
Preferably, the drain pipes are pvc hard pipes with the diameter of 20cm, 3-4 drain pipes are arranged in parallel according to the actual drainage efficiency requirement, and share one floating water taking tank and one upward convex water injection and gas collection device.
Preferably, a dam top drain pipe is laid at the top of the dam body.
The technical scheme of the invention has the following beneficial technical effects:
the intelligent control siphon drainage of the silt dam can be realized, the upstream water taking adopts a floating water taking structure and can be freely adjusted along with the change of the water level of an upstream reservoir, the defect that a conventional water collecting well needs to be continuously raised along with the sedimentation of a reservoir area is avoided, and meanwhile, clear water on the surface layer of the upstream reservoir is extracted during drainage, so that the sediment loss is further reduced; the intelligent early warning energy supply system can realize remote intelligent control to adjust the height of the downstream water outlet so as to control the drainage speed and the shutdown and start of drainage; the active and passive exhaust pipes are added, so that the water injection is ensured to be smooth in the starting process of the device, and meanwhile, the air remained in the pipeline can be effectively discharged in the running process, so that the siphon drainage operation is ensured to be smoothly carried out; after the siphon water pump is installed, continuous and discontinuous siphon water drainage operation can be realized only by injecting water once, the defects of a conventional siphon pipe are avoided, extra energy is not needed in the whole water drainage process, and the problem that power supply is needed for conventional water pumping is avoided; by adopting the assembled flexible stilling pool device, cost reduction and efficiency improvement can be realized, and multiple assembling adjustment can be realized.
Drawings
Fig. 1 is a schematic structural view of an intelligent siphon drainage and flexible force-relieving pool system for a check dam according to the present invention.
FIG. 2 is a partial structural schematic view of an intelligent siphon drainage and flexible force-relief pool system for a silt dam according to the present invention.
Fig. 3 is a schematic top view of a floating water intake box in an intelligent siphon drainage and flexible stilling basin system for a check dam according to the present invention.
Fig. 4 is a schematic top view of a convex water injection and gas collection device in an intelligent control siphon drainage and flexible stress relief pool system for a silt dam according to the present invention.
Fig. 5 is a system diagram of an intelligent siphon control and flexible stilling basin system for a check dam according to the present invention.
Reference numerals: 1. a floating water taking tank; 2. a drain pipe; 3. a one-way check valve; 4. a trash rack; 5. a connecting flange; 6. the buoyancy can be adjusted and the floating platform; 7. a floating platform water injection/discharge port; 8. the upward convex water injection and gas collection device; 9. a water filling port with a valve; 10. an exhaust port; 11. an active and passive exhaust pipe; 12. a downstream side drain pipe; 13. a dam body; 14. an upstream drain pipe trough; 15. a water channel is arranged at the top of the dam; 16. a downstream force absorbing step; 17. a downstream drain pipe tank; 18. lifting the winch; 19. lifting the fixed pulley; 20. a pull cable; 21. lowering the hoist; 22. a metal wire frame; 23. descending the fixed pulley; 24. a hoisting ring; 25. an active and passive exhaust port; 26. fixing the buckle; 27. a flexible bellows; 28. a flexible stress relief pool system; 29. a drain pipe float; 30. a water outlet pipe; 31. a drain pipe at the top of the dam; 32. the system comprises a communication module, a video monitoring system 34, a rainfall and water level monitoring instrument, a solar photovoltaic module 35 and a solar photovoltaic module; 36. and a controller.
Detailed Description
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention will be described in further detail with reference to the accompanying drawings in conjunction with the following detailed description. It should be understood that the description is intended to be exemplary only, and is not intended to limit the scope of the present invention. Moreover, in the following description, descriptions of well-known structures and techniques are omitted so as to not unnecessarily obscure the concepts of the present invention.
As shown in fig. 1-5, the intelligent siphon drainage and flexible stilling pool system for silt dams, provided by the invention, comprises a floating water taking tank 1, a drainage pipe 2, a connecting flange 5, an upward convex water injection and gas collection device 8, a downstream side drainage pipe 12, a dam body 13, a flexible corrugated pipe 27, a flexible stilling pool system 28 and a drainage pipe floater 29;
the water discharge pipe 2 is communicated with the floating water taking tank 1 through a connecting flange 5, the water discharge pipe 2 floats on the water surface of the reservoir area through a water discharge pipe floater 29, an upstream water discharge pipe groove 14, a downstream water discharge pipe groove 17 and a dam top water passing culvert 15 are formed in the dam body 13, the upward-convex water and gas injection device 8 is installed on the dam body 13, the water discharge pipe 2 and the downstream water discharge pipe 12 are respectively laid in the upstream water discharge pipe groove 14 and the dam top water passing culvert 15 and penetrate through the dam top water passing culvert 15 to be connected with the upward-convex water and gas injection device 8, the upward-convex water and gas injection device 8 is communicated with the downstream water discharge pipe 12, and the downstream water discharge pipe 12 is communicated with the water outlet pipe 30 through a flexible corrugated pipe 27 to form a complete siphon water discharge structure;
a driving mechanism is arranged on the dam body 13 and is connected with the flexible corrugated pipe 27 and the water outlet pipe 30;
an intelligent early warning energy supply system is arranged on the dam body 13 and is connected with the driving mechanism;
the flexible relief pool system 28 is provided on the downstream side of the dam 13.
In an optional embodiment, the intelligent early warning energy supply system comprises a solar photovoltaic module 35, a video monitoring system 33, a rainfall water level monitoring instrument 34, a communication module 32 and a controller 36, wherein the controller 36 is respectively in control connection with the solar photovoltaic module 35, the video monitoring system 33, the rainfall water level monitoring instrument 34 and a driving mechanism through the communication module 32, the solar photovoltaic module 35 is electrically connected with the driving mechanism, collected data are processed and analyzed, the controller 36 controls the driving mechanism to adjust the height of the water outlet pipe 30, remote intelligent control of the drainage speed of the reservoir area of the silt reservoir and control of starting-stopping and the like are achieved, and an early warning function is provided according to analysis of the monitored data.
In an alternative embodiment, the upward-convex water injection and gas collection device 8 is communicated with an active and passive exhaust pipe 11 through an exhaust port 10, and the active and passive exhaust pipe 11 is communicated with the water outlet pipe 30 through an active and passive exhaust port 25; the water injection and gas collection can be conveniently carried out on the pipeline during starting, and the gas in the pipeline is discharged by matching with the active and passive exhaust pipes 11;
upward convex water injection gas collection device 8 lays at the dam top and leans on the downstream side, the device upstream side import is low, the downstream side play water position is high, form upward convex structure, be provided with at this structure top and take valve water filling port 9, the top is equipped with gas vent 10, and link to each other with active and passive blast pipe 11, take valve water filling port 9 and gas vent all with drain pipe 2 intercommunication, through the inside water injection of water filling port 9 to drain pipe 2, and through gas vent 10 with the interior air escape of drain pipe 2, realize siphon drainage function.
In an optional embodiment, one end of the drain pipe 2 located inside the floating type water taking tank 1 is fixedly provided with the one-way check valve 3, the bottom of the floating type water taking tank 1 is provided with an installation opening, a trash rack 4 is fixedly installed at the installation opening, an adjustable buoyancy floating platform 6 is fixedly installed inside the floating type water taking tank 1, one side of the adjustable buoyancy floating platform 6 is provided with a floating platform water injection/drainage opening 7, and the buoyancy of the adjustable buoyancy floating platform can be adjusted to realize that the water taking opening is submerged during working. During the maintenance working condition and the period of not running in winter, the buoyancy of the floating platform 6 is improved to enable the water intake 1 to be separated from the water surface to realize the water discharging function, and the pipeline is prevented from being frozen and cracked in winter.
In an optional embodiment, the active and passive exhaust pipes 11 are fixed on the downstream drain pipe 2 by using flexible plastic pipes, the connection between the active and passive exhaust pipes 11 and the tail end of the water outlet is designed to be an acute angle, when water flow is rapidly discharged along the downstream drain pipe 2, negative pressure is formed at the connection between the active and passive exhaust pipes 11 and the tail end of the water outlet due to flow rate difference, and air remaining in the upward-convex water injection and air collection device 8 is sucked out, so that smooth and efficient operation of a siphon drainage system is guaranteed.
In an alternative embodiment, the driving mechanism comprises a lifting winch 18, a lifting fixed pulley 19, two guys 20, a descending winch 21, a metal hinge frame 22, a descending fixed pulley 23 and two hanging rings 24, wherein the lifting winch 18, the descending winch 21 and the metal hinge frame 22 are all installed on the dam body 13, a wheel frame of the lifting fixed pulley 19 and a wheel frame of the descending fixed pulley 23 are both fixedly connected with the dam body 13, a water outlet pipe 30 is connected with one side of the metal hinge frame 22 through a fixed buckle 26, the two hanging rings 24 are respectively and fixedly installed on two sides of the water outlet pipe 30, one end of one guy 20 is fixedly connected with the hanging rings 24, the other end of the guy 20 bypasses the lifting fixed pulley 19 and is wound with a winding roller of the lifting winch 18, one end of the other guy 20 is fixedly connected with the hanging rings 24, the other end of the guy 20 bypasses the descending fixed pulley 23 and is wound with a winding roller of the descending winch 21, the lifting winch 18 and the descending winch 21 are both in communication connection with the controller 36, and the water outlet can be controlled by adjusting the height of the downstream water outlet and the water drainage function can be controlled by turning over or releasing the metal hinge frame 22;
in an alternative embodiment, the flexible pool system 28 is assembled by filling pebbles in super-weather-resistant polypropylene geomembrane bags, and is assembled according to 2-3 layers, and impermeable films are arranged between the upper and lower bag bodies. When the cost is saved conveniently and quickly, the blocks can be assembled again under the condition of siltation at the downstream, and the secondary construction cost is reduced.
In an optional embodiment, the dam top water flowing duct 15 is connected with a downstream drainage pipe groove 17, and the downstream drainage pipe groove 17 is provided with a downstream dissipation step 16, so that the flood discharge requirement of a reservoir area under the extreme rainfall working condition is prevented, the dam overflowing risk caused by overhigh reservoir water level is prevented, and the risk resistance of the dam body is improved.
In an alternative embodiment, the water discharge pipes 2 are pvc hard pipes with the diameter of 20cm, 3-4 water discharge pipes 2 are arranged in parallel according to the actual water discharge efficiency requirement, and the water discharge pipes 2 share one floating water taking box 1 and one upward convex water injection and gas collection device 8.
In an alternative embodiment, a dam top drain 31 is laid on the top of the dam 13.
The lifting of the outlet pipe 30 is achieved by lifting the winch 18 and lowering the winch 21.
It should be noted that, after the floating water intake box 1 is connected to the water discharge pipe 2 through the connecting flange 5, the part together with part of the water discharge pipe 2 floats on the upstream water surface of the dam 13, the water discharge pipe 2 is placed in the upstream water discharge pipe groove 14 of the dam 13, and is connected to the upward convex water injection and gas collection device 8 through the connecting flange 5 through the dam top water discharge culvert 15, and is connected to the downstream water discharge pipe 12 through the connecting flange 5, and the downstream water discharge pipe 12 is connected to the flexible corrugated pipe 27 and is connected to the water outlet, so as to form a complete siphon water discharge structure.
The siphon structure needs to be filled with water to the pipeline for the first time, before water is filled, the water outlet pipe 30 is lifted to the vertical direction through a lifting winch 18 of a driving system in combination with a lifting fixed pulley 19 and a pull rope 20, at the moment, the water outlet pipe 30 is at the highest point, then, an external water suction pump is adopted to fill water to the pipeline through a water filling port 9 with a valve on an upward-convex water filling and gas collecting device 8, due to the upward-convex structural design of the upward-convex water filling and gas collecting device 8, water in the water filling pipeline firstly flows into a water discharging pipe 2 on the upstream side, due to the fact that a one-way check valve 3 is arranged in a floating water taking tank 1, the one-way check valve 3 is in a closed state at the moment, the water can be guaranteed to be filled into the water discharging pipe 2 on the upstream side, then the filled water flows into a water discharging pipe 12 on the downstream side through the upward-convex water filling and gas collecting device 8, and due to the fact that a main and passive exhaust pipe 11 connected with an exhaust port 10 arranged on the upward-convex water filling and gas collecting device 8 is directly connected with a main and a passive exhaust port 25 on the water outlet pipe 30, the water outlet pipe 12, smooth discharging process in the downstream side can be guaranteed, and when the water filling process is finished.
It should be noted that after water injection, a siphon drainage function is realized, which is specifically as follows:
the inhaul cable 20 is driven by the descending winch 21, the inhaul cable 20 pulls the water outlet pipe 30 to descend to the lowest point through the descending fixed pulley 23, at the moment, an obvious water level difference exists between the water outlet pipe 30 and the floating water taking tank 1, the drainage function of a reservoir area of a silty dam is realized, meanwhile, due to the angle arrangement between the active and passive exhaust ports 25 and the water outlet pipe 30, negative pressure is generated when high-speed water flows through the active and passive exhaust ports 25, and air remained in the downstream side drain pipe 12 in the upper convex water injection and air collection device 8 is discharged out of a pipeline through the active and passive exhaust pipe 11.
In an alternative embodiment, the above difference of this embodiment is that the intelligent warning and energy supply system is used to adjust and close the drainage speed of the siphon drainage system. The method comprises the following specific steps:
the water outlet pipe 30 is lifted by the driving of the lifting winch 18, the water level difference between the water outlet pipe 30 and the floating water taking tank 1 is reduced, the drainage speed is reduced, the lowest water level of drainage of the silty dam can be controlled by controlling the height of the water outlet pipe 30, and when the water level of an upstream reservoir area is consistent with the height of the water outlet pipe 30, the siphon drainage system automatically stops drainage.
When the siphon drainage system needs to be shut down, the water outlet pipe 30 is lifted to the highest point only by being driven by the lifting winch 18, at the moment, due to the effect of the one-way check valve 3 arranged in the floating water taking tank 1, when the water outlet pipe 30 is higher than the floating water taking tank 1, the one-way check valve 3 is automatically closed, the whole siphon pipeline is ensured to be in a full water state, and the siphon drainage system is convenient to start and operate again next time.
In an alternative embodiment, the difference of this embodiment is that the siphon drainage system is emptied by the intelligent early warning energy supply system. The specific implementation is as follows:
in order to maintain and repair the system and prevent freezing in winter, the water in the siphon drainage system needs to be emptied. Firstly, water in the floating water taking tank 1 is discharged through the floating platform water injection/discharge port 7, so that the buoyancy of the buoyancy adjustable floating platform 6 is increased, the floating water taking tank 1 floats upwards, and the water inlet of the floating water taking tank 1 is separated from the water surface. At this time, the descending winch 21 is driven to place the water outlet pipe 30 at the lowest position, so that all water bodies in the siphon drainage system can be emptied.
It is to be understood that the above-described embodiments of the present invention are merely illustrative of or explaining the principles of the invention and are not to be construed as limiting the invention. Therefore, any modification, equivalent replacement, improvement and the like made without departing from the spirit and scope of the present invention should be included in the protection scope of the present invention. Further, it is intended that the appended claims cover all such variations and modifications as fall within the scope and boundaries of the appended claims or the equivalents of such scope and boundaries.

Claims (7)

1. An intelligent control siphon drainage and flexible stilling basin system for a silt dam is characterized by comprising a floating water taking tank (1), a drain pipe (2), a connecting flange (5), an upward-protruding water injection and gas collection device (8), a downstream side drain pipe (12), a dam body (13), a flexible corrugated pipe (27), a flexible stilling basin system (28) and a drain pipe floater (29);
the water discharge pipe (2) is communicated with the floating water taking tank (1) through a connecting flange (5), the water discharge pipe (2) floats on the water surface of the reservoir area through a water discharge pipe floater (29), the dam body (13) is provided with an upstream water discharge pipe groove (14), a downstream water discharge pipe groove (17) and a dam top water passing culvert (15), the upward convex water injection and gas collection device (8) is installed on the dam body (13), the water discharge pipe (2) and the downstream water discharge pipe (12) are respectively laid in the upstream water discharge pipe groove (14) and the dam top water passing culvert (15) and penetrate through the dam top water passing culvert (15) to be connected with the upward convex water injection and gas collection device (8), the upward convex water injection and gas collection device (8) is communicated with the downstream water discharge pipe (12), and the downstream water discharge pipe (12) is communicated with the water outlet pipe (30) through a flexible corrugated pipe (27);
a driving mechanism is arranged on the dam body (13), and the driving mechanism is connected with the flexible corrugated pipe (27) and the water outlet pipe (30);
an intelligent early warning energy supply system is arranged on the dam body (13) and is connected with the driving mechanism;
the flexible stilling basin system (28) is arranged on the downstream side of the dam body (13); the intelligent early warning energy supply system comprises a solar photovoltaic module (35), a video monitoring system (33), a rainfall water level monitoring instrument (34), a communication module (32) and a controller (36), wherein the controller (36) is in control connection with the solar photovoltaic module (35), the video monitoring system (33), the rainfall water level monitoring instrument (34) and a driving mechanism through the communication module (32), and the solar photovoltaic module (35) is electrically connected with the driving mechanism; the upward-convex water injection and gas collection device (8) is communicated with an active and passive exhaust pipe (11) through an exhaust port (10), and the active and passive exhaust pipe (11) is communicated with a water outlet pipe (30) through an active and passive exhaust port (25);
the upward convex water injection and gas collection device (8) is arranged at the position close to the downstream side of the dam top, the inlet at the upstream side of the device is low, the water outlet position at the downstream side of the device is high, an upward convex structure is formed, a water injection port (9) with a valve is arranged at the top of the structure, an exhaust port (10) is arranged at the top of the structure and is connected with a driving exhaust pipe (11) and a driven exhaust pipe (11), and the water injection port (9) with the valve and the exhaust port are both communicated with a drain pipe (2);
the driving mechanism comprises a lifting winch (18), a lifting fixed pulley (19), two guys (20), a descending winch (21), a metal hinge frame (22), a descending fixed pulley (23) and two hoisting rings (24), wherein the lifting winch (18), the descending winch (21) and the metal hinge frame (22) are all installed on the dam body (13), a wheel frame of the lifting fixed pulley (19) and a wheel frame of the descending fixed pulley (23) are all fixedly connected with the dam body (13), a water outlet pipe (30) is connected with one side of the metal hinge frame (22) through a fixed buckle (26), the two hoisting rings (24) are respectively and fixedly installed on two sides of the water outlet pipe (30), one end of one guy (20) is fixedly connected with the hoisting rings (24), the other end of the guy (20) bypasses the lifting fixed pulley (19) and is wound with a winding roller of the lifting winch (18), one end of the guy (20) is fixedly connected with the hoisting rings (24), the other end of the descending fixed pulley (23) bypasses the descending fixed pulley and is connected with the winding roller of the lifting winch (21), and the hoisting winch (21) is communicated with the descending fixed pulley (20) and the hoisting rings (21) and controls the descending winch.
2. The intelligent siphon drainage and flexible force-dissipating pool system for the check dam according to claim 1, wherein a one-way check valve (3) is fixedly installed at one end, located inside the floating water taking tank (1), of the drainage pipe (2), a mounting opening is formed in the bottom of the floating water taking tank (1), a trash rack (4) is fixedly installed at the mounting opening, an adjustable buoyancy floating platform (6) is fixedly installed inside the floating water taking tank (1), and an injection/drainage port (7) of the floating platform is formed in one side of the adjustable buoyancy floating platform (6).
3. The intelligent siphon drainage and flexible stilling system of the silt dam according to claim 1, wherein the active and passive exhaust pipes (11) are fixed on the downstream drain pipe (2) by flexible plastic pipes.
4. The intelligent siphon drainage and flexible stilling system for the silt dam according to claim 1, wherein the flexible stilling system (28) is assembled by filling pebbles in polypropylene geomembrane bags with super-weatherability, is assembled according to 2-3 layers, and is provided with an impermeable membrane between the upper bag body and the lower bag body.
5. The intelligent control siphon drainage and flexible force-relief pool system for the silt dam according to claim 1, wherein the intelligent control siphon drainage and flexible force-relief pool system for the silt dam is characterized in that: the dam top water passing duct (15) is connected with a downstream drainage pipe groove (17), and the downstream drainage pipe groove (17) is provided with a downstream force eliminating step (16).
6. The intelligent siphon drainage and flexible stilling pond system for the silt dam according to claim 1, wherein the drainage pipes (2) are pvc hard pipes with the diameter of 20cm, 3-4 drainage pipes (2) are arranged in parallel according to actual drainage efficiency requirements, and the drainage pipes (2) share one floating water taking tank (1) and an upward-protruding water injection and gas collection device (8).
7. The intelligent siphon drainage and flexible stilling pond system of a check dam according to claim 1, characterized in that a dam top drainage pipe (31) is laid on the top of the dam body (13).
CN202110784760.6A 2021-07-12 2021-07-12 Intelligent control siphon drainage and flexible stilling basin system for check dam Active CN113622377B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110784760.6A CN113622377B (en) 2021-07-12 2021-07-12 Intelligent control siphon drainage and flexible stilling basin system for check dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110784760.6A CN113622377B (en) 2021-07-12 2021-07-12 Intelligent control siphon drainage and flexible stilling basin system for check dam

Publications (2)

Publication Number Publication Date
CN113622377A CN113622377A (en) 2021-11-09
CN113622377B true CN113622377B (en) 2022-10-28

Family

ID=78379507

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110784760.6A Active CN113622377B (en) 2021-07-12 2021-07-12 Intelligent control siphon drainage and flexible stilling basin system for check dam

Country Status (1)

Country Link
CN (1) CN113622377B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114277771B (en) * 2021-12-31 2023-07-25 浙江省交通运输科学研究院 Highway slope siphon drainage device and method capable of automatically adjusting underground water level along with slope

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2219905Y (en) * 1995-03-25 1996-02-14 贵州省水利科学研究所 Automatic opening or closing water-taking device by reservoir buoyancy
CN201206246Y (en) * 2008-04-03 2009-03-11 中国水利水电科学研究院 Water discharge engineer for check dam
CN201821715U (en) * 2010-07-24 2011-05-11 寇振岭 Siphon type simple gravity irrigation device
CN202187327U (en) * 2011-07-04 2012-04-11 河海大学 Water level controller for siphon drainage pipe
CN206581224U (en) * 2017-03-21 2017-10-24 于学峰 A kind of protection slope
CN207567736U (en) * 2017-12-07 2018-07-03 河海大学 Silt arrester water storage intelligence delayed release device
CN111535249A (en) * 2020-05-08 2020-08-14 张金良 Non-management and protection integrated check dam and construction method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2219905Y (en) * 1995-03-25 1996-02-14 贵州省水利科学研究所 Automatic opening or closing water-taking device by reservoir buoyancy
CN201206246Y (en) * 2008-04-03 2009-03-11 中国水利水电科学研究院 Water discharge engineer for check dam
CN201821715U (en) * 2010-07-24 2011-05-11 寇振岭 Siphon type simple gravity irrigation device
CN202187327U (en) * 2011-07-04 2012-04-11 河海大学 Water level controller for siphon drainage pipe
CN206581224U (en) * 2017-03-21 2017-10-24 于学峰 A kind of protection slope
CN207567736U (en) * 2017-12-07 2018-07-03 河海大学 Silt arrester water storage intelligence delayed release device
CN111535249A (en) * 2020-05-08 2020-08-14 张金良 Non-management and protection integrated check dam and construction method thereof

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
装配式抢险排洪虹吸管;汪永剑等;《水利科技与经济》;20080130(第01期);62-64 *
长距离虹吸管输水试验研究初探;许史等;《中国农村水利水电》;20100315(第03期);70-72 *

Also Published As

Publication number Publication date
CN113622377A (en) 2021-11-09

Similar Documents

Publication Publication Date Title
CN1023723C (en) Spillway for discharging extraordinary floods at dams having at least two floods discharge structures
CN104532796B (en) The rubber dam of a kind of wear-resistant steel plate of self-control type band
CN201762694U (en) Dam flow guiding device
CN113622377B (en) Intelligent control siphon drainage and flexible stilling basin system for check dam
CN206986911U (en) A kind of spacing automatic start-stop device of underground pipe gallery deep foundation pit precipitation pipe well water-pump
CN216475468U (en) Cut dirty main pipe and prevent flowing backward reposition of redundant personnel well
CN204343257U (en) The rubber dam of the wear-resistant steel plate of a kind of autocontrol band
CN205557464U (en) Type of can decontaminating intelligence flood control dam
CN212956903U (en) A diversion system for pump station desilting
CN109778768B (en) Ice melting and anti-freezing device in front of dam
CN213448816U (en) Integrated rainwater and sewage diversion pump station with silt-proof function
CN111519682A (en) Unpowered sand suction device and method
CN217203918U (en) Upturning type hydraulic integrated pump gate
CN212641711U (en) Prevent flowing backward rainwater box culvert and cut dirty pump station
CN214423534U (en) Intelligent sewage intercepting well of overturning weir
CN106988400A (en) It is a kind of keep off it is damp, anti-blocking, maintenance it is convenient, can sand washing desilting hondo formula closure works system and method
CN210976044U (en) Wall-mounted micro drainage pump station for sewage interception engineering
CN112081185A (en) Integral fire-fighting water pool and construction method thereof
CN210712774U (en) Novel structure of built-in desilting basin of dam rolls
CN209941630U (en) Pump valve pipeline type fish passing facility
CN113605490A (en) Riverbed type underground water taking structure
CN207109987U (en) A kind of hondo formula closure works system
CN216339277U (en) Anti-freezing device for gate
CN211948317U (en) Ecological flow drainage facility for constructed diversion canal type rural hydropower station
CN109555090A (en) Ecological flow for hydroenergy storage station is released facility and implementation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant