CN113605211A CN202110756589.8A CN202110756589A CN113605211A CN 113605211 A CN113605211 A CN 113605211A CN 202110756589 A CN202110756589 A CN 202110756589A CN 113605211 A CN113605211 A CN 113605211A
Authority
CN
China
Prior art keywords
substructure
track
arch
rigid frame
rib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110756589.8A
Other languages
Chinese (zh)
Inventor
曾敏
崔旸
严爱国
文望青
刘阳明
饶少臣
刘诗文
陈丽莎
马明
李元俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN202110756589.8A priority Critical patent/CN113605211A/en
Publication of CN113605211A publication Critical patent/CN113605211A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D12/00Bridges characterised by a combination of structures not covered as a whole by a single one of groups E01D2/00 - E01D11/00
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B25/00Tracks for special kinds of railways
    • E01B25/22Tracks for railways with the vehicle suspended from rigid supporting rails
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/04Bearings; Hinges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The embodiment of the application provides a continuous rigid frame arch bridge of a suspended monorail, wherein a track assembly comprises a first cross beam, a second cross beam and two track beams, the track beams are arranged at intervals along the transverse bridge direction and extend along the longitudinal bridge direction, and the first cross beam and the second cross beam are arranged between the track beams and are arranged at intervals along the longitudinal bridge direction; a first substructure in the substructure supports the first beam, and a second substructure is disposed on an underside of a space between the first beam and the second beam; the first arch springing of the first arch rib structure arranged between the track beams is connected with the first beam, and the second springing extends to the lower part of the track assembly from between the track beams and is connected with the second substructure; the area of the first arch rib structure, which is positioned at the upper side of the track assembly, is connected with each track beam through a first connecting piece; one end of the supporting component arranged between the track beams is connected with the second substructure, and the other end of the supporting component is connected with the second cross beam. The continuous rigid frame arch bridge of the suspension type monorail provided by the embodiment of the application has high spanning capacity.

Description

Suspension type monorail continuous rigid frame arch bridge
Technical Field
The invention relates to the field of urban novel rail transit, in particular to a continuous rigid frame arch bridge with a suspended monorail.
Background
Suspension type monorail transit belongs to track traffic's novel technique, is used for scenic spot and city more, and its bridge structures structure is succinct, the vision is penetrating, has avoided appearing more complicated component and has sheltered from the sight. At present, the research and construction of the rail beam at home and abroad are concentrated in the conventional span (the span is less than or equal to 30m), but the large-span suspension type monorail bridge is indispensable due to the diversity of the required spanning barriers, and sometimes even becomes a key node for implementing the suspension type monorail.
Compared with other long-span bridge girders, the track girder of the suspended monorail is a load-bearing structure and also serves as a running and guiding track of a vehicle, and has strict requirements on deformation of the track girder under the action of vehicle load in order to ensure the safety and comfort of train operation, so that the bridge girder structure has enough vertical and transverse rigidity. After the span of the conventional suspended monorail beam exceeds 30m, the vertical deflection and the transverse deflection of the rail beam are too large, and the requirements on rigidity and comfort are difficult to meet.
Disclosure of Invention
In view of the above, the main object of the embodiments of the present application is to provide a continuous rigid frame arch bridge with a suspended monorail having high spanning capability.
In order to achieve the above purpose, the technical solution of the embodiment of the present application is implemented as follows:
the embodiment of the application provides a continuous rigid frame arch bridge of suspension type monorail, includes:
the track assembly comprises a first cross beam, a second cross beam and two track beams, the two track beams are arranged at intervals along the transverse bridge direction and extend along the longitudinal bridge direction, and the first cross beam and the second cross beam are arranged between the two track beams and are arranged at intervals along the longitudinal bridge direction;
a substructure including a first substructure supporting the first beam and a second substructure disposed on an underside of a space between the first beam and the second beam;
a first rib structure disposed between the two track beams, the first rib structure having a first rib foot and a second rib foot, the first rib foot being connected to the first beam, the second rib foot extending from between the two track beams to below the track assembly and being connected to the second substructure;
the first arch rib structures are positioned in the area on the upper side of the track assembly and connected with the track beams through the first connecting pieces;
and the supporting component is arranged between the two track beams, one end of the supporting component is connected with the second substructure, and the other end of the supporting component is connected with the second cross beam.
In one embodiment, the support assembly is a diagonal leg.
In one embodiment, the continuous rigid frame arch bridge further includes a first movable support disposed at the top of the first substructure, and the first beam is connected to the first movable support.
In one embodiment, the support assembly comprises a second rib structure having a third rib foot and a fourth rib foot, and a plurality of second connectors, the substructure further comprising a third substructure;
the third substructure supports the second beam, the third rib structure has the third rib leg connected to the second beam, and the fourth rib leg extends between the two track beams to below the track assembly and is connected to the second substructure;
the second arch rib structure is connected between the area of the upper side of the track assembly and each track beam through the second connecting piece.
In one embodiment, the area of the first rib structure on the upper side of the track assembly is asymmetric with the area of the second rib structure on the upper side of the track assembly.
In one embodiment, the continuous rigid frame arch bridge further includes a first movable support and a second movable support, the first movable support is disposed at the top of the first substructure, the first beam is connected to the first movable support, the second movable support is disposed at the top of the third substructure, and the second beam is connected to the second movable support.
In one embodiment, the first and second rib structures are both steel box structures.
In one embodiment, the second substructure includes a first platform, and the second arch foot and the support assembly are both connected to the first platform.
In one embodiment, the second substructure includes a bridge pier and a second bearing platform, the bridge pier is connected with the second bearing platform, and the second arch springing and the support component are both connected with the bridge pier.
In one embodiment, the region of the first rib structure on the underside of the track assembly is symmetrically disposed with respect to the region of the support assembly on the underside of the track assembly.
The embodiment of the application provides a single-rail continuous rigid frame arched bridge of suspension type, this continuous rigid frame arched bridge is through setting up first arch rib structure between two track roof beams, combine together arched bridge and suspension type single track, the demand of suspension type vehicle to the operating space has been satisfied, first arch rib structure is located and is connected through first connecting piece between the region of track subassembly upside and each track roof beam, therefore, the gravity of two track roof beam bodies and the load effort of vehicle on the roof beam can transmit first arch rib structure through first connecting piece on. In addition, the first arch springing of the first arch rib structure is connected with the first beam, the first beam is supported by the first substructure, and the second arch springing extends to the lower part of the track assembly from between the two track beams and is connected with the second substructure, so that the force on the first arch rib structure can be transmitted to the first substructure and the second substructure, and the stress of the continuous rigid frame arch bridge is more uniform. One end of the supporting component is connected with the second substructure, and the other end of the supporting component is connected with the second cross beam, so that the horizontal thrust generated by the continuous rigid frame arch bridge at the second arch springing is balanced, the structure has larger vertical, transverse and torsional rigidity, and the spanning capability of the continuous rigid frame arch bridge is greatly improved.
Drawings
FIG. 1 is a block diagram of a continuous rigid frame arch bridge with a suspended monorail constructed in accordance with a first embodiment of the present application;
FIG. 2 is a view a-a of FIG. 1;
FIG. 3 is a structural view of a continuous rigid frame arch bridge of a suspended monorail of a second embodiment of the present application;
fig. 4 is a structural view of a continuous rigid frame arch bridge of a suspended monorail of the third embodiment of the present application.
Description of the reference numerals
A track assembly 10; a first cross member 11; a track beam 12; a lower structure 20; a first substructure 21; a second substructure 22; a first stage 221; a second platform 222; bridge piers 223; a third substructure 23; a first rib structure 30; a first connecting member 40; a support assembly 50; a second connecting member 51; a second rib structure 52.
Detailed Description
It should be noted that, in the present application, technical features in examples and embodiments may be combined with each other without conflict, and the detailed description in the specific embodiment should be understood as an explanation of the gist of the present application and should not be construed as an improper limitation to the present application.
In the present application, the "longitudinal direction", "vertical direction", "upper" and "lower" orientation or positional relationship is based on the orientation or positional relationship shown in fig. 1, and the "transverse direction" orientation or positional relationship is based on the orientation or positional relationship shown in fig. 2. It is to be understood that such directional terms are merely for convenience in describing the present application and for simplicity in description, and are not intended to indicate or imply that the referenced device or element must have a particular orientation, be constructed and operated in a particular orientation, and are not to be considered limiting of the present application.
Referring to fig. 1 and 2, the continuous rigid frame arch bridge of the suspended monorail includes a rail assembly 10, a substructure 20, a first arch rib structure 30 disposed between two rail beams 12, a plurality of first connecting members 40, and a support assembly 50 disposed between two rail beams 12. The track assembly 10 includes a first beam 11, a second beam, and two track beams 12, that is, the continuous rigid frame arch bridge of the present application has two tracks, which may be two same-direction tracks or two opposite-direction tracks, and the two tracks are symmetrically disposed about the first arch rib structure 30. Two track roof beams 12 set up and extend to the interval along indulging the bridge along horizontal bridge, and first crossbeam 11 and second crossbeam setting just set up to the interval along indulging the bridge between two track roof beams 12, can improve the stability of two track roof beams 12 to the load on two track roof beams 12 of transmission makes the roof beam body atress more even.
It should be noted that besides the first cross beam 11 and the second cross beam, a plurality of other cross beams are disposed between the two track beams 12, and all the cross beams are disposed between the two track beams 12 and are spaced apart from each other in the longitudinal bridge direction.
The substructure 20 comprises a first substructure 21 and a second substructure 22, the first substructure 21 supporting the first beam 11, i.e. the forces experienced on the first beam 11 can be transferred to the first substructure 21 and through the first substructure 21 into the foundation, making the bridge structure more stable. The second substructure 22 is disposed at a lower side of the space between the first beam 11 and the second beam, that is, the first beam 11 and the second beam are respectively located at two sides of the second substructure 22.
The first arch rib structure 30 is connected with each track beam 12 through the first connecting piece 40 in the area of the upper side of the track assembly 10, and the dead weight of the track beam 12 and the load of the vehicle on the beam can be transmitted to the first arch rib structure 30 through the first connecting piece 40, so as to share the bearing pressure of the track beam 12 and improve the stability of the bridge.
The first connecting member 40 may be a hanger bar, which may be a high-strength wire bundle, a thick steel bar, reinforced concrete or prestressed concrete member, etc., to enhance the stability of the first arch rib.
The first arch rib structure 30 has a first arch foot and a second arch foot, the first arch foot is connected with the first beam 11, that is, the first arch foot is directly connected with the first beam 11, namely, the through arch foot, the first arch rib structure 30 can transmit the acting force from the track beam 12 and the self gravity to the first beam 11, and transmit the acting force to the foundation through the supporting function of the first substructure 21.
The second arch foot extends from between the two track beams 12 to the lower part of the track assembly 10 and is connected with the second substructure 22, that is, the second arch foot is directly connected with the second substructure 22 after passing through the track assembly 10, and is a half-through arch foot, which can provide horizontal thrust to reduce the bending moment of the first arch rib structure 30, thereby improving the rigidity of the structure.
One end of the supporting component 50 is connected with the second substructure 22, and the other end of the supporting component 50 is connected with the second beam, so that the horizontal force generated by the first arch rib structure 30 can be balanced, the pressure of the second substructure 22 is reduced, and the safety performance of the bridge is improved.
In one embodiment, the main span of the bridge can reach more than 60m, and larger span capacity is realized.
In one embodiment, referring to fig. 4, the second substructure 22 includes a first platform 221, and the second arch foot and supporting element 50 are connected to the first platform 221, that is, the second arch foot and supporting element 50 may be directly supported on the first platform 221, or may not be connected to the bridge pier 223.
It should be noted that the second arch foot and support assembly 50 may be connected to the same position on the first platform 221, or may be connected to different positions on the first platform 221.
In one embodiment, referring to fig. 1, the second substructure 22 includes an abutment 223 and a second platform 222, the abutment 223 is connected to the second platform 222, and the second arch and the supporting element 50 are both connected to the abutment 223, that is, after the second arch and the supporting element 50 are connected to the abutment 223, the abutment 223 is connected to the second platform 222, and the force is transmitted to the foundation through the foundation.
In one embodiment, referring to fig. 3, the supporting component 50 is a slant leg, one end of the slant leg is connected to the second substructure 22, and the other end is connected to the second beam, so as to balance the internal force of the main beam.
In an embodiment, referring to fig. 3, the continuous rigid frame arch bridge further includes a first movable support, the first movable support is disposed on the top of the first substructure 21, the first beam 11 is connected to the first movable support, the track assembly 10 can horizontally displace at the first movable support, and when the structure expands with heat and contracts with cold due to the change of the external environment temperature, the track assembly 10 can perform necessary horizontal displacement at the first movable support, so as to reduce the temperature stress generated by the structural limitation in the continuous rigid frame arch bridge and maintain the stability of the bridge.
In some embodiments, the diagonal leg may also be fixedly connected to the second cross member.
In one embodiment, referring to fig. 1, the support assembly 50 includes a second rib structure 52 and a plurality of second connecting members 51, the second rib structure 52 is disposed between the two track beams 12, the second rib structure 52 has a third rib foot and a fourth rib foot, and the substructure 20 further includes a third substructure 23.
The third substructure 23 supports the second beam, the force transmitted to the second beam by the bridge can be transmitted to the foundation through the third substructure 23, the third arch foot of the second arch rib structure 52 is connected with the second beam, the fourth arch foot extends to the lower part of the track assembly 10 from between the two track beams 12 and is connected with the second substructure 22, one part of the force of the second arch rib structure 52 can be transmitted to the third substructure 23 through the second beam, and the other part can be directly connected with the second substructure 22 to complete the force transmission, so that the force transmission of the bridge can be smoother, and the beam body is more stable.
The second arch rib structure 52 is connected with each track beam 12 through the second connecting piece 51 in the area of the upper side of the track assembly 10, and the self weight of the track beam 12 and the load of the vehicle on the beam can be transmitted to the second arch rib structure 52 through the second connecting piece 51 and transmitted to the foundation through the third substructure 23 and the second substructure 22, so that the stress is more uniform.
It will be appreciated that as the bridge span increases, the substructure 20 may also be provided with a plurality of other substructures which may be used to support other beams than the first beam 11 and the second beam.
The second connector 51 may be a hanger bar, which may be a high-strength wire bundle, a thick steel bar, reinforced concrete or prestressed concrete member, etc., to enhance the stability of the first arch rib.
In one embodiment, referring to fig. 1, the substructure 20 includes a third substructure 23, and the continuous rigid frame arch bridge includes a first movable support and a second movable support, the first movable support is disposed on the top of the first substructure 21, the first beam 11 is connected to the first movable support, the second movable support is disposed on the top of the third substructure 23, and the second beam is connected to the second movable support to adapt to the expansion and contraction deformation of the bridge structure caused by environmental changes such as temperature and humidity.
That is to say, the first beam is movably connected with the first substructure 21, and the second arch springing is fixedly connected with the second substructure 22, so that the bridge structure has larger vertical, transverse and torsional rigidity, and the influence caused by temperature stress can be reduced.
It should be noted that, when there are a plurality of other substructures in the substructure 20, other beams except the first beam 11 and the second beam are also movably connected to their corresponding substructures.
In one embodiment, referring to fig. 1, the area of the first rib structure 30 on the upper side of the track assembly 10 and the area of the second rib structure 52 on the upper side of the track assembly 10 are asymmetric arch axes.
It should be noted that the area of the first rib structure 30 or the second rib structure 52 on the upper side of the track assembly 10 may be asymmetric with respect to the respective vertex vertical central axes, or the area of the first rib structure 30 and the second rib structure 52 on the upper side of the track assembly 10 may be asymmetric with respect to each other.
In a specific embodiment, please refer to fig. 1, the bridge span corresponding to the first arch rib structure is a mid-span, the bridge span corresponding to the second arch rib structure is a side-span, the first arch rib structure 30 has a larger appearance than the second arch rib structure 52, the mid-span and the side-span are skillfully matched, the arch axes of the first arch rib structure 30 and the second arch rib structure 52 are broken line type, and the vertexes of the arch axes of the first arch rib structure and the second arch rib structure are close to the second substructure 22 side, so as to form an asymmetric "heart pulse beating" shape, the overall shape is simple, beautiful and innovative, and the landscape requirements of the bridge structures in cities and scenic spots are met.
In one embodiment, the first arch rib structure 30 and the second arch rib structure 52 are both steel box structures, and the structural section may be a single box and single chamber section, and the section is formed by enclosing an upper top plate, two side plates and a lower bottom plate.
In an embodiment, referring to fig. 1 and fig. 3, the area of the first arch rib structure 30 on the lower side of the track assembly 10 and the area of the supporting assembly 50 on the lower side of the track assembly 10 are symmetrically disposed, and the two areas may be symmetrically disposed about the vertical central axis of the second substructure 22, or may be symmetrically disposed about any vertical axis of the second substructure 22, so that the horizontal forces at the second substructure 22 are balanced, the horizontal forces applied to the foundation are reduced, and the amount of foundation engineering is saved.
It should be noted that when the support member 50 is a slant leg, the whole slant leg 51 is located at the lower side of the track member 10.
In an embodiment, the first arch rib structure 30, the second arch rib structure 52, the first connecting member 40, the second connecting member 51, the track beam 12, the first beam 11 and the second beam are all steel structures, and can be prefabricated in a factory and assembled by welding on site, so that the construction is convenient and fast, and the practicability is strong.
The above description is only a preferred embodiment of the present application and is not intended to limit the present application, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, improvement and the like made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims (10)

1. A continuous rigid frame arch bridge of a suspended monorail, comprising:
the track assembly comprises a first cross beam, a second cross beam and two track beams, the two track beams are arranged at intervals along the transverse bridge direction and extend along the longitudinal bridge direction, and the first cross beam and the second cross beam are arranged between the two track beams and are arranged at intervals along the longitudinal bridge direction;
a substructure including a first substructure supporting the first beam and a second substructure disposed on an underside of a space between the first beam and the second beam;
a first rib structure disposed between the two track beams, the first rib structure having a first rib foot and a second rib foot, the first rib foot being connected to the first beam, the second rib foot extending from between the two track beams to below the track assembly and being connected to the second substructure;
the first arch rib structures are positioned in the area on the upper side of the track assembly and connected with the track beams through the first connecting pieces;
and the supporting component is arranged between the two track beams, one end of the supporting component is connected with the second substructure, and the other end of the supporting component is connected with the second cross beam.
2. The continuous rigid frame arch bridge of claim 1, wherein the support assemblies are skew legs.
3. The continuous rigid frame arch bridge of claim 2, further comprising a first cradle disposed on top of the first substructure, the first beam being connected to the first cradle.
4. A continuous rigid frame arch bridge according to claim 1, wherein the support assembly comprises a second rib structure having a third rib foot and a fourth rib foot, and a plurality of second connectors, the substructure further comprising a third substructure;
the third substructure supports the second beam, the third rib structure has the third rib leg connected to the second beam, and the fourth rib leg extends between the two track beams to below the track assembly and is connected to the second substructure;
the second arch rib structure is connected between the area of the upper side of the track assembly and each track beam through the second connecting piece.
5. A continuous rigid frame arch bridge according to claim 4, wherein the area of the first arch rib structure on the upper side of the track assembly is asymmetric arch axis with the area of the second arch rib structure on the upper side of the track assembly.
6. The continuous rigid frame arch bridge of claim 4, further comprising a first cradle and a second cradle, the first cradle being disposed on top of the first substructure, the first beam being connected to the first cradle, the second cradle being disposed on top of the third substructure, the second beam being connected to the second cradle.
7. A continuous rigid frame arch bridge according to claim 4, wherein the first and second arch rib structures are each steel box structures.
8. The continuous rigid frame arch bridge of claim 1, wherein the second substructure includes a first platform, the second arch foot and the support assembly each being connected to the first platform.
9. The continuous rigid frame arch bridge of claim 1, wherein the second substructure includes an abutment and a second cap, the abutment being connected to the second cap, the second arch shoe and the support assembly both being connected to the abutment.
10. A continuous rigid frame arch bridge according to claim 1, wherein the region of the first arch rib structure on the underside of the track assembly is symmetrically disposed with respect to the region of the support assembly on the underside of the track assembly.
CN202110756589.8A 2021-07-05 2021-07-05 Suspension type monorail continuous rigid frame arch bridge Pending CN113605211A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110756589.8A CN113605211A (en) 2021-07-05 2021-07-05 Suspension type monorail continuous rigid frame arch bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110756589.8A CN113605211A (en) 2021-07-05 2021-07-05 Suspension type monorail continuous rigid frame arch bridge

Publications (1)

Publication Number Publication Date
CN113605211A true CN113605211A (en) 2021-11-05

Family

ID=78337260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110756589.8A Pending CN113605211A (en) 2021-07-05 2021-07-05 Suspension type monorail continuous rigid frame arch bridge

Country Status (1)

Country Link
CN (1) CN113605211A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080005857A1 (en) * 2005-08-29 2008-01-10 Yong Li Arch bridge
CN205347954U (en) * 2015-11-30 2016-06-29 中铁第四勘察设计院集团有限公司 Wave arched bridge
CN106436550A (en) * 2016-09-20 2017-02-22 江苏京沪重工有限公司 Two-span continuous spatial special-shaped arch combination bridge structure
CN107724225A (en) * 2017-11-21 2018-02-23 中铁第四勘察设计院集团有限公司 A kind of suspension type monorail Long span track girder system
CN111945541A (en) * 2020-08-10 2020-11-17 詹刚毅 Half-through tied arch bridge
CN112195748A (en) * 2020-09-21 2021-01-08 中铁第四勘察设计院集团有限公司 Space net rack steel truss girder suitable for suspended monorail and construction method thereof
CN112323610A (en) * 2020-11-26 2021-02-05 中铁第四勘察设计院集团有限公司 A well formula arched bridge that holds for suspension type single track
CN112376393A (en) * 2020-12-02 2021-02-19 中铁第四勘察设计院集团有限公司 Suspension type single-rail simply-supported beam bridge
CN213328632U (en) * 2020-09-23 2021-06-01 中铁第六勘察设计院集团有限公司 Suspension type monorail trolley-bus tie-rod arch bridge structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080005857A1 (en) * 2005-08-29 2008-01-10 Yong Li Arch bridge
CN205347954U (en) * 2015-11-30 2016-06-29 中铁第四勘察设计院集团有限公司 Wave arched bridge
CN106436550A (en) * 2016-09-20 2017-02-22 江苏京沪重工有限公司 Two-span continuous spatial special-shaped arch combination bridge structure
CN107724225A (en) * 2017-11-21 2018-02-23 中铁第四勘察设计院集团有限公司 A kind of suspension type monorail Long span track girder system
CN111945541A (en) * 2020-08-10 2020-11-17 詹刚毅 Half-through tied arch bridge
CN112195748A (en) * 2020-09-21 2021-01-08 中铁第四勘察设计院集团有限公司 Space net rack steel truss girder suitable for suspended monorail and construction method thereof
CN213328632U (en) * 2020-09-23 2021-06-01 中铁第六勘察设计院集团有限公司 Suspension type monorail trolley-bus tie-rod arch bridge structure
CN112323610A (en) * 2020-11-26 2021-02-05 中铁第四勘察设计院集团有限公司 A well formula arched bridge that holds for suspension type single track
CN112376393A (en) * 2020-12-02 2021-02-19 中铁第四勘察设计院集团有限公司 Suspension type single-rail simply-supported beam bridge

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘宗峰: "旅游轨道交通桥梁设计特点分析――以张家界市旅游轨道交通为例", 《铁道标准设计》 *

Similar Documents

Publication Publication Date Title
US8689383B2 (en) Upper structure for bridge
CN110777643A (en) Large-span steel truss combined continuous beam structure and construction method thereof
CN111749337A (en) Large-span cable net structure supported by self-balancing arch truss
CN109930469B (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
CN111155709B (en) Assembled roof truss system
CN113605211A (en) Suspension type monorail continuous rigid frame arch bridge
CN209779361U (en) Steel truss girder supporting system suitable for asymmetric suspension type monorail
CN111424521A (en) V-shaped supporting continuous rigid frame bridge of steel-concrete beam
CN111827079A (en) Combined beam bridge with cantilever arms for highway and railway dual-purpose box girders
KR101929531B1 (en) Truss unit
CN109594461B (en) Assembled steel concrete composite beam and forming method thereof
CN112323610B (en) Middle-bearing arch bridge for suspension type monorail
CN211689854U (en) Large-span steel truss combined continuous beam structure
CN113174831B (en) Steel truss combined main beam structure of cable-stayed bridge of ballastless track of high-speed railway
CN214656270U (en) A well formula arched bridge that holds for suspension type single track
CN209941469U (en) Steel box girder thin-wall pier rigid frame cable-stayed bridge suitable for straddle type monorail
CN114482278A (en) Multi-arch combined stress self-balancing large-span arch steel structure system
CN107574747B (en) Structure system of highway-railway co-construction multi-tower cable-stayed bridge
CN109252455B (en) Cantilever assembling construction method of multi-main-truss steel truss girder structure
CN111764250A (en) Steel truss web combined beam cable-stayed bridge
CN111733714A (en) Beam column node structure of overhead station and interval bridge
CN216615451U (en) Large-span cable-stayed bridge structure for suspended monorail trolley bus
CN215857136U (en) Partial cable-stayed bridge
CN217869918U (en) Assembled steel truss composite beam double-deck bridge with rigid frame cross beam
CN211256619U (en) Steel temporary bridge suitable for construction of long-span steel bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211105