CN113595086B - Power transmission network topology optimization method - Google Patents
Power transmission network topology optimization method Download PDFInfo
- Publication number
- CN113595086B CN113595086B CN202111156022.3A CN202111156022A CN113595086B CN 113595086 B CN113595086 B CN 113595086B CN 202111156022 A CN202111156022 A CN 202111156022A CN 113595086 B CN113595086 B CN 113595086B
- Authority
- CN
- China
- Prior art keywords
- transmission network
- power
- power transmission
- main transformer
- topology optimization
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/04—Circuit arrangements for ac mains or ac distribution networks for connecting networks of the same frequency but supplied from different sources
- H02J3/06—Controlling transfer of power between connected networks; Controlling sharing of load between connected networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/10—Power transmission or distribution systems management focussing at grid-level, e.g. load flow analysis, node profile computation, meshed network optimisation, active network management or spinning reserve management
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
The invention discloses a power transmission network topology optimization method, which comprises the following steps: the method comprises the steps of taking load balancing and the minimum number of switching actions before and after topological optimization of the power transmission network as optimization targets, and comprehensively considering 8 large boundary constraint conditions of topological optimization to construct a topological optimization model of the power transmission network; acquiring operation data of the power transmission network in real time; and inputting the acquired power transmission network operation data into a power transmission network topology optimization model, and calculating and outputting the optimized network topology and switch state by the model. The power transmission network topology optimization model constructed by the invention is more reasonable in network topology structure according to the power transmission network operation data output acquired in real time, and has higher application value for reducing the fault range and the power failure time of the power transmission network and reducing the network loss of the power transmission network in a normal state, thereby improving the rationality of the power transmission network tide distribution and the operation safety of a power transmission system.
Description
Technical Field
The invention relates to the technical field of power transmission network topology optimization, in particular to a power transmission network topology optimization method.
Background
The high-voltage power transmission network is an important ring for power transmission of an electric power system, and the topological structure and the power flow distribution of the high-voltage power transmission network are reasonable or not, so that the power supply safety of the whole area is directly concerned. At present, a high-voltage power transmission network is optimized mainly by means of offline manual adjustment, so that the efficiency is very low, and various boundary constraints are difficult to consider (for example, the power change of a 220kV transformer substation in the high-voltage power transmission system before and after network topology optimization should not exceed a given range), and therefore the method cannot be applied to real-time optimization and calculation of complex power transmission network topology.
Disclosure of Invention
The invention provides a power transmission network topology optimization method aiming at realizing real-time optimization of complex power transmission network topology and improving the rationality of power transmission network topology structure and power flow distribution.
In order to achieve the purpose, the invention adopts the following technical scheme:
provided is a power transmission network topology optimization method, which comprises the following steps:
the method comprises the steps that load balancing and the minimum number of switching actions before and after topological optimization of a power transmission network are taken as optimization targets, a power change range of a 220kV transformer substation before and after topological optimization, branch power operation limit values, power reverse transmission prevention, node power balance, simultaneous closing of reverse disconnecting switches of the transformer substation are not allowed, the number of 110kV main transformers connected under outgoing lines is limited, 110kV main transformer power supplies cannot be the same, and equipment fault states are set as boundary constraint conditions of network topological optimization, so that a power transmission network topological optimization model is constructed;
acquiring operation data of the power transmission network in real time;
inputting the acquired power transmission network operation data into the power transmission network topology optimization model, and calculating and outputting the optimized network topology and switch state by the model;
the objective function solved by the power transmission network topology optimization model is expressed by the following formula (1):
in the formula (1), the first and second groups,an objective function representing the power transmission network topology optimization model;
indicating a fault condition of the power transmission network,,the number of fault states of the power transmission network;
in the formula (2), the first and second groups,representing the main branch in the transmission network in a normal stateRoad surfaceThe load factor of (a) is,calculated by the following formula (3):
in the formula (3), the first and second groups,representing the main transformer branch circuit in the normal state of the power transmission networkThe active load of (2);
indicating that said grid is flowing through said main transformer branch under normal conditionsThe maximum allowed power of;
in the formula (2) and the formula (3)Representing the second in said transmission networkA node or aA strip bus;
representing each of said main transformer branches within said transmission networkThe average load rate of (a) is,calculated by the following formula (4):
in the formula (4), the first and second groups,representing the number of said primary transformers within said power transmission network;
in the formula (5), the first and second groups,indicating fault condition of transmission networkLower main transformer branchSwitch or knife state in;
As a preferred scheme of the present invention, the transmission network operation data obtained in real time includes a current load, a rated active power, a bus number, a node number, node numbers at two outgoing line ends, a rated active power of an outgoing line, a rated active power of a contact line between 110kV stations, active loads of buses in 110kV stations, node numbers at two ends of a disconnecting link or a switch, an equipment fault set, and maximum allowable power of main transformer branches before and after a fault in a high-voltage transmission network.
As a preferred solution of the present invention, the constraint condition of the power variation range of the 220kV substation for power transmission network topology optimization is expressed by the following formula (6):
in the formula (6), the first and second groups,representing the maximum allowable power fluctuation rate of the 220kV transformer substation;
representing that the current flows through a main transformer branch in the 220kV transformer substation before the topological optimization of the transmission networkIs provided withWork load;
representing the main transformer branch in the 220kV transformer substation after the transmission network restores to the normal state through topology optimizationThe active load of (2).
As a preferred aspect of the present invention, the branch power operation limit constraint condition of the power transmission network topology optimization is expressed by the following equations (7) to (8):
in the formula (8), the first and second groups,indicating the fault stateThe main transformer branch in the lower power transmission networkActive power of (d);
indicating that the grid is in the fault stateDownward flow through the main transformer branchIs measured.
As a preferred aspect of the present invention, the constraint of preventing power back-off for grid topology optimization is expressed by the following equation (9):
and representing that the active flow direction of the main transformer in the power transmission network flows from the main transformer to the load.
As a preferred aspect of the present invention, the node power balance constraint of the power transmission network topology optimization is expressed by the following equations (10) to (11):
in the formulae (10) to (11),、in normal and fault states, respectivelyLower superior electric network injection nodeOr bus barActive power of (d);
indicating the fault stateThe main transformer branch in the lower power transmission networkActive power of (d);
As a preferred scheme of the present invention, the constraint condition that the transformer substation inverted disconnecting link for power transmission network topology optimization does not allow simultaneous closing is:
two disconnecting switches with one end connected to the same node and the other end connected to different buses of the same substation are not allowed to be closed at the same time.
As a preferred scheme of the present invention, the limiting constraint condition of the number of the outgoing lower string 110kV main transformers in the topology optimization of the power transmission network is as follows:
and the number of the 110kV main transformers which are connected in series under the outgoing line of each 220kV station of the 220kV transformer station is not more than 3.
As a preferred scheme of the present invention, the constraint condition that the 110kV main transformer power supply for transmission network topology optimization cannot be the same is:
when a plurality of transformers or a plurality of buses exist in the 110kV transformer substation, the 110kV transformer substation is powered by different 220kV transformer substations.
As a preferred scheme of the present invention, the constraint condition for setting the fault state of the equipment in power transmission network topology optimization is as follows:
when the main transformer branchWhen equipment or line in the system is in fault, the main transformer branch circuit is connected with the main transformerForced to the open state.
The invention takes the minimum load balance and the minimum switching action times before and after the topological optimization of the power transmission network as optimization targets, comprehensively considers various boundary constraints before and after the topological optimization, and the constructed topological optimization model of the power transmission network is more reasonable in network topology structure output according to the real-time acquired running data of the power transmission network, thereby having higher application value for reducing the fault range and the power failure time of the power transmission network and reducing the network loss of the power transmission network in the normal state, further improving the rationality of the power flow distribution of the power transmission network and the running safety of a power transmission system.
Drawings
In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required to be used in the embodiments of the present invention will be briefly described below. It is obvious that the drawings described below are only some embodiments of the invention, and that for a person skilled in the art, other drawings can be derived from them without inventive effort.
Fig. 1 is a diagram of implementation steps of a power transmission network topology optimization method provided by an embodiment of the present invention;
fig. 2 is a schematic diagram of part of the wiring of the high voltage power transmission network.
Detailed Description
The technical scheme of the invention is further explained by the specific implementation mode in combination with the attached drawings.
Wherein the showings are for the purpose of illustration only and are shown by way of illustration only and not in actual form, and are not to be construed as limiting the present patent; to better illustrate the embodiments of the present invention, some parts of the drawings may be omitted, enlarged or reduced, and do not represent the size of an actual product; it will be understood by those skilled in the art that certain well-known structures in the drawings and descriptions thereof may be omitted.
The same or similar reference numerals in the drawings of the embodiments of the present invention correspond to the same or similar components; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right", "inner", "outer", etc. are used for indicating the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, it is only for convenience of description and simplification of description, but it is not indicated or implied that the referred device or element must have a specific orientation, be constructed in a specific orientation and be operated, and therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and are not to be construed as limitations of the present patent, and the specific meanings of the terms may be understood by those skilled in the art according to specific situations.
In the description of the present invention, unless otherwise explicitly specified or limited, the term "connected" or the like, if appearing to indicate a connection relationship between the components, is to be understood broadly, for example, as being fixed or detachable or integral; can be mechanically or electrically connected; they may be directly connected or indirectly connected through intervening media, or may be connected through one or more other components or may be in an interactive relationship with one another. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Before specifically describing the transmission network topology optimization method provided by the embodiment of the present invention, firstly, the transmission network operation data required to be obtained by topology optimization and the high-voltage transmission network structure to be subjected to topology optimization are described. Topology optimization requires acquisition of grid operating data including, but not limited to: the method comprises the steps of current load, rated active power, bus number of a transmission network, node number, node numbers at two outgoing ends, rated active power of outgoing lines, rated active power of a contact line between 110kV stations, active load of each bus in the 110kV station, node numbers at two ends of a disconnecting link or a switch, equipment fault set and maximum allowable power of each branch before and after the fault in a high-voltage transmission network (also called a high-voltage transmission system, hereinafter referred to as a transmission network). Fig. 2 shows a schematic diagram of a part of the wiring of a high voltage transmission network, and the definition and parameters of the acquired operational data of the transmission network will be explained below with reference to fig. 2.
A, B in FIG. 2 is a 220kV substation, and C-K is a 110kV substation; numbers 1-16 are bus numbers of the power transmission network, and numbers 17-25 are node numbers; the lines of the connecting nodes 17-23 are 220kV substation outgoing lines, and the outgoing lines of other 220kV substations are 4-21, 18-24, 19-14, 20-16 and the like. The lines connecting the buses 8 and 9 are 110kV interstation connecting lines, and other 110kV interstation connecting lines comprise 7-21, 8-21, 9-10, 10-22, 13-25, 14-15 and the like. The 220kV main transformer branch comprises 1-4, 2-5 and 3-6. 7 is an in-station bus of a 110kV transformer substation, and the in-station bus of the 110kV transformer substation is also 8-16.
The following explains a specific implementation of the power transmission network topology optimization method provided by the embodiment of the invention.
In order to guarantee the operation safety of a power transmission system, under a normal operation state, a power transmission network should meet the condition of load balancing as much as possible so as to reduce the network operation loss and improve the overload risk capability of the system after the system resists the fault of key equipment. Under the fault state, the transmission network can recover the normal operation after a limited number of inverted drainage operations, so as to reduce the fault range and the power failure time as much as possible. Therefore, the targets of the topology optimization of the power transmission network comprise a load balancing target after the power transmission network is restored to a normal state through the topology optimization and a switching action time control target of the topology optimization in a fault state.
The load balancing target in the normal state indicates that the load rates of main transformers (main transformers) in the 220kV transformer substation are the same or similar after the transmission network is recovered to be normal through topology optimization. The load rates are similar, so that the load distribution is more uniform, the system operation loss is generally smaller, and the overload risk after the fault is lower. The objective function for achieving load balancing is expressed by the following equation (1):
representing main transformer branches in a transmission networkThe branch set (as in fig. 2, main transformer branches 1-4, 2-5, 3-6);
indicating main transformer branch in power transmission network under normal stateThe load factor of (d);
in the formula (2), the first and second groups,main transformer branch circuit for indicating normal state of power transmission networkThe positive direction of the active load is the nodeTo the bus;
Main transformer branch circuit for indicating normal state of power transmission networkThe maximum allowed power of;
in the formula (3), the first and second groups,the main transformers (the number of main transformers) in the high-voltage power transmission system are shown.
Taking the load balance of a 220kV transformer substation in a high-voltage transmission system as an example, the aim of realizing the load balance of the 220kV transformer substation is as follows: main transformer branch in 220kV transformer substation in high-voltage power transmission systemLoad factor and each main transformer branch in all 220kV transformer substationsThe absolute value of the difference of the average load rates of (a) is smallest. For example, the active load of the main transformer branch 1-4 of the 220kV substation "a" in fig. 2 after topology optimization isThe maximum allowable power of the main transformer branch 1-4 isAnd calculating the load rate of the main transformer branches 1-4 after the topology optimization is recovered to be normal through the formula (2). Only 2 220kV transformer substations in the high-voltage transmission system are provided, namely 'A' and 'B', main transformer branches in the 220kV transformer substation 'B' are 2-5, and the load factor of the main transformer branches 2-5 after the topology optimization is recovered to be normal is calculated through the formula (2)Then, the main transformer branches in all 220kV substations in the high-voltage transmission system can be calculated by the above formula (3)Average load factor of (main transformer branches 1-4, 2-5). And finally, calculating a target value of a load balancing target function of the 220kV transformer substation after topology optimization through the formula (1).
The topology optimized switch action times control objective in fault conditions indicates that the number of switch and/or knife switch opening or closing operations within the power transmission network in fault conditions should be controlled. The fewer the number of controls, the lower the risk of switch action and the shorter the time required for the system to recover. The objective function controlling the number of switching actions is expressed by the following equation (4):
in the formula (4), the first and second groups,indicating main transformer branch circuit of power transmission network in normal stateSwitch and/or knife switch (as in fig. 2, knife switch in main transformer branch 5-17, switch in 17-23, switch in 1-4) state,when it is, it represents the main transformer branchThe switch or knife switch in (1) is in an open state,when it is, it represents the main transformer branchIn which the switch or knife-switch is in the closed state;Indicating fault condition of transmission networkLower main transformer branchThe switch and/or knife switch state in (1),time of day indicates a faultLower main transformer branchThe switch or knife switch in (1) is in an open state,time of day indicates a faultLower main transformer branchThe switch or knife switch in (1) is in a closed state,in (1)When the value is 0, the power transmission network is in a normal state,,is the number of failures.
Because the formula (1) and the formula (4) contain absolute valuesThe topological optimization algorithm of the power transmission network provided by the invention cannot be directly solved due to the value operation, and therefore, the invention introduces auxiliary variables、And constraining formulas (5) and (6) to equivalently transform the objective formulas (1) and (4), and the transformed objective functions can be expressed as formula (7) and formula (8).
Considering that the importance degrees of the load balancing target and the control target of the number of switching actions before and after the fault are possibly different under different power transmission network topology optimization scenes, the invention carries out linear weighting on a formula (7) and a formula (8), and finally constructs an objective function for obtaining power transmission network topology optimization and expresses the objective function as follows through a formula (9):
in the formula (9), the reaction mixture,、respectively representing function termsAndthe weight of (c).
According to the invention, the power change range of a 220kV transformer substation, the branch power operation limit value, the prevention of power back-off, node power balance, the simultaneous closing of transformer substation back-off disconnecting switches which are not allowed before and after the transmission network topology optimization is built, the limitation of the number of 110kV main transformers which are connected under an outgoing line and cannot be the same under the 110kV main transformers, 8 boundary constraint conditions of equipment fault states are fully considered, and the network topology optimization result output by the model is more reasonable. The following describes the 8 boundary constraint conditions considered by the power transmission network topology optimization model construction one by one:
1. power variation range constraint of 220kV transformer substation
Before and after network topology optimization, the power change of the 220kV transformer substation should not exceed a given range, namely:
in the formula (10), the first and second groups,representing the maximum of a 220kV substation, such as 220kV substation A in FIG. 2Allowing a power fluctuation rate;
in the formula (10), the first and second groups,main transformer branch circuit in 220kV transformer substation flows through before representing topological optimization of power transmission network(e.g., main transformer branches 1-4 in 220kV substation a in fig. 2);
in the formula (10), the first and second groups,main variable branch in 220kV transformer substation after transmission network is recovered to normal state through network topology optimization(e.g., main transformer branches 1-4 in 220kV substation a in fig. 2).
2. Branch power operating limit constraints
The branch power in the transmission network before and after topology optimization should not exceed a given operating limit, i.e.
In the formula (12), the first and second groups,indicating a faultMain transformer branch in lower power transmission networkActive power of (d);
in the formula (11), the reaction mixture,indicating the main transformer branch in the normal state of the transmission networkThe active load of (2);
in the formula (11), the reaction mixture,indicating that the transmission network flows through the main transformer branch circuit in a normal stateThe maximum allowed power of;
in the formula (12), the first and second groups,indicating fault condition of transmission networkFlows through the main transformer branchIs measured.
The formula (11) and the formula (12) are respectively used for limiting the value ranges of the branch power in the normal state and the fault state. E.g. branches 7-21 in fig. 2, which have active power in the normal stateShould be inIn the range of fault conditionskActive power ofShould be inWithin the range.
In addition, in the normal operation state of the power transmission network, after one line is switched from the operation state to the standby state, one line must be switched from the standby state to the operation state, that is, the number of branches of the line which is put into operation remains unchanged, and the constraint condition that the switching number remains unchanged can be expressed by the following formula (13):
in the formula (13), the first and second groups,representing the number of lines put into operation, and counting according to the initial line state;
3. Preventing power back-off constraints
With the gradual increase of the proportion of new energy accessed to the power grid, the situation of power back-off may occur at part of the nodes of the power transmission network, that is, the low-voltage nodes reversely supply power to the high-voltage nodes through the main transformer. Normally, the generated power of the new energy should be consumed as locally as possible to avoid power back-feeding, so it is necessary to limit the active flow direction of each main transformer (e.g. 220kV substation B connected to bus 2-5 in fig. 2) in the transmission network, i.e. to limit the active flow direction
The active flow of the main transformer in the transmission network (e.g. 220kV substation B connected to bus 2-5 in fig. 2) is shown from the main transformer to the load.
4. Node power balance constraints
In the invention, node power balance constraint, namely that active power flowing into and out of each bus and/or node is equal, namely that:
in the formulae (15) to (16),、in normal and fault states, respectivelyLower superior electric network injection nodeOr bus barActive power of (d);
5. Restriction that transformer substation's reverse-row disconnecting link does not allow simultaneous closure
For avoiding appearing the circulation, reducing short-circuit current, preventing that the accident scope enlarges, connect in same node to one end, the other end is connected in two switches of the different generating lines of same transformer substation, do not allow simultaneously closed, promptly:
indicating that the connection is at the node in the normal state of the gridAnd bus barThe on-off state of the knife switch in between,it is indicated that the knife switch is opened,indicating that the knife switch is closed;indicating that the connection is at the node in the normal state of the gridAnd bus barThe on-off state of the knife switch in between,it is indicated that the knife switch is opened,indicating that the knife switch is closed;
indicating fault condition of transmission networkLower connection at nodeAnd bus barThe on-off state of the knife switch in between,it is indicated that the knife switch is opened,indicating that the knife switch is closed;indicating fault condition of transmission networkLower connection at nodeAnd bus barThe on-off state of the knife switch in between,it is indicated that the knife switch is opened,indicating that the knife switch is closed.
For example, the two knife switches in branches 5-17 and 6-17 (connecting different busbars 5, 6 at the same node 17) shown in fig. 2 cannot be closed at the same time; the two switches in branches 5-18 and 6-18 cannot be closed simultaneously.
6. Outgoing line lower string 110kV main transformer number limitation
In order to limit the influence range of faults, the number of 110kV main transformers carried by outgoing lines of each 220kV station is generally not more than 3 (as shown in figure 2, the outgoing lines 4-21 are provided with C-E3 110kV transformers (main transformers) at most). To represent the constraint, virtual loads can be introduced at each bus of the 110kV substation (such as buses 7-16 in FIG. 2), and the virtual load valuesAre all 1, and the virtual load values of the rest buses or nodes are all 0. When a given lower string main transformer has the maximum number ofThen the constraint may use the virtual stream on the outgoing lineNot exceedingTo indicate that:
further explanation is made to equation (19) for the virtual flow of lines 4-21 in FIG. 2For example, to ensure that the line can only carry 3 110kV main transformers at most, i.e.Then virtual streamShould be between-3 and 3. When the outlet lines 4-21 are disconnectedThe outgoing line does not have any 110kV main transformer, so that the outgoing line has(ii) a When the outlet lines 4-21 are closed and put into operation, i.e. when they are closedAnd the outgoing line is provided with 3 110kV main transformers at most, so that。
The virtual flows into and out of each node or bus should be balanced, i.e.:
in the formula (20), the first and second groups of the compound,injecting node for superior power grid of power transmission network in normal stateOr bus bar(e.g., bus 1, 2, 3, etc. in fig. 2).
7.110kV main transformer power supply can not be the same
When a plurality of transformers or a plurality of buses exist in the 110kV transformer substation, the upper-level power supply of the transformer substation comes from different 220kV transformer substations so as to reduce the fault range and the power failure time, namely:
in the formula (21), the first and second groups,connected to the same bus in a 220kV transformer substationThe other ends of two disconnecting switches (such as a bus 5 in fig. 2) are respectively connected with one outgoing line (outgoing lines 17-23 and 18-24 in fig. 2), and the two outgoing lines supply power to the same 110kV transformer substation (such as a 110kV transformer substation G in fig. 2). For example, two switches in branches 5-17, 5-18 in fig. 2 cannot be closed at the same time, and two switches in branches 6-17, 6-18 cannot be closed at the same time.
8. Equipment fault condition setting constraints
When the main transformer branchWhen equipment (such as 220kV transformer substation and 110kV transformer substation) or line fails, the main transformer needs to be branchedThe forced open state, i.e. the switch in the corresponding branch should be forced open, is expressed as follows:
indicating that the grid is malfunctioningAfter, faultCorresponding branch circuitThe open state should be forced. For example, in fig. 2, if a 220kV substation a has a fault and the fault number is 1, thenIndicating a fault of "1", branches 1-4 are forced open (byOpening the switches in branches 1-4).
In summary, as shown in fig. 1, the power transmission network topology optimization method provided by the embodiment of the present invention includes three steps:
step S1, constructing a transmission network topology optimization model by taking load balance and minimum switching action times before and after transmission network topology optimization as optimization targets, and taking 220kV transformer substation power change range, branch power operation limit value, power reverse transmission prevention, node power balance, transformer substation reverse disconnecting link disallowing simultaneous closing, outgoing line lower string 110kV main transformer number limitation, 110kV main transformer power supply inequality, and equipment fault state as boundary constraint conditions of network topology optimization before and after topology optimization;
step S2, acquiring the operation data of the power transmission network in real time;
and step S3, inputting the acquired transmission network operation data into a transmission network topology optimization model, and calculating the network topology and the switch state after output optimization by the model through the formulas (1) - (22).
It should be understood that the above-described embodiments are merely preferred embodiments of the invention and the technical principles applied thereto. It will be understood by those skilled in the art that various modifications, equivalents, changes, and the like can be made to the present invention. However, such variations are within the scope of the invention as long as they do not depart from the spirit of the invention. In addition, certain terms used in the specification and claims of the present application are not limiting, but are used merely for convenience of description.
Claims (10)
1. A power transmission network topology optimization method is characterized by comprising the following steps:
the method comprises the steps that load balancing and the minimum number of switching actions before and after topological optimization of a power transmission network are taken as optimization targets, a power change range of a 220kV transformer substation before and after topological optimization, branch power operation limit values, power reverse transmission prevention, node power balance, simultaneous closing of reverse disconnecting switches of the transformer substation are not allowed, the number of 110kV main transformers connected under outgoing lines is limited, 110kV main transformer power supplies cannot be the same, and equipment fault states are set as boundary constraint conditions of network topological optimization, so that a power transmission network topological optimization model is constructed;
acquiring operation data of the power transmission network in real time;
inputting the acquired power transmission network operation data into the power transmission network topology optimization model, and calculating and outputting the optimized network topology and switch state by the model;
the objective function solved by the power transmission network topology optimization model is expressed by the following formula (1):
in the formula (1), the first and second groups,an objective function representing the power transmission network topology optimization model;
indicating a fault condition of the power transmission network,,the number of fault states of the power transmission network;
in the formula (2), the first and second groups,indicating the main transformer branch in the power transmission network in a normal stateThe load factor of (a) is,calculated by the following formula (3):
in the formula (3), the first and second groups,representing the main transformer branch circuit in the normal state of the power transmission networkThe active load of (2);
indicating that said grid is flowing through said main transformer branch under normal conditionsThe maximum allowed power of;
in the formula (2) and the formula (3)Representing the second in said transmission networkA node or aA strip bus;
representing each of said main transformer branches within said transmission networkThe average load rate of (a) is,calculated by the following formula (4):
in the formula (4), the first and second groups,representing the number of said primary transformers within said power transmission network;
in the formula (5), the first and second groups,indicating fault condition of transmission networkLower main transformer branchSwitch or knife state in;
2. The transmission network topology optimization method according to claim 1, wherein the transmission network operation data obtained in real time includes a current load of a 220kV substation in the high voltage transmission network, a rated active power, a bus number of the transmission network, a node number at two ends of an outgoing line, a rated active power of the outgoing line, a rated active power of a contact line between 110kV stations, an active load of each bus in a 110kV station, a node number at two ends of a disconnecting link or a switch, a set of equipment faults, and maximum allowable power of each main transformer branch before and after the faults.
3. The transmission network topology optimization method according to claim 1, wherein the 220kV substation power variation range constraint condition of transmission network topology optimization is expressed by the following equation (6):
in the formula (6), the first and second groups,representing the maximum allowable power fluctuation rate of the 220kV transformer substation;
representing that the current flows through a main transformer branch in the 220kV transformer substation before the topological optimization of the transmission networkThe active load of (2);
4. The grid topology optimization method according to claim 1, wherein the branch power operation limit constraints of grid topology optimization are expressed by the following equations (7) - (8):
in the formula (8), the first and second groups,indicating the fault stateThe main transformer branch in the lower power transmission networkActive power of (d);
5. The grid topology optimization method according to claim 1, wherein the power backtracking prevention constraint of grid topology optimization is expressed by the following equation (9):
6. The grid topology optimization method according to claim 1, wherein the node power balance constraints of grid topology optimization are expressed by the following equations (10) - (11):
in the formulae (10) to (11),、in normal and fault states, respectivelyLower superior electric network injection nodeOr bus barActive power of (d);
indicating the fault stateThe main transformer branch in the lower power transmission networkActive power of (d);
7. The method according to claim 1, wherein the constraint that the substation disconnecting link from the inverted transmission line for optimizing the transmission network topology does not allow simultaneous closing is as follows:
two disconnecting switches with one end connected to the same node and the other end connected to different buses of the same substation are not allowed to be closed at the same time.
8. The transmission network topology optimization method according to claim 1, wherein the limiting constraint condition of the number of the 110kV main transformers in the outgoing line lower string for transmission network topology optimization is as follows:
and the number of the 110kV main transformers which are connected in series under the outgoing line of each 220kV station of the 220kV transformer station is not more than 3.
9. The transmission network topology optimization method according to claim 1, wherein the constraint condition that the 110kV main transformer power supplies of transmission network topology optimization cannot be the same is:
when a plurality of transformers or a plurality of buses exist in the 110kV transformer substation, the 110kV transformer substation is powered by different 220kV transformer substations.
10. The grid topology optimization method according to claim 1, wherein the equipment fault status setting constraints of grid topology optimization are:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111156022.3A CN113595086B (en) | 2021-09-30 | 2021-09-30 | Power transmission network topology optimization method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111156022.3A CN113595086B (en) | 2021-09-30 | 2021-09-30 | Power transmission network topology optimization method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113595086A CN113595086A (en) | 2021-11-02 |
CN113595086B true CN113595086B (en) | 2022-01-04 |
Family
ID=78242634
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111156022.3A Active CN113595086B (en) | 2021-09-30 | 2021-09-30 | Power transmission network topology optimization method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113595086B (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101251836A (en) * | 2008-04-07 | 2008-08-27 | 昆明理工大学 | Transmission line turnaround plan optimizing method for recording power off hidden loss |
CN110350510A (en) * | 2019-05-23 | 2019-10-18 | 国网河南省电力公司郑州供电公司 | A kind of power distribution network service restoration method considering failure disturbance degree |
-
2021
- 2021-09-30 CN CN202111156022.3A patent/CN113595086B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101251836A (en) * | 2008-04-07 | 2008-08-27 | 昆明理工大学 | Transmission line turnaround plan optimizing method for recording power off hidden loss |
CN110350510A (en) * | 2019-05-23 | 2019-10-18 | 国网河南省电力公司郑州供电公司 | A kind of power distribution network service restoration method considering failure disturbance degree |
Also Published As
Publication number | Publication date |
---|---|
CN113595086A (en) | 2021-11-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Rahimi et al. | Evaluation of requirements for Volt/Var control and optimization function in distribution management systems | |
CN109449945B (en) | 10kV loop closing current constraint power distribution network transfer optimization method based on DG (distributed generation) adjustment | |
CN112260282B (en) | Active power distribution network transfer optimization method considering closed loop current constraint | |
CN107529678B (en) | Multi-objective optimization control method capable of expanding safety and stability constraint for alternating current and direct current power grid | |
CN111555266B (en) | Comprehensive planning method for distribution network automation system based on reliability constraint | |
CN106786423A (en) | Service restoration method after a kind of failure under power distribution network differential protection action | |
CN110929212B (en) | Online calculation method for searching weak thermal stability section of large power grid and formulating quota | |
Shen et al. | Review of service restoration methods in distribution networks | |
CN113595086B (en) | Power transmission network topology optimization method | |
Flottemesch et al. | Optimized energy exchange in primary distribution networks with DC links | |
CN207853185U (en) | The female simultaneous other system structure of substation | |
CN114050558B (en) | Control protection architecture of special parallel three-terminal direct current transmission system | |
RU2377630C1 (en) | Stabiliser of ac voltage with elements of protection and back-up (versions) | |
Kontos et al. | Effect of power flow control methods on the DC fault response of multi-terminal DC networks | |
Afifi et al. | Comparative study between single-objective and multi-objective optimization approaches for directional overcurrent relays coordination considering different fault locations | |
Wu et al. | Reliability assessment of AC/DC hybrid distribution network based on sequential monte carlo method | |
CN113872199A (en) | High-voltage transmission network topology optimization method | |
CN111404161B (en) | Intelligent electricity management and inter-station mutual-aid transfer system and method | |
Anitha et al. | DC Microgrid: A Review on Issues and Control | |
CN107069715A (en) | A kind of closed loop network switchs cyclization control method | |
CN106787123B (en) | 30 degree of phase angle difference distribution lines, which do not have a power failure, to be turned for breaker group sequence method | |
CN109888718B (en) | Direct current field equipment control system and method | |
Peng et al. | Implementing automatic transfer scheme in a main-tie-main configuration using IEC 61850 | |
CN221688317U (en) | Power supply system for factories | |
Liu et al. | A VSC-HVDC based flexible controller for improving the performance of looped electromagnetic networks in Guangzhou power grid |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |