CN113585273A - Earth-rock geological foundation pit forming construction method - Google Patents

Earth-rock geological foundation pit forming construction method Download PDF

Info

Publication number
CN113585273A
CN113585273A CN202110903742.5A CN202110903742A CN113585273A CN 113585273 A CN113585273 A CN 113585273A CN 202110903742 A CN202110903742 A CN 202110903742A CN 113585273 A CN113585273 A CN 113585273A
Authority
CN
China
Prior art keywords
foundation pit
hole
steel plate
die
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110903742.5A
Other languages
Chinese (zh)
Inventor
武海军
张振兴
张恩惠
王冠淇
沈峰
郇恒德
张泽林
李万麟
王冬冬
赵明
张景峰
王藉彬
赵山水
孙海鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huazhong Engineering Co ltd Of Cccc Tunnel Bureau
CCCC Tunnel Engineering Co Ltd
Original Assignee
Huazhong Engineering Co ltd Of Cccc Tunnel Bureau
CCCC Tunnel Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huazhong Engineering Co ltd Of Cccc Tunnel Bureau, CCCC Tunnel Engineering Co Ltd filed Critical Huazhong Engineering Co ltd Of Cccc Tunnel Bureau
Priority to CN202110903742.5A priority Critical patent/CN113585273A/en
Publication of CN113585273A publication Critical patent/CN113585273A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a forming construction method of an earthen stone geological foundation pit, which comprises the following steps: s1, slightly flattening the foundation pit position on the original ground, and placing a steel plate mold on the ground; s2, vertically inserting the breaking hammer into the ground through a hole of the steel plate die, digging a hole by using the breaking hammer until the depth of the hole meets the design requirement, and drawing out the breaking hammer; s3, inserting a hole plugging die into the pit dug by the breaking hammer; s4, vertically inserting and pulling out the breaking hammer according to the serial number, inserting the hole plugging die, and repeatedly operating until the hole plugging die is inserted into the last hole; s5, pulling out all hole plugging molds, and taking away the steel plate molds; and S6, connecting the holes in the foundation pit, and forming the foundation pit of the upright post of the protective fence. The invention accelerates the construction progress: compared with the traditional foundation pit excavation, the extrusion pore-forming of the crushing hammer head of the existing equipment is utilized, and resources are not wasted quickly. Meanwhile, the construction quality is ensured: the foundation pit quality is guaranteed, disturbance to peripheral rock soil is avoided, and disturbance of the bottom of the foundation pit is guaranteed.

Description

Earth-rock geological foundation pit forming construction method
Technical Field
The invention relates to the field of engineering construction, in particular to a method for forming and constructing a geological foundation pit with soil and stones.
Background
The foundation pit is an indispensable ring in the capital construction process, however, foundation pit excavation construction methods are various, and are in a thousand-odd-state, soil-rock-filled geological excavation is difficult in the foundation pit excavation process, particularly small foundation pits, national standard protective fence foundation pits are 60 cm long and 70cm high, manual excavation is affected by soil-rock-filled rocks, construction cannot be performed when shovels touch the rocks every time, the progress is slow, the efficiency is low, the span of the 12-36-degree upright columns of the protective fence is generally 1.15m, if the excavation foundation pit is enlarged, the foundation pit and the foundation pit are connected to form a ditch, however, the protective fence upright columns and the sill are backfilled after installation is completed, backfilling is performed, backfilling is difficult and heavy due to the influence of the sill, and the efficiency is low.
Disclosure of Invention
The invention provides a method for forming and constructing a geological foundation pit with included soil and stones, which aims to overcome the problems.
The invention comprises the following steps:
s1, leveling the position of the foundation pit on the original ground, and placing a steel plate mold on the leveled ground;
s2, vertically inserting the breaking hammer into the ground through a hole of the steel plate die, extruding the ground through the breaking hammer to form a hole, and drawing out the breaking hammer when the depth of the hole meets the design requirement; inserting a plugging hole die into the hole; repeating the operation until all holes in the design requirement are inserted by the hole plugging die;
s3, discharging all hole plugging molds, and taking away the steel plate molds;
and S4, connecting holes in the foundation pit according to design requirements, and forming the foundation pit.
Further, leveling the original ground in S1 includes: leveling the original ground by using a breaking hammer according to the measured position until the original ground is leveled to meet the excavation requirement of the foundation pit and the installation requirement of the steel plate mold;
further, the steel plate die arrangement requirement includes: the steel plate mould is arranged at the measuring position and is stable on the ground, namely the steel plate mould does not move.
Further, the steel plate die is manufactured by punching holes on the steel plate according to design requirements.
Further, the hole plugging die comprises: the hole blocking die comprises a cone body and annular metal, wherein the lower end of the hole blocking die is the cone body, the cone body is formed by welding two sections of steel pipes with the same diameter as the breaking hammer, and the annular metal is welded at the upper end of the cone body.
Furthermore, after the steel plate die and the hole plugging die are taken away, the periphery of the foundation pit is manually cleaned until the periphery of the foundation pit is vertically arranged to meet the design requirements.
The invention accelerates the construction progress: compared with traditional foundation pit excavation, 0.6 x 0.6m foundation pit excavation is difficult, and no matter how far the excavation is performed with equipment, the excavation progress is slow because the excavation soil and stone inclusion geology seems anecdotal, and the extrusion pore-forming of the broken hammer head of the existing equipment is not only quick but also is not wasted resources. Meanwhile, the construction quality is ensured: the breaking hammer is used for digging the pit, namely the pit is formed by extrusion, so that the quality of the foundation pit is guaranteed while the requirement of design specifications is met, the disturbance to the peripheral rock soil and the bottom of the foundation pit is not caused and guaranteed like the traditional foundation pit excavation.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings needed to be used in the description of the embodiments or the prior art will be briefly introduced below, and it is obvious that the drawings in the following description are some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a flow chart of the present invention;
FIG. 2 is a block diagram of the breaking hammer of the present invention;
FIG. 3 is a structural diagram of a steel plate mold according to the present invention;
fig. 4 is a view showing the structure of the plugging hole die of the present invention.
The reference numbers illustrate:
1. a breaking hammer; 2. a steel plate mold; 21. a diagonal first hole; 22. a diagonal second hole; 3. and (4) a hole plugging die.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
As shown in fig. 1, the present invention includes:
s1, leveling the position of the foundation pit on the original ground, and placing the steel plate mold 2 on the leveled ground;
particularly, the original ground is level and smooth, according to the position of measuring the unwrapping wire, levels original ground with quartering hammer 1, and the level and smooth specification in original ground must satisfy the foundation ditch excavation demand, also must satisfy the steel sheet mould and settle. The setting of the steel plate mold 2 includes: after the original ground is leveled, the steel plate die 2 is arranged according to the position of the measurement paying-off, and the steel plate die 2 is closely matched and stable with the original ground.
S2, vertically inserting the breaking hammer 1 into the ground through the hole of the steel plate die 2, extruding the ground through the breaking hammer 1 to form a hole, and drawing out the breaking hammer 1 when the depth of the hole meets the design requirement; inserting a plugging hole die into the hole; repeating the operation until all holes in the design requirement are inserted by the hole plugging die;
particularly, the quartering hammer inserts the first hole 21 of diagonal of steel sheet mould, and quartering hammer does not collide steel sheet mould 2 all around as far as possible when inserting, prevents that the foundation ditch from shifting, and the degree of depth targets in place the back, and quartering hammer 1 rocks all around gently, prevents that quartering hammer 1 from extracting and takes earth all around out, damages the foundation ditch shape, and construction at every turn all needs rock all around gently. The hole blocking die 3 is formed by welding steel pipes with the same diameter as the breaking hammer, the lower end of the hole blocking die is a cone, and the upper end of the hole blocking die is welded with annular metal, so that the hole blocking die is convenient to place. Every hole is punched and is all stopped up with stifled hole mould 3, prevents that next hole is bayonet from extruding the closely knit preceding hole, what number of stifled hole mould 3 of how many holes are needed to steel sheet mould 2. The breaking hammer 1 is inserted into the diagonal second holes 22, the diagonal second holes 22 are located on a diagonal line, and the breaking hammer jacks are sequentially and symmetrically arranged, so that the accuracy of the position of the foundation pit is maintained, and the foundation pit cannot be deviated.
S3, pulling out all the hole plugging molds 3, and taking the steel plate molds 2 away;
particularly, after all holes are inserted and beaten, all hole plugging molds 3 are extracted, the hole plugging molds 3 are also extracted according to the inserting and beating sequence, the manual work is extracted, the holes are forcefully shaken all around before being extracted, the holes are prevented from being adhered to all around soil, and the smooth and smooth hole diameter is ensured. And taking away the steel plate die 2, and after the hole plugging die 3 is pulled out, taking away the steel plate die 2, and placing the steel plate die stably for next recycling.
And S4, connecting holes in the foundation pit according to design requirements, and forming the foundation pit.
Particularly, clear up the mud rib in the foundation ditch, steel sheet mould 2 and stifled hole mould 3 take the back away, and the foundation ditch forms a plurality of cellular structure that have the hole, shovels cellular structure through the manual work, and the foundation ditch is perpendicular clearance all around and targets in place, guarantees that the foundation ditch hangs down the straightness and satisfies the designing requirement all around, prevents to become centrum foundation ditch.
Has the advantages that:
1. accelerating the construction progress: compared with traditional foundation pit excavation, 0.6 x 0.6m foundation pit excavation is difficult, and no matter how far the excavation is performed with equipment, the excavation progress is slow because the excavation soil and stone inclusion geology seems anecdotal, and the extrusion pore-forming of the broken hammer head of the existing equipment is not only quick but also is not wasted resources.
2. The construction quality is ensured: adopt the quartering hammer to dig the hole, extrude into the hole promptly, both satisfied design standard's requirement, guarantee foundation ditch quality again, can not cause the disturbance and guarantee the disturbance of foundation ditch bottom to peripheral ground like traditional foundation ditch excavation yet.
Finally, it should be noted that: the above embodiments are only used to illustrate the technical solution of the present invention, and not to limit the same; while the invention has been described in detail and with reference to the foregoing embodiments, it will be understood by those skilled in the art that: the technical solutions described in the foregoing embodiments may still be modified, or some or all of the technical features may be equivalently replaced; and the modifications or the substitutions do not make the essence of the corresponding technical solutions depart from the scope of the technical solutions of the embodiments of the present invention.

Claims (5)

1. A forming construction method for a soil-rock geological foundation pit is characterized by comprising the following steps:
s1, leveling the position of the foundation pit on the original ground, and placing a steel plate mold (2) on the leveled ground;
s2, vertically inserting the breaking hammer (1) into the ground through a hole of the steel plate die (2), extruding the ground through the breaking hammer (1) to form a hole, and drawing out the breaking hammer (1) when the depth of the hole meets the design requirement; inserting a plugging hole die (3) into the hole; repeatedly operating until all holes in the design requirement are inserted by the hole plugging die (3);
s3, pulling out all the hole plugging molds (3), and taking the steel plate molds (2) away;
and S4, connecting the holes in the foundation pit according to design requirements, and forming the foundation pit.
2. The method for forming and constructing a soil-filled stone geological foundation pit according to claim 1, wherein the step of leveling the original ground in S1 comprises the following steps: according to the measured position, leveling the original ground by using a breaking hammer (1) until the original ground is leveled, and meeting the foundation pit excavation requirement and the steel plate mold (2) arrangement requirement;
the steel plate mould (2) arrangement requirement comprises: the steel plate die (2) is arranged at the measuring position, and the steel plate die (2) is stable on the ground, namely the steel plate die (2) does not move on the ground.
3. The method for forming and constructing an earthwork pit according to claim 1, wherein the steel plate mold (2) is formed by punching holes on a steel plate according to design requirements.
4. The method for forming and constructing a soil-filled stone geological foundation pit according to claim 1, wherein the hole blocking mould (3) comprises: the hole blocking die comprises a cone body and annular metal, wherein the lower end of the hole blocking die (3) is the cone body, the cone body is formed by welding two sections of steel pipes with the same diameter as that of the breaking hammer (1), and the annular metal is welded at the upper end of the cone body.
5. The method for forming and constructing the soil-filled stone geological foundation pit according to claim 1, characterized in that after the steel plate mold (2) and the hole plugging mold (3) are taken away, the periphery of the foundation pit is manually cleaned until the verticality of the periphery of the foundation pit meets the design requirements.
CN202110903742.5A 2021-08-06 2021-08-06 Earth-rock geological foundation pit forming construction method Pending CN113585273A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110903742.5A CN113585273A (en) 2021-08-06 2021-08-06 Earth-rock geological foundation pit forming construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110903742.5A CN113585273A (en) 2021-08-06 2021-08-06 Earth-rock geological foundation pit forming construction method

Publications (1)

Publication Number Publication Date
CN113585273A true CN113585273A (en) 2021-11-02

Family

ID=78255932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110903742.5A Pending CN113585273A (en) 2021-08-06 2021-08-06 Earth-rock geological foundation pit forming construction method

Country Status (1)

Country Link
CN (1) CN113585273A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB9914111D0 (en) * 1999-05-18 1999-08-18 Murray Thomas G A tool
WO2012099288A1 (en) * 2011-01-21 2012-07-26 주식회사 거원엔지니어링 Reusable and reinforceable soil retaining wall and method of constructing same
CN111119191A (en) * 2019-12-18 2020-05-08 中建三局基础设施建设投资有限公司 Rock foundation pit guide hole type non-blasting excavation method
WO2020173100A1 (en) * 2019-02-26 2020-09-03 济南轨道交通集团有限公司 Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN111733827A (en) * 2020-06-29 2020-10-02 中铁六局集团天津铁路建设有限公司 Station yard deep foundation pit protection construction method under adjacent high-speed rail complex environment silt geology
CN213836676U (en) * 2020-12-01 2021-07-30 中交一航局第三工程有限公司 Foundation ditch excavation steel sleeve supporting device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB9914111D0 (en) * 1999-05-18 1999-08-18 Murray Thomas G A tool
WO2012099288A1 (en) * 2011-01-21 2012-07-26 주식회사 거원엔지니어링 Reusable and reinforceable soil retaining wall and method of constructing same
WO2020173100A1 (en) * 2019-02-26 2020-09-03 济南轨道交通集团有限公司 Reinforcement apparatus and construction method for local freezing reinforcement of deep foundation pit in water-rich sand gravel stratum
CN111119191A (en) * 2019-12-18 2020-05-08 中建三局基础设施建设投资有限公司 Rock foundation pit guide hole type non-blasting excavation method
CN111733827A (en) * 2020-06-29 2020-10-02 中铁六局集团天津铁路建设有限公司 Station yard deep foundation pit protection construction method under adjacent high-speed rail complex environment silt geology
CN213836676U (en) * 2020-12-01 2021-07-30 中交一航局第三工程有限公司 Foundation ditch excavation steel sleeve supporting device

Similar Documents

Publication Publication Date Title
CN104947690B (en) Grooving construction method for embedding underground continuous wall into rock
KR101777176B1 (en) Construction method of cast-in-placed-pile using steel pipes having different shapes to each other
CN106522242A (en) Foundation pit supporting system for subsurface structure close to soft ground stratum and construction method of foundation pit supporting system
CN110685698B (en) Climbing reverse construction method for newly building large-section tunnel in existing cavern side direction
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN112030956A (en) Karst stratum bored pile construction method
JPS62288218A (en) Settlement caisson
CN108222054B (en) Tower-crane foundation structure and its construction method
CN113074003A (en) Method for inhibiting deformation of small-clear-distance tunnel in argillaceous sandstone stratum
CN111877321A (en) Cast-in-place pile applied to underground reinforced concrete structure and construction method thereof
CN210797603U (en) Pumping well shaft
CN113585273A (en) Earth-rock geological foundation pit forming construction method
CN110030004B (en) Method for excavating barrier lake drainage tunnel
CN215482984U (en) Bottom die sand box capable of being rapidly disassembled
CN111877352B (en) Construction method for excavating fully weathered sandstone high slope
CN208604588U (en) Underground power house partition wall rock mass pays protection structure and underground power house partition wall rock mass structure in advance
CN210946533U (en) A closed channel structure for open cut construction
CN110409474B (en) Pipe well dewatering well arranged at bottom of underground diaphragm wall
CN109268030B (en) Multistage sleeve arch structure for tunnel portal support, pipe shed sleeve arch structure and construction method of pipe shed sleeve arch structure
KR102579002B1 (en) Method of demolition of underground exterior walls
CN212405120U (en) Bored concrete pile of construction is executed to underground reinforced concrete structure department
CN109469087A (en) Cesspool strengthening of foundation system and its construction method in a kind of industrial premises room
CN103337719A (en) High-frequency interference protection grounding electrode and laying method thereof
CN212956513U (en) Precast concrete block for hole digging pile retaining wall and manual hole digging pile retaining wall mounting structure
CN2199240Y (en) Building basic technique foundation pit inclined guard post

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211102

RJ01 Rejection of invention patent application after publication