CN113502988A - Double-layer waterproof gutter system and construction method thereof - Google Patents

Double-layer waterproof gutter system and construction method thereof Download PDF

Info

Publication number
CN113502988A
CN113502988A CN202110834646.XA CN202110834646A CN113502988A CN 113502988 A CN113502988 A CN 113502988A CN 202110834646 A CN202110834646 A CN 202110834646A CN 113502988 A CN113502988 A CN 113502988A
Authority
CN
China
Prior art keywords
gutter
coiled material
waterproof coiled
plate
additional
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110834646.XA
Other languages
Chinese (zh)
Other versions
CN113502988B (en
Inventor
刘宇伟
陈俊臣
司兆峰
肖明
高伟
卢兴辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Center International Group Co Ltd
Original Assignee
Center International Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Center International Group Co Ltd filed Critical Center International Group Co Ltd
Priority to CN202110834646.XA priority Critical patent/CN113502988B/en
Publication of CN113502988A publication Critical patent/CN113502988A/en
Application granted granted Critical
Publication of CN113502988B publication Critical patent/CN113502988B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage; Sky-lights
    • E04D13/04Roof drainage; Drainage fittings in flat roofs, balconies or the like
    • E04D13/064Gutters
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage; Sky-lights
    • E04D13/16Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure
    • E04D13/1687Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure the insulating material having provisions for roof drainage
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Abstract

The invention discloses a double-layer waterproof gutter system and a construction method thereof, wherein the double-layer waterproof gutter system comprises a gutter plate, a gutter waterproof coiled material and a roof waterproof coiled material, the gutter waterproof coiled material and the roof waterproof coiled material form a whole, the gutter waterproof coiled material is laid on a bottom support and a side wall support in a gutter, the cross section of the gutter plate is consistent with that of the gutter, the gutter plate is laid in a manner of being attached to the gutter waterproof coiled material, gutter pressing parts are further arranged at the upper ends of the two side wall supports of the gutter, the gutter plate, the roof waterproof coiled material and the side wall support are fixed through the gutter pressing parts, an additional waterproof coiled material is further arranged on the roof waterproof coiled material at the upper ends of the side wall supports, the additional waterproof coiled material spans over the upper ends of the gutter plate and then extends downwards into the gutter along the outer side surfaces of the gutter pressing parts, and the additional waterproof coiled material is fixed with the gutter pressing parts, the roof waterproof coiled material and the side wall support through connecting parts. Before the gutter plate is installed, the hanging bracket crossing the top of the gutter is welded, so that the influence on other materials below the gutter plate in the welding process of the gutter plate is effectively avoided.

Description

Double-layer waterproof gutter system and construction method thereof
Technical Field
The invention relates to the field of metal roof maintenance systems, in particular to a double-layer waterproof gutter system and a construction method thereof.
Background
In recent years, metal maintenance system roofs are favored by more and more owners and investors, and are widely applied to the fields of industrial buildings and public buildings in view of the advantages of low cost, short construction period, wide application range of building appearance and the like, and building waterproofing always pursues an optimal solution, and buildings adopt different roof waterproofing grades according to different application occasions and service lives.
According to projects above domestic medium-scale in recent years, the waterproof grade of the metal roof is designed to be the first-level roof waterproof grade, namely the roof is provided with two waterproof fortifications. According to current metal roofing construction technology, the combination commonly used is upper metal roof boarding + lower floor TPO polymer waterproofing membrane (TPO for short hereafter), and two kinds of materials are soft one just rigid intercoupling, and the perfect one-level roofing waterproof requirement of satisfying. But still have deficiencies from the standpoint of gutter systems alone. Fig. 1 is a conventional gutter system, and fig. 2 is a partial enlarged node diagram, which mainly has the following two disadvantages:
first, there is a drainage defect at the junction of the roofing system and the gutter system. Roofing TPO and gutter system TPO should realize whole linking up, and the gutter board exists in gutter TPO top alone again, and according to the drainage principle, inside roofing system rivers should flow into the gutter, because of gutter system and roofing system TPO do not carry out the structural connection, can't guarantee that the rivers get into the gutter system completely.
Secondly, the metal roof gutter system is mostly made of austenite 304 or austenite 316 stainless steel materials, and is formed in a factory according to actual sizes and then is spliced and welded on site. The normal construction flow is that the gutter is put in place and then is spliced and welded, the argon arc welding process can generate high temperature of more than 2000 ℃, and TPO is melted and deformed at the temperature of 700-800 ℃. How to control the integrity of TPO in the welding process of the gutter plate is taken as the control key point of the roof waterproof performance.
Disclosure of Invention
Aiming at the defects of the prior art, the invention provides a double-layer waterproof gutter system and a construction method thereof, which solve the drainage problem existing in the connection of a roof system and a stainless steel gutter plate and the adverse effect on a waterproof coiled material below the gutter plate during welding of the gutter plate, ensure that water flow is completely drained into a gutter, and effectively avoid the adverse effect on the waterproof coiled material caused by the welding of the stainless steel plate.
The invention adopts the following technical scheme:
in one aspect, the invention provides a double-layer waterproof gutter system, which comprises a gutter plate, a gutter waterproof roll and a roof waterproof roll, wherein the gutter waterproof roll and the roof waterproof roll form a whole, the gutter waterproof roll is laid on a bottom support and a side wall support in a gutter, the gutter plate is consistent with the cross section of the gutter and is laid by being attached to the inner side surface of the gutter waterproof roll, gutter pressing parts are further arranged at the upper ends of the two side wall supports of the gutter, the gutter pressing parts are used for fixing the gutter plate, the roof waterproof roll and the side wall support together, an additional waterproof roll is further arranged on the roof waterproof roll at the upper end of the side wall support, after the additional waterproof roll crosses the upper end of the gutter plate, the additional waterproof roll extends downwards into the gutter along the outer side surface of the gutter pressing part, and the gutter pressing parts are connected with the additional waterproof roll through connecting parts, The roof waterproof roll and the side wall are supported and fixed together.
Further, the top of the gutter plate is provided with a folded edge which is bent towards the inner side of the gutter plate in a right angle, and the folded edge is flush with the upper end of the side wall support; the cross section of the gutter casting die is of an L-shaped panel structure, the long edge of the gutter casting die covers the roof waterproof coiled material at the top of the side wall support and the folded edge of the gutter plate, and the short edge of the gutter casting die extends towards the bottom of the gutter.
Further preferably, the additional waterproof roll completely covers the gutter pressing piece, one end of the additional waterproof roll extends out of the end part of the gutter pressing piece and is fixed with the roof waterproof roll through welding, the other end of the additional waterproof roll is attached to the short edge of the gutter pressing piece, and the additional waterproof roll is fixed with the short edge of the gutter pressing piece through a connecting piece.
Furthermore, a gutter edge-closing plate is attached to the short edge of the gutter pressing piece, a drain hole is formed in the gutter edge-closing plate, the upper end and the lower end of the gutter edge-closing plate extend out of the gutter pressing piece, and the gutter edge-closing plate, the additional waterproof coiled material and the gutter pressing piece are fixed together through a connecting piece.
On the other hand, the invention also provides a construction method of the double-layer waterproof gutter system, which comprises the following steps:
step 1, paving waterproof coiled materials on a gutter and roofs on two sides of the gutter;
step 2, arranging a plurality of hanging brackets at intervals at the upper ends of the supports on the two side walls of the gutter, and arranging protective rubber pads between the two ends of each hanging bracket and the supports on the two side walls of the gutter;
step 3, placing the primarily assembled gutter plates on a suspension bracket, and forming a whole after splicing and welding;
step 4, arranging a plurality of gate-type suspension brackets which are supported by spanning two side walls of the gutter above the finished gutter, wherein the plurality of gate-type suspension brackets are arranged at intervals along the length direction of the gutter;
step 5, lifting the welded gutter plate in the step 4 integrally through a lifting cross rod connected with the upper end of the gutter plate and a lifting tool arranged on the door type suspension bracket, taking out the suspended bracket, and then dropping the gutter plate into the gutter to enable the gutter plate to be attached to the supports at the two side walls and the bottom of the gutter;
step 6, mounting a gutter pressing piece at the upper end of the side wall support, pressing and fixing the gutter plate by the gutter pressing piece, covering the gutter pressing piece with an additional waterproof coiled material, welding one end of the additional waterproof coiled material with the roof waterproof coiled material, and extending the other end of the additional waterproof coiled material into the gutter;
and 7, supporting and fixing the additional waterproof coiled material, the gutter casting die, the roof waterproof coiled material and the side wall together through a connecting piece.
The construction method further comprises the following steps:
and 8, vertically attaching the additional waterproof coiled material in the step 6 to the side surface of the gutter pressing piece, attaching the gutter edge-closing piece and the additional waterproof coiled material in the gutter, and fixing the gutter edge-closing plate, the additional waterproof coiled material and the gutter pressing piece together through a connecting piece.
The technical scheme of the invention has the following advantages:
A. the invention adds additional waterproof coiled materials on the roof waterproof coiled materials at two sides of the gutter, the additional waterproof coiled materials solve the problems of continuity and effectiveness of the first-level roof waterproof coiled materials, in a roof system, no matter the roof waterproof coiled materials are metal plates at the upper layer or waterproof coiled materials at the lower layer, water flow of the roof waterproof coiled materials is completely drained into the gutter and discharged through a rainwater hopper.
B. When the gutter is constructed, the gutter plates are placed on the suspension brackets for suspension welding after splicing, and in the welding process of the gutter plates, the suspension brackets, the isolation welding and the integral falling mode are adopted, so that the gutter plates can be effectively prevented from contacting with gutter waterproof coiled materials laid at the bottom of the gutter in the welding process, the performance requirements of the gutter plates as waterproof materials are met, and the influence on other materials below the gutter plates in the welding process is effectively avoided, such as: the heat insulating material, the steam insulating material and other materials influenced by high temperature ensure the integrity and effectiveness of the waterproof coiled material.
Drawings
In order to more clearly illustrate the embodiments of the present invention, the drawings which are needed to be used in the embodiments will be briefly described below, and it is apparent that the drawings in the following description are some embodiments of the present invention, and other drawings can be obtained from the drawings without inventive labor to those skilled in the art.
FIG. 1 is a front view of a prior art conventional gutter approach;
FIG. 2 is an enlarged view of a portion of the prior art gutter approach of FIG. 1;
FIG. 3 is an elevation view of a gutter embodiment provided by the present invention;
FIG. 4 is an enlarged view of a portion of the gutter embodiment of FIG. 3;
FIG. 5 is a schematic view of a suspended bracket fabricated before welding the roof gutter panel according to the present invention;
fig. 6 is a schematic view of the present invention using a suspension bracket to hoist a gutter plate.
The labels in the figure are as follows:
1-gutter waterproof coiled material; 2-roof waterproof coiled material; 3-gutter plate; 4-gutter casting die
5-a connector; 6-gutter edge-closing piece; 7-additional waterproof coiled material; 8-protective rubber pad
9-hanging brackets; 10-a vertical support; 11-lifting the cross bar; 12-bottom leg 13-lateral hanger; 14-triangular support; 15-a lifting tool; 16-base support
17-side wall support.
Detailed Description
The technical solutions of the present invention will be described clearly and completely with reference to the accompanying drawings, and it should be understood that the described embodiments are some, but not all embodiments of the present invention. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; the connection can be mechanical connection or electrical connection; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
As shown in fig. 3 to 6, the present invention provides a double-layer waterproof gutter system, comprising a gutter plate 3, a gutter waterproof roll 1 and a roof waterproof roll 2, wherein the gutter waterproof roll 1 and the roof waterproof roll 2 form a whole, i.e. the gutter waterproof roll 1 and the roof waterproof roll 2 are the same waterproof roll, the gutter is formed by welding a bottom support 16 and two side wall supports 17, the gutter waterproof roll 1 is laid on the bottom surface of the bottom support 16 and two inner side surfaces of the side wall supports 17 in the gutter, the cross section of the gutter plate 3 is consistent with that of the gutter and is laid by being attached to the inner side surfaces of the gutter waterproof roll 1, gutter press parts 4 are further provided at the upper ends of the two side wall supports 17 of the gutter, the gutter press parts 4 fix the gutter plate 3, the roof waterproof roll 2 and the side wall supports 17 together, an additional waterproof roll 7 is further provided on the roof waterproof roll 2 at the upper ends of the side wall supports 17, the additional waterproof coiled material 7 strides over the upper end of the gutter plate 3 and then extends downwards into the gutter along the outer side surface of the gutter pressing part 4, namely, the additional waterproof coiled material 7 strides over the gap between the roof waterproof coiled material 2 and the gutter plate 3 to completely cover the gap, and the additional waterproof coiled material 7 is fixed with the gutter pressing part 4, the roof waterproof coiled material 2 and the side wall support 17 through the connecting piece 5.
Here, the top of the gutter plate 3 is formed with a folded edge 31 folded at a right angle toward the inside thereof, as shown in fig. 4, the folded edge 31 being kept flush with the side wall support upper end 17; the cross section of the gutter casting die 4 is of an L-shaped panel structure, the long side of the die covers the roof waterproof coiled material 2 at the top of the side wall support 17 and the folded edge 31 of the gutter plate 3, and the short side of the die is positioned in the gutter and extends towards the bottom of the gutter. The gutter pressing member 4 is positioned at the upper portion of the gutter to fix the upper portion of the gutter plate 3.
The additional waterproof coiled material 7 completely covers the gutter pressing piece 4, one end of the additional waterproof coiled material 7 is fixed with the roof waterproof coiled material 2 through welding, and the other end of the additional waterproof coiled material is fixed with the short edge of the gutter pressing piece 4 through the connecting piece 5. According to the invention, the additional waterproof coiled material 7 is laid above the roof waterproof coiled material, the two parts are overlapped and welded, meanwhile, the additional waterproof coiled material 7 spans the gap between the roof waterproof coiled material 2 and the gutter plate 3 and extends into the gutter, and by increasing the waterproof connection construction measure between the roof system and the gutter, the water flow can be completely drained into the gutter, and the waterproof continuity of the waterproof coiled material is realized.
In addition, a gutter edge-closing plate 6 is attached to the short side of the gutter pressing piece 4, a drain hole is formed in the gutter edge-closing plate 6, the upper end and the lower end of the gutter edge-closing plate extend out of the gutter pressing piece 4, and the gutter edge-closing plate 6, the additional waterproof roll 7 and the gutter pressing piece 4 are fixed together through a connecting piece 5.
As shown in fig. 5 and 6, in order to avoid damage to materials such as waterproof coiled materials or other insulating layers below the gutter plates when the gutter plates are welded after being spliced, the invention also provides a construction method of the double-layer waterproof gutter system, which comprises the following steps:
step 1, paving waterproof coiled materials on a gutter and roofs on two sides of the gutter;
step 2, a plurality of hanging brackets 9 arranged at intervals are arranged at the upper ends of the supports on the two side walls of the gutter, and protective rubber pads 8 are arranged between the two ends of each hanging bracket 9 and the supports 17 on the two side walls of the gutter respectively;
step 3, placing the primarily assembled gutter plates 3 on a suspension bracket 9, and forming a whole after splicing and welding;
step 4, arranging a plurality of gate-type suspension brackets which cross two side wall supports 17 of the gutter above the finished gutter, wherein the gate-type suspension brackets are arranged at intervals along the length direction of the gutter;
step 5, lifting the welded gutter plate 3 in the step 4 integrally through a lifting cross rod 11 connected with the upper end of the gutter plate 3 and a lifting tool 15 arranged on a portal type suspension bracket, taking out the suspension bracket 9, and then dropping the gutter plate 3 into the gutter to enable the gutter plate to be attached to two side wall supports 17 and a bottom support 16 of the gutter;
step 6, mounting the gutter pressing piece 4 at the upper end of the side wall support 17, pressing and fixing the gutter plate 3 by the gutter pressing piece 4, covering the gutter pressing piece 4 with the additional waterproof roll 7, welding one end of the additional waterproof roll 7 with the roof waterproof roll 2, and extending the other end of the additional waterproof roll into the gutter;
and 7, fixing the additional waterproof roll 7, the gutter casting die 4, the roof waterproof roll 2 and the side wall support 17 together through the connecting piece 5.
And 8, vertically attaching the additional waterproof coiled material 7 in the step 6 to the side surface of the gutter pressing piece 4, attaching the gutter edge-closing piece 6 to the additional waterproof coiled material 7 in the gutter, and fixing the gutter edge-closing plate 6, the additional waterproof coiled material 7 and the gutter pressing piece 4 together through the connecting piece 5.
Considering that the transportation and the loading and unloading are convenient, a finished product gutter plate 3 processing factory can be generally processed into a length of 1.5m, 3m or 4m, the field gutter is usually longer in length, the preliminary splicing of the gutter plates 3 can be carried out on the ground in advance, the roof welding operation is reduced to the maximum extent, and the ground splicing is carried out as much as possible under the condition of meeting the hoisting requirement.
After the gutter waterproof roll 1 and the roof waterproof roll 2 are installed, the gutter plate 3 is installed in the gutter. The specific installation is described below in conjunction with fig. 5 and 6: before the roof splicing operation, according to the figure 5, the hanging bracket 9 of the gutter plate 3 is manufactured, and a 50mm square tube is transversely arranged above the gutter at a distance of 4.5 meters. The gutter plate 3 which has been preliminarily spliced is suspended above the hanging bracket 9 for welding connection. As shown in fig. 6, the portal suspension support is made of a square tube of 50mm, the single portal suspension support is composed of 2 bottom support legs 12, 2 vertical supports 10, 1 transverse hanger 13, 2 triangular supports 14 and 1 lifting cross bar 11, the length of the bottom support leg 12 is 500mm, and the height of the portal suspension support is determined according to the height of a gutter, which is generally 1 m to 1.2 m. The gate-type suspends a set of support interval 4m in midair, utilize 3 both sides anti-water dog-ears of gutter board as the stress point, carry out the whole promotion of whole gutter through promoting horizontal pole 11 cooperation lifting means 15 (optionally with hand-drive block), take out the unsettled bracket 9 in bottom after promoting to 100mm height, fall into the gutter inslot with 3 whole gutter boards, the gate-type suspends the support in midair after gutter board 3 takes one's place, and then accomplished gutter board 3 installation, carry out follow-up gutter casting die 4, additional waterproofing membrane 7 and gutter edge-folding piece 6's installation. This mode has effectively been solved because of the influence of 3 welding of stainless steel gutter plate to gutter waterproofing membrane 1 destruction, can effectively avoid among the welding process and gutter waterproofing membrane 1 that lays bottom the gutter to contact to guaranteed its performance requirement as waterproof material, also can effectively avoid in gutter plate welding process to the influence of other materials in its below, for example: the heat insulating material, the steam insulating material and other materials influenced by high temperature ensure the integrity and effectiveness of the waterproof coiled material.
And then installing gutter pressing parts 4 on two sides of the gutter plate to fix the gutter plate 3, extending 150mm positions along the gutter edge towards the roof direction, additionally welding an additional waterproof coiled material with the width of 250mm along the length direction of the gutter, performing hot air welding, wherein the width of a welding line is 80-120 mm, enabling the other end of the additional waterproof coiled material to enter the gutter along the upper part of the gutter pressing part, fixing the additional waterproof coiled material 7 above the additional waterproof coiled material 7 through a roof fixing support or a fixing pressing sheet, installing a gutter edge-receiving part 6 after the roof plate is installed, attaching the additional waterproof coiled material 7 to the vertical surface of the gutter pressing part 4, and fixing through self-tapping screws. Through the steps, on the basis of ensuring double-layer waterproofing of the roof system and the gutter system, the continuity of drainage between the roof and the gutter can be realized, the additional waterproof coiled material can be effectively utilized to form drainage closure between the roof system and the gutter system, and the problem of waterproof continuity is solved.
The specific dimensions or ranges of dimensions given above by way of example do not limit the scope of protection of the invention.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And obvious variations or modifications therefrom are intended to be within the scope of the invention.

Claims (6)

1. The utility model provides a double-deck waterproof gutter system, includes gutter board (3), gutter waterproofing membrane (1) and roofing waterproofing membrane (2), gutter waterproofing membrane (1) with roofing waterproofing membrane (2) form a whole, gutter waterproofing membrane (1) is laid on bottom sprag (16) and lateral wall support (17) in the gutter, gutter board (3) with the gutter cross section is unanimous, and the laminating gutter waterproofing membrane (1) is laid, the upper end of the both sides wall support (17) of gutter still is equipped with gutter casting die (4), gutter casting die (4) will gutter board (3), roofing waterproofing membrane (2) and lateral wall support (17) are fixed together, its characterized in that is located still be equipped with additional waterproofing membrane (7) on roofing waterproofing membrane (2) of lateral wall support (17) upper end, additional waterproofing membrane (7) stride across behind gutter board (3) upper end, and the additional waterproof coiled material (7) extends downwards into the gutter along the outer side surface of the gutter pressing piece (4), and is fixed with the gutter pressing piece (4), the roof waterproof coiled material (2) and the side wall support (17) through a connecting piece (5).
2. The double-deck watertight gutter system according to claim 1, characterized in that the top of the gutter plate (3) is formed with a hem (31) bent at a right angle to the inside thereof, the hem (31) remaining flush with the side wall support upper end (17); the cross section of the gutter casting die (4) is of an L-shaped panel structure, the long side of the gutter casting die covers the roof waterproof roll (2) at the top of the side wall support (17) and the folded edge (31) of the gutter plate (3), and the short side of the gutter casting die extends towards the bottom of the gutter.
3. A double-layer waterproofing gutter system according to claim 2, wherein the additional waterproofing membrane (7) completely covers the gutter pressing member (4), one end of which protrudes from the end of the gutter pressing member (4) and is fixed to the roofing waterproofing membrane (2) by welding, and the other end of which is attached to the short side of the gutter pressing member (4), and the additional waterproofing membrane (7) is fixed to the short side of the gutter pressing member (4) by a connecting member (5).
4. The double-layer waterproof gutter system according to claim 3, wherein a gutter edge-closing plate (6) is further attached to the short side of the gutter pressing member (4), a drain hole is formed in the gutter edge-closing plate (6), the upper end and the lower end of the gutter edge-closing plate extend out of the gutter pressing member (4), and the gutter edge-closing plate (6), the additional waterproof roll (7) and the gutter pressing member (4) are fixed together through a connecting member (5).
5. A construction method of a double-layer waterproof gutter system is characterized by comprising the following steps:
step 1, paving waterproof coiled materials on a gutter and roofs on two sides of the gutter;
step 2, arranging a plurality of hanging brackets at intervals at the upper ends of the supports on the two side walls of the gutter, and arranging protective rubber pads between the two ends of each hanging bracket and the supports on the two side walls of the gutter;
step 3, placing the primarily assembled gutter plates on a suspension bracket, and forming a whole after splicing and welding;
step 4, arranging a plurality of gate-type suspension brackets supported by spanning two side walls of the gutter above the finished gutter, wherein the gate-type suspension brackets are distributed at intervals along the length direction of the gutter;
step 5, lifting the welded gutter plate in the step 4 integrally through a lifting cross rod connected with the upper end of the gutter plate and a lifting tool arranged on the door type suspension bracket, taking out the suspended bracket, and then dropping the gutter plate into the gutter to enable the gutter plate to be attached to the supports at the two side walls and the bottom of the gutter;
step 6, mounting a gutter pressing piece at the upper end of the side wall support, pressing and fixing the gutter plate by the gutter pressing piece, covering the gutter pressing piece with an additional waterproof coiled material, welding one end of the additional waterproof coiled material with the roof waterproof coiled material, and extending the other end of the additional waterproof coiled material into the gutter;
and 7, supporting and fixing the additional waterproof coiled material, the gutter casting die, the roof waterproof coiled material and the side wall together through a connecting piece.
6. The construction method of the double-deck watertight gutter system according to claim 5, further comprising:
and 8, vertically attaching the additional waterproof coiled material in the step 6 to the side surface of the gutter pressing piece, attaching the gutter edge-closing piece and the additional waterproof coiled material in the gutter, and fixing the gutter edge-closing plate, the additional waterproof coiled material and the gutter pressing piece together through a connecting piece.
CN202110834646.XA 2021-07-23 2021-07-23 Double-layer waterproof gutter system and construction method thereof Active CN113502988B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110834646.XA CN113502988B (en) 2021-07-23 2021-07-23 Double-layer waterproof gutter system and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110834646.XA CN113502988B (en) 2021-07-23 2021-07-23 Double-layer waterproof gutter system and construction method thereof

Publications (2)

Publication Number Publication Date
CN113502988A true CN113502988A (en) 2021-10-15
CN113502988B CN113502988B (en) 2023-04-28

Family

ID=78014286

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110834646.XA Active CN113502988B (en) 2021-07-23 2021-07-23 Double-layer waterproof gutter system and construction method thereof

Country Status (1)

Country Link
CN (1) CN113502988B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115059247A (en) * 2022-06-27 2022-09-16 深圳市科顺防水工程有限公司 Waterproof structure assembly paved in gutter and paving method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1153529A (en) * 1980-10-20 1983-09-13 Robert J. Demartini Rain gutter devices
CN2430493Y (en) * 2000-07-05 2001-05-16 潘旭鹏 Large span light high strength thermal insulation cross truss combined roof plate
CN204691106U (en) * 2015-05-26 2015-10-07 上海精锐金属建筑系统有限公司 The waterproof construction of a kind of metal roofing board and U-shaped gutter joint portion
CN106522392A (en) * 2016-12-28 2017-03-22 北京港源建筑装饰工程有限公司 Room-in-room sound-insulation and shock-absorption system and construction method thereof
CN109610851A (en) * 2018-12-21 2019-04-12 中冶天工集团有限公司 A kind of assembled moulding bed and its construction method of curved surface truss
CN110094023A (en) * 2018-01-31 2019-08-06 中国二十冶集团有限公司 A kind of light fire-proof heat-insulating plate open valley anti-leaking method using stainless steel inner lining
CN110195496A (en) * 2019-06-20 2019-09-03 精工工业建筑系统有限公司 A kind of overboard system of roofing external gutter
CN210658995U (en) * 2019-08-30 2020-06-02 四川华神钢构有限责任公司 Waterproof construction of steel construction roofing gutter end of meeting water
CN211114476U (en) * 2019-09-29 2020-07-28 森特士兴集团股份有限公司 Point type roof steel gutter system
CN213477431U (en) * 2020-09-14 2021-06-18 山东雅博科技股份有限公司 Steel sheet roofing gable position roof boarding and gutter receipts limit structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA1153529A (en) * 1980-10-20 1983-09-13 Robert J. Demartini Rain gutter devices
CN2430493Y (en) * 2000-07-05 2001-05-16 潘旭鹏 Large span light high strength thermal insulation cross truss combined roof plate
CN204691106U (en) * 2015-05-26 2015-10-07 上海精锐金属建筑系统有限公司 The waterproof construction of a kind of metal roofing board and U-shaped gutter joint portion
CN106522392A (en) * 2016-12-28 2017-03-22 北京港源建筑装饰工程有限公司 Room-in-room sound-insulation and shock-absorption system and construction method thereof
CN110094023A (en) * 2018-01-31 2019-08-06 中国二十冶集团有限公司 A kind of light fire-proof heat-insulating plate open valley anti-leaking method using stainless steel inner lining
CN109610851A (en) * 2018-12-21 2019-04-12 中冶天工集团有限公司 A kind of assembled moulding bed and its construction method of curved surface truss
CN110195496A (en) * 2019-06-20 2019-09-03 精工工业建筑系统有限公司 A kind of overboard system of roofing external gutter
CN210658995U (en) * 2019-08-30 2020-06-02 四川华神钢构有限责任公司 Waterproof construction of steel construction roofing gutter end of meeting water
CN211114476U (en) * 2019-09-29 2020-07-28 森特士兴集团股份有限公司 Point type roof steel gutter system
CN213477431U (en) * 2020-09-14 2021-06-18 山东雅博科技股份有限公司 Steel sheet roofing gable position roof boarding and gutter receipts limit structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
常建立、曹智: "《建筑工程施工技术 下》", 28 February 2017, 北京理工大学出版社, pages: 176 - 177 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115059247A (en) * 2022-06-27 2022-09-16 深圳市科顺防水工程有限公司 Waterproof structure assembly paved in gutter and paving method

Also Published As

Publication number Publication date
CN113502988B (en) 2023-04-28

Similar Documents

Publication Publication Date Title
CN212984396U (en) Heat collector installation connecting node structure for heat-preservation sloping roof
CN113502988A (en) Double-layer waterproof gutter system and construction method thereof
CN209942071U (en) Flashing joint structure for steel skeleton light plate roof and parapet wall
CN109457876B (en) Metal roof system with hidden maintenance horse way
CN109469233B (en) Special-shaped curtain wall system and construction method thereof
CN111576747A (en) Double-layer metal roof construction process
CN110924601A (en) Photovoltaic integrated roof structure and construction method
CN207469611U (en) A kind of roof board system for improving water resistance
CN109083325A (en) Corrugated metal wall system and its installation method
CN201671190U (en) Flashing device of roof pipeline of steel structure building
JP2931240B2 (en) Building with solar cell module
CN113802724A (en) Anti-seepage construction structure and construction method for outer wall tongue-and-groove joint
CN112982755A (en) Stone curtain wall and glass awning handing-over constructional system
CN212957309U (en) Heat collector installation connecting node structure at eaves edge of heat-insulation roof
CN213806205U (en) Tile hanging sloping roof
CN213015035U (en) Asphalt felt tile pitched roof heat collector installation connecting node structure
CN216616607U (en) Support structure of steel gutter
CN217105863U (en) Concrete parapet and eaves mouth are gutter structure for sealing connection
CN205369742U (en) A roofing system of falling into water for steel construction
CN217984394U (en) Roofing cable testing bridge supporting structure that possesses waterproof performance
CN213682431U (en) Ultrathin same-layer drainage floor drain steel frame structure
CN220539039U (en) Metal waterproof system
CN215948634U (en) Ridge connecting structure
CN217353256U (en) Accessible roof deformation joint
CN217871273U (en) Floor support plate bottom membrane joint structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant