CN113468649A - 一种用于轨道交通供电系统的bim设计方法 - Google Patents
一种用于轨道交通供电系统的bim设计方法 Download PDFInfo
- Publication number
- CN113468649A CN113468649A CN202110856924.1A CN202110856924A CN113468649A CN 113468649 A CN113468649 A CN 113468649A CN 202110856924 A CN202110856924 A CN 202110856924A CN 113468649 A CN113468649 A CN 113468649A
- Authority
- CN
- China
- Prior art keywords
- power supply
- supply system
- substation
- design
- bim
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Geometry (AREA)
- Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Economics (AREA)
- Health & Medical Sciences (AREA)
- Computer Hardware Design (AREA)
- Computational Mathematics (AREA)
- Public Health (AREA)
- Pure & Applied Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Mathematical Analysis (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Mathematical Optimization (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- General Business, Economics & Management (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
本发明设计轨道交通领域,尤其涉及一种用于轨道交通供电系统的BIM设计方法,以大幅提高轨道交通供电系统BIM设计效率,方法包括以下步骤:①利用布点设计指标建立变电所二维平面布点图;②设计人员提取资料,建立变电所设备布置二维平面图;③在revit中建立设备模型库;④在revit软件中构建变电所BIM模型;⑤结合步骤①中变电所平面布点图与步骤④各变电站BIM模型在线路专业提供的模型基础上,在revit软件中完成全线供电系统模型的设计;⑥将所述供电系统模型与其他专业模型交互,由设计人员校核后,在设计系统中修改图纸,再重复步骤③~⑤,从而实现最终设计。
Description
技术领域
本发明涉及轨道交通领域,一种用于轨道交通供电系统的BIM设计方法。
背景技术
BIM(建筑信息模型)是一种应用于工程项目的设计、建造、管理的数据化技术,通过对建筑的数据化、信息化模型整合,在项目前期策划、正常运行和维护的全生命周期过程中进行信息数据的共享和传递,已经在全球范围内得到广泛认可,它可以实现建筑全生命周期信息的流通、集成,将设计、施工、运行,各种全生命周期信息整合于一个三维模型信息数据库中,设计团队、施工单位、设施运维部门和业主等各方人员都可以进行协同工作,有效提高工作效率、节省资源、降低成本。
BIM暂未用于轨道交通供电系统设计,目前供电系统设计所建立模型往往过于庞大,占用资源大,且必须在线路等站前专业完成建模后才可以开始供电系统的设计,不可避免会造成设计等待,大大影响设计效率。另一方面,设计优化时,需频繁交互、并根据其他专业修改情况对模型进行逐一修改,进一步降低了效率。
发明内容
为解决上述问题,本发明提供一种用于轨道交通供电系统的BIM设计方法。
为了实现该目的,本发明采取的技术方案是:一种用于轨道交通供电系统的BIM设计方法,包括以下步骤:
①建立变电所二维平面布点图,利用布点设计指标完成变电所二维平面布点图;
②建立变电所设备布置二维平面图,设计人员提取资料,完成设计变电所设备布置二维平面图设计;
③在revit软件中建立设备模型库,用以储存供电系统所需的设备模型;
④建立变电所BIM模型,将步骤③的设备模型与步骤②的变电所设备布置二维图结合,在revit软件中构建变电所BIM模型;
⑤设计全线供电系统BIM模型,结合步骤①中变电所二维平面布点图与步骤④各变电所BIM模型在线路专业提供的模型基础上,在revit软件中完成全线供电系统模型的设计;
⑥将所述供电系统模型与其他专业模型交互,由设计人员校核后,在设计系统中修改图纸,再重复步骤③~⑤,从而实现最终设计。
作为优选方式,步骤①设计指标包括实地施工情况、线路专业要求、周围地质条件,设计指标从其他专业提取资料。
作为优选方式,步骤①变电所二维平面布点图用于表达变电所位置、全线变电所数量、变电所名称、变电所间距。
作为优选方式,步骤②提取资料内容包括线路布置、建筑结构、电扶梯布置情况。
作为优选方式,步骤②变电所设备布置二维平面图用于表述变电所设备类型、设备布置位置、设备数量。
作为优选方式,步骤④变电所BIM模型建立在建筑专业、结构专业的模型之上。
作为优选方式,步骤⑤全线供电系统BIM模型,由设计人员结合线路专业提供的区间线路模型,在revit软件中完成全线供电系统模型的设计。
作为优选方式,步骤⑥与其他专业模型交互,由设计人员将步骤⑤所建模型与其他专业模型结合,校验设计是否合理、有无冲突,若有冲突于设计系统中修改图纸,在revit软件中重新建立全线供电系统BIM模型,再与其他专业的模型校核,若无冲突,则完成供电系统设计。
与现有技术相比,本发明的有益效果是:
1、本发明所述的一种用于轨道交通供电系统的BIM设计方法能够有效减少设计等待,提高设计效率。
2、本发明所述的一种用于轨道交通供电系统的BIM设计方法具有强化模型交互渠道、减小优化成本的优点。
附图说明
图1:供电系统BIM设计步骤图
图2:全线供电系统BIM模型(局部)
具体实施方式
为了对本发明的技术特征、目的和效果有更加清楚的理解,现对照附图详细说明本发明的具体实施方式。
参照图1,本发明的一种用于轨道交通供电系统的BIM设计方法,包括以下步骤:
①建立变电所二维平面布点图,将布点设计指标结合其他专业资料,完成变电所二维平面布点图;设计指标包括实地施工情况、线路专业要求、周围地质条件,设计指标从其他专业提取资料。变电所二维平面布点图用于表达变电所位置、全线变电所数量、变电所名称、变电所间距。
②建立变电所设备布置二维平面图,设计人员从其他专业提取资料,完成设计变电所设备布置二维平面图设计;提取资料内容包括线路布置、建筑结构、电扶梯布置情况。变电所设备布置二维平面图用于表述变电所设备类型、设备布置位置、设备数量。
③在revit软件中建立设备模型库,用以储存供电系统所需的设备模型;
④建立变电所BIM模型,将步骤③的设备模型与步骤②的变电所设备布置二维图结合,在revit软件中构建变电所BIM模型;变电所BIM模型建立在建筑专业、结构专业的模型之上。
⑤设计全线供电系统BIM模型,结合步骤①中变电所二维平面布点图与步骤④各变电所BIM模型在线路专业提供的模型基础上,在revit软件中完成全线供电系统模型的设计;全线供电系统BIM模型,由设计人员结合线路专业提供的区间线路模型,在revit软件中完成全线供电系统模型的设计。
⑥将所述供电系统模型与其他专业模型交互,由设计人员校核后,在设计系统中修改图纸,再重复步骤③~⑤,从而实现最终设计。
与其他专业模型交互,由设计人员将步骤⑤所建模型与其他专业模型结合,校验设计是否合理、有无冲突,若有冲突于设计系统中修改图纸,在revit软件中重新建立全线供电系统BIM模型,再与其他专业的模型校核,若无冲突,则完成供电系统设计。
Claims (8)
1.一种用于轨道交通供电系统的BIM设计方法,其特征在于,包括如下步骤:
①建立变电所二维平面布点图,利用布点设计指标完成变电所二维平面布点图;
②建立变电所设备布置二维平面图,设计人员提取资料,完成设计变电所设备布置二维平面图设计;
③在revit软件中建立设备模型库,用以储存供电系统所需的设备模型;
④建立变电所BIM模型,将步骤③的设备模型与步骤②的变电所设备布置二维图结合,在revit软件中构建变电所BIM模型;
⑤设计全线供电系统BIM模型,结合步骤①中变电所二维平面布点图与步骤④各变电所BIM模型在线路专业提供的模型基础上,在revit软件中完成全线供电系统模型的设计;
⑥将所述供电系统模型与其他专业模型交互,由设计人员校核后,在设计系统中修改图纸,再重复步骤③~⑤,从而实现最终设计。
2.如权利要求1所述的一种用于轨道交通供电系统的BIM设计方法,其特征在于:步骤①设计指标包括实地施工情况、线路专业要求、周围地质条件,设计指标从其他专业提取资料。
3.如权利要求1所述的一种用于轨道交通供电系统的BIM设计方法,其特征在于:步骤①变电所二维平面布点图用于表达变电所位置、全线变电所数量、变电所名称、变电所间距。
4.如权利要求1所述的一种用于轨道交通供电系统的BIM设计方法,其特征在于:步骤②提取资料内容包括线路布置、建筑结构、电扶梯布置情况。
5.如权利要求1所述的一种用于轨道交通供电系统的BIM设计方法,其特征在于:步骤②变电所设备布置二维平面图用于表述变电所设备类型、设备布置位置、设备数量。
6.如权利要求1所述的一种用于轨道交通供电系统的BIM设计方法,其特征在于:步骤④变电所BIM模型建立在建筑专业、结构专业的模型之上。
7.如权利要求1所述的一种用于轨道交通供电系统的BIM设计方法,其特征在于:步骤⑤全线供电系统BIM模型,由设计人员结合线路专业提供的区间线路模型,在revit软件中完成全线供电系统模型的设计。
8.如权利要求1所述的一种用于轨道交通供电系统的BIM设计方法,其特征在于:步骤⑥与其他专业模型交互,由设计人员将步骤⑤所建模型与其他专业模型结合,校验设计是否合理、有无冲突,若有冲突于设计系统中修改图纸,在revit软件中重新建立全线供电系统BIM模型,再与其他专业的模型校核,若无冲突,则完成供电系统设计。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110856924.1A CN113468649A (zh) | 2021-07-28 | 2021-07-28 | 一种用于轨道交通供电系统的bim设计方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110856924.1A CN113468649A (zh) | 2021-07-28 | 2021-07-28 | 一种用于轨道交通供电系统的bim设计方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN113468649A true CN113468649A (zh) | 2021-10-01 |
Family
ID=77882810
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110856924.1A Pending CN113468649A (zh) | 2021-07-28 | 2021-07-28 | 一种用于轨道交通供电系统的bim设计方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113468649A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116305654A (zh) * | 2023-03-24 | 2023-06-23 | 中铁四局集团电气化工程有限公司 | 一种基于bim云平台的变电所设备组装调试方法 |
CN116882018A (zh) * | 2023-07-17 | 2023-10-13 | 广东方程建筑科技有限公司 | 一种基于大数据的建筑图纸自动设计和质量评估管理系统 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103699731A (zh) * | 2013-12-19 | 2014-04-02 | 中铁第一勘察设计院集团有限公司 | 一种铁道工程真实场景模型协同设计平台的构建方法 |
CN109459965A (zh) * | 2018-10-31 | 2019-03-12 | 中交航局安装工程有限公司 | 一种基于bim的冷藏集装箱电能监控系统 |
CN110688713A (zh) * | 2019-08-26 | 2020-01-14 | 国网上海市电力公司 | 一种变电工程电气设备三维设计的线路连接系统 |
CN111311181A (zh) * | 2020-02-11 | 2020-06-19 | 广州地铁设计研究院股份有限公司 | 一种城市轨道交通多专业正向协同设计交互方法 |
CN111488634A (zh) * | 2020-04-14 | 2020-08-04 | 中国铁路设计集团有限公司 | 基于3dgis+bim的铁路勘察设计交付成果管理方法 |
CN211296946U (zh) * | 2020-02-21 | 2020-08-18 | 北京东峰英杰科技有限公司 | 铁路电力综合运维管理系统 |
CN112346351A (zh) * | 2020-11-19 | 2021-02-09 | 四川九门科技股份有限公司 | 一种基于bim的物联网设备一体化智能集控系统 |
CN112668130A (zh) * | 2020-12-30 | 2021-04-16 | 广州轨道交通建设监理有限公司 | 一种用于地铁区间隧道供电专业中的接触网建模方法 |
-
2021
- 2021-07-28 CN CN202110856924.1A patent/CN113468649A/zh active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103699731A (zh) * | 2013-12-19 | 2014-04-02 | 中铁第一勘察设计院集团有限公司 | 一种铁道工程真实场景模型协同设计平台的构建方法 |
CN109459965A (zh) * | 2018-10-31 | 2019-03-12 | 中交航局安装工程有限公司 | 一种基于bim的冷藏集装箱电能监控系统 |
CN110688713A (zh) * | 2019-08-26 | 2020-01-14 | 国网上海市电力公司 | 一种变电工程电气设备三维设计的线路连接系统 |
CN111311181A (zh) * | 2020-02-11 | 2020-06-19 | 广州地铁设计研究院股份有限公司 | 一种城市轨道交通多专业正向协同设计交互方法 |
CN211296946U (zh) * | 2020-02-21 | 2020-08-18 | 北京东峰英杰科技有限公司 | 铁路电力综合运维管理系统 |
CN111488634A (zh) * | 2020-04-14 | 2020-08-04 | 中国铁路设计集团有限公司 | 基于3dgis+bim的铁路勘察设计交付成果管理方法 |
CN112346351A (zh) * | 2020-11-19 | 2021-02-09 | 四川九门科技股份有限公司 | 一种基于bim的物联网设备一体化智能集控系统 |
CN112668130A (zh) * | 2020-12-30 | 2021-04-16 | 广州轨道交通建设监理有限公司 | 一种用于地铁区间隧道供电专业中的接触网建模方法 |
Non-Patent Citations (3)
Title |
---|
史海欧等: ""基于BIM交互与数据驱动的多专业正向协同设计技术"", 《西南交通大学学报》 * |
李天阳: ""电气化铁路牵引供电系统 BIM 技术应用研究"", 《中国优秀博硕士学位论文全文数据库(硕士)工程科技Ⅱ辑》 * |
王博: ""基于RBAC和BIM的地铁综合管线协同设计应用研究"", 《中国优秀博硕士学位论文全文数据库(硕士)工程科技Ⅱ辑》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116305654A (zh) * | 2023-03-24 | 2023-06-23 | 中铁四局集团电气化工程有限公司 | 一种基于bim云平台的变电所设备组装调试方法 |
CN116305654B (zh) * | 2023-03-24 | 2023-11-10 | 中铁四局集团电气化工程有限公司 | 一种基于bim云平台的变电所设备组装调试方法 |
CN116882018A (zh) * | 2023-07-17 | 2023-10-13 | 广东方程建筑科技有限公司 | 一种基于大数据的建筑图纸自动设计和质量评估管理系统 |
CN116882018B (zh) * | 2023-07-17 | 2024-01-23 | 广东方程建筑科技有限公司 | 一种基于大数据的建筑图纸自动设计和质量评估管理系统 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107967399B (zh) | 一种基于bim软件的装配式建筑深化设计方法 | |
CN113468649A (zh) | 一种用于轨道交通供电系统的bim设计方法 | |
CN109388902A (zh) | 一种应用bim技术的场地布置施工方法 | |
CN102156776B (zh) | 一种利用关系型数据库构建电缆桥架网络的方法 | |
CN109523424A (zh) | 一种基于bim的装配式建筑信息化管理系统及方法 | |
CN112560134A (zh) | 一种基于cad与bim的装配式结构叠合板批量深化设计方法 | |
CN112036760A (zh) | 船舶舾装工艺顺序自动规划方法、装置、终端及存储介质 | |
Liang et al. | Research on design optimization of prefabricated residential houses based on BIM technology | |
CN112288384A (zh) | 一种基于p-bias装配式建筑全生命周期管理的应用 | |
CN115600298A (zh) | 一种基于revit的BIM建筑正向设计标准化出图方法 | |
Li et al. | Impact evaluation of prefabricated buildings cost on Game Theory-cloud model | |
CN111581700A (zh) | 基于catia模型添加bim属性并输出bim属性表的方法 | |
Li | The Application of Computer BIM Technology in Prefabricated Construction Project Management | |
CN107679332A (zh) | 基于Tekla平台的输电铁塔BIM模型构建方法 | |
CN109537896B (zh) | 一种基于bim的施工场地电箱智能化布置方法及系统 | |
Li et al. | Application of BIM technology in green building engineering construction | |
CN112906235A (zh) | 一种三维工厂建设及工程应用的方法 | |
CN112035935A (zh) | 一种基于bim的大跨度钢桁架可视化施工方法 | |
Zhao et al. | Application Strategy of BIM Technology in Virtual Construction of Prefabricated Buildings | |
Zhang et al. | Application of BIM technology in energy-saving design of green building [J] | |
Dang | Research on examination of construction drawings of university construction projects | |
Lixiao et al. | Research and development of prefabricated detailed design software based on intelligent construction | |
Bi | Application Research of Building Information Model in the Construction Project Life Cycle | |
Tang | Research on the application of BIM technology in the design of prefabricated buildings and green construction | |
Ge et al. | Interaction and application of bim technology in urban rail transit design phase |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20211001 |