CN113463897A - A remove operation car for high slope protection construction - Google Patents
A remove operation car for high slope protection construction Download PDFInfo
- Publication number
- CN113463897A CN113463897A CN202110918449.6A CN202110918449A CN113463897A CN 113463897 A CN113463897 A CN 113463897A CN 202110918449 A CN202110918449 A CN 202110918449A CN 113463897 A CN113463897 A CN 113463897A
- Authority
- CN
- China
- Prior art keywords
- walking frame
- slope protection
- high slope
- operation platform
- bidirectional screw
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 14
- 230000002457 bidirectional effect Effects 0.000 claims abstract description 15
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 230000001681 protective effect Effects 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/36—Scaffolds for particular parts of buildings or buildings of particular shape, e.g. for stairs, cupolas, domes
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/24—Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G5/00—Component parts or accessories for scaffolds
- E04G5/14—Railings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G1/00—Scaffolds primarily resting on the ground
- E04G1/24—Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
- E04G2001/242—Scaffolds movable on wheels or tracks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
The invention provides a mobile operation vehicle for high slope protection construction, belonging to the technical field of mobile operation vehicles, and comprising a walking frame, an operation platform, a winch, a guider, a telescopic supporting rod and a bidirectional screw jack; one side of the operation platform is hinged to the walking frame; one end of each telescopic supporting rod and one end of each bidirectional screw jack are respectively hinged to the walking frame, and the other ends of the telescopic supporting rods and the bidirectional screw jacks are respectively hinged to the operation platform; the winch and the guider are fixed on the walking frame; the walking frame is movably provided with walking wheels; the design of the invention solves the moving and adjusting problems of the high slope protection operation platform, and is suitable for various operations and various devices.
Description
Technical Field
The invention relates to the technical field of mobile operation vehicles, in particular to a mobile operation vehicle for high slope protection construction.
Background
At present, when high slope protection operation is carried out, the operation platform is troublesome to move and adjust, and the construction efficiency is greatly influenced.
Disclosure of Invention
Aiming at the technical defects, the invention aims to provide the mobile operation vehicle for high slope protection construction.
In order to solve the technical problems, the invention adopts the following technical scheme:
a mobile operation vehicle for high slope protection construction is characterized by comprising a walking frame, an operation platform, a winch, a guider, a telescopic supporting rod and a bidirectional screw jack;
one side of the operation platform is hinged to the walking frame; one end of each telescopic supporting rod and one end of each bidirectional screw jack are respectively hinged to the walking frame, and the other ends of the telescopic supporting rods and the bidirectional screw jacks are respectively hinged to the operation platform;
the winch and the guider are fixed on the walking frame; the walking frame is movably provided with walking wheels.
Preferably, the operation platform is provided with a guard rail.
Preferably, the walking frame and the working platform are respectively provided with a locking device.
Preferably, the deadlocking means is a fastening bolt.
The invention has the beneficial effects that: the design of the invention solves the moving and adjusting problems of the high slope protection operation platform, and is suitable for various operations and various devices.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to the drawings without creative efforts.
Fig. 1 is a schematic structural diagram of a mobile work vehicle for high slope protection construction according to an embodiment of the present invention.
Description of reference numerals:
the device comprises a guider 1, a protective railing 2, an operation platform 3, a telescopic supporting rod 4, a bidirectional screw jack 5, a winch 6, a walking frame 7, walking wheels 8 and buried anchor bolts 9.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be noted that in the description of the present invention, the terms "in", "upper", "lower", "lateral", "inner", etc. indicate directions or positional relationships based on those shown in the drawings, which are merely for convenience of description, and do not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention.
Furthermore, it should be noted that, in the description of the present invention, unless otherwise explicitly specified or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly and may be, for example, fixedly connected, detachably connected, or integrally connected; may be a mechanical connection; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
As shown in fig. 1, a mobile operation vehicle for high slope protection construction comprises a walking frame 7, an operation platform 3, a winch 6, a guider 1, a telescopic support rod 4 and a bidirectional screw jack 5;
one side of the operation platform 3 is hinged on the walking frame 7; one end of the telescopic supporting rod 4 and one end of the bidirectional screw jack 5 are respectively hinged on the walking frame 7, and the other ends are respectively hinged on the operation platform 3;
the winch 6 and the guider 1 are fixed on the walking frame 7; a walking wheel 8 is movably arranged on the walking frame 7; the front end of the wire rope of the hoist 6 passes through the guide 1, and the front end of the wire rope is connected with a buried anchor bolt 9.
Further, the working platform 3 is provided with a protective railing 2.
Furthermore, the walking frame 7 and the operation platform 3 are respectively provided with a locking device for fixing the hinged position of the operation platform 3 and the walking frame 7, the hinged position of the walking frame 7 and the telescopic support rod 4, the hinged position of the bidirectional screw jack 5, the hinged position of the telescopic support rod 4, the bidirectional screw jack 5 and the hinged position of the operation platform 3.
Further, the locking device is a fastening bolt.
The operation method comprises the following steps:
before operation, the equipment is assembled into a whole, a walking frame 7, an equipment base (arranged on an operation platform 3) and a supporting rod are triangular, four walking wheels 8 are arranged on two sides of the walking frame 7 during installation, a 3t winch 6 is arranged above the walking frame 7 and is provided with a phi 12 steel wire rope, and a guider 1 is arranged at the center of the front end of the walking frame 7 to control the traction direction; the front end of the operation platform 3 is connected with the front end of the walking frame 7 through a shaft, the periphery of the platform is provided with a detachable protective railing 2, the rear end of the platform is connected with the shaft through a telescopic supporting rod 4 (a drawing type, which is an existing product), and an electric bidirectional screw jack 5 is arranged and used for adjusting the angle of the platform.
Set up buried anchor bolt 9 at the side slope top during the operation, connect fixedly 6 wire rope ends of hoist engine, start 6 traction equipment of hoist engine and climb the walking, adopt two-way screw jack 5 adjusting device to suitable angle after walking to the assigned position, die each axle position lock, form each part fixedly, carry out the construction operation, the equal mode removes to next operation point after the operation is accomplished.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.
Claims (4)
1. A mobile operation vehicle for high slope protection construction is characterized by comprising a walking frame, an operation platform, a winch, a guider, a telescopic supporting rod and a bidirectional screw jack;
one side of the operation platform is hinged to the walking frame; one end of each telescopic supporting rod and one end of each bidirectional screw jack are respectively hinged to the walking frame, and the other ends of the telescopic supporting rods and the bidirectional screw jacks are respectively hinged to the operation platform;
the winch and the guider are fixed on the walking frame; the walking frame is movably provided with walking wheels.
2. The mobile working vehicle for high slope protection construction according to claim 1, wherein a protection railing is arranged on the working platform.
3. The mobile working vehicle for high slope protection construction according to claim 1, wherein the walking frame and the working platform are respectively provided with a locking device.
4. The mobile work vehicle for high slope protection construction according to claim 3, wherein the locking means is a fastening bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110918449.6A CN113463897A (en) | 2021-08-11 | 2021-08-11 | A remove operation car for high slope protection construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110918449.6A CN113463897A (en) | 2021-08-11 | 2021-08-11 | A remove operation car for high slope protection construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN113463897A true CN113463897A (en) | 2021-10-01 |
Family
ID=77866323
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110918449.6A Pending CN113463897A (en) | 2021-08-11 | 2021-08-11 | A remove operation car for high slope protection construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113463897A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115217312A (en) * | 2022-08-25 | 2022-10-21 | 中国十七冶集团有限公司 | Movable and adjustable slope operation platform and construction method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005076404A (en) * | 2003-09-03 | 2005-03-24 | Kyodo Kensetsu Fujimuragumi:Kk | Transferable platform for slope drilling device |
JP2014043713A (en) * | 2012-08-27 | 2014-03-13 | Kawase Co Ltd | Slope scaffolding device |
CN211114745U (en) * | 2019-08-26 | 2020-07-28 | 云南省水利水电勘测设计研究院 | Hanging basket equipment for reservoir slope cleaning |
CN215978365U (en) * | 2021-08-11 | 2022-03-08 | 中铁三局集团有限公司 | A remove operation car for high slope protection construction |
-
2021
- 2021-08-11 CN CN202110918449.6A patent/CN113463897A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005076404A (en) * | 2003-09-03 | 2005-03-24 | Kyodo Kensetsu Fujimuragumi:Kk | Transferable platform for slope drilling device |
JP2014043713A (en) * | 2012-08-27 | 2014-03-13 | Kawase Co Ltd | Slope scaffolding device |
CN211114745U (en) * | 2019-08-26 | 2020-07-28 | 云南省水利水电勘测设计研究院 | Hanging basket equipment for reservoir slope cleaning |
CN215978365U (en) * | 2021-08-11 | 2022-03-08 | 中铁三局集团有限公司 | A remove operation car for high slope protection construction |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115217312A (en) * | 2022-08-25 | 2022-10-21 | 中国十七冶集团有限公司 | Movable and adjustable slope operation platform and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100523383C (en) | Method for mounting trestle bridge segment box girder | |
JP2809990B2 (en) | Bridge girder erection equipment | |
CN110655015A (en) | Trackless self-propelled platform car for subway tunnel maintenance | |
CN109694024A (en) | A kind of self-propelled lifting hoisting platform device | |
CN215978365U (en) | A remove operation car for high slope protection construction | |
CN113463897A (en) | A remove operation car for high slope protection construction | |
CN114678794A (en) | Maintenance platform device for outdoor transformer | |
CN204629405U (en) | Navigational lighting aid tower fragile stem jacking system | |
CN112030777B (en) | Descending movable formwork support bracket crossing type transfer construction method | |
CN110341732B (en) | Overhead contact system overhauls operation car and auxiliary device thereof | |
CN111287498B (en) | Protective shed frame for construction of overhead bridge box girder crossing railway and erection method | |
CN219136299U (en) | Electric elevator | |
CN107386138B (en) | Totally-enclosed sound insulation screen construction vehicle and totally-enclosed sound insulation screen installation method | |
CN216008539U (en) | Be used for subway tunnel steel truss to support multi-functional platform truck | |
CN214885625U (en) | Multi-point prefabricated part mounting platform | |
CN212613839U (en) | Sideslip device | |
CN208778011U (en) | Concrete- liner tunnel side wall steel formwork trolley | |
CN211472166U (en) | Simple movable hanging basket vehicle for highway bridge construction | |
CN103043531B (en) | Method and device for replacing wheel group of bridge crane | |
CN210366717U (en) | Be applied to console mode and from climbing formula whole construction work platform | |
CN219792253U (en) | Segmental beam lifting and transporting frame integrated machine | |
CN221194187U (en) | Scaffold for interior decoration engineering | |
CN211198525U (en) | Building engineering machinery maintenance work frame | |
CN211776074U (en) | Movable T roof beam prefabrication field cat ladder of ascending a height | |
CN220596846U (en) | Flue board concatenation installation device in lower top type tunnel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20220127 Address after: 030001 269 Yingze street, Yingze District, Taiyuan, Shanxi. Applicant after: CHINA RAILWAY NO.3 ENGINEERING GROUP Co.,Ltd. Applicant after: China Railway Third Bureau Group Bridge and Tunnel Engineering Co., Ltd Address before: No. 666, jinfenghuang Avenue, Jinniu hi tech Industrial Park, Chengdu, Sichuan 610000 Applicant before: CHINA RAILWAY THIRD ENGINEERING GROUP BRIDGE & TUNNEL ENGINEERING Co.,Ltd. |