CN113449457A - Three-dimensional planning method and system for transformer substation based on 3Dgis - Google Patents

Three-dimensional planning method and system for transformer substation based on 3Dgis Download PDF

Info

Publication number
CN113449457A
CN113449457A CN202110791584.9A CN202110791584A CN113449457A CN 113449457 A CN113449457 A CN 113449457A CN 202110791584 A CN202110791584 A CN 202110791584A CN 113449457 A CN113449457 A CN 113449457A
Authority
CN
China
Prior art keywords
area
model
substations
newly
gis
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110791584.9A
Other languages
Chinese (zh)
Other versions
CN113449457B (en
Inventor
潘海毅
王毅
李阔
许杰
陈宇健
洪炜平
曾谷泉
吕远帆
陈华民
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd filed Critical Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Priority to CN202110791584.9A priority Critical patent/CN113449457B/en
Publication of CN113449457A publication Critical patent/CN113449457A/en
Application granted granted Critical
Publication of CN113449457B publication Critical patent/CN113449457B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • G06F30/25Design optimisation, verification or simulation using particle-based methods
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06NCOMPUTING ARRANGEMENTS BASED ON SPECIFIC COMPUTATIONAL MODELS
    • G06N3/00Computing arrangements based on biological models
    • G06N3/004Artificial life, i.e. computing arrangements simulating life
    • G06N3/006Artificial life, i.e. computing arrangements simulating life based on simulated virtual individual or collective life forms, e.g. social simulations or particle swarm optimisation [PSO]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • G06T5/70
    • G06T5/90
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F2111/00Details relating to CAD techniques
    • G06F2111/04Constraint-based CAD
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T2207/00Indexing scheme for image analysis or image enhancement
    • G06T2207/10Image acquisition modality
    • G06T2207/10028Range image; Depth image; 3D point clouds

Abstract

The invention provides a three-dimensional planning method and a three-dimensional planning system for a transformer substation based on 3 Dgis. In one aspect, the method comprises: s1, acquiring a 3D gis model of the region to be planned; s2, carrying out load prediction on the area to be planned to obtain a load prediction result; s3, determining the total number of the newly-built transformer substations according to the load prediction result; s4, establishing a to-be-optimized model of the transformer substation; and S5, optimizing the model to be optimized by adopting a particle swarm algorithm to obtain the coordinates of the newly-built transformer substation. On the other hand, the invention also provides a corresponding system for realizing the method. According to the method, the 3D gis model is established, three-dimensional coordinates are provided for parameters in the model to be optimized, so that the distance between the transformer substations can be more accurately represented by the optimization model, the optimization model can be accurately represented in the aspects of cost, loss and area limitation, and the accuracy of a planning result is improved.

Description

Three-dimensional planning method and system for transformer substation based on 3Dgis
Technical Field
The invention relates to the field of planning, in particular to a three-dimensional planning method and a three-dimensional planning system for a transformer substation based on 3 Dgis.
Background
An existing transformer substation planning mode is generally planned based on a two-dimensional map, and when constraint conditions are established in a planning process, a planar straight-line distance is often used to replace a distance between two transformer substations, however, in an actual environment, altitudes between the two transformer substations are generally different, so that a final planning result is not an optimal result.
Disclosure of Invention
In view of the above problems, the present invention aims to provide a method and a system for three-dimensional planning of a substation based on 3d gis,
on one hand, the invention provides a transformer substation three-dimensional planning method based on 3Dgis, which comprises the following steps:
s1, acquiring a 3D gis model of the region to be planned;
s2, carrying out load prediction on the area to be planned to obtain a load prediction result;
s3, determining the total number of the newly-built transformer substations according to the load prediction result;
s4, establishing a to-be-optimized model of the transformer substation;
and S5, optimizing the model to be optimized by adopting a particle swarm algorithm to obtain the coordinates of the newly-built transformer substation.
Preferably, the acquiring a 3d gis model of the region to be planned includes:
acquiring a two-dimensional image of a planning area by using an unmanned aerial vehicle;
converting the two-dimensional image into a three-dimensional dense point cloud through a triangle analysis algorithm;
and establishing a 3D gis model of a planning region based on the three-dimensional dense point cloud.
Preferably, the load prediction of the area to be planned to obtain a prediction result includes:
dividing the region to be divided into a plurality of sub-regions based on administrative region information;
respectively calculating the load prediction result of each sub-region:
Figure BDA0003161144870000011
wherein valforcast (a) represents the load prediction result of the sub-area a, S (j, a) represents the floor area of the j-th type of land in the sub-area a, and load (j, a) represents the load per unit area of the j-th type of land in the sub-area a; nofare represents the total number of land types in sub-area a; c represents a preset prediction coefficient.
Preferably, the determining the total number of newly-built substations according to the load prediction result includes:
respectively calculating the total number of the newly-built transformer substations in each sub-area:
Figure BDA0003161144870000021
wherein nofns (a) represents the total number of newly-built substations in the sub-area a, br represents the capacity-to-load ratio of the substations, valow (a) represents the total capacity of existing substations in the sub-area a, b1Represents the load dispersion coefficient, b2Representing the reserve factor, b3Indicating transformerSafe operating rate, b4The transformer operation rate is represented, and the value represents the average capacity of the newly-built substation;
calculating the total number of the newly-built transformer substations by adopting the following formula:
Figure BDA0003161144870000022
in the formula, Us represents the set of all sub-regions, and nofw represents the total number of newly-built substations.
Preferably, the establishing of the to-be-optimized model of the substation includes:
establishing a to-be-optimized model of the transformer substation through the following formula:
Figure BDA0003161144870000023
wherein df represents a model to be optimized, Unew represents a set of newly built substations, u and v represent two different substations in Unew, cstofv (u, v) represents the cost per unit length of cable between u and v, dist (u, v) represents the distance between u and v,
Figure BDA0003161144870000024
(x (u), y (u), z (u)), (x (v), y (v), z (v)) represent the three-dimensional coordinates of u and v in the 3D gis model, respectively, cstfe (u, v) represents the voltage loss per unit length of cable between u and v, H represents the set of areas that cannot be used for building substations in the area to be planned, sg (u, v, H) represents the loss function if
Figure BDA0003161144870000025
Then
Figure BDA0003161144870000026
If it is
Figure BDA0003161144870000027
Sg (u, v, h) is 0, D denotes a loss coefficient, dist (u, h) denotes a distance between u and h, dist (v, h) denotes a distance between v and hThe distance between the first and second electrodes,
Figure BDA0003161144870000028
(x (h), y (h), z (h)) represents the three-dimensional coordinates of h in the 3D gis model,
Figure BDA0003161144870000029
the constraint conditions include:
Figure BDA0003161144870000031
dist(u,v)≤madist
Figure BDA0003161144870000032
on the other hand, the invention provides a three-dimensional planning system of a transformer substation based on 3Dgis,
comprising an gis module, a prediction module, a first calculation module, a modeling module, and a second calculation module,
the gis module is used for obtaining a 3D gis model of a region to be planned;
the prediction module is used for predicting the load of the area to be planned to obtain a load prediction result;
the first calculation module is used for determining the total number of the newly-built transformer substations according to the load prediction result;
the modeling module is used for establishing a to-be-optimized model of the transformer substation;
and the second calculation module is used for optimizing the model to be optimized by adopting a particle swarm algorithm to obtain the coordinates of the newly-built transformer substation.
According to the method, the 3D gis model is established, three-dimensional coordinates are provided for parameters in the model to be optimized, so that the distance between the transformer substations can be more accurately represented by the optimization model, the optimization model can be accurately represented in the aspects of cost, loss and area limitation, and the accuracy of a planning result is improved.
Drawings
The invention is further illustrated by means of the attached drawings, but the embodiments in the drawings do not constitute any limitation to the invention, and for a person skilled in the art, other drawings can be obtained on the basis of the following drawings without inventive effort.
Fig. 1 is a diagram of an exemplary embodiment of a transformer substation three-dimensional planning method and system based on 3 Dgis.
Detailed Description
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the accompanying drawings are illustrative only for the purpose of explaining the present invention, and are not to be construed as limiting the present invention.
As shown in fig. 1, the present invention provides a method and system for three-dimensional planning of a 3d gis-based substation,
on one hand, the invention provides a transformer substation three-dimensional planning method based on 3Dgis, which comprises the following steps:
s1, acquiring a 3D gis model of the region to be planned;
s2, carrying out load prediction on the area to be planned to obtain a load prediction result;
s3, determining the total number of the newly-built transformer substations according to the load prediction result;
s4, establishing a to-be-optimized model of the transformer substation;
and S5, optimizing the model to be optimized by adopting a particle swarm algorithm to obtain the coordinates of the newly-built transformer substation.
Specifically, the optimization process adopting the particle swarm algorithm comprises the following steps:
and after each iteration, judging whether the coordinates of the newly-built transformer substation meet the regional limitation condition, if not, adjusting the coordinates of the newly-built transformer substation until the coordinates of the newly-built transformer substation meeting the constraint condition and the regional limitation condition are obtained, and the optimal value is obtained by the optimization model.
The area limiting condition refers to the condition that the coordinates of the newly-built substation cannot fall into areas such as cultivated lands and roads which cannot be changed in use.
Preferably, the acquiring a 3d gis model of the region to be planned includes:
acquiring a two-dimensional image of a planning area by using an unmanned aerial vehicle;
converting the two-dimensional image into a three-dimensional dense point cloud through a triangle analysis algorithm;
and establishing a 3D gis model of a planning region based on the three-dimensional dense point cloud.
The method adopts an unmanned aerial vehicle mode to obtain the two-dimensional image of the planning area, and then establishes the 3D GIS model by combining with the GIS data of the area to be planned. Compared with a mode of using a remote sensing satellite, the method has higher accuracy.
Specifically, the converting the two-dimensional image into a three-dimensional dense point cloud by a triangulation algorithm includes:
carrying out noise reduction processing on the two-dimensional image to obtain a noise-reduced image;
and converting the noise reduction image into a three-dimensional dense point cloud through a triangle analysis algorithm.
The influence of noise points on the generation of the point cloud can be avoided through noise reduction, so that point cloud data with higher accuracy can be obtained.
Specifically, the denoising processing is performed on the two-dimensional image to obtain a denoised image, and the denoising processing includes:
converting the two-dimensional image into a grayscale image;
performing wavelet decomposition processing on the gray level image to obtain a high-frequency wavelet decomposition coefficient HX and a low-frequency wavelet decomposition coefficient LX;
for the high-frequency wavelet decomposition coefficient HX, if HX is less than or equal to tha1It is processed using the following function:
Figure BDA0003161144870000041
if tha1≤|HX|≤tha2It is processed using the following function:
Figure BDA0003161144870000042
if tha2≦ HX |, it is processed using the following function:
aHX=|HX|
wherein aHX represents the result of processing HX, α and β represent preset weight coefficients, tha1And tha2Respectively representing a first judgment parameter and a second judgment parameter which are preset, xhn (hx) representing a judgment function,
Figure BDA0003161144870000051
ctr denotes a preset regulating parameter, Q1And Q2Respectively representing the standard deviation and variance of the pixel values of the pixels in HX,
processing the low-frequency wavelet decomposition coefficient LX by using a non-local mean de-noising algorithm to obtain a result aLX of processing the LX;
aHX and aLX are reconstructed to obtain a noise-reduced image.
The wavelet decomposition and reconstruction mode is adopted for denoising, and the edge information in the two-dimensional image can be effectively reserved while denoising, so that the method is favorable for providing a high-quality denoised image for the process of obtaining the three-dimensional dense point cloud, and is favorable for obtaining the accurate three-dimensional dense point cloud, and the method is favorable for improving the accuracy of the 3D gis model. Specifically, HX and LX are processed respectively in the noise reduction process, improvement of accuracy of a reconstruction result is facilitated, when HX is processed, different functions are selected for processing through setting of judgment parameters to HX under different conditions, improvement of pertinence of the functions is facilitated, accuracy of aHX is improved, when LX is processed, a non-local mean noise reduction algorithm is used, and more edge detail information can be further reserved.
Preferably, the load prediction of the area to be planned to obtain a prediction result includes:
dividing the region to be divided into a plurality of sub-regions based on administrative region information;
respectively calculating the load prediction result of each sub-region:
Figure BDA0003161144870000052
wherein valforcast (a) represents the load prediction result of the sub-area a, S (j, a) represents the floor area of the j-th type of land in the sub-area a, and load (j, a) represents the load per unit area of the j-th type of land in the sub-area a; nofare represents the total number of land types in sub-area a; c represents a preset prediction coefficient.
Specifically, according to the administrative area information, for example, an administrative area belonging to a village or an administrative area of a street is taken as a sub-area, and the person skilled in the art can select the sub-area according to the size of the planned area.
Preferably, the determining the total number of newly-built substations according to the load prediction result includes:
respectively calculating the total number of the newly-built transformer substations in each sub-area:
Figure BDA0003161144870000061
wherein nofns (a) represents the total number of newly-built substations in the sub-area a, br represents the capacity-to-load ratio of the substations, valow (a) represents the total capacity of existing substations in the sub-area a, b1Represents the load dispersion coefficient, b2Representing the reserve factor, b3Representing the safe operation rate of the transformer, b4The transformer operation rate is represented, and the value represents the average capacity of the newly-built substation;
calculating the total number of the newly-built transformer substations by adopting the following formula:
Figure BDA0003161144870000062
in the formula, Us represents the set of all sub-regions, and nofw represents the total number of newly-built substations.
When the total number of the substations is calculated, the average capacity of the substations, the capacity of the existing substations, the predicted load and the like are calculated, and a relatively accurate calculation result can be obtained.
Preferably, the establishing of the to-be-optimized model of the substation includes:
establishing a to-be-optimized model of the transformer substation through the following formula:
Figure BDA0003161144870000063
wherein df represents a model to be optimized, Unew represents a set of newly built substations, u and v represent two different substations in Unew, cstofv (u, v) represents the cost per unit length of cable between u and v, dist (u, v) represents the distance between u and v,
Figure BDA0003161144870000064
(x (u), y (u), z (u)), (x (v), y (v), z (v)) represent the initialized three-dimensional coordinates of u and v in the 3D gis model, respectively, cstfe (u, v) represents the voltage loss per unit length of cable between u and v, H represents the set of areas that cannot be used for building substations in the area to be planned, sg (u, v, H) represents the loss function if, for example, u and v represent the loss function
Figure BDA0003161144870000065
Then
Figure BDA0003161144870000066
If it is
Figure BDA0003161144870000067
Sg (u, v, h) is 0, D denotes a loss coefficient, dist (u, h) denotes a distance between u and h, dist (v, h) denotes a distance between v and h,
Figure BDA0003161144870000071
(x (h), y (h), z (h)) represents the three-dimensional coordinates of h in the 3D gis model,
Figure BDA0003161144870000072
the constraint conditions include:
Figure BDA0003161144870000073
dist(u,v)≤madist
Figure BDA0003161144870000074
in the establishment of the optimization model, the present invention considers the aspects of cost, voltage loss, distance between the substation and the area that cannot be used for building the substation, and the like, so that the coordinates that the total cost is as low as possible, the total voltage loss is as small as possible, and the distance between the substation and the area that cannot be used for building the substation is as far as possible can be selected as the coordinates of the substation. Meanwhile, when the distance is calculated, the three-dimensional coordinates are adopted, and the distance is reflected more accurately compared with the traditional two-dimensional coordinates, so that the accuracy of the obtained coordinates of the newly-built transformer substation is improved.
On the other hand, the invention provides a three-dimensional planning system of a transformer substation based on 3Dgis,
comprising an gis module, a prediction module, a first calculation module, a modeling module, and a second calculation module,
the gis module is used for obtaining a 3D gis model of a region to be planned;
the prediction module is used for predicting the load of the area to be planned to obtain a load prediction result;
the first calculation module is used for determining the total number of the newly-built transformer substations according to the load prediction result;
the modeling module is used for establishing a to-be-optimized model of the transformer substation;
and the second calculation module is used for optimizing the model to be optimized by adopting a particle swarm algorithm to obtain the coordinates of the newly-built transformer substation.
It should be noted that, the system is used for implementing the functions of the method, and each module in the apparatus corresponds to the steps of the method, and can implement different embodiments of the method.
According to the method, the 3D gis model is established, three-dimensional coordinates are provided for parameters in the model to be optimized, so that the distance between the transformer substations can be more accurately represented by the optimization model, the optimization model can be accurately represented in the aspects of cost, loss and area limitation, and the accuracy of a planning result is improved.
While embodiments of the invention have been shown and described, it will be understood by those skilled in the art that: various changes, modifications, substitutions and alterations can be made to the embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the claims and their equivalents.

Claims (6)

1. The three-dimensional planning method of the transformer substation based on the 3Dgis is characterized by comprising the following steps:
s1, acquiring a 3D gis model of the region to be planned;
s2, carrying out load prediction on the area to be planned to obtain a load prediction result;
s3, determining the total number of the newly-built transformer substations according to the load prediction result;
s4, establishing a to-be-optimized model of the transformer substation;
and S5, optimizing the model to be optimized by adopting a particle swarm algorithm to obtain the coordinates of the newly-built transformer substation.
2. The method for three-dimensional planning of a 3D gis-based substation according to claim 1, wherein the obtaining of the 3D gis model of the area to be planned comprises:
acquiring a two-dimensional image of a planning area by using an unmanned aerial vehicle;
converting the two-dimensional image into a three-dimensional dense point cloud through a triangle analysis algorithm;
and establishing a 3D gis model of a planning region based on the three-dimensional dense point cloud.
3. The three-dimensional planning method for the transformer substation based on the 3D gis is characterized in that the load prediction of the area to be planned is carried out to obtain a prediction result, and the method comprises the following steps:
dividing the region to be divided into a plurality of sub-regions based on administrative region information;
respectively calculating the load prediction result of each sub-region:
Figure FDA0003161144860000011
wherein valforcast (a) represents the load prediction result of the sub-area a, S (j, a) represents the floor area of the j-th type of land in the sub-area a, and load (j, a) represents the load per unit area of the j-th type of land in the sub-area a; nofare represents the total number of land types in sub-area a; c represents a preset prediction coefficient.
4. The method for three-dimensional planning of 3D gis-based substations according to claim 3, wherein said determining the total number of newly-built substations according to the load prediction result includes:
respectively calculating the total number of the newly-built transformer substations in each sub-area:
Figure FDA0003161144860000012
wherein nofns (a) represents the total number of newly-built substations in the sub-area a, br represents the capacity-to-load ratio of the substations, valow (a) represents the total capacity of existing substations in the sub-area a, b1Represents the load dispersion coefficient, b2Representing the reserve factor, b3Representing the safe operation rate of the transformer, b4The transformer operation rate is represented, and the value represents the average capacity of the newly-built substation;
calculating the total number of the newly-built transformer substations by adopting the following formula:
Figure FDA0003161144860000021
in the formula, Us represents the set of all sub-regions, and nofw represents the total number of newly-built substations.
5. The 3D gis-based substation three-dimensional planning method according to claim 3, wherein the establishing of the substation model to be optimized comprises:
establishing a to-be-optimized model of the transformer substation through the following formula:
Figure FDA0003161144860000022
wherein df represents a model to be optimized, Unew represents a set of newly built substations, u and v represent two different substations in Unew, cstofv (u, v) represents the cost per unit length of cable between u and v, dist (u, v) represents the distance between u and v,
Figure FDA0003161144860000023
(x (u), y (u), z (u)), (x (v), y (v), z (v)) represent the three-dimensional coordinates of u and v in the 3D gis model, respectively, cstfe (u, v) represents the voltage loss per unit length of cable between u and v, H represents the set of areas that cannot be used for building substations in the area to be planned, sg (u, v, H) represents the loss function if
Figure FDA0003161144860000024
Then
Figure FDA0003161144860000025
If it is
Figure FDA0003161144860000026
Sg (u, v, h) is 0, D denotes a loss coefficient, dist (u, h) denotes a distance between u and h, dist (v, h) denotes a distance between v and h,
Figure FDA0003161144860000027
(x (h), y (h), z (h)) represents the three-dimensional coordinates of h in the 3D gis model,
Figure FDA0003161144860000028
the constraint conditions include:
Figure FDA0003161144860000029
dist(u,v)≤madist
Figure FDA0003161144860000031
6. the three-dimensional planning system of the transformer substation based on the 3Dgis is characterized by comprising an gis module, a prediction module, a first calculation module, a modeling module and a second calculation module,
the gis module is used for obtaining a 3D gis model of a region to be planned;
the prediction module is used for predicting the load of the area to be planned to obtain a load prediction result;
the first calculation module is used for determining the total number of the newly-built transformer substations according to the load prediction result;
the modeling module is used for establishing a to-be-optimized model of the transformer substation;
and the second calculation module is used for optimizing the model to be optimized by adopting a particle swarm algorithm to obtain the coordinates of the newly-built transformer substation.
CN202110791584.9A 2021-07-13 2021-07-13 Three-dimensional planning method and system for transformer substation based on 3Dgis Active CN113449457B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110791584.9A CN113449457B (en) 2021-07-13 2021-07-13 Three-dimensional planning method and system for transformer substation based on 3Dgis

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110791584.9A CN113449457B (en) 2021-07-13 2021-07-13 Three-dimensional planning method and system for transformer substation based on 3Dgis

Publications (2)

Publication Number Publication Date
CN113449457A true CN113449457A (en) 2021-09-28
CN113449457B CN113449457B (en) 2022-03-08

Family

ID=77816164

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110791584.9A Active CN113449457B (en) 2021-07-13 2021-07-13 Three-dimensional planning method and system for transformer substation based on 3Dgis

Country Status (1)

Country Link
CN (1) CN113449457B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130166270A1 (en) * 2011-12-23 2013-06-27 East China Grid Company Limited Method of substation-control center two-level distributed modeling for power grid
US20150212534A1 (en) * 2014-01-24 2015-07-30 International Business Machines Corporation Generating electric substation load transfer control parameters
CN109035392A (en) * 2018-07-25 2018-12-18 上海华测导航技术股份有限公司 A kind of modeling method for substation's threedimensional model
CN111062577A (en) * 2019-11-22 2020-04-24 湖南经研电力设计有限公司 GIS-based substation site selection method
CN111177814A (en) * 2018-10-24 2020-05-19 国网浙江省电力有限公司 Transformer substation engineering three-dimensional modeling method and system based on DEM data
CN111881131A (en) * 2020-06-18 2020-11-03 广东电网有限责任公司广州供电局 Three-dimensional GIS platform applied to power grid planning

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130166270A1 (en) * 2011-12-23 2013-06-27 East China Grid Company Limited Method of substation-control center two-level distributed modeling for power grid
US20150212534A1 (en) * 2014-01-24 2015-07-30 International Business Machines Corporation Generating electric substation load transfer control parameters
CN109035392A (en) * 2018-07-25 2018-12-18 上海华测导航技术股份有限公司 A kind of modeling method for substation's threedimensional model
CN111177814A (en) * 2018-10-24 2020-05-19 国网浙江省电力有限公司 Transformer substation engineering three-dimensional modeling method and system based on DEM data
CN111062577A (en) * 2019-11-22 2020-04-24 湖南经研电力设计有限公司 GIS-based substation site selection method
CN111881131A (en) * 2020-06-18 2020-11-03 广东电网有限责任公司广州供电局 Three-dimensional GIS platform applied to power grid planning

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
罗华伟: "基于GIS 和差分进化粒子群的变电站选址方法", 《信息技术》 *

Also Published As

Publication number Publication date
CN113449457B (en) 2022-03-08

Similar Documents

Publication Publication Date Title
CN107179768B (en) Obstacle identification method and device
CN110866531A (en) Building feature extraction method and system based on three-dimensional modeling and storage medium
CN101901343A (en) Remote sensing image road extracting method based on stereo constraint
CN105678747B (en) A kind of tooth mesh model automatic division method based on principal curvatures
CN111323788B (en) Building change monitoring method and device and computer equipment
CN113077486B (en) Method and system for monitoring vegetation coverage rate in mountainous area
CN110853064B (en) Image collaborative segmentation method based on minimum fuzzy divergence
CN112435267B (en) Disparity map calculation method for high-resolution urban satellite stereo image
CN111458691B (en) Building information extraction method and device and computer equipment
KR101549155B1 (en) Method of automatic extraction of building boundary from lidar data
CN116189147A (en) YOLO-based three-dimensional point cloud low-power-consumption rapid target detection method
CN113449457B (en) Three-dimensional planning method and system for transformer substation based on 3Dgis
CN110991230B (en) Method and system for detecting ship by using remote sensing images in any direction based on rotation candidate frame
CN117092647A (en) Method and system for manufacturing regional satellite-borne optical and SAR image DOM
CN111476879A (en) Point cloud data processing method, terminal and storage medium
CN112884026B (en) Image identification-assisted power transmission line laser LiDAR point cloud classification method
CN114758087A (en) Method and device for constructing city information model
WO2022159592A1 (en) Systems and methods for roof area and slope estimation using a point set
CN112419149A (en) Distributed remote sensing image defogging method based on dark channel prior and guided filtering
CN111429509A (en) Centralized measuring and calculating method for height of target object
CN108694720A (en) A kind of high score image building area extracting method based on multi-dimension texture space clustering
CN110717981A (en) Method and device for acquiring indoor passable area of small robot
CN117236668B (en) Regional water resource allocation analysis decision method and system based on supply and consumption
CN108805063A (en) A kind of multiresolution visual perception method to object and environment
CN116627164B (en) Terrain-height-based unmanned aerial vehicle ground-simulated flight control method and system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant