CN113404518B - Shield tunnel segment repairing process - Google Patents

Shield tunnel segment repairing process Download PDF

Info

Publication number
CN113404518B
CN113404518B CN202110601870.4A CN202110601870A CN113404518B CN 113404518 B CN113404518 B CN 113404518B CN 202110601870 A CN202110601870 A CN 202110601870A CN 113404518 B CN113404518 B CN 113404518B
Authority
CN
China
Prior art keywords
robot
steel plate
welding
punching
assembling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110601870.4A
Other languages
Chinese (zh)
Other versions
CN113404518A (en
Inventor
班延军
张浩文
罗红梅
李恒
高旭东
郑军
梅元元
唐俊龙
牟松
庄元顺
鄷忠良
张轩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Service Co Ltd
Original Assignee
China Railway Engineering Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Service Co Ltd filed Critical China Railway Engineering Service Co Ltd
Priority to CN202110601870.4A priority Critical patent/CN113404518B/en
Publication of CN113404518A publication Critical patent/CN113404518A/en
Priority to PCT/CN2022/096374 priority patent/WO2022253243A1/en
Application granted granted Critical
Publication of CN113404518B publication Critical patent/CN113404518B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/40Devices or apparatus specially adapted for handling or placing units of linings or supporting units for tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members

Abstract

The invention provides a shield tunnel segment repair process, which comprises segment deformation evaluation, pretreatment, steel plate assembly by a reinforcing device, welding, grouting and spraying; and (4) recovering the pipeline and the track bed and returning to the field for acceptance. Aiming at the problems of long construction period, high construction cost, low construction efficiency and great construction difficulty in the prior art, the invention integrates a mechanical device, improves the intelligent level and construction efficiency of tunnel construction, and reduces the labor intensity of operators.

Description

Shield tunnel segment repairing process
Technical Field
The invention relates to the technical field of tunnel support, in particular to a shield tunnel segment repairing process.
Background
The space range of human activities is continuously enlarged, and along with the continuous development of underground space, the subway construction of large and medium-sized cities in China needs to construct a plurality of shield tunnels. In shield construction, shield segments are main assembly members of shield construction, are outermost barriers of tunnels and play a role in resisting soil layer pressure, underground water pressure and some special loads. As a typical tunnel supporting technology, the fabricated reinforced concrete pipe piece is widely applied to the field of shield tunnel supporting due to the advantages of convenient material obtaining, simple manufacturing process, low manufacturing cost, high construction speed, high strength and the like. However, the phenomenon of cracking and damage of the segment lining on the tunnel site sometimes happens, the cracking and damage of the segment can weaken the overall supporting strength of the tunnel lining, and once the control is unfavorable, if the phenomenon of block falling is generated, the fatal threat can be brought to subway operation trains. How to carry out quick repair of the field segment lining is an important task for guaranteeing the construction and operation safety of the tunnel.
In the prior art, a steel plate ring reinforcing method is mainly adopted for repairing and reinforcing damaged segments of an external shield subway tunnel, steel plate rings are grabbed and installed, seams among a plurality of steel plate rings are welded, a plurality of links such as epoxy resin glue injection and steel plate ring corrosion prevention after segment pretreatment and steel plate ring installation further need manual intervention, and the on-site segment lining cannot be effectively and quickly repaired.
Therefore, how to provide a shield tunnel segment repair process reduces the manual intervention link, and the processes of once-through steel plate ring installation, positioning and anchoring, integral welding, steel plate glue injection, anti-corrosion treatment and the like reduce the error rate, improve the shield tunnel segment repair efficiency, and shorten the repair time is a technical problem that needs to be solved urgently by technical personnel in the field.
Disclosure of Invention
The invention aims to solve one of the technical problems in the related technology at least to a certain extent, provides a shield tunnel segment repairing process, aims at solving the problems of long construction period, high construction cost, low construction efficiency and great construction difficulty in the prior art, improves the intelligent level and construction efficiency of tunnel construction, and reduces the labor intensity of operators.
In view of the above, a shield tunnel segment repair process is characterized by comprising the following steps:
1) evaluating the deformation of the duct piece; scanning, detecting and collecting evaluation parameters of the inner wall of the tunnel according to a laser scanner and an industrial vision system; the evaluation parameters comprise ovality of the inner wall of the tunnel, dislocation and measurement of damaged crack gaps; determining a reinforcement position according to a scanning result, drawing up a reinforcement scheme, and preparing reinforcement equipment and materials;
2) pre-treating; changing pipelines, cutting and chiseling a ballast bed, plugging and floating pipe piece rings, longitudinal joints and hand holes, keeping the joints of the pipe pieces free of leakage and drying the surfaces, and then polishing and roughening;
3) assembling steel plates by a reinforcing device, welding, grouting and spraying;
the reinforcing device comprises an assembling system, a punching system, a welding system, a bottom system, an auxiliary operation platform system, a steel plate ring support and an epoxy resin glue barrel; after the steel plate ring is grabbed and installed at a preset position by the assembling system, drilling holes by the punching system and installing anchor bolts, wherein the screwing depth is more than 125mm, the drilling holes are reserved as a grouting hole and an exhaust hole from bottom to top in sequence; for the duct piece with the bolt as a through hole due to overlarge staggered joint, the steel plates are installed in a riding joint mode, the welding system welds joints among a plurality of steel plate rings, and the bottom system moves integrally; the joints between the two sides of the steel plate and the segment are plugged by epoxy cement, then an auxiliary operation platform is used for assisting workers to perform epoxy resin pressure injection between the steel plate and the segment from the grouting holes, anchor bolts are installed at the original grouting holes and the exhaust holes, and finally the auxiliary operation platform is used for assisting the workers to perform spraying of antirust, anticorrosive and fireproof coatings;
fixing a steel plate ring in the inner wall of the duct piece in a manner of screwing an anchor bolt through a punching system;
4) recovering pipelines and track beds;
5) and (5) returning and checking.
The robot is used for assembling, drilling, anchoring and welding, positioning, obstacle detection and path planning are carried out through an intelligent vision system, and efficient and accurate assembling actions are achieved. Hole site recognition is carried out to the drilling likewise adoption vision positioning system, can accurate location hole site, realizes automatic drilling, gets the material, loads, screws up the action, and the operating efficiency is high. Replace manual welding through welding robot, can effectively improve welding efficiency, shorten the activity duration, in addition, also solved the problem that the long time kept the overhead welding posture during manual welding tunnel top steel sheet welding seam. The whole operation process only needs 2 people to cooperate to accomplish can, personnel's input reduces by a wide margin, personnel's cost greatly reduced.
Furthermore, the assembling system comprises an assembling robot, an electric permanent magnetic chuck is arranged at one end of the assembling robot, a scanning and positioning module is fixedly arranged above the electric permanent magnetic chuck, and an assembling robot sliding table is connected to the bottom of the assembling robot in a sliding mode.
Further, the system of punching includes the punching machine people, and the one end of punching machine people is provided with punching module, installing module, screws up the module, and punching machine people's bottom sliding connection has the punching machine people slip table, and punching machine people slip table's bottom is provided with punching machine people lift platform.
Furthermore, the welding system comprises a welding robot, and one end of the welding robot is provided with a welding seam scanning and positioning module, a robot arc welding gun and a welding seam detection module.
Further, the bottom system comprises a multi-track bogie, a bidirectional traction flat car is arranged at the top of the multi-track bogie, and balance support legs are arranged at the bottom of the multi-track bogie.
Furthermore, the auxiliary operation platform system comprises an auxiliary operation platform, an equipment control cabinet is arranged at the bottom of the auxiliary operation platform, and a welding module power supply is arranged on one side of the equipment control cabinet.
Further, a steel plate ring support is fixed on one side of the assembling robot and used for storing steel plate rings; and an air compressor is arranged on one side of the epoxy resin glue barrel.
Further, the ovality of the inner wall of the tunnel is
Figure BDA0003093197570000031
When a is more than 20 per mill or the unidirectional deformation rate is 12 per mill<a1<And reinforcing the tunnel by 20 per mill.
Wherein D max Is the maximum outer diameter; d min Is the minimum outer diameter; d is the nominal outer diameter; a1 is the vertical deformation ratio.
When a is less than 6 per mill, the standard requirement is met, and reinforcement is not performed; 6 per mill < a <12 per mill, if the surrounding rock conditions are good, the structure is stable and can not be reinforced; 12 per mill < a <20 per mill or 9 per mill of single-direction deformation rate < a1<12 per mill, no obvious longitudinal crack and serious damage; and in the elastic stress stage, the influence of the assembling quality of the duct pieces is considered, and weak reinforcement is adopted.
Further, in the step 2), the elastic epoxy grout is injected into the annular and longitudinal seams in an inclined drilling mode under the condition that the grouting pressure is not more than 0.2 Mpa.
Furthermore, in the step 3), the joints between the two sides of the steel plate and the segment are sealed by epoxy cement, epoxy resin is injected between the segment and the grouting holes, and the pressure is controlled to be 0.1-0.15 MPa.
According to the technical scheme, the steel plate rings can be grabbed and installed at the preset positions through the assembling system, after the steel plate rings are initially installed in place, the steel plate rings can be fixed through punching and installing anchor bolts through the punching system, the welding system can weld joints among the steel plate rings, so that the steel plate rings in the tunnel are integrally fixed, the bottom system can ensure the overall operation and working stability of the device, the auxiliary operation platform can assist workers, the assembling system can realize automation and intellectualization of the grabbing, installing and placing processes of the steel plate rings, the installing positions and the steel plate rings are scanned firstly, the electric permanent magnetic chucks are aligned to the pre-installing positions after the electric permanent magnetic chucks are grabbed through the electric permanent magnetic disks, and the initial installation of the steel plate rings is finished The installation crab-bolt with screw up the crab-bolt, welding system all can realize automation and intellectuality with the seam welding between the steel sheet ring, has reduced the human cost.
Drawings
The above and/or additional aspects and advantages of the present invention will become apparent and readily appreciated from the following description of the embodiments, taken in conjunction with the accompanying drawings of which:
fig. 1 is a schematic structural view of a reinforcing apparatus provided by the present invention.
Figure 2 is an isometric view of a reinforcement device provided by the present invention.
Fig. 3 is a schematic structural diagram of the splicing system provided by the present invention.
Fig. 4 is a schematic structural diagram of a welding system provided by the present invention.
Fig. 5 is a schematic structural diagram of the punching system provided by the present invention.
Fig. 6 is a schematic structural view of the anchor bolt continuous feeding assembly provided by the invention.
Fig. 7 is a schematic structural view of a feeding gripper assembly provided by the present invention.
Fig. 8 is a schematic structural view of a steel plate ring support provided by the present invention.
Wherein 1-epoxy resin glue barrel; 2-an air compressor; 3, a punching robot sliding table; 4-a punching robot; 5-assembling the robot; 6-welding a robot sliding table; 7-a welding robot; 8-an auxiliary work platform; 9-equipment control cabinet; 10-welding module power supply; 11-a welding robot lifting platform; 12-steel plate ring support; 1201-support base, 1202-storage rack bottom plate, 1203-limiting block and 13-assembling robot sliding table; 14-a balance leg; 15-a punching robot lifting platform; 16-a multi-track bogie; 17-bidirectional traction flatbed; 18-installing a scanning positioning module; 19-electric permanent magnetic chuck; 20-a welding seam scanning and positioning module; 21-a robotic arc welding torch; 22-a punching module; 23-installing a module; 24-screwing the module; 25-anchor bolt continuous feeding assembly, 2501-socket, 2502-backing plate, 2503-anchor bolt fixing frame, 2504-socket base plate, 2505-anchor bolt, 26-feeding gripper assembly, 2601-first air cylinder, 2602-first air cylinder mounting seat, 2603-second air cylinder, 2604-second air cylinder mounting seat, 2605-third air cylinder, 2606-third air cylinder mounting seat and 2607-gripper assembly.
Detailed Description
In order that the above objects, features and advantages of the present invention can be more clearly understood, a more particular description of the invention, taken in conjunction with the accompanying drawings and detailed description, is set forth below. It should be noted that the embodiments of the present invention and features of the embodiments may be combined with each other without conflict.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention, however, the present invention may be practiced otherwise than as specifically described herein and, therefore, the scope of the present invention is not limited by the specific embodiments disclosed below.
Example 1
A shield tunnel segment repair process is characterized by comprising the following steps:
1) evaluating the deformation of the duct piece; scanning, detecting and collecting evaluation parameters of the inner wall of the tunnel according to a laser scanner and an industrial vision system; the evaluation parameters comprise ovality of the inner wall of the tunnel, dislocation and measurement of damaged crack gaps; determining a reinforcement position according to a scanning result, drawing up a reinforcement scheme, and preparing reinforcement equipment and materials;
ovality of tunnel inner wall of
Figure BDA0003093197570000051
When a is more than 20 per mill or the unidirectional deformation rate is 12 per mill<a1<Reinforcing the tunnel by 20 per mill;
wherein D max Is the maximum outer diameter; d min Is the minimum outer diameter; d is the nominal outer diameter; a1 is the vertical deformation ratio.
When a is less than 6 per mill, the standard requirement is met, and reinforcement is not performed; 6 per mill < a <12 per mill, if the surrounding rock conditions are good, the structure is stable and can not be reinforced; 12 per mill < a <20 per mill or 9 per mill < a1<12 per mill of unidirectional deformation rate, and no obvious longitudinal crack and serious breakage; and in the elastic stress stage, the influence of the assembling quality of the duct pieces is considered, and weak reinforcement is adopted.
2) Pre-treating; and (3) changing pipelines, cutting and chiseling a ballast bed, leveling the ring, longitudinal joints and hand hole plugs of the pipe pieces, keeping the leakage-free surfaces of the joints of the pipe pieces dry, polishing and roughening, and obliquely drilling holes and injecting elastic epoxy slurry into the middle ring and the longitudinal joints under the condition that the grouting pressure is not more than 0.2 Mpa.
In the pretreatment, pipeline changing is firstly carried out, a ballast bed is cut and chiseled, then, the oblique drilling holes of the pipe piece rings and the longitudinal joints are injected with elastic epoxy slurry, then, the pipe piece damage repair and the staggered repair are carried out, the post-grouting of the pipe piece walls is carried out to fill the holes and stop water, then, the bolt hand holes and the longitudinal joints of the pipe pieces are plugged by anti-crack mortar, and finally, after the surface of the joints of the pipe pieces is kept to be free of leakage and dry, the inner walls are polished and napped by a grinding machine.
The method comprises the following steps of (1) blocking and treating the damaged cracks of the duct piece according to four different conditions:
first water-impermeable fracture: injecting elastic epoxy resin slurry and epoxy adhesive by adopting the pressure in the crack;
and (3) water seepage cracks of a second type: firstly, pouring double-liquid slurry into a secondary grouting hole, then using oil polyurethane to perform local leakage stoppage, and finally sealing by using elastic epoxy resin slurry and epoxy adhesive;
the third one is not more than 0.2m 2 Partial breakage of (2): when the steel bar does not exceed the steel bar protective layer, high-strength epoxy mortar is used for repairing and sealing;
fourth is greater than 0.2m 2 Partial breakage of (2): and (4) repairing by using high-strength epoxy mortar, embedding a grouting pipe, and injecting elastic epoxy slurry into the grouting pipe.
In the pretreatment process, if the slab staggering is not more than 2cm, high-strength epoxy resin mortar is adopted for flattening, if the slab staggering is more than 2cm, quincunx bar planting is firstly carried out, and then the high-strength epoxy resin mortar is adopted for flattening.
3) Assembling steel plates by a reinforcing device, welding, grouting and spraying;
the reinforcing device comprises an assembling system, a punching system, a welding system, a bottom system, an auxiliary operation platform system and a steel plate ring support 12.
The system of assembling is including assembling robot 5, the one end of assembling robot 5 is provided with electric permanent magnetism sucking disc 19, the fixed installation scanning orientation module 18 that is provided with in top of electric permanent magnetism sucking disc 19, the bottom sliding connection who assembles robot 5 has and assembles robot slip table 13, the system of assembling is including assembling robot 5, the one end of assembling robot 5 is provided with electric permanent magnetism sucking disc 19, the fixed installation scanning orientation module 18 that is provided with in top of electric permanent magnetism sucking disc 19, the bottom sliding connection who assembles robot 5 has and assembles robot slip table 13. One side of the assembling robot 5 is fixedly provided with a steel plate ring bracket 12 for storing steel plate rings. The plate ring storage rack comprises a support base 1201, a storage rack bottom plate 1202 is arranged above the support base 1201, two limiting blocks 1203 are symmetrically arranged on the storage rack bottom plate 1202, each limiting block 1203 comprises four limiting blocks 1203, arc-shaped structures are arranged on the four limiting blocks 1203, the radian of the arc-shaped structures of the four limiting blocks 1203 is identical to the radian of a placed steel plate ring, the steel plate rings are limited in cooperation, overlapping placement of the steel plate rings can be achieved, and the steel plate rings are prevented from moving along with the bidirectional traction flat car 17 to generate displacement. One side that the robot 4 that punches kept away from and assembles robot 5 is provided with epoxy and glues bucket 1, and one side that epoxy glued bucket 1 is provided with air compressor 2, and air compressor 2 provides atmospheric pressure when being used for section of jurisdiction preliminary treatment, section of jurisdiction injecting glue and changeing the clear hole in hole, contains epoxy in the epoxy bucket for the welding seam injecting glue after the section of jurisdiction installation welding provides the raw materials.
The auxiliary operation platform system comprises an auxiliary operation platform 8, an equipment control cabinet 9 is arranged at the bottom of the auxiliary operation platform 8, and a welding module power supply 10 is arranged on one side of the equipment control cabinet 9.
The welding system comprises a welding robot 7, a welding robot sliding table 6, a welding robot lifting platform 11, a welding seam scanning and positioning module 20, a robot arc welding gun 21 and a welding seam detection module.
The punching system comprises a punching robot 4, a punching module 22, an installation module 23 and a screwing module 24 are arranged at one end of the punching robot 4, the bottom of the punching robot 4 is connected with a punching robot sliding table 3 in a sliding mode, and a punching robot lifting platform 15 is arranged at the bottom of the punching robot sliding table 3.
The punching system further comprises an anchor bolt continuous feeding assembly 25 and a feeding gripper assembly 26, wherein the anchor bolt continuous feeding assembly 25 comprises a socket 2501, a backing plate 2502, an anchor bolt fixing frame 2503, a socket plate 2504 and a plurality of anchor bolts 2505; wherein two ends of the backing plate 2502 are movably connected below the socket 2501 in an inserting manner; the anchor bolt fixing bracket 2503 is arranged below the backing plate 2502; a plurality of the anchor bolts 2505 are provided on the anchor bolt fixing bracket 2503. The number of the socket board 2504 is several, one end of which is vertically connected above the socket board 2501 and is parallel to the anchor bolt 2505; the anchor bolt fixing frame 2503 is a buckle or a clamping groove in which an electric permanent magnet block is arranged.
The feeding gripper assembly 26 is arranged at one end of the punching robot 4 and comprises a first cylinder mounting seat 2602 provided with a first cylinder 2601, a second cylinder mounting seat 2604 provided with a second cylinder 2603, a third cylinder mounting seat 2606 provided with a third cylinder 2605 and a gripper assembly 2607; wherein the first cylinder mount 2602 is coupled with the mobile module; the first cylinder 2601 is connected with the second cylinder mounting block 2604; the second cylinder 2603 is connected with a third cylinder mounting seat 2606; the third cylinder 2605 is connected with the gripper assembly 2607 through a gripper support; the gripper assembly 2607 grips the anchor bolt 2505 on the anchor bolt continuous feeder assembly 25 and aligns the anchor bolt 2505 to the installation module 23. After the gripper assembly 2607 grips the anchor bolt 2505, the third air cylinder 2605 is retracted to extend the gripper gripping anchor 2505, the second air cylinder 2603 and the third air cylinder 2605 a suitable distance to avoid collision of the gripper with other components as it rotates, the gripper assembly 2607 is rotated 180 to move the gripper downward, the first air cylinder 2601, the second air cylinder 2603 and the third air cylinder 2605 are retracted to an adjusted position to align the upper anchor 2505 of the gripper with the installation module 23 to install the anchor bolt 2505 in the borehole in cooperation with the installation module 23, and the tightening module 24 then tightens the nut on the anchor bolt 2505 to complete the installation of the anchor bolt 2505.
When the anchor bolt 2505 is used for feeding, the base plate 2502 which is movably connected below the socket 2501 in an inserting manner is drawn out, a buckle is fixed on the base plate 2502 in time, and the anchor bolt 2505 is clamped in the bayonet to feed the socket anchor bolt 2505.
The bottom system comprises a multi-track bogie 16, a bidirectional traction flat car 17 is arranged on the top of the multi-track bogie 16, and a balance leg 14 is arranged on the bottom of the multi-track bogie 16.
Wherein the bottom system comprises a bidirectional traction platform 17, a multi-track bogie 16, a balance leg 14 and a brake section. The double-traction flat car 17 is reserved with a bidirectional traction joint so as to ensure that when one end of the traction locomotive breaks down, equipment can be pulled away from the subway rail from the traction joint at the other end in time, and normal subway operation is not influenced. The multi-track bogie 16 can be operated on an operated subway tunnel and can also be operated on a built subway tunnel. The balance supporting legs 14 can be unfolded after the double-traction flat car is in place, so that the anti-overturning capacity of the equipment can be improved, and the stability of the equipment during operation can be ensured; the balance leg 14 can also be aligned to the subway tunnel axis during operation.
The assembling robot 5 positions the steel plate ring installation position and the steel plate ring position through an installation scanning positioning module 18, the moving path of the assembling robot 5 is calculated through a computer, an electric permanent magnetic chuck 19 is moved to one side of a steel plate ring storage rack, the steel plate ring is grabbed from the steel plate ring storage rack through the electric permanent magnetic chuck 19, the posture of the steel plate ring is adjusted through rotation, pitching and other actions of the assembling robot 5, the steel plate ring is assembled to the shield tunnel, the punching robot 4 is matched with a vision system to scan and position the punching position, a punching module 22 of the punching robot 4 punches holes, an M16 anchor bolt 2505 is installed on an installation module 23, a tightening module 24 tightens the anchor bolt 2505, the steel plate ring is fixed on the inner wall of a subway tunnel segment, the screwing depth is more than 125mm, the grouting depth is sequentially from bottom to top, the anchor bolt holes are reserved as a grouting hole and an exhaust hole, and after the installation operation of the whole ring steel plate ring is completed, the welding robot 7 passes through a robot lifting platform 11, The 7 gestures of welding robot are adjusted to robot slip table 6, and the seam of welding robot 7 scanning orientation module 20 positioning weld position, seam between the welding steel sheet ring, functions such as welding seam searching location, welding seam pursuit, welding seam detection can be realized to the welding system of robot. The bottom system is moved integrally, the auxiliary operation platform 8 assists workers in grouting and steel plate ring corrosion prevention spraying, the two sides of the steel plate and the joint of the duct piece are plugged by epoxy cement, epoxy resin is injected between the grouting hole and the duct piece, the pressure is controlled to be 0.1-0.15 Mpa, and finally the auxiliary operation platform assists workers in spraying rust prevention, corrosion prevention and fire-resistant coatings.
4) Recovering pipelines and track beds.
5) And (5) returning and checking.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. A shield tunnel segment repairing process is characterized by comprising the following steps:
1) evaluating the deformation of the duct piece; scanning, detecting and collecting evaluation parameters of the inner wall of the tunnel according to a laser scanner and an industrial vision system; the evaluation parameters comprise ovality of the inner wall of the tunnel, dislocation and damaged crack gap measurement;
2) pre-treating; changing pipelines, cutting and chiseling a ballast bed, plugging and floating the circular seams, longitudinal seams and hand holes of the duct pieces, keeping the seams of the duct pieces free of leakage and drying the surfaces, and then polishing and napping;
3) assembling steel plates by a reinforcing device, welding, grouting and spraying;
the reinforcing device comprises an assembling system, a punching system, a welding system, a bottom system, an auxiliary operation platform system, a steel plate ring support and an epoxy resin glue barrel; after the steel plate ring is grabbed and installed at a preset position by the assembling system, drilling and installing anchor bolts by the punching system, wherein the screwing depth is more than 125mm, the drilling is reserved as a grouting hole and an exhaust hole from bottom to top in sequence; the welding system welds the seams among the steel plate rings; the bottom system is integrally moved; after the auxiliary operation platform assists workers to perform pressure injection between the steel plate and the duct piece from the grouting hole, the anchor bolts are installed from the grouting hole and the exhaust hole, and finally the auxiliary operation platform assists the workers to perform spraying of antirust, anticorrosion and fireproof coatings;
4) recovering pipelines and a track bed;
5) and (5) returning to the field and checking.
2. The repair process according to claim 1, wherein the assembling system comprises an assembling robot, one end of the assembling robot is provided with an electric permanent magnetic chuck, an installation scanning and positioning module is fixedly arranged above the electric permanent magnetic chuck, and the bottom of the assembling robot is slidably connected with an assembling robot sliding table.
3. The repair process according to claim 1, wherein the punching system comprises a punching robot, one end of the punching robot is provided with a punching module, an installation module and a screwing module, the bottom of the punching robot is slidably connected with a punching robot sliding table, and the bottom of the punching robot sliding table is provided with a punching robot lifting platform.
4. The repair process according to claim 1, wherein the welding system comprises a welding robot, and one end of the welding robot is provided with a weld scanning and positioning module, a robotic arc welding gun and a weld detection module.
5. The repair process of claim 1 wherein the bottom system comprises a multi-track bogie with a bi-directional traction flatbed on top and a balance leg on the bottom.
6. The repair process according to claim 1, wherein the auxiliary work platform system comprises an auxiliary work platform, wherein an equipment control cabinet is arranged at the bottom of the auxiliary work platform, and a welding module power supply is arranged on one side of the equipment control cabinet.
7. The rehabilitation process according to claim 2, wherein the steel plate ring holder is fixed to one side of the erector robot for storing the steel plate rings; and an air compressor is arranged on one side of the epoxy resin glue barrel.
8. Repair process according to claim 1, characterized in that the ovality of the inner wall of the tunnel is
Figure FDA0003606661720000021
When the a is larger than 20 per thousand, reinforcing the tunnel; wherein D max The maximum outer diameter of the segment; d min The minimum outer diameter of the segment; d is the nominal outer diameter of the segment.
9. The repair process according to claim 1, wherein in the step 2), the ring and the longitudinal seam are drilled obliquely with elastic epoxy slurry under the grouting pressure of not more than 0.2 Mpa.
10. The repair process according to claim 1, wherein in step 3), the joints between the two sides of the steel plate and the segment are sealed by epoxy cement, and epoxy resin is injected between the segment and the injection hole, wherein the pressure is controlled to be 0.1-0.15 Mpa.
CN202110601870.4A 2021-05-31 2021-05-31 Shield tunnel segment repairing process Active CN113404518B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202110601870.4A CN113404518B (en) 2021-05-31 2021-05-31 Shield tunnel segment repairing process
PCT/CN2022/096374 WO2022253243A1 (en) 2021-05-31 2022-05-31 Complete device for repairing and reinforcing shield tunnel segments, and repair and reinforcement process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110601870.4A CN113404518B (en) 2021-05-31 2021-05-31 Shield tunnel segment repairing process

Publications (2)

Publication Number Publication Date
CN113404518A CN113404518A (en) 2021-09-17
CN113404518B true CN113404518B (en) 2022-07-26

Family

ID=77675395

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110601870.4A Active CN113404518B (en) 2021-05-31 2021-05-31 Shield tunnel segment repairing process

Country Status (1)

Country Link
CN (1) CN113404518B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2022253243A1 (en) * 2021-05-31 2022-12-08 中铁工程服务有限公司 Complete device for repairing and reinforcing shield tunnel segments, and repair and reinforcement process

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101457648A (en) * 2008-12-30 2009-06-17 中铁隧道勘测设计院有限公司 Full-ring steel tunnel segment structure with seal protection door
CN102080547A (en) * 2010-12-31 2011-06-01 上海市隧道工程轨道交通设计研究院 Method for plugging big aperture hand hole in shield tunnel
CN102979536A (en) * 2012-12-11 2013-03-20 上海市基础工程有限公司 Construction method for tunnel segment repair and reinforcement
CN103061780A (en) * 2012-12-25 2013-04-24 上海隧道工程股份有限公司 Operating tunnel structure reinforcement construction method through steel ring
CN104457572A (en) * 2014-12-04 2015-03-25 上海岩土工程勘察设计研究院有限公司 Method for extracting shield tunnel staggered joint and dislocation quantity on basis of three-dimensional scanning technology
CN106761812A (en) * 2017-01-17 2017-05-31 铁道第三勘察设计院集团有限公司 A kind of existing shield tunnel tunnel segment structure reinforcement means
CN111350522A (en) * 2020-03-23 2020-06-30 中铁二十五局集团第五工程有限公司 Reinforcing system for damaged segments of subway communication channel in construction period and construction method
JP2020117919A (en) * 2019-01-23 2020-08-06 Jfe建材株式会社 Composite segment, ring body and buried structure
CN112324475A (en) * 2020-10-30 2021-02-05 同济大学 Method for reinforcing shield tunnel lining structure
CN212837830U (en) * 2020-03-23 2021-03-30 中铁二十五局集团第五工程有限公司 Reinforcement system for reinforcing damaged segments of shield tunnel

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109339824A (en) * 2018-12-04 2019-02-15 中铁二十四局集团有限公司 A kind of duct pieces of shield tunnel Treatment Measures to Leakage method

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101457648A (en) * 2008-12-30 2009-06-17 中铁隧道勘测设计院有限公司 Full-ring steel tunnel segment structure with seal protection door
CN102080547A (en) * 2010-12-31 2011-06-01 上海市隧道工程轨道交通设计研究院 Method for plugging big aperture hand hole in shield tunnel
CN102979536A (en) * 2012-12-11 2013-03-20 上海市基础工程有限公司 Construction method for tunnel segment repair and reinforcement
CN103061780A (en) * 2012-12-25 2013-04-24 上海隧道工程股份有限公司 Operating tunnel structure reinforcement construction method through steel ring
CN104457572A (en) * 2014-12-04 2015-03-25 上海岩土工程勘察设计研究院有限公司 Method for extracting shield tunnel staggered joint and dislocation quantity on basis of three-dimensional scanning technology
CN106761812A (en) * 2017-01-17 2017-05-31 铁道第三勘察设计院集团有限公司 A kind of existing shield tunnel tunnel segment structure reinforcement means
JP2020117919A (en) * 2019-01-23 2020-08-06 Jfe建材株式会社 Composite segment, ring body and buried structure
CN111350522A (en) * 2020-03-23 2020-06-30 中铁二十五局集团第五工程有限公司 Reinforcing system for damaged segments of subway communication channel in construction period and construction method
CN212837830U (en) * 2020-03-23 2021-03-30 中铁二十五局集团第五工程有限公司 Reinforcement system for reinforcing damaged segments of shield tunnel
CN112324475A (en) * 2020-10-30 2021-02-05 同济大学 Method for reinforcing shield tunnel lining structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
某运营地铁隧道管片钢环加固工法介绍;杨勇;《现代物业(上旬刊)》;20121205(第12期);全文 *

Also Published As

Publication number Publication date
CN113404518A (en) 2021-09-17

Similar Documents

Publication Publication Date Title
WO2022253243A1 (en) Complete device for repairing and reinforcing shield tunnel segments, and repair and reinforcement process
CN111350522B (en) Reinforcing system for damaged segments of subway communication channel in construction period and construction method
CN113833480A (en) Shield initial tunneling and arrival construction method
CN112727504A (en) Subway tunnel steel ring lining reinforcement construction process
CN113404518B (en) Shield tunnel segment repairing process
CN113494295B (en) Butt joint construction method in ground of long shield tunnel
CN109578023A (en) The displaced type rotary jet grouting trolley and construction method that Tunnel Repair is reinforced
CN212837830U (en) Reinforcement system for reinforcing damaged segments of shield tunnel
CN114382505A (en) Steel lining reinforcing method
CN109778611B (en) Deviation rectifying method for ballastless track structure in railway tunnel
CN112727470B (en) Construction reinforcing method for shield tunnel at overlapped section
CN107642013A (en) A kind of subway route railway roadbed sleeper nylon sleeve crash handling construction method
CN112815144A (en) Artificial pipe jacking construction process
CN110905218A (en) Sectional hoisting process for super-large-span box-shaped steel beam
CN111946358B (en) Correction tool for treating shield tail deformation in water-rich sand layer and construction process of correction tool
CN116290809A (en) Modularized construction method for super high-rise pipe well vertical pipe
JP5642988B2 (en) Detachable guide jig and steel pipe pile construction method using the same
CN113090816A (en) Self-anchored internally-penetrated nodular cast iron pipe installation method
CN113464721A (en) Low-noise vibration-reduction slot-opening-free construction method and device for tunnel jacking pipe
CN107869139B (en) Pile planting machine with monitoring function
JP2017128907A (en) Jig for installation and covering from weather of lining plate and method for installation of lining plate using the jig
CN111322096A (en) Method for connecting tunnel primary support inverted arch with lower step arch
CN212568609U (en) Anchorage magnetic powder fluorescence flaw detector
CN215633004U (en) Be suitable for section of jurisdiction circumferential weld wrong platform controlling means in TBM tunnel
CN214368163U (en) Pipe ramming construction equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant