CN113404286A - Aluminum alloy template and wood template combined structure and construction method - Google Patents
Aluminum alloy template and wood template combined structure and construction method Download PDFInfo
- Publication number
- CN113404286A CN113404286A CN202110833467.4A CN202110833467A CN113404286A CN 113404286 A CN113404286 A CN 113404286A CN 202110833467 A CN202110833467 A CN 202110833467A CN 113404286 A CN113404286 A CN 113404286A
- Authority
- CN
- China
- Prior art keywords
- aluminum
- aluminum alloy
- template
- formwork
- angle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000838 Al alloy Inorganic materials 0.000 title claims abstract description 80
- 239000002023 wood Substances 0.000 title claims abstract description 59
- 238000010276 construction Methods 0.000 title claims abstract description 22
- XAGFODPZIPBFFR-UHFFFAOYSA-N aluminium Chemical compound [Al] XAGFODPZIPBFFR-UHFFFAOYSA-N 0.000 claims abstract description 141
- 229910052782 aluminium Inorganic materials 0.000 claims abstract description 126
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 34
- 239000010959 steel Substances 0.000 claims abstract description 34
- 238000009415 formwork Methods 0.000 claims description 53
- 230000003014 reinforcing effect Effects 0.000 claims description 11
- 238000009434 installation Methods 0.000 claims description 8
- 238000000034 method Methods 0.000 claims description 7
- 239000004411 aluminium Substances 0.000 description 23
- 238000003780 insertion Methods 0.000 description 7
- 230000037431 insertion Effects 0.000 description 7
- 235000017166 Bambusa arundinacea Nutrition 0.000 description 6
- 235000017491 Bambusa tulda Nutrition 0.000 description 6
- 241001330002 Bambuseae Species 0.000 description 6
- 235000015334 Phyllostachys viridis Nutrition 0.000 description 6
- 239000011425 bamboo Substances 0.000 description 6
- 238000003466 welding Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 230000007306 turnover Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G9/00—Forming or shuttering elements for general use
- E04G9/02—Forming boards or similar elements
- E04G9/06—Forming boards or similar elements the form surface being of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/001—Corner fastening or connecting means for forming or stiffening elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/02—Connecting or fastening means for non-metallic forming or stiffening elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/04—Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements
- E04G17/047—Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements simultaneously tying two facing forms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G9/00—Forming or shuttering elements for general use
- E04G9/02—Forming boards or similar elements
- E04G9/04—Forming boards or similar elements the form surface being of wood
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Wood Science & Technology (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention discloses an aluminum alloy template and wood template combined structure and a construction method, which comprises an aluminum alloy template and a wood template, wherein the side wall of the aluminum alloy template is fixedly welded with an angle aluminum frame plate, angle aluminum is inserted on the angle aluminum frame plate, the wood template is arranged on the angle aluminum, the angle aluminum is fixedly connected with the wood template through screws, a batten is arranged below the wood template, the batten is fixedly connected with the wood template through a steel nail, a double steel pipe is arranged below the batten, the double steel pipe is fixedly arranged in a top support, the top support is fixedly arranged on a vertical rod of a common frame body, and a special vertical rod for the aluminum alloy template is arranged below the aluminum alloy template. The aluminum alloy template and the wood template can be conveniently and quickly assembled and disassembled.
Description
Technical Field
The invention relates to the technical field of building construction devices, in particular to an aluminum alloy template and wood template combined structure and a construction method.
Background
In recent years, aluminum alloy templates have the characteristics of repeated use times, convenience in construction, high efficiency, good stability, difficulty in deformation, high concrete forming quality and the like, and are widely used in the building industry. However, because the aluminum alloy template needs to be deepened in advance, then the aluminum alloy template is processed and manufactured according to the specified size, the matched die is installed at the fixed position, each processing of the aluminum alloy template is a more complex and time-consuming process, and the manufacturing cost is very high and the cost performance is very low if the aluminum alloy template cannot be reused. Although the aluminum alloy template is widely used, the characteristics of multiple times of repeated use, convenient construction and high efficiency can be embodied only when a standard layer is constructed, but the defect of the aluminum alloy template causes the aluminum alloy template to be widely used but also limits the application range of the aluminum alloy template.
Therefore, the invention provides an aluminum alloy template and wood template combined structure and a construction method for solving the problems.
Disclosure of Invention
The invention aims to provide an aluminum alloy template and wood template combined structure and a construction method, which aim to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides an aluminum alloy template and plank sheathing integrated configuration and construction method, including aluminum alloy template and plank sheathing, the fixed welding of lateral wall of aluminum alloy template has angle aluminium frame board, it has angle aluminium to peg graft on the angle aluminium frame board, angle aluminium passes through the pin to be fixed on aluminum alloy template, the plank sheathing sets up on angle aluminium, and angle aluminium passes through screw fixed connection with the plank sheathing, be equipped with the flitch below the plank sheathing, pass through steel nail fixed connection between flitch and the plank sheathing, be equipped with two steel pipes below the flitch, two steel pipe fixed mounting are in the top support, top support fixed mounting is on ordinary support body pole setting, install the special pole setting of aluminum alloy template below the aluminum alloy template, all fixed mounting has fixed U type frame below the lower extreme lateral wall of aluminum alloy template and the side of flitch, be equipped with the connection anchor strut between the fixed U type frame.
Preferably, the special upright stanchion for the aluminum alloy template consists of an insertion rod, a bolt and a cylinder pole, the insertion rod is inserted in the cylinder pole, the upper end of the insertion rod is installed on the bottom surface of the aluminum alloy template, a first rod insertion hole is formed in the lower part of the insertion rod, a second insertion hole is formed in the upper end of the cylinder pole, and the bolt is installed on the second insertion hole.
Preferably, the connection reinforcing rod consists of a threaded cylinder and a threaded rod, the threaded rod is respectively installed at two ends of the threaded cylinder in a threaded mode, and the end portion of the threaded rod is provided with a bayonet.
Preferably, the thickness, the hole opening position and the aperture of the angle aluminum are consistent with those of the aluminum alloy template, and when the angle aluminum is completely inserted in the angle aluminum frame plate, the distance between the upper surface of the angle aluminum and the upper surface of the aluminum alloy template is equal to the thickness of the wood template.
Preferably, the reinforcing block is welded in the middle of the side wall of the angle aluminum frame plate in an integrated mode, and the upper surface of the reinforcing block is flush with the upper surface of the angle aluminum frame plate.
Preferably, the side of flitch is seted up flutedly, and the recess is provided with a plurality of, and quantity and angle aluminium's quantity phase-match, and the front end of angle aluminium is pegged graft in the recess, and the size of recess is unanimous with angle aluminium thickness.
Preferably, ordinary support body horizontal pole is connected between the ordinary support body pole setting and is formed wholly, and ordinary support body pole setting and ordinary support body horizontal pole are disconnected with the special support pole setting of aluminum alloy template.
The construction steps are as follows:
s1: adjusting the periphery of the aluminum die, and adding matched angle aluminum, wherein the thickness, the hole opening position and the aperture of the matched angle aluminum are consistent with those of the aluminum die;
s2: fixing the matched angle aluminum and the aluminum die by using a special pin for the aluminum die, and simultaneously correcting the installation quality in the fixing process;
s3: a steel pipe scaffold is adopted to support a wood formwork frame body, a secondary back ridge at the bottom of the formwork is made of battens, grooves are reserved on the battens at the joint positions of the battens and the angle aluminum so as to ensure that the battens are tightly combined with the formwork in the reinforcing process, and a main back ridge is made of common double steel pipes;
s4: after the frame body is erected and corrected, a wood template is laid, the wood template is fixed with angle aluminum through screws and fixed with battens through steel nails, the installation quality is checked after the template is laid, and steel bars are bound after the installation quality is checked;
s5: the adjacent wood formwork frame bodies are connected into a whole by steel pipes, the stability of the frame bodies is improved, and the frame bodies at the aluminum formwork positions are supported and reinforced by aluminum formwork special supporting vertical rods;
s6: when the template is dismantled, the frame body is locally dismantled, then the angle aluminum and the pin for fixing the aluminum mold are dismantled, after the aluminum mold and the angle aluminum are separated, the wood mold and the angle aluminum are dismantled together, and finally the angle aluminum and the wood mold are fixed and separated by a screw;
s7: and repeating the construction method in the steps S1-S6 until the project is finished.
Compared with the prior art, the invention has the beneficial effects that:
1. according to the construction method for combining the aluminum alloy template and the wood template, the matched angle aluminum is added to the aluminum mould, the thickness, the hole opening position and the aperture size of the matched angle aluminum are consistent with those of the aluminum mould, and the matched angle aluminum is fixed with the aluminum mould by using the special pin for the aluminum mould, so that the construction efficiency can be improved, and the aluminum alloy template and the wood template can be conveniently and quickly installed and detached;
2. according to the construction method for combining the aluminum alloy formwork and the wood formwork, adjacent wood formwork frame bodies are connected into a whole through the steel pipes, the stability of the frame bodies is improved, the frame bodies at the positions of the aluminum formworks are supported and reinforced through the aluminum formwork special supporting vertical rods, the aluminum alloy formwork frame bodies and the wood formwork frame bodies are not connected with each other, the respective formwork removal is not influenced, and the turnover utilization rate of the aluminum formwork is improved;
3. according to the construction method for combining the aluminum alloy template and the wood template, the wood template and the angle aluminum are fixed by the screws and are fixed by the steel nails, so that the construction method is simple and easy to operate, and can be used repeatedly and quicken the mounting and dismounting efficiency of the template.
Drawings
FIG. 1 is a perspective view of the present invention;
FIG. 2 is a front view of the structure of the present invention;
FIG. 3 is a perspective detail view of an aluminum alloy form;
FIG. 4 is a perspective detail view of an aluminum corner;
fig. 5 is a perspective view of a threaded cartridge and threaded rod configuration.
In the figure: the aluminum alloy formwork comprises an aluminum alloy formwork 1, a pin 2, an angle aluminum 3, a screw 4, a batten 5, a wood formwork 6, a double steel pipe 7, a groove 71, a jacking 8, a special upright rod 9 for the aluminum alloy formwork, an inserting rod 91, a bolt 92, a cylinder column rod 93, a common frame upright rod 10, a common frame cross rod 11, a steel nail 12, an angle aluminum frame plate 13, a reinforcing block 14, a threaded cylinder 15, a threaded rod 16 and a fixed U-shaped frame 17.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below. The embodiments of the present invention, and all other embodiments obtained by a person of ordinary skill in the art without any inventive work, belong to the scope of protection of the present invention.
Referring to fig. 1 to 5, the present invention provides a technical solution: an aluminum alloy template and wood template combined structure and a construction method thereof comprise an aluminum alloy template 1 and a wood template 6, wherein the side wall of the aluminum alloy template 1 is fixedly welded with an angle aluminum frame plate 13, angle aluminum 3 is inserted on the angle aluminum frame plate 13, the angle aluminum 3 is fixed on the aluminum alloy template 1 through a pin 2, the wood template 6 is arranged on the angle aluminum 3, and angle aluminium 3 passes through screw 4 fixed connection with plank sheathing 6, be equipped with flitch 5 below the plank sheathing 6, pass through steel nail 12 fixed connection between flitch 5 and the plank sheathing 6, be equipped with two steel pipes 7 below the flitch 5, two steel pipes 7 fixed mounting are in the top holds in the palm 8, 8 fixed mounting are held in the palm on ordinary support body pole setting 10 in the top, install the special pole setting 9 of aluminum alloy formwork below the aluminum alloy formwork 1, equal fixed mounting has fixed U type frame 17 below the lower extreme lateral wall of aluminum alloy formwork 1 and the side of flitch 5, be equipped with the connection anchor strut between the fixed U type frame 17.
The special upright stanchion 9 of aluminum alloy template comprises plug-in connection pole 91, bolt 92 and a section of thick bamboo post 93, and plug-in connection pole 91 is pegged graft in a section of thick bamboo post 93, and the bottom surface at aluminum alloy template 1 is installed to plug-in connection pole 91's upper end, and if pole spliced eye one has been seted up to plug-in connection pole 91's lower part, spliced eye two has been seted up to a section of thick bamboo post 93's upper end, installs bolt 92 on the spliced eye two, makes things convenient for plug-in connection pole 91's height to adjust like this.
Connect the anchor strut to comprise a screw thread section of thick bamboo 15 and threaded rod 16, threaded rod 16 is respectively threaded mounting at the both ends of a screw thread section of thick bamboo 15, and the bayonet socket has been seted up to the tip of threaded rod 16, makes things convenient for threaded rod 16 card like this on fixed U type frame 17, through the rotation of a screw thread section of thick bamboo 15, can consolidate aluminum alloy template 1 and flitch 5 for the connection between aluminum alloy template 1 and the flitch 5 is more firm.
The thickness, the trompil position, the aperture size of angle aluminium 3 are unanimous with aluminum alloy template 1, and when angle aluminium 3 was pegged graft in angle aluminium frame board 13 completely, the distance of 3 upper surfaces of angle aluminium 1 upper surfaces apart from aluminum alloy template equals the thickness of plank sheathing 6, can guarantee like this that 6 installation of plank sheathing are accomplished back and aluminum alloy template 1 levels and does not have the wrong platform.
Integral type welding has boss 14 in the middle of the lateral wall of angle aluminium frame board 13, and the upper surface of boss 14 and the upper surface parallel and level of angle aluminium frame board 13 make angle aluminium 3 peg graft like this behind angle aluminium frame board 13, and boss 14 can support angle aluminium 3 for be connected between angle aluminium 3 and the plank sheathing 6 is more firm.
The side of flitch 5 is seted up recess 71, and recess 71 is provided with a plurality ofly, and the quantity matches with the quantity of angle aluminium 3, and the front end of angle aluminium 3 is pegged graft in recess 71, and the size of recess 71 is unanimous with angle aluminium 3 thickness.
Ordinary support body horizontal pole 11 is connected between ordinary support body pole setting 10 and is formed wholly, increases overall structure's stability, and ordinary support body pole setting 10 and ordinary support body horizontal pole 11 are disconnected with aluminum alloy template special use support pole setting 9.
The construction steps are as follows:
s1, adjusting the periphery of the aluminum die 1, adding the matched angle aluminum 3, wherein the thickness, the hole opening position and the aperture size of the matched angle aluminum 3 are consistent with those of the aluminum die;
s2, fixing the matched angle aluminum 3 and the aluminum die 1 by using the special pin 2 for the aluminum die, and simultaneously correcting the installation quality of the pin 2 in the fixing process;
s3, erecting a wood formwork 6 frame body by adopting a steel pipe 10 scaffold, wherein a secondary back ridge at the bottom of the formwork 6 is made of a batten 5, a groove is reserved on the batten 5 at the joint position of the batten 5 and the angle aluminum 3 to ensure that the batten 5 is tightly combined with the formwork 6 in the reinforcing process, and a main back ridge is made of a common double steel pipe 7;
s4, after the frame body is erected and corrected, a wood template 6 is laid, the wood template 6 and the angle aluminum 3 are fixed through screws 4, the wood template 6 and the batten 5 are fixed through steel nails 12, after the template 6 is laid, the installation quality is checked, and after the checking is correct, steel bars are bound;
s5, the adjacent wood formwork 6 frame bodies are connected into a whole through steel pipes 10, the stability of the frame bodies is improved, and the frame bodies at the positions of the aluminum moulds 1 are supported and reinforced through supporting upright rods 9 special for the aluminum moulds 1;
s6, when the template 6 is removed, the frame body is partially removed, then the angle aluminum 3 and the pin 2 for fixing the aluminum mold are removed, after the aluminum mold 1 and the angle aluminum 3 are separated, the wood mold 6 and the angle aluminum 3 are removed together, and finally the angle aluminum 3 and the wood mold 6 are fixed and separated by the screw 4;
and S7, repeating the construction method in the steps S1-S6 until the project is finished.
The working principle is as follows: when the aluminum alloy template 1 and the wood template 6 are combined for use, firstly, the periphery of the aluminum mould 1 is adjusted by S, the matched angle aluminum 3 is inserted into the angle aluminum frame plate 13, then the angle aluminum 3 and the aluminum mould 1 are fixed by the pin 2, after the fixing is finished, a steel pipe 10 scaffold is adopted to support the frame body of the wood mould 6, then the bottom of the wood template 6 is built with the batten 5, the joint of the groove 71 of the batten 5 and the angle aluminum 3 is tightly combined, the top support 8 and the upright rod 10 of the common frame body are built below the batten 5, the double steel pipe 7 is fixedly arranged in the top support 8 to support the batten 5, after the building of the batten 5 is finished, the batten 5 and the wood template 6 are fixed by the steel nail 12, meanwhile, the wood template 6 and the angle aluminum 3 are fixed by the screw 4, then the threaded rods 16 at two ends of the threaded cylinder 15 are respectively clamped on the fixed U-shaped frames 17 on the aluminum alloy template 1 and the batten 5, realize being connected between aluminum alloy template 1 and the flitch 5, strengthen overall structure's stability, at last repeat operation like this, just can accomplish aluminum alloy template 1 and 6 builddings of plank sheathing.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.
Claims (8)
1. The utility model provides an aluminum alloy template and plank sheathing integrated configuration, includes aluminum alloy template (1) and plank sheathing (6), its characterized in that: the aluminum alloy formwork is characterized in that an angle aluminum frame plate (13) is fixedly welded on the side wall of the aluminum alloy formwork (1), angle aluminum (3) is inserted on the angle aluminum frame plate (13), the angle aluminum (3) is fixed on the aluminum alloy formwork (1) through a pin (2), a wood formwork (6) is arranged on the angle aluminum (3), the angle aluminum (3) is fixedly connected with the wood formwork (6) through a screw (4), a batten (5) is arranged below the wood formwork (6), the batten (5) is fixedly connected with the wood formwork (6) through a steel nail (12), double steel pipes (7) are arranged below the batten (5), the double steel pipes (7) are fixedly arranged in a top support (8), the top support (8) is fixedly arranged on a common frame body upright rod (10), an aluminum alloy formwork special upright rod (9) is arranged below the aluminum alloy formwork (1), and fixed U-shaped frames (17) are fixedly arranged below the side wall of the lower end of the aluminum alloy formwork (1) and the side edge of the batten (5), a connecting reinforcing rod is arranged between the fixed U-shaped frames (17).
2. The aluminum alloy formwork and wood formwork combination structure of claim 1, wherein: the special upright stanchion (9) for the aluminum alloy template is composed of an inserting rod (91), a bolt (92) and a cylinder column rod (93), the inserting rod (91) is inserted into the cylinder column rod (93), the upper end of the inserting rod (91) is installed on the bottom surface of the aluminum alloy template (1), a first inserting hole is formed in the lower part of the inserting rod (91), a second inserting hole is formed in the upper end of the cylinder column rod (93), and the bolt (92) is installed on the second inserting hole.
3. The aluminum alloy formwork and wood formwork combination structure of claim 1, wherein: the connecting reinforcing rod is composed of a thread cylinder (15) and a threaded rod (16), the threaded rod (16) is respectively installed at two ends of the thread cylinder (15) in a threaded mode, and a bayonet is formed in the end portion of the threaded rod (16).
4. The aluminum alloy formwork and wood formwork combination structure of claim 1, wherein: the thickness, the hole opening position and the aperture size of the angle aluminum (3) are consistent with those of the aluminum alloy template (1), and when the angle aluminum (3) is completely inserted in the angle aluminum frame plate (13), the distance between the upper surface of the angle aluminum (3) and the upper surface of the aluminum alloy template (1) is equal to the thickness of the wood template (6).
5. The aluminum alloy formwork and wood formwork combination structure of claim 1, wherein: the middle of the side wall of the angle aluminum frame plate (13) is integrally welded with a reinforcing block (14), and the upper surface of the reinforcing block (14) is flush with the upper surface of the angle aluminum frame plate (13).
6. The aluminum alloy formwork and wood formwork combination structure of claim 1, wherein: the side of the batten (5) is provided with a plurality of grooves (71), the number of the grooves (71) is matched with the number of the angle aluminum (3), the front end of the angle aluminum (3) is inserted into the grooves (71), and the size of the grooves (71) is consistent with the thickness of the angle aluminum (3).
7. The aluminum alloy formwork and wood formwork combination structure of claim 1, wherein: ordinary support body horizontal pole (11) are connected between ordinary support body pole setting (10) and are formed wholly, and ordinary support body pole setting (10) and ordinary support body horizontal pole (11) are disconnected with special support pole setting (9) of aluminum alloy template.
8. The aluminum alloy formwork and wood formwork combination structure as claimed in any one of claims 1 to 7, wherein the construction method comprises the following construction steps:
s1: the periphery of the aluminum die (1) is adjusted, the matched angle aluminum (3) is added, and the thickness, the hole opening position and the aperture size of the matched angle aluminum (3) are consistent with those of the aluminum die;
s2: fixing the matched angle aluminum (3) and the aluminum die (1) by using a special pin (2) for the aluminum die, and (2) simultaneously correcting the installation quality in the fixing process;
s3: a steel pipe (10) scaffold is adopted to support a wood formwork (6) frame body, a secondary back ridge at the bottom of the formwork (6) is made of battens (5), grooves are reserved on the battens (5) at the joint positions of the battens (5) and the angle aluminum (3) to ensure that the battens (5) are tightly combined with the formwork (6) in the reinforcing process, and a main back ridge is made of a common double steel pipe (7);
s4: after the frame body is erected and corrected, a wood template (6) is laid, the wood template (6) and the angle aluminum (3) are fixed through screws (4), and are fixed through steel nails (12) with battens (5), the installation quality is checked after the template (6) is laid, and steel bars are bound after the template is checked to be correct;
s5: the adjacent wooden template (6) frame bodies are connected into a whole by steel pipes (10), so that the stability of the frame body is improved, and the frame body at the position of the aluminum mould (1) is supported and reinforced by a special supporting upright rod (9) of the aluminum mould (1);
s6: when the template (6) is removed, the frame body is partially removed, then the angle aluminum (3) and the pin (2) for fixing the aluminum mold are removed, after the aluminum mold (1) and the angle aluminum (3) are separated, the wood mold (6) and the angle aluminum (3) are removed together, and finally the angle aluminum (3) and the wood mold (6) are fixed and separated by the screw (4);
s7: and repeating the construction method in the steps S1-S6 until the project is finished.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110833467.4A CN113404286A (en) | 2021-07-23 | 2021-07-23 | Aluminum alloy template and wood template combined structure and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110833467.4A CN113404286A (en) | 2021-07-23 | 2021-07-23 | Aluminum alloy template and wood template combined structure and construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN113404286A true CN113404286A (en) | 2021-09-17 |
Family
ID=77687364
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110833467.4A Pending CN113404286A (en) | 2021-07-23 | 2021-07-23 | Aluminum alloy template and wood template combined structure and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113404286A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113982131A (en) * | 2021-10-22 | 2022-01-28 | 重庆中科建设(集团)有限公司 | Construction method of disassembly-free insulation board |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106320691A (en) * | 2016-08-23 | 2017-01-11 | 中建八局第二建设有限公司 | Aluminum-wood formwork construction method |
CN110439259A (en) * | 2018-05-02 | 2019-11-12 | 深圳市前海胜德建筑科技有限公司 | Fit structure and construction method between aluminum alloy pattern plate and plank sheathing |
CN110541565A (en) * | 2019-09-05 | 2019-12-06 | 深圳市建工集团股份有限公司 | Aluminum-wood combined structure for root of non-standard layer wall column and construction method |
CN211058292U (en) * | 2019-11-06 | 2020-07-21 | 深圳市正知建筑技术有限公司 | Aluminum alloy template and wood template splicing structure |
CN211286595U (en) * | 2019-10-23 | 2020-08-18 | 北京建工博海建设有限公司 | OKS warm steel plate die carrier |
CN212015051U (en) * | 2020-04-08 | 2020-11-27 | 唐山润枫建筑工程有限公司 | Adjustable paper placing device for building construction |
CN212671266U (en) * | 2020-05-13 | 2021-03-09 | 唐山市规划建筑设计研究院 | Building structure's reinforcement connecting device |
-
2021
- 2021-07-23 CN CN202110833467.4A patent/CN113404286A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106320691A (en) * | 2016-08-23 | 2017-01-11 | 中建八局第二建设有限公司 | Aluminum-wood formwork construction method |
CN110439259A (en) * | 2018-05-02 | 2019-11-12 | 深圳市前海胜德建筑科技有限公司 | Fit structure and construction method between aluminum alloy pattern plate and plank sheathing |
CN110541565A (en) * | 2019-09-05 | 2019-12-06 | 深圳市建工集团股份有限公司 | Aluminum-wood combined structure for root of non-standard layer wall column and construction method |
CN211286595U (en) * | 2019-10-23 | 2020-08-18 | 北京建工博海建设有限公司 | OKS warm steel plate die carrier |
CN211058292U (en) * | 2019-11-06 | 2020-07-21 | 深圳市正知建筑技术有限公司 | Aluminum alloy template and wood template splicing structure |
CN212015051U (en) * | 2020-04-08 | 2020-11-27 | 唐山润枫建筑工程有限公司 | Adjustable paper placing device for building construction |
CN212671266U (en) * | 2020-05-13 | 2021-03-09 | 唐山市规划建筑设计研究院 | Building structure's reinforcement connecting device |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113982131A (en) * | 2021-10-22 | 2022-01-28 | 重庆中科建设(集团)有限公司 | Construction method of disassembly-free insulation board |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102704672B (en) | Installation construction method for large all-steel formwork at internal corner of shear wall | |
CN202706198U (en) | Building structure | |
CN113404286A (en) | Aluminum alloy template and wood template combined structure and construction method | |
CN210067045U (en) | Assembled energy-saving house | |
CN109235871B (en) | Construction method of variable cross-section structure aluminum alloy template | |
CN212078669U (en) | Formwork structure with wooden I-beam | |
CN102587665B (en) | Pouring method of coupled shear wall structure | |
CN209799400U (en) | Multifunctional pier column reinforcement jig frame | |
CN112196257A (en) | Aluminum alloy formwork construction method for variable-storey-height building | |
CN112343330A (en) | Cylinder wall construction method and cylinder wall template structure of large-diameter reinforced concrete cylinder | |
CN209686866U (en) | A kind of building frame structure square column circumference button formwork | |
CN113152878B (en) | Aluminum frame plastic formwork for building | |
CN103334582B (en) | Method for installing and constructing short-leg shear wall formwork supporting system | |
CN112196260A (en) | Assembly type template of foreign-style house outer eave concrete structure and construction method thereof | |
CN202055523U (en) | Supporting formwork component and supporting formwork for construction of building frame structural beams | |
CN112227681A (en) | Novel socket key groove type formwork support, formwork system and building method thereof | |
CN114892969B (en) | Unsupported template system and construction method thereof | |
CN215407373U (en) | Building template and building template structure | |
CN210767842U (en) | Slot type stair wood formwork | |
CN203891457U (en) | Form erecting device for fair-faced concrete external corner formworks | |
CN216840607U (en) | Stair well department arc wood grain clear water concrete beam template construction system | |
CN214302862U (en) | Combined square pipe truss support | |
CN212773471U (en) | Wood formwork supporting structure for beam | |
CN216552513U (en) | Fabricated batten wall constructional column prefabricated part based on straight tenon | |
CN212866977U (en) | Earthquake-resistant reinforcing structure of reinforced concrete building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20210917 |
|
RJ01 | Rejection of invention patent application after publication |