CN113389386A - Method for installing steel box-concrete combined structure - Google Patents

Method for installing steel box-concrete combined structure Download PDF

Info

Publication number
CN113389386A
CN113389386A CN202110789466.4A CN202110789466A CN113389386A CN 113389386 A CN113389386 A CN 113389386A CN 202110789466 A CN202110789466 A CN 202110789466A CN 113389386 A CN113389386 A CN 113389386A
Authority
CN
China
Prior art keywords
outer frame
steel box
decomposition
installation
unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110789466.4A
Other languages
Chinese (zh)
Inventor
何健
钱娟
陈航宇
王航
张佶
黄晓亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong 20 Metallurgical Construction Co ltd
China MCC20 Group Corp Ltd
Original Assignee
Guangdong 20 Metallurgical Construction Co ltd
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong 20 Metallurgical Construction Co ltd, China MCC20 Group Corp Ltd filed Critical Guangdong 20 Metallurgical Construction Co ltd
Priority to CN202110789466.4A priority Critical patent/CN113389386A/en
Publication of CN113389386A publication Critical patent/CN113389386A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/10Geometric CAD
    • G06F30/13Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Geometry (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Theoretical Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Electromagnetism (AREA)
  • Computational Mathematics (AREA)
  • Mathematical Analysis (AREA)
  • Mathematical Optimization (AREA)
  • Pure & Applied Mathematics (AREA)
  • Evolutionary Computation (AREA)
  • General Engineering & Computer Science (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a method for installing a steel box-concrete combined structure, which comprises the following steps: a decomposition step, namely decomposing the shear wall of the core cylinder steel box, the outer frame column and beam, the auxiliary operation platform and the safety protection facility; coding, namely coding each decomposition unit of the core cylinder steel box shear wall, each decomposition unit of the outer frame column and the outer frame beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility respectively, and establishing a database; manufacturing, namely manufacturing each decomposition unit of the core tube steel box shear wall, each decomposition unit of the outer frame column and the outer frame beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility, and conveying the decomposition units to a construction site; and in the mounting step, mounting the core cylinder steel box shear wall, the outer frame column and beam, the auxiliary operating platform and the safety protection facility. The invention carries out discretization decomposition on the main structure, unifies the manufacture and installation of all the decomposition units into rapid construction, and realizes seamless connection and efficient construction.

Description

Method for installing steel box-concrete combined structure
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a method for installing a steel box-concrete combined structure.
Background
In recent years, due to the promotion of national energy-saving and environment-friendly strategies, the rapid development of building industrialization and the weakening of labor supply in the building industry, high-energy building materials and modular assembly type construction methods are gradually popularized and applied to various buildings. The steel-concrete composite structure is increasingly applied to various buildings and is gradually popularized and applied to the field of super high-rise building structures. At present, steel box (steel tube) -concrete columns are applied to super high-rise buildings more, but steel box-concrete shear walls are applied less, so that the rapid installation of a steel box-concrete shear wall core tube + outer frame columns (steel tube concrete) and beam structure system cannot be realized.
Disclosure of Invention
In view of the above, the invention provides an installation method of a steel box-concrete combined structure, and aims to solve the problem that the prior art cannot realize the rapid installation of a steel box-concrete shear wall core tube + outer frame column and beam structure system.
The invention provides a method for installing a steel box-concrete combined structure, which comprises the following steps: a decomposition step, namely decomposing the shear wall of the core cylinder steel box, the outer frame column and beam, the auxiliary operation platform and the safety protection facility; coding, namely coding each decomposition unit of the core cylinder steel box shear wall, each decomposition unit of the outer frame column and the outer frame beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility respectively, and establishing a database; manufacturing, namely manufacturing each decomposition unit of the core tube steel box shear wall, each decomposition unit of the outer frame column and the outer frame beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility, and conveying the decomposition units to a construction site; and in the mounting step, mounting the core cylinder steel box shear wall, the outer frame column and beam, the auxiliary operating platform and the safety protection facility.
Further, in the method for installing the steel box-concrete composite structure, in the step of decomposing, the core cylinder steel box shear wall is decomposed into a plurality of box-type unit wall bodies; each decomposed box-type unit wall body meets the requirements of space scale, weight and rigidity for manufacturing, transportation and field hoisting, and meets the requirements of space positions of structural openings and beam-slab joints; the height of each box-type unit wall body after decomposition is 6-9 m, and the width of each box-type unit wall body is less than or equal to 4 m; and designing auxiliary rigidity reinforcing nodes, lifting points and auxiliary installation correcting nodes in manufacturing, transporting and installing projects of each decomposed box-type unit wall body.
Further, in the method for installing the steel box-concrete composite structure, in the step of decomposing, the outer frame column is decomposed into a plurality of column units, and the outer frame beam is decomposed into a plurality of beam units; each decomposed column unit meets the requirements of space scale, weight and rigidity for manufacturing, transportation and field hoisting, and meets the requirements of space positions of beam and plate joints; the height of each decomposed column unit is 6-9 m; decomposing and combining the decomposed beam units according to the installation sequence and the hoisting batches; and designing auxiliary rigidity strengthening nodes and lifting points, auxiliary installation correcting nodes and auxiliary installation bolts of each decomposed column unit and each decomposed beam unit in manufacturing, transporting and installing projects.
Further, in the installation method of the steel box-concrete combined structure, in the decomposition step, the auxiliary operation platform and the safety protection facilities are decomposed into a plurality of decomposition units according to the structure construction sequence.
Further, in the installation method of the steel box-concrete combined structure, in the coding step, each decomposition unit of the core cylinder steel box shear wall, each decomposition unit of the outer frame column and the beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility are coded according to respective installation sequence, and the codes of each decomposition unit are recorded into a system to establish a database.
Further, in the installation method of the steel box-concrete combined structure, in the coding step, two-dimensional codes are set for the decomposition units according to the codes of the decomposition units.
Further, in the installation method of the steel box-concrete combined structure, in the manufacturing step, a two-dimensional code nameplate is arranged on each decomposition unit.
Further, in the installation method of the steel box-concrete combined structure, in the installation step, the core barrel is advanced, and the shear wall and the outer frame column are installed in a manner that concrete does not occupy the time of the steel structure installation process when being poured into the steel box-concrete combined structure.
Further, in the installation method of the steel box-concrete composite structure, in the installation step, the maximum free height of the core cylinder steel box shear wall exceeding the horizontal floor slab is 12-18 m; the maximum free height of the outer frame column exceeding the horizontal floor slab is 6-9 m; the maximum lagging layer number of concrete poured in the core tube steel box shear wall and the outer frame column is lower than 1 floor support plate layer; or pouring concrete into the core tube steel box shear wall and the outer frame columns, wherein the maximum lagging layer number lags behind the installation height of the core tube steel box shear wall by 16-22 m and the lagging behind outer frame column by 9-14 m; the core tube steel box shear wall, the outer frame column and the steel beam plate of each layer form a mounting ring, after one mounting ring is mounted, 2 layers of units with the height of 4 floors are mounted in advance on the core tube steel box shear wall in the next mounting ring, 1 layer of units with the height of 2 floors are mounted in advance on the outer frame column, and concrete is poured into the core tube steel box shear wall and the outer frame column and lags behind by 1 floor.
Further, in the installation method of the steel box-concrete combined structure, in the installation step, the concrete in the shear wall of the core cylinder steel box and the outer frame column is poured in a top-throwing pouring or side-throwing pouring mode.
According to the method, a core cylinder steel box shear wall, an outer frame column and a beam, an auxiliary operation platform and a safety protection facility are firstly decomposed, all the decomposition units are coded to establish a database, then all the decomposition units are manufactured, and then the core cylinder steel box shear wall, the outer frame column and the beam, the auxiliary operation platform and the safety protection facility are installed The problem of rapid installation of beam structure systems.
Drawings
Various other advantages and benefits will become apparent to those of ordinary skill in the art upon reading the following detailed description of the preferred embodiments. The drawings are only for purposes of illustrating the preferred embodiments and are not to be construed as limiting the invention. Also, like reference numerals are used to refer to like parts throughout the drawings. In the drawings:
FIG. 1 is a flow chart of a method for installing a steel box-concrete composite structure according to an embodiment of the present invention;
fig. 2 is an exploded schematic view of a core tube steel box shear wall in the method for installing a steel box-concrete composite structure according to the embodiment of the present invention;
fig. 3 is a schematic diagram of a disassembled box-type unit wall in the installation method of the steel box-concrete composite structure according to the embodiment of the invention;
fig. 4 is another schematic diagram of the disassembled box-type unit wall in the installation method of the steel box-concrete composite structure according to the embodiment of the invention;
fig. 5 is a schematic view of an exploded outer frame column in the method for installing a steel box-concrete composite structure according to the embodiment of the present invention;
fig. 6 is a schematic diagram of an exploded outer frame beam in the method for installing the steel box-concrete composite structure according to the embodiment of the present invention.
Detailed Description
Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be embodied in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the disclosure to those skilled in the art. It should be noted that the embodiments and features of the embodiments may be combined with each other without conflict. The present invention will be described in detail below with reference to the embodiments with reference to the attached drawings.
Referring to fig. 1, fig. 1 is a flow chart illustrating an installation method of a steel box-concrete composite structure according to an embodiment of the present invention. As shown in the figure, the installation method of the steel box-concrete composite structure comprises the following steps:
and a decomposition step S1, decomposing the core cylinder steel box shear wall, the outer frame column and beam, the auxiliary operation platform and the safety protection facility.
Specifically, the core cylinder steel box shear wall, the outer frame column and the beam, the auxiliary operation platform and the safety protection facility are respectively decomposed.
When the core tube steel box shear wall is decomposed, the core tube steel box shear wall is decomposed into a plurality of box-type unit wall bodies. Specifically, referring to fig. 2, the core tube steel box shear wall is discretized and decomposed into m small box-type unit walls in a simulated manner to meet the manufacturing, transportation and installation requirements.
The design principle of discrete decomposition is as follows:
(1) the decomposed box-type unit wall bodies meet the requirements of space scale, weight and rigidity for manufacturing, transportation and field hoisting.
(2) The decomposed box-type unit wall bodies meet the space position requirements of structural openings and beam-slab joints, and meanwhile, on-site assembly welding seams are avoided at the positions with maximum stress or stress concentration.
(3) The height of each box-type unit wall body after decomposition is 6-9 m, the width is less than or equal to 4m, and on-site high-altitude assembly welding seams are reduced as much as possible.
(4) And designing auxiliary rigidity reinforcing nodes, lifting points and auxiliary installation correcting nodes in manufacturing, transporting and installing projects of each decomposed box-type unit wall body.
When the outer frame columns and the beams are decomposed, the outer frame columns are decomposed into a plurality of column units, and the outer frame beams are decomposed into a plurality of beam units. Specifically, referring to fig. 3 to 6, the outer frame columns and beams are discretized, the outer frame columns are decomposed into n column units and the outer frame beams are decomposed into k beam units in a simulation manner, so as to meet the batch manufacturing, transportation and installation requirements.
The design principle of discrete decomposition is as follows:
(1) the decomposed column units meet the requirements of space scale, weight and rigidity for factory manufacture, transportation and field hoisting.
(2) The decomposed column units meet the requirements of beam and plate joints and other spatial positions, and meanwhile, the on-site assembly welding seam is avoided at the position with the maximum stress or stress concentration.
(3) The height of each decomposed column unit is 6-9 m, and on-site high-altitude assembly welding seams are reduced as much as possible.
(4) And decomposing and combining the decomposed outer frame beam units according to the installation sequence and the hoisting batches.
(5) And designing auxiliary rigidity strengthening nodes and lifting points, auxiliary installation correcting nodes and auxiliary installation bolts of each decomposed column unit and each decomposed beam unit in manufacturing, transporting and installing projects.
When the auxiliary operation platform and the safety protection facilities are decomposed, the auxiliary operation platform and the safety protection facilities are decomposed into a plurality of decomposition units according to the structure construction sequence. Specifically, the auxiliary operation platform and the safety protection facilities of the core tube steel box shear wall, the outer frame column and the beam are dispersed according to the structural construction sequence and are decomposed into j hoisting units or hoisting batches, including turnover hoisting.
And a coding step S2, coding each decomposition unit of the core tube steel box shear wall, each decomposition unit of the outer frame column and the outer frame beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility respectively, and establishing a database.
Specifically, each decomposition unit of the core tube steel box shear wall, each decomposition unit of the outer frame column and the beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility are coded according to respective installation sequence, and the codes of each decomposition unit are recorded into a system to establish a database.
More specifically, each decomposition unit of the core cylinder steel box shear wall (code is W for short) is coded according to the installation sequence (W)1、W2、W3………Wm). Coding each decomposition unit of outer frame column and beam (coding is abbreviated as C) according to installation sequence (C)1、C2、C3………Cn). Coding each decomposition unit of the auxiliary operation platform and the safety protection facility (coding is abbreviated as S) according to the installation sequence (S)1、S2、S3………Sj). And recording the codes of all the decomposition units into a computer system, and establishing a database of the units and the components.
Preferably, a two-dimensional code is set for each decomposition unit according to the code of each decomposition unit, so as to facilitate subsequent tracking identification.
And a manufacturing step S3, manufacturing all the decomposition units of the core tube steel box shear wall, all the decomposition units of the outer frame columns and beams, all the decomposition units of the auxiliary operation platform and all the decomposition units of the safety protection facility, and conveying the decomposition units to a construction site.
Specifically, the decomposition units of the core tube steel box shear wall, the decomposition units of the outer frame columns and beams, the auxiliary operation platform and the decomposition units of the safety protection facility are organized according to design requirements, and are organized according to the installation sequence and transported to an installation construction site.
Preferably, all set up the data plate of two-dimensional code to every decomposition unit, like this, can look over the information and transportation, the installation status of each decomposition unit, component through sweeping the sign indicating number.
And an installation step S4, namely installing the core cylinder steel box shear wall, the outer frame columns and beams, the auxiliary operation platform and the safety protection facilities.
Specifically, the principle of field installation is as follows:
(1) the installation is carried out on the principle that the core tube is advanced, and concrete is poured into the shear wall and the outer frame column without occupying the time of the steel structure installation procedure. Specifically, the core tube is firstly advanced, and the key process time of steel structure installation is not occupied by concrete poured in the shear wall and the outer frame column, so that rapid installation is realized.
(2) The maximum free height of the core tube steel box shear wall exceeding the horizontal floor slab is 12-18 m. Specifically, the maximum free height of the core tube steel box shear wall exceeding the horizontal floor slab is calculated according to on-site wind pressure check, and the maximum free height of the core tube steel box shear wall exceeding the horizontal floor slab is controlled to be 12-18 m.
(3) The maximum free height of the outer frame column exceeding the horizontal floor slab is 6-9 m. Specifically, the maximum free height of the outer frame column exceeding the horizontal floor slab is calculated according to on-site wind pressure check, and the maximum free height of the outer frame column exceeding the horizontal floor slab is controlled to be 6-9 m.
(4) The maximum lagging layer number of concrete poured in the core tube steel box shear wall and the outer frame column is lower than 1 floor support plate layer; or the maximum lagging layers of concrete are poured into the core tube steel box shear wall and the outer frame columns, and the mounting height of the core tube steel box shear wall is 16-22 m and the mounting height of the outer frame columns is 9-14 m.
Specifically, the maximum lagging layer number of concrete poured in the core tube steel box shear wall and the outer frame column is checked and calculated according to on-site wind pressure and steel structure system correction factors, and the maximum lagging layer number is controlled to be lower than 1 floor or the installation height of the lagging core tube steel box shear wall is 16-22 m, and the installation height of the lagging outer frame column is 9-14 m. That is to say, the limitation of the maximum lagging layer number of the concrete poured in the core tube steel box shear wall and the outer frame column can be that the requirement of 'being lower than the floor deck 1 layer', the requirement of 'the installation height of the lagging core tube steel box shear wall is 16-22 m, and the installation height of the lagging outer frame column is 9-14 m', and the two limitation conditions are selected.
(5) The core tube steel box shear wall, the outer frame column and the steel beam plate of each layer form a mounting ring, after one mounting ring is mounted, 2 layers of units with the height of 4 floors are mounted in advance on the core tube steel box shear wall in the next mounting ring, 1 layer of units with the height of 2 floors are mounted in advance on the outer frame column, and concrete is poured into the core tube steel box shear wall and the outer frame column and lags behind by 1 floor.
(6) And pouring concrete in the core cylinder steel box shear wall and the outer frame column in a top casting or side casting manner.
Specifically, the concrete in the core tube steel box shear wall and the outer frame column adopts a top casting pouring or side casting pouring mode according to steel structure installation line production, and does not occupy the key process time of structure installation.
It can be seen that in the embodiment, the core tube steel box shear wall, the outer frame column and beam, the auxiliary operation platform and the safety protection facility are firstly decomposed, each decomposition unit is coded to establish a database, then each decomposition unit is manufactured, and then the core tube steel box shear wall, the outer frame column and beam, the auxiliary operation platform and the safety protection facility are installed The problem of rapid installation of beam structure systems.
It should be noted that in the description of the present invention, the terms of direction or positional relationship indicated by the terms "upper", "lower", "left", "right", "inner", "outer", etc. are based on the directions or positional relationships shown in the drawings, which are only for convenience of description, and do not indicate or imply that the device or element must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention.
Furthermore, it should be noted that, in the description of the present invention, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
It will be apparent to those skilled in the art that various changes and modifications may be made in the present invention without departing from the spirit and scope of the invention. Thus, if such modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include such modifications and variations.

Claims (10)

1. The installation method of the steel box-concrete combined structure is characterized by comprising the following steps of:
a decomposition step, namely decomposing the shear wall of the core cylinder steel box, the outer frame column and beam, the auxiliary operation platform and the safety protection facility;
coding, namely coding each decomposition unit of the core cylinder steel box shear wall, each decomposition unit of the outer frame column and the outer frame beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility, and establishing a database;
manufacturing, namely manufacturing each decomposition unit of the core tube steel box shear wall, each decomposition unit of the outer frame column and the outer frame beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility, and conveying the decomposition units to a construction site;
and in the mounting step, the core tube steel box shear wall, the outer frame columns and beams, the auxiliary operating platform and the safety protection facilities are mounted.
2. The method of installing a steel box-concrete composite structure according to claim 1, wherein in the disassembling step,
decomposing the core tube steel box shear wall into a plurality of box-type unit walls;
each decomposed box-type unit wall body meets the requirements of space scale, weight and rigidity for manufacturing, transportation and field hoisting, and meets the requirements of space positions of structural openings and beam-slab joints;
the height of each box-type unit wall body after decomposition is 6-9 m, and the width of each box-type unit wall body is less than or equal to 4 m;
and designing auxiliary rigidity reinforcing nodes, lifting points and auxiliary installation correcting nodes in manufacturing, transporting and installing projects of each decomposed box-type unit wall body.
3. The method of installing a steel box-concrete composite structure according to claim 1, wherein in the disassembling step,
decomposing the outer frame column into a plurality of column units and the outer frame beam into a plurality of beam units;
each decomposed column unit meets the requirements of space scale, weight and rigidity for manufacturing, transportation and field hoisting, and meets the requirements of space positions of beam and plate nodes;
the height of each decomposed column unit is 6-9 m;
decomposing and combining the decomposed beam units according to the installation sequence and the hoisting batches;
and designing auxiliary rigidity strengthening nodes, hoisting points, auxiliary installation correcting nodes and auxiliary installation bolts of each decomposed column unit and each decomposed beam unit in manufacturing, transporting and installing projects.
4. The method of installing a steel box-concrete composite structure according to claim 1, wherein in the disassembling step,
and decomposing the auxiliary operation platform and the safety protection facilities into a plurality of decomposition units according to the structure construction sequence.
5. The method for installing a steel box-concrete composite structure according to claim 1, wherein in the coding step,
and coding each decomposition unit of the core tube steel box shear wall, each decomposition unit of the outer frame column and the outer frame beam, each decomposition unit of the auxiliary operation platform and each decomposition unit of the safety protection facility according to respective installation sequence, recording the codes of each decomposition unit into a system, and establishing a database.
6. The steel box-concrete composite structure installation method according to claim 5, wherein, in the coding step,
and setting a two-dimensional code for each decomposition unit according to the code of each decomposition unit.
7. The method for installing a steel box-concrete composite structure according to claim 6, wherein in the step of manufacturing,
and arranging a two-dimensional code nameplate for each decomposition unit.
8. The steel box-concrete composite structure installation method according to claim 1, wherein in said installation step,
the installation is carried out on the principle that the core tube is advanced, and concrete is poured into the shear wall and the outer frame column without occupying the time of the steel structure installation procedure.
9. The steel box-concrete composite structure installation method according to claim 1, wherein in said installation step,
the maximum free height of the core tube steel box shear wall exceeding the horizontal floor slab is 12-18 m;
the maximum free height of the outer frame column exceeding the horizontal floor slab is 6-9 m;
the maximum lagging layer number of the core tube steel box shear wall and the outer frame column after concrete is poured is lower than 1 floor support plate layer; or the maximum lagging layer number of concrete poured in the core tube steel box shear wall and the outer frame column lags behind the installation height of the core tube steel box shear wall by 16-22 m and lags behind the installation height of the outer frame column by 9-14 m;
the core section of thick bamboo steel case shear force wall, outer frame post and the girder steel plate-type of each layer form a collar, accomplish one after the installation the collar, next in the collar 2 layer unit 4 floor height is installed in advance to the core section of thick bamboo steel case shear force wall, 1 layer unit 2 floor height is installed in advance to the outer frame post, core section of thick bamboo steel case shear force wall the pouring concrete lags behind 1 floor height in the outer frame post.
10. The steel box-concrete composite structure installation method according to claim 1, wherein in said installation step,
and the core cylinder steel box shear wall and the concrete in the outer frame column are poured in a top casting or side casting manner.
CN202110789466.4A 2021-07-13 2021-07-13 Method for installing steel box-concrete combined structure Pending CN113389386A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110789466.4A CN113389386A (en) 2021-07-13 2021-07-13 Method for installing steel box-concrete combined structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110789466.4A CN113389386A (en) 2021-07-13 2021-07-13 Method for installing steel box-concrete combined structure

Publications (1)

Publication Number Publication Date
CN113389386A true CN113389386A (en) 2021-09-14

Family

ID=77625895

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110789466.4A Pending CN113389386A (en) 2021-07-13 2021-07-13 Method for installing steel box-concrete combined structure

Country Status (1)

Country Link
CN (1) CN113389386A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120304584A1 (en) * 2011-05-30 2012-12-06 National Taiwan University Of Science And Technology Architectured reinforcement structure
CN108560718A (en) * 2018-03-19 2018-09-21 广州容柏生建筑工程设计咨询有限公司 A kind of Core Walls Structure system and preparation method thereof of new steel plate compound shear wall composition
CN111639371A (en) * 2020-05-07 2020-09-08 中国化学工程重型机械化有限公司 Novel modular design method for steel structure

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20120304584A1 (en) * 2011-05-30 2012-12-06 National Taiwan University Of Science And Technology Architectured reinforcement structure
CN108560718A (en) * 2018-03-19 2018-09-21 广州容柏生建筑工程设计咨询有限公司 A kind of Core Walls Structure system and preparation method thereof of new steel plate compound shear wall composition
CN111639371A (en) * 2020-05-07 2020-09-08 中国化学工程重型机械化有限公司 Novel modular design method for steel structure

Similar Documents

Publication Publication Date Title
Ferdous et al. New advancements, challenges and opportunities of multi-storey modular buildings–A state-of-the-art review
CN107090925B (en) Reinforced precast reinforced concrete shear wall, structural system and construction method thereof
Banks et al. Enhancing high-rise residential construction through design for manufacture and assembly–a UK case study
CN107761950B (en) Assembled reinforced concrete angle support frame and construction method thereof
Hong et al. Composite beam composed of steel and precast concrete (modularized hybrid system). Part III: Application for a 19‐storey building
CN112502714B (en) Assembled shaft barrel structure and design and construction method
Liew et al. Steel concrete composite systems for modular construction of high-rise buildings
CN113882712A (en) Temporary support reinforcing method for large-scale suspension type steel structure construction
Oval et al. A prototype low-carbon segmented concrete shell building floor system
Liew et al. Innovation in modular building construction
Gong et al. A Review of Key Technologies Development of Super High‐Rise Building Construction in China
CN104631629A (en) Assembling type frame structure
Oval et al. A path towards off-site automated fabrication of segmented concrete shells as building floors
CN112681511B (en) Reinforced concrete structure construction method using section steel to replace part of reinforcing steel bars
CN113389386A (en) Method for installing steel box-concrete combined structure
Munmulla et al. Sustainable approaches to improve the resilience of modular buildings under wind loads
CN113356361A (en) Production and assembly process of assembled building component based on steel-concrete composite section bar
CN112983090B (en) Silo top and construction method thereof
CN206554265U (en) A kind of suspension type modular architectural structural
CN212453063U (en) Assembly and pouring integrated shear wall structure building system
WO2018163134A1 (en) Hexagonal flanged prefabricated connection
Ismail et al. Computational structural design and fabrication of hollow-core concrete beams
Wang Evolution of modern mega-buildings in China: innovations and sustainability
Seo et al. Case study of a synchronous hydraulic jack-up system for constructing high-rise residential buildings
CN111597623A (en) Petrochemical device modular design method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210914