CN113374502A - Construction method for reinforcing cavity by splicing lining grouting based on mine method tunnel construction - Google Patents

Construction method for reinforcing cavity by splicing lining grouting based on mine method tunnel construction Download PDF

Info

Publication number
CN113374502A
CN113374502A CN202110863769.6A CN202110863769A CN113374502A CN 113374502 A CN113374502 A CN 113374502A CN 202110863769 A CN202110863769 A CN 202110863769A CN 113374502 A CN113374502 A CN 113374502A
Authority
CN
China
Prior art keywords
grouting
prefabricated
tunnel
longitudinal
prefabricated pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110863769.6A
Other languages
Chinese (zh)
Other versions
CN113374502B (en
Inventor
宁远思
王聚山
杨光华
陈海锋
何泉
蔡建刚
李成立
刘盛
张蕉
齐如见
李洋
司鹏
江明锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
China Railway Chengdu Group Co Ltd
China Railway Tunnel Group Yichu Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
China Railway Chengdu Group Co Ltd
China Railway Tunnel Group Yichu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG, China Railway Chengdu Group Co Ltd, China Railway Tunnel Group Yichu Co Ltd filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN202110863769.6A priority Critical patent/CN113374502B/en
Publication of CN113374502A publication Critical patent/CN113374502A/en
Application granted granted Critical
Publication of CN113374502B publication Critical patent/CN113374502B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a construction method for reinforcing a cavity by splicing lining grouting based on mine tunnel construction, which comprises the following steps of: step A, early-stage work preparation; b, grouting after the arch crown is backfilled with concrete, and stopping grouting when mortar overflows from the exhaust pipe; step C, radial grouting: after the radial grouting holes are punched through by electric drills, the radial grouting holes are used for grouting, when the exhaust pipe overflows, grouting is stopped, and the radial grouting holes are blocked by grouting hole spiral pipes; step D, longitudinal seam grouting: blocking the prefabricated duct piece and the outer side of the morning joint of the side wall by using mortar, and then grouting from a longitudinal joint grouting hole; and E, constructing the next group of tunnel linings according to the sequence of the steps A-D until the secondary lining of the tunnel is completely constructed. The invention relates to a construction method capable of solving the problem of cavities between a prefabricated pipe piece and a primary support and at the splicing position of the prefabricated pipe piece and a side wall.

Description

Construction method for reinforcing cavity by splicing lining grouting based on mine method tunnel construction
Technical Field
The invention relates to a tunnel concrete lining construction technology, in particular to a construction method for reinforcing cavities by cast-in-place grouting of prefabricated pipe pieces and side walls of tunnel arch parts.
Background
The mining method adopts the traditional construction process of the secondary lining of the tunnel, and adopts the principle that the gravity of concrete is utilized to fill the space of the secondary lining by injecting the concrete into the vertical pouring hole at the top part hole by hole. Because the fluidity of the concrete is difficult to reach an ideal state, after the concrete is poured into the vault of the tunnel, the whole pouring longitudinal section is basically in isosceles triangle normal distribution, the isosceles sides of the isosceles triangles change along with the size of the distance between the pouring openings, the larger the distance between the pouring openings is, the longer the isosceles triangle is, and the larger the gap is after the two backing materials is, the larger the gap is. This phenomenon also can change along with the size of concrete pump pressure that pours, and the evacuation phenomenon can reduce when pouring pressure is bigger than normal, and the evacuation phenomenon can increase when pouring pressure is bigger than normal, and the air between two vault pouring orifices also is difficult whole evacuation simultaneously, and the appearance of vault cavity phenomenon is inevitable.
Therefore, the traditional construction process of the tunnel secondary lining is limited by the existing pouring construction equipment and process, and the phenomenon of back void of the arch part of the secondary lining is common.
Disclosure of Invention
The invention aims to provide a construction method for reinforcing a cavity by splicing lining grouting based on mine tunnel construction, which has simple steps and clear operation and solves the problem of cavities between a prefabricated duct piece and a primary support and between the prefabricated duct piece and a side wall.
Therefore, the technical scheme adopted by the invention is as follows: a construction method for reinforcing a cavity by splicing lining grouting based on mine method tunnel construction comprises the following steps:
step A, early-stage work preparation: the method comprises the steps of pouring side walls in situ, conveying prefabricated pipe pieces into a tunnel after prefabrication outside the tunnel is completed, and longitudinally installing the prefabricated pipe pieces in groups, wherein at least two radial grouting holes with unpenetrated outer walls are formed in the prefabricated pipe pieces, two ends of each prefabricated pipe piece are respectively provided with a longitudinal seam grouting hole which gradually inclines downwards from the inner wall of each prefabricated pipe piece to an end head, the end heads of the prefabricated pipe pieces and the side walls are assembled in a hemispherical mode, the longitudinal grouting pipes and exhaust pipes are longitudinally arranged in parallel at the arch part of the tunnel and are tightly attached to a primary supporting waterproof plate, after the assembly is completed, plugging plates are installed on the outer sides of each group of prefabricated pipe pieces which are assembled finally and are used for plugging, the length of each longitudinal grouting pipe and each exhaust pipe is larger than the total length of each group of prefabricated pipe pieces, so that the longitudinal grouting pipes and each exhaust pipe extend to the outside the plugging plates, concrete backfilling pumping pipes are also installed on the plugging plates, and an observation window is reserved in the arch part;
b, vault concrete backfilling: carrying out vault concrete backfill through a concrete backfill pumping pipe;
step C, radial grouting: after the radial grouting hole is punched by an electric drill, performing cement mortar grouting by using the radial grouting hole, stopping grouting when the exhaust pipe overflows, and plugging the radial grouting hole by using a grouting hole spiral pipe;
step D, vault grouting: then, vault longitudinal grouting is carried out through a longitudinal grouting pipe, and grouting is stopped when mortar overflows from the exhaust pipe;
e, longitudinal seam grouting: blocking the outer surface of a joint formed by assembling the prefabricated duct piece and the side wall by using mortar, reserving an exhaust hole at a high point of the block, then grouting from a longitudinal joint grouting hole, observing at the high point, blocking the exhaust hole by using the mortar when the mortar is pressed to a high position, and maintaining the pressure at a low point for a period of time to finish the process;
and F, constructing the next group of tunnel linings according to the sequence of the steps A to E until the secondary lining of the tunnel is completely constructed.
Preferably, the reserved thickness of the radial grouting holes in the step A which are not penetrated is 5cm, and the diameters of the longitudinal grouting pipes and the pipeline of the exhaust pipe are both 3.2 cm.
Further preferably, when the prefabricated segments in the step A are constructed in groups, 5 prefabricated segments are used as a group for the first time, 6 prefabricated segments are used as a group, and 7 prefabricated segments are used for mounting, backfilling and grouting for the last group, so that the construction efficiency is improved. The lining is generally based on 6 prefabricated pipe pieces as one group, 5 prefabricated pipe pieces are used for the first time as one group, then 6 prefabricated pipe pieces are used as one group, the position of one prefabricated pipe piece can be vacated when each group is assembled except for the last group, the plugging plate is installed by utilizing the position of the prefabricated pipe piece, and 7 prefabricated pipe pieces are used in the last group to supplement the poor prefabricated pipe pieces.
Preferably, the backfill concrete in the step B is fine aggregate concrete, the grouting material in the steps C and D is M20 cement mortar, and the pressure is controlled at 0.1 MPa.
Preferably, the grouting material in the step E is grouting material, the water-material ratio is 0.14:1, and the grouting pressure is 0.1 MPa.
The invention has the beneficial effects that:
(1) by adopting the secondary lining construction method of the arch prefabricated duct piece and the side wall cast-in-place, the prefabricated duct piece is prefabricated and formed outside the tunnel, the quality defect of vertically pouring secondary lining concrete from bottom to top in the prior art can be effectively avoided, and the risk of vault falling and collapse is avoided.
(2) The novel process of longitudinal concrete backfill, radial grouting, longitudinal grouting and longitudinal seam filling is adopted, when arch grouting is carried out, concrete backfill and radial grouting are adopted, and longitudinal grouting and longitudinal seam filling are combined, so that the hidden dangers that single material grouting consumes long time, is not easy to fill, leaves arch cavities and the like can be avoided, grouting materials can fully fill the cavities behind the secondary lining, and the hidden safety quality danger caused by the tunnel arch cavities is effectively eliminated.
(3) The two ends of the prefabricated pipe piece are of hemispherical structures, so that the working stress is effectively reduced when the prefabricated pipe piece is assembled with a side wall, the abrasion is effectively reduced, and the negative conditions of bending, cracking and breaking of parts are reduced.
(4) The radial grouting hole of prefabricated section of jurisdiction does not pierce through prefabricated section of jurisdiction, avoids appearing the phenomenon that thick liquid spills over from radial grouting hole when carrying out the vault and pour, and the radial grouting hole of reserving simultaneously can be opened up fast again through the electric drill and carry out the slip casting, convenient and fast.
In conclusion, the method is simple in steps, efficient and feasible, and can be used for fully filling the cavity gaps generated after the secondary lining construction in three grouting directions, so that the firmness of the tunnel support is increased, and the safety of constructors is guaranteed.
Drawings
FIG. 1 is a schematic view of the longitudinal pressurized grouting of the present invention.
Fig. 2 is a schematic view of the structure of a prefabricated segment according to the present invention.
Fig. 3 is a partially enlarged view of fig. 2.
Fig. 4 is a schematic view of a grouting hole spiral tube structure.
Detailed Description
The invention will be further illustrated by the following examples in conjunction with the accompanying drawings:
as shown in fig. 1-4, a construction method for reinforcing a cavity by grouting an assembled lining based on mine-method tunnel construction includes the following steps:
step A, early-stage work preparation: and (4) pouring the side wall 1 in situ, and conveying the prefabricated pipe pieces 2 to the inside of the tunnel after the prefabrication outside the tunnel is finished and longitudinally installing the prefabricated pipe pieces in groups.
When the prefabricated pipe segments 2 are constructed in groups, preferably, 5 prefabricated pipe segments 2 are used as a group for the first time, then 6 prefabricated pipe segments 2 are used as a group, and finally 7 prefabricated pipe segments 2 are used for installation, backfilling and grouting.
Two radial grouting holes 21 which are not penetrated by the outer wall are formed in the prefabricated pipe piece 2, the two radial grouting holes 21 which are not penetrated by the outer wall are arranged in a bilateral symmetry mode, and the number of the radial grouting holes 21 is at least two, but not limited to two. The thickness of the radial grouting holes 21 is preferably 5cm, and the pipe diameters of the longitudinal grouting pipes 5 and the exhaust pipes 6 are preferably 3.2 cm.
Two ends of the prefabricated pipe piece 2 are respectively provided with a longitudinal joint grouting hole 22, the longitudinal joint grouting holes 22 are inclined holes with high inside and low outside, and the longitudinal joint grouting holes 22 gradually incline downwards from the inner wall of the prefabricated pipe piece 2 and extend to the end head.
The end of the prefabricated pipe piece 2 is spliced with the side wall 1 in a hemispherical manner. The longitudinal grouting pipes 5 and the exhaust pipes 6 are longitudinally and parallelly located on the tunnel arch 3 and tightly attached to the waterproof plate of the primary support 4, after assembly is completed, the outer side of each group of prefabricated pipe pieces 2 assembled at last is provided with a plugging plate 7 for plugging, the length of each longitudinal grouting pipe 5 and each exhaust pipe 6 is larger than the total length of each group of prefabricated pipe pieces 2, so that the longitudinal grouting pipes 5 and the exhaust pipes 6 extend out of the plugging plates 7, the plugging plates 7 are also provided with concrete backfill pumping pipes 9, and an observation window is reserved in the arch for observing whether concrete is filled.
B, vault concrete backfilling: and (4) carrying out vault concrete backfill through the concrete backfill pumping pipe 9, wherein the backfill concrete adopts fine aggregate concrete.
Step C, radial grouting: after the radial grouting hole 21 is punched through by an electric drill, the radial grouting hole 21 is utilized for grouting, the grouting material is preferably M20 cement mortar, the pressure is controlled to be 0.1Mpa, when the exhaust pipe 6 overflows, grouting is stopped, and the radial grouting hole 21 is blocked by the grouting hole spiral pipe 8.
Step D, vault grouting: and the longitudinal grouting pipe 5 performs vault longitudinal grouting, and grouting is stopped when mortar overflows from the exhaust pipe 6.
E, longitudinal seam grouting: and (2) blocking the outer surface of a joint formed by assembling the prefabricated pipe piece 2 and the side wall 1 by using mortar, reserving an exhaust hole at the high point of the block, grouting from a longitudinal joint grouting hole 22, preferably adopting grouting material, wherein the water-material ratio is 0.14:1, the grouting pressure is 0.1MPa, observing at the high point, blocking the exhaust hole by using the mortar when the slurry is pressed to the high point, and maintaining the pressure at the low point for a period of time to finish the process.
And F, constructing the next group of tunnel linings according to the sequence of the steps A to E until the secondary lining of the tunnel is completely constructed.

Claims (5)

1. A construction method for reinforcing a cavity by grouting an assembled lining based on mine method tunnel construction is characterized by comprising the following steps:
step A, early-stage work preparation: the side wall (1) is cast in place, the prefabricated pipe pieces (2) are transported into the tunnel after being prefabricated outside the tunnel and are longitudinally installed in groups, at least two radial grouting holes (21) with unpenetrated outer walls are formed in the prefabricated pipe pieces (2), two longitudinal seam grouting holes (22) are formed in two ends of each prefabricated pipe piece (2) and gradually incline downwards from the inner wall of the prefabricated pipe piece (2) to the end, the end of each prefabricated pipe piece (2) and the side wall (1) are assembled in a hemispherical mode, the longitudinal grouting pipes (5) and the exhaust pipes (6) are longitudinally arranged in parallel in the arch portion (3) of the tunnel and are tightly attached to a waterproof plate of an initial support (4), after the prefabricated pipe pieces are assembled, a plugging plate (7) is installed on the outer side of each group of the prefabricated pipe pieces (2) which are assembled finally, the length of each longitudinal grouting pipe (5) and each exhaust pipe (6) is larger than the total length of each group of the prefabricated pipe pieces (2), so that the longitudinal grouting pipes (5) and the exhaust pipes (6) extend out of each group of the plugging plate (7), a concrete backfill pumping pipe (9) is also arranged on the plugging plate (7), and an observation window is reserved in the arch part;
b, vault concrete backfilling: vault concrete backfilling is carried out through a concrete backfilling pumping pipe (9);
step C, radial grouting: after the radial grouting hole (21) is punched through by an electric drill, cement mortar grouting is carried out by utilizing the radial grouting hole (21), when the exhaust pipe (6) overflows, grouting is stopped, and the radial grouting hole (21) is blocked by using a grouting hole spiral pipe (8);
step D, vault grouting: carrying out vault longitudinal grouting through a longitudinal grouting pipe (5), and stopping grouting when mortar overflows from the exhaust pipe (6);
e, longitudinal seam grouting: blocking the outer surface of a joint where the prefabricated pipe piece (2) and the side wall (1) are assembled by mortar, reserving an exhaust hole at a high point of the block, then grouting from a longitudinal joint grouting hole (22), observing at the high point, blocking the exhaust hole by the mortar when the slurry is pressed to the high point, and maintaining the pressure at the low point for a period of time to finish the process;
and F, constructing the next group of tunnel linings according to the sequence of the steps A to E until the secondary lining of the tunnel is completely constructed.
2. The construction method for reinforcing the cavity by grouting the spliced lining based on the mine tunnel construction, according to claim 1, is characterized in that: the reserved thickness of the radial grouting holes (21) in the step A which are not penetrated is 5cm, and the diameters of the longitudinal grouting pipes (5) and the exhaust pipes (6) are both 3.2 cm.
3. The construction method for reinforcing the cavity by grouting the spliced lining based on the mine tunnel construction, according to claim 1, is characterized in that: and B, when the prefabricated pipe pieces (2) in the step A are constructed in groups, 5 prefabricated pipe pieces (2) are used as a group for the first time, 6 prefabricated pipe pieces (2) are used as a group for the later time, and 7 prefabricated pipe pieces (2) are used for installation, backfilling and grouting for the last group.
4. The construction method for reinforcing the cavity by grouting the spliced lining based on the mine tunnel construction, according to claim 1, is characterized in that: and B, adopting fine aggregate concrete as the backfilling concrete in the step B, adopting M20 cement mortar as the grouting material in the steps C and D, and controlling the pressure to be 0.1 Mpa.
5. The construction method for reinforcing the cavity by grouting the spliced lining based on the mine tunnel construction, according to claim 1, is characterized in that: and E, adopting grouting material as grouting material, wherein the water-material ratio is 0.14:1, and the grouting pressure is 0.1 MPa.
CN202110863769.6A 2021-07-29 2021-07-29 Construction method for splicing lining grouting reinforcement cavity based on mine tunnel construction Active CN113374502B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110863769.6A CN113374502B (en) 2021-07-29 2021-07-29 Construction method for splicing lining grouting reinforcement cavity based on mine tunnel construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110863769.6A CN113374502B (en) 2021-07-29 2021-07-29 Construction method for splicing lining grouting reinforcement cavity based on mine tunnel construction

Publications (2)

Publication Number Publication Date
CN113374502A true CN113374502A (en) 2021-09-10
CN113374502B CN113374502B (en) 2024-07-23

Family

ID=77583045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110863769.6A Active CN113374502B (en) 2021-07-29 2021-07-29 Construction method for splicing lining grouting reinforcement cavity based on mine tunnel construction

Country Status (1)

Country Link
CN (1) CN113374502B (en)

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100988457B1 (en) * 2009-06-29 2010-10-18 조향래 The back feel grouting method for upper part of tunnel
JP3174028U (en) * 2011-12-21 2012-03-01 株式会社光計画設計事務所 Seismic reinforcement structure for tunnels
CN103993895A (en) * 2014-06-10 2014-08-20 中铁二院工程集团有限责任公司 Hoisting, hydraulic reclamation and grouting embedded assembly for segmental lining prefabricated according to TMB construction method
CN106285722A (en) * 2016-08-30 2017-01-04 中铁十局集团第四工程有限公司 A kind of device preventing tunnel double-lining vault to come to nothing and construction method thereof
CN206942799U (en) * 2017-06-16 2018-01-30 中铁第一勘察设计院集团有限公司 A kind of shield tunnel anti-floating system based on prestress anchorage cable
CN108301846A (en) * 2018-03-21 2018-07-20 长安大学 Tunnel-liner vault band is molded into sizing device and its construction
CN108506028A (en) * 2018-05-30 2018-09-07 中铁十九局集团第六工程有限公司 A kind of tunnel lining trolley vault comprehensive grouting pipe device and its application method
CN208669320U (en) * 2018-07-06 2019-03-29 浙江大学城市学院 The anti-horizontal ovalizing deflection shield tunnel ruggedized construction of pre-embedded steel slab
CN209277877U (en) * 2018-08-01 2019-08-20 广东华隧建设集团股份有限公司 A kind of shield machine list dual slurry combined type synchronous grouting system
CN110206555A (en) * 2019-07-09 2019-09-06 中建五局土木工程有限公司 A kind of shield driving method
CN111997659A (en) * 2020-08-11 2020-11-27 天津大学 Tunnel segment and plugging slurry and construction method for treating water burst and sand burst accidents at joint of tunnel segment
CN112647972A (en) * 2021-03-15 2021-04-13 中铁九局集团第四工程有限公司 Shield tunnel segment orientation method
CN112879037A (en) * 2021-04-22 2021-06-01 黄河交通学院 Safe construction method for mine tunnel

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100988457B1 (en) * 2009-06-29 2010-10-18 조향래 The back feel grouting method for upper part of tunnel
JP3174028U (en) * 2011-12-21 2012-03-01 株式会社光計画設計事務所 Seismic reinforcement structure for tunnels
CN103993895A (en) * 2014-06-10 2014-08-20 中铁二院工程集团有限责任公司 Hoisting, hydraulic reclamation and grouting embedded assembly for segmental lining prefabricated according to TMB construction method
CN106285722A (en) * 2016-08-30 2017-01-04 中铁十局集团第四工程有限公司 A kind of device preventing tunnel double-lining vault to come to nothing and construction method thereof
CN206942799U (en) * 2017-06-16 2018-01-30 中铁第一勘察设计院集团有限公司 A kind of shield tunnel anti-floating system based on prestress anchorage cable
CN108301846A (en) * 2018-03-21 2018-07-20 长安大学 Tunnel-liner vault band is molded into sizing device and its construction
CN108506028A (en) * 2018-05-30 2018-09-07 中铁十九局集团第六工程有限公司 A kind of tunnel lining trolley vault comprehensive grouting pipe device and its application method
CN208669320U (en) * 2018-07-06 2019-03-29 浙江大学城市学院 The anti-horizontal ovalizing deflection shield tunnel ruggedized construction of pre-embedded steel slab
CN209277877U (en) * 2018-08-01 2019-08-20 广东华隧建设集团股份有限公司 A kind of shield machine list dual slurry combined type synchronous grouting system
CN110206555A (en) * 2019-07-09 2019-09-06 中建五局土木工程有限公司 A kind of shield driving method
CN111997659A (en) * 2020-08-11 2020-11-27 天津大学 Tunnel segment and plugging slurry and construction method for treating water burst and sand burst accidents at joint of tunnel segment
CN112647972A (en) * 2021-03-15 2021-04-13 中铁九局集团第四工程有限公司 Shield tunnel segment orientation method
CN112879037A (en) * 2021-04-22 2021-06-01 黄河交通学院 Safe construction method for mine tunnel

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
张秀文;张欢;何玉书;: "带模注浆新型铁路隧道衬砌台车施工技术的优化", 铁道建筑, no. 05, pages 60 - 62 *
郑志滇;王定宝;: "拱顶回填注浆处理在壁板坡隧道中的应用", 智能城市, no. 02, pages 92 - 93 *
钟亮根;: "隧道二衬拱顶脱空预注浆施工技术", 四川建筑, no. 04, pages 203 - 205 *
雷璇;: "隧道二衬带模注浆施工技术应用", 工程技术研究, no. 02, pages 117 - 118 *

Also Published As

Publication number Publication date
CN113374502B (en) 2024-07-23

Similar Documents

Publication Publication Date Title
CN109611150B (en) Waterproof drainage structure and waterproof drainage method for tunnel
CN110656959B (en) Large-section loess tunnel primary support limit-invasion arch-changing construction method
CN111119935B (en) Multi-layer grouting reinforcement method for surrounding rock of soft and broken roadway structure
CN106150519B (en) A kind of tunneling boring prefbricated tunnel lining structure and construction method for drill+blast tunnel
CN106988750B (en) Implementation mode of ultra-short-distance underpass of existing station of large-span interval tunnel
CN211038657U (en) Cover encircles based deeply buries loess tunnel deformation control construction structures
CN110593890B (en) Tunnel corrugated steel double-layer primary lining supporting method
CN104631440B (en) A kind of existing large-section in-situ concrete pile strength core increases foundation pit supporting construction and constructional method
CN111119910A (en) Tunnel collapse section back-blowing sand grouting backfill structure and construction method thereof
CN113294166A (en) Large-section rectangular jacking pipe oblique starting method
CN113586066B (en) Integral type straight middle wall top integrated backfilling and pouring method for multi-arch tunnel
CN109184752B (en) Supporting structure for coal mine to penetrate through old kiln goaf and supporting method thereof
CN108457667A (en) Self-compacting concrete segment lining structure and construction method thereof
CN110671132B (en) Deep loess tunnel deformation control construction structure and method based on sleeve arch
CN210768793U (en) Two-lining construction system at intersection of main tunnel and double-layer construction transverse channel
CN112681334A (en) Deep foundation pit side wall concrete pouring construction structure and method
CN113374502A (en) Construction method for reinforcing cavity by splicing lining grouting based on mine method tunnel construction
CN215256214U (en) Arch prefabricated segment back grouting system suitable for assembled lining
CN116025366A (en) Small clear distance tunnel construction method
CN217078737U (en) Assembled static pressure concrete anchor rod
CN211598669U (en) Tunnel collapse cavity backfill structure
CN215332886U (en) Tunnel arch prefabricated duct piece convenient for grouting
CN110778341B (en) Backfill construction method for construction vertical shaft and construction transverse passage
CN114151096A (en) Shield type TBM air-propelled assembled segment tunnel construction method
CN210768913U (en) Backfill construction system of dismantling-free temporary inverted arch of double-layer pilot tunnel construction transverse passage

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant