CN113356256B - Prefabricated back cover of offshore wind power implanted high-rise pile cap and installation process - Google Patents

Prefabricated back cover of offshore wind power implanted high-rise pile cap and installation process Download PDF

Info

Publication number
CN113356256B
CN113356256B CN202110726753.0A CN202110726753A CN113356256B CN 113356256 B CN113356256 B CN 113356256B CN 202110726753 A CN202110726753 A CN 202110726753A CN 113356256 B CN113356256 B CN 113356256B
Authority
CN
China
Prior art keywords
bearing platform
back cover
ring
pile
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110726753.0A
Other languages
Chinese (zh)
Other versions
CN113356256A (en
Inventor
黄桥兴
林晓
王其标
熊汉东
张新炜
黄建阳
陈东伟
郭新杰
林志航
黄博坚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cccc Third Aviation Bureau Sixth Engineering Xiamen Co Ltd
CCCC Third Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Original Assignee
Cccc Sanya Xiamen Engineering Co ltd
CCCC Third Harbor Engineering Co Ltd
CCCC Third Harbor Engineering Co Ltd Xiamen Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cccc Sanya Xiamen Engineering Co ltd, CCCC Third Harbor Engineering Co Ltd, CCCC Third Harbor Engineering Co Ltd Xiamen Branch filed Critical Cccc Sanya Xiamen Engineering Co ltd
Priority to CN202110726753.0A priority Critical patent/CN113356256B/en
Publication of CN113356256A publication Critical patent/CN113356256A/en
Application granted granted Critical
Publication of CN113356256B publication Critical patent/CN113356256B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种海上风电植入式高桩承台预制封底及安装工艺,包括以下流程:承台预制封底岸上制作、海上植桩、承台预制封底安装和承台二期施工。承台预制封底包括砼封底板、六个均布开设在砼封底板上的穿桩孔、六个一一对应地埋设在多个穿桩孔中的套管、安装在砼封底板的顶面中央的基础环、六块均布地径向连接在基础环的外周面上的连接腹板及六个一一对应地连接在六块连接腹板的外端并一一对应地位于六个套管上方的十字连接件;每个套管的顶、底面一一对应地连接一个顶、底环板;六根工程桩的顶部一一对应地穿过六个套管并一一对应地与六个十字连接件连接。本发明将封底模板安装至连接腹板安装等作业在岸上进行,能大大减少海上吊装及作业时间。

Figure 202110726753

The invention discloses a prefabricated back cover of an offshore wind power implantable high pile cap and an installation process, which includes the following procedures: onshore fabrication of the prefabricated back cover of the cap, planting of piles at sea, installation of the prefabricated back cover of the cap, and second-stage construction of the cap. The prefabricated bottom cover of the bearing platform includes a concrete sealing bottom plate, six pile holes evenly distributed on the concrete sealing bottom plate, six bushings embedded in a plurality of pile holes correspondingly one by one, and installed on the top surface of the concrete sealing bottom plate. The central base ring, six connecting webs evenly distributed and radially connected to the outer peripheral surface of the base ring, and six connecting webs connected to the outer ends of the six connecting webs in a one-to-one correspondence and located in the six sleeves in a one-to-one correspondence The upper cross connector; the top and bottom surfaces of each bushing are connected to a top and bottom ring plate one-to-one; Connector connection. In the invention, the operations such as the installation of the back cover template to the connecting web are carried out on the shore, which can greatly reduce the hoisting and operation time at sea.

Figure 202110726753

Description

一种海上风电植入式高桩承台预制封底及安装工艺Prefabricated back cover and installation process of offshore wind power implantable high pile cap

技术领域technical field

本发明涉及一种海上风电植入式高桩承台预制封底及安装工艺。The invention relates to a prefabricated back cover of an offshore wind power implantable high pile cap and an installation process.

背景技术Background technique

植入式高桩承台主要应用于海上风电项目地质复杂,地层起伏变化大,局部覆盖层薄且存在零星孤石。从目前海上风电项目同类型地质状况选择的结构形式发展来看,针对目前植入式单桩基础施工遇到困难,分别遇孤石护筒卷边、多次塌孔、溜桩和护筒垂直度超标等现象导致增加施工技术处理难度和存在较大、安全风险及工期延误风险,并且塌孔后,处理周期长,效果不明显。目前海上风电正处于“抢装潮”的势态,大型钻机及起重船等施工资源进一步收缩,为尽快解决植入式单桩基础施工问题,故采用植入式高桩承台基础,进行植入式高桩承台基础施工时设备及船机有较多选择。Implanted high pile caps are mainly used in offshore wind power projects with complex geology, large stratum fluctuations, thin local covering layers and sporadic boulders. Judging from the development of the structure form selected for the same type of geological conditions of the current offshore wind power project, in view of the difficulties encountered in the construction of the implanted single-pile foundation at present, the boulder casing curling, multiple collapse holes, sliding piles and vertical casings are encountered respectively. Exceeding the standard and other phenomena will increase the difficulty of construction technology processing and have greater safety risks and risks of delays in the construction period. After the hole is collapsed, the processing period is long and the effect is not obvious. At present, offshore wind power is in a situation of "rushing to install", and construction resources such as large drilling rigs and crane ships are further shrinking. There are many choices of equipment and ship machinery for the construction of the high-pile cap foundation.

植入式高桩承台基础的现场施工流程为:嵌岩平台搭设→嵌岩孔施工→植入工程桩→工程桩封底→工程桩外壁注浆→拔除护筒→桩芯砼浇筑→拆除嵌岩平台→附属套笼安装→承台封底模板安装→工程桩间加固→承台封底钢筋绑扎→承台封底砼浇筑→承台底钢筋绑扎→承台套箱安装→基础环安装→连接件安装→连接腹板等焊接→承台钢筋绑扎→承台砼浇筑。承台封底的主要功能是配合风机塔筒的基础环安装及连接件安装。The on-site construction process of the implanted high pile cap foundation is: rock-socketed platform erection → rock-socketed hole construction → implantation of engineering piles → engineering pile bottom sealing → engineering pile outer wall grouting → removal of casing → pile core concrete pouring → removal of embedded Rock platform → installation of auxiliary cages → installation of cap and bottom cover formwork → reinforcement between project piles → binding of steel bars for cap bottom cover → concrete pouring of cap bottom cover → reinforcing steel lashing of cap bottom → cap box box installation → foundation ring installation → connecting piece installation → Welding of connecting webs, etc. → Binding of steel reinforcement on the platform → Concrete pouring on the platform. The main function of the bottom cover of the cap is to cooperate with the installation of the foundation ring of the fan tower and the installation of the connecting parts.

由于高桩承台基础现场施工流程较多而海上有效作业时间较少,因此亟待优化高桩承台基础的施工工艺。Since there are many on-site construction processes for high-pile cap foundations and less effective operation time at sea, it is urgent to optimize the construction technology of high-pile cap foundations.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于克服现有技术的缺陷而提供一种海上风电植入式高桩承台预制封底及安装工艺,它能将承台的封底模板安装至连接腹板安装等焊接作业在岸上进行,可减少海上吊装及作业时间,为海上风电施工及抢装潮下由于海上作业船舶较匮乏提供便利。The purpose of the present invention is to overcome the defects of the prior art and provide a prefabricated back cover and an installation process for the offshore wind power implantable high pile cap, which can install the back cover template of the cap to the connection web and perform welding operations on the shore. , which can reduce the time of offshore hoisting and operation, and provide convenience for offshore wind power construction and rush installation due to the lack of offshore vessels under the tide.

本发明的目的是这样实现的:一种海上风电植入式高桩承台预制封底及安装工艺,包括以下流程:承台预制封底岸上制作、海上植桩、承台预制封底安装和承台二期施工;The purpose of the present invention is to achieve this: a kind of offshore wind power implantation type high pile cap prefabricated back cover and installation process, including the following processes: the production of the prefabricated cap back cover on the shore, the offshore pile planting, the installation of the cap prefabricated back cover and the second cap period construction;

所述承台预制封底包括砼封底板、六个均布开设在砼封底板上的穿桩孔、六个一一对应地埋设在多个穿桩孔中且高度与砼封底板的厚度相同的套管、安装在砼封底板的顶面中央的基础环、六块环向均布地径向连接在基础环的外周面上的连接腹板及六个一一对应地连接在六块连接腹板的外端并一一对应地位于六个套管上方的十字连接件;每个套管的顶面和底面一一对应地连接一个顶环板和底环板;六根工程桩的顶部一一对应地穿过六个套管并一一对应地与六个十字连接件的下部连接;The prefabricated bottom cover of the bearing platform includes a concrete sealing bottom plate, six pile-piercing holes evenly distributed on the concrete sealing bottom plate, and six pile-piercing holes which are embedded in a one-to-one correspondence and whose height is the same as the thickness of the concrete sealing bottom plate. The casing, the base ring installed in the center of the top surface of the concrete sealing bottom plate, the six connecting webs connected to the outer peripheral surface of the base ring in an evenly distributed radial direction, and the six connecting webs connected to the six connecting webs in a one-to-one correspondence The outer ends of the piles are located in a one-to-one cross connection above the six casings; the top and bottom surfaces of each casing are connected to a top ring plate and a bottom ring plate in a one-to-one correspondence; the tops of the six engineering piles are in a one-to-one correspondence Pass through the six sleeves and connect with the lower parts of the six cross connectors in one-to-one correspondence;

进行承台预制封底岸上制作流程时,包括以下步骤:套管定位和加固、封底板钢筋和承台外侧钢筋同步绑扎、封底板砼浇筑、承台底层钢筋和基础环内侧钢筋同步绑扎、基础环和连接件安装、基础环外侧钢筋绑扎及承台钢套箱安装;The process of making the prefabricated back cover of the cap on the shore includes the following steps: casing positioning and reinforcement, synchronous binding of the reinforcing steel bars of the capping base plate and the outside reinforcing bars of the cap, concrete pouring of the capping base, synchronous binding of the reinforcing bars at the bottom of the cap and the reinforcing bars on the inner side of the foundation ring, and the foundation ring. Installation of connecting pieces, binding of steel bars on the outside of the foundation ring, and installation of steel sleeves on the platform;

进行套管定位和加固步骤时,在底胎座上将六个套管均布地布置在一个与工程桩的布桩直径相同的圆上,并通过六根外侧槽钢和三根内侧槽钢将六个套管连成整体,六根外侧槽钢一一对应地连接在两根相邻的套管之间,三根内侧槽钢一一对应地连接在两根呈对角布置的套管之间;When the casing positioning and reinforcement steps are carried out, the six casings are evenly distributed on a circle with the same diameter as the construction pile on the base, and the six outer channels and the three inner channels are connected. The casings are connected as a whole, six outer channel steels are connected between two adjacent casings in a one-to-one correspondence, and three inner channel steels are connected between two diagonally arranged casings;

进行封底板钢筋和承台外侧钢筋同步绑扎步骤时,在底胎座上绑扎封底板钢筋时,在每个套管的外侧绑扎环向钢筋,环向钢筋与封底板钢筋焊接连接;在封底板钢筋上预埋三个调平支座、三个辅助支座和六个吊耳;三个调平支座和三个辅助支座均布置在一个与基础环的环身钢管的外径相同的圆上,三个调平支座均布设置,三个辅助支座均布地设在三个调平支座之间,其中一个辅助支座设在风电的塔筒门方向;六个吊耳均布地布置在六个套管的同一个圆上并一一对应地位于两根相邻的套管之间;在绑扎封底板钢筋时还要预留电缆管穿孔和ICCP管穿孔;When performing the step of synchronizing the binding of the reinforcing bars for the sealing floor and the outer reinforcing bars of the bearing platform, when tying the reinforcing bars for the sealing floor on the bottom tire base, the circumferential reinforcing bars are bound on the outside of each casing, and the circumferential reinforcing bars are connected with the reinforcing bars of the sealing floor by welding; Three leveling supports, three auxiliary supports and six lifting lugs are embedded on the steel bar; the three leveling supports and three auxiliary supports are all arranged in a same outer diameter as the outer diameter of the surrounding steel pipe of the foundation ring. On the circle, three leveling supports are evenly arranged, three auxiliary supports are evenly arranged between the three leveling supports, one of the auxiliary supports is located in the direction of the tower door of the wind power plant; The layout is arranged on the same circle of the six casings and is located between two adjacent casings in a one-to-one correspondence; when tying and sealing the reinforcement of the bottom plate, the cable pipe perforation and the ICCP pipe perforation should be reserved;

进行封底板砼浇筑步骤时,砼浇筑完成后要养护7天;When carrying out the concrete pouring step of the closed bottom plate, the concrete should be cured for 7 days after the completion of the pouring;

进行基础环和连接件安装步骤时,先将基础环上的塔筒门标记对准一个设在塔筒门位置的辅助支座后套在基础环内侧钢筋上并坐落在三个调平支座和三个辅助支座上,接着通过三个调平支座初步调整基础环的顶面水平度,调整到位后将基础环与三个辅组支座进行点焊临时固定,再将六块连接腹板均布地径向焊接在基础环的外周面上,六块连接腹板的环向位置与六个套管的环向位置一一对应;然后将六个十字连接件以比设定位置提高一定距离H的方式一一对应地临时焊接在六块连接腹板的外端;When carrying out the installation steps of the foundation ring and the connecting piece, first align the tower door mark on the foundation ring with an auxiliary support located at the position of the tower door, then put it on the inner reinforcement of the foundation ring and seat it on the three leveling supports. and three auxiliary supports, and then preliminarily adjust the level of the top surface of the base ring through the three leveling supports. After the adjustment is in place, the base ring and the three auxiliary supports are spot welded and temporarily fixed, and then the six pieces are connected. The webs are radially welded on the outer peripheral surface of the base ring, and the circumferential positions of the six connecting webs are in one-to-one correspondence with the circumferential positions of the six sleeves; A certain distance H is temporarily welded to the outer ends of the six connecting webs in one-to-one correspondence;

进行承台底层钢筋和基础环外侧钢筋同步绑扎步骤时,在砼封底板上绑扎承台底层钢筋,同时在基础环的下部绑扎基础环外侧钢筋;When performing the step of synchronously binding the reinforcing bars on the bottom of the cap and the reinforcing bars on the outside of the foundation ring, bind the reinforcing bars on the bottom of the cap on the concrete sealing bottom plate, and at the same time bind the reinforcing bars on the outside of the foundation ring at the lower part of the foundation ring;

进行承台钢套箱安装步骤时,将承台钢套箱套在承台外侧钢筋上;在承台钢套箱安装完后形成承台预制封底,再将承台预制封底运至海上施工现场;When carrying out the installation steps of the cap steel sleeve box, the cap steel sleeve box is sleeved on the steel bars outside the cap platform; after the cap steel sleeve box is installed, the cap prefabricated back cover is formed, and then the cap prefabricated back cover is transported to the offshore construction site ;

进行海上植桩流程时,包括以下步骤:嵌岩施工平台搭设、钢护筒沉设、嵌岩孔施工、工程桩植入、工程桩封底砼浇筑、工程桩外侧环空灌浆、钢护筒拔出、电缆管和ICCP管安装及承台支撑体系焊接;The process of offshore pile planting includes the following steps: rock-socketed construction platform erection, steel casing sinking, rock-socketed hole construction, engineering pile implantation, engineering pile bottom-sealing concrete pouring, engineering pile outer annulus grouting, steel casing extraction Outlet, cable pipe and ICCP pipe installation and platform support system welding;

进行承台支撑体系焊接步骤时,在每根工程桩的位于承台底标高的外壁面上焊接一个支撑环板和若干环向均布地焊接在支撑环板的底面与工程桩的外壁面之间的下支撑筋板,六根工程桩上的支撑环板和下支撑筋板形成承台支撑体系;During the welding step of the cap support system, a support ring plate is welded on the outer wall surface of each engineering pile located at the bottom elevation of the cap, and a plurality of circumferentially distributed welding are welded between the bottom surface of the support ring plate and the outer wall surface of the engineering pile. The lower supporting rib plate, the supporting ring plate and the lower supporting rib plate on the six engineering piles form a cap support system;

进行承台预制封底安装流程时,包括以下步骤:承台预制封底吊装及承台预制封底与工程桩连接;When carrying out the installation process of the prefabricated back cover of the cap, it includes the following steps: hoisting the prefabricated back cover of the cap and connecting the prefabricated back cover of the cap to the engineering pile;

进行承台预制封底吊装步骤时,先将承台预制封底的封底板上的预留孔套在电缆管及ICCP管上,并将封底板上的六个套管一一对应地套在六根工程桩上,接着将承台预制封底缓慢下落至承台支撑体系上,再将每根工程桩上的支撑环板与对应的套管的底环板焊接加固,并在每个套管的顶环板与对应的工程桩的外壁面之间通过若干环向均布的上支撑筋板焊接加固,然后复测基础环的水平度;When carrying out the hoisting step of the prefabricated bottom cover of the cap, firstly put the reserved holes on the base plate of the cap prefabricated back cover on the cable pipe and the ICCP pipe, and put the six sleeves on the base plate one by one on the six projects. On the pile, then slowly drop the prefabricated back cover of the cap to the support system of the cap, and then weld and reinforce the support ring plate on each engineering pile and the bottom ring plate of the corresponding casing, and place it on the top ring of each casing. The plate and the outer wall of the corresponding engineering pile are welded and reinforced by several upper support ribs distributed uniformly in the circumferential direction, and then the levelness of the foundation ring is re-measured;

进行承台预制封底与工程桩连接步骤时,先在每根工程桩的顶部内壁面上根据对应的十字连接件的投影开设高度为H的焊接坡口,接着解除每个十字连接件与对应的连接腹板的临时焊接,再将十字连接件的下部沿对应的工程桩的焊接坡口插入工程桩内,然后将十字连接件的上部与对应的连接腹板焊接,同时将十字连接件的下部与对应的工程桩焊接;When performing the step of connecting the prefabricated back cover of the cap and the engineering piles, first open a welding groove with a height of H on the top inner wall of each engineering pile according to the projection of the corresponding cross connector, and then release each cross connector from the corresponding cross connector. Temporary welding of the connecting web, insert the lower part of the cross connector into the engineering pile along the welding groove of the corresponding engineering pile, then weld the upper part of the cross connector with the corresponding connecting web, and at the same time weld the lower part of the cross connector Welding with corresponding engineering piles;

进行承台二期施工流程时,包括以下步骤:电缆管和ICCP管接长、承台其余钢筋绑扎和预埋件安装及承台砼浇筑。The construction process of the second stage of the cap includes the following steps: connecting the cable pipe and ICCP pipe, tying the remaining steel bars of the cap, installing the embedded parts, and pouring the cap concrete.

上述的海上风电植入式高桩承台预制封底及安装工艺,其中,所述基础环包括环身钢管、焊接在环身钢管底部的底座环板、两个间隔地焊接在环身钢管下部的连接环板和焊接在环身钢管顶部的环顶法兰,所述底座环板上对应三个调平支座的位置各自开设一对调平螺栓孔,使基础环通过三对调平螺栓与三个调平支座连接;六块所述连接腹板均布地连接在基础环的两个连接环板之间;每个十字连接件的上部与对应的连接腹板的外端焊接,每个十字连接件的下部插入对应的工程桩的顶部内腔中并与工程桩的顶部内壁焊接。The above-mentioned offshore wind power implantable high pile cap prefabricated back cover and installation process, wherein, the base ring includes a surrounding steel pipe, a base ring plate welded on the bottom of the surrounding steel pipe, and two welded at the bottom of the surrounding steel pipe Connecting the ring plate and the ring top flange welded on the top of the steel pipe of the ring body, a pair of leveling bolt holes are respectively provided on the base ring plate at the positions corresponding to the three leveling supports, so that the foundation ring passes through the three pairs of leveling bolts and the three The leveling support is connected; the six connecting webs are evenly connected between the two connecting ring plates of the base ring; the upper part of each cross connecting piece is welded with the outer end of the corresponding connecting web, and each cross connecting The lower part of the piece is inserted into the top inner cavity of the corresponding engineering pile and welded with the top inner wall of the engineering pile.

本发明的海上风电植入式高桩承台预制封底及安装工艺具有以下特点:The prefabricated back cover and installation process of the offshore wind power implantable high pile cap of the present invention have the following characteristics:

1)本发明的植入式高桩承台预制封底,在封底板的结构上预埋与工程桩对应的套管及与套管连接的内、外侧槽钢,可优化植入式高桩承台的结构形式,并在海上安装承台预制封底时通过在工程桩上焊接承台支撑体系,使承台封底板坐落在承台支撑体系上,整体结构更稳定,施工更简便;1) The prefabricated bottom cover of the implanted high pile cap of the present invention, the casing corresponding to the engineering pile and the inner and outer channel steels connected with the casing are pre-embedded on the structure of the sealing bottom plate, which can optimize the implanted high pile bearing. The structural form of the platform, and the platform support system is welded on the engineering piles when the prefabricated back cover of the platform is installed at sea, so that the bottom plate of the platform seal is located on the platform support system, the overall structure is more stable, and the construction is easier;

2)本发明在岸上制作承台预制封底时,依序进行浇筑封底板砼、绑扎承台底层钢筋、承台外侧钢筋、基础环内侧钢筋、基础环安装、连接腹板焊接、基础环外侧钢筋、十字连接件安装和承台钢套箱安装等集于一体,并将这些结构作为整体进行海上吊装作业,可优化海上作业时间,同时可保证工程施工质量;2) When the present invention makes the prefabricated back cover of the cap on the shore, pouring and sealing the bottom concrete, binding the bottom reinforcement of the cap, the outer reinforcement of the cap, the inner reinforcement of the foundation ring, the installation of the foundation ring, the welding of the connecting web, the reinforcement of the outer side of the foundation ring are carried out in sequence. Integrate the installation of cross-connectors, the installation of steel caps, etc., and use these structures as a whole to carry out offshore hoisting operations, which can optimize the offshore operation time and ensure the construction quality of the project;

3)本发明的承台预制封底安装完成后,只需将基础环与封底板上的辅助支座临时加固点解除进行调平,并现场在工程桩上开设十字连接件的焊接坡口,可达到更高的安装精确,操作简便;3) After the installation of the prefabricated back cover of the bearing platform of the present invention is completed, it is only necessary to release the temporary reinforcement points of the auxiliary support on the foundation ring and the cover bottom plate for leveling, and set up the welding groove of the cross connector on the engineering pile on the spot, which can be Achieve higher installation accuracy and easy operation;

4)本发明将原先在海上进行的作业工序放在岸上进行,即从承台封底模板安装至连接腹板安装等焊接作业,不仅能保证焊接及砼浇筑质量,还能大大减少海上吊装及作业时间,且后续与工程桩连接完成后不需要再进行注浆加固处理等工作,为海上风电施工及抢装潮下由于海上作业船舶较匮乏提供便利;对于二期承台施工只需要绑扎部分承台钢筋及部分焊接工作,加快海上风电的施工进度。4) In the present invention, the operation procedures previously carried out at sea are carried out on the shore, that is, welding operations such as the installation of the cap bottom cover formwork to the installation of the connecting web can not only ensure the quality of welding and concrete pouring, but also greatly reduce the lifting and operation at sea. After the completion of the subsequent connection with the engineering pile, grouting and reinforcement treatment is not required, which provides convenience for offshore wind power construction and rush installation due to the lack of offshore vessels under the tide; Steel bars and some welding work have been carried out to speed up the construction progress of offshore wind power.

附图说明Description of drawings

图1a是进行本发明的安装工艺的承台预制封底岸上制作流程中的套管定位和加固步骤后的结构示意图;Fig. 1a is a structural schematic diagram after the steps of positioning and reinforcing the casing in the production process of the prefabricated back cover bank of the cap for the installation process of the present invention;

图1b是进行本发明的安装工艺的承台预制封底岸上制作流程中的封底板砼浇筑后的结构示意图;Fig. 1b is the structural schematic diagram of the cover plate after the concrete is poured in the production process of the prefabricated bottom cover bank of the cap for the installation process of the present invention;

图1c是进行本发明的安装工艺的承台预制封底岸上制作流程中的承台底层钢筋和基础环内侧钢筋同步绑扎步骤后的结构示意图;Fig. 1c is the structural schematic diagram after the step of synchronously binding the reinforcing bars on the bottom of the cap and the reinforcing bars on the inner side of the foundation ring in the production process of the prefabricated back cover of the cap in the installation process of the present invention;

图1d是进行本发明的安装工艺的承台预制封底岸上制作流程中的基础环和连接件安装步骤后的结构示意图;Fig. 1d is a schematic structural diagram of the base ring and the connector after the installation step in the production process of the prefabricated back cover bank of the platform for the installation process of the present invention;

图1e是进行本发明的安装工艺的承台预制封底岸上制作流程中的基础环外侧钢筋绑扎步骤后的一种结构示意图;Fig. 1e is a kind of structural representation after the step of tying the reinforcing bars on the outside of the foundation ring in the production process of the prefabricated bottom cover of the cap for the installation process of the present invention;

图1f是进行本发明的安装工艺的承台预制封底岸上制作流程中的基础环外侧钢筋绑扎步骤后的另一种结构示意图;Fig. 1f is another structural schematic diagram after the step of tying the reinforcing bars on the outside of the foundation ring in the production process of the prefabricated bottom cover of the cap for the installation process of the present invention;

图1g是进行本发明的安装工艺的承台预制封底岸上制作流程中的承台钢套箱安装步骤后形成的承台预制封底的结构示意图;Fig. 1g is the structural representation of the prefabricated back cover of the cap formed after the step of installing the cap prefabricated back cover in the production process on the shore of the cap prefabricated back cover of the installation process of the present invention;

图2是进行本发明的安装工艺的植桩流程中的承台支撑体系焊接步骤后的结构示意图;Fig. 2 is the structural schematic diagram after the welding step of the cap support system in the pile planting process of the installation process of the present invention;

图3是进行本发明的安装工艺的承台预制封底安装流程中的承台预制封底吊装步骤后的结构示意图;Fig. 3 is the structural schematic diagram after the hoisting step of the prefabricated back cover of the cap in the installation process of the prefabricated back cover of the cap of the installation process of the present invention;

图4是进行本发明的安装工艺的承台预制封底安装流程中的承台预制封底与工程桩连接步骤后的结构示意图;4 is a schematic structural diagram after the step of connecting the prefabricated back cover of the cap and the engineering pile in the installation process of the prefabricated cap back cover of the installation process of the present invention;

图5是图4的俯视图;Fig. 5 is the top view of Fig. 4;

图6是图5中的A-A向视图。FIG. 6 is an A-A view in FIG. 5 .

具体实施方式Detailed ways

下面将结合附图对本发明作进一步说明。The present invention will be further described below with reference to the accompanying drawings.

请参阅图1a至图6,本发明的海上风电植入式高桩承台预制封底及安装工艺,包括以下流程:承台预制封底岸上制作、海上植桩、承台预制封底安装和承台二期施工;Please refer to FIGS. 1 a to 6 , the offshore wind power implantable high-pile cap prefabricated back cover and installation process of the present invention include the following processes: onshore fabrication of the cap prefabricated back cover, offshore pile planting, installation of the cap prefabricated back cover and two period construction;

承台预制封底包括砼封底板10、六个均布开设在砼封底板10上的穿桩孔、六个一一对应地埋设在多个穿桩孔中且高度与砼封底板10的厚度相同的套管20、安装在砼封底板10的顶面中央的基础环30、六块环向均布地径向连接在基础环30的外周面上的连接腹板40及六个一一对应地连接在六块连接腹板40的外端并一一对应地位于六个套管20上方的十字连接件50;每个套管20的顶面和底面一一对应地连接一个顶环板21和底环板22;六根工程桩70的顶部一一对应地穿过六个套管20并一一对应地与六个十字连接件50的下部连接;The prefabricated bottom cover of the cap comprises a concrete sealing bottom plate 10, six pile-piercing holes evenly distributed on the concrete sealing bottom plate 10, and six pile-piercing holes which are embedded in a one-to-one correspondence and have the same height as the thickness of the concrete sealing bottom plate 10. The sleeve 20, the base ring 30 installed in the center of the top surface of the concrete sealing bottom plate 10, the six connecting webs 40 that are radially connected to the outer peripheral surface of the base ring 30 in a one-to-one correspondence Cross connectors 50 located at the outer ends of the six connecting webs 40 and located above the six sleeves 20 in a one-to-one correspondence; the top and bottom surfaces of each sleeve 20 are connected to a top ring plate 21 and a bottom in a one-to-one correspondence The ring plate 22; the tops of the six engineering piles 70 pass through the six sleeves 20 in a one-to-one correspondence and are connected with the lower parts of the six cross connectors 50 in a one-to-one correspondence;

基础环30包括环身钢管300、焊接在环身钢管300底部的底座环板301、两个间隔地焊接在环身钢管300下部的连接环板302和焊接在环身钢管300顶部的环顶法兰303;海上风电的塔筒安装在基础环30的环顶法兰303上;底座环板301上均布地开设三对调平螺栓孔;The base ring 30 includes a ring body steel pipe 300, a base ring plate 301 welded on the bottom of the ring body steel pipe 300, two connecting ring plates 302 welded on the lower part of the ring body steel pipe 300 at intervals, and a ring top method welded on the top of the ring body steel pipe 300 flange 303; the tower of offshore wind power is installed on the ring top flange 303 of the foundation ring 30; three pairs of leveling bolt holes are evenly distributed on the base ring plate 301;

六块连接腹板40环向均布地径向连接在基础环30的两个连接环板302之间;The six connecting webs 40 are radially connected between the two connecting ring plates 302 of the base ring 30 in a circumferentially uniform manner;

每个十字连接件50的上部与对应的连接腹板40的外端焊接,每个十字连接件50的下部插入对应的工程桩70的顶部内腔中并与工程桩70的顶部内壁焊接。The upper part of each cross connection piece 50 is welded with the outer end of the corresponding connection web 40 , and the lower part of each cross connection piece 50 is inserted into the top inner cavity of the corresponding engineering pile 70 and welded with the top inner wall of the engineering pile 70 .

进行承台预制封底岸上制作流程时,包括以下步骤:套管定位和加固、封底板钢筋和承台外侧钢筋同步绑扎、封底板砼浇筑、承台底层钢筋和基础环内侧钢筋同步绑扎、基础环及连接件安装、承台底层钢筋和基础环外侧钢筋同步绑扎及承台钢套箱安装;The process of making the prefabricated back cover of the cap on the shore includes the following steps: casing positioning and reinforcement, synchronous binding of the reinforcing steel bars of the capping base plate and the outside reinforcing bars of the cap, concrete pouring of the capping base, synchronous binding of the reinforcing bars at the bottom of the cap and the reinforcing bars on the inner side of the foundation ring, and the foundation ring. And the installation of connecting parts, the synchronous binding of the steel bars on the bottom of the cap and the outside of the foundation ring, and the installation of the cap steel sleeves;

进行套管定位和加固步骤时,在底胎座上将六个套管20均布地布置在一个与工程桩70的布桩直径相同的圆上,并通过六根外侧槽钢23和三根内侧槽24钢将六个套管20连成整体,六根外侧槽钢23一一对应地连接在两根相邻的套管20之间,三根内侧槽钢24一一对应地连接在两根呈对角布置的套管20之间(见图1a);During the casing positioning and reinforcement steps, the six casings 20 are evenly distributed on a circle with the same diameter as the construction pile 70 on the base, and pass through the six outer channel steels 23 and the three inner channels 24. The steel connects the six sleeves 20 as a whole, the six outer channel steels 23 are connected between the two adjacent sleeves 20 in a one-to-one correspondence, and the three inner channel steels 24 are connected in a one-to-one correspondence between two diagonally arranged. between the sleeves 20 (see Figure 1a);

进行封底板钢筋和承台外侧钢筋同步绑扎步骤时,在底胎座上绑扎封底板钢筋时,在每个套管20的外侧绑扎环向钢筋,环向钢筋与封底板钢筋焊接连接,在封底板钢筋上预埋三个调平支座31、三个辅助支座32和六个吊耳35;三个调平支座31和三个辅助支座32均布置在一个与基础环30的环身钢管300的外径相同的圆上,三个调平支座31均布设置,三个辅助支座32均布地设在三个调平支座31之间(见图1b和图1c),其中一个辅助支座32设在风电的塔筒门方向;六个吊耳35均布地布置在六个套管20的同一个圆上并一一对应地位于两根相邻的套管20之间(见图2);在绑扎封底板钢筋时还要预留电缆管穿孔12和ICCP管穿孔13;When performing the step of synchronizing the binding of the reinforcing steel bars for the bottom plate and the outside of the cap, when binding the reinforcing bars for the bottom plate on the base, the circumferential reinforcing bars are bound on the outside of each casing 20, and the circumferential reinforcing bars are connected with the reinforcing bars of the bottom sealing plate by welding. Three leveling supports 31, three auxiliary supports 32 and six lifting lugs 35 are embedded in the steel plate; On the circle with the same outer diameter of the body steel pipe 300, the three leveling supports 31 are evenly arranged, and the three auxiliary supports 32 are evenly arranged between the three leveling supports 31 (see Fig. 1b and Fig. 1c ). One of the auxiliary supports 32 is arranged in the direction of the tower door of the wind power plant; the six lifting lugs 35 are evenly arranged on the same circle of the six bushings 20 and are located between two adjacent bushings 20 in a one-to-one correspondence. (See Figure 2); when tying the reinforcing bars of the sealing floor, the cable pipe perforation 12 and the ICCP pipe perforation 13 should be reserved;

进行封底板砼浇筑步骤时,砼浇筑完成后要养护7天;When carrying out the concrete pouring step of the closed bottom plate, the concrete should be cured for 7 days after the completion of the pouring;

进行基础环和连接件安装步骤时,将基础环30上的塔筒门标记对准一个设在塔筒门位置的辅助支座32后套在基础环内侧钢筋33上并坐落在三个调平支座31和三个辅助支座32上,并将基准环30的底座环板301上的三对调平螺栓孔与三个调平支座31上的调平螺栓一一对准,使基础环30通过三对调平螺栓与三个调平支座31连接,接着通过三个调平支座31初步调整基础环30的顶面水平度,要求基础环30的顶面对角最大相对高差不大于2mm,调整到位后将基础环30的底座环板301与三个辅组支座32进行点焊临时固定;再将六块连接腹板40均布地径向焊接在基础环30的外周面上,六块连接腹板40的环向位置与六个套管20的环向位置一一对应;然后将六个十字连接件50以比设定位置提高设定距离H=1.2m的方式一一对应地临时焊接在六块连接腹板40的外端(见图1d);考虑到十字连接件50的壁厚为40mm,考虑安装精度的要求,现场在工程桩70的顶部内壁上开焊接坡口不能过大,若先在工程桩70上开焊接坡口,有可能与十字连接件50对不准,造成十字连接件50安装不成功,因此六个十字连接件50在与对应的连接腹板40临时焊接时比设定位置提高1.2m,该位置在承台预制封底安装到位后,六个十字连接件50的底部恰好一一对应地位于六根工程桩70的顶部;When carrying out the installation steps of the foundation ring and the connecting piece, align the tower door mark on the foundation ring 30 with an auxiliary support 32 located at the position of the tower door, and then cover it on the inner steel bar 33 of the foundation ring and seat it on the three leveling brackets. On the support 31 and the three auxiliary supports 32, align the three pairs of leveling bolt holes on the base ring plate 301 of the reference ring 30 with the leveling bolts on the three leveling supports 31 one by one, so that the base ring 30 is connected with three leveling supports 31 through three pairs of leveling bolts, and then the top surface level of the base ring 30 is preliminarily adjusted through the three leveling supports 31. If the size is greater than 2mm, after adjusting in place, spot welding the base ring plate 301 of the base ring 30 and the three auxiliary group supports 32 to temporarily fix it; , the circumferential positions of the six connecting webs 40 are in one-to-one correspondence with the circumferential positions of the six sleeves 20; then the six cross-connecting pieces 50 are increased by a set distance H=1.2m from the set position one by one. Correspondingly, it is temporarily welded on the outer ends of the six connecting webs 40 (see Figure 1d); considering that the wall thickness of the cross connector 50 is 40mm, and considering the requirements of installation accuracy, a welding slope is opened on the top inner wall of the engineering pile 70 on site. The opening should not be too large. If the welding groove is first made on the engineering pile 70, it may be misaligned with the cross connector 50, resulting in the unsuccessful installation of the cross connector 50. Therefore, the six cross connectors 50 are in the corresponding connection belly. When the plate 40 is temporarily welded, it is 1.2m higher than the set position. After the prefabricated back cover of the cap is installed in place, the bottoms of the six cross connectors 50 are located on the top of the six engineering piles 70 in a one-to-one correspondence;

进行承台底层钢筋和基础环外侧钢筋同步绑扎步骤时,在砼封底板10上绑扎承台底层钢筋11,同时在基础环30的下部绑扎基础环外侧钢筋34(见图1e和图1f);When carrying out the step of synchronously binding the reinforcing bars on the bottom of the cap and the reinforcing bars on the outside of the foundation ring, bind the reinforcing bars 11 on the bottom of the cap on the concrete sealing bottom plate 10, and at the same time bind the reinforcing bars 34 on the outside of the foundation ring at the lower part of the foundation ring 30 (see Figure 1e and Figure 1f);

进行承台钢套箱安装步骤时,将承台钢套箱60套在承台外侧钢筋61上(见图1g);在承台钢套箱60安装完后形成承台预制封底,再将承台预制封底运至海上施工现场;When carrying out the steps of installing the steel cap box, cover the steel cap box 60 on the steel bar 61 outside the cap (see Fig. 1g); The prefabricated back cover is transported to the offshore construction site;

进行海上植桩流程时,包括以下步骤:嵌岩施工平台搭设、钢护筒沉设、嵌岩孔施工、工程桩植入、工程桩封底砼浇筑、工程桩外侧环空灌浆、钢护筒拔出、电缆管和ICCP管安装及承台支撑体系焊接;The process of offshore pile planting includes the following steps: rock-socketed construction platform erection, steel casing sinking, rock-socketed hole construction, engineering pile implantation, engineering pile bottom-sealing concrete pouring, engineering pile outer annulus grouting, steel casing extraction Outlet, cable pipe and ICCP pipe installation and platform support system welding;

进行承台支撑体系焊接步骤时,在每根工程桩70的位于承台底标高的外壁面上焊接一个支撑环板71和若干环向均布地焊接在支撑环板71的底面与工程桩70的外壁面之间的下支撑筋板72(见图2),六根工程桩70上的支撑环板71和下支撑筋板72形成承台支撑体系;When performing the welding step of the cap support system, a support ring plate 71 is welded on the outer wall surface of each engineering pile 70 at the bottom elevation of the cap, and a plurality of circumferentially evenly distributed welds are welded on the bottom surface of the support ring plate 71 and the engineering pile 70. The lower support rib plate 72 (see FIG. 2 ) between the outer walls, the support ring plate 71 and the lower support rib plate 72 on the six engineering piles 70 form a cap support system;

进行承台预制封底安装流程时,包括以下步骤:承台预制封底吊装及承台预制封底与工程桩连接;When carrying out the installation process of the prefabricated back cover of the cap, it includes the following steps: hoisting the prefabricated back cover of the cap and connecting the prefabricated back cover of the cap to the engineering pile;

进行承台预制封底吊装步骤时,先将承台预制封底的封底板10上预留的电缆管穿孔12和ICCP管穿孔13一一对应地套在电缆管120及ICCP管130上,并将封底板10上的六个套管20一一对应地套在与六根工程桩70上,接着将承台预制封底缓慢下落至工程桩70的承台支撑体系上(见图3),此时六个十字连接件50的底部恰好一一对应地位于六根工程桩70的顶部,再将每根工程桩70上的支撑环板71与对应的套管20的底环板22焊接加固,并在每个套管20的顶环板21与对应的工程桩70的外壁面之间通过若干环向均布的上支撑筋板焊接加固,然后复测基础环30的水平度;复测时,解除基础环30的座底环板301与三个辅助支座32的点焊,通过三个调平支座31调整基础环30的水平度;When carrying out the step of hoisting the prefabricated bottom cover of the platform, firstly cover the cable tube perforations 12 and ICCP tube perforations 13 reserved on the sealing bottom plate 10 of the platform prefabricated back cover on the cable tube 120 and the ICCP tube 130 in one-to-one correspondence, and put the back cover. The six sleeves 20 on the plate 10 are set on the six engineering piles 70 in one-to-one correspondence, and then the prefabricated back cover of the cap is slowly dropped onto the cap support system of the engineering pile 70 (see FIG. 3 ). The bottom of the cross connector 50 is located on the top of the six engineering piles 70 in a one-to-one correspondence, and then the support ring plate 71 on each engineering pile 70 and the bottom ring plate 22 of the corresponding casing 20 are welded and strengthened, and each The top ring plate 21 of the casing 20 and the outer wall surface of the corresponding engineering pile 70 are welded and reinforced by several upper support ribs evenly distributed in the circumferential direction, and then the levelness of the foundation ring 30 is re-measured; during the re-measurement, the foundation ring is removed. The spot welding of the base ring plate 301 of the base 30 and the three auxiliary supports 32, and the leveling of the base ring 30 is adjusted through the three leveling supports 31;

进行承台预制封底与工程桩连接步骤时,先在每根工程桩70的顶部内壁面上根据对应的十字连接件50的投影开设高度为H=1.2m的焊接坡口,接着解除每个十字连接件50与对应的连接腹板40的临时焊接,再将十字连接件50的下部1.2m沿对应的工程桩70的焊接坡口插入工程桩70内,然后将十字连接件50的上部与对应的连接腹板40焊接,同时将十字连接件50的下部与对应的工程桩70焊接(见图4、图5和图6);When performing the step of connecting the prefabricated back cover of the cap and the engineering piles, firstly open a welding groove with a height of H=1.2m on the top inner wall surface of each engineering pile 70 according to the projection of the corresponding cross connector 50, and then release each cross. Temporary welding of the connecting piece 50 and the corresponding connecting web 40, then insert the lower 1.2m of the cross connecting piece 50 into the engineering pile 70 along the welding groove of the corresponding engineering pile 70, and then connect the upper part of the cross connecting piece 50 to the corresponding engineering pile 70. The connecting web 40 is welded, and at the same time, the lower part of the cross connector 50 is welded with the corresponding engineering pile 70 (see Figure 4, Figure 5 and Figure 6);

进行承台二期施工流程时,包括以下步骤:电缆管和ICCP管接长、承台其余钢筋绑扎和预埋件安装及承台砼浇筑;During the second-phase construction process of the cap, it includes the following steps: connecting the cable pipe and the ICCP pipe, tying the remaining steel bars of the cap, installing the embedded parts, and pouring the cap concrete;

进行电缆管和ICCP管接长步骤时,将电缆管承台段和ICCP管承台段各自通过法兰一一对应地与电缆管120和ICCP管130连接,使电缆管承台段的上端和ICCP管承台段的上端至承台的顶面。During the step of connecting the cable tube and the ICCP tube, connect the cable tube support section and the ICCP tube support section to the cable tube 120 and the ICCP tube 130 through flanges in one-to-one correspondence, so that the upper end of the cable tube support section and the ICCP tube are connected to each other. The upper end of the ICCP pipe cap section to the top surface of the cap.

以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变型,因此所有等同的技术方案也应该属于本发明的范畴,应由各权利要求所限定。The above embodiments are only for illustrating the present invention, rather than limiting the present invention. Those skilled in the relevant technical field can also make various changes or modifications without departing from the spirit and scope of the present invention. Therefore, all equivalents The technical solution of the invention should also belong to the scope of the present invention and should be defined by the claims.

Claims (2)

1. The prefabricated back cover and the installation process of the offshore wind power implanted high-rise pile cap are characterized by comprising the following processes: the method comprises the following steps of (1) onshore manufacturing of a prefabricated back cover of a bearing platform, offshore pile planting, prefabricated back cover installation of the bearing platform and second-stage construction of the bearing platform;
the bearing platform prefabricated back cover comprises a concrete back cover plate, six pile penetrating holes uniformly distributed on the concrete back cover plate, six sleeves which are embedded in the pile penetrating holes in a one-to-one correspondence mode and have the same height as the thickness of the concrete back cover plate, a base ring arranged in the center of the top surface of the concrete back cover plate, six connecting webs which are radially connected to the outer peripheral surface of the base ring in an evenly distributed mode and six cross-shaped connecting pieces which are connected to the outer ends of the six connecting webs in a one-to-one correspondence mode and located above the six sleeves in a one-to-one correspondence mode; the top surface and the bottom surface of each sleeve are connected with a top ring plate and a bottom ring plate in a one-to-one correspondence manner; the tops of the six engineering piles penetrate through the six sleeves in a one-to-one corresponding manner and are connected with the lower parts of the six cross-shaped connecting pieces in a one-to-one corresponding manner;
when the shoreside manufacturing process of the bearing platform prefabricated back cover is carried out, the method comprises the following steps: positioning and reinforcing a sleeve, synchronously binding reinforcing steel bars of a sealing bottom plate and reinforcing steel bars outside a bearing platform, pouring concrete of the sealing bottom plate, synchronously binding reinforcing steel bars of a bottom layer of the bearing platform and reinforcing steel bars inside a foundation ring, installing the foundation ring and a connecting piece, binding reinforcing steel bars outside the foundation ring and installing a steel sleeve box of the bearing platform;
when the sleeve positioning and reinforcing step is carried out, six sleeves are uniformly distributed on a circle with the same diameter as the pile arrangement diameter of an engineering pile on a base tire seat, and are connected into a whole through six outer side channel steels and three inner side channel steels, the six outer side channel steels are connected between two adjacent sleeves in a one-to-one correspondence manner, and the three inner side channel steels are connected between two sleeves which are arranged diagonally in a one-to-one correspondence manner;
when the synchronous binding step of the reinforcing steel bars of the sealing bottom plate and the reinforcing steel bars outside the bearing platform is carried out, when the reinforcing steel bars of the sealing bottom plate are bound on the bottom tire seat, the annular reinforcing steel bars are bound on the outer side of each sleeve, and the annular reinforcing steel bars are welded with the reinforcing steel bars of the sealing bottom plate; embedding three leveling supports, three auxiliary supports and six lifting lugs on the reinforcing steel bars of the sealing bottom plate; the three leveling supports and the three auxiliary supports are uniformly arranged on a circle with the same outer diameter as the ring body steel pipe of the foundation ring, the three leveling supports are uniformly arranged, the three auxiliary supports are uniformly arranged among the three leveling supports, and one auxiliary support is arranged in the direction of a tower door of the wind power generation tower; the six lifting lugs are uniformly distributed on the same circle of the six sleeves and are positioned between two adjacent sleeves in a one-to-one correspondence manner; a cable pipe perforation and an ICCP pipe perforation are reserved when the steel bars of the sealing bottom plate are bound;
when the step of pouring the concrete of the sealing bottom plate is carried out, the concrete is cured for 7 days after the pouring is finished;
when the step of installing the foundation ring and the connecting piece is carried out, firstly, aligning a tower drum door mark on the foundation ring with an auxiliary support arranged at the position of the tower drum door, then sleeving the tower drum door mark on the steel bars at the inner side of the foundation ring, and locating the tower drum door mark on the three leveling supports and the three auxiliary supports, then primarily adjusting the levelness of the top surface of the foundation ring through the three leveling supports, temporarily fixing the foundation ring and the three auxiliary supports in a spot welding manner after the adjustment is in place, then uniformly and radially welding six connecting webs on the outer peripheral surface of the foundation ring, wherein the annular positions of the six connecting webs correspond to the annular positions of six sleeves one by one; then, temporarily welding the six cross connecting pieces at the outer ends of the six connecting webs in a one-to-one correspondence manner in a manner of increasing a certain distance H from the set position;
when the step of synchronously binding the reinforcing steel bars at the bottom layer of the bearing platform and the reinforcing steel bars at the outer side of the foundation ring is carried out, the reinforcing steel bars at the bottom layer of the bearing platform are bound on the concrete sealing bottom plate, and meanwhile, the reinforcing steel bars at the outer side of the foundation ring are bound at the lower part of the foundation ring;
when the step of installing the bearing platform steel sleeve box is carried out, the bearing platform steel sleeve box is sleeved on the reinforcing steel bars outside the bearing platform; forming a bearing platform prefabricated back cover after the bearing platform steel sleeve box is installed, and then transporting the bearing platform prefabricated back cover to the offshore construction site;
when the offshore pile planting process is carried out, the method comprises the following steps: erecting a rock-socketed construction platform, sinking a steel casing, constructing a rock-socketed hole, implanting an engineering pile, pouring bottom sealing concrete of the engineering pile, grouting annular space outside the engineering pile, pulling out the steel casing, installing a cable pipe and an ICCP pipe and welding a bearing platform support system;
when the step of welding the bearing platform supporting system is carried out, a supporting ring plate and a plurality of lower supporting rib plates which are annularly and uniformly welded between the bottom surface of the supporting ring plate and the outer wall surface of the engineering pile are welded on the outer wall surface of each engineering pile, and the supporting ring plates and the lower supporting rib plates on the six engineering piles form the bearing platform supporting system;
when the bearing platform prefabricated back cover installation process is carried out, the method comprises the following steps: hoisting the prefabricated back cover of the bearing platform and connecting the prefabricated back cover of the bearing platform with the engineering pile;
when the bearing platform prefabricated back cover hoisting step is carried out, firstly, the preformed holes on the back cover plate of the bearing platform prefabricated back cover are sleeved on the cable pipe and the ICCP pipe, six sleeves on the back cover plate are sleeved on six engineering piles in a one-to-one correspondence mode, then, the bearing platform prefabricated back cover slowly falls to a bearing platform support system, then, a support ring plate on each engineering pile and a bottom ring plate of the corresponding sleeve are welded and reinforced, and a plurality of upper support rib plates which are circumferentially and uniformly distributed are welded and reinforced between a top ring plate of each sleeve and the outer wall surface of the corresponding engineering pile, and then, the levelness of the foundation ring is measured again;
when the step of connecting the prefabricated bottom cover of the bearing platform with the engineering piles is carried out, firstly, a welding groove with the height of H is formed in the inner wall surface of the top of each engineering pile according to the projection of the corresponding cross-shaped connecting piece, then the temporary welding between each cross-shaped connecting piece and the corresponding connecting web plate is removed, then, the lower part of each cross-shaped connecting piece is inserted into the engineering pile along the welding groove of the corresponding engineering pile, then, the upper part of each cross-shaped connecting piece is welded with the corresponding connecting web plate, and meanwhile, the lower part of each cross-shaped connecting piece is welded with the corresponding engineering pile;
when the second-stage construction process of the bearing platform is carried out, the method comprises the following steps: the cable pipe and the ICCP pipe are lengthened, the rest reinforcing steel bars of the bearing platform are bound, the embedded part is installed, and the concrete of the bearing platform is poured.
2. The offshore wind power implanted high pile cap prefabricated bottom sealing and mounting process according to claim 1, wherein the foundation ring comprises a ring body steel pipe, a base ring plate welded at the bottom of the ring body steel pipe, two connecting ring plates welded at intervals at the lower part of the ring body steel pipe and a ring top flange welded at the top of the ring body steel pipe, wherein a pair of leveling bolt holes are respectively formed in the positions, corresponding to the three leveling supports, on the base ring plate, so that the foundation ring is connected with the three leveling supports through the three pairs of leveling bolts; the six connecting webs are uniformly connected between the two connecting ring plates of the foundation ring; the upper part of each cross connecting piece is welded with the outer end of the corresponding connecting web plate, and the lower part of each cross connecting piece is inserted into the inner cavity of the top of the corresponding engineering pile and is welded with the inner wall of the top of the engineering pile.
CN202110726753.0A 2021-06-29 2021-06-29 Prefabricated back cover of offshore wind power implanted high-rise pile cap and installation process Active CN113356256B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110726753.0A CN113356256B (en) 2021-06-29 2021-06-29 Prefabricated back cover of offshore wind power implanted high-rise pile cap and installation process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110726753.0A CN113356256B (en) 2021-06-29 2021-06-29 Prefabricated back cover of offshore wind power implanted high-rise pile cap and installation process

Publications (2)

Publication Number Publication Date
CN113356256A CN113356256A (en) 2021-09-07
CN113356256B true CN113356256B (en) 2022-05-06

Family

ID=77537043

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110726753.0A Active CN113356256B (en) 2021-06-29 2021-06-29 Prefabricated back cover of offshore wind power implanted high-rise pile cap and installation process

Country Status (1)

Country Link
CN (1) CN113356256B (en)

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938645B (en) * 2014-03-14 2016-05-04 中国电建集团西北勘测设计研究院有限公司 The precast concrete cushion cap in reserved basic annular distance and stake nest hole and many pile foundations of the assembled installation method based on this cushion cap
CN103912007B (en) * 2014-03-14 2016-05-25 中国电建集团西北勘测设计研究院有限公司 The installation method of the precast concrete cushion cap of reserved basic annular distance and stake nest annular distance and the many pile foundations of assembled based on this cushion cap
CN107152032A (en) * 2017-05-23 2017-09-12 中能电力科技开发有限公司 The template system and the construction method of cushion cap of a kind of bearing platform construction for offshore wind farm
CN111218950B (en) * 2020-03-12 2024-08-02 中交第三航务工程局有限公司 Offshore wind power single pile and high pile cap foundation steel pipe pile planting shared construction platform
CN212956608U (en) * 2020-07-28 2021-04-13 中交第三航务工程局有限公司 Rock-socketed construction platform of combined type offshore wind power foundation steel pipe pile

Also Published As

Publication number Publication date
CN113356256A (en) 2021-09-07

Similar Documents

Publication Publication Date Title
CN111851567B (en) Newly built or expanded wind power foundation on shallow overburden layer of soft foundation and construction method thereof
KR101659783B1 (en) Hybrid type concrete foundation of offshore wind turbine using composite of concrete and steel sleevee and fabrication method thereof
CN101691751B (en) Construction method for making ultra-long artificial excavating pile penetrate cave and ultra-long pile penetrating cave
CN105863042A (en) All-steel structure building and construction method thereof
CN108678751B (en) Assembly type construction method of shield cutter head manhole by jacking and excavating firstly
KR20160143599A (en) Hybrid type concrete foundation of offshore wind turbine using composite of concrete and steel sleevee and fabrication method thereof
CN109680702A (en) Suction cartridge type single-pile foundation structure and its construction method
CN113914392A (en) Existing building transformation method
CN212561601U (en) New and expanded wind power foundations on weak foundations and shallow overlays
CN210086295U (en) Compound assembled underground structure
CN112302052B (en) Vertical shaft construction system and construction method thereof
KR101187170B1 (en) Application of under pinning method in remodeling
CN112483126A (en) Construction method of underground excavation air duct of composite stratum with upper soft part and lower hard part
CN113356256B (en) Prefabricated back cover of offshore wind power implanted high-rise pile cap and installation process
CN109930624A (en) A kind of embedding petrographic province blower foundation of offshore wind farm and construction method
CN210395407U (en) Anchor rod gravity type offshore wind power foundation
CN210562287U (en) Compound assembled underground structure
CN115961639B (en) A kind of overhead power transmission line platform on water and construction method thereof
CN218597172U (en) Bottom-expanding foundation pit assembled type retaining wall device suitable for mountain region emergency and recycling
JP2020128672A (en) Installation method of mono-pile foundation for offshore wind power generation and mono-pile foundation for offshore wind power generation
CN112900479B (en) Construction method of implanted single-pile foundation of ocean tidal current energy generator set
JP4475116B2 (en) Vertical shaft structure and its construction method
CN210857277U (en) Assembled underground structure
EP3779050A1 (en) Method for building concrete foundations for lattice-type offshore structures, and foundations built using this method
CN222685471U (en) Rock Embedded Construction Equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road

Patentee after: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Patentee after: CCCC Third Aviation Bureau Sixth Engineering (Xiamen) Co., Ltd.

Patentee after: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Address before: 200032 No. 139, Xuhui District, Shanghai, Pingjiang Road

Patentee before: CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

Patentee before: CCCC Sanya (Xiamen) Engineering Co.,Ltd.

Patentee before: XIAMEN BRANCH OF CCCC THIRD HARBOR ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder