CN113290527A - Quick assembling and disassembling device for tower barrel - Google Patents

Quick assembling and disassembling device for tower barrel Download PDF

Info

Publication number
CN113290527A
CN113290527A CN202110793345.7A CN202110793345A CN113290527A CN 113290527 A CN113290527 A CN 113290527A CN 202110793345 A CN202110793345 A CN 202110793345A CN 113290527 A CN113290527 A CN 113290527A
Authority
CN
China
Prior art keywords
tower
cylinder
cross beam
cross
inner tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110793345.7A
Other languages
Chinese (zh)
Inventor
魏秋东
孙从义
魏中保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heze Jingjiu Special Automobile Co ltd
Original Assignee
Heze Jingjiu Special Automobile Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heze Jingjiu Special Automobile Co ltd filed Critical Heze Jingjiu Special Automobile Co ltd
Priority to CN202110793345.7A priority Critical patent/CN113290527A/en
Publication of CN113290527A publication Critical patent/CN113290527A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25BTOOLS OR BENCH DEVICES NOT OTHERWISE PROVIDED FOR, FOR FASTENING, CONNECTING, DISENGAGING OR HOLDING
    • B25B27/00Hand tools, specially adapted for fitting together or separating parts or objects whether or not involving some deformation, not otherwise provided for
    • B25B27/14Hand tools, specially adapted for fitting together or separating parts or objects whether or not involving some deformation, not otherwise provided for for assembling objects other than by press fit or detaching same

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Wind Motors (AREA)

Abstract

The invention relates to the technical field of handling equipment, and discloses a tower cylinder rapid handling device which comprises a cross beam and a platform, wherein the top of the platform is fixedly provided with a guide outer cylinder, a lifting inner cylinder is sleeved in the guide outer cylinder, a cross beam is fixedly arranged between the two lifting inner cylinders, two ends of the cross beam are fixedly arranged at the top of the lifting inner cylinder through connecting pins, the surface of the cross beam is symmetrically provided with cross arms, the lifting inner cylinder is internally provided with a hydraulic connecting rod, the top of the hydraulic connecting rod is provided with a piston, the piston consists of four bases and two cross beams, each base consists of the platform, a rib plate, the guide outer cylinder and the lifting inner cylinder, each cross beam is provided with two movable cross arms which can fix tower cylinders with different sizes, the cross beams and the bases are connected through the connecting pins, so that the effects of convenient disassembly and convenient transportation are achieved, and the distance between the two cross arms can be adjusted at will, thereby the effect of adaptation different external diameter tower barrels has been reached.

Description

Quick assembling and disassembling device for tower barrel
Technical Field
The invention relates to the technical field of loading and unloading equipment, in particular to a tower cylinder rapid loading and unloading device.
Background
Wind energy is increasingly gaining attention as a clean renewable energy source in all countries of the world. The wind power generation device has huge energy, the global wind power is about 2.74 multiplied by 10^9MW, the available wind power is 2 multiplied by 10^7MW and is 10 times larger than the total amount of water energy which can be developed and utilized on the earth, wind is utilized by people very early, mainly water pumping, surface grinding and the like are carried out through a windmill, at present, people are interested in how to utilize wind to generate electricity, the wind power generation is valued at home at the present stage, natural resources are fully utilized, the environment is protected, no pollution is caused, the wind power generation can not leave large-sized fans and towers, the transportation and installation of the towers in the wind power generation device mainly use cranes, the time and labor are wasted, and the cost is high.
Disclosure of Invention
The invention aims to provide a tower cylinder rapid assembling and disassembling device to solve the problems in the prior art
In order to achieve the purpose, the invention provides the following technical scheme: the utility model provides a tower section of thick bamboo fast loading and unloading device, includes crossbeam and platform, the top fixed mounting of platform has the direction urceolus, the inside cover of direction urceolus is equipped with lifts the inner tube, two lift and fixedly be provided with the crossbeam between the inner tube, the both ends of crossbeam are through connecting pin fixed mounting at the top of lifting the inner tube, the surface symmetry of crossbeam is provided with the cross arm, the inside of lifting the inner tube is provided with the hydraulic link, the piston is installed at the top of hydraulic link.
Preferably, the pneumatic cylinder is provided with four, the pneumatic cylinder passes through ball valve and leads two liang of intercommunications of oil pipe, two the pneumatic cylinder leads and connects in switching-over valve interface department through quick-operation joint between the oil pipe, switching-over valve one side is connected with the check valve through leading oil pipe, the check valve is through leading oil pipe and hydraulic pump connection, hydraulic pump and power supply intercommunication.
Preferably, the cross arm is movably sleeved on the surface of the cross beam, and a plurality of positioning holes are formed in the surface of the cross beam.
Preferably, the top of the lifting inner cylinder is fixedly provided with a mounting fork, two ends of the cross beam are arranged in the mounting fork, two sets of through holes are symmetrically formed in the two sides of the mounting fork at the top of the lifting inner cylinder, and the connecting pin penetrates through the through holes in the two sides of the mounting fork.
Preferably, rib plates are symmetrically arranged on two sides of the top of the platform, and the tops of the rib plates are welded on two sides of the guide outer cylinder.
Preferably, a barrel bottom bolt is screwed at the bottom of the hydraulic oil cylinder, and the cross beam and the cross arm are made of I-shaped steel materials.
Compared with the prior art, the invention provides a tower cylinder rapid loading and unloading device, which has the following beneficial effects:
this tower section of thick bamboo fast loading and unloading device through constituting by four bases and two crossbeams, the base comprises platform, gusset, direction urceolus, the inner tube of lifting, and has two activity cross arms on every crossbeam, can fix the tower section of thick bamboo of equidimension not, and the crossbeam is connected by the connecting pin with the base to reached convenient to detach, the effect of convenient transportation, and can adjust the interval at will between two cross arms, thereby reached the effect that adapts to different external diameter tower section of thick bamboo.
The quick loading and unloading device for the tower barrel is characterized in that two devices are hoisted to proper positions at the front end and the rear end of the tower barrel by a vehicle, a hydraulic oil cylinder is driven by a power source, a cross beam is lifted to a proper height, a cross arm and the tower barrel are connected by bolts, so that the tower barrel and the cross arm are fixed, the inner barrel is lifted through power source control to lift the tower barrel to a certain height, the transport vehicle is driven to the lower portion of the tower barrel, the crossbeam tower barrel is descended to complete loading, the loading and unloading device is placed at a proper position in a field, the crossbeam is lifted to a certain height, the wind power generation tower barrel transport vehicle is driven to the lower portion of the two crossbeams, the lifting inner barrel is controlled to descend to a proper position, the cross arm and the tower barrel are connected through bolts, a flange of the tower barrel and the cross arm are fixed through bolts, the power source drives the hydraulic cylinder, the lifting inner barrel is lifted, the tower barrel is separated from a vehicle body, the transport vehicle is driven out, the tower barrel is descended to the ground to complete stacking of the tower barrel, and therefore the effect of fast loading and unloading of the tower barrel is achieved.
Drawings
FIG. 1 is a front view of the present invention;
FIG. 2 is a cross-sectional view of the present invention;
FIG. 3 is a left side view of the present invention;
FIG. 4 is a top view of the present invention;
FIG. 5 is a hydraulic schematic of a tower of the present invention.
In the figure: 1. a cross beam; 2. a cross arm; 3. a platform; 4. a guide outer cylinder; 5. lifting the inner barrel; 6. a rib plate; 7. a connecting pin; 8. a hydraulic cylinder; 9. a barrel bottom bolt; 10. a hydraulic link; 11. a piston; 12. a hydraulic cylinder; 13. a ball valve; 14. a quick coupling; 15. a diverter valve; 16. a one-way valve; 17. a power source; 18. a hydraulic pump.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-5, a tower cylinder fast loading and unloading device includes a cross beam 1 and a platform 3, a guide outer cylinder 4 is fixedly installed on the top of the platform 3, a lifting inner cylinder 5 is sleeved inside the guide outer cylinder 4, the cross beam 1 is fixedly installed between the two lifting inner cylinders 5, two ends of the cross beam 1 are fixedly installed on the top of the lifting inner cylinder 5 through a connecting pin 7, cross arms 2 are symmetrically installed on the surface of the cross beam 1, a hydraulic connecting rod 10 is installed inside the lifting inner cylinder 5, and a piston 11 is installed on the top of the hydraulic connecting rod 10.
In order to show the working principle of the hydraulic cylinder 8 more clearly, in the embodiment, preferably, four hydraulic cylinders 12 are provided, the hydraulic cylinders 12 are communicated with two oil guide pipes through ball valves 13, the two oil guide pipes of the two hydraulic cylinders 12 are connected to a joint of a reversing valve 15 through quick connectors 14, one side of the reversing valve 15 is connected with a one-way valve 16 through the oil guide pipe, the one-way valve 16 is connected with a hydraulic pump 18 through the oil guide pipe, and the hydraulic pump 18 is communicated with a power source 17.
In order to fix 2 positions of cross arm after adjusting, prevent at the handling in-process, because rock and lead to cross arm 2 to take place the displacement, preferred in this embodiment, cross arm 2 movable sleeve establishes on the surface of crossbeam 1, and a plurality of locating holes have been seted up on the surface of crossbeam 1.
In order to conveniently install the cross beam 1 on the top of the lifting inner cylinder 5, in this embodiment, preferably, the top of the lifting inner cylinder 5 is fixedly installed with an installation fork, two ends of the cross beam 1 are placed in the installation fork, two sides of the installation fork at the top of the lifting inner cylinder 5 are symmetrically provided with two groups of through holes, and the connecting pin 7 penetrates through the through holes at two sides of the installation fork.
In order to enhance the stability of the guide outer cylinder 4 and improve the rigidity of the device, in the embodiment, it is preferable that rib plates 6 are symmetrically arranged on two sides of the top of the platform 3, and the tops of the rib plates 6 are welded on two sides of the guide outer cylinder 4.
In order to make the cross beam 1 and the cross arm 2 have stronger pressure-bearing capacity and reduce the cost in the manufacturing process, in this embodiment, it is preferable that the bottom of the hydraulic cylinder 8 is screwed with a barrel bottom bolt 9, and both the cross beam 1 and the cross arm 2 are made of i-steel materials.
The working principle is as follows: before the device is used, a user needs to check the device, check whether the connection and installation of each part of the device are normal or not, and use the device after the check is finished, firstly, a base and a beam 1 are connected by a connecting pin 7 for assembly, two devices are hoisted to proper positions at the front end and the rear end of a tower drum by using a vehicle, a power source 17 drives a hydraulic oil cylinder 8, the beam 1 is hoisted to proper height, a cross arm 2 and the tower drum are connected by using bolts, the tower drum is fixed with the cross arm 2, a hoisting inner cylinder 5 is controlled by the power source 17 to hoist to certain height, a transport vehicle is driven to the lower part of the tower, the beam 1 is descended to complete loading, the loading and unloading device is hoisted by using the vehicle to proper position in the field, the beam 1 is hoisted to certain height, the transport vehicle for the wind power generation tower is driven to hoist to certain height under the two beams 1, the hoisting inner cylinder 5 is controlled to descend to proper position, the cross arm 2 and the tower drum are connected by using bolts, the flange of the tower cylinder and the cross arm 2 are fixed by bolts, the power source 17 drives the hydraulic cylinder 12 to lift the lifting inner cylinder 5, the tower cylinder is separated from the vehicle body, the transport vehicle is driven out, and the tower cylinder is lowered to the ground to complete stacking of the tower cylinder, so that the effect of quickly loading and unloading the tower cylinder is achieved.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a tower section of thick bamboo fast loading and unloading device, includes crossbeam (1) and platform (3), its characterized in that: the top fixed mounting of platform (3) has direction urceolus (4), the inside cover of direction urceolus (4) is equipped with lifts inner tube (5), two lift inner tube (5) between the fixed crossbeam (1) that is provided with, the both ends of crossbeam (1) are through connecting pin (7) fixed mounting at the top of lifting inner tube (5), the surface symmetry of crossbeam (1) is provided with cross arm (2), the inside of lifting inner tube (5) is provided with hydraulic link (10), piston (11) are installed at the top of hydraulic link (10).
2. A tower section of thick bamboo fast loading and unloading device, includes pneumatic cylinder (12) and switching-over valve (15), its characterized in that: pneumatic cylinder (12) are provided with four, pneumatic cylinder (12) are through ball valve (13) and two liang of intercommunications of oil pipe, two pneumatic cylinder (12) are led and are connected at switching-over valve (15) kneck through quick-operation joint (14) between the oil pipe, switching-over valve (15) one side is connected with check valve (16) through leading oil pipe, check valve (16) are connected with hydraulic pump (18) through leading oil pipe, hydraulic pump (18) and power supply (17) intercommunication.
3. The tower quick assembly disassembly device of claim 1, wherein: the cross arm (2) is movably sleeved on the surface of the cross beam (1), and a plurality of positioning holes are formed in the surface of the cross beam (1).
4. The tower quick assembly disassembly device of claim 1, wherein: the top fixed mounting who lifts inner tube (5) has the installation fork, the both ends of crossbeam (1) are put and are pitched in, lift inner tube (5) top installation fork bilateral symmetry and seted up two sets of through-holes, connecting pin (7) run through the installation and pitch both sides through-hole.
5. The tower quick assembly disassembly device of claim 1, wherein: rib plates (6) are symmetrically arranged on two sides of the top of the platform (3), and the tops of the rib plates (6) are welded on two sides of the guide outer cylinder (4).
6. The tower quick assembly disassembly device of claim 1, wherein: the bottom of the hydraulic oil cylinder (8) is screwed with a barrel bottom bolt (9), and the cross beam (1) and the cross arm (2) are made of I-shaped steel materials.
CN202110793345.7A 2021-07-14 2021-07-14 Quick assembling and disassembling device for tower barrel Pending CN113290527A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110793345.7A CN113290527A (en) 2021-07-14 2021-07-14 Quick assembling and disassembling device for tower barrel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110793345.7A CN113290527A (en) 2021-07-14 2021-07-14 Quick assembling and disassembling device for tower barrel

Publications (1)

Publication Number Publication Date
CN113290527A true CN113290527A (en) 2021-08-24

Family

ID=77331029

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110793345.7A Pending CN113290527A (en) 2021-07-14 2021-07-14 Quick assembling and disassembling device for tower barrel

Country Status (1)

Country Link
CN (1) CN113290527A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1250630A (en) * 1967-11-09 1971-10-20
DE10318675A1 (en) * 2003-04-24 2004-11-18 Greifzug Hebezeugbau Gmbh Lifting platform for inspection installations for maintaining wind power installation rotor blades has platform elements fitted around an opening with dimensions adapted to the blades
CN202518969U (en) * 2012-03-27 2012-11-07 沈阳华创风能有限公司 Tower hoisting equipment

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1250630A (en) * 1967-11-09 1971-10-20
DE10318675A1 (en) * 2003-04-24 2004-11-18 Greifzug Hebezeugbau Gmbh Lifting platform for inspection installations for maintaining wind power installation rotor blades has platform elements fitted around an opening with dimensions adapted to the blades
CN202518969U (en) * 2012-03-27 2012-11-07 沈阳华创风能有限公司 Tower hoisting equipment

Similar Documents

Publication Publication Date Title
CN203159047U (en) Hydraulic span and height adjustable gantry crane
CN104477788B (en) Spanning self-climbing type translational crane of wind power generation tower
CN103342296B (en) Adhering self-elevating-type tower crane for hoisting wind power equipment
CN102101630B (en) Hydraulic climbing self-hoisting device for wind driven generator
CN202645875U (en) Movable type support protection device for wind driven generator blade
CN202240369U (en) Slewing bearing replacement device for crane
CN212315372U (en) Electromagnet adsorption device of crane for wind power generation installation and maintenance
CN113290527A (en) Quick assembling and disassembling device for tower barrel
CN202400754U (en) Mast crane
CN103195660B (en) A kind of pylon of truss structure
CN204281116U (en) Wind power generation stepped leap self-crawling type translation loop wheel machine
CN108439266B (en) Jacking device for crane
CN102094543A (en) Pneumatic lifting communication tower
CN215364450U (en) Utility tunnel hoist and portal crane
CN109236211A (en) A kind of production rig
CN202055507U (en) Desulfurizing tower examination and repair platform
CN204281114U (en) Wind power generation stepped from climbing arch maintenance robot
CN203808097U (en) Foundation structure of offshore wind-power pipe frame
CN202556057U (en) Propeller pitch changing operating platform for wheel type wind driven generator impeller
CN201619965U (en) Climbing lift
CN111547629A (en) Electromagnet adsorption device of crane for wind power generation installation and maintenance
CN204877284U (en) Open -air resource investigation uses scalable derrick
CN205820706U (en) A kind of gantry crane's supporting legs
CN207175356U (en) A kind of hydraulic lift
CN102277957B (en) Overhaul platform of desulfurizing tower

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination