CN113235920A - Formwork supporting platform and secondary erecting construction method - Google Patents

Formwork supporting platform and secondary erecting construction method Download PDF

Info

Publication number
CN113235920A
CN113235920A CN202110466740.4A CN202110466740A CN113235920A CN 113235920 A CN113235920 A CN 113235920A CN 202110466740 A CN202110466740 A CN 202110466740A CN 113235920 A CN113235920 A CN 113235920A
Authority
CN
China
Prior art keywords
platform
beams
pad
main
supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110466740.4A
Other languages
Chinese (zh)
Inventor
徐愿生
余振林
汤继友
王龙
汪永
白守更
熊航
刘泽芳
陈翰林
于永浩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202110466740.4A priority Critical patent/CN113235920A/en
Publication of CN113235920A publication Critical patent/CN113235920A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention relates to the field of building construction, in particular to a template supporting platform and a secondary erection construction method; the method is characterized in that: the platform comprises a space system consisting of platform stand columns, platform pad beams, platform connecting beams and platform main beams, wherein the platform stand columns are vertical supporting pieces, the platform pad beams, the platform connecting beams and the platform main beams are horizontal supporting pieces, the platform pad beams are positioned at the tops of the platform stand columns, the platform connecting beams are positioned on the upper portions of the platform pad beams and are placed in a crossed mode with the platform pad beams, and the platform main beams are positioned on the upper portions of the platform connecting beams and are placed in a crossed mode with the platform connecting beams to form a full-hall supporting frame supporting base. The template supporting platform and the secondary frame aligning method thereof have the advantages that: the turnover material consumption of a high and large formwork support system is reduced, the installation and dismantling workload of the support frame is reduced, the construction efficiency is improved, the construction cost is reduced, and the safety is improved.

Description

Formwork supporting platform and secondary erecting construction method
Technical Field
The invention relates to the field of building construction, in particular to a formwork supporting platform and a secondary erection construction method.
Background
The common method of formwork support in the building construction field is to set up a full-hall support frame, the using amount of turnover materials of a frame body is large, the setting workload of the frame body is large, the construction efficiency is low, the construction cost is high, and the safety risk is high.
Disclosure of Invention
The invention aims to overcome the defects and shortcomings of construction by using a traditional full framing formwork support system, provides a simple construction method for secondary erection by using a platform, and is particularly suitable for a high and large formwork support system.
In order to achieve the above object, the present invention is realized by:
the utility model provides a template supporting platform, includes the space system who comprises platform stand, platform pad roof beam, platform even roof beam, platform girder, wherein, the platform stand is vertical support piece, platform pad roof beam, platform even roof beam, platform girder are horizontal support piece, platform pad roof beam is located platform stand top, platform even roof beam is located platform pad roof beam upper portion, alternately places with platform pad roof beam, the platform girder is located platform even roof beam upper portion, even roof beam is alternately placed with the platform, constitutes full hall support frame supporting pedestal.
The method for carrying out secondary erection construction on the formwork supporting platform comprises the following steps,
the method comprises the following steps: the upright post of the platform is installed,
the platform upright post is positioned at the lower part of the formwork support system and is a space system formed by mutually connecting a group of vertical rods, cross rods and inclined rods;
step two: a pad beam of the platform is installed,
the top of the platform upright post is provided with a platform pad beam which is supported at the top of two (or more) upright posts;
step three: a connecting beam of a cross beam of the mounting platform,
the platform beam connecting beam is arranged on the upper part of the platform pad beam and is crossed with the platform pad beam;
step four: a main beam of a cross beam of the platform is installed,
the platform beam main beam is arranged at the upper part of the platform connecting beam and is crossed with the platform connecting beam;
step five: a full hall frame supporting system is installed,
a full-hall supporting frame system is installed on the platform beam main beam, and a full-hall supporting frame vertical rod is supported on the platform beam main beam.
The template supporting platform and the secondary frame aligning method thereof have the advantages that: the turnover material consumption of a high and large formwork support system is reduced, the installation and dismantling workload of the support frame is reduced, the construction efficiency is improved, the construction cost is reduced, and the safety is improved.
Drawings
FIG. 1 is a schematic view of the method for mounting the platform column.
Fig. 2 is a schematic view of the method for mounting the platform bolster.
Fig. 3 is a schematic view of the mounting platform beam connecting beam in the method.
FIG. 4 is a schematic view of the method for mounting the platform beam main beam.
Fig. 5 is a schematic view of the method of installing the upper full-scale support system.
Detailed Description
The invention is further illustrated by the following specific examples.
As shown in fig. 1-5, a formwork support platform comprises a space system consisting of platform columns, platform pad beams, platform connecting beams and platform main beams, wherein the platform columns are vertical support members, the platform pad beams, the platform connecting beams and the platform main beams are horizontal support members, the platform pad beams are positioned at the tops of the platform columns, the platform connecting beams are positioned on the upper portions of the platform pad beams and are placed in a crossed mode with the platform pad beams, the platform main beams are positioned on the upper portions of the platform connecting beams and are placed in a crossed mode with the platform connecting beams, and a full-hall support frame support base is formed.
The method for carrying out secondary erection construction on the formwork supporting platform comprises the following steps,
the method comprises the following steps: the upright post of the platform is installed,
the platform upright post is positioned at the lower part of the formwork support system and is a space system formed by mutually connecting a group of vertical rods, cross rods and inclined rods;
step two: a pad beam of the platform is installed,
the top of the platform upright post is provided with a platform pad beam which is supported at the top of two (or more) upright posts;
step three: a connecting beam of a cross beam of the mounting platform,
the platform beam connecting beam is arranged on the upper part of the platform pad beam and is crossed with the platform pad beam;
step four: a main beam of a cross beam of the platform is installed,
the platform beam main beam is arranged at the upper part of the platform connecting beam and is crossed with the platform connecting beam;
step five: a full hall frame supporting system is installed,
a full-hall supporting frame system is installed on the platform beam main beam, and a full-hall supporting frame vertical rod is supported on the platform beam main beam.
The template supporting platform and the secondary frame aligning method thereof have the advantages that: the turnover material consumption of a high and large formwork support system is reduced, the installation and dismantling workload of the support frame is reduced, the construction efficiency is improved, the construction cost is reduced, and the safety is improved.

Claims (2)

1. A formwork support platform is characterized in that: the platform comprises a space system consisting of platform stand columns, platform pad beams, platform connecting beams and platform main beams, wherein the platform stand columns are vertical supporting pieces, the platform pad beams, the platform connecting beams and the platform main beams are horizontal supporting pieces, the platform pad beams are positioned at the tops of the platform stand columns, the platform connecting beams are positioned on the upper portions of the platform pad beams and are placed in a crossed mode with the platform pad beams, and the platform main beams are positioned on the upper portions of the platform connecting beams and are placed in a crossed mode with the platform connecting beams to form a full-hall supporting frame supporting base.
2. The method for secondary erection by using the formwork support platform of claim 1, which is characterized in that: comprises the steps of (a) preparing a mixture of a plurality of raw materials,
the method comprises the following steps: the upright post of the platform is installed,
the platform upright post is positioned at the lower part of the formwork support system and is a space system formed by mutually connecting a group of vertical rods, cross rods and inclined rods;
step two: a pad beam of the platform is installed,
the top of the platform upright post is provided with a platform pad beam which is supported at the top of two (or more) upright posts;
step three: a connecting beam of a cross beam of the mounting platform,
the platform beam connecting beam is arranged on the upper part of the platform pad beam and is crossed with the platform pad beam;
step four: a main beam of a cross beam of the platform is installed,
the platform beam main beam is arranged at the upper part of the platform connecting beam and is crossed with the platform connecting beam;
step five: a full hall frame supporting system is installed,
a full-hall supporting frame system is installed on the platform beam main beam, and a full-hall supporting frame vertical rod is supported on the platform beam main beam.
CN202110466740.4A 2021-04-28 2021-04-28 Formwork supporting platform and secondary erecting construction method Pending CN113235920A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110466740.4A CN113235920A (en) 2021-04-28 2021-04-28 Formwork supporting platform and secondary erecting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110466740.4A CN113235920A (en) 2021-04-28 2021-04-28 Formwork supporting platform and secondary erecting construction method

Publications (1)

Publication Number Publication Date
CN113235920A true CN113235920A (en) 2021-08-10

Family

ID=77129764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110466740.4A Pending CN113235920A (en) 2021-04-28 2021-04-28 Formwork supporting platform and secondary erecting construction method

Country Status (1)

Country Link
CN (1) CN113235920A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07317331A (en) * 1994-05-21 1995-12-05 Kajima Corp Beam type form supporting device, and assembling and disassembling method thereof
CN103669815A (en) * 2013-12-02 2014-03-26 中国一冶集团有限公司 Method for constructing hanging rope and pipe combined all-round scaffold construction platform and protective system
CN205421912U (en) * 2016-01-19 2016-08-03 中铁十二局集团有限公司 Dish knot formula supports support body double flute steel joist and plays secondary support body system
CN106150083A (en) * 2016-08-21 2016-11-23 中铁四局集团建筑工程有限公司 A kind of slip form platform of metro depot beam slab concrete structure construction
CN106522531A (en) * 2016-12-09 2017-03-22 上海建工二建集团有限公司 Ring lock scaffold opening portion bracket supporting system
CN212478555U (en) * 2020-05-30 2021-02-05 中铁十二局集团建筑安装工程有限公司 Girder transition layer girder lap joint structure of secondary elevated formwork system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07317331A (en) * 1994-05-21 1995-12-05 Kajima Corp Beam type form supporting device, and assembling and disassembling method thereof
CN103669815A (en) * 2013-12-02 2014-03-26 中国一冶集团有限公司 Method for constructing hanging rope and pipe combined all-round scaffold construction platform and protective system
CN205421912U (en) * 2016-01-19 2016-08-03 中铁十二局集团有限公司 Dish knot formula supports support body double flute steel joist and plays secondary support body system
CN106150083A (en) * 2016-08-21 2016-11-23 中铁四局集团建筑工程有限公司 A kind of slip form platform of metro depot beam slab concrete structure construction
CN106522531A (en) * 2016-12-09 2017-03-22 上海建工二建集团有限公司 Ring lock scaffold opening portion bracket supporting system
CN212478555U (en) * 2020-05-30 2021-02-05 中铁十二局集团建筑安装工程有限公司 Girder transition layer girder lap joint structure of secondary elevated formwork system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
余卫华等: "浅谈盘扣式支架体系在轨道车场的应用", 《城市建设理论研究(电子版)》 *
张荣双: "盘扣式钢管支架在轨道交通停车场项目中的应用――以南宁市轨道交通2号线东延工程新村停车场为例", 《中外建筑》 *

Similar Documents

Publication Publication Date Title
CN110439270B (en) Construction method of post-cast strip disassembly-free support system
CN108560719A (en) The support installation method of super large span double-layer Bidirectional hanging rope structure
CN210032599U (en) Beam-slab common supporting unit in beam-slab structure concrete cast-in-place supporting system
CN201991215U (en) Door frame type high-support formwork scaffold
CN102277980A (en) Device for integrally jacking roof of single-layer industrial factory building and construction method thereof
CN111877773A (en) Installation method of large-span annular pressure ring single-layer grid steel roof
CN212249231U (en) Adjustable beam slab co-supporting type cantilever tripod construction device
CN113622652A (en) Independent tower supporting unit of beam slab node in cast-in-place concrete supporting system
CN113235920A (en) Formwork supporting platform and secondary erecting construction method
CN209741895U (en) Connection structure of assembled elevator steel construction and base
CN106988520B (en) Construction method and support system for high-rise suspension structure
CN106351429A (en) Heavy support system and construction method thereof
CN217046842U (en) Reverse special-shaped mould of pouring of bridge prefabricated pier cap
CN202831628U (en) Combined type bailey frame load-bearing shelving for pouring large span concrete beam
CN216616848U (en) Beam plate post-cast strip supporting and mold sealing structure
CN217232907U (en) Folding fan-shaped classical landscape corridor frame
CN114233048A (en) Construction method for few-support erection of assembled laminated slab
CN210395107U (en) Temporary supporting device for large-span prestressed capping beam
CN217581140U (en) Latticed shell jacking device
CN112177323B (en) Cell body structure assembled support system
CN214574108U (en) Lattice column stabilizing structure for tower crane foundation for building construction
CN216007527U (en) Support beam for giant inclined truss structure of high-rise building
CN217253985U (en) Assembled steel case roof beam preparation bed-jig
CN215443102U (en) Template strutting arrangement is economized to assembled structure
CN216786886U (en) Rapid formwork structure for reinforcing bottom plate at bridge bearing

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210810