CN113217002A - Construction method for jacking side position of existing line crossing in frame culvert point - Google Patents

Construction method for jacking side position of existing line crossing in frame culvert point Download PDF

Info

Publication number
CN113217002A
CN113217002A CN202110381790.2A CN202110381790A CN113217002A CN 113217002 A CN113217002 A CN 113217002A CN 202110381790 A CN202110381790 A CN 202110381790A CN 113217002 A CN113217002 A CN 113217002A
Authority
CN
China
Prior art keywords
jacking
sliding plate
frame
construction
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110381790.2A
Other languages
Chinese (zh)
Other versions
CN113217002B (en
Inventor
高晨辉
殷浩喜
曹建鹏
倪伟
张永鹏
王浩洋
付跃伟
马骁
康耀奇
赵小丽
赵艺飞
赵凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Taiyuan Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Taiyuan Railway Construction Co Ltd of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Taiyuan Railway Construction Co Ltd of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN202110381790.2A priority Critical patent/CN113217002B/en
Publication of CN113217002A publication Critical patent/CN113217002A/en
Application granted granted Critical
Publication of CN113217002B publication Critical patent/CN113217002B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention relates to the technical field of railway construction, in particular to a construction method for jacking a side position crossing an existing line in a frame culvert point; the construction method comprises the following steps of (1) constructing a manual hole digging protection pile; (2) dismantling the plate girder and the bridge deck attachment; (3) changing the road; (4) constructing a steel sheet pile; (5) excavating a foundation pit; (6) dismantling the splayed wall and the baffle; (7) manufacturing a sliding plate, an anchor beam, a guide pier, a sliding layer and a back; (8) prefabricating a frame culvert; (9) jacking the frame culvert; (10) restoring the retaining wall; (11) backfilling a foundation pit; (12) auxiliary engineering and pavement restoration; the method of the invention has minimal impact on railway transportation. The method has the advantages of practicability, convenient operation and low construction cost. The safety risk is reduced, and the driving safety is ensured. The prefabricated frame culvert is far away from the existing line and has small interference to driving. The working efficiency is improved, the construction progress is accelerated, and the construction period is shortened. The prefabricated frame culvert does not need key point construction, and the construction progress is independently controllable. Meanwhile, the protective measures for the existing lines are correspondingly less, and the investment is saved.

Description

Construction method for jacking side position of existing line crossing in frame culvert point
Technical Field
The invention relates to the technical field of railway construction, in particular to a construction method for jacking a side position crossing an existing line in a frame culvert point.
Background
In the reconstruction construction of the existing station yard, the common construction method for lengthening the frame culvert of the existing railway comprises the following steps: and (5) sealing the existing line for cast-in-place construction. The method has long time for closing the existing railway, has larger influence on railway transportation, and is generally suitable for sections with smaller transportation volume or small influence on the railway transportation, so the construction method for lengthening the railway frame culvert brings great inconvenience to the railway transportation; there is a need for a safe, convenient and economical construction method that has little impact on railway transportation.
Disclosure of Invention
The invention overcomes the defects of the prior art and provides a construction method for jacking the side position of the existing line crossing in the frame culvert point.
In order to solve the technical problems, the technical scheme adopted by the invention is as follows: a construction method for jacking a side position of an existing line crossing inside a frame culvert point comprises the following steps of (1) manually digging a hole and protecting a pile for construction; (2) dismantling the plate girder and the bridge deck attachment; (3) changing the road; (4) constructing a steel sheet pile; (5) excavating a foundation pit; (6) dismantling the splayed wall and the baffle; (7) manufacturing a sliding plate, an anchor beam, a guide pier, a sliding layer and a back; (8) prefabricating a frame culvert; (9) jacking the frame culvert; (10) restoring the retaining wall; (11) backfilling a foundation pit; (12) auxiliary engineering and pavement restoration, characterized in that, the frame culvert jacking of (9) includes the following steps:
a. removing the line and the contact network cable, removing the line, opening the joint and removing the sleeper according to the jacking position;
b. chiseling the bottom plate of the U-shaped groove by adopting an excavator matched with a cannon hammer;
c. after the U-shaped groove is chiseled, leveling the original ground, and paving a sliding rail which is connected with the sliding rail at the top of the sliding plate;
d. the frame constructs the top and advances, chooses 500t hydraulic jack, top iron for use: setting top irons with the top ranges of 50cm, 1m, 2m and 4m, wherein when the top irons are placed, the direction of top iron top columns is consistent with the axis of a jacking force, and the supporting surfaces are required to be closely attached; in order to transmit the acting force of the jack to the back and the box body, a beam is respectively arranged between the back and the top iron and between the box body bottom plate and the jack; the beam is horizontally placed by an upper layer and a lower layer of two I-shaped steels with the thickness not less than I500 multiplied by 200mm, and the upper layer I-shaped steel and the lower layer I-shaped steel are welded together by reinforcing steel bars; in order to keep the stability of the jacking iron, a jacking column cross beam which is welded by two I-shaped steels not smaller than I500 x 200mm is arranged every 4-8 m and is arranged in a fixed section which is changed into a long jacking column;
e. restoring the line and contacting the network cable, loading the ballast in advance in the frame culvert, placing sleepers, connecting the line after jacking in place, and repairing the ballast and tamping drum.
Compared with the prior art, the invention has the following beneficial effects:
the method of the invention has minimal impact on railway transportation. The construction of chiseling the existing retaining wall and the splayed wall in the early stage can be carried out by utilizing the railway skylight for 3 hours every day. And the jacking process only needs to be stopped and wired for 24 hours.
The method has the advantages of practicability, convenient operation and low construction cost.
The safety risk is reduced, and the driving safety is ensured. The prefabricated frame culvert is far away from the existing line and has small interference to driving.
The working efficiency is improved, the construction progress is accelerated, the construction period is shortened, and the economic benefit and the social benefit are remarkable. The prefabricated frame culvert does not need key point construction, and the construction progress is independently controllable. Meanwhile, the protective measures for the existing lines are correspondingly less, and the investment is saved.
Drawings
Fig. 1 is a schematic view of the construction of a fender pile according to embodiment 1.
Fig. 2 is a schematic view showing the longitudinal arrangement of the guide piers according to example 1.
Fig. 3 is a schematic diagram of frame culvert prefabrication.
The figures are labeled as follows:
1-protective pile, 2-existing machine 2-line, 3-steel sheet pile, 4-guide pier, 5-anchor beam and 6-slide plate.
Detailed Description
The present invention is further illustrated by the following specific examples.
Example 1
In the embodiment, the elm secondary station energy expansion transformation project DL9K0+ 384.61-6 m frame culvert lengthening construction is taken as an example, and the construction method is adopted to carry out jacking construction crossing the existing line side position in the frame culvert point.
DL9K0+384.60 has the net height of 1-5m culvert 6m, the indoor machine in station runs 2 lines through the culvert, if cast-in-place construction is adopted, the machine needs to be stopped and run 2 lines for 60 days, and the influence on transportation is large. And combining field practice, the rear side of the frame culvert needs to be jacked in the north side of the machine walking 2 lines.
The culvert lengthening adopts a 1-6m frame culvert, the jacking length is 11m, the jacking distance is 8.5m, the jacking section adopts a hole digging pile and a steel sheet pile to protect the existing roadbed, the contact network cable is changed in point, the circuit is dismantled, a U-shaped groove concrete bottom plate is chiseled, and the circuit and the contact network cable are recovered after jacking in place.
The principle is as follows: and prefabricating the lateral position of the frame culvert, and jacking in the point. Firstly, carrying out manual hole digging protective pile construction on the west side of a foundation pit, dismantling an enclosure of a compartment of the elm-woven line, changing a temporary road, and driving a steel plate protective pile on the north side of the foundation pit. Chiseling out the concrete pavement of the existing 1-13m plate girder and the concrete pavement of the roads on the two sides, and dismantling the auxiliary structures such as the anti-throwing net on the plate girder. And (3) hoisting the existing 1-13m plate beam by using a 200t crane through a III-level blocking point. And then, carrying out foundation pit excavation operation, arranging a soil discharging channel on the east side of the foundation pit, and chiseling the existing splayed wall and the retaining walls on the two sides of the existing mechanical walking 2 line by utilizing a III-level blocking point. And secondly, constructing a sliding plate, a guide pier, an anchor beam and the like. After the frame culvert is prefabricated, the machine-walking 2 lines are dismantled by using a III-level locking point (24 h), the frame culvert is jacked in place, and the lines are recovered. And then carrying out foundation pit backfilling, retaining wall restoration, 1-13m plate beams, existing concrete roads and other constructions.
The method specifically comprises the following steps:
1. construction of manual hole digging protective pile
As shown in figure 1, the jacking section is provided with a manual hole digging protective pile on the left side of the machine walking 2 line and on the west side of the foundation pit. The diameter of the manual hole digging pile is 1.25m, the length of the pile is 16m, and the distance between the pile and the manual hole digging pile is 2 m. The hole is formed by adopting a mode of manually mixing a concrete retaining wall for pouring and manually rolling the soil. And binding the main body steel bars of the hole digging pile in sections in the hole, and pouring concrete by using a ground pump. And calculating according to the designed geological data, wherein the underground water level is positioned at the position 6m below the rail surface, and the water pump is adopted to pump water below 12.81m to perform precipitation in the hole. Adopting a mode of separating pile excavation to excavate.
2. Demolish board roof beam and bridge floor and attach
a. And (3) manually dismantling the existing heat supply pipeline and pipeline support at the 1-13m plate beam by using the adjacent class C plan. Chiseling 1-13m plate beam concrete pavement and concrete surfaces of roads on two sides of the concrete pavement by using a small hammer machine, and removing auxiliary structures such as anti-throwing nets on the plate beams.
b. And stopping the machine for 2 lines and 180 minutes by using a III-grade sealing point seal, and removing 1-13m of the existing plate beam in the point. The single plate beam is 25t, the total number of the single plate beam is two, and the single plate beam is hoisted twice by a 200t crane.
3. Road changing
A1-6 m frame culvert foundation pit is positioned on the south side of the elm-woven line workshop, and an existing road needs to be changed before excavation of the foundation pit. The newly-built sidewalk is located on the outer side of the elm-woven line garage, and a 43m temporary manshaped sidewalk needs to be built by removing the existing enclosing wall. The width of the temporary shifted road is 2.5-4m, the front and the back of the temporary shifted road are connected with the existing road, and the road surface is paved with 0.2m thick gravels. The outer side of the access road is provided with a color steel plate for isolation. The road junction is provided with an anti-collision sand pier, and the color steel plate is provided with a reflective strip, a warning mark and an indicating mark.
4. Construction of steel sheet pile
The north side of the foundation pit is protected by Larsen steel sheet piles, and the length of each steel sheet pile is 15 m. And (5) adopting a vibration pile pressing method for construction.
Secondly, when the pile driver presses the pile, the center line of the pile cap and the pile body must be superposed.
And secondly, checking the perpendicularity of the pile body at any time in the pile pressing process, finding that the pile body suddenly inclines and equipment reaches rated pressure for 20min in the processes of displacement, inclination and pressing-in of the pile body in the initial pressing process, and pulling out the pile body to be newly driven when the pile body still cannot sink.
Before vibrating the pile, the pile clamp of the vibration hammer should clamp the upper end of the steel pile, and the vibration hammer and the center of gravity of the steel pile are on the same straight line.
Fourthly, the steel pile is clamped by a vibration hammer to be hoisted, so that the steel sheet pile is vertically positioned or the locking opening of the steel sheet pile is inserted into the locking opening of the adjacent pile, and then the steel sheet pile is vibrated to sink after the pile is stable, the position is correct and vertical. And (3) stopping vibration to detect the verticality of the pile every time the steel pile sinks for about 1-2 m, finding out deviation and correcting in time.
And fifthly, suddenly reducing the sinking speed of the steel pile in the pile sinking, stopping the pile sinking, upwards pulling the steel pile for 0.6-1.0 m, and then rapidly sinking again.
5. Excavation of foundation pit
The excavation depth of the foundation pit is 7.9m, the length of the foundation pit along the road is 14m, and the width of the foundation pit is 12 m. Excavating twice, wherein the first excavation depth is 3m, the second excavation depth is 4.9m, and an unearthed channel is reserved on the east side of the road.
6. Demolish splayed wall and barricade
And stopping the machine for 2 lines and 180 minutes by using a III-grade sealing point seal, and chiseling the existing retaining wall and splayed wall in the hammer point. The stone chips between the lines are cleaned by manual cooperation.
7. Manufacture of slide plate, anchor beam, guide pier and back
a. Sliding plate
The central line of the sliding plate is consistent with the design central line of the jacking frame, and the sliding plate is a 20cm gravel cushion and 30cmC25 concrete. The front end of the sliding plate is longer than the box body by 1m, the rear end of the sliding plate is connected with the back, the two sides of the sliding plate are respectively wider than the box body by 1m, and the bottom of the sliding plate is connected with the ground anchor beam.
In order to enable the top surface of the sliding plate to reach higher flatness, a square grid control elevation method is adopted for control, namely, before the sliding plate is poured, the horizontal control piles are lofted, and reinforcing steel bar heads with the diameter not smaller than 16mm are driven into the soil body of a working pit to form a 2.5m square grid.
b. Ground anchor beam
The ground anchor beam is C25 concrete, is positioned at the bottom of the sliding plate, has the same length as the sliding plate, 0.7m width, 0.5m depth and 3m spacing. The earth anchor beam soil body adopts manual excavation, and the concrete is poured together with the slide body.
c. Guide pier
In order to reduce the direction deviation of the frame after jacking and starting, guide piers are arranged on two sides of the sliding plate, the distance between the center of each guide pier and the wall side of the frame structure is 0.3m, the width of each guide pier is 0.4m, and the height of each guide pier is 0.5 m. The guide piers are arranged longitudinally as shown in fig. 2.
d. Sliding layer
After the bottom plate is constructed, the machine oil and the talcum powder with the thickness of 3mm are coated on the bottom plate, the surface is required to be smooth, and a layer of plastic cloth is laid before the frame-structured bottom plate is poured to reduce the jacking friction resistance.
e. Back
The back beam is 11m long, 1.5m wide and 2.5m high, and is of a C25 reinforced concrete structure. The back beam and the sliding plate are poured simultaneously. And (5) binding the steel bars according to the requirements of design drawings. The template adopts a wood pattern, and simultaneously adopts 5-5 cm square wood and a steel pipe for reinforcement. The concrete is fully vibrated and compacted by pumping.
8. Frame culvert prefabrication
The frame structure is prefabricated by utilizing an adjacent C-type plan, the total length of the frame structure is 11m, the inner diameter is 6m, the net height is 7.2m, the thickness of a bottom plate is 0.6m, the thicknesses of side walls and a top plate are 0.5m, a main body is cast by C35 concrete, and a bowl-buckled full-hall red scaffold is adopted. As shown in fig. 3.
9. Jacking frame culvert
And (4) sealing and stopping by using a III-grade sealing point, namely, organically walking 2 lines for 24 hours to carry out jacking construction, wherein the jacking distance is 8.5 m. A new isolating switch and a section insulator are installed on the overhead line system on the machine-walking 2 lines at this time for permanent use.
a. Removing circuits and contacting network cables
According to the jacking position, 50m of lines need to be removed, joints 3 are opened, 20 sleepers are removed, and contact network cables 420m are removed. 4 electric screw loosening machines, 2 gas welding acetylene sleeves, 30 crowbars, 1 220 digging machine, 7 ladder cars, 50 net workers and 80 linemen, and the time is 1 hour.
b. Chiseling on bottom plate of U-shaped groove
And carrying out U-shaped groove cultivation on the seeds with the length of 11.5m, the width of 2.8m and the depth of 1.2m, wherein the total length is 38.6 m. And (4) chiseling by matching an excavator with a cannon hammer, and transporting earth and stones to the south side of the frame structure. 2 hammers 220 and 2 excavators 220, and the time is 10 hours.
c. Laying slide rail
And after the U-shaped groove is chiseled, leveling the original ground, paving 11P 50-8.5m slide rails in total, and connecting the slide rails with the top of the slide plate. The P50 splice splint 11 cover, lineman 50, for 2 hours.
d. Frame structure jacking
And (4) jacking the steel pipe by 8.5m, selecting 500t of oil jack, jacking 4 pickaxes for standby 1 jack, and jacking 0.6m per hour for each pickaxe. 15 people in common work, and the time is 7 hours.
Carrying out iron jacking: and setting top irons with the top ranges of 50cm, 1m, 2m and 4 m. When the supporting device is placed, the direction of the iron jacking column is consistent with the jacking force axis, and the supporting surface is required to be closely attached. When the jacking is detected to have deformation (such as arching, bending and the like), the jacking is immediately stopped for adjustment. The steel plate is flat, straight and is vertical to the cross iron or the cross beam.
Distributing the cross beams: in order to transmit the acting force of the jack to the back and the box body, a beam is respectively arranged between the back and the top iron and between the box body bottom plate and the jack. The beam is horizontally arranged by an upper layer and a lower layer of two I-shaped steels with the thickness not less than I500 multiplied by 200mm, and the upper layer I-shaped steel and the lower layer I-shaped steel are welded together by reinforcing steel bars.
A top column beam: in order to keep the stability of the jacking iron, a jacking column cross beam which is welded by two I-shaped steels not smaller than I500 x 200mm is arranged every 4-8 m and is arranged in a fixed section which is changed into a long jacking column.
e. Recovery circuit and contact network cable
And (4) ballasting in advance in the frame culvert, placing sleepers, jacking in place, connecting the circuits, and supplementing the ballast and tamping drums. The contact net utilizes the power failure skylight point of the elm secondary junction for 180 minutes, and 400 meters of 083# -094# conductor bearing wires are replaced. 2 rail hauler, 2 flexible axle tamping tools, 20m railway ballast, 20 sets of line accessories, 80 linemen, 50 net workers, 6 ladder cars, 3 hours of time.
Power outage range: the ascending and descending lines between the ulmus pumila (without) and the prunus humilis (without) comprise the first, second, third, fourth and northelm turn-back sections; and the power supply arm of the overhead contact net of the cargo connection ascending line and the overhead contact net of the cargo connection descending line between the middle vessel logistics park (without), the elm secondary field (with) and the elm secondary field (with) is powered off.
f. Opening of inspection
And checking the line elevation, the correction loss and the connection condition of the fastening fittings, cleaning the road material, and reaching the opening condition, wherein the time is 1 hour and 20 workers are required.
The railway frame culvert is lengthened by adopting a lateral jacking mode. The construction method has high construction feasibility, minimizes the influence on the operation of the existing line, reduces the safety risk, improves the working efficiency, accelerates the construction progress, shortens the construction period and has obvious economic benefit and social benefit.

Claims (3)

1. A construction method for jacking a side position of an existing line crossing inside a frame culvert point comprises the following steps of (1) manually digging a hole and protecting a pile for construction; (2) dismantling the plate girder and the bridge deck attachment; (3) changing the road; (4) constructing a steel sheet pile; (5) excavating a foundation pit; (6) dismantling the splayed wall and the baffle; (7) manufacturing a sliding plate, an anchor beam, a guide pier, a sliding layer and a back; (8) prefabricating a frame culvert; (9) jacking the frame culvert; (10) restoring the retaining wall; (11) backfilling a foundation pit; (12) auxiliary engineering and pavement restoration, characterized in that, the frame culvert jacking of (9) includes the following steps:
a. removing the line and the contact network cable, removing the line, opening the joint and removing the sleeper according to the jacking position;
b. chiseling the bottom plate of the U-shaped groove by adopting an excavator matched with a cannon hammer;
c. after the U-shaped groove is chiseled, leveling the original ground, and paving a sliding rail which is connected with the sliding rail at the top of the sliding plate;
d. the frame constructs the top and advances, chooses 500t hydraulic jack, top iron for use: setting top irons with the top ranges of 50cm, 1m, 2m and 4m, wherein when the top irons are placed, the direction of top iron top columns is consistent with the axis of a jacking force, and the supporting surfaces are required to be closely attached; in order to transmit the acting force of the jack to the back and the box body, a beam is respectively arranged between the back and the top iron and between the box body bottom plate and the jack; the beam is horizontally placed by an upper layer and a lower layer of two I-shaped steels with the thickness not less than I500 multiplied by 200mm, and the upper layer I-shaped steel and the lower layer I-shaped steel are welded together by reinforcing steel bars; in order to keep the stability of the jacking iron, a jacking column cross beam which is welded by two I-shaped steels not smaller than I500 x 200mm is arranged every 4-8 m and is arranged in a fixed section which is changed into a long jacking column;
e. restoring the line and contacting the network cable, loading the ballast in advance in the frame culvert, placing sleepers, connecting the line after jacking in place, and repairing the ballast and tamping drum.
2. The construction method for jacking in the cross existing line side position in the frame culvert point according to claim 1, wherein in the step (8), the prefabricated body of the frame culvert is cast by C35 concrete, and a bowl-buckled full-hall red scaffold is adopted.
3. The construction method for jacking across the existing line side in the frame culvert point according to claim 1, wherein the step (7) of constructing the slide plate, the anchor beam, the guide pier, the sliding layer and the back specifically comprises the following steps:
a. the center line of the sliding plate is consistent with the design center line of the jacking frame, and the sliding plate is a 20cm gravel cushion and 30cmC25 concrete; the front end of the sliding plate is longer than the box body by 1m, the rear end of the sliding plate is connected with the back, the two sides of the sliding plate are respectively wider than the box body by 1m, and the bottom of the sliding plate is connected with the ground anchor beam; in order to enable the top surface of the sliding plate to reach higher flatness, a square grid control elevation method is adopted for control, namely, before the sliding plate is poured, a horizontal control pile is lofted, and a reinforcing steel bar head with the diameter not smaller than 16mm of the horizontal control pile is driven into the soil body of a working pit to form a 2.5m square grid;
b. the ground anchor beam is C25 concrete and is positioned at the bottom of the sliding plate, the length of the ground anchor beam is consistent with that of the sliding plate, the width of the ground anchor beam is 0.7m, the depth of the ground anchor beam is 0.5m, and the distance of the ground anchor beam is 3 m;
the earth anchor beam soil body adopts manual excavation, and concrete and the sliding plate body are poured together;
c. the guide piers are arranged on two sides of the sliding plate in order to reduce the direction deviation of the frame after jacking and starting, the center of each guide pier is 0.3m away from the frame structure wall, the width of each guide pier is 0.4m, and the height of each guide pier is 0.5 m;
d. after the construction of the bottom plate of the sliding layer, coating machine oil and talcum powder with the thickness of 3mm on the bottom plate, and paving a layer of plastic cloth before pouring the frame bottom plate to reduce the jacking friction;
e. the back is of a C25 reinforced concrete structure, the back beam and the sliding plate are simultaneously poured, steel bars are bound according to the requirements of design drawings, a template adopts a wood pattern, and simultaneously, 5 × 5cm square timbers and steel pipes are adopted for reinforcement; the concrete is fully vibrated and compacted by pumping.
CN202110381790.2A 2021-04-09 2021-04-09 Construction method for jacking side positions crossing existing lines in frame culvert points Active CN113217002B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110381790.2A CN113217002B (en) 2021-04-09 2021-04-09 Construction method for jacking side positions crossing existing lines in frame culvert points

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110381790.2A CN113217002B (en) 2021-04-09 2021-04-09 Construction method for jacking side positions crossing existing lines in frame culvert points

Publications (2)

Publication Number Publication Date
CN113217002A true CN113217002A (en) 2021-08-06
CN113217002B CN113217002B (en) 2024-02-13

Family

ID=77086727

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110381790.2A Active CN113217002B (en) 2021-04-09 2021-04-09 Construction method for jacking side positions crossing existing lines in frame culvert points

Country Status (1)

Country Link
CN (1) CN113217002B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101787679A (en) * 2010-02-10 2010-07-28 中铁六局集团有限公司 T-shaped beam longitudinal shift construction method
CN103362073A (en) * 2013-08-08 2013-10-23 中铁六局集团天津铁路建设有限公司 Method for pushing frame bridge
CN103485288A (en) * 2013-10-11 2014-01-01 中铁一局集团有限公司 Construction process of double-layer jacking culvert penetrating through existing railway lines
CN104612056A (en) * 2014-12-10 2015-05-13 中铁第四勘察设计院集团有限公司 Quick pushing and transverse moving method for integral frame bridge
CN105464008A (en) * 2016-01-12 2016-04-06 中铁第五勘察设计院集团有限公司 Large longitudinal beam system line reinforcement construction device and method
CN106337373A (en) * 2015-07-13 2017-01-18 中铁第六勘察设计院集团有限公司 Construction method for oblique through existing line overhead jacking box culvert and pipe joint structure applying the same
CN107558375A (en) * 2017-09-12 2018-01-09 中铁六局集团有限公司 The construction method that contact net bar is torn down and reconstructed during a kind of Framed underpass bridge
CN108374341A (en) * 2018-02-13 2018-08-07 新疆铁道勘察设计院有限公司 The U-type groove of railway box-shaped bridge combines basil construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101787679A (en) * 2010-02-10 2010-07-28 中铁六局集团有限公司 T-shaped beam longitudinal shift construction method
CN103362073A (en) * 2013-08-08 2013-10-23 中铁六局集团天津铁路建设有限公司 Method for pushing frame bridge
CN103485288A (en) * 2013-10-11 2014-01-01 中铁一局集团有限公司 Construction process of double-layer jacking culvert penetrating through existing railway lines
CN104612056A (en) * 2014-12-10 2015-05-13 中铁第四勘察设计院集团有限公司 Quick pushing and transverse moving method for integral frame bridge
CN106337373A (en) * 2015-07-13 2017-01-18 中铁第六勘察设计院集团有限公司 Construction method for oblique through existing line overhead jacking box culvert and pipe joint structure applying the same
CN105464008A (en) * 2016-01-12 2016-04-06 中铁第五勘察设计院集团有限公司 Large longitudinal beam system line reinforcement construction device and method
CN107558375A (en) * 2017-09-12 2018-01-09 中铁六局集团有限公司 The construction method that contact net bar is torn down and reconstructed during a kind of Framed underpass bridge
CN108374341A (en) * 2018-02-13 2018-08-07 新疆铁道勘察设计院有限公司 The U-type groove of railway box-shaped bridge combines basil construction method

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
曹建鹏;: "浅谈既有线增二线架梁施工的施工控制", 山西建筑, no. 15 *
李向东;: "穿铁路既有线框架桥顶进施工技术", 工程质量, no. 03 *
李高峰;: "铁路组合式工便梁连续加固线路顶进施工技术", 价值工程, no. 09 *
程海维;: "铁路箱涵顶进施工技术探讨", 内蒙古公路与运输, no. 05 *
罗福亮: "铁路既有线下穿式顶进涵施工关键技术", 科技创新导报 *
韩勤生: "既有线框架顶进箱涵施工工艺", 西部探矿工程, no. 1 *

Also Published As

Publication number Publication date
CN113217002B (en) 2024-02-13

Similar Documents

Publication Publication Date Title
US9322137B2 (en) Method for building structures, particularly passages under operating railways or the like
CN106641440B (en) A kind of transverse crossing railway line underground piping jacking construction method
CN101963061B (en) Construction method for underground box culvert of existing railway line
CN101736749B (en) Method for constructing soft soil foundation continuous caisson
CN111676819A (en) Jacking construction method for combined type temporary beam continuous reinforced line large-span frame structure bridge
CN111503368B (en) Pipe jacking construction method under sandy gravel geological condition
CN103711056A (en) Steel tool type temporary construction road and construction method thereof
CN113005918A (en) Method for constructing large-span frame bridge by high filling of multi-strand railway in protective railway station
CN110258600B (en) Vertical cofferdam construction method suitable for deepwater area
JP6144726B2 (en) Rehabilitation method for mountain road tunnels on expressway and suspension pier for rehabilitation method
CN109024670B (en) Underground comprehensive pipe gallery protection and reinforcement system penetrating through buried high-voltage cable and reinforcement method
KR20210078779A (en) Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same
KR100948059B1 (en) Constructing method for widening road using steel casing retaining wall
CN114411721B (en) Replacement construction method for steel trestle bridge forming and then anchoring steel pipe pile
KR20210055980A (en) Underground roadway by top-down method using steel continuous wall in the earth without traffic control and temporary road and method for constructing the same
CN113217002B (en) Construction method for jacking side positions crossing existing lines in frame culvert points
CN115506382A (en) Construction method for pile plate wall of island building platform
CN112983493B (en) Reinforcing structure for shield to closely penetrate large-section bridge and culvert downwards and construction method
CN212270945U (en) Existing railway line foundation pit supporting system
CN113338340A (en) Reverse construction method for vertical shaft ensuring normal use of existing pipeline
RU2453650C1 (en) Complex for construction of motor road on piles
KR20210055981A (en) Underground roadway using steel continuous wall in the earth with minimum traffic control in constructing by top-down method and method for constructing the same
Konstantis et al. Box jacking/pushing method for tunnel construction in rock: Doha Metro, Gold Line Project
CN115929399B (en) Construction protection device and construction protection method for electric power tunnel
CN213038426U (en) Extension slide plate for stable and rapid jacking construction of box culvert under large excavation surface

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant