CN113202480B - Combined bearing double-layer well wall and construction method thereof - Google Patents

Combined bearing double-layer well wall and construction method thereof Download PDF

Info

Publication number
CN113202480B
CN113202480B CN202110668284.1A CN202110668284A CN113202480B CN 113202480 B CN113202480 B CN 113202480B CN 202110668284 A CN202110668284 A CN 202110668284A CN 113202480 B CN113202480 B CN 113202480B
Authority
CN
China
Prior art keywords
well wall
wall
grouting
layer
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110668284.1A
Other languages
Chinese (zh)
Other versions
CN113202480A (en
Inventor
杨维好
杨志江
任彦龙
张驰
张涛
韩涛
黄家会
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN202110668284.1A priority Critical patent/CN113202480B/en
Publication of CN113202480A publication Critical patent/CN113202480A/en
Application granted granted Critical
Publication of CN113202480B publication Critical patent/CN113202480B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/06Lining shafts; Linings therefor with iron or steel
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/11Lining shafts; Linings therefor with combinations of different materials, e.g. wood, metal, concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mechanical Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Wood Science & Technology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a combined bearing double-layer well wall and a construction method thereof, belonging to the technical field of double-layer well wall construction, wherein the combined bearing double-layer well wall comprises an inner layer well wall and an outer layer well wall, the outer layer well wall is formed by segmented tunneling and pouring, and construction joints exist among all sections of the outer layer well wall; the inner well wall is formed by continuous casting; a gap is arranged between the inner well wall and the outer well wall, and a micro-expansion grouting material is injected into the gap to form a micro-expansion interlayer. The invention adopts micro-expansion slurry material to carry out grouting between the inner and outer layer walls, and the solidified slurry can tightly adhere the inner layer well wall and the outer layer well wall and densely fill water seepage channels in the outer layer well wall and the stratum close to the well wall.

Description

Combined bearing double-layer well wall and construction method thereof
Technical Field
The invention belongs to the technical field of double-layer well wall construction, and particularly relates to a combined bearing double-layer well wall and a construction method thereof.
Background
The shaft in the water-rich stratum in China is usually excavated by an artificial freezing method, and a double-layer reinforced concrete well wall (referred to as a double-layer well wall for short) or a double-layer reinforced concrete composite well wall with a plastic interlayer (referred to as a double-layer composite well wall for short) is mostly adopted for supporting. The shaft is a life line connecting the ground and the underground, so that the shaft wall serving as a supporting structure must have strong bearing capacity (bearing the pressure of the stratum and the underground water) and high water sealing performance (the water inflow of the shaft can meet the use requirement) within the service life.
The double-layer well wall consists of an inner layer well wall and an outer layer well wall, the wall building material is concrete, and reinforcing steel bars are arranged if necessary. The main functions of the outer well wall are to resist the formation pressure and the construction load in the construction period and resist the formation pressure together with the inner well wall in the service period. Because of the existence of more construction joints and construction cracks which are difficult to completely avoid, the water sealing function of the outer well wall is limited. The main function of the inner well wall is to resist the pressure of the groundwater during the service life and to resist the pressure of the formation together with the outer well wall.
In fact, as the freezing well wall needs to undergo rapid and large temperature change, under the constraint action of the outer well wall, complex temperature stress is generated inside the inner well wall, and the cracking is common and serious. A large number of temperature cracks obviously reduce the water sealing performance of the inner well wall, and the pressure between the walls is difficult to increase during grouting, so that the filling range of the grout is limited. In addition, due to shrinkage during the process of cement paste calculus, the grout is difficult to densely fill the water seepage channel. Therefore, the expected effects of improving the overall water sealing performance of the well wall and reducing the hydraulic load of the inner well wall are difficult to achieve remarkably in the grouting between the walls. Therefore, the value of the hydraulic load of the inner well wall is close to or even equal to the hydrostatic pressure of the calculated depth during design, and as a result, the design thickness and the concrete strength grade of the inner well wall increase nonlinearly along with the depth of the well, so that the cost of the well is increased rapidly. On the other hand, in order to make the water inflow of the shaft meet the use requirements, a production unit has to repeatedly perform grouting between the inner wall and the outer wall, even between the outer wall and the surrounding rock, within the service life of the shaft for many times. Repeated grouting not only affects normal production and increases production cost, but also has poor effect and high safety risk due to the operation of propping against high-pressure underground water.
The double-layer composite well wall is an improvement on the double-layer well wall. On the basis of the double-layer well wall, a plastic thin plate (generally 1-2 layers, each layer is 1.5mm thick) is additionally arranged between the inner layer well wall and the outer layer well wall of the double-layer composite well wall; for a shaft in the soil layer, a layer of foam board (generally 50-75 mm thick) is additionally arranged between the outer well wall and the soil layer. The foam board plays the effect of heat preservation slow compression, is favorable to outer wall of a well concrete intensity to increase. The plastic plate can reduce the constraint effect of the outer well wall on the inner well wall, and reduce the temperature stress in the inner well wall when the temperature changes, thereby greatly relieving the cracking problem of the inner well wall. The double-layer composite well wall improves the water sealing performance of the inner well wall, thereby greatly improving the overall water sealing performance of the well wall, and is a freezing well wall structure mainly adopted in China at present. However, the double-layer composite well wall cannot improve the filling effect of the grouting between walls on the water seepage channels of the well wall. On the contrary, the existence of the plastic plate obviously deteriorates the filling effect of the slurry on the gaps between the inner and outer well walls, so that the inner and outer walls are completely separated, and a smooth water storage space is formed between the walls. During the use of the shaft, underground water enters between the inner wall and the outer wall through the outer wall water seepage channel, so that the inner well wall can completely bear the water pressure between the walls. In the long term, the pressure of water between the inner wall and the outer wall is consistent with the underground water pressure of the stratum, so that the value of the hydraulic load of the inner well wall is equal to the hydrostatic pressure of the calculated depth in the design process. So, compare in double-deck wall of a well under the same condition, the inlayer wall of a well design thickness of double-deck compound wall of a well is the same or even bigger.
Therefore, for a frozen shaft in a deep water-rich stratum, a double-layer shaft wall and a construction method thereof which can reduce the thickness of the shaft wall on the premise of ensuring the water sealing performance of the shaft wall are urgently needed.
Disclosure of Invention
The invention aims to provide a double-layer well wall capable of reducing the thickness of the well wall on the premise of ensuring the water sealing performance of the well wall and a construction method thereof, and the technical scheme is as follows:
a jointly-loaded double-layer well wall comprises an inner-layer well wall and an outer-layer well wall, wherein the outer-layer well wall is formed by segmented tunneling and pouring, and construction joints exist among all sections of the outer-layer well wall; the inner well wall is formed by continuous pouring; a gap is formed between the inner well wall and the outer well wall, and a micro-expansion grouting material is injected into the gap to form a micro-expansion interlayer.
Furthermore, the inner well wall is formed by continuously pouring low-hydration heat micro-expansion concrete meeting the design strength from bottom to top, and the outer well wall is formed by tunneling and pouring in sections from top to bottom.
Furthermore, a plurality of grouting pipes are arranged on the inner well wall and used for injecting micro-expansion grouting materials into a gap between the inner well wall and the outer well wall.
Furthermore, the grouting pipes are in multiple groups, and the multiple groups of grouting pipes are vertically arranged on the inner well wall at intervals; the number of each group of grouting pipes is 4-12, and the grouting pipes are evenly distributed along the circumferential direction of the inner well wall.
Furthermore, the vertical spacing distance between each group of grouting pipes is less than or equal to 20m.
The construction method for manufacturing the combined bearing double-layer well wall is characterized by comprising the following steps:
s10, tunneling in sections from top to bottom and pouring an outer well wall;
s20, continuously pouring the micro-expansion inner-layer well wall from bottom to top; drilling in the casting process or after casting, and vertically arranging a plurality of groups of grouting pipes on the inner well wall at intervals for grouting between the inner well wall and the outer well wall in the later period;
and S30, after the inner well wall construction is finished, injecting a micro-expansion grouting material between the inner well wall and the outer well wall through a grouting pipe, wherein the final pressure of grouting in each hole reaches a preset pressure.
Further, before the construction in the step S10, a stratum thawing area, a stratum freezing area and a stratum non-freezing area are sequentially formed outside the preset position of the outer well wall by adopting an artificial freezing method.
Further, in the construction process of the step S20, before the frozen junction area of the stratum is partially and completely melted, grouting between the inner well wall and the outer well wall is completed; before the inner well wall is constructed, the freezing cold quantity is regulated and controlled according to the design.
Further, the temperature states of the stratum freezing area and the outer well wall are obtained through analysis of temperature measurement data of a freezing system or through testing of a pre-embedded part of the temperature sensors during construction of the outer well wall.
Has the beneficial effects that:
the invention provides a double-layer well wall capable of bearing by combining an inner layer wall and an outer layer wall and a construction method thereof, aiming at the two technical defects that the inner layer well wall of the existing double-layer well wall structure is seriously cracked, grouting slurry cannot compactly fill gaps between the inner layer wall and the outer layer wall and other water seepage channels, and the invention adopts low hydration heat micro-expansion concrete and freezing cold quantity regulation and control technology to control the cooling rate and amplitude of the inner layer well wall so as to reduce cracks of the inner layer well wall; and by optimizing the grouting time, grouting between the inner well wall and the outer well wall by adopting a micro-expansion slurry material, wherein the solidified slurry can tightly adhere the inner well wall and the outer well wall and densely fill water seepage channels in the outer well wall and the stratum close to the well wall. The invention reduces the cracks of the inner well wall, improves the self water sealing performance of the inner well wall on one hand, and can properly improve the grouting pressure during grouting between the two walls, thereby being beneficial to the grouting effect.
The invention can also compensate the curing shrinkage of grouting slurry and even control the proper expansion of the slurry after curing; one can more closely fill the construction joint, the construction crack of the outer well wall and the water guide channel in the near well wall stratum, thereby increasing the infiltration resistance of the underground water between the inner well wall and the outer well wall; and secondly, after the slurry is solidified, the inner well wall and the outer well wall can be tightly adhered, and a water storage space between the walls is eliminated, so that the underground water infiltrated from the outer well wall only acts on the outer wall in a pore water pressure mode.
Meanwhile, the water sealing performance of the inner well wall is improved, and the water seepage channels of the well wall and the near-wall stratum are fully filled, so that the overall water sealing performance of the well wall is superior to that of a double-layer well wall. The inner well wall and the outer well wall are closely adhered, the two well walls jointly resist the formation pressure and the groundwater pressure, and the inner well wall is only pressed by the pore water pressure, so the required thickness of the inner well wall is less than that of the double-layer well wall.
Because the inner well wall in the well wall of the invention is only acted by the pore water pressure, the hydraulic load is obviously smaller than the inner well wall in the double-layer well wall and the double-layer composite well wall in the prior art, and the inner and outer well walls can resist the formation pressure and the underground water pressure in a combined way. The well wall of the invention has convenient construction and good integral water sealing performance, the required well wall thickness is obviously less than that of the existing double-layer well wall and double-layer composite well wall under the same condition, and the construction cost of the well wall in the deep water-rich stratum can be obviously saved.
Drawings
FIG. 1 is a schematic structural view of the present invention;
wherein, 1, an inner well wall; 2. a micro-expanded interlayer; 3. an outer well wall; 4. constructing a joint; 5. a formation defrosting zone; 6. a formation freeze zone; 7. the unfrozen area of the formation.
Detailed Description
Example 1
A jointly-loaded double-layer well wall comprises an inner-layer well wall 1 and an outer-layer well wall 3, wherein the outer-layer well wall 3 is formed by tunneling and casting in sections, and construction joints 4 are arranged among the sections of the outer-layer well wall 3; the inner well wall 1 is formed by continuous casting; a gap is arranged between the inner well wall 1 and the outer well wall 3, and micro-expansion grouting materials are injected into the gap to form a micro-expansion interlayer 2.
In this embodiment, the inner wall 1 is formed by continuously casting low hydration heat micro expansion concrete satisfying the design strength from bottom to top.
Wherein, outer wall of a well 3 from top to bottom segmentation is pour, has construction joint 4 between the wall of a well of adjacent section. The inner well wall 1 is continuously poured from bottom to top, no construction joint 4 exists, and the integrity is good.
In this embodiment, a plurality of grouting pipes are preset on the inner well wall 1 for injecting micro-expansion grouting material into the gap between the inner well wall 1 and the outer well wall 3. Wherein, the inner well wall 1 is provided with a grouting pipe in a pre-buried or direct drilling mode.
The grouting pipes are arranged on the inner well wall 1 in a vertical and spaced manner; the number of each group of grouting pipes is 4-12, and the grouting pipes are evenly distributed along the circumferential direction of the inner well wall 1. The vertical spacing distance between each group of grouting pipes is less than or equal to 20m.
In this embodiment, after the inner well wall 1 and the outer well wall 3 are constructed, the gap between the inner well wall 1 and the outer well wall 3 is grouted by using a grouting pipe which is pre-buried or directly drilled and installed on the inner well wall 1, and the grout material is micro-expansion grout.
The main function of grouting is to fill the gap between the inner well wall 1 and the outer well wall 3, and also fill the water seepage channels possibly existing in the inner well wall 1, the outer well wall 3 and the stratum close to the well wall, so as to improve the overall water sealing performance of the well wall and reduce the hydraulic load applied to the inner well wall 1.
In the embodiment, the inner well wall 1 is cast by low hydration heat micro expansion concrete meeting the design strength requirement, the shrinkage (including drying shrinkage, carbonization shrinkage, self-shrinkage, temperature shrinkage and the like) of the inner well wall 1 is compensated, the cracking risk is reduced, and steel fibers can be doped to resist cracking if necessary. In the construction process, before the inner well wall 1 is constructed, the inward cold energy transmission of the freezing zone 6 of the stratum is controlled through freezing regulation (such as regulating the flow rate of brine, the temperature of the brine and the like). The combination of the low-hydration heat concrete and the freezing temperature control can control the cooling rate and amplitude of the inner well wall 1, and effectively reduce temperature cracks.
In this embodiment, the micro-expansion interlayer 2 is made of micro-expansion grouting material, and after the inner well wall 1 is completely constructed, a grouting pipe pre-buried or directly drilled and installed on the inner well wall 1 is used for injecting into a gap between the inner well wall 1 and the outer well wall 3 before the formation freezing zone 6 is partially and completely melted (partially permeable, commonly referred to as "windowing"). Because the inner well wall 1 has few cracks, the pressure can be increased during grouting (even the pressure can be slightly greater than the hydrostatic pressure of the grouting depth, and the actual bearing capacity of the inner well wall 1 is used as a control index, so that the grouting pressure can be designed). Inner wall of a well 1 is not leaked thick liquid, stratum frozen area 6 is not passed through thick liquid, therefore, the thick liquid can only flow or get into stratum thawing zone 5 of nearly wall of a well through outer wall of a well 3 construction joint 4 and construction crack along between inner wall of a well 1 and the outer wall of a well 3 (after inner wall of a well 1 is pour, because the heat of hydration releases, the heat is to outer wall and stratum direction transmission, can melt the partial frozen area of nearly wall of a well, form the thawing zone of certain extent), not only can form micro-expansion intermediate layer 2 between inner wall of a well 1 and the outer wall of a well 3, and outer wall of a well 3 and stratum thaw water channel of freezing zone 5 all obtain fully filled.
The size of the slurry is slightly expanded in the curing process, and the channel filled with the slurry cannot be degraded into a water seepage channel after the slurry is cured, so that the permeability of the outer well wall 3 and the formation thawing area 5 is obviously reduced. Under the expansion effect, a micro-expansion interlayer 2 formed by solidifying slurry between the inner well wall 1 and the outer well wall 3 can be tightly adhered to the inner well wall 1 and the outer well wall 3, so that the inner well wall 1 and the outer well wall 3 are jointly loaded.
Example 2
This embodiment is a construction method for manufacturing the jointly loaded double-layer well wall provided in embodiment 1, and includes the following steps:
and S10, tunneling in sections from top to bottom and pouring the outer well wall 3.
S20, continuously pouring the micro-expansion inner-layer well wall 1 from bottom to top; in the pouring process, a plurality of groups of grouting pipes are embedded in the inner well wall 1 at vertical intervals and are used for grouting between the inner well wall and the outer well wall in the later period.
In another embodiment, after the inner well wall 1 is poured, a plurality of groups of grouting pipes are installed in the inner well wall 1 at vertical intervals for grouting between the inner well wall and the outer well wall in the later period.
And S30, after the construction of the inner well wall 1 is completed, injecting a micro-expansion grouting material between the inner well wall 1 and the outer well wall 3 through a grouting pipe, wherein the final pressure of grouting in each hole is required to reach the preset pressure.
In this embodiment, before the construction in step S10, a formation frozen area 5, a formation frozen area 6 and a formation non-frozen area 7 should be sequentially formed outside the predetermined position of the outer well wall 3 by using an artificial freezing method.
Wherein, the stratum defrosting district 5 originally is the freezing district, pours the in-process at the outer wall, because the concrete hydration heat of outer wall of a well 3 releases, can melt a part of stratum near outer wall of a well 3 naturally, and this part of stratum is exactly the defrosting district. During this section-by-section downward construction of the outer wall 3, the upper freeze-thaw area may be frozen again into the freeze-thaw area. When the inner well wall 1 is constructed upwards, a thawing area can be formed again due to the release of the concrete hydration heat of the inner well wall 1.
In the construction process of the step S20, before the stratum freezing area 5 is partially and completely melted, grouting between the inner well wall 1 and the outer well wall 3 is completed; before the inner well wall 1 is constructed, the freezing cold quantity is regulated and controlled according to the design.
In this embodiment, the temperature states of the formation freezing zone 5 and the outer well wall 3 are obtained through analysis of temperature measurement data of a freezing system or through testing of embedded partial temperature sensors during construction of the outer well wall 3. The purpose of this part is mainly to control the outer wall of the well 3 and the near wall region to be in a normal temperature state, and grouting at this time is good in effect.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the technical scope of the present invention, so that any minor modifications, equivalent changes and modifications made to the above embodiment according to the technical spirit of the present invention are within the technical scope of the present invention.

Claims (5)

1. The construction method of the jointly-loaded double-layer well wall is characterized in that the jointly-loaded double-layer well wall comprises an inner layer well wall and an outer layer well wall, the outer layer well wall is formed by segmented tunneling and pouring, and construction joints exist among all the segments of the outer layer well wall; the inner well wall is formed by continuous pouring; a gap is formed between the inner well wall and the outer well wall, and a micro-expansion grouting material is injected into the gap to form a micro-expansion interlayer;
the inner well wall is formed by continuously pouring low-hydration heat micro-expansion concrete meeting the design strength from bottom to top, and the outer well wall is formed by tunneling and pouring in sections from top to bottom;
the construction method of the combined bearing double-layer well wall comprises the following steps:
s10, tunneling in sections from top to bottom and pouring an outer well wall;
s20, continuously pouring the micro-expansion inner well wall from bottom to top; drilling in the casting process or after casting, and vertically arranging a plurality of groups of grouting pipes on the inner well wall at intervals for grouting between the inner well wall and the outer well wall in the later period;
s30, after the inner well wall construction is finished, injecting a micro-expansion grouting material between the inner well wall and the outer well wall through a grouting pipe, wherein the final grouting pressure of each hole reaches a preset pressure;
before the construction in the step S10, a stratum thawing area, a stratum freezing area and a stratum non-freezing area are sequentially formed outside the preset position of the outer well wall by adopting an artificial freezing method;
in the construction process of the step S20, before the frozen junction area of the stratum is partially and completely melted, grouting between the inner well wall and the outer well wall is completed; before the inner well wall is constructed, the freezing cold quantity is regulated and controlled according to the design.
2. The method as claimed in claim 1, wherein a plurality of grouting pipes are provided on the inner wall for injecting a micro-expansive grouting material into the gap between the inner wall and the outer wall.
3. The construction method of the combined bearing double-layer well wall according to claim 2, wherein the grouting pipes are in a plurality of groups, and the groups of grouting pipes are vertically arranged on the inner well wall at intervals; the number of each group of grouting pipes is 4-12, and the grouting pipes are evenly distributed along the circumferential direction of the inner well wall.
4. The method of claim 3 wherein the vertical spacing between each set of grout pipes is no greater than 20m.
5. The construction method of the combined bearing double-layer well wall as claimed in claim 1, wherein the temperature states of the formation freezing zone and the outer well wall are obtained by analysis of temperature measurement data of a freezing system or by testing of embedded temperature sensors during construction of the outer well wall.
CN202110668284.1A 2021-06-16 2021-06-16 Combined bearing double-layer well wall and construction method thereof Active CN113202480B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110668284.1A CN113202480B (en) 2021-06-16 2021-06-16 Combined bearing double-layer well wall and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110668284.1A CN113202480B (en) 2021-06-16 2021-06-16 Combined bearing double-layer well wall and construction method thereof

Publications (2)

Publication Number Publication Date
CN113202480A CN113202480A (en) 2021-08-03
CN113202480B true CN113202480B (en) 2022-11-22

Family

ID=77024725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110668284.1A Active CN113202480B (en) 2021-06-16 2021-06-16 Combined bearing double-layer well wall and construction method thereof

Country Status (1)

Country Link
CN (1) CN113202480B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113668582B (en) * 2021-08-06 2023-05-26 中国联合工程有限公司 Grouting type double-wall pressure-bearing water-reducing pipe well device and construction method thereof

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1108435C (en) * 2000-04-11 2003-05-14 山东科技大学防水建材研究所 Anti-leakage compound wall of freeze well and its construction method
CN100545418C (en) * 2006-07-11 2009-09-30 盛天宝 Quick filling system between the composite shaft lining wall
CN206409234U (en) * 2017-01-14 2017-08-15 安徽省皖北煤电集团有限责任公司百善煤矿 A kind of pitshaft water-tight device
CN106837340B (en) * 2017-02-27 2018-10-23 中国矿业大学 The construction method of wall clearance grouting waterproof and reinforcing shaft wall structure under frost wall protection
CN107246267B (en) * 2017-07-25 2023-07-04 马钢(集团)控股有限公司 Vertical shaft wall structure in bad stratum, construction device and construction method
CN108775241B (en) * 2018-05-23 2020-03-10 北京中煤矿山工程有限公司 Filling process capable of enabling slurry to be uniformly distributed between inner wall and outer wall of freezing shaft
CN208816125U (en) * 2018-07-24 2019-05-03 北京隧盾市政建设有限公司 Shield inspection-pit maintenance backfill support construction
CN109577989B (en) * 2018-12-13 2020-08-25 山东大学 Novel deep mine shaft wall structure and construction method
CN109723087B (en) * 2018-12-26 2020-06-26 中国矿业大学 Double-layer well wall with steel members assembled on outer wall and construction process

Also Published As

Publication number Publication date
CN113202480A (en) 2021-08-03

Similar Documents

Publication Publication Date Title
CN108035335B (en) Method for constructing shaft type underground parking garage by freezing method
CN110965595B (en) Raft foundation building lifting reinforcement structure and method under corrosive geological environment
CN104806253A (en) Construction method for opening hole between rectangular pipe jacking channels
CN112663694B (en) Construction method for lifting and rectifying building on silt geology
CN113202480B (en) Combined bearing double-layer well wall and construction method thereof
CN112112654A (en) Isolation plate structure in upper soft and lower hard stratum and construction method thereof
CN110130324B (en) Steel pipe mini pile and construction method thereof
CN111379253A (en) Construction method for high-speed railway expanded cement slurry post-grouting discrete material pile composite foundation
CN111395263A (en) Leakage treatment method for roller compacted concrete dam body
CN112482415B (en) Consolidation grouting method for underground cavern under high external water pressure and flowing water condition
CA3217077C (en) Single-layer shaft lining with joint sealing structure and grouting system and its construction method
CN109208412A (en) Inter-city passenger rail fragment-free track slab Disease Treatment method and operating system
CN108914911A (en) A kind of stratum prestress advanced excavation stability control method
CN113356887B (en) Single-layer well wall with grouting water-stop connecting piece and construction method thereof
CN114776323B (en) Method for controlling double compensation of stratum and stress loss of shield tunnel
CN108930211A (en) The method for building heat preservation gutter using foam concrete
CN109537630B (en) Reinforcing method for synergistic effect of steel pipe shed and frozen soil
CN112431189A (en) Advanced freezing and reinforcing method for water-rich silt stratum for underground continuous wall construction
CN110029999B (en) Orifice closed hole internal circulation deep-seated part soluble rock grouting method
CN105019487A (en) Shallow raft foundation building correcting method
CN117779742B (en) Regional directional grouting system and method combining freezing and dewatering in water-rich region
CN216239901U (en) Roof leakage repairing structure
CN219220417U (en) Tunnel structure suitable for soft stratum condition
CN113404009B (en) Novel concrete panel structure of rock-fill dam and construction method
CN118110161A (en) Pressure irrigation prefabricated hardened soil pile and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant