CN113158291A - 一种桥墩在地震作用下摩擦桩桩长的计算方法 - Google Patents
一种桥墩在地震作用下摩擦桩桩长的计算方法 Download PDFInfo
- Publication number
- CN113158291A CN113158291A CN202110226742.6A CN202110226742A CN113158291A CN 113158291 A CN113158291 A CN 113158291A CN 202110226742 A CN202110226742 A CN 202110226742A CN 113158291 A CN113158291 A CN 113158291A
- Authority
- CN
- China
- Prior art keywords
- pile
- calculating
- foundation
- pier
- length
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F2119/00—Details relating to the type or aim of the analysis or the optimisation
- G06F2119/14—Force analysis or force optimisation, e.g. static or dynamic forces
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02T—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO TRANSPORTATION
- Y02T90/00—Enabling technologies or technologies with a potential or indirect contribution to GHG emissions mitigation
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- Computer Hardware Design (AREA)
- General Physics & Mathematics (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Foundations (AREA)
Abstract
本发明公开了一种桥墩在地震作用下摩擦桩桩长的计算方法,包括以下步骤:不考虑地震作用计算桥墩基顶外力;由基顶外力计算初始桩长;由桩长和桩底土反算基顶刚度;由基顶刚度计算桥墩地震力;计算考虑地震作用下的桥墩基顶外力;检算该桩长是否满足此基顶外力;如果满足要求则桩长计算完成,否则增加桩长并返回步骤C。本发明的针对地震作用下的桥墩桩基,认为桥墩地震力与基础刚度相互影响,桩长和桩底土的竖向地基系数对基础刚度起决定作用,为了节省迭代时间,首先,不考虑地震作用计算初始桩长,然后,按照一定的步长计算基础刚度,最后,根据基础刚度计算地震力。每次计算一遍后需要检算桩长是否满足承载力要求,如果满足则计算停止。
Description
技术领域
本发明属于交通运输业桥梁工程技术领域,具体涉及一种桥墩在地震作用下摩擦桩桩长的计算方法。
背景技术
在桥墩桩基计算中,地震力对桩基的影响较大,桥墩地震力与基础刚度成正比,而基础刚度不但与基础结构有关,还与基础所处的地质情况有关。设计者在基础计算时,往往只输入初始桩长,桩底因为事先不知道落在哪一层,往往保守设计,竖向地基系数按所有土层中最大值输入,而计算过程一般认为竖向地基系数对桩长影响较小,不会在试算桩长时对该值进行修改,因此计算的桩长往往偏大。
针对上述地震作用下桥墩桩基计算中存在的实际问题,亟需一种思路清晰操作简便的方法来解决桥墩桩长试算的计算问题。
发明内容
本发明为解决现有技术存在的问题而提出,其目的是提供一种桥墩在地震作用下摩擦桩桩长的计算方法。
本发明的技术方案是:一种桥墩在地震作用下摩擦桩桩长的计算方法,包括以下步骤:
A.不考虑地震作用计算桥墩基顶外力
计算桥墩基顶外力,先只考虑主力、附加力、特殊荷载,不考虑地震作用,计算各种作用后进行荷载组合;
B.由基顶外力计算初始桩长
采用m值法将基顶外力从群桩分配到单桩,然后根据单桩外力与摩阻力和端阻力平衡,求解初始桩长;
C.由桩长和桩底土反算基顶刚度
桩长确定后,桩周边土的区域已确定,就能够准确计算基顶刚度;
D.由基顶刚度计算桥墩地震力
基顶刚度越大,计算的桥墩地震力越大;
E.计算考虑地震作用下的桥墩基顶外力
考虑地震作用的桥墩基顶外力=步骤A计算的基顶外力+地震力;
F.检算该桩长是否满足此基顶外力
由此基顶外力计算群桩基底应力、单桩承载力,看是否满足要求;
G.如果满足要求则桩长计算完成,否则增加桩长并返回步骤C。
更进一步的,步骤A和步骤B能够快速得到初始计算桩长,节省迭代时间。
更进一步的,步骤C中基顶刚度随着桩长增加而增加,但是受桩底土的影响更大,单桩竖向刚度ρ1可以写为:
其中,l0+ξh为等效桩长,EA为桩身的受压弹性模量和横截面积,C0为桩底土的竖向地基系数,A0为桩底土的扩散面积。
更进一步的,步骤G中迭代计算桩长时,步长不能跳跃,可以按照0.5m一级慢慢往上涨。
更进一步的,每迭代计算桩长一次都需要重新确定桩底土的情况,修改桩底土的竖向地基系数C0。
本发明有益效果如下:
本发明的针对地震作用下的桥墩桩基,认为桥墩地震力与基础刚度相互影响,桩长和桩底土的竖向地基系数对基础刚度起决定作用,因此设计了一套迭代计算方法。为了节省迭代时间,首先,不考虑地震作用计算初始桩长,然后,按照一定的步长计算基础刚度,最后,根据基础刚度计算地震力。每次计算一遍后需要检算桩长是否满足承载力要求,如果满足则计算停止。
本发明能够针对交通运输领域如铁路、公路、市政、轻轨等不同类型的桥墩桩基计算,能够正确考虑地震作用的影响,该方法不仅能够快速获得初始桩长节省迭代时间,而且可以适时修改桩底土的竖向基底系数,从而能够减少计算桩长。
附图说明
图1是本发明的方法流程图;
图2是本发明桥墩桩基的示意图。
具体实施方式
以下,参照附图和实施例对本发明进行详细说明:
如图1~2所示,一种桥墩在地震作用下摩擦桩桩长的计算方法,包括以下步骤:
A.不考虑地震作用计算桥墩基顶外力
计算桥墩基顶外力时,先只考虑主力、附加力、特殊荷载,不考虑地震作用,计算各种作用后进行荷载组合;
B.由基顶外力计算初始桩长
采用m值法将基顶外力从群桩分配到单桩,然后根据单桩外力与摩阻力和端阻力平衡,求解初始桩长;
C.由桩长和桩底土反算基顶刚度
桩长确定后,桩周边土的区域已确定,就能够准确计算基顶刚度;
D.由基顶刚度计算桥墩地震力
基顶刚度越大,计算的桥墩地震力越大;
E.计算考虑地震作用下的桥墩基顶外力
考虑地震作用的桥墩基顶外力=步骤A计算的基顶外力+地震力;
F.检算该桩长是否满足此基顶外力
由此基顶外力计算群桩基底应力、单桩承载力,看是否满足要求;
G.如果满足则桩长计算完成,否则增加桩长回到步骤C。
桩长迭代计算非常费时间,步骤A和B能够快速得到初始计算桩长,节省迭代时间。
步骤C中基顶刚度随着桩长增加而增加,但是受桩底土的影响更大,单桩竖向刚度ρ1可以写为:
注:l0+ξh为等效桩长,EA为桩身的受压弹性模量和横截面积,C0为桩底土的竖向地基系数,A0为桩底土的扩散面积。
步骤D中基顶刚度可作为墩底的边界条件,采用单墩力学模型求解出桥墩的地震力。
步骤F中检算时,单桩承载力需要按单桩轴向拉力和单桩轴向压力分别考虑,此外,沉降控制时也应增加桩长。
步骤G中迭代计算桩长时,步长不能跳跃,可以按照0.5m一级慢慢往上涨,地震设防烈度较小时,一般在4步以内,地震设防烈度较大时,需要步数较多。
以上步骤中,每迭代一次都需要重新确定桩底土的情况,修改桩底土的竖向地基系数C0。
实施例一
12根1m的桥墩桩基础,设计地震加速度Ag=0.2g,该基础所处的地质情况见图2。
设计者在计算时,由于事先不知道桩底落在哪层土上,采用包络设计的思想,选择碎石土,地基基本承载力σ0=800kPa作为桩底土,这样计算的桥墩地震力较保守,结果计算桩长为41m,如附图2所示。
采用本发明的方法,计算该基础的初始桩长28m,桩底落在碎石土,σ0=800kPa上,经过迭代计算,最终桩长为35m,桩底落在碎石土,σ0=450kPa上。因为桩底土较以前小,计算的桥墩地震力小,所以桩长也减少了。
综合得到,经过本发明的优化,该基础的桩长优化了7m,如果在地震区使用,将会节省成本,降低工程造价。
本发明的针对地震作用下的桥墩桩基,认为桥墩地震力与基础刚度相互影响,桩长和桩底土的竖向地基系数对基础刚度起决定作用,因此设计了一套迭代计算方法。为了节省迭代时间,首先,不考虑地震作用计算初始桩长,然后,按照一定的步长计算基础刚度,最后,根据基础刚度计算地震力。每次计算一遍后需要检算桩长是否满足承载力要求,如果满足则计算停止。
本发明能够针对交通运输领域如铁路、公路、市政、轻轨等不同类型的桥墩桩基计算,能够正确考虑地震作用的影响,该方法不仅能够快速获得初始桩长节省迭代时间,而且可以适时修改桩底土的竖向基底系数,从而能够减少计算桩长。
Claims (5)
1.一种桥墩在地震作用下摩擦桩桩长的计算方法,其特征在于:包括以下步骤:
(A)不考虑地震作用计算桥墩基顶外力
计算桥墩基顶外力,先只考虑主力、附加力、特殊荷载,不考虑地震作用,计算各种作用后进行荷载组合;
(B)由基顶外力计算初始桩长
采用m值法将基顶外力从群桩分配到单桩,然后根据单桩外力与摩阻力和端阻力平衡,求解初始桩长;
(C)由桩长和桩底土反算基顶刚度
桩长确定后,桩周边土的区域已确定,就能够准确计算基顶刚度;
(D)由基顶刚度计算桥墩地震力
基顶刚度越大,计算的桥墩地震力越大;
(E)计算考虑地震作用下的桥墩基顶外力
考虑地震作用的桥墩基顶外力=步骤A计算的基顶外力+地震力;
(F)检算该桩长是否满足此基顶外力
由此基顶外力计算群桩基底应力、单桩承载力,看是否满足要求;
(G)如果满足要求则桩长计算完成,否则增加桩长并返回步骤(C)。
2.根据权利要求1所述的一种桥墩在地震作用下摩擦桩桩长的计算方法,其特征在于:步骤(A)和步骤(B)能够快速得到初始计算桩长,节省迭代时间。
4.根据权利要求1所述的一种桥墩在地震作用下摩擦桩桩长的计算方法,其特征在于:步骤(G)中迭代计算桩长时,步长不能跳跃,可以按照0.5m一级慢慢往上涨。
5.根据权利要求4所述的一种桥墩在地震作用下摩擦桩桩长的计算方法,其特征在于:每迭代计算桩长一次都需要重新确定桩底土的情况,修改桩底土的竖向地基系数C0。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110226742.6A CN113158291B (zh) | 2021-03-01 | 2021-03-01 | 一种桥墩在地震作用下摩擦桩桩长的计算方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110226742.6A CN113158291B (zh) | 2021-03-01 | 2021-03-01 | 一种桥墩在地震作用下摩擦桩桩长的计算方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113158291A true CN113158291A (zh) | 2021-07-23 |
CN113158291B CN113158291B (zh) | 2023-06-20 |
Family
ID=76883961
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110226742.6A Active CN113158291B (zh) | 2021-03-01 | 2021-03-01 | 一种桥墩在地震作用下摩擦桩桩长的计算方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113158291B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116383955A (zh) * | 2023-06-07 | 2023-07-04 | 中国建筑第六工程局有限公司 | 柱桩最短长度的计算方法 |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1042991A (zh) * | 1988-11-24 | 1990-06-13 | 浙江省建筑科学研究所 | 振动法和传递函数法结合的试桩技术 |
JP2003155751A (ja) * | 2001-11-22 | 2003-05-30 | Pacific Consultants Co Ltd | 長短混在杭長を用いる基礎工法 |
JP2007093353A (ja) * | 2005-09-28 | 2007-04-12 | Ohbayashi Corp | 鉛直地震応答の解析方法、設計方法及び構造物 |
CN103266634A (zh) * | 2013-01-09 | 2013-08-28 | 交通运输部公路科学研究所 | 一种超长钻孔灌注桩承载力确定方法 |
CN110397063A (zh) * | 2019-07-26 | 2019-11-01 | 长安大学 | 一种深厚软土地区桥梁桩基的合理桩长的计算方法 |
JP2020148013A (ja) * | 2019-03-14 | 2020-09-17 | 住友林業株式会社 | 杭状地盤補強設計装置及び費用見積装置 |
CN112100863A (zh) * | 2020-03-16 | 2020-12-18 | 上海大学 | 用于桩基工程的桩基负摩擦力解析解分析方法 |
CN112329104A (zh) * | 2020-11-05 | 2021-02-05 | 中国铁路设计集团有限公司 | 一种旋挖挤扩灌注桩的计算方法 |
-
2021
- 2021-03-01 CN CN202110226742.6A patent/CN113158291B/zh active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1042991A (zh) * | 1988-11-24 | 1990-06-13 | 浙江省建筑科学研究所 | 振动法和传递函数法结合的试桩技术 |
JP2003155751A (ja) * | 2001-11-22 | 2003-05-30 | Pacific Consultants Co Ltd | 長短混在杭長を用いる基礎工法 |
JP2007093353A (ja) * | 2005-09-28 | 2007-04-12 | Ohbayashi Corp | 鉛直地震応答の解析方法、設計方法及び構造物 |
CN103266634A (zh) * | 2013-01-09 | 2013-08-28 | 交通运输部公路科学研究所 | 一种超长钻孔灌注桩承载力确定方法 |
JP2020148013A (ja) * | 2019-03-14 | 2020-09-17 | 住友林業株式会社 | 杭状地盤補強設計装置及び費用見積装置 |
CN110397063A (zh) * | 2019-07-26 | 2019-11-01 | 长安大学 | 一种深厚软土地区桥梁桩基的合理桩长的计算方法 |
CN112100863A (zh) * | 2020-03-16 | 2020-12-18 | 上海大学 | 用于桩基工程的桩基负摩擦力解析解分析方法 |
CN112329104A (zh) * | 2020-11-05 | 2021-02-05 | 中国铁路设计集团有限公司 | 一种旋挖挤扩灌注桩的计算方法 |
Non-Patent Citations (8)
Title |
---|
Y. F. LEUNG 等: "Theoretical Study on Pile Length Optimization of Pile Groups and Piled Rafts", vol. 136, no. 2, pages 319 - 330 * |
周春霖 等: "桩土共同作用下桩长对结构抗震性能影响分析", 华北地震科学, vol. 27, no. 03, pages 7 - 11 * |
徐雁飞: "基于ANSYS地震作用下群桩动力响应的研究", no. 4, pages 038 - 481 * |
慢慢: "桩长计算", pages 1 - 2 * |
朱家桥: "摩擦型预制桩有效桩长对单桩承载力影响", 土工基础, vol. 15, no. 01, pages 42 - 45 * |
极客风: "土木极客:地震力到底是怎么算出来的?", pages 1 - 5 * |
行者MARK: "桩基桩长的计算", pages 1 - 4 * |
贾允祥: "郑焦城际跨济东高速公路特大桥(40+64+40)m连续梁桥墩设计", vol. 593, no. 8, pages 53 - 56 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116383955A (zh) * | 2023-06-07 | 2023-07-04 | 中国建筑第六工程局有限公司 | 柱桩最短长度的计算方法 |
CN116383955B (zh) * | 2023-06-07 | 2023-08-01 | 中国建筑第六工程局有限公司 | 柱桩最短长度的计算方法 |
Also Published As
Publication number | Publication date |
---|---|
CN113158291B (zh) | 2023-06-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201962688U (zh) | 地下连续墙码头桩基础结构 | |
CN103792593A (zh) | 一种基于库水位和位移监测的库岸边坡稳定性测定方法 | |
CN208604617U (zh) | 连续刚构桥基础隔震结构 | |
CN113158291A (zh) | 一种桥墩在地震作用下摩擦桩桩长的计算方法 | |
CN108446428A (zh) | 一种基于推覆理论的深基坑抗滑桩优化设计方法 | |
KR20150070843A (ko) | 수평지지력 증대용 마이크로파일 시공방법 | |
Jian et al. | Mechanics and deformation characteristics of an oversized inclined caisson foundation when being reused | |
CN209339011U (zh) | 一种铁路重力式桥墩防御性抗震加固装置 | |
CN206562613U (zh) | 一种微型桩锚杆支护结构 | |
Rogers et al. | Structural dynamics of offshore wind turbines subject to extreme wave loading | |
Ghalesari et al. | The settlement behavior of piled raft interaction in undrained soil | |
KR101640992B1 (ko) | 동적침하량 추정을 통한 파이프라인의 해저안정성 평가방법 | |
CN115048819A (zh) | 一种桩基础下拉力的预测方法、装置和电子设备 | |
CN104631467A (zh) | 基坑开挖工程的l型换撑板的支设方法 | |
Chen et al. | On fluid-filled mixture model for suction pile foundation analysis | |
CN109137931B (zh) | 一种适用于狭窄基坑的嵌固长度的计算方法 | |
Wang | Centrifuge modelling of seismic and lateral behaviors of suction bucket foundations for offshore wind turbines | |
CN108867720B (zh) | 一种路堤下桩间盐渍土溶陷量的测算方法 | |
CN206503156U (zh) | 一种光伏支架基础 | |
Krolis et al. | Determining the embedded pile length for large-diameter monopiles | |
CN207092161U (zh) | 一种基桩竖向抗压静载试验装置 | |
Wang et al. | Model experimental study on the load sharing of piled raft on foundation underpinning | |
CN109487801B (zh) | 一种超前动态边坡支护方法 | |
Wang et al. | Investigation of hybrid monopile foundations for offshore wind turbines under lateral cyclic loading in sand | |
Ahidashti et al. | Insight into the post-liquefaction behaviour of skirted foundations |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |