CN113137060B - Water tank hoisting device of water tower and construction method thereof - Google Patents

Water tank hoisting device of water tower and construction method thereof Download PDF

Info

Publication number
CN113137060B
CN113137060B CN202110444468.XA CN202110444468A CN113137060B CN 113137060 B CN113137060 B CN 113137060B CN 202110444468 A CN202110444468 A CN 202110444468A CN 113137060 B CN113137060 B CN 113137060B
Authority
CN
China
Prior art keywords
water tank
steel ring
lifting
hoisting
annular plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202110444468.XA
Other languages
Chinese (zh)
Other versions
CN113137060A (en
Inventor
叶志钢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Jingye Zhongcheng Construction Co ltd
Original Assignee
Wuhan Jingye Zhongcheng Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Jingye Zhongcheng Construction Co ltd filed Critical Wuhan Jingye Zhongcheng Construction Co ltd
Priority to CN202110444468.XA priority Critical patent/CN113137060B/en
Publication of CN113137060A publication Critical patent/CN113137060A/en
Application granted granted Critical
Publication of CN113137060B publication Critical patent/CN113137060B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/06Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for minimising or preventing longitudinal or transverse swinging of loads
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/18Control systems or devices
    • B66C13/20Control systems or devices for non-electric drives
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • E04G11/24Construction of lifting jacks or climbing rods for sliding forms
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16FSPRINGS; SHOCK-ABSORBERS; MEANS FOR DAMPING VIBRATION
    • F16F15/00Suppression of vibrations in systems; Means or arrangements for avoiding or reducing out-of-balance forces, e.g. due to motion
    • F16F15/02Suppression of vibrations of non-rotating, e.g. reciprocating systems; Suppression of vibrations of rotating systems by use of members not moving with the rotating systems
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A20/00Water conservation; Efficient water supply; Efficient water use

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Acoustics & Sound (AREA)
  • Aviation & Aerospace Engineering (AREA)
  • Automation & Control Theory (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a water tank hoisting device of a water tower, which comprises a support cylinder and a water tank, wherein a stabilizing device is arranged between the support cylinder and the water tank, the stabilizing device comprises an inner steel ring, an outer steel ring and an annular plate, the inner wall of the inner steel ring is tightly propped against the outer wall of the support cylinder, the outer steel ring is arranged on the water tank, the annular plate is arranged between the outer wall of the inner steel ring and the inner wall of the outer steel ring, and a steel strand is connected with the annular plate; the construction method of the water tower comprises the steps of installing a stabilizing device and manufacturing a lifting device; the invention has the beneficial effects that: the hoisting device is provided with the stabilizing device, the stabilizing device can effectively avoid the possibility that the water tank and the support cylinder are damaged due to collision in the hoisting process, so that the engineering quality is influenced and potential safety hazards are caused.

Description

Water tank hoisting device of water tower and construction method thereof
Technical Field
The invention belongs to the field of construction facilities and methods of water towers, and particularly relates to a water tank hoisting device of a water tower and a construction method thereof.
Background
The water tower is a high-rise structure for storing water and distributing water, used for keeping and regulating the water quantity and water pressure in a water supply pipe network, mainly comprising a water tank and a support or a bracket for connecting the water tank and the support. And (4) sliding and lifting the template after each layer of concrete is poured until the pouring of the structure is finished.
In the existing construction method, after the construction of a supporting cylinder slip form is finished, a slip form device is usually disassembled, then a water tank is cast on the outer side of the supporting cylinder, and after the water tank is cast and placed for a period of time, the water tank is hoisted along the supporting cylinder in a mode of arranging a pulley block hoisting device on the top of a straight-through way or a hoisting machine; in the existing water tank hoisting mode, shaking can be caused in the hoisting process, so that the water tank is rubbed and collided with the support cylinder in the hoisting process, the water tank and the support cylinder are easily damaged, the engineering quality is influenced, and potential safety hazards exist; meanwhile, if the sliding mode device needs to be disassembled when the hoisting devices such as the pulley hoisting set and the like are installed at the top of the supporting cylinder, the time for disassembling the sliding mode device and installing the hoisting device also needs to be set, and a large amount of construction period and waste of human resources can be caused.
Disclosure of Invention
In order to solve the problems in the prior art, the invention aims to provide a water tank hoisting device of a water tower and a construction method thereof.
The technical scheme adopted by the invention is as follows:
a water tank hoisting device of a water tower comprises a hoisting device and a stabilizing device, wherein the hoisting device and the stabilizing device are connected through a plurality of steel strands; the water tank is arranged at the top of the support cylinder through a hoisting device, the lifting device is arranged at the top of the support cylinder, and the stabilizing device is arranged between the support cylinder and the water tank;
the stabilizing device comprises an inner steel ring, an outer steel ring and an annular plate, the inner wall of the inner steel ring supports against the outer wall of the supporting cylinder, the outer steel ring is installed on the water tank, the annular plate is arranged between the outer wall of the inner steel ring and the inner wall of the outer steel ring, and the steel strand is connected with the annular plate.
Furthermore, a plurality of first vertical supports are further arranged between the outer wall of the inner steel ring and the inner wall of the outer steel ring and are uniformly distributed at the bottom of the annular plate.
Further, a filling layer is arranged between the inner steel ring and the outer wall of the support cylinder.
Furthermore, a force guide plate is arranged on the upper shell of the water tank, and one end of the force guide plate is arranged on the annular plate.
Furthermore, the shape of the force guide plate is matched with that of the upper shell, and a second vertical support is arranged between the annular plate and the force guide plate.
Furthermore, a plurality of first hoisting holes are formed in the annular plate, and the steel strand penetrates through the first hoisting holes.
Further, hoisting device includes lower steel ring, well steel ring and the last steel ring that from the bottom up set gradually, and lower steel ring is installed at a section of thick bamboo top, is provided with the bracket support down between steel ring and the well steel ring, is connected through hydraulic lifting system between well steel ring and the last steel ring.
Furthermore, a plurality of second hoisting holes are formed in the middle steel ring, a plurality of third hoisting holes are formed in the upper steel ring, the second hoisting holes and the third hoisting holes are coaxially arranged, and the steel strands sequentially penetrate through the third hoisting holes and the second hoisting holes.
Furthermore, a plurality of first hoisting holes and second hoisting holes are coaxially arranged, the steel strand sequentially passes through the third hoisting hole, the second hoisting hole and the first hoisting hole, and the lower end of the steel strand is connected to the annular plate.
Further, the construction method comprising the water tank hoisting device comprises the following steps:
a) The foundation construction comprises the following steps: measuring and positioning, leveling a field, measuring and lofting, excavating earth and stone, treating a substrate, testing a groove of a foundation and pouring a cushion layer;
b) Assembling a slip form device, wherein the slip form device comprises a template, a surrounding ring, a lifting frame, an operating platform, a supporting rod and a hydraulic lifting system;
c) Constructing the supporting cylinder main body, namely constructing the supporting cylinder main body through a slip form device to reach the design height;
d) On-spot prefabrication of water tank and maintenance and the installation of stabilising arrangement, the on-spot prefabrication of water tank includes with the maintenance: installing a template scaffold of the water tank, installing an outer template of the shell, binding reinforcing steel bars, sequentially combining inner concrete pouring, curing concrete, dismantling the template and decorating the outer surface of the water tank; after the water tank is formed, placing for a period of time, installing a stabilizing device on the inner side of the water tank, firstly installing an outer steel ring along the inner side wall of a middle ring beam of the water tank, then installing a force guide plate along an upper shell of the water tank, then installing an annular plate at a designed position, then installing a first vertical support and a second vertical support, and finally installing an inner steel ring;
e) The slipform device is demolishd and hoisting device preparation, and the slipform device is demolishd and is included: dismantling the template, the enclosure and the supporting rod; the manufacturing of the lifting device comprises the following steps: installing a lower steel ring on the operating platform, using an upper support and a lower support of the lifting frame as an upper steel ring and a middle steel ring respectively, installing a bracket support between the lower steel ring and the middle steel ring, and then enabling the steel strand to pass through a hydraulic lifting system;
f) Lifting and mounting the water tank, namely mounting the steel strand on the annular plate, lifting the water tank to a designed position through a lifting device, then pouring a ring joist, and mounting the lower shell of the water tank on the ring joist;
g) The engineering is ended, and the engineering end includes: the pipeline electrical installation and the test of water tank, the construction of dormer top cap, door and window construction, decoration construction and anticorrosive construction, hoisting device and securing device demolish, finish and deal with and check and accept.
The invention has the beneficial effects that:
the invention provides a water tank hoisting device of a water tower and a construction method of the water tower.
Drawings
FIG. 1 is a schematic view of the installation of the overall structure of the present invention;
FIG. 2 is a cross-sectional schematic view of the water tank and the stabilizing device;
FIG. 3 is a schematic view of a view of the stabilizer;
FIG. 4 is a schematic structural view of another view of the stabilization device;
in the figure: 1-supporting cylinder, 2-water tank, 21-lower shell, 22-middle ring beam, 23-upper shell, 3-lifting device, 31-lower steel ring, 32-bracket support, 33-middle steel ring, 34-hydraulic lifting system, 35-upper steel ring, 4-stabilizing device, 41-first vertical support, 42-annular plate, 421-first hoisting hole, 43-guide plate, 44-second vertical support, 45-inner steel ring, 46-outer steel ring, 5-steel strand and 6-filling layer.
Detailed Description
The first embodiment is as follows:
in this embodiment, as shown in fig. 1, a water tank hoisting device for a water tower comprises a supporting cylinder 1 and a water tank 2, wherein the supporting cylinder 1 is manufactured by a slip form construction method, the water tank 2 is installed at the top of the supporting cylinder 1 through the hoisting device, the hoisting device comprises a hoisting device 3 and a stabilizing device 4, the hoisting device 3 is connected with the stabilizing device 4 through a plurality of steel strands 5, the hoisting device 3 is installed at the top of the supporting cylinder 1, and the stabilizing device 4 is installed between the supporting cylinder 1 and the water tank 2;
in this embodiment, as shown in fig. 1 to 4, the stabilizing device 4 includes an inner steel ring 45, an outer steel ring 46 and an annular plate 42, the inner wall of the inner steel ring 45 abuts against the outer wall of the support tube 1, the outer steel ring 46 is mounted on the water tank 2, the annular plate 42 is disposed between the outer wall of the inner steel ring 45 and the inner wall of the outer steel ring 46, the plurality of steel strands 5 are connected to the annular plate 42, and the whole water tank 2 is lifted by driving the annular plate 42, specifically, the inner steel ring 45 surrounds the outer wall of the support tube 1, the diameter of the inner steel ring 45 is smaller than the upper and lower outlets of the tank body 2, the outer steel ring 46 is mounted on the inside of the water tank 2, the annular plate 42 connects the inner steel ring 45 and the outer steel ring 46 and plays a buffering role, when the lifting process shakes, the inner steel ring 45 first contacts with the support tube 1, the collision force is transmitted to the annular plate 42 through the inner steel ring 45, then the annular plate 42 is partially deformed to discharge the impact force, and the annular plate 42 is connected to the outer steel ring 46, the impact force is transmitted to the outer steel ring 46 to the water tank 2 synchronously, thereby dispersing the impact force at most of the original water tank, and preventing the support tube 1 from being damaged, and the damage of the water tank 2.
In this embodiment, the lifting device 3 is provided with 12 steel strands according to the design requirements and relevant standards of this embodiment.
The second embodiment:
in this embodiment, as shown in fig. 1 to 4, in the embodiment, a first vertical support 42 is added on the basis of the first embodiment, a plurality of first vertical supports 41 are further disposed between the outer wall of the inner steel ring 45 and the inner wall of the outer steel ring 46, the plurality of first vertical supports 41 are uniformly distributed at the bottom of the annular plate 42, the first vertical supports 42 are used for reinforcing the connection between the inner steel ring 45, the outer steel ring 46 and the annular plate 42, and meanwhile, when the steel strand 5 lifts the annular plate 42, the annular plate 42 is reinforced, so that the annular plate 42 is prevented from being damaged by pulling in the process of lifting the water tank 2 again due to insufficient rigidity.
Example three:
in this embodiment, as shown in fig. 1, in the second embodiment, a filling layer 6 is added, the filling layer 6 is disposed between the inner steel ring 45 and the branch tube 1, and the filling layer 6 is mounted on the inner steel ring 45 for further buffering the impact force and avoiding the direct contact friction between the inner steel ring 45 and the branch tube 1 to damage the surface of the branch tube 1 by contact, so that the filling layer 6 should be made of a material having lower strength, hardness and rigidity than the materials of the branch tube 1 and the inner steel ring 45 and having stronger wear resistance, specifically, the branch tube 1 is concrete, the inner steel ring 45 is Q235-B material, preferably, the filling layer 6 is made of polytetrafluoroethylene.
Example four:
in this embodiment, as shown in fig. 1 to 4, a force guide plate 43 is added to the second embodiment, the force guide plate 43 is mounted on the upper housing 23 of the water tank 2, one end of the force guide plate 43 is mounted on the annular plate 42, and the force guide plate 43 is used for further dispersing the collision force at multiple positions.
Example five:
in this embodiment, as shown in fig. 1 to 4, the present embodiment is a further supplement to the fourth embodiment, the shape of the force guide plate 43 is matched with the upper housing 23, the force guide plate 43 and the upper housing 23 should be attached as much as possible to prevent stress concentration, a second vertical support 44 is disposed between the annular plate 42 and the force guide plate 43, and the second vertical support 44 makes the force guide plate 43 mounted more stably.
Example six:
in this embodiment, as shown in fig. 1 to 4, which is a further supplement to the first embodiment, the annular plate 42 is provided with a plurality of first hoisting holes 421, the steel strand 5 passes through the first hoisting holes 421, the other end of the steel strand 5 should be connected to a baffle (not shown in the figure) that cannot pass through the hoisting holes 421, and specifically, the annular plate 42 is provided with 12 first hoisting holes 421.
Example seven:
in this embodiment, as shown in fig. 1, the present embodiment is a further supplement to the first embodiment, the lifting device 3 sequentially includes a lower steel ring 31, a middle steel ring 33 and an upper steel ring 35 from bottom to top, the lower steel ring 31 is installed on the top of the support tube 1, a bracket 32 is disposed between the lower steel ring 31 and the middle steel ring 33, the middle steel ring 33 and the upper steel ring 35 are connected by a hydraulic lifting system 34, specifically, the upper steel ring 35, the middle steel ring 33, the lower steel ring 31 and the bracket 32 are made of Q235-B and are manufactured strictly according to a construction scheme and design requirements, 12 jacks are uniformly disposed between the middle steel ring 33 and the upper steel ring 35, the hydraulic lifting system 34 is internally installed with a steel strand 5, and according to the design requirements and related standards of the present embodiment, the hydraulic lifting system 34 selects a 100t hydraulic jack, and a hydraulic control console (not shown in the present embodiment) is further provided, and the hydraulic console is configured to control the multiple hydraulic jacks to simultaneously operate or stop, so as to prevent the water tank 2 from tilting during the lifting process.
Example eight:
in this embodiment, as shown in fig. 1, this embodiment is a further supplement to embodiment seven, a plurality of second hoisting holes are provided on the middle steel ring 33, a plurality of third hoisting holes are provided on the upper steel ring 35, the plurality of second hoisting holes and the third hoisting holes are coaxially arranged, anchor clips are installed in the second hoisting holes and the third hoisting holes, the steel strands 5 sequentially penetrate through the third hoisting holes and the second hoisting holes, specifically, 12 second hoisting holes are provided on the middle steel ring 33, and 12 third hoisting holes are provided on the upper steel ring 35.
Example nine:
in this embodiment, as shown in fig. 1, this embodiment is a further supplement to embodiment eight, where a plurality of first hoisting holes 421 and second hoisting holes are coaxially disposed, the steel strand 5 sequentially passes through the third hoisting hole, the second hoisting hole and the first hoisting hole 421, and the lower end of the steel strand 5 is connected to the annular plate 42, specifically, the installation process of the steel strand 5 includes locking the anchor clamping piece on the annular plate 42, striking the anchor clamping piece with a hammer to make the end flat, and pressing the clamping piece with a limiting plate. Tensioning the steel strands 5 by using 1t of pretightening force through a 20t of penetrating type jack on the upper steel ring 35, clamping the steel strands on the anchor of the middle steel ring 33 one by one, pre-threading the steel strands 5 symmetrically according to the group, pulling the steel strands by hand to determine whether the stress is uniform or not, pre-tightening the steel strands again if the stress is not uniform, and after the pre-tightening operation is finished, well clamping the upper steel ring 35 on the anchor, clamping the steel strands, and adjusting all the anchors to form the limiting plates.
So far, the working mode of the water tank hoisting device of the water tower provided by the invention is as follows: the steel ring is lifted by 12 hydraulic jacks of 100t to act between the upper steel ring and the middle steel ring, the upper steel ring beam and the lower steel ring beam act alternately through retraction and lifting of the jacks, the water tank is driven by the anchorage device and the steel strand to ascend gradually, the ascending distance is calculated according to actual conditions each time, and the water tank is lifted by a certain distance.
Example ten:
the embodiment describes a construction method of a water tower to which the water tank hoisting device of the water tower is applied, and comprises the following steps:
a construction method of a water tower comprises the following steps:
a) The method comprises the following steps The foundation construction comprises the following steps: measuring and positioning, leveling a field, measuring and lofting, excavating earth and stone, treating a substrate, testing a groove of a foundation and pouring a cushion layer;
specifically, measurement positioning: the project is an independent circular structure, the position is not closely related to other projects, so the construction measurement control is relatively simple, 2 plane control points can be arranged in an encrypted manner near a construction site and also used as harmonic control points according to measurement control network information provided by an owner, each control pile is arranged at a position which is not interfered by construction and has good visibility, simultaneously, an obvious mark is made at the periphery, the control points are arranged to be convenient and easy to consider lofting work, and the measurement precision is required to accord with the regulations of engineering measurement Specifications (GB 50026-93) and design requirements;
leveling the field: firstly, surveying a construction site, finding out the actual condition of a project, leveling the site according to the elevation required by the design, removing all barriers on the ground and underground in a construction area, well performing drainage work of the construction site, and arranging intercepting ditches and drainage ditches around the site to ensure that the site does not accumulate water;
measuring and lofting: two professional pay-off measurers with profound services and two auxiliary staff are equipped to specially engage in measurement positioning work, and a J2-1 high-precision theodolite is adopted to control perpendicularity and detail lofting work; the main task of construction measurement is to set up the central position of the water tower and the elevation of each subsection; before and after partial project construction such as foundation trench excavation, foundation cushion, foundation bottom plate and the like, laying out the center of the water outlet tower and relevant side lines thereof according to field control points respectively, and timely guiding elevation to a structure at different stages and layer heights of construction; the measurement work needs to be carried out by personnel and instruments, and needs to be careful, tight and quick, so that the construction precision and quality are ensured, and the requirements of on-site continuous operation are met;
excavating earth and stone: according to actual conditions on site, the excavated earthwork is stacked at a site designated place or transported to an off-site designated soil piling field by a dump truck, so as to prevent over excavation and slope stabilization;
substrate treatment: mechanically excavating to reach the elevation close to the bottom of the designed pit, reserving a protective layer with the thickness of more than 300mm, and manually removing the protective layer before paving the cushion layer;
testing a groove on the foundation: carrying out concealed acceptance work of foundations and the like, and clearing impurities, accumulated water, sludge, floating soil, weeds and the like in the foundation pit;
pouring a cushion layer: and backfilling and tamping the bedding course earthwork in sections and layers, digging the joint portion into a step shape, wherein the step height is 25cm, the width is not less than 100cm, and tamping by using a frog rammer when backfilling the step portion. In the backfilling process, when the rubber soil phenomenon occurs, the tamping work is stopped, the rubber soil is timely dug out, and the rubber soil is replaced by good soil. After each layer of backfilled soil is tamped, sampling and detecting in time, and after the backfilled soil is qualified, backfilling the next layer, wherein the compactness is more than 0.94, and then pouring according to a design file.
b) The method comprises the following steps Assembling a slip form device, wherein the slip form device comprises a template, a surrounding ring, a lifting frame, an operating platform, a supporting rod and a hydraulic lifting system;
assembling a template: the independent foundation is formed by splicing and nailing four side plates in principle, two side plates are equal to corresponding structural sizes, and the other two side plates are 150-200 mm longer than the designed side and have the same height. The periphery of the square frame is spliced by wood boards, and the periphery of the square frame is provided with an inclined support and a flat support which are firmly fixed; a hoisting frame: the lifting frame is in an open shape, and the beam is a channel steel with the length of 1m and the money of 12 cm;
support bar and hydraulic lifting system: the supporting rods are steel pipes with the diameter of 48.3 multiplied by 3.5mm, the supporting rods penetrate into the hydraulic lifting system 34, the supporting rods are welded between two channel steels, the notches of the channel steels face the steel pipes, the hydraulic lifting system 34 adopts 12 hydraulic jacks, each jack works to lift 60kN, and the hydraulic jacks fall on the cross beam;
operating the platform and the enclosure: operation platform divide into interior operation platform and outer operation platform, and interior operation platform's crossbeam adopts wide 14 cm's channel-section steel, and the vertical and horizontal interval of crossbeam is 0.6m, links to each other with the channel-section steel enclosure that the hoisting frame passes through width 12, and the enclosure sets up along the hoop through-length, and every angle steel that is long 0.42m75 degree angle holds in the palm the enclosure. The 5 cm-thick wood springboard is fully paved on the platform, the cross beam of the outer operating platform adopts 12 channel steel with the length of 2.5m, and the cross beam is welded on the lifting frame upright post. The width of the external operating platform is 1.5m, and the end of the beam is stretched and hung with a dense mesh type safety net which is connected with the bottom of the lower hanging ladder. The dense mesh type safety net is arranged along the circumferential through length to prevent sundries from falling to the ground, the elevation of an internal and external operation platform is flush with the elevation of the top of the steel formwork, angle steel with the length of 1.5m and the angle of 75 degrees is welded between the cross beam and the upright post of the lifting frame to be used as an inclined strut,
c) The method comprises the following steps Constructing a main body of the support cylinder 1, and constructing the main body of the support cylinder 1 to reach a design height through a slip form device; the slip form construction comprises three stages of initial lifting, normal sliding lifting and final lifting. After the normal sliding is carried out, if the sliding is required to be suspended (such as water cut, power cut or wind power reaching six levels), sliding stopping measures are required; before slip form construction, the following slip form equipment is overhauled;
initial rising: before the template slides up, concrete with the height of 60cm is poured on the bottom layer, and the template slides after the stopping time is 3 to 5 hours until the strength of the concrete at the bottom reaches 0.3 to 0.4MPa required by the specification;
and (3) normal sliding: the normal slip form mainly comprises steel bar binding, concrete warehousing and slip form lifting, wherein the height of each slip form is about 30cm, the slip form lifting is carried out after the steel bar binding and before the concrete pouring according to the working procedures, and the transition platform of the tower body and the inlet hole and the lower cylinder body are continuously constructed.
Final liter: and (3) sliding to a position close to the top (elevation), measuring the elevation of the concrete and making a corresponding mark, accelerating the pouring speed as much as possible when the last layer of concrete is poured, leveling the concrete in the mold in time, lifting the template by 30cm after the last layer of concrete is poured, and vibrating once in a support cylinder to ensure the width of the section.
d) 2 on-spot prefabrications of water tank and maintenance and the installation of securing device 4, 2 on-spot prefabrications of water tank include with the maintenance: installing a template scaffold of the water tank 2, installing an outer template of the shell, binding reinforcing steel bars, sequentially combining inner concrete, curing concrete, dismantling the template and decorating the outer surface of the water tank; after the water tank 2 is formed and placed for a period of time, the stabilizing device 4 is installed on the inner side of the water tank 2, an outer steel ring 46 is installed along the inner side wall of the middle ring beam 22 of the water tank 2, then a guide plate 43 is installed along the upper shell 23 of the water tank 2, then an annular plate 42 is installed at a designed position, then a first vertical support 41 and a second vertical support 44 are installed, and finally an inner steel ring 45 is installed;
e) The method comprises the following steps The slipform apparatus is dismantled and the hoisting device 3 is made, and the slipform apparatus is dismantled and includes: dismantling the template, the enclosure and the supporting rod; the manufacturing of the lifting device 3 comprises the following steps: installing a lower steel ring 31 on the operating platform, using an upper support and a lower support of the lifting frame as an upper steel ring 35 and a middle steel ring 33 respectively, installing a bracket support 32 between the lower steel ring 31 and the middle steel ring 33, and then passing the steel strand 5 through a hydraulic lifting system 34;
f) The method comprises the following steps Lifting and mounting the water tank 2, mounting the steel strand 5 on the annular plate 42, lifting the water tank 2 to a designed position through the lifting device 3, then pouring a ring joist, and mounting the lower shell 21 of the water tank 2 on the ring joist;
g) The method comprises the following steps The engineering is ended, and the engineering end includes: the pipeline electrical installation and test of the water tank 2, the construction of the top cover of the clerestory, the door and window, the decoration, the anticorrosion construction, the removal of the lifting device and the stabilizing device, the finishing and the repair, the delivery and the acceptance check, and the project finishing is executed according to the relevant standards, which is not repeated herein.
The present invention is not limited to the above-described alternative embodiments, and various other forms of products can be obtained by anyone in light of the present invention. The above detailed description should not be taken as limiting the scope of the invention, which is defined in the claims, and which the description is intended to be interpreted accordingly.

Claims (10)

1. The water tank hoisting device for the water tower is characterized by comprising a hoisting device (3) and a stabilizing device (4), wherein the hoisting device (3) is connected with the stabilizing device (4) through a plurality of steel strands (5); the water tank is characterized by further comprising a supporting cylinder (1) and a water tank (2), wherein the water tank (2) is mounted at the top of the supporting cylinder (1) through the hoisting device, the lifting device (3) is mounted at the top of the supporting cylinder (1), and the stabilizing device (4) is mounted between the supporting cylinder (1) and the water tank (2);
the stabilizing device (4) comprises an inner steel ring (45), an outer steel ring (46) and an annular plate (42), the inner wall of the inner steel ring (45) is tightly abutted to the outer wall of the support cylinder (1), the outer steel ring (46) is installed on the water tank (2), the annular plate (42) is arranged between the outer wall of the inner steel ring (45) and the inner wall of the outer steel ring (46), and the steel strand (5) is connected with the annular plate (42);
when the hoisting process is shaken, the inner steel ring (45) is in contact with the support tube (1), the collision force is transmitted to the annular plate (42) through the inner steel ring (45), and the annular plate (42) is partially deformed to unload the impact force.
2. The water tank lifting device of a water tower as claimed in claim 1, wherein a plurality of first vertical supports (41) are further provided between the outer wall of the inner steel ring (45) and the inner wall of the outer steel ring (46), and a plurality of first vertical supports (41) are uniformly distributed at the bottom of the annular plate (42).
3. The water tank lifting device of a water tower as claimed in claim 1, wherein a filling layer (6) is arranged between the inner steel ring (45) and the outer wall of the branch pipe (1).
4. The water tank lifting device of a water tower as claimed in claim 2, wherein a force guide plate (43) is mounted on the upper shell (23) of the water tank (2), and one end of the force guide plate (43) is mounted on the annular plate (42).
5. The water tank lifting device of a water tower according to claim 4, characterized in that the force guide plate (43) is shaped to match the upper housing (23), and a second vertical support (44) is arranged between the annular plate (42) and the force guide plate (43).
6. The water tank lifting device of the water tower as claimed in claim 5, wherein a plurality of first lifting holes (421) are formed in the annular plate (42), and the steel strand (5) passes through the first lifting holes (421).
7. The water tank hoisting device of the water tower according to claim 6, wherein the lifting device (3) comprises a lower steel ring (31), a middle steel ring (33) and an upper steel ring (35) which are sequentially arranged from bottom to top, the lower steel ring (31) is installed on the top of the support tube (1), a bracket support (32) is arranged between the lower steel ring (31) and the middle steel ring (33), and the middle steel ring (33) and the upper steel ring (35) are connected through a hydraulic lifting system (34).
8. The water tank lifting device of a water tower as claimed in claim 7, wherein a plurality of second lifting holes are formed on the middle steel ring (33), a plurality of third lifting holes are formed on the upper steel ring (35), a plurality of second lifting holes and third lifting holes are coaxially arranged, and the steel strand (5) sequentially passes through the third lifting holes and the second lifting holes.
9. The water tank hoisting device of the water tower as claimed in claim 8, wherein the first hoisting holes (421) and the second hoisting holes are coaxially arranged, the steel strand (5) sequentially passes through the third hoisting hole, the second hoisting hole and the first hoisting hole (421), and the lower end of the steel strand (5) is connected to the annular plate (42).
10. A construction method comprising the water tank lifting device of claim 9, characterized by comprising the steps of:
a) The foundation construction comprises the following steps: measuring and positioning, leveling a field, measuring and lofting, excavating earth and stone, treating a substrate, testing a groove of a foundation and pouring a cushion layer;
b) Assembling a slip form device, wherein the slip form device comprises a template, a surrounding ring, a lifting frame, an operating platform, a supporting rod and a hydraulic lifting system;
c) Constructing a main body of the support cylinder (1), and constructing the main body of the support cylinder (1) to reach a design height through a slip form device;
d) Water tank (2) field prefabrication and maintenance and securing device (4) installation, water tank (2) field prefabrication and maintenance include: installing a template scaffold of the water tank (2), installing a shell outer template, binding reinforcing steel bars, sequentially combining inner concrete pouring, curing concrete, dismantling the template and decorating the outer surface of the water tank; after the water tank (2) is molded, the water tank is placed for a period of time, the stabilizing device (4) is installed on the inner side of the water tank (2), the outer steel ring (46) is installed along the inner side wall of the middle ring beam (22) of the water tank (2), then the force guide plate (43) is installed along the upper shell (23) of the water tank (2), then the annular plate (42) is installed at a designed position, then the first vertical support (41) and the second vertical support (44) are installed, and finally the inner steel ring (45) is installed;
e) The slipform device is dismantled and hoisting device (3) is made, and the slipform device is dismantled and includes: removing the template, the enclosure and the supporting rod; the manufacturing of the lifting device (3) comprises the following steps: installing a lower steel ring (31) on the operation platform, wherein an upper support and a lower support of the lifting frame are respectively used as an upper steel ring (35) and a middle steel ring (33), installing a bracket support (32) between the lower steel ring (31) and the middle steel ring (33), and then passing the steel strand (5) through a hydraulic lifting system (34);
f) Lifting and installing the water tank (2), installing the steel strand (5) on the annular plate (42), lifting the water tank (2) to a design position through the lifting device (3), then pouring a ring joist, and installing a lower shell (21) of the water tank (2) on the ring joist;
g) The engineering is ended, and the engineering end includes: the pipeline electrical installation and the test of water tank (2), the construction of clerestory top cover, the door and window construction, decoration construction and anticorrosive construction, hoisting device and securing device demolish, finish and deal with and accept.
CN202110444468.XA 2021-04-23 2021-04-23 Water tank hoisting device of water tower and construction method thereof Active CN113137060B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110444468.XA CN113137060B (en) 2021-04-23 2021-04-23 Water tank hoisting device of water tower and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110444468.XA CN113137060B (en) 2021-04-23 2021-04-23 Water tank hoisting device of water tower and construction method thereof

Publications (2)

Publication Number Publication Date
CN113137060A CN113137060A (en) 2021-07-20
CN113137060B true CN113137060B (en) 2022-11-18

Family

ID=76811835

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110444468.XA Active CN113137060B (en) 2021-04-23 2021-04-23 Water tank hoisting device of water tower and construction method thereof

Country Status (1)

Country Link
CN (1) CN113137060B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114892966B (en) * 2022-06-27 2024-07-26 中交二公局第七工程有限公司 Integral casting concrete supporting component and supporting method for inverted cone-shell water tower water tank

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1072153A (en) * 1992-11-02 1993-05-19 俞仁杰 The method for improving of water tower parts and lifting facility thereof
CN1272595A (en) * 1999-03-30 2000-11-08 富士重工业株式会社 Horizontal axle type wind turbomachine and its manufacturing method
CN201258603Y (en) * 2008-08-23 2009-06-17 中冶天工建设有限公司 Lifting device for back taper case water box
CN101538936A (en) * 2009-03-19 2009-09-23 二十三冶建设集团有限公司 Hydraulic slip-and-lift construction method for water tower, hydraulic slip-form device, lifting device and hanger rod connecting piece thereof
CN101809283A (en) * 2007-08-29 2010-08-18 维斯塔斯风力系统集团公司 Monopile foundation for offshore wind turbine
CN103195287A (en) * 2013-04-09 2013-07-10 中国十九冶集团有限公司 Hydraulic lifting anti-falling device and method for inverted cone-shaped water tank of reinforced concrete water tower
CN204899397U (en) * 2015-08-09 2015-12-23 中国能源建设集团安徽电力建设第二工程有限公司 A ring beam that is used for cable wire hydraulic lifting chimney steel inner tube
CN210264130U (en) * 2019-05-05 2020-04-07 苏州泰高烟囱科技有限公司 Hoisting stabilizer

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1072153A (en) * 1992-11-02 1993-05-19 俞仁杰 The method for improving of water tower parts and lifting facility thereof
CN1272595A (en) * 1999-03-30 2000-11-08 富士重工业株式会社 Horizontal axle type wind turbomachine and its manufacturing method
CN101809283A (en) * 2007-08-29 2010-08-18 维斯塔斯风力系统集团公司 Monopile foundation for offshore wind turbine
CN201258603Y (en) * 2008-08-23 2009-06-17 中冶天工建设有限公司 Lifting device for back taper case water box
CN101538936A (en) * 2009-03-19 2009-09-23 二十三冶建设集团有限公司 Hydraulic slip-and-lift construction method for water tower, hydraulic slip-form device, lifting device and hanger rod connecting piece thereof
CN103195287A (en) * 2013-04-09 2013-07-10 中国十九冶集团有限公司 Hydraulic lifting anti-falling device and method for inverted cone-shaped water tank of reinforced concrete water tower
CN204899397U (en) * 2015-08-09 2015-12-23 中国能源建设集团安徽电力建设第二工程有限公司 A ring beam that is used for cable wire hydraulic lifting chimney steel inner tube
CN210264130U (en) * 2019-05-05 2020-04-07 苏州泰高烟囱科技有限公司 Hoisting stabilizer

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
于国成.倒伞型大吨位水塔水箱柔性提升施工方法.《中国高新技术企业》.2012,(第6期),第86-88页. *

Also Published As

Publication number Publication date
CN113137060A (en) 2021-07-20

Similar Documents

Publication Publication Date Title
CN102031784B (en) Slope protection pile pouring and cable bolting construction method for deep foundation pit
CN110306557B (en) Earth excavation method based on basement deep foundation pit engineering
CN112982181B (en) Construction method for steel-concrete combined section of through-type steel box continuous arch bridge
CN111456019A (en) Safe construction method for foundation pit excavation
CN107044142B (en) Adjustable reinforcement deviation correcting method and structure for reducing uneven settlement of house
CN110863498A (en) Deep foundation pit combined supporting construction method next to subway station
CN114837088A (en) Construction method of bearing platform on highway
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN113137060B (en) Water tank hoisting device of water tower and construction method thereof
CN118110193A (en) Whole-process construction method for large-diameter open caisson on land in complex geology
CN110748701A (en) Pipe-jacking working pit construction method
CN113417300A (en) Slope support system and construction method thereof
CN117166510A (en) Deep large-diameter open caisson construction method
CN106758852A (en) Across foundation pit enclosure to support beam trestle construction technology
CN114108485A (en) Gate-type pier capping beam construction method
CN113266019B (en) Construction method of foundation pit steel pipe support system
CN115717397A (en) Larsen steel sheet pile and prestressed anchor cable combined supporting construction method
CN216129955U (en) Steel-concrete combined section structure of through-type steel box continuous arch bridge
CN115897600A (en) Construction method for newly-built foundation pit close to existing subway station deep foundation pit proximity area
CN113152978A (en) Hydraulic self-lifting construction method based on inverted cone shell water tank
CN112095377B (en) Off-pit construction road structure next to subway deep foundation pit and construction method thereof
CN204728568U (en) The levelling plate of a kind of pin-connected panel precast concrete
CN216865172U (en) Basement foundation pit support system newly added in existing factory building
CN111719576B (en) Sinking guiding system suitable for underground shaft group construction and underground shaft group construction method
CN110847212B (en) Construction method for 2 meters below horizontal plane for green carving

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant