CN113090284A - 一种用于地下矿山松软破碎岩体的巷道支护方法 - Google Patents

一种用于地下矿山松软破碎岩体的巷道支护方法 Download PDF

Info

Publication number
CN113090284A
CN113090284A CN202110399667.3A CN202110399667A CN113090284A CN 113090284 A CN113090284 A CN 113090284A CN 202110399667 A CN202110399667 A CN 202110399667A CN 113090284 A CN113090284 A CN 113090284A
Authority
CN
China
Prior art keywords
anchor
roadway
support
anchor rod
primary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202110399667.3A
Other languages
English (en)
Other versions
CN113090284B (zh
Inventor
刘允秋
许传华
肖益盖
孙国权
李宁
汪亮
李卿
谢智谋
井立祥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Original Assignee
Sinosteel Nanjing Huaxin Technology Co ltd
Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinosteel Nanjing Huaxin Technology Co ltd, Huawei National Engineering Research Center of High Efficient Cyclic and Utilization of Metallic Mineral Resources Co Ltd, Sinosteel Maanshan General Institute of Mining Research Co Ltd filed Critical Sinosteel Nanjing Huaxin Technology Co ltd
Priority to CN202110399667.3A priority Critical patent/CN113090284B/zh
Publication of CN113090284A publication Critical patent/CN113090284A/zh
Application granted granted Critical
Publication of CN113090284B publication Critical patent/CN113090284B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/003Machines for drilling anchor holes and setting anchor bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/107Reinforcing elements therefor; Holders for the reinforcing elements
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

本发明公开了一种用于地下矿山松软破碎岩体的巷道支护方法,适用于岩体弱风化、锤子敲击声哑、岩体强度值≤10Mpa的巷道支护工程,超前支护锚杆沿巷道拱部布置,同时不同循环进尺施工的管缝式锚杆相互重叠,这样对松软岩体的支护效果更好,其中初始巷道设计巷道断面为三心拱、反底拱形式,接着进行锚杆超前支护,即超前支护锚杆中的管缝式锚杆插入巷道顶板拱部,插入巷道顶板1.5m,外露1m,每个循环进尺不超过1m,外露部分保护人员在其下方安全作业,然后进行锚网喷注初次支护,初次支护与二次支护间隔50~80m,整个完整的支护方法可实现金属矿山井巷工程支护永久稳固性,提高巷道支护施工质量,降低巷道返修率,从而降低支护成本。

Description

一种用于地下矿山松软破碎岩体的巷道支护方法
技术领域
本发明涉及矿山巷道支护技术领域,特别涉及一种用于地下矿山松软破碎岩体的巷道支护方法。
背景技术
金属矿山地下开采巷道掘进过程中,经常遇到松软破碎岩体,岩石松软破碎,裂隙面较多,裂隙中有充填物,分界面不规则,岩体强度较低、遇水膨胀、完整性较差、支护难度大的情况,在此种环境下,巷道开挖面支护难度极大。
我国金属矿山类似松软破碎岩体支护方式基本采用钢拱架或者砌碹支护,比如:马钢白象山铁矿、山东黄金三山岛金矿、沂南金矿、鲁中矿业、矾山磷矿,矿山井下均采取了钢拱架支护,外层喷浆支护形式,由于钢拱架支护属于被动支护,无法主动承压,最后均以失败告终。巷道支护变形失效后,重新返修,既增加了采矿成本,又耽误了生产工期。松软破碎岩体巷道的掘进与支护施工难度大、成本高,如支护设计不合理,同时也增加了安全隐患。所以急需一种能满足松软破碎岩体支护要求的巷道支护方法。
发明内容
本发明的目的在于提供一种用于地下矿山松软破碎岩体的巷道支护方法,具备稳固性高,提高巷道支护施工质量,降低巷道返修率,从而降低支护成本的优点,以解决上述背景技术中提出的问题。
为实现上述目的,本发明提供如下技术方案:
一种用于地下矿山松软破碎岩体的巷道支护方法,支护结构包括超前支护锚杆、初次支护工件和二次支护工件,所述初次支护工件覆盖在超前支护锚杆的外侧,超前支护锚杆采用管缝式锚杆,初次支护工件的外侧覆盖二次支护工件,初次支护工件包括钢筋网、注浆锚杆和初级混凝土层,钢筋网布置在巷道的侧壁上,巷道的侧壁和顶壁表面均喷射有初级混凝土层,注浆锚杆垂直打入巷道岩体中,注浆锚杆的尾端连接钢筋网,钢筋网和注浆锚杆均与初级混凝土层接触,初级混凝土层的外侧覆盖二次支护工件,所述二次支护工件包括预应力锚索、加强网、强力锚杆、反底拱、二次混凝土层和复喷层,预应力锚索和强力锚杆贯穿初次支护工件并垂直打入巷道岩体中,加强网预设在初次支护工件的外侧,加强网上喷射二次混凝土层,二次混凝土层的底端安装反底拱,二次混凝土层和反底拱的外表面覆盖有一层复喷层,复喷层还与强力锚杆和预应力锚索接触;
支护结构在支护时按照如下方法:
S1:巷道断面开挖,其中在挖掘巷道时需要预留变形距离,其中在净断面尺寸之上预留变形量为100mm,同时需要在净断面基础之上预留支护厚度150mm,设计巷道断面为三心拱、反底拱形式;
S2:锚杆超前支护,其中采用管缝式锚杆进行超前支护,先预制直径40mm长度2500mm的管缝式锚杆,然后超前支护锚杆中的管缝式锚杆插入巷道顶板拱部,插入巷道顶板1.5m,外露1m,每个循环进尺不超过1m,外露部分保护人员在其下方安全作业;
S3:锚网喷注初次支护,初次支护的施工顺序为:挂网,打注浆锚杆,喷浆,注浆;
a挂网,即铺设钢筋网,钢筋网采用Φ6mm钢筋焊接制成,相邻的两块钢筋网相互搭接,两块钢筋网的搭接长度100mm,相邻的两块钢筋网搭接处用双股12#铁丝双股双排扣绑扎连接,钢筋网的搭接处必须利用锚杆压紧;
b打注浆锚杆,其中锚杆采用注浆锚杆支护工艺,注浆锚杆采用Φ22mm×2200mm无缝钢管滚丝制作,注浆锚杆的杆尾制作成麻花状,注浆锚杆既用作注浆又作为锚杆使用,锚杆间排距800mm×800mm;
c喷浆,即在钢筋网上制备初级混凝土层,其中初级混凝土层的强度等级为C25,初级混凝土层中的水泥、水、沙子的配合比为1:2:2,同时在制备混凝土泥浆时掺入总质量3~5%的速凝剂,初级混凝土层厚度为50mm,初级混凝土层覆盖锚杆托盘;
d注浆,注浆采用单液水泥-水玻璃浆液,水泥使用42.5级普通硅酸盐水泥,水灰比控制在0.8~1.0左右,水玻璃的掺量为水泥用量的3~5%。浆液结石率不低于92%,浆液固结体强度不低于20MPa,注浆压力控制在2.0MPa以内;
S4:二次支护,初次支护与二次支护间隔50~80m,二次支护的施工顺序为:挂网、喷浆、反底拱、打锚杆、打锚索、复喷;
a挂网,其中加强网预设在初次支护工件的外侧,相邻的两块加强网相互搭接,相邻的两块加强网搭接处用双股12#铁丝双股双排扣绑扎连接;
b喷浆,即在加强网上喷射混凝土,加强网固定完毕后喷射制成二次混凝土层,二次混凝土层的厚度为70mm、二次混凝土层的强度等级为C25;
c反底拱,反底拱采用U29型钢和C30混凝土制成,即在弯曲的U29型钢上铺设C30混凝土,C30混凝土表面平整,反底拱的最大厚度为500mm,U29型钢的排距为1000mm,反底拱的U29型钢与上部型钢相连形成封闭结构,结构更加稳定,保证整体支护效果;
d打锚杆,即安装施工强力锚杆,强力锚杆采用牌号为BHRB500的高性能螺纹钢锚杆,高性能螺纹钢锚杆的规格为Φ20mm×2200mm,间排距为800mm×800mm,锚杆孔直径为Φ28mm;
e打锚索,即安装施工预应力锚索,预应力锚索采用1×19股高强度低松弛预应力钢绞线制作,为拉压分散型预应力锚索;锚索直径为Φ22mm,长度为6000mm;孔径为Φ28mm;
f复喷,即完成二次支护前,进行再次喷浆,形成复喷层,复喷层对锚索和注浆管进行保护,复喷层的混凝土强度和配合比与二次混凝土层相同,复喷层的厚度值为30mm。
优选的,所述超前支护锚杆中的管缝式锚杆采用1m/进尺设计,每个循环均进行锚杆超前支护,管缝式锚杆全长2.5m,每个循环进尺重叠长度为1.5m。
优选的,所述超前支护锚杆中的管缝式锚杆沿巷道拱部布置,管缝式锚杆间距300mm,其中管缝式锚杆斜向上插入,倾斜角度10~15°。
优选的,所述钢筋网和加强网的网格规格均为100mm×100mm。
优选的,所述反底拱的上表面铺设喷射混凝土回弹料制成的垫层,反底拱的下方铺设有采用单层Φ6mm钢筋焊接而成的经纬网,相邻经纬网的搭接长度大于200mm。
优选的,所述注浆锚杆安装时采用1卷Z2330型树脂药卷临时锚固,预紧力矩不低于300N·m,托盘采用拱型高强度托盘,规格为150mm×150mm×12mm。
优选的,所述强力锚杆安装时采用1卷Z2350型和1卷K2350型树脂药卷加长锚固,锚固力不低于110kN,预紧力矩不低于300N·m,托盘采用拱型高强度托盘,规格为150mm×150mm×12mm,每根锚杆安装一个让压管,强力锚杆安装时,顶板及两帮锚杆应通过钢筋梯连接,钢筋梯采用Φ14mm的钢筋焊接而成,钢筋梯共片,钢筋梯的尺寸为2400mm×80mm。
优选的,所述预应力锚索沿巷道拱部布置3根,预应力锚索的间排距为800mm×1600mm,预应力锚索的长度值大于注浆锚杆与强力锚杆的长度值。
优选的,所述预应力锚索安装时采用1卷快速K2350和2卷中速Z2350型树脂药卷加长锚固,其极限承载力为607kN,伸长率为7%,预应力锚索采用高强度可调心托盘和专用锚具与设备进行张拉、固定和切割,预应力锚索的预应力不低于150kN。
优选的,所述初次支护工件中的锚网喷注初次支护施工要求在前探梁防护下作业。
与现有技术相比,本发明的有益效果是:本发明提出的一种用于地下矿山松软破碎岩体的巷道支护方法,适用于岩体弱风化、锤子敲击声哑、岩体强度值≤10Mpa的巷道支护工程,超前支护锚杆沿巷道拱部布置,超前支护锚杆中的管缝式锚杆向上倾斜10-15度,同时不同循环进尺施工的管缝式锚杆相互重叠,这样对松软岩体的支护效果更好,其中初始巷道设计巷道断面为三心拱、反底拱形式,接着进行锚杆超前支护,即超前支护锚杆中的管缝式锚杆插入巷道外侧,然后进行锚网喷注初次支护,锚网喷注初次支护的施工顺序为:挂网,打注浆锚杆,喷浆,注浆,其中初次支护与二次支护间隔50~80m,二次支护的施工顺序为:挂网、喷浆、反底拱、打锚杆、打锚索、复喷;整个完整的支护方法可实现金属矿山井巷工程支护永久稳固性,提高巷道支护施工质量,降低巷道返修率,从而降低支护成本。
附图说明
图1为本发明的初次支护后的效果示意图;
图2为本发明的二次支护后的剖面示意图;
图3为本发明的初次支护后的剖面示意图;
图4为本发明的A处放大示意图;
图5为本发明的巷道支护总体流程示意图;
图6为本发明的巷道支护初次支护流程示意图;
图7为本发明的巷道支护二次支护流程示意图;
图中:1、超前支护锚杆;2、初次支护工件;21、钢筋网;22、注浆锚杆;23、初级混凝土层;3、二次支护工件;31、预应力锚索;32、加强网;33、强力锚杆;34、反底拱;35、二次混凝土层;36、复喷层。
具体实施方式
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
请参阅附图1-附图4,一种用于地下矿山松软破碎岩体的巷道支护方法,支护结构包括超前支护锚杆1、初次支护工件2和二次支护工件3,支护顺序的实施时间依次为超前支护锚杆1、初次支护工件2和二次支护工件3,其中初次支护与二次支护间隔50~80m,初次支护工件2覆盖在超前支护锚杆1的外侧,超前支护锚杆1采用管缝式锚杆,超前支护锚杆1中的管缝式锚杆沿巷道拱部布置,管缝式锚杆间距300mm,其中管缝式锚杆斜向上插入,倾斜角度10~15°,超前支护锚杆1中的管缝式锚杆采用1m/进尺设计,每个循环均进行锚杆超前支护,不同循环进尺施工的管缝式锚杆相互重叠,管缝式锚杆重叠长度为1.5m,这样对松软破碎岩体的支护效果更好,初次支护工件2的外侧覆盖二次支护工件3,初次支护工件2包括钢筋网21、注浆锚杆22和初级混凝土层23,钢筋网21网格规格为100mm×100mm,相邻两块钢筋网21的搭接长度为100mm,钢筋网21布置在巷道的侧壁上,巷道的侧壁和顶壁表面均喷射有初级混凝土层23,注浆锚杆22垂直打入巷道岩体中,注浆锚杆22的尾端连接钢筋网21,注浆锚杆22安装时采用1卷Z2330型树脂药卷临时锚固,预紧力矩不低于300N·m,托盘采用拱型高强度托盘,规格为150mm×150mm×12mm,钢筋网21和注浆锚杆22均与初级混凝土层23接触,钢筋网21作为初级混凝土层23的骨架,同时也便于初级混凝土层23的附着,初级混凝土层23的外侧覆盖二次支护工件3,其中初次支护与二次支护间隔50~80m,同时在初次支护过程中进行注浆锚杆22的安装就可以保证了强度,无需额外安装钢拱架,节约了钢拱架的安装和拆卸工序,二次支护工件3包括预应力锚索31、加强网32、强力锚杆33、反底拱34、二次混凝土层35和复喷层36,预应力锚索31和强力锚杆33贯穿初次支护工件2并垂直打入巷道岩体中,预应力锚索31沿巷道拱部布置3根,预应力锚索31的间排距为800mm×1600mm,预应力锚索31的长度值大于注浆锚杆22与强力锚杆33的长度值,强力锚杆33安装时,顶板及两帮锚杆应通过钢筋梯连接,钢筋梯采用Φ14mm的钢筋焊接而成,钢筋梯共3片,钢筋梯的尺寸为2400mm×80mm,加强网32预设在初次支护工件2的外侧,加强网32的网格规格为100mm×100mm,加强网32上喷射二次混凝土层35,其中二次混凝土层35的厚度值大于初级混凝土层23的厚度值,二次混凝土层35的底端安装反底拱34,反底拱34为一种U29型钢制成的构件,反底拱34的上表面铺设喷射混凝土回弹料制成的垫层,反底拱34的下方铺设有采用单层Φ6mm钢筋焊接而成的经纬网,相邻经纬网的搭接长度大于200mm,反底拱34与上部支撑相连形成封闭结构,整体支撑效果好,二次混凝土层35和反底拱34的外表面覆盖有一层复喷层36,复喷层36还与强力锚杆33和预应力锚索31接触。
请参阅附图5-附图7,支护结构在支护时按照如下方法:
第一步:巷道断面开挖,其中在挖掘巷道时需要预留变形距离,其中在净断面尺寸之上预留变形量为100mm,同时需要在净断面基础之上预留支护厚度150mm,设计巷道断面为三心拱、反底拱形式;
第二步:锚杆超前支护,其中采用管缝式锚杆进行超前支护,先预制直径40mm长度2500mm的管缝式锚杆,然后超前支护锚杆1中的管缝式锚杆插入巷道顶板拱部,插入巷道顶板1.5m,外露1m,每个循环进尺不超过1m,外露部分保护人员在其下方安全作业;
第三步:锚网喷注初次支护,其中整个锚网喷注初次支护施工要求在前探梁防护下作业,初次支护的施工顺序为:挂网,打注浆锚杆,喷浆,注浆;
a挂网,即铺设钢筋网21,钢筋网21采用Φ6mm钢筋焊接制成,相邻的两块钢筋网21相互搭接,两块钢筋网21的搭接长度100mm,相邻的两块钢筋网21搭接处用双股12#铁丝双股双排扣绑扎连接,钢筋网21的搭接处必须利用锚杆压紧;
b打注浆锚杆,其中锚杆采用注浆锚杆22支护工艺,注浆锚杆22采用Φ22mm×2200mm无缝钢管滚丝制作,注浆锚杆22的杆尾制作成麻花状,注浆锚杆22既用作注浆又作为锚杆使用,锚杆间排距800mm×800mm,注浆锚杆22安装时采用1卷Z2330型树脂药卷临时锚固,预紧力矩不低于300N·m,托盘采用拱型高强度托盘,规格为150mm×150mm×12mm;
c喷浆,即在钢筋网21上制备初级混凝土层23,其中初级混凝土层23的强度等级为C25,初级混凝土层23中的水泥、水、沙子的配合比为1:2:2,同时在制备混凝土泥浆时掺入总质量3~5%的速凝剂,初级混凝土层23厚度为50mm,初级混凝土层23覆盖锚杆托盘;
d注浆,注浆采用单液水泥-水玻璃浆液,水泥使用42.5级普通硅酸盐水泥,水灰比控制在0.8~1.0左右,水玻璃的掺量为水泥用量的3~5%。浆液结石率不低于92%,浆液固结体强度不低于20MPa,注浆压力控制在2.0MPa以内;
第四步:二次支护,初次支护与二次支护间隔50~80m,二次支护的施工顺序为:挂网、喷浆、反底拱、打锚杆、打锚索、复喷;
a挂网,其中加强网32预设在初次支护工件2的外侧,相邻的两块加强网32相互搭接,相邻的两块加强网32搭接处用双股12#铁丝双股双排扣绑扎连接;
b喷浆,即在加强网32上喷射混凝土,加强网32固定完毕后喷射制成二次混凝土层35,二次混凝土层35的厚度为70mm、二次混凝土层35的强度等级为C25;
c反底拱,反底拱34采用U29型钢和C30混凝土制成,即在弯曲的U29型钢上铺设C30混凝土,C30混凝土表面平整,反底拱34的最大厚度为500mm,U29型钢的排距为1000mm,反底拱34的U29型钢与上部型钢相连形成封闭结构,结构更加稳定,保证整体支护效果反,底拱34的下方铺设有采用单层Φ6mm钢筋焊接而成的经纬网,相邻经纬网的搭接长度大于200mm;
d打锚杆,即安装施工强力锚杆33,强力锚杆33采用牌号为BHRB500的高性能螺纹钢锚杆,高性能螺纹钢锚杆的规格为Φ20mm×2200mm,间排距为800mm×800mm,锚杆孔直径为Φ28mm;强力锚杆33安装时采用1卷Z2350型和1卷K2350型树脂药卷加长锚固,锚固力不低于110kN,预紧力矩不低于300N·m,托盘采用拱型高强度托盘,规格为150mm×150mm×12mm,每根锚杆安装一个让压管;强力锚杆33安装时,顶板及两帮锚杆应通过钢筋梯连接,钢筋梯采用Φ14mm的钢筋焊接而成,钢筋梯共3片,钢筋梯的尺寸为2400mm×80mm,
e打锚索,即安装施工预应力锚索31,预应力锚索31采用1×19股高强度低松弛预应力钢绞线制作,为拉压分散型预应力锚索;锚索直径为Φ22mm,长度为6000mm;孔径为Φ28mm;预应力锚索31安装时采用1卷快速K2350和2卷中速Z2350型树脂药卷加长锚固,其极限承载力为607kN,伸长率为7%,预应力锚索31采用高强度可调心托盘和专用锚具与设备进行张拉、固定和切割,预应力锚索31的预应力不低于150kN;预应力锚索31沿巷道拱部布置3根,预应力锚索31的间排距为800mm×1600mm,预应力锚索31的长度值大于注浆锚杆22与强力锚杆33的长度值。
f复喷,即完成二次支护前,进行再次喷浆,形成复喷层36,复喷层36对锚索和注浆管进行保护,复喷层36的混凝土强度和配合比与二次混凝土层35相同,复喷层36的厚度值为30mm。
本一种用于地下矿山松软破碎岩体的巷道支护方法,适用于岩体弱风化、锤子敲击声哑、岩体强度值≤10Mpa的巷道支护工程,支护顺序依次为超前支护锚杆1、初次支护工件2和二次支护工件3,其中初次支护与二次支护间隔50~80m,同时在初次支护过程中进行注浆锚杆22的安装就可以保证了强度,无需额外安装钢拱架,节约了钢拱架的安装和拆卸工序,初次支护工件2覆盖在超前支护锚杆1的外侧,超前支护锚杆1沿巷道拱部布置,超前支护锚杆1中的管缝式锚杆向上倾斜10-15度,同时不同循环进尺施工的管缝式锚杆相互重叠,这样对松软岩体的支护效果更好,初次支护工件2的外侧覆盖二次支护工件3,初次支护工件2包括钢筋网21、注浆锚杆22和初级混凝土层23,钢筋网21和注浆锚杆22与初级混凝土层23接触,钢筋网21作为初级混凝土层23的骨架,初级混凝土层23的外侧覆盖二次支护工件3,二次支护工件3包括预应力锚索31、加强网32、强力锚杆33、反底拱34、二次混凝土层35和复喷层36,预应力锚索31和强力锚杆33贯穿初次支护工件2并伸入巷道岩体中,预应力锚索31沿巷道拱部布置3根,强力锚杆33安装时,顶板及两帮锚杆应通过钢筋梯连接,可增加强度同时保证整体的支护效果,反底拱34与上部支撑相连形成封闭结构,整体支撑效果好,二次混凝土层35和反底拱34的外表面覆盖有一层复喷层36,复喷层36还与强力锚杆33和预应力锚索31接触;其中巷道支护的方法依次为巷道断面开挖,即先挖掘初始巷道,设计巷道断面为三心拱、反底拱形式,接着进行锚杆超前支护,其中采用管缝式锚杆进行超前支护,超前支护锚杆1中的管缝式锚杆插入巷道外侧,然后进行锚网喷注初次支护,锚网喷注初次支护的施工顺序为:挂网,打注浆锚杆,喷浆,注浆,挂网即铺设钢筋网21,喷浆即在钢筋网21上制备初级混凝土层22,初次支护与二次支护间隔50~80m,二次支护的施工顺序为:挂网、喷浆、反底拱、打锚杆、打锚索、复喷;即在加强网32上喷射混凝土,接着进行反底拱施工,反底拱34采用U29型钢和C30混凝土制成,然后打锚杆,即安装施工强力锚杆33,接着打锚索,即安装施工预应力锚索37,最后进行复喷,即完成二次支护前,进行再次喷浆,形成复喷层36,复喷层36对锚索和注浆管进行保护,整个完整的支护方法可实现金属矿山井巷工程支护永久稳固性,提高巷道支护施工质量,降低巷道返修率,从而降低支护成本。
综上所述,本发明提出的一种用于地下矿山松软破碎岩体的巷道支护方法,适用于岩体弱风化、锤子敲击声哑、岩体强度值≤10Mpa的巷道支护工程,超前支护锚杆1沿巷道拱部布置,超前支护锚杆1中的管缝式锚杆向上倾斜10-15度,同时不同循环进尺施工的管缝式锚杆相互重叠,这样对松软岩体的支护效果更好,其中初始巷道设计巷道断面为三心拱、反底拱形式,接着进行锚杆超前支护,即超前支护锚杆1中的管缝式锚杆插入巷道外侧,然后进行锚网喷注初次支护,锚网喷注初次支护的施工顺序为:挂网,打注浆锚杆,喷浆,注浆,其中初次支护与二次支护间隔50~80m,同时在初次支护过程中进行注浆锚杆22的安装就可以保证了强度,无需额外安装钢拱架,节约了钢拱架的安装和拆卸工序,二次支护的施工顺序为:挂网、喷浆、反底拱、打锚杆、打锚索、复喷;整个完整的支护方法可实现金属矿山井巷工程支护永久稳固性,提高巷道支护施工质量,降低巷道返修率,从而降低支护成本。
需要说明的是,在本文中,诸如第一和第二等之类的关系术语仅仅用来将一个实体或者操作与另一个实体或操作区分开来,而不一定要求或者暗示这些实体或操作之间存在任何这种实际的关系或者顺序。而且,术语“包括”、“包含”或者其任何其他变体意在涵盖非排他性的包含,从而使得包括一系列要素的过程、方法、物品或者设备不仅包括那些要素,而且还包括没有明确列出的其他要素,或者是还包括为这种过程、方法、物品或者设备所固有的要素。
以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明披露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。

Claims (10)

1.一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,支护结构包括超前支护锚杆(1)、初次支护工件(2)和二次支护工件(3),所述初次支护工件(2)覆盖在超前支护锚杆(1)的外侧,超前支护锚杆(1)采用管缝式锚杆,初次支护工件(2)的外侧覆盖二次支护工件(3),初次支护工件(2)包括钢筋网(21)、注浆锚杆(22)和初级混凝土层(23),钢筋网(21)布置在巷道的侧壁上,巷道的侧壁和顶壁表面均喷射有初级混凝土层(23),注浆锚杆(22)垂直打入巷道岩体中,注浆锚杆(22)的尾端连接钢筋网(21),钢筋网(21)和注浆锚杆(22)均与初级混凝土层(23)接触,初级混凝土层(23)的外侧覆盖二次支护工件(3),所述二次支护工件(3)包括预应力锚索(31)、加强网(32)、强力锚杆(33)、反底拱(34)、二次混凝土层(35)和复喷层(36),预应力锚索(31)和强力锚杆(33)贯穿初次支护工件(2)并垂直打入巷道岩体中,加强网(32)预设在初次支护工件(2)的外侧,加强网(32)上喷射二次混凝土层(35),二次混凝土层(35)的底端安装反底拱(34),二次混凝土层(35)和反底拱(34)的外表面覆盖有一层复喷层(36),复喷层(36)还与强力锚杆(33)和预应力锚索(31)接触;
支护结构在支护时按照如下方法:
S1:巷道断面开挖,其中在挖掘巷道时需要预留变形距离,其中在净断面尺寸之上预留变形量为100mm,同时需要在净断面基础之上预留支护厚度150mm,设计巷道断面为三心拱、反底拱形式;
S2:锚杆超前支护,其中采用管缝式锚杆进行超前支护,先预制直径40mm长度2500mm的管缝式锚杆,然后超前支护锚杆(1)中的管缝式锚杆插入巷道顶板拱部,插入巷道顶板1.5m,外露1m,每个循环进尺不超过1m,外露部分保护人员在其下方安全作业;
S3:锚网喷注初次支护,初次支护的施工顺序为:挂网,打注浆锚杆,喷浆,注浆;
a挂网,即铺设钢筋网(21),钢筋网(21)采用Φ6mm钢筋焊接制成,相邻的两块钢筋网(21)相互搭接,两块钢筋网(21)的搭接长度100mm,相邻的两块钢筋网(21)搭接处用双股12#铁丝双股双排扣绑扎连接,钢筋网(21)的搭接处必须利用锚杆压紧;
b打注浆锚杆,其中锚杆采用注浆锚杆(22)支护工艺,注浆锚杆(22)采用Φ22mm×2200mm无缝钢管滚丝制作,注浆锚杆(22)的杆尾制作成麻花状,注浆锚杆(22)既用作注浆又作为锚杆使用,锚杆间排距800mm×800mm;
c喷浆,即在钢筋网(21)上制备初级混凝土层(23),其中初级混凝土层(23)的强度等级为C25,初级混凝土层(23)中的水泥、水、沙子的配合比为1:2:2,同时在制备混凝土泥浆时掺入总质量3~5%的速凝剂,初级混凝土层(23)厚度为50mm,初级混凝土层(23)覆盖锚杆托盘;
d注浆,注浆采用单液水泥-水玻璃浆液,水泥使用42.5级普通硅酸盐水泥,水灰比控制在0.8~1.0左右,水玻璃的掺量为水泥用量的3~5%。浆液结石率不低于92%,浆液固结体强度不低于20MPa,注浆压力控制在2.0MPa以内;
S4:二次支护,初次支护与二次支护间隔50~80m,二次支护的施工顺序为:挂网、喷浆、反底拱、打锚杆、打锚索、复喷;
a挂网,其中加强网(32)预设在初次支护工件(2)的外侧,相邻的两块加强网(32)相互搭接,相邻的两块加强网(32)搭接处用双股12#铁丝双股双排扣绑扎连接;
b喷浆,即在加强网(32)上喷射混凝土,加强网(32)固定完毕后喷射制成二次混凝土层(35),二次混凝土层(35)的厚度为70mm、二次混凝土层(35)的强度等级为C25;
c反底拱,反底拱(34)采用U29型钢和C30混凝土制成,即在弯曲的U29型钢上铺设C30混凝土,C30混凝土表面平整,反底拱(34)的最大厚度为500mm,U29型钢的排距为1000mm,反底拱(34)的U29型钢与上部型钢相连形成封闭结构,结构更加稳定,保证整体支护效果;
d打锚杆,即安装施工强力锚杆(33),强力锚杆(33)采用牌号为BHRB500的高性能螺纹钢锚杆,高性能螺纹钢锚杆的规格为Φ20mm×2200mm,间排距为800mm×800mm,锚杆孔直径为Φ28mm;
e打锚索,即安装施工预应力锚索(31),预应力锚索(31)采用1×19股高强度低松弛预应力钢绞线制作,为拉压分散型预应力锚索;锚索直径为Φ22mm,长度为6000mm;孔径为Φ28mm;
f复喷,即完成二次支护前,进行再次喷浆,形成复喷层(36),复喷层(36)对锚索和注浆管进行保护,复喷层(36)的混凝土强度和配合比与二次混凝土层(35)相同,复喷层(36)的厚度值为30mm。
2.根据权利要求1所述的一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,所述超前支护锚杆(1)中的管缝式锚杆采用1m/进尺设计,每个循环均进行锚杆超前支护,管缝式锚杆全长2.5m,每个循环进尺重叠长度为1.5m。
3.根据权利要求4所述的一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,所述超前支护锚杆(1)中的管缝式锚杆沿巷道拱部布置,管缝式锚杆间距300mm,其中管缝式锚杆斜向上插入,倾斜角度10~15°。
4.根据权利要求1所述的一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,所述钢筋网(21)和加强网(32)的网格规格均为100mm×100mm。
5.根据权利要求1所述的一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,所述反底拱(34)的上表面铺设喷射混凝土回弹料制成的垫层,反底拱(34)的下方铺设有采用单层Φ6mm钢筋焊接而成的经纬网,相邻经纬网的搭接长度大于200mm。
6.根据权利要求1所述的一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,所述注浆锚杆(22)安装时采用1卷Z2330型树脂药卷临时锚固,预紧力矩不低于300N·m,托盘采用拱型高强度托盘,规格为150mm×150mm×12mm,。
7.根据权利要求1所述的一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,所述强力锚杆(33)安装时采用1卷Z2350型和1卷K2350型树脂药卷加长锚固,锚固力不低于110kN,预紧力矩不低于300N·m,托盘采用拱型高强度托盘,规格为150mm×150mm×12mm,每根锚杆安装一个让压管,强力锚杆(33)安装时,顶板及两帮锚杆应通过钢筋梯连接,钢筋梯采用Φ14mm的钢筋焊接而成,钢筋梯3片,钢筋梯的尺寸为2400mm×80mm。
8.根据权利要求1所述的一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,所述预应力锚索(31)沿巷道拱部布置3根,预应力锚索(31)的间排距为800mm×1600mm,预应力锚索(31)的长度值大于注浆锚杆(22)与强力锚杆(33)的长度值。
9.根据权利要求1所述的一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,所述预应力锚索(31)安装时采用1卷快速K2350和2卷中速Z2350型树脂药卷加长锚固,其极限承载力为607kN,伸长率为7%,预应力锚索(31)采用高强度可调心托盘和专用锚具与设备进行张拉、固定和切割,预应力锚索(31)的预应力不低于150kN。
10.根据权利要求1所述的一种用于地下矿山松软破碎岩体的巷道支护方法,其特征在于,所述初次支护工件(2)中的锚网喷注初次支护施工要求在前探梁防护下作业。
CN202110399667.3A 2021-04-14 2021-04-14 一种用于地下矿山松软破碎岩体的巷道支护方法 Active CN113090284B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110399667.3A CN113090284B (zh) 2021-04-14 2021-04-14 一种用于地下矿山松软破碎岩体的巷道支护方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110399667.3A CN113090284B (zh) 2021-04-14 2021-04-14 一种用于地下矿山松软破碎岩体的巷道支护方法

Publications (2)

Publication Number Publication Date
CN113090284A true CN113090284A (zh) 2021-07-09
CN113090284B CN113090284B (zh) 2022-08-16

Family

ID=76677361

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110399667.3A Active CN113090284B (zh) 2021-04-14 2021-04-14 一种用于地下矿山松软破碎岩体的巷道支护方法

Country Status (1)

Country Link
CN (1) CN113090284B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113339031A (zh) * 2021-07-22 2021-09-03 内蒙古上海庙矿业有限责任公司 极软地层条件下巷道支护工艺系统及施工方法
CN113790066A (zh) * 2021-09-15 2021-12-14 中国恩菲工程技术有限公司 高应力碎岩巷道卸压支护系统和方法
CN116220740A (zh) * 2023-03-02 2023-06-06 云南省交通规划设计研究院有限公司 一种无中导连拱隧道后行洞的横向超前支护设计方法
CN117145524A (zh) * 2023-10-31 2023-12-01 华侨大学 一种大断面分岔隧道开挖中夹岩支护装置及使用方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1218125A1 (ru) * 1984-10-23 1986-03-15 Специальное конструкторско-технологическое бюро Института геотехнической механики АН УССР Способ возведени армопородобетонной блочной крепи
JP2007321490A (ja) * 2006-06-02 2007-12-13 Shimizu Corp トンネル掘削方法
CN101906975A (zh) * 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道下穿铁路的支护结构及其施工方法
CN105178981A (zh) * 2015-09-30 2015-12-23 中国矿业大学 破碎软岩巷道全断面封闭式深浅耦合让压锚注支护方法
CN205387940U (zh) * 2016-03-23 2016-07-20 山东科技大学 一种复合式软岩巷道支护体系
CN110985049A (zh) * 2019-11-29 2020-04-10 西北矿冶研究院 一种穿越软弱千枚岩逆断层的巷道支护方法
CN111794791A (zh) * 2020-08-19 2020-10-20 龙口矿业集团有限公司 一种软岩破碎巷道无骨灌注支护方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1218125A1 (ru) * 1984-10-23 1986-03-15 Специальное конструкторско-технологическое бюро Института геотехнической механики АН УССР Способ возведени армопородобетонной блочной крепи
JP2007321490A (ja) * 2006-06-02 2007-12-13 Shimizu Corp トンネル掘削方法
CN101906975A (zh) * 2010-08-09 2010-12-08 中铁第一勘察设计院集团有限公司 一种特大断面黄土隧道下穿铁路的支护结构及其施工方法
CN105178981A (zh) * 2015-09-30 2015-12-23 中国矿业大学 破碎软岩巷道全断面封闭式深浅耦合让压锚注支护方法
CN205387940U (zh) * 2016-03-23 2016-07-20 山东科技大学 一种复合式软岩巷道支护体系
CN110985049A (zh) * 2019-11-29 2020-04-10 西北矿冶研究院 一种穿越软弱千枚岩逆断层的巷道支护方法
CN111794791A (zh) * 2020-08-19 2020-10-20 龙口矿业集团有限公司 一种软岩破碎巷道无骨灌注支护方法

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113339031A (zh) * 2021-07-22 2021-09-03 内蒙古上海庙矿业有限责任公司 极软地层条件下巷道支护工艺系统及施工方法
CN113790066A (zh) * 2021-09-15 2021-12-14 中国恩菲工程技术有限公司 高应力碎岩巷道卸压支护系统和方法
CN116220740A (zh) * 2023-03-02 2023-06-06 云南省交通规划设计研究院有限公司 一种无中导连拱隧道后行洞的横向超前支护设计方法
CN116220740B (zh) * 2023-03-02 2023-10-27 云南省交通规划设计研究院有限公司 一种无中导连拱隧道后行洞的横向超前支护设计方法
CN117145524A (zh) * 2023-10-31 2023-12-01 华侨大学 一种大断面分岔隧道开挖中夹岩支护装置及使用方法

Also Published As

Publication number Publication date
CN113090284B (zh) 2022-08-16

Similar Documents

Publication Publication Date Title
CN113090284B (zh) 一种用于地下矿山松软破碎岩体的巷道支护方法
CN110005434B (zh) 一种软岩隧道围岩大变形灾害的恒阻大变形锚索控制方法
CN109372556B (zh) 一种适于高应力软岩隧巷道围岩支护的夹心拱及施工方法
CN205117366U (zh) 一种大断面松软破碎煤巷双承压拱支护装置
CN103603676B (zh) 一种电耙巷道支护方法
CN108316941B (zh) 一种破碎围岩及软岩巷道u型钢套棚支护方法
CN105040712B (zh) 一种软硬破碎互层式复合岩质边坡高压冲洗植锚回灌综合生态防护结构及其施工方法
CN108005675A (zh) 一种断层破碎带巷道的动态迭加耦合支护方法及支护结构
CN102852528A (zh) 一种反底拱锚固梁控制底鼓的方法
CN106593467A (zh) 一种煤矿井下软岩巷道支护方法
CN106523003A (zh) 一种适于深部开采巷道的刚柔耦合吸能支护技术
CN102562093A (zh) 全长锚固密集型树脂锚杆喷锚网支护方法
CN108930543A (zh) 一种大断面沿空掘巷耦合支护结构及施工方法
CN104533483A (zh) 一种巷道全空间预应力桁架锚索锚杆协同支护方法
CN113062760A (zh) 一种基于让压锚索的隧道支护方法
CN102425422A (zh) 主巷不间断运输条件下全煤特大断面交岔硐室施工方法
CN110645018B (zh) 矿井下强动压巷道预应力锚充一体化支护结构及方法
CN111411978A (zh) 相邻出矿巷道夹板式支护结构及其施工工艺
CN204875812U (zh) 一种软硬破碎互层式复合岩质边坡高压冲洗植锚回灌综合生态防护结构
CN106761867A (zh) 急倾斜回采巷道围岩稳定支护设施及支护工艺
CN116641724B (zh) 一种深埋软岩巷道高预应力恒阻锚杆和锚索协同控制方法
CN103982197B (zh) 一种深部巷道非连续双壳加固方法
CN111691895A (zh) 软碎移动大偏压湿润炭质页岩隧道柔硬双层初支开挖方法
CN210483744U (zh) 一种适用于大变形软岩隧道的自适应复合衬砌结构
CN111022086A (zh) 一种巷道工程支护用单层拱架及其快速支护方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20231010

Address after: 243000 No. 666 Xitang Road, Ma'anshan Economic Development Zone, Anhui Province

Patentee after: MAANSHAN Mine Research Institute Co.,Ltd.

Patentee after: HUAWEI METAL MINERAL RESOURCE EFFICIENT RECYCLING UTILIZATION NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Address before: 243000 No. 666 Xitang Road, Ma'anshan Economic Development Zone, Anhui Province

Patentee before: MAANSHAN Mine Research Institute Co.,Ltd.

Patentee before: HUAWEI METAL MINERAL RESOURCE EFFICIENT RECYCLING UTILIZATION NATIONAL ENGINEERING RESEARCH CENTER Co.,Ltd.

Patentee before: Sinosteel Nanjing Huaxin Technology Co.,Ltd.