CN113073678A - Construction method for embedded bolt sleeve of upper structure of turbine generator base - Google Patents

Construction method for embedded bolt sleeve of upper structure of turbine generator base Download PDF

Info

Publication number
CN113073678A
CN113073678A CN202110423823.5A CN202110423823A CN113073678A CN 113073678 A CN113073678 A CN 113073678A CN 202110423823 A CN202110423823 A CN 202110423823A CN 113073678 A CN113073678 A CN 113073678A
Authority
CN
China
Prior art keywords
embedded
fixing frame
construction method
concrete
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110423823.5A
Other languages
Chinese (zh)
Inventor
卢志杰
刘根深
王鹏
肖杨
马丽
邢孔斌
王梦夏
李跃
陈凯
陈力舟
王永
李志强
江海勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction First Group Corp Ltd
China Construction First Bureau Group South China Construction Co Ltd
Original Assignee
China Construction First Group Corp Ltd
China Construction First Bureau Group South China Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction First Group Corp Ltd, China Construction First Bureau Group South China Construction Co Ltd filed Critical China Construction First Group Corp Ltd
Priority to CN202110423823.5A priority Critical patent/CN113073678A/en
Publication of CN113073678A publication Critical patent/CN113073678A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/44Foundations for machines, engines or ordnance
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • E04G21/06Solidifying concrete, e.g. by application of vacuum before hardening
    • E04G21/08Internal vibrators, e.g. needle vibrators
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • E04G21/122Machines for joining reinforcing bars
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/12Mounting of reinforcing inserts; Prestressing
    • E04G21/122Machines for joining reinforcing bars
    • E04G21/123Wire twisting tools

Abstract

The invention discloses a construction method of an embedded bolt sleeve of an upper structure of a base of a steam turbine generator, which comprises the following steps: s1, pre-burying a fixing frame; s2, measuring and lofting; s3, mounting the embedded sleeve and the bolt; s4, binding steel bars; s5, setting a scaffold and a template; and S6, pouring concrete. The construction method for the embedded bolt sleeve of the upper structure of the turbine generator base is reasonable in arrangement, and effectively improves the installation precision of the turbine generator base; the embedded fixing frame is arranged, so that parallel operation of embedding and civil engineering is realized, and the overall construction efficiency is improved; in addition, the problem of quick installation of the casing is solved, the problem of the rigid casing floating pipe is controlled, and the method has good popularization value.

Description

Construction method for embedded bolt sleeve of upper structure of turbine generator base
Technical Field
The invention belongs to the technical field of constructional engineering, and relates to a construction method of an embedded bolt sleeve of an upper structure of a base of a steam turbine generator.
Background
The embedded part is a member embedded in hidden engineering in advance, namely a structure part which is installed in advance when the structure is poured with concrete and mainly serves as a connecting piece or a lap joint part in the subsequent construction process. By adopting the embedded part, the operation of secondary construction for installing the structural part on the concrete wall body in the later stage can be reduced, so that the efficiency of installing and fixing the external engineering equipment foundation is improved.
The turbine generator base is an important part of the power generation base, and the fixing precision of the turbine generator base is important. How to improve the accuracy of its fixation is always a problem to be solved by the skilled person. In addition, the construction of the embedded part conflicts with the civil engineering construction, and the construction needs to be carried out respectively in the prior art, so that the overall progress of project construction is influenced to a certain extent.
Therefore, a construction method for embedding a bolt sleeve in an upper structure of a base of a steam turbine generator is needed to solve the technical problems in the prior art.
Disclosure of Invention
The invention aims to solve at least part of technical problems in the prior art to a certain extent, and provides a construction method for embedding a bolt sleeve in an upper structure of a base of a turbonator, which is reasonable in arrangement and effectively improves the installation precision of the base of the turbonator; the embedded fixing frame is arranged, so that parallel operation of embedding and civil engineering is realized, and the overall construction efficiency is improved; in addition, the problem of quick installation of the casing is solved, the problem of the rigid casing floating pipe is controlled, and the method has good popularization value.
In order to solve the technical problem, the invention provides a construction method of an embedded bolt sleeve of an upper structure of a base of a steam turbine generator, which comprises the following steps:
s1, pre-embedding a fixing frame: avoiding the position of an electrical buried pipe according to the principle of proximity of foundation bolts and sleeves, and arranging a pre-buried fixing frame; the embedded fixing frame comprises an upright post, a cross beam and a longitudinal beam, and the upright post, the cross beam and the longitudinal beam form a rectangular structure;
s2, measuring and lofting: paying off a steam turbine generator base through a square grid control point by using a total station, and determining an axis, a center line and a column line for installing the steam turbine generator base;
s3, installing the embedded sleeve and the bolt: fixing the embedded sleeve and the bolt in an embedded mode before concrete pouring is carried out on the running layer of the turbonator;
s4, binding steel bars: arranging a steel bar platform around the running layer of the turbonator, and binding steel bars on the cross beam and the longitudinal beam of the pre-embedded fixing frame;
s5, setting the scaffold and the template: arranging a scaffold for a turbine generator base, installing a concrete pouring template, and reserving a gap between the template and a beam body to prevent the template from being exploded;
s6, pouring concrete: and (3) pouring concrete along the longitudinal beam direction of the pre-embedded fixing frame, uniformly discharging materials around the bolts, and keeping the distance between the vibrating rod and the bolts to be 150-200 mm during concrete vibrating operation.
In step S1, in a preferred embodiment, No. 14 channel steel is selected as the upright, the cross beam and the longitudinal beam.
In step S2, in a preferred embodiment, the beam and the longitudinal beam of the pre-buried fixing frame are wired, and the mounting positions of the pre-buried sleeve and the bolt are determined.
As a preferred embodiment, the position of the opening is determined by measuring and setting out the pre-embedded fixing frame, and the pre-embedded fixing frame is provided with a through hole; the embedded sleeve is fixed through the through hole, adjusting bolts are arranged on the outer peripheral side of the embedded sleeve, and the adjusting bolts are uniformly distributed along the center of the embedded sleeve and are located on the upper side of the embedded fixing frame.
In step S5, the template is a black template, and the gap between the template and the beam is 10mm-20 mm.
In step S6, concrete is poured in layers, and the height of each concrete layer is 300mm-500 mm.
In step S6, the concrete is vibrated by using an insertion vibrator, which is vertically constructed to prevent the embedded fixing frame from being deviated.
As a preferred embodiment, the position of the sleeve is compounded and embedded before the steel bars are bound.
As a preferred embodiment, the position of the embedded casing is rechecked before the concrete pouring construction.
As a preferred embodiment, in step S3, the embedded casing is reinforced by a reinforcing channel and a wood cake, the wood cake is disposed at the bottom of the embedded casing, and the reinforcing channel is perpendicular to the embedded casing and located at the upper portion of the embedded casing.
The invention has the beneficial effects that:
the construction method for the embedded bolt sleeve of the upper structure of the turbine generator base is reasonable in arrangement, and effectively improves the installation precision of the turbine generator base; the embedded fixing frame is arranged, so that parallel operation of embedding and civil engineering is realized, and the overall construction efficiency is improved; in addition, the problem of quick installation of the casing is solved, the problem of the rigid casing floating pipe is controlled, and the method has good popularization value.
Drawings
The above advantages of the present invention will become more apparent and more readily appreciated from the detailed description set forth below when taken in conjunction with the drawings, which are intended to be illustrative, not limiting, of the invention and in which:
FIG. 1 is a flow chart of a construction method for embedding a bolt sleeve in an upper structure of a base of a steam turbine generator according to the present invention;
fig. 2 is a schematic view of the pre-buried fixing frame of the present invention.
Detailed Description
Fig. 1 to fig. 2 are schematic diagrams related to a construction method of an embedded bolt sleeve of a superstructure of a turbine generator base according to the present application, and the present invention will be described in detail below with reference to specific embodiments and the accompanying drawings.
The examples described herein are specific embodiments of the present invention, are intended to be illustrative and exemplary in nature, and are not to be construed as limiting the scope of the invention. In addition to the embodiments described herein, those skilled in the art will be able to employ other technical solutions which are obvious based on the disclosure of the claims and the specification of the present application, and these technical solutions include technical solutions which make any obvious replacement or modification for the embodiments described herein.
The drawings in the present specification are schematic views to assist in explaining the concept of the present invention, and schematically show the shapes of respective portions and their mutual relationships. It is noted that the drawings are not necessarily to the same scale so as to clearly illustrate the structures of the various elements of the embodiments of the invention. Like reference numerals are used to denote like parts.
The invention relates to a flow chart of a construction method of an embedded bolt sleeve of an upper structure of a base of a steam turbine generator, which is shown in figure 1. The construction method of the embedded bolt sleeve of the upper structure of the turbine generator base comprises the following steps:
s1, pre-embedding a fixing frame: according to the principle of the foundation bolt and the sleeve close to each other, avoiding the position of an electrical buried pipe, and arranging a pre-buried fixing frame 10 as shown in figure 1; the embedded fixing frame comprises an upright post, a cross beam and a longitudinal beam, and the upright post, the cross beam and the longitudinal beam form a rectangular structure;
in step S1, the column, the cross beam, and the side member select channel 14. The supporting plate is embedded at the side of the beam, the beam surface can be fixed by a template reinforcing system or a scaffold, and embedded pipes in various beams can be reinforced by angle iron and reinforcing steel bars.
S2, measuring and lofting: paying off a steam turbine generator base through a square grid control point by using a total station, and determining an axis, a center line and a column line for installing the steam turbine generator base;
in step S2, the beams and the longitudinal beams of the embedded fixing frame are paid off, and the mounting positions of the embedded sleeves and the bolts are determined. Specifically, 4 axes of the turbonator base, the turbonator center line and 2 transverse column lines are released by the total station in a grid control point mode. The axis is compounded with the bottom plate line and can be used as a datum line for the construction of the basic upper structure of the turbonator after being qualified through four-stage acceptance. And the elevation of each layer is measured by utilizing a level gauge to obtain the reference elevation of the upper structure of the turbonator on the adjacent building.
S3, installing the embedded sleeve and the bolt: before concrete pouring is carried out on the running layer of the turbonator, fixing the embedded sleeve 20 and the bolts shown in the figure 2 in an embedded mode;
as a preferred embodiment, the position of the opening is determined by measuring and setting out the pre-embedded fixing frame, and the pre-embedded fixing frame is provided with a through hole; the embedded sleeve is fixed through the through hole, adjusting bolts are arranged on the outer peripheral side of the embedded sleeve, and the adjusting bolts are uniformly distributed along the center of the embedded sleeve and are located on the upper side of the embedded fixing frame.
In step S3, the embedded casing is reinforced by using a reinforcing channel steel and a wood cake, the wood cake is disposed at the bottom of the embedded casing, and the reinforcing channel steel is perpendicular to the embedded casing and located at the upper portion of the embedded casing. Here, the wood cake may be referred to as wood cake for short.
The reinforcing step of the embedded sleeve comprises the following steps: after the center of the embedded pipe is released from the die surface of the beam bottom, a wood cake is processed in advance by a wood plate with the thickness of 18mm, the wood cake is 1mm smaller than the embedded sleeve, a hole is drilled in the middle of the wood cake, a bolt of M12 is adopted to connect the double-layer wood cake with the die plate, the height of the double-layer wood cake is 36mm, the wood cake is directly sleeved on the base of the embedded sleeve, after the upper part of the embedded sleeve passes through the reinforced channel steel, the upper part of the embedded sleeve is propped against the embedded sleeve by adjusting bolts welded on the periphery of the steel beam after the central line and the elevation are adjusted, meanwhile, two phi 25 steel bars are respectively adopted to reinforce the embedded sleeve from the lower part and the middle of the.
The perpendicularity of the embedded sleeve can be corrected according to the hanging hammer and the adjusting bolt at the top of the fine-tuning sleeve. In order to prevent the concrete from flowing into the embedded sleeve in the concrete pouring process, the gap between the embedded sleeve and the wood handle can be filled with hemp velvet.
S4, binding steel bars: arranging a steel bar platform around the running layer of the turbonator, and binding steel bars on the cross beam and the longitudinal beam of the pre-embedded fixing frame;
the steam turbine generator base operation layer roof beam reinforcing bar is 360 tons totally, and the reinforcing bar volume is big and complicated, for the convenience of the interlude of roof beam reinforcing bar, sets up the reinforcing bar platform all around at steam turbine generator operation layer, is connected with operation layer outer scaffold frame, and the platform height flushes with the bottom of the roof beam. After the embedded parts, the embedded sleeves and the foundation parts are embedded well and retested to be correct, the reinforcing steel bars are inserted, the longitudinal beams are firstly arranged and then the cross beams are arranged,
and (3) binding the longitudinal beams, namely preparing a steel bar support frame on the paved beam bottom, welding the support frame by using deformed steel bars with the diameter of 32, and placing three times at each step, wherein the height of the support frame is equal to the level of the bottom layer steel bars on the beam surface. At the moment, gluten starts to penetrate, and when the upright column is reinforced by bolts, corresponding holes are formed in the steel column and then reinforcing steel bars penetrate. When large embedded sleeves are encountered, the reinforcing steel bars can be wound in an arc shape, and the reinforcing steel bars cannot be broken and then welded. After the gluten is penetrated, the hoop is sleeved, and finally the bottom rib is penetrated and the binding wire is bound.
The binding method of the cross beam is the same as that of the longitudinal beam. After the reinforcing steel bars of all the beams are bound, adjusting the bolts again, embedding the sleeves, and binding the reinforcing steel bars of the grouting layer after retesting without errors.
S5, setting the scaffold and the template: arranging a scaffold for a turbine generator base, installing a concrete pouring template, and reserving a gap between the template and a beam body to prevent the template from being exploded;
in step S5, the template is a black template, and the reserved gap between the template and the beam body is 10-20 mm.
S6, pouring concrete: and (3) pouring concrete along the longitudinal beam direction of the pre-embedded fixing frame, uniformly discharging materials around the bolts, and keeping the distance between the vibrating rod and the bolts to be 150-200 mm during concrete vibrating operation.
In step S6, concrete is poured in layers, and the height of each concrete layer is 300mm-500 mm.
In step S6, the concrete is vibrated by using an insertion vibrator, and the insertion vibrator is vertically constructed to prevent the embedded fixing frame from deviating.
And (4) rechecking the positions of the embedded sleeves before concrete pouring construction.
The concrete is poured by adopting three vehicle-mounted towing pumps (one is arranged for standby use) to convey the concrete into a warehouse, and the conveying strength is about 40-50 m per hour36-7 agitating trucks are needed for transportation, preferably two trucks are needed for standby. To ensure the continuous concrete pouring work.
Because the thrust of the pump is very big, can exert an influence to whole skeleton when pouring, so set up the pouring platform in the department of roughly 300mm on the whole operation layer reinforcing bar face, the framed bent is double, lean on the one row of roof beam outside with the help of the outer framed bent pole that has set up on the spot, the one row of pole setting of roof beam inboard rises by interior framed bent, and then by big horizontal bar vertical connection, at last horizontal connection.
The construction sequence of pouring concrete is as follows: starting from one end, advancing in the direction of the stringer. The concrete is vibrated by adopting an inserted vibrator, the column beam plate concrete is poured in layers strictly according to the layering thickness of about 300-500 mm, the insertion points are uniformly arranged and move point by point, the vibration point interval is less than or equal to 1.5R, the vibration time is controlled to be about 15-20 seconds, and the concrete is prevented from approaching a template and a sleeve to prevent deformation and displacement.
In order to avoid the deviation of the embedded part caused by the flowing and the vibration of the concrete in the concrete pouring process, the embedded part is reinforced stably, and meanwhile, the material is uniformly discharged around the bolt as much as possible, so that the concrete surface around the bolt gradually rises, and the overlarge height difference is avoided. When the concrete is vibrated, the distance of 150-200 mm is kept between the vibrating spear and the bolt. The concrete vibrators are symmetrically and vertically inserted to avoid displacement or deflection caused by collision of the bolts and the fixed frame.
In the concrete pouring process of the running layer of the turbonator, professional measuring personnel are dispatched to observe the height change conditions of the embedded bolt sleeve and the top surface embedded part with shifts, problems are found in time, measures are taken in time, and therefore the accuracy of the embedded bolt sleeve is guaranteed to meet the standard requirements. Meanwhile, the elevation of the top concrete of the running layer is strictly controlled, and the deviation of the top concrete is ensured to meet the standard requirements of design and construction specifications.
In the heat preservation and moisture preservation maintenance of the large-volume concrete, the inner surface temperature, the top surface temperature and the bottom surface temperature of the concrete and the outdoor temperature are monitored, corresponding adjustment is made to the maintenance measures according to the monitoring result, and the requirement of temperature control indexes is ensured.
Compared with the defects and shortcomings of the prior art, the construction method for the embedded bolt sleeve of the upper structure of the turbine generator base is reasonable in arrangement, and installation accuracy of the turbine generator base is effectively improved; the embedded fixing frame is arranged, so that parallel operation of embedding and civil engineering is realized, and the overall construction efficiency is improved; in addition, the problem of quick installation of the casing is solved, the problem of the rigid casing floating pipe is controlled, and the method has good popularization value.
The present invention is not limited to the above embodiments, and any other products in various forms can be obtained by the teaching of the present invention, but any changes in the shape or structure thereof, which are the same as or similar to the technical solutions of the present invention, fall within the protection scope of the present invention.

Claims (10)

1. A construction method for embedding bolt sleeves in an upper structure of a base of a steam turbine generator is characterized by comprising the following steps:
s1, pre-embedding a fixing frame: avoiding the position of an electrical buried pipe according to the principle of proximity of foundation bolts and sleeves, and arranging a pre-buried fixing frame; the embedded fixing frame comprises an upright post, a cross beam and a longitudinal beam, and the upright post, the cross beam and the longitudinal beam form a rectangular structure;
s2, measuring and lofting: paying off a steam turbine generator base through a square grid control point by using a total station, and determining an axis, a center line and a column line for installing the steam turbine generator base;
s3, installing the embedded sleeve and the bolt: fixing the embedded sleeve and the bolt in an embedded mode before concrete pouring is carried out on the running layer of the turbonator;
s4, binding steel bars: arranging a steel bar platform around the running layer of the turbonator, and binding steel bars on the cross beam and the longitudinal beam of the pre-embedded fixing frame;
s5, setting the scaffold and the template: arranging a scaffold for a turbine generator base, installing a concrete pouring template, and reserving a gap between the template and a beam body to prevent the template from being exploded;
s6, pouring concrete: and (3) pouring concrete along the longitudinal beam direction of the pre-embedded fixing frame, uniformly discharging materials around the bolts, and keeping the distance between the vibrating rod and the bolts to be 150-200 mm during concrete vibrating operation.
2. The construction method according to claim 1, wherein in step S1, channel 14 is selected as the columns, beams and stringers.
3. The construction method according to claim 2, wherein in step S2, the beam and the longitudinal beam of the pre-buried fixing frame are extended to determine the installation positions of the pre-buried sleeve and the bolt.
4. The construction method according to claim 1, wherein the position of the opening is determined by measuring and setting out the pre-buried fixing frame, and the pre-buried fixing frame is provided with a through hole; the embedded sleeve is fixed through the through hole, adjusting bolts are arranged on the outer peripheral side of the embedded sleeve, and the adjusting bolts are uniformly distributed along the center of the embedded sleeve and are located on the upper side of the embedded fixing frame.
5. The construction method according to claim 1, wherein in step S5, the form is a black form, and the reserved gap between the form and the beam body is 10mm-20 mm.
6. The construction method according to claim 1, wherein the concrete is cast in layers in step S6, and the height of each concrete layer is 300mm-500 mm.
7. The construction method according to claim 1, wherein the concrete is vibrated by using an insertion vibrator which is vertically constructed to prevent the pre-buried fixing frame from being deviated at step S6.
8. The construction method according to claim 1, wherein the position of the composite embedded sleeve is before the binding of the reinforcing bars.
9. The construction method according to claim 1, wherein the position of the embedded sleeve is rechecked before the concrete pouring construction.
10. The construction method according to claim 1, wherein in step S3, the embedded casing is reinforced by a reinforcing channel and a wood cake, the wood cake is disposed at the bottom of the embedded casing, and the reinforcing channel is perpendicular to the embedded casing and located at the upper portion of the embedded casing.
CN202110423823.5A 2021-04-20 2021-04-20 Construction method for embedded bolt sleeve of upper structure of turbine generator base Pending CN113073678A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110423823.5A CN113073678A (en) 2021-04-20 2021-04-20 Construction method for embedded bolt sleeve of upper structure of turbine generator base

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110423823.5A CN113073678A (en) 2021-04-20 2021-04-20 Construction method for embedded bolt sleeve of upper structure of turbine generator base

Publications (1)

Publication Number Publication Date
CN113073678A true CN113073678A (en) 2021-07-06

Family

ID=76618346

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110423823.5A Pending CN113073678A (en) 2021-04-20 2021-04-20 Construction method for embedded bolt sleeve of upper structure of turbine generator base

Country Status (1)

Country Link
CN (1) CN113073678A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114134927A (en) * 2021-12-03 2022-03-04 山东方大工程有限责任公司 Device and method for embedding large power equipment foundation embedded pipe

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004332395A (en) * 2003-05-08 2004-11-25 Tomisu:Kk Embedded casing
CN101575875A (en) * 2009-06-09 2009-11-11 中天建设集团有限公司天津分公司 Construction method of cantilever steel girder
CN203348837U (en) * 2013-06-17 2013-12-18 中国能源建设集团广东省电力第一工程局 Reinforcing frame structure of embedded bolts of steamer engine base
CN111550054A (en) * 2020-04-03 2020-08-18 中交二航局市政建设有限公司 Construction method for ensuring quality of concrete around embedded large-diameter steel sleeve

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004332395A (en) * 2003-05-08 2004-11-25 Tomisu:Kk Embedded casing
CN101575875A (en) * 2009-06-09 2009-11-11 中天建设集团有限公司天津分公司 Construction method of cantilever steel girder
CN203348837U (en) * 2013-06-17 2013-12-18 中国能源建设集团广东省电力第一工程局 Reinforcing frame structure of embedded bolts of steamer engine base
CN111550054A (en) * 2020-04-03 2020-08-18 中交二航局市政建设有限公司 Construction method for ensuring quality of concrete around embedded large-diameter steel sleeve

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
刘小林等: "火电厂汽机基座预埋套管高精度安装工艺", 《电力建设》 *
刘齐君等: "火力发电厂汽轮发电机砼基础螺栓埋设工艺", 《科技咨询导报》 *
杨连志: "汽轮发电机基座螺栓套管及锚固板加固技术方案研讨", 《科技创业家》 *
楼海英: "大型汽轮发电机基础的施工关键技术探讨", 《武汉大学学报(工学版)》 *
王万刚: "汽轮机基座施工技术", 《四川建筑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114134927A (en) * 2021-12-03 2022-03-04 山东方大工程有限责任公司 Device and method for embedding large power equipment foundation embedded pipe

Similar Documents

Publication Publication Date Title
CN107090932B (en) Construction method of large-span thin-wall plane arch truss based on stiff ring beam
CN109763569B (en) Construction method of cantilever awning
CN101481902A (en) V type pier inclined leg combined type support for continuous rigid frame bridge and layered cast-in-situ construction method
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
CN115467421B (en) Hoisting construction method for complex large-span steel roof
CN110778116B (en) Construction method of complex curved surface giant concrete beam tube structure
CN206667063U (en) Prestressing force bellows altitude calibration system in a kind of bridge construction
CN111927088A (en) Construction process of aluminum alloy template for building construction
CN113073678A (en) Construction method for embedded bolt sleeve of upper structure of turbine generator base
CN114214917A (en) Steel pipe concrete tied arch bridge and construction method
CN112695898A (en) Construction method of steel structure embedded part capable of bearing large tension force and limited in space
CN112227817A (en) Construction method for casting circular herringbone column of cooling tower in sections
JP5033334B2 (en) Tower crane support method
CN212771968U (en) Full-prefabricated assembled bridge bearing platform positioning system
CN111927111B (en) Construction method of ultrahigh special-shaped outer frame steel structure
CN115012575A (en) Construction process for lifting hyperbolic square pipe truss roof of railway station house in blocks
CN210685474U (en) Concrete underpins structure
CN114182883A (en) Large-section square tube concrete column and construction method
CN112942809A (en) Combined template assembling method capable of realizing mechanical construction
CN108487295B (en) 4M compressor foundation integral pouring construction method
CN111501531A (en) Construction method of V-shaped thin-wall pier and 0# block main beam supporting system
CN206554273U (en) A kind of pre-assembled Anchor Bolts in Steel Column Bases structure
CN106498975B (en) Wet type paper machine room anchor bolt installation method
CN214785936U (en) Core tube structure-based auxiliary steel structure for climbing of creeping formwork
CN113216591B (en) Climbing formwork climbing auxiliary steel structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20210706

RJ01 Rejection of invention patent application after publication