CN113007039B - Wind power plant inertia response testing method and device - Google Patents
Wind power plant inertia response testing method and device Download PDFInfo
- Publication number
- CN113007039B CN113007039B CN202110293273.XA CN202110293273A CN113007039B CN 113007039 B CN113007039 B CN 113007039B CN 202110293273 A CN202110293273 A CN 202110293273A CN 113007039 B CN113007039 B CN 113007039B
- Authority
- CN
- China
- Prior art keywords
- power plant
- preset
- wind power
- wind
- alternating current
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F03—MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
- F03D—WIND MOTORS
- F03D17/00—Monitoring or testing of wind motors, e.g. diagnostics
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/38—Arrangements for parallely feeding a single network by two or more generators, converters or transformers
- H02J3/381—Dispersed generators
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2300/00—Systems for supplying or distributing electric power characterised by decentralized, dispersed, or local generation
- H02J2300/20—The dispersed energy generation being of renewable origin
- H02J2300/28—The renewable source being wind energy
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/70—Wind energy
- Y02E10/76—Power conversion electric or electronic aspects
Landscapes
- Engineering & Computer Science (AREA)
- Power Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Wind Motors (AREA)
Abstract
The invention provides a wind power plant inertia response testing method and device, wherein the method comprises the following steps: constructing a power system simulation model containing a wind power plant according to preset alternating current system parameters; initializing the simulation model according to a preset wind power plant active power control mode and a preset power level; carrying out a wind power plant inertia response simulation test on the initialized simulation model according to a group of preset alternating current system frequency change parameters to obtain a simulation result; judging whether the simulation result meets the preset requirement or not; if not, exiting the test process; if the set of the frequency variation parameters meets the preset requirement, acquiring a next set of preset alternating current system frequency variation parameters, performing a wind power plant inertia response simulation test on the initialized simulation model according to the next set of the frequency variation parameters, and returning to the step of judging whether the simulation result meets the preset requirement until all the preset alternating current system frequency variation parameter sets are used for simulation. The method can test the inertia response of the wind power plant with low cost and high efficiency.
Description
Technical Field
The invention relates to the technical field of wind power plant inertia response testing, in particular to a wind power plant inertia response testing method and device.
Background
With the larger and larger scale of the accessed wind power plant, the networking control function of the wind power plant is more and more important, and the inertia response is an important part of the wind power plant. At present, the condition of a large-scale wind power plant grid-related control performance physical test is not available, so that the inertia response of a wind turbine generator is difficult to test and evaluate, the wind power plant is difficult to access the performance of a power grid, and the safe operation of the power grid is difficult to maintain effectively.
Disclosure of Invention
The invention aims to provide a method and a device for testing the inertia response characteristic of a wind power plant, so that the inertia response effect of the wind power plant can be evaluated according to the test result, and the wind power plant can be connected to the performance of a power grid and the safe operation of the power grid can be maintained.
In a first aspect, an embodiment of the present invention provides a wind farm inertia response testing method, including:
s1, acquiring a set of preset alternating current system parameters, and constructing a power system simulation model containing a wind power plant according to the preset alternating current system parameters;
s2, initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level;
s3, acquiring a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized simulation model containing the wind power plant electric power system according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result;
s4, judging whether the wind power plant inertia response simulation result meets a preset requirement or not;
s5, if not, exiting the test process;
s6, if yes, judging whether all the preset alternating current system frequency change parameter sets are used for simulation;
and S7, if not, acquiring the next group of preset alternating current system frequency change parameters, performing a wind power plant inertia response simulation test on the initialized power system simulation model containing the wind power plant according to the next group of preset alternating current system frequency change parameters, and returning to the step of judging whether the wind power plant inertia response simulation result meets the preset requirements or not until all the preset alternating current system frequency change parameter groups are used for simulation.
Further, the wind farm inertia response testing method further includes:
if all the preset alternating current system frequency change parameter groups are used for simulation, judging whether all the preset wind power plant active power control modes and power levels are used for initializing the power system simulation model containing the wind power plant;
if not, acquiring a next preset wind power plant active power control mode and power level, initializing the power system simulation model containing the wind power plant according to the next preset wind power plant active power control mode and power level, returning to acquire a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized power system simulation model containing the wind power plant according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result until all preset wind power plant active power control modes and power levels are used for initializing the power system simulation model containing the wind power plant.
Further, the wind farm inertia response testing method further includes:
if all the preset active power control modes and power levels of the wind power plant are used for initializing the power system simulation model containing the wind power plant, judging whether all the sets of alternating current system parameters are used for constructing the power system simulation model containing the wind power plant;
if yes, exiting the test process;
if not, acquiring the next set of preset alternating current system parameters, constructing a power system simulation model containing the wind power plant according to the next set of preset alternating current system parameters, and returning to the step of initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level until all sets of alternating current system parameters are used for constructing the power system simulation model containing the wind power plant.
Further, the active power control mode of the wind power plant is a power limited mode or a power unlimited mode.
Further, initializing the power system simulation model including the wind farm according to a preset wind farm active power control mode and power level, specifically:
and initializing the power system simulation model containing the wind power plant according to the preset wind power plant active power control mode which is a power unlimited mode and the power level which is 0.2pu-0.3 pu.
Further, if all the preset alternating current system frequency change parameter sets are used for simulation, acquiring a next preset wind farm active power control mode and power level, initializing the power system simulation model including the wind farm according to the next preset wind farm active power control mode and power level, returning to acquire a group of preset alternating current system frequency change parameters, performing a wind farm inertia response simulation test on the initialized simulation model including the wind farm power system according to the group of preset alternating current system frequency change parameters, and acquiring a wind farm inertia response simulation result until all the preset wind farm active power control modes and power levels are used for initializing the power system simulation model including the wind farm, which specifically includes:
according to the steps S2-S7, a wind power plant inertia response test is completed, wherein the wind power plant active power control mode is a power unlimited mode, and the power level is 0.9pu-1.0 pu;
according to the steps S2-S7, the test of the wind power plant inertia response function is completed, wherein the wind power plant active power control mode is a power limited mode, and the power level is 0.2 pu;
according to the steps S2-S7, a wind power plant inertia response test with the wind power plant active power control mode being a power limited mode and the power level being 0.4pu is completed;
according to the steps S2-S7, a wind power plant inertia response test with the wind power plant active power control mode being a power limited mode and the power level being 0.6pu is completed;
and completing a wind power plant inertia response test with the wind power plant active power control mode being a power limited mode and the power level being 0.8pu according to the steps S2-S7.
Further, the evaluation indexes of the wind power plant inertia response simulation result include, but are not limited to, wind power plant active power output variation, active power output deviation, wind power plant active current, inertia response time and alternating current system frequency.
Further, the ac system parameters include system capacity and system impedance.
In a second aspect, an embodiment of the present invention provides a wind farm inertia response testing apparatus, including:
the model building module is used for obtaining a set of preset alternating current system parameters and building a power system simulation model containing a wind power plant according to the preset alternating current system parameters;
the initialization module is used for initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level;
the inertia response simulation test module is used for acquiring a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized simulation model containing the wind power plant electric power system according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result;
the first judgment module is used for judging whether the wind power plant inertia response simulation result meets a preset requirement or not;
the exit module is used for exiting the test flow if the test flow does not meet the requirement;
the second judgment module is used for judging whether all the preset alternating current system frequency change parameter groups are used for simulation if the preset alternating current system frequency change parameter groups are met;
and the return module is used for acquiring the next group of preset alternating current system frequency change parameters if the wind power plant inertia response simulation test is not performed on the initialized power system simulation model containing the wind power plant according to the next group of preset alternating current system frequency change parameters, and returning to the step of judging whether the wind power plant inertia response simulation result meets the preset requirement or not until all the preset alternating current system frequency change parameter groups are used for simulation.
Further, the wind farm inertia response testing device further comprises:
the second returning module is used for judging whether all the preset active power control modes and power levels of the wind power plant are used for initializing the power system simulation model containing the wind power plant if all the preset alternating current system frequency change parameter groups are used for simulation; if not, acquiring a next preset wind power plant active power control mode and power level, initializing the power system simulation model containing the wind power plant according to the next preset wind power plant active power control mode and power level, returning to acquire a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized power system simulation model containing the wind power plant according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result until all preset wind power plant active power control modes and power levels are used for initializing the power system simulation model containing the wind power plant.
Compared with the prior art, the wind power plant inertia response function evaluation method provided by the embodiment of the invention comprises the following steps: acquiring a set of preset alternating current system parameters, and constructing a power system simulation model containing a wind power plant according to the preset alternating current system parameters; initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level; acquiring a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized simulation model containing the wind power plant electric power system according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result; judging whether the wind power plant inertia response simulation result meets a preset requirement or not; if not, exiting the test process; if yes, judging whether all preset alternating current system frequency change parameter groups are used for simulation; if not, acquiring a next group of preset alternating current system frequency change parameters, performing a wind power plant inertia response simulation test on the initialized simulation model containing the wind power plant electric power system according to the next group of preset alternating current system frequency change parameters, and returning to the step of judging whether an inertia response simulation result meets preset requirements or not until all preset alternating current system frequency change parameter groups are used for simulation. Through the design, the wind power plant inertia response test device can test the wind power plant inertia response, and is further favorable for accessing the wind control electric field to the power grid performance and maintaining the safe operation of the power grid. In addition, the inertia response testing method is low in cost and high in efficiency.
Drawings
In order to more clearly illustrate the technical solution of the present invention, the drawings needed to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art that other drawings can be obtained according to the drawings without creative efforts.
FIG. 1 is a flow chart of a wind farm inertia response testing method according to an embodiment of the present invention;
FIG. 2 is a flow chart of a wind farm inertia response testing method according to another embodiment of the present invention;
fig. 3 is a schematic structural diagram of a wind farm inertia response testing apparatus according to an embodiment of the present invention.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It should be understood that the step numbers used herein are for convenience of description only and are not intended as limitations on the order in which the steps are performed.
It is to be understood that the terminology used in the description of the invention herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. As used in the specification of the present invention and the appended claims, the singular forms "a," "an," and "the" are intended to include the plural forms as well, unless the context clearly indicates otherwise.
The terms "comprises" and "comprising" indicate the presence of the described features, integers, steps, operations, elements, and/or components, but do not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components, and/or groups thereof.
The term "and/or" refers to and includes any and all possible combinations of one or more of the associated listed items.
Referring to fig. 1, an embodiment of the present invention provides a wind farm inertia response testing method, including:
s1, acquiring a set of preset alternating current system parameters, and constructing a power system simulation model containing a wind power plant according to the preset alternating current system parameters.
In the embodiment of the invention, it should be understood that a large number of parameters are needed for constructing the power system simulation model containing the wind farm, and the ac system parameters are only a small part of parameters in the power system simulation model containing the wind farm, and are especially important for the test method of the invention, so that a person skilled in the art can construct the model according to the common knowledge for constructing the power system containing the wind farm even though the invention does not list all the model construction parameters.
In the embodiment of the invention, the power system simulation model comprising the wind power plant is constructed on a hardware-in-loop real-time simulation platform. The alternating current system parameters are set according to the required preset parameters, such as system capacity and system impedance. The communication system can be in the form of an equivalent system or a detailed model.
And S2, initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level.
In the embodiment of the invention, the active power control mode of the wind power plant is a power limited mode or a power unlimited mode, the power level is set according to actual requirements, and the invention is not limited herein.
In the embodiment of the present invention, it should be noted that initializing the power system simulation model including the wind farm according to a preset wind farm active power control mode and a preset power level is to set an operating state of the wind farm in the simulation model.
S3, acquiring a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized simulation model containing the wind power plant electric power system according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result;
and S4, judging whether the wind power plant inertia response simulation result meets the preset requirement.
In the embodiment of the invention, the wind farm inertia response simulation result includes, but is not limited to, wind farm active power output variation, inertia response time, alternating current system frequency and the like.
S5, if not, exiting the test process;
s6, if yes, judging whether all the preset alternating current system frequency change parameter sets are used for simulation;
and S7, if not, acquiring the next group of preset alternating current system frequency change parameters, performing a wind power plant inertia response simulation test on the initialized power system simulation model containing the wind power plant according to the next group of preset alternating current system frequency change parameters, and returning to the step of judging whether the wind power plant inertia response simulation result meets the preset requirements or not until all the preset alternating current system frequency change parameter groups are used for simulation.
Compared with the prior art, the method can test the inertia response of the wind power plant, and is further favorable for accessing the wind power plant to the performance of the power grid and maintaining the safe operation of the power grid. In addition, the inertia response testing method provided by the invention has the advantages of low cost and high efficiency.
Referring to fig. 2, in order to test inertia response under multiple working conditions to further more comprehensively evaluate a wind farm inertia response effect, as an example of the embodiment of the present invention, the wind farm inertia response test method further includes:
if all the preset alternating current system frequency change parameter groups are used for simulation, judging whether all the preset wind power plant active power control modes and power levels are used for initializing the power system simulation model containing the wind power plant;
if not, acquiring a next preset wind power plant active power control mode and power level, initializing the power system simulation model containing the wind power plant according to the next preset wind power plant active power control mode and power level, returning to acquire a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized power system simulation model containing the wind power plant according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result until all preset wind power plant active power control modes and power levels are used for initializing the power system simulation model containing the wind power plant.
In order to test the inertia response of the wind farm under different system conditions, as an example of the embodiment of the present invention, the method for testing the inertia response of the wind farm further includes:
if all the preset active power control modes and power levels of the wind power plant are used for initializing the power system simulation model containing the wind power plant, judging whether all the sets of alternating current system parameters are used for constructing the power system simulation model containing the wind power plant;
if yes, exiting the test process;
if not, acquiring the next set of preset alternating current system parameters, constructing a power system simulation model containing the wind power plant according to the next set of preset alternating current system parameters, and returning to the step of initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level until all sets of alternating current system parameters are used for constructing the power system simulation model containing the wind power plant.
As an example of the embodiment of the present invention, initializing the power system simulation model including the wind farm according to a preset wind farm active power control mode and a preset power level, specifically:
and initializing the power system simulation model containing the wind power plant according to the preset active power control mode of the wind power plant as a power unlimited mode and the power level of 0.2pu-0.3 pu.
As an example of the embodiment of the present invention, if all the preset ac system frequency variation parameter sets are used for simulation, the next preset active power control mode and power level of the wind farm are obtained, initializing the power system simulation model containing the wind power plant according to the next preset wind power plant active power control mode and power level, returning to obtain a group of preset alternating current system frequency change parameters, performing a wind power plant inertia response simulation test on the initialized simulation model containing the wind power plant electric power system according to the set of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result until all the preset wind power plant active power control modes and power averages are used for initializing the power system simulation model containing the wind power plant, and the method specifically comprises the following steps of:
according to the steps S2-S7, a wind power plant inertia response test is completed, wherein the wind power plant active power control mode is a power unlimited mode, and the power level is 0.9pu-1.0 pu;
according to the steps S2-S7, the test of the wind power plant inertia response function is completed, wherein the wind power plant active power control mode is a power limited mode, and the power level is 0.2 pu;
according to the steps S2-S7, a wind power plant inertia response test with the wind power plant active power control mode being a power limited mode and the power level being 0.4pu is completed;
according to the steps S2-S7, a wind power plant inertia response test with the wind power plant active power control mode being a power limited mode and the power level being 0.6pu is completed;
and completing a wind power plant inertia response test with the wind power plant active power control mode being a power limited mode and the power level being 0.8pu according to the steps S2-S7.
In order to test inertia response under different system working conditions, in specific implementation, a common test flow is as follows:
(1) firstly, a set of alternating current system parameters are set, so that a power system simulation model containing a wind power plant is constructed according to the set of alternating current system parameters. And then, the wind turbine generator in the wind power plant is connected to the grid, the wind turbine generator/wind power plant inertia response related control function enabling is set, and corresponding inertia response observed quantities such as wind power plant active power, alternating current system frequency and the like are added.
(2) And setting the active power control of the wind power plant to be in a power unlimited mode, wherein the active power level is 0.2pu-0.3pu, so as to initialize the power system simulation model containing the wind power plant.
(3) Setting a first group of alternating current system frequency change parameters to enable the power system simulation model containing the wind power plant to carry out a wind power plant inertia response simulation test according to the group of alternating current system frequency change parameters, and calculating to obtain an inertia response simulation result; judging whether a preset requirement is met or not according to the inertia response simulation result; and if the preset requirements are met, testing whether the inertia response under the frequency change parameters of other alternating current systems is correct by adopting the next group of alternating current system frequency change parameters until all alternating current system frequency change parameter group tests are finished. If not, exiting the test flow;
(4) setting the active power control of the wind power plant to be in a power unlimited mode, setting the active power level to be 0.9pu-1.0pu, and carrying out the inertia response test again according to the step (3).
(5) And setting the active power control of the wind power plant to be in a power limited mode, and respectively carrying out inertia response test tests again according to the step (3) under the conditions that the active power levels are 0.2pu, 0.4pu, 0.6pu and 0.8 pu.
(6) Setting the next set of alternating current system parameters, constructing a power system simulation model containing the wind power plant again according to the set of alternating current system parameters, carrying out grid connection on the wind turbine generator in the wind power plant, and repeating the steps (2) to (5) after setting the inertia response related control function enabling of the wind turbine generator/the wind power plant until the evaluation test of all the alternating current system parameters is completed, so that the test is finished.
Example 2:
referring to fig. 3, an embodiment of the present invention provides a wind farm inertia response testing apparatus, including:
the model building module 1 is used for obtaining a set of preset alternating current system parameters and building a power system simulation model containing a wind power plant according to the preset alternating current system parameters;
the initialization module 2 is used for initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level;
the inertia response simulation module 3 is used for acquiring a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized simulation model containing the wind power plant electric power system according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result;
the first judgment module 4 is used for judging whether the wind power plant inertia response simulation result meets a preset requirement or not;
the exit module 5 is used for exiting the test flow if the test flow does not meet the requirement;
the second judging module 6 is used for judging whether all the preset alternating current system frequency change parameter groups are used for simulation if the preset alternating current system frequency change parameter groups are met;
and the returning module 7 is used for obtaining the next group of preset alternating current system frequency change parameters if the wind power plant inertia response simulation test is not performed on the initialized power system simulation model containing the wind power plant according to the next group of preset alternating current system frequency change parameters, and returning to the step of judging whether the wind power plant inertia response simulation result meets the preset requirement or not until all the preset alternating current system frequency change parameter groups are used for simulation.
As an example of the embodiment of the present invention, the device for testing response of inertia of a ground wind farm further includes:
the second returning module is used for judging whether all the preset active power control modes and power levels of the wind power plant are used for initializing the power system simulation model containing the wind power plant if all the preset alternating current system frequency change parameter groups are used for simulation; if not, acquiring a next preset wind power plant active power control mode and power level, initializing the power system simulation model containing the wind power plant according to the next preset wind power plant active power control mode and power level, returning to acquire a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized power system simulation model containing the wind power plant according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result until all preset wind power plant active power control modes and power levels are used for initializing the power system simulation model containing the wind power plant.
It should be noted that, all or part of the flow in the method according to the above embodiments of the present invention may also be implemented by a computer program instructing related hardware, where the computer program may be stored in a computer-readable storage medium, and when the computer program is executed by a processor, the steps of the above embodiments of the method may be implemented. Wherein the computer program comprises computer program code, which may be in the form of source code, object code, an executable file or some intermediate form, etc. The computer-readable medium may include: any entity or device capable of carrying the computer program code, recording medium, usb disk, removable hard disk, magnetic disk, optical disk, computer Memory, Read-Only Memory (ROM), Random Access Memory (RAM), electrical carrier wave signals, telecommunications signals, software distribution medium, and the like. It should be further noted that the computer readable medium may contain content that is subject to appropriate increase or decrease as required by legislation and patent practice in jurisdictions, for example, in some jurisdictions, computer readable media does not include electrical carrier signals and telecommunications signals in accordance with legislation and patent practice.
While the foregoing is directed to the preferred embodiment of the present invention, it will be understood by those skilled in the art that various changes and modifications may be made without departing from the spirit and scope of the invention.
Claims (10)
1. A wind power plant inertia response testing method is characterized by comprising the following steps:
s1, acquiring a set of preset alternating current system parameters, and constructing a power system simulation model containing a wind power plant according to the preset alternating current system parameters;
s2, initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level;
s3, acquiring a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized simulation model containing the wind power plant electric power system according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result;
s4, judging whether the wind power plant inertia response simulation result meets a preset requirement or not;
s5, if not, exiting the test process;
s6, if yes, judging whether all the preset alternating current system frequency change parameter sets are used for simulation;
and S7, if not, acquiring the next group of preset alternating current system frequency change parameters, performing a wind power plant inertia response simulation test on the initialized power system simulation model containing the wind power plant according to the next group of preset alternating current system frequency change parameters, and returning to the step of judging whether the wind power plant inertia response simulation result meets the preset requirements or not until all the preset alternating current system frequency change parameter groups are used for simulation.
2. The wind farm inertia response test method of claim 1, further comprising:
if all the preset alternating current system frequency change parameter groups are used for simulation, judging whether all the preset wind power plant active power control modes and power levels are used for initializing the power system simulation model containing the wind power plant;
if not, acquiring a next preset wind power plant active power control mode and power level, initializing the power system simulation model containing the wind power plant according to the next preset wind power plant active power control mode and power level, returning to acquire a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized power system simulation model containing the wind power plant according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result until all preset wind power plant active power control modes and power levels are used for initializing the power system simulation model containing the wind power plant.
3. The wind farm inertia response test method of claim 2, further comprising:
if all the preset active power control modes and power levels of the wind power plant are used for initializing the power system simulation model containing the wind power plant, judging whether all the alternating current system parameter sets are used for constructing the power system simulation model containing the wind power plant;
if yes, exiting the test process;
if not, acquiring the next set of preset alternating current system parameters, constructing a power system simulation model containing the wind power plant according to the next set of preset alternating current system parameters, and returning to the step of initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level until all sets of alternating current system parameters are used for constructing the power system simulation model containing the wind power plant.
4. The wind farm inertia response test method of claim 3, wherein the wind farm active power control mode is a power limited mode or a power unlimited mode.
5. The wind farm inertia response test method according to claim 4, wherein the power system simulation model including the wind farm is initialized according to a preset wind farm active power control mode and power level, specifically:
and initializing the power system simulation model containing the wind power plant according to the preset active power control mode of the wind power plant, which is a power unlimited mode, and the power level of the power system is 0.2pu-0.3 pu.
6. The wind farm inertia response testing method according to claim 5, wherein if all the preset alternating current system frequency variation parameter sets are used for simulation, a next preset wind farm active power control mode and power level are obtained, the power system simulation model including the wind farm is initialized according to the next preset wind farm active power control mode and power level, a set of preset alternating current system frequency variation parameters is obtained in a return mode, a wind farm inertia response simulation test is performed on the initialized simulation model including the wind farm power system according to the set of preset alternating current system frequency variation parameters, and a wind farm inertia response simulation result is obtained until all the preset wind farm active power control modes and power levels are used for initializing the power system simulation model including the wind farm, the method specifically comprises the following steps:
according to the steps S2-S7, a wind power plant inertia response test is completed, wherein the wind power plant active power control mode is a power unlimited mode, and the power level is 0.9pu-1.0 pu;
according to the steps S2-S7, a wind power plant inertia response test is completed, wherein the wind power plant active power control mode is a power limited mode, and the power level is 0.2 pu;
according to the steps S2-S7, a wind power plant inertia response test with the wind power plant active power control mode being a power limited mode and the power level being 0.4pu is completed;
according to the steps S2-S7, a wind power plant inertia response test with the wind power plant active power control mode being a power limited mode and the power level being 0.6pu is completed;
and completing a wind power plant inertia response test with the wind power plant active power control mode being a power limited mode and the power level being 0.8pu according to the steps S2-S7.
7. The wind farm inertia response test method according to any one of claims 1 to 6, wherein the evaluation indexes of the wind farm inertia response simulation result include, but are not limited to, wind farm active power output variation, active power output deviation, wind farm active current, inertia response time, and alternating current system frequency.
8. A wind farm inertia response test method according to any of claims 1-6, wherein the AC system parameters comprise system capacity and system impedance.
9. A wind farm inertia response testing device is characterized by comprising:
the model building module is used for obtaining a set of preset alternating current system parameters and building a power system simulation model containing a wind power plant according to the preset alternating current system parameters;
the initialization module is used for initializing the power system simulation model containing the wind power plant according to a preset wind power plant active power control mode and power level;
the inertia response simulation test module is used for acquiring a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized simulation model containing the wind power plant electric power system according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result;
the first judgment module is used for judging whether the wind power plant inertia response simulation result meets a preset requirement or not;
the exit module is used for exiting the test flow if the test flow does not meet the requirement;
the second judgment module is used for judging whether all the preset alternating current system frequency change parameter groups are used for simulation if the preset alternating current system frequency change parameter groups are met;
and the return module is used for acquiring the next group of preset alternating current system frequency change parameters if the wind power plant inertia response simulation test is not performed on the initialized power system simulation model containing the wind power plant according to the next group of preset alternating current system frequency change parameters, and returning to the step of judging whether the wind power plant inertia response simulation result meets the preset requirement or not until all the preset alternating current system frequency change parameter groups are used for simulation.
10. The wind farm inertia response testing device of claim 9, further comprising:
the second returning module is used for judging whether all the preset active power control modes and power levels of the wind power plant are used for initializing the power system simulation model containing the wind power plant if all the preset alternating current system frequency change parameter groups are used for simulation; if not, acquiring a next preset wind power plant active power control mode and power level, initializing the power system simulation model containing the wind power plant according to the next preset wind power plant active power control mode and power level, returning to acquire a group of preset alternating current system frequency change parameters, and performing a wind power plant inertia response simulation test on the initialized power system simulation model containing the wind power plant according to the group of preset alternating current system frequency change parameters to obtain a wind power plant inertia response simulation result until all preset wind power plant active power control modes and power levels are used for initializing the power system simulation model containing the wind power plant.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110293273.XA CN113007039B (en) | 2021-03-18 | 2021-03-18 | Wind power plant inertia response testing method and device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110293273.XA CN113007039B (en) | 2021-03-18 | 2021-03-18 | Wind power plant inertia response testing method and device |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113007039A CN113007039A (en) | 2021-06-22 |
CN113007039B true CN113007039B (en) | 2022-06-14 |
Family
ID=76402708
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110293273.XA Active CN113007039B (en) | 2021-03-18 | 2021-03-18 | Wind power plant inertia response testing method and device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113007039B (en) |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202008005030U1 (en) * | 2008-04-11 | 2008-09-04 | National Penghu University, Makung City | Tester for generator |
ES2545674A1 (en) * | 2014-03-11 | 2015-09-14 | Gamesa Innovation & Technology, S.L. | Inertia control system for wind turbine (Machine-translation by Google Translate, not legally binding) |
CN106655159A (en) * | 2016-10-27 | 2017-05-10 | 中国电力科学研究院 | New energy power station primary frequency modulation capability testing system and testing method thereof |
CN108365616A (en) * | 2018-03-13 | 2018-08-03 | 南方电网科学研究院有限责任公司 | Primary frequency modulation control method, device, equipment and the medium of Wind turbines |
CN109038613A (en) * | 2018-07-02 | 2018-12-18 | 三峡大学 | A kind of adaptive low frequency deloading method counted and wind-powered electricity generation virtual inertia/primary frequency modulation responds |
CN110797976A (en) * | 2019-09-18 | 2020-02-14 | 中国电力科学研究院有限公司 | Test platform and test method suitable for wind power plant power controller evaluation |
CN111864769A (en) * | 2020-07-29 | 2020-10-30 | 国网山东省电力公司日照供电公司 | Frequency modulation parameter determination method and system considering frequency response characteristics of fan and system |
CN112072674A (en) * | 2020-07-21 | 2020-12-11 | 中国电力科学研究院有限公司 | Method and system for determining inertia of power system |
EP3764109A1 (en) * | 2019-07-11 | 2021-01-13 | University College Dublin | A method for evaluating frequency regulation in an electrical grid |
CN112487588A (en) * | 2020-11-16 | 2021-03-12 | 南方电网科学研究院有限责任公司 | Wind power plant reactive voltage regulation function test method, terminal equipment and storage medium |
CN112510734A (en) * | 2021-02-05 | 2021-03-16 | 沈阳微控新能源技术有限公司 | Virtual inertia response offline test system and method based on flywheel energy storage device |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2679809A1 (en) * | 2012-06-28 | 2014-01-01 | Siemens Aktiengesellschaft | Method and arrangement for responding to a grid event, such as fast frequency drop, by combining demand response, inertial response and spinning reserve |
CN104600742B (en) * | 2014-12-25 | 2017-05-17 | 华中科技大学 | Method for compensating wind power plant virtual inertia by utilizing energy accumulation device |
US20160285265A1 (en) * | 2015-03-25 | 2016-09-29 | Eleon Energy, Inc. | Methods and systems for power restoration planning employing simulation and a frequency analysis test |
DE102017105367A1 (en) * | 2017-03-14 | 2018-09-20 | Wobben Properties Gmbh | Test method for testing the behavior of a wind farm for an underfrequency event |
-
2021
- 2021-03-18 CN CN202110293273.XA patent/CN113007039B/en active Active
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202008005030U1 (en) * | 2008-04-11 | 2008-09-04 | National Penghu University, Makung City | Tester for generator |
ES2545674A1 (en) * | 2014-03-11 | 2015-09-14 | Gamesa Innovation & Technology, S.L. | Inertia control system for wind turbine (Machine-translation by Google Translate, not legally binding) |
CN106655159A (en) * | 2016-10-27 | 2017-05-10 | 中国电力科学研究院 | New energy power station primary frequency modulation capability testing system and testing method thereof |
CN108365616A (en) * | 2018-03-13 | 2018-08-03 | 南方电网科学研究院有限责任公司 | Primary frequency modulation control method, device, equipment and the medium of Wind turbines |
CN109038613A (en) * | 2018-07-02 | 2018-12-18 | 三峡大学 | A kind of adaptive low frequency deloading method counted and wind-powered electricity generation virtual inertia/primary frequency modulation responds |
EP3764109A1 (en) * | 2019-07-11 | 2021-01-13 | University College Dublin | A method for evaluating frequency regulation in an electrical grid |
CN110797976A (en) * | 2019-09-18 | 2020-02-14 | 中国电力科学研究院有限公司 | Test platform and test method suitable for wind power plant power controller evaluation |
CN112072674A (en) * | 2020-07-21 | 2020-12-11 | 中国电力科学研究院有限公司 | Method and system for determining inertia of power system |
CN111864769A (en) * | 2020-07-29 | 2020-10-30 | 国网山东省电力公司日照供电公司 | Frequency modulation parameter determination method and system considering frequency response characteristics of fan and system |
CN112487588A (en) * | 2020-11-16 | 2021-03-12 | 南方电网科学研究院有限责任公司 | Wind power plant reactive voltage regulation function test method, terminal equipment and storage medium |
CN112510734A (en) * | 2021-02-05 | 2021-03-16 | 沈阳微控新能源技术有限公司 | Virtual inertia response offline test system and method based on flywheel energy storage device |
Non-Patent Citations (3)
Title |
---|
基于改进SFR模型的含风电虚拟惯性/一次调频电力系统频率响应特性;李世春等;《可再生能源》;20190516(第05期);全文 * |
直驱永磁风电机组虚拟惯量控制的实验方法研究;侍乔明等;《中国电机工程学报》;20150331(第08期);全文 * |
虚拟惯量配合变桨控制的风机一次调频实验研究;王济菘等;《电测与仪表》;20191210(第23期);第18-22页 * |
Also Published As
Publication number | Publication date |
---|---|
CN113007039A (en) | 2021-06-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110518591B (en) | Load flow calculation method for uncertain power system | |
CN110646733A (en) | Method and system for testing low voltage ride through characteristics of wind turbine generator and storage medium | |
CN112800683B (en) | System short-circuit current level evaluation method and system based on convolutional neural network | |
CN110969305B (en) | Photovoltaic power station simulation model parameter optimization method and system | |
CN112487588B (en) | Wind power plant reactive voltage regulation function test method, terminal equipment and storage medium | |
CN110867889A (en) | Method and system for judging oscillation stability of wind power plant/unit accessed to alternating current power grid | |
CN113007039B (en) | Wind power plant inertia response testing method and device | |
CN113627655B (en) | Method and device for simulating and predicting pre-disaster fault scene of power distribution network | |
CN115616412A (en) | Energy storage battery pack modeling method, device, equipment and readable storage medium | |
CN112444675B (en) | Harmonic superstandard early warning method, device, equipment and medium for power transmission network nodes | |
CN107665185A (en) | A kind of customer behavior analysis method and relevant apparatus based on short message service | |
CN114744631A (en) | Data driving voltage estimation method based on non-PMU power distribution network | |
CN110797906B (en) | Method and device for determining maximum installed capacity of wind power base and storage medium | |
CN114548762A (en) | Real-time power system cascading failure risk assessment method and system based on space-time diagram neural network | |
CN111340335A (en) | Method and system for evaluating flexibility supply capacity of thermal power generating unit | |
CN110224441B (en) | Power plant unit recovery sequence optimization method and device | |
CN115063255B (en) | Operation and maintenance resource optimal allocation method, device and system for offshore wind farm | |
CN117543559A (en) | New energy station admittance aggregation method, device, storage medium and equipment | |
CN114329866A (en) | Random production simulation method and device for wind power storage combined system | |
CN117195499B (en) | Simulation modeling method, device and equipment for large wind farm and storage medium | |
CN117215205B (en) | DC system control parameter analysis method based on decision tree and ISS theory | |
CN117313293B (en) | Small signal equivalent modeling method, system, terminal and medium for direct-drive wind farm | |
CN111244972B (en) | Method and device for improving stability of power system, electronic device and storage medium | |
Nayak et al. | Capacity value estimation of wind power incorporating hourly wind speed | |
CN118211375A (en) | Simulation test method, device, terminal and medium for power system model |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |