CN112945663A - Method for detecting cohesiveness of hydraulic asphalt concrete and concrete base - Google Patents
Method for detecting cohesiveness of hydraulic asphalt concrete and concrete base Download PDFInfo
- Publication number
- CN112945663A CN112945663A CN202110111096.9A CN202110111096A CN112945663A CN 112945663 A CN112945663 A CN 112945663A CN 202110111096 A CN202110111096 A CN 202110111096A CN 112945663 A CN112945663 A CN 112945663A
- Authority
- CN
- China
- Prior art keywords
- concrete
- asphalt
- concrete base
- hydraulic
- cohesiveness
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N1/00—Sampling; Preparing specimens for investigation
- G01N1/28—Preparing specimens for investigation including physical details of (bio-)chemical methods covered elsewhere, e.g. G01N33/50, C12Q
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01N—INVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
- G01N19/00—Investigating materials by mechanical methods
- G01N19/04—Measuring adhesive force between materials, e.g. of sealing tape, of coating
Landscapes
- Physics & Mathematics (AREA)
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Chemical & Material Sciences (AREA)
- Analytical Chemistry (AREA)
- Biochemistry (AREA)
- General Health & Medical Sciences (AREA)
- General Physics & Mathematics (AREA)
- Immunology (AREA)
- Pathology (AREA)
- Road Repair (AREA)
Abstract
The invention discloses a method for detecting the cohesiveness of hydraulic asphalt concrete and a concrete base, which is implemented according to the following steps: selecting an asphalt concrete raw material; carrying out a paving test to obtain construction parameters required by construction; pretreating the concrete base, and heating and uniformly mixing the asphalt concrete raw material to obtain an asphalt mixture; paving an asphalt mixture on the surface of the pretreated concrete base, embedding a pull rod piece in the asphalt mixture, and rolling and compacting to form a spreading layer; drilling a hole outside the pull rod piece by using a concrete core drilling machine, wherein the drilled hole extends into the concrete base; connecting the pulled rod piece with a loading force-bearing device, increasing the stress of the pulled rod piece through the loading force-bearing device until the core column is broken, and judging whether the cohesiveness of the hydraulic asphalt concrete and the concrete base is qualified or not according to the broken surface; through pre-burying the pull rod piece, the cohesiveness of the hydraulic asphalt concrete and the concrete base is detected, and the interference of human factors is avoided.
Description
Technical Field
The invention belongs to the technical field of water conservancy and hydropower seepage-proofing engineering, and relates to a method for detecting the cohesiveness of hydraulic engineering asphalt concrete and a concrete base.
Background
As a commonly used seepage-proofing structure of hydraulic and hydroelectric engineering, the asphalt concrete seepage-proofing core wall is connected with a bedrock, a concrete seepage-proofing wall and a bank slope through a concrete base. The asphalt concrete core wall-concrete base-bed rock and impervious curtain or the asphalt concrete core wall-concrete base-concrete impervious wall form a rock-fill dam impervious system; the bonding of the joint surface of the asphalt concrete core wall and the dam foundation concrete base is one of weak load bearing links of an anti-seepage system, and the detection of the bonding of the joint surface of the asphalt concrete core wall and the dam foundation concrete base is of great importance.
The task of detecting the bonding property of the joint surface of the asphalt concrete core wall and the dam foundation concrete base is arranged in an off-site paving test before the construction of the asphalt concrete core wall. At present, in a paving test, a method for detecting the cohesiveness of the hydraulic asphalt concrete and the concrete base is only limited to drilling and taking a core sample, an observation method is used for observing the appearance phenomenon of the joint of the hydraulic asphalt concrete of the core sample and the concrete base surface, the cohesiveness of the hydraulic asphalt concrete and the concrete base is judged by combining engineering experience of technicians, the detection result is greatly influenced by human factors, and the cohesiveness of the hydraulic asphalt concrete and the concrete base is difficult to obtain a unified standard.
Disclosure of Invention
The invention aims to provide a method for detecting the cohesiveness of hydraulic engineering asphalt concrete and a concrete base, which solves the problem that evaluation standards are inconsistent due to the influence of human subjective factors in the conventional method for judging the cohesiveness of the hydraulic engineering asphalt concrete and the concrete base.
The technical scheme adopted by the invention is that the method for detecting the cohesiveness of the hydraulic asphalt concrete and the concrete base is implemented according to the following steps:
step 1, selecting an asphalt concrete raw material according to the requirements of engineering design technical indexes;
and 6, connecting the pulled rod piece with a loading force-bearing device, increasing the stress of the pulled rod piece through the loading force-bearing device until the core column is broken, and judging whether the bonding property of the hydraulic asphalt concrete and the concrete base is qualified or not according to the broken surface.
The invention is also characterized in that:
and 2, the construction parameters comprise equipment type selection, rolling temperature and rolling times.
And 4, the pulled rod piece in the step 4 is deformed steel with the diameter of 16 mm.
The pre-buried depth of pre-buried tension member in bituminous mixture is 15 cm.
And 4, paving the asphalt mixture with the thickness of 30 cm.
The rolling compaction process in the step 4 comprises the following specific steps: and after the temperature of the paved asphalt mixture reaches the primary rolling temperature, carrying out canvas covering and rolling by adopting 3T double-vibration rolling according to construction parameters, and taking down the canvas after the rolling is finished.
And 5, drilling holes outside the pulled rod piece by using a concrete core drilling machine, wherein the diameter of the drilled holes is 100 mm.
And 5, extending the drill hole into the concrete base by a depth of not less than 5 cm.
Step 6, judging whether the cohesiveness of the hydraulic asphalt concrete and the concrete base is qualified according to the fracture surface comprises the following specific processes: if the fracture surface is not at the joint surface of the hydraulic asphalt concrete and the concrete base, the hydraulic asphalt concrete and the concrete base are judged to have good cohesiveness; and if the fracture surface appears at the joint surface of the hydraulic asphalt concrete and the concrete base, judging that the adhesion between the hydraulic asphalt concrete and the concrete base is unqualified.
The invention has the beneficial effects that:
according to the method for detecting the cohesiveness of the hydraulic asphalt concrete and the concrete base, the cohesiveness of the hydraulic asphalt concrete and the concrete base is detected by embedding the pull rod pieces, so that the interference of human factors is avoided, and the uniform standard for evaluating the cohesiveness of the asphalt concrete core wall and the dam foundation concrete base is conveniently formed.
Drawings
Fig. 1 is a schematic position diagram of a pre-buried tension member according to the present invention;
FIG. 2 is a schematic diagram of a fracture surface with good adhesion in the detection process of the embodiment of the present invention.
In the figure, 1, a concrete base, 2, a joint surface of asphalt concrete and the concrete base, 3, asphalt mixture, 4, a pulled rod piece and 5, a core column.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings.
The invention relates to a method for detecting the cohesiveness of hydraulic asphalt concrete and a concrete base, which is implemented according to the following steps:
step 1, selecting an asphalt concrete raw material according to the requirements of engineering design technical indexes;
And 3, chiseling the surface of the concrete base, removing scum, drying the surface, spraying diluted asphalt on the surface of the concrete base, drying the diluted asphalt, and brushing asphalt mortar, wherein the asphalt mortar comprises asphalt, sand (the particle size is not more than 2.36mm) and mineral powder in a mass ratio of 1: 2: 2, heating and uniformly mixing the asphalt concrete raw material, and fully grading the coarse aggregate, the fine aggregate and the mineral powder according to the mineral aggregate grading of the construction mixing ratio; then the prepared mineral aggregate (the general name of coarse aggregate and fine aggregate powder) is pushed into a heating room to be dried and heated (the heating temperature of the mineral aggregate is less than or equal to 180 ℃); then the mineral aggregate is dry-mixed in a stirrer, and the dry-mixing time is more than or equal to 15 s; adding asphalt (the temperature of the asphalt is 150 +/-5 ℃) for wet mixing for more than or equal to 45s, mixing the mineral powder with the heated coarse aggregate and fine aggregate, and then uniformly mixing the mixture with the asphalt to obtain an asphalt mixture;
wherein, cover the canvas so that the bituminous concrete of new shop fully exhausts the flood, protects the bituminous concrete aspect of new shop simultaneously, avoids the raise dust pollution.
The method adopts 3T double-vibration rolling to roll, and the compaction is carried out according to three stages of static rolling leveling, vibration rolling compaction and static rolling finishing.
step 6, connecting the pulled rod piece with a loading force-bearing device, increasing the stress of the pulled rod piece through the loading force-bearing device until the core column is broken, and judging whether the cohesiveness of the hydraulic asphalt concrete and the concrete base is qualified according to the broken surface, wherein the concrete process comprises the following steps: if the fracture surface is not at the joint surface of the hydraulic asphalt concrete and the concrete base, the hydraulic asphalt concrete and the concrete base are judged to have good cohesiveness; and if the fracture surface appears at the joint surface of the hydraulic asphalt concrete and the concrete base, judging that the adhesion between the hydraulic asphalt concrete and the concrete base is unqualified. And if the concrete base surface is unqualified, finding the reason, improving and perfecting the paving test scheme, and performing roughening, cleaning and drying treatment on the concrete base surface again, or changing the proportion and the construction process of diluted asphalt, or changing the proportion and the construction process of asphalt mortar.
Examples
The detection method is adopted for practical operation verification, and the verification process is that when the first layer of asphalt concrete is paved, a deformed steel bar tension member with the diameter of 16mm is embedded, and the embedding depth is 15 cm; after the first layer of asphalt concrete is cooled to the ambient temperature of 22 ℃ after construction is completed, drilling the core column of the pull rod receiving member in the center by using a concrete core drilling machine; connecting the pull rod piece with a loading force-bearing device, increasing the stress of the pull rod piece through the loading force-bearing device until the core column is broken, measuring the maximum load to be 2.35kN, calculating the tensile strength to be 0.30MPa (the tensile strength of asphalt concrete at 22.3 ℃ is 0.27MPa in a laboratory test), and enabling the broken surface to be positioned 19cm below the asphalt concrete layer, namely the broken surface is not positioned at the joint surface of the asphalt concrete and the concrete base, so that the bonding quality of the asphalt concrete and the concrete base is qualified, as shown in fig. 2.
The method of the invention can be obtained by carrying out multiple parallel verification and is consistent with the result of artificial judgment, and because the method of the invention directly obtains the conclusion according to the fracture surface, the method does not relate to the influence of artificial voting or other main factors.
According to the method, the binding property of the hydraulic asphalt concrete and the concrete base is detected by pre-embedding the pull rod pieces, so that the interference of human factors is avoided, the unified standard for evaluating the binding property quality of the asphalt concrete core wall and the dam foundation concrete base is convenient to form, the processing method and the quality control standard for roughening, cleaning and drying the dam foundation concrete base surface can be determined according to the detection result of the method, the diluted asphalt proportion, the mixing method, the spraying process and the quality control standard are determined, and the asphalt mortar proportion, the mixing method, the coating process and the quality control standard are determined.
Claims (10)
1. The method for detecting the cohesiveness of the hydraulic asphalt concrete and the concrete base is characterized by comprising the following steps of:
step 1, selecting an asphalt concrete raw material according to the requirements of engineering design technical indexes;
step 2, carrying out a paving test to obtain construction parameters required by construction;
step 3, pretreating the concrete base, and heating and uniformly mixing the asphalt concrete raw material to obtain an asphalt mixture;
step 4, paving an asphalt mixture on the surface of the pretreated concrete base, embedding a pull rod piece in the asphalt mixture, and rolling and compacting to form a paving layer;
step 5, cooling the layer to be paved to the ambient temperature, drilling holes outside the pulled rod piece by using a concrete core drilling machine, and extending the drilled holes into the concrete base to obtain a core column containing the pulled rod piece;
and 6, connecting the pulled rod piece with a loading force-bearing device, increasing the stress of the pulled rod piece through the loading force-bearing device until the core column is broken, and judging whether the bonding property of the hydraulic asphalt concrete and the concrete base is qualified or not according to the broken surface.
2. The method for detecting the cohesiveness of the hydraulic asphalt concrete and the concrete foundation according to claim 1, wherein the construction parameters in the step 2 comprise equipment type selection, rolling temperature and rolling times.
3. The method for detecting the cohesiveness of the hydraulic asphalt concrete and the concrete base as claimed in claim 1, wherein the concrete base is pretreated in the step 3 by a specific process comprising: chiseling the surface of the concrete base, removing scum, drying the surface, spraying diluted asphalt on the surface of the concrete base, drying the diluted asphalt, and brushing asphalt mortar on the surface.
4. The method for detecting the adhesion between the hydraulic asphalt concrete and the concrete base as claimed in claim 1, wherein the tension member in step 4 is deformed steel bar with a diameter of 16 mm.
5. The method for detecting the cohesiveness of the hydraulic asphalt concrete and the concrete base as claimed in claim 1, wherein the pre-buried depth of the tension members pre-buried in the asphalt mixture is 15 cm.
6. The method for detecting the adhesiveness of the hydraulic asphalt concrete and the concrete base according to claim 1, wherein the thickness of the paved asphalt mixture in the step 4 is 30 cm.
7. The method for detecting the cohesiveness of the hydraulic asphalt concrete and the concrete base as claimed in claim 1, wherein the concrete rolling compaction process in step 4 is as follows: and after the temperature of the paved asphalt mixture reaches the primary rolling temperature, carrying out canvas covering and rolling by adopting 3T double-vibration rolling according to construction parameters, and taking down the canvas after the rolling is finished.
8. The method for detecting the adhesion between the hydraulic asphalt concrete and the concrete base as claimed in claim 1, wherein the diameter of the drilled hole drilled outside the pulled rod by the concrete core drilling machine in the step 5 is 100 mm.
9. The method for detecting the adhesion between the hydraulic asphalt concrete and the concrete base as claimed in claim 1, wherein in the step 5, the drill hole extends into the concrete base by a depth of not less than 5 cm.
10. The method for detecting the cohesiveness of the hydraulic asphalt concrete and the concrete base according to claim 1, wherein the specific process of judging whether the cohesiveness of the hydraulic asphalt concrete and the concrete base is qualified according to the fracture surface in the step 6 is as follows: if the fracture surface is not at the joint surface of the hydraulic asphalt concrete and the concrete base, the hydraulic asphalt concrete and the concrete base are judged to have good cohesiveness; and if the fracture surface appears at the joint surface of the hydraulic asphalt concrete and the concrete base, judging that the adhesion between the hydraulic asphalt concrete and the concrete base is unqualified.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110111096.9A CN112945663B (en) | 2021-01-27 | 2021-01-27 | Method for detecting cohesiveness of hydraulic asphalt concrete and concrete base |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110111096.9A CN112945663B (en) | 2021-01-27 | 2021-01-27 | Method for detecting cohesiveness of hydraulic asphalt concrete and concrete base |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112945663A true CN112945663A (en) | 2021-06-11 |
CN112945663B CN112945663B (en) | 2022-11-25 |
Family
ID=76237838
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110111096.9A Active CN112945663B (en) | 2021-01-27 | 2021-01-27 | Method for detecting cohesiveness of hydraulic asphalt concrete and concrete base |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112945663B (en) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001141624A (en) * | 1999-11-10 | 2001-05-25 | Tokyo Electric Power Co Inc:The | Method and device for measuring asphalt strength |
CN102864758A (en) * | 2012-10-22 | 2013-01-09 | 安蓉建设总公司 | Construction method of rolling compaction type asphalt concrete impervious core wall in high altitude and cold areas |
CN109060653A (en) * | 2018-09-03 | 2018-12-21 | 中国建筑科学研究院有限公司 | Method and device for detecting bonding strength of bonding surface of laminated member |
CN211825622U (en) * | 2020-04-07 | 2020-10-30 | 山东文登抽水蓄能有限公司 | Device for measuring cohesive force of sprayed concrete and rock |
-
2021
- 2021-01-27 CN CN202110111096.9A patent/CN112945663B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001141624A (en) * | 1999-11-10 | 2001-05-25 | Tokyo Electric Power Co Inc:The | Method and device for measuring asphalt strength |
CN102864758A (en) * | 2012-10-22 | 2013-01-09 | 安蓉建设总公司 | Construction method of rolling compaction type asphalt concrete impervious core wall in high altitude and cold areas |
CN109060653A (en) * | 2018-09-03 | 2018-12-21 | 中国建筑科学研究院有限公司 | Method and device for detecting bonding strength of bonding surface of laminated member |
CN211825622U (en) * | 2020-04-07 | 2020-10-30 | 山东文登抽水蓄能有限公司 | Device for measuring cohesive force of sprayed concrete and rock |
Non-Patent Citations (1)
Title |
---|
杨子业等: "水泥混凝土桥面防水粘结材料性能试验研究", 《城市道桥与防洪》 * |
Also Published As
Publication number | Publication date |
---|---|
CN112945663B (en) | 2022-11-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Liu et al. | Experimental study on real-time control of roller compacted concrete dam compaction quality using unit compaction energy indices | |
CN104062190B (en) | Shearing strength detection method for new and old pavement connecting layer material | |
CN104372727B (en) | The mixing proportion design method of normal temperature modified asphalt | |
Tariq et al. | Mechanical behaviour of cement-treated sand | |
Bonicelli et al. | Laboratory analysis for investigating the impact of compaction on the properties of pervious concrete mixtures for road pavements | |
CN205024904U (en) | Solid brick curtain structural texture | |
CN102967520A (en) | Method for measuring aggregate crushing value | |
CN112945663B (en) | Method for detecting cohesiveness of hydraulic asphalt concrete and concrete base | |
CN115494224A (en) | Method for evaluating fusion degree of new asphalt and old asphalt of hot mix plant recycled asphalt mixture | |
Han et al. | Engineering properties and air void characteristics of cold recycled mixtures with different compaction methods | |
CN108169463A (en) | A kind of detection method of the pervious concrete working performance based on slurry rheology | |
Li et al. | Experimental Investigation on Influence of Molding Methods on Properties of Pervious Concrete | |
CN107121336A (en) | The method for building up of Sandy Silt uniaxial compressive strength curve | |
Bulbul Ahmed et al. | Improvement of soil strength using cement and lime admixtures | |
Sivakumar et al. | Influence of testing on permeability of compacted fine soils | |
CN110763583A (en) | Concrete strength detection method | |
Jiang | [Retracted] Damage Mechanism of Asphalt Concrete Pavement under Different Immersion Environments | |
CN111335094A (en) | Method for preparing flowing material by using tail dust of asphalt mixing station and backfilling engineering part | |
CN107476160B (en) | Improvement method of laterite gravel road base layer | |
Sravya et al. | Swell and strength characteristics of expansive soil reinforced with synthetic fibers | |
Zhang et al. | Investigation on shear strength properties of water-bearing concrete-rock interface based on convolutional neural network recognition method | |
Konthesingha et al. | Bond and compressive strength of masonry for locally available bricks | |
Zhang et al. | Research on New Type of Cement-soil Piles to Reinforce Soft Soil Foundation | |
Hasan et al. | An investigation of geomechanical and microstructural properties of full-scale jet grout column constructed in organic soil | |
CN115110523B (en) | Screw pile integrity defect grouting repairing method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |